Rooftop Unit Working Group (RTUG) August 20, 2012

16
Evaluation of the RTF Standard Protocol Fan and Cooling Savings from Commercial-Sector Heat Pump Units Rooftop Unit Working Group (RTUG) August 20, 2012

description

Evaluation of the RTF Standard Protocol Fan and Cooling Savings from Commercial-Sector Heat Pump Units. Rooftop Unit Working Group (RTUG) August 20, 2012. BEGINNINGS. RTUG recommendation to RTF in 2010 to add heat pumps to the RTU Protocol and Annual Energy Use and Savings Calculator - PowerPoint PPT Presentation

Transcript of Rooftop Unit Working Group (RTUG) August 20, 2012

Page 1: Rooftop Unit Working Group (RTUG) August 20, 2012

Evaluation of the RTF Standard Protocol Fan and Cooling Savings from Commercial-Sector

Heat Pump Units

Rooftop Unit Working Group (RTUG)August 20, 2012

Page 2: Rooftop Unit Working Group (RTUG) August 20, 2012

Top

ic 1To

pic 2

Top

ic 3BEGINNINGS

• RTUG recommendation to RTF in 2010 to add heat pumps to

the RTU Protocol and Annual Energy Use and Savings

Calculator

• 3 heat pumps were selected (Vancouver, WA) for metering for

winter-summer 2011, continuing to winter 2011-2012, and

currently into summer 2012

• Change of data service provider from Powermand to Makad

Energy disrupted data acquisition

– 1 site survived with all required data

– 1 site had most of the data

– 1 site dropped out due to gateway failure during provider

transition

Page 3: Rooftop Unit Working Group (RTUG) August 20, 2012

RESEARCH BACKGROUNDHeat pump heating is different because it includes resistance backup heat + defrost cycles. Principal research questions included:

1. Do these heating differences fit in an energy signature model?

2. How widespread is poorly controlled/contradictory heating and cooling?

3. If the heating signature is accurately derived, how should heat pump monitoring be staged for summer/winter measurement?

Page 4: Rooftop Unit Working Group (RTUG) August 20, 2012

METERED DATA

Per RTF/RTU protocol: One-minute data intervals

• Total power

• Outside air temperature

• Supply air temperature

Page 5: Rooftop Unit Working Group (RTUG) August 20, 2012

Top

ic 1To

pic 2

Top

ic 3RESEARCH TASKS

• Assure measurement & data acquisition equipment installed & operating effectively properly

• Collect initial 12 months data + tracking of maintenance work done by the HVAC service techs

• Test the data with the standard RTF/RTU protocol including: – Identifying the applicable monitoring period– Making recommendations as necessary for changes in

the standard protocol to accommodate heat pumps in cooling and heating modes

– Present results to the RTUG for review and recommendations to the RTF on next steps

Page 6: Rooftop Unit Working Group (RTUG) August 20, 2012

Top

ic 1To

pic 2

Top

ic 3HEAT PUMP SIGNATURE

Page 7: Rooftop Unit Working Group (RTUG) August 20, 2012

Top

ic 1To

pic 2

Top

ic 3OVERALL SIGNATURE: WINTER/SUMMER

Unit 1

Page 8: Rooftop Unit Working Group (RTUG) August 20, 2012

Top

ic 1To

pic 2

Top

ic 3METERED/PREDICTED ENERGY USE

Energy Use - Unit 1

Normalized predicted annual 41,244 kWh/yr

Actual metered (5 months) 10,537 kWh/yr

Signature predicted (5 months) 10,389 kWh/yr

Reconstruction Error 1.4%

Long-term metered energy use was constructed from the winter and summer energy signatures

Page 9: Rooftop Unit Working Group (RTUG) August 20, 2012

Top

ic 1To

pic 2

Top

ic 3RTU PROTOCOL

HOURLY ENERGY USE PROFILES-WINTER

Unit 1

Page 10: Rooftop Unit Working Group (RTUG) August 20, 2012

Top

ic 1To

pic 2

Top

ic 3

RTU PROTOCOL HOURLY ENERGY USE PROFILES-SUMMER

Unit 1

Page 11: Rooftop Unit Working Group (RTUG) August 20, 2012

Top

ic 1To

pic 2

Top

ic 3HEAT PUMP ANALYSIS REQUIRES

ANNUAL PERSPECTIVE• Summer signature from July or August

• Winter Signature from December or January

• September, October, November have minimal useful signature data

• Measure installation needs to be coordinated with metering

Page 12: Rooftop Unit Working Group (RTUG) August 20, 2012

Top

ic 1To

pic 2

Top

ic 3OPERATIONAL ISSUES

  Site 1 Site 2Size, tons 15 6Loading, average duty cycle

40% 40%

Observed kWh/yr 41,244 NA - missing resistance load

Est improved kWh/yr 32,540 NAEst savings, kWh/yr 8,704 NAEst savings, kWh/yr/ton 580 NARecommended EEMs • Control

adjustment - faulty interstage differential leads to unnecessary resistance heating

• 24 hour fan on lightly loaded space could be set back at night

• first stage heating has low efficiency

• Control adjustment – unnecessary use of resistance heat, reduce lockout temperature

• Possible over active de-frost with alternating cycles of heating and cooling;

• Anomalous 3 day period around 12/18 with half power and almost no heat

Page 13: Rooftop Unit Working Group (RTUG) August 20, 2012

Top

ic 1To

pic 2

Top

ic 3RECOMMENDED NEXT STEPS

1. Update Regional RTU Research Database to included metered data from the heat pump project.

2. Notify the Vancouver facility operator of observed deficiencies in RTU operation.

3. Continuing metering/data collection for another 12 months, assuming there is continued access to the Dreamwatts system data, which is unknown at this time.

4. Adapt the RTF/RTU Standard Protocol and Calculator to produce winter signatures. In the near term, this adaptation could take the form of an adapted spreadsheet tool. The adaptation includes annualizing a normalized year estimate by dividing the year into portions associated with the winter and summer signatures.

Page 14: Rooftop Unit Working Group (RTUG) August 20, 2012

Top

ic 1To

pic 2

Top

ic 3RECOMMENDED NEXT STEPS-2

5. Further test and substantiate the two-season signature approach

on additional heat pump units = 10 units, 5 east side, 5 west side,

with at least 6 months data, to provide for normalized annual

energy use and savings estimates in the Calculator.

6. Expand the tested application of the heat pump signature by

revisiting earlier heat pump metering data from the BPA RTU

research program and coordinate with future BPA-sponsored heat

pump metering and Pacific Northwest National Laboratory heat

pump metering that is just underway.

7. Consider proposing a heat pump addition to the RTU standard

protocol by the RTF in 2014 or sooner if additional data is

available. In this project as well as others, the existence of an

approved protocol has been shown to be a substantial analytical

time saver.

Page 15: Rooftop Unit Working Group (RTUG) August 20, 2012

Top

ic 1To

pic 2

Top

ic 3

EXPANDING THE RTF/RTU PROTOCOL NBI is developing a detailed physical RTU model for

cooling/ventilation through the Variable Rate RTU Test (VRTUT) project with NEEA/BPA

The physical model can provide measure savings estimates, benchmarking and zone characterization (net energy transfer out of the zone/space, effect of outside air temperature)

The RTF/RTU Protocol measurement approach and the aggregate results from the Calculator are not changed.

Linking the characteristics of the RTU signature to the physical circumstances of the RTU including schedules/controls, results in an enhanced predictive modeling capability supported by the energy signature under a range of variable zone and RTU operating conditions

Page 16: Rooftop Unit Working Group (RTUG) August 20, 2012

Top

ic 1To

pic 2

Top

ic 3Contact

Mark Cherniack

[email protected]

Howdy Reichmuth

[email protected]