RIverhead school board presentation construction progress and budget

download RIverhead school board presentation construction progress and budget

of 14

Transcript of RIverhead school board presentation construction progress and budget

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    1/32

    1

    BBS

    Riverhead

    Central School District

    Board of Education Update Meeting

    October 13, 2015

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    2/32

    2

    BBSRiverhead High School Progress Classroom Addition

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    3/32

    3

    BBSRiverhead High School Progress Classroom Addition

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    4/32

    4

    BBSRiverhead High School – Main Lobby

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    5/32

    5

    BBSRiverhead High School – Corridors

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    6/32

    6

    BBSRiverhead High School – Science Classrooms

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    7/32

    7

    BBSRiverhead High School – Science Classrooms

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    8/32

    8

    BBSRiverhead High School – Courtyard

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    9/32

    9

    BBSRiverhead Middle School – Classroom Addition

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    10/32

    10

    BBSRiverhead Middle School – Music Addition

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    11/32

    11

    BBSRiverhead Middle School – Music Addition

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    12/32

    12

    BBSRiverhead Middle School - Cafeteria/Auditorium

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    13/32

    13

    BBSRiverhead Middle School – Science Classrooms

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    14/32

    14

    BBSRiverhead Middle School – Main Office

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    15/32

    15

    BBSRiverhead Middle School – Windows

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    16/32

    16

    BBSFootball Field and Bleachers

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    17/32

    17

    BBSRoanoke Elementary School Progress

    Classroom Addition

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    18/32

    18

    BBSRoanoke Elementary School Progress

    Toilet Rooms

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    19/32

    19

    BBSPulaski Elementary School Progress

    Cafeteria Addition

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    20/32

    20

    BBSPulaski Elementary School Progress

    Classroom Renovations

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    21/32

    21

    BBSPulaski Elementary School Progress

    Professional Development Room

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    22/32

    22

    BBS

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    23/32

    23

    BBS

    All figures are subject to adjustment. 10/13/15

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    24/32

    All 

    figures 

    are 

    subject 

    to 

    adjustment. 10/13/15

    All 

    figures 

    are 

    subject 

    to 

    adjustment. 1

    Riverhead CSD$78,334,247 Capital

    Construction Project

    Presented by Sam M. Schneider, AssistantSuperintendent for Finance and Operations

    Riverhead Central School District

    Board of Education Meeting

    October 13, 2015

    All 

    figures 

    are 

    subject 

    to 

    adjustment. 10/13/15

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    25/32

    g j j / /

    All 

    figures 

    are 

    subject 

    to 

    adjustment. 2

    Capital Construction Project• In October 2011, the voters approved spending

    $78,334,247 on capital construction projects atall seven schools and some athletic fields.

    Conception Reality

    All 

    figures 

    are 

    subject 

    to 

    adjustment. 10/13/15

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    26/32

    All 

    figures 

    are 

    subject 

    to 

    adjustment. 3

    Capital Construction Project

    • The voters were presented with an projected budget for each project within the$78,334,247.

    • Where individual school projects have been

    completed for less than originally anticipated,the funds are transferred to other school projects where costs have increased, but thefinal cost for all eight projects will not exceed

    $78,334,247.

    All 

    figures 

    are 

    subject 

    to 

    adjustment. 10/13/15

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    27/32

    All 

    figures 

    are 

    subject 

    to 

    adjustment. 4

    Transfers Among Projects

    • Projects can generate savings over the initial budget due to:

     – Favorable bidding climate

     – Few unanticipated expenses – Less extensive original work scope

    Project

    Initial

    Budget Final Budget Savings

    McKillop Field $1,604,751 $931,505 $673,246Aquebogue $3,807,996 $3,130,834 $677,162

    Riley $5,666,831 $5,346,251 $320,580

    These funds were transferred to other projects, including RHS and RMS.

    All 

    figures 

    are 

    subject 

    to 

    adjustment. 10/13/15

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    28/32

    All 

    figures 

    are 

    subject 

    to 

    adjustment. 5

    Change Orders?

    • A change order is an agreement between the

    contractor and the District to alter the originalcontract of work to either add or delete work.

    • Change orders are funded through contingency

    funds that were built into the $78,334,247approved by the voters.

    • Change orders are for: – Discovery of unanticipated conditions

     – Design changes necessitated by building code or practical realities

    All 

    figures 

    are 

    subject 

    to 

    adjustment. 10/13/15

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    29/32

    All 

    figures 

    are 

    subject 

    to 

    adjustment. 6

    Bond Expenditures as of Oct. 1, 2015by School

    Project

    Original

    Estimate

    Current

    Budget

    Expenditures as

    of 10/1/15

    Encumbrances

    Outstanding

    Unencumbered 

    Balance

    Aquebogue $3,807,996 $3,130,834 $3,130,834 $0 $0

    Phillips $4,025,891 $4,109,168 $4,109,168 $0 $0

    Riley $5,666,831 $5,346,251 $5,346,251 $0 $0

    McKillop Field $1,604,751 $931,505 $842,803 $88,702 $0

    High School $32,129,979 $33,256,165 $30,719,942 $2,391,599 $144,623

    Middle School $15,426,347 $16,171,341 $12,571,836 $3,546,546 $52,959

    Roanoke $7,791,777 $8,356,284 $2,077,150 $6,121,974 $157,159

    Pulaski $7,880,675 $7,032,699 $2,213,081 $4,427,487 $392,133

    Total $78,334,247 $78,334,247 $61,011,065 $16,576,308 $746,874

    The above figures do not include money appropriated by the

    Board from the Repair Reserve, which are not capital expenses

    even when such work is performed by the same contractor.

    All 

    figures 

    are 

    subject 

    to 

    adjustment. 10/13/15

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    30/32

    All 

    figures 

    are 

    subject 

    to 

    adjustment. 7

    Bond Expenditures as of Oct. 1, 2015by Category

    Miscellaneous costs include printing costs during the bidding

     process, professional movers who pack buildings in and out,

    temporary signage, temporary relocation of utilities, etc.

    Category

    Expenditures as

    of 10/1/15

    Encumbrances

    Outstanding

    Unencumbered 

    Balance

    Attorney $143,478 $102,000 $9,803

    Misc. Costs $361,766 $85,369 $17,177

    Survey/Engineering $905,138 $170,068 $176,748

    Construction Mgr. $1,610,125 $262,485 $4,569

    Architect $3,855,187 $270,775 $16,342Furniture/Equipment $2,967,162 $1,229,187 $101,064

    Construction $51,168,209 $14,456,424 $421,171

    Total $61,011,065 $16,576,308 $746,874

    Grand Total: $78,334,247

    All 

    figures 

    are 

    subject 

    to 

    adjustment. 10/13/15

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    31/32

    All 

    figures 

    are 

    subject 

    to 

    adjustment. 8

    Bond Revenue

    • The Riverhead CSD has

    financed the projects byissuing three series of bonds, spaced out toensure that money is

    only borrowed when itis needed.

    • Bonds are sold on theopen market to the

     bidder offering thelowest interest rate.

    Official Statement issued for bonds

    All 

    figures 

    are 

    subject 

    to 

    adjustment. 10/13/15

  • 8/20/2019 RIverhead school board presentation construction progress and budget

    32/32

    All 

    figures 

    are 

    subject 

    to 

    adjustment. 9

    Bond Revenue•  November 2012

     –  $13,500,000 bonds

     –  20 year repayment –  2.65% average interest rate

    • March 2014 –  $32,572,000 bonds

     –  20 year repayment –  3.1625% average interestrate

    •  November 2015 –  $32,262,247 bonds

     –  15 year repayment –  Interest TBD at closing

    Moody’s Investors Service rating of Aa2.