RTUG Project Management Contract Expansion And RTF 2010 Work Plan Budget Adjustments

15
1 RTUG Project Management Contract Expansion And RTF 2010 Work Plan Budget Adjustments RTF March 2, 2010

description

RTF March 2, 2010. RTUG Project Management Contract Expansion And RTF 2010 Work Plan Budget Adjustments. Goal Today. Direction on Scope of Work & Deliverables Decision on funding additional project management & research (Phase 4). Refresher: Phase 3. Monitored data on 174 units in 2009 - PowerPoint PPT Presentation

Transcript of RTUG Project Management Contract Expansion And RTF 2010 Work Plan Budget Adjustments

Page 1: RTUG Project Management Contract Expansion  And RTF 2010 Work Plan Budget Adjustments

1

RTUG Project Management Contract Expansion

And RTF 2010 Work Plan Budget Adjustments

RTF

March 2, 2010

Page 2: RTUG Project Management Contract Expansion  And RTF 2010 Work Plan Budget Adjustments

2

Goal Today

• Direction on Scope of Work & Deliverables

• Decision on funding additional project management & research (Phase 4)

Page 3: RTUG Project Management Contract Expansion  And RTF 2010 Work Plan Budget Adjustments

3

Refresher: Phase 3• Monitored data on 174 units in 2009• Promising results & savings methodology

– Presented November 2009 – Further analysis & development needed for Savings

Methodology, calculator or deemed savings:• Annual metering results• Specifications & protocol • Half dozen other issues to resolve with additional research

• Out of funding for RTUG project management

Page 4: RTUG Project Management Contract Expansion  And RTF 2010 Work Plan Budget Adjustments

4

January 2010• RTUG endorsed continuation of the project

management by New Buildings Institute (NBI)– Valuable regional cooperative effort– Sole source basis subject to review of scope

• Last RTF Meeting– Preliminary cost estimate Phase 4

• >$80K for project & technical management

– Raised issue of how to determine going forward• Will it fit in budget?• What other projects might come before RTF?• How to decide in uncertain future?

Page 5: RTUG Project Management Contract Expansion  And RTF 2010 Work Plan Budget Adjustments

5

Since Last RTF Meeting• NBI solicited & assembled next-step research

– Polled key RTUG participants for ideas– Developed research & analytical path

• Draft scope for Phase 4 circulated to the RTUG for comment– Project management & coordination– Research & analytical scope based on comments

• BPA questioning cost-effectiveness– Costs high, unknown persistence

Page 6: RTUG Project Management Contract Expansion  And RTF 2010 Work Plan Budget Adjustments

6

Where to from here?

Page 7: RTUG Project Management Contract Expansion  And RTF 2010 Work Plan Budget Adjustments

7

Next Steps to Get to Savings Methodology1. Complete collecting & storing the 12-month data 2. Determine confidence in annual savings methodology3. Further assessment of data:

Baseline & treatment conditions, persistence of fan schedules, annual fan power & duty cycle, negative savings, isolate refrig & air flow conditions, TMY vs site temps, service tech interviews

4. Develop scope & budget for extending to 36-month monitor5. Establish functioning data repository with open access

Direct Research Funded by BPA via Cadmus.

Needs RTUG review & technical guidance. Unfunded Project Management.

Page 8: RTUG Project Management Contract Expansion  And RTF 2010 Work Plan Budget Adjustments

8

Revised Scope of Work Phase 4Management ($27K)

• Management, Communications & Reporting– 3 RTUG & 3 RTF meetings over 9 months

• 75 hours

– Facilitate regional service & field measurement protocols, encourage added M&V & sampling

• 75 hours

– Communicate & collaborate with other regions• 30 hours

– Meeting minutes, reports, presentations, final report

Page 9: RTUG Project Management Contract Expansion  And RTF 2010 Work Plan Budget Adjustments

9

Revised Scope of Work Phase 4Technical ($21K)

– Review results of analysis by BPA/Cadmus, synthesize for discussion at RTUG & presentation to RTF

• Develop the complete savings methodology for proposal to the RTF • 70 hours

– Phase 1 database development assistance• 10 hours

– Develop elements of strategic plan for RTU next steps• Service vs early replacement, incorporate DCV/Premium Ventilation,

VSD/ECM motors, fan upgrade, FDD, Evap Hybrid RTU, Advanced RTU, digital economizer control, other Emerging Tech

• Internet-enabled T-Stats, lower-cost monitoring, whole-building approach to monitoring,

• 75 hours

Page 10: RTUG Project Management Contract Expansion  And RTF 2010 Work Plan Budget Adjustments

10

Summary of Critical Path Costs

Unfunded Management

NBI Project Management $27K

NBI Technical Management $21K

NBI Admin & Direct $ 4K

NBI Total $52K

Page 11: RTUG Project Management Contract Expansion  And RTF 2010 Work Plan Budget Adjustments

11

Summary of Potential Additional RTU Research Costs

Unfunded Potential Direct Research

Reconcile measured results & simulation modeling. Develop simulation tools (DOE2/eQUEST) that reflect measured results from study

$20K-$50K

Expected Value Premium Ventilation Analysis $15K-35K

Extended RTU DDC Sequences & Testing $15K

Inverse modeling approach vs 2-week pre-post ?

Extending long-term monitoring to 36 months or longer

?

Test of RTU control Internet performance monitoring

$100K

Co-funding ASHRAE 1608 RTAR $20K ?

Page 12: RTUG Project Management Contract Expansion  And RTF 2010 Work Plan Budget Adjustments

12

So Where’s the Money?

Page 13: RTUG Project Management Contract Expansion  And RTF 2010 Work Plan Budget Adjustments

13

Work Item Modified Approved

Budget

Allocated Adam

Reserved Contract

Available for Projects

Available for Admin

End-Use Load Study - Phase 2a $ 3,000 $ 3,000 $ 0 Review RTF deemed measures, savings, and measure lives against others; document consistent methodology

$ 235,000 $ 235,000 $ 0

Develop Simplified M&V protocols and/or calculators for non-deemable measures, including behavioral and O&M measures

$ 235,000 $ 235,000 $ 0

Identify Measures and M&V Protocols that are applicable to small and/or rural utilities

$ 50,000 $ 50,000 $ 0

Provide Technical Support to the Ductless Heat Pump Evaluation.

$ 5,000 $ 5,000 $ 0

Support & Review Heat Pump Water Heater Research. $ 5,000 $ 5,000 $ 0 Develop consistent methodology for assigning EUIs to commercial buildings

$ 10,000 $ 10,000

Respond to NEET Recommendations for the RTF. $ 5,000 $ 5,000 $ 0 Support Roof Top HVAC Work - Commercial Economizer Phase 3.

$ 37,500 $ 37,500 $ 0

Support Development of Savings Methodologies for Rooftop HVAC.

$ 5,000 $ 5,000 $ 0

Overhaul RTF Website. $ 10,000 $ 10,000 $ 0 PTR Support. $ 15,000 $ 15,000 $ 0 Regional Conservation Progress Tracking $ 10,000 $ 10,000 $ 0 Measure and Technology Reviews. (for RFQs) $ 200,000 $ 35,000 $ 165,000 IT M&V Protocol Review and Adoption $ 20,000 $ 20,000 $ 0 Member & Corresponding Member Special Project Support. $ 35,000 $ 42,000 $ (7,000)Member RTF Meetings. $ 65,000 $ 50,000 $ 15,000 RTF Meetings (Minutes and lunches) $ 20,000 $ 18,000 $ 2,000 Contract Management. $ 50,000 $ 15,000 $ 35,000 RTF Management. $ 25,000 $ 25,000 $ 0 Council Staff $ 180,000 Total Budget (not including Council Staff) $ 1,040,500 $ 118,000 $ 702,500 $ 175,000 $ 45,000

Budget Snap Shot – March 2010

Page 14: RTUG Project Management Contract Expansion  And RTF 2010 Work Plan Budget Adjustments

14

Issues

• About $175K budget for “unidentified incoming” for the remainder 2010

• How much of that for RTUG Phase 4?• What other unidentified incoming will show up?

• Where to get any remainder for RTUG?– Solicit direct contributions– Find a sugar daddy– Cut the RTUG phase 4 scope & budget

Page 15: RTUG Project Management Contract Expansion  And RTF 2010 Work Plan Budget Adjustments

15

Proposal

• Allocate $52K of “Available” to RTUG Phase 4 Scope– Sole source to NBI

– Final scope to RTF staff working with RTUG

• Decide later on RTF support for further RTUG work (2011) or find other funders

• Leaves $120K for remainder of 2010 for other incoming projects