September 2017
South 206th and South 208th Streets Cross Section
30’ roadwaycurb
1
36’ roadway5’ sidewalk 5’ sidewalkcurb curb
2
20’ roadway
3
99
1 2 3
Existing Conditions
Proposed South 206th and South 208th Streets - Looking East
sidewalk sidewalkroadway bio-retention6ʹ 6ʹ28ʹ 8ʹ
*Contingent on soil testing.
SR 509 Completion ProjectPuget Sound Gateway Program
-
September 2017
South 204th Street and 34th Avenue South Cross Section
28’ roadway
224’ roadway
curb
1991 2 Existing Conditions
Proposed South 204th Street - Looking East Proposed 34th Avenue South - Looking South
sidewalkroadwaybio-retention*6ʹ28ʹ8ʹ
*Contingent on soil testing.
SR 509 Completion ProjectPuget Sound Gateway Program
-
September 2017
Visualization
South 272nd Street Before South 272nd Street After
SR 509 Completion ProjectPuget Sound Gateway Program
-
September 2017
SR 509 Before SR 509 After
Visualization
SR 509 Completion ProjectPuget Sound Gateway Program
-
September 2017
SR 516 Interchange Before SR 516 Interchange After
Visualization
SR 509 Completion ProjectPuget Sound Gateway Program
-
September 2017
SR 509 and Sound Transit Coordination
Preliminary draftSubject to revision
Federal Way Link ExtensionSouth 206th Street South 208th Street 34th Avenue South South 204th Street SR 509
99
99
South 206th Street
South 204th Street
34th
Ave
nue
Sout
h
South 208th Street
Federal Way Link Extension
509
509
SR 509 Completion ProjectPuget Sound Gateway Program
-
September 2017
2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
SR 509Early work
Sound Transit Federal Way Link Extension
Stage 1I-5 to 28th/24th
Stage 228th/24th to 188th
DESIGN/RIGHT-OF-WAY
DESIGN/RIGHT OF WAY
CONSTRUCTION
CONSTRUCTION
CONSTRUCTION
OPEN
SR 509 Project Timeline
• South 204th Street• South 208th Street• 34th Ave South• South 206th Street
SR 509 Completion ProjectPuget Sound Gateway Program
-
September 2017
Connecting WA
Local Funding
Toll Funding
2015-2017 2021-20232017-2019 2025-20272023-20252019-2021 2027-2029 2029-2031
$2.5M$2.5M $93.5M $395M $283M
$30M
$305M $206M
$60M
$260M
$40M
$20M
$180M$93.5M
$305M
$395M
$266M
$313M$300M
$200M
Gateway Program Funding Timeline for SR 509 and SR 167
Puget Sound Gateway Program