RIverhead school board presentation construction progress and budget
-
Upload
riverheadlocal -
Category
Documents
-
view
215 -
download
0
Transcript of RIverhead school board presentation construction progress and budget
-
8/20/2019 RIverhead school board presentation construction progress and budget
1/32
1
BBS
Riverhead
Central School District
Board of Education Update Meeting
October 13, 2015
-
8/20/2019 RIverhead school board presentation construction progress and budget
2/32
2
BBSRiverhead High School Progress Classroom Addition
-
8/20/2019 RIverhead school board presentation construction progress and budget
3/32
3
BBSRiverhead High School Progress Classroom Addition
-
8/20/2019 RIverhead school board presentation construction progress and budget
4/32
4
BBSRiverhead High School – Main Lobby
-
8/20/2019 RIverhead school board presentation construction progress and budget
5/32
5
BBSRiverhead High School – Corridors
-
8/20/2019 RIverhead school board presentation construction progress and budget
6/32
6
BBSRiverhead High School – Science Classrooms
-
8/20/2019 RIverhead school board presentation construction progress and budget
7/32
7
BBSRiverhead High School – Science Classrooms
-
8/20/2019 RIverhead school board presentation construction progress and budget
8/32
8
BBSRiverhead High School – Courtyard
-
8/20/2019 RIverhead school board presentation construction progress and budget
9/32
9
BBSRiverhead Middle School – Classroom Addition
-
8/20/2019 RIverhead school board presentation construction progress and budget
10/32
10
BBSRiverhead Middle School – Music Addition
-
8/20/2019 RIverhead school board presentation construction progress and budget
11/32
11
BBSRiverhead Middle School – Music Addition
-
8/20/2019 RIverhead school board presentation construction progress and budget
12/32
12
BBSRiverhead Middle School - Cafeteria/Auditorium
-
8/20/2019 RIverhead school board presentation construction progress and budget
13/32
13
BBSRiverhead Middle School – Science Classrooms
-
8/20/2019 RIverhead school board presentation construction progress and budget
14/32
14
BBSRiverhead Middle School – Main Office
-
8/20/2019 RIverhead school board presentation construction progress and budget
15/32
15
BBSRiverhead Middle School – Windows
-
8/20/2019 RIverhead school board presentation construction progress and budget
16/32
16
BBSFootball Field and Bleachers
-
8/20/2019 RIverhead school board presentation construction progress and budget
17/32
17
BBSRoanoke Elementary School Progress
Classroom Addition
-
8/20/2019 RIverhead school board presentation construction progress and budget
18/32
18
BBSRoanoke Elementary School Progress
Toilet Rooms
-
8/20/2019 RIverhead school board presentation construction progress and budget
19/32
19
BBSPulaski Elementary School Progress
Cafeteria Addition
-
8/20/2019 RIverhead school board presentation construction progress and budget
20/32
20
BBSPulaski Elementary School Progress
Classroom Renovations
-
8/20/2019 RIverhead school board presentation construction progress and budget
21/32
21
BBSPulaski Elementary School Progress
Professional Development Room
-
8/20/2019 RIverhead school board presentation construction progress and budget
22/32
22
BBS
-
8/20/2019 RIverhead school board presentation construction progress and budget
23/32
23
BBS
All figures are subject to adjustment. 10/13/15
-
8/20/2019 RIverhead school board presentation construction progress and budget
24/32
All
figures
are
subject
to
adjustment. 10/13/15
All
figures
are
subject
to
adjustment. 1
Riverhead CSD$78,334,247 Capital
Construction Project
Presented by Sam M. Schneider, AssistantSuperintendent for Finance and Operations
Riverhead Central School District
Board of Education Meeting
October 13, 2015
All
figures
are
subject
to
adjustment. 10/13/15
-
8/20/2019 RIverhead school board presentation construction progress and budget
25/32
g j j / /
All
figures
are
subject
to
adjustment. 2
Capital Construction Project• In October 2011, the voters approved spending
$78,334,247 on capital construction projects atall seven schools and some athletic fields.
Conception Reality
All
figures
are
subject
to
adjustment. 10/13/15
-
8/20/2019 RIverhead school board presentation construction progress and budget
26/32
All
figures
are
subject
to
adjustment. 3
Capital Construction Project
• The voters were presented with an projected budget for each project within the$78,334,247.
• Where individual school projects have been
completed for less than originally anticipated,the funds are transferred to other school projects where costs have increased, but thefinal cost for all eight projects will not exceed
$78,334,247.
All
figures
are
subject
to
adjustment. 10/13/15
-
8/20/2019 RIverhead school board presentation construction progress and budget
27/32
All
figures
are
subject
to
adjustment. 4
Transfers Among Projects
• Projects can generate savings over the initial budget due to:
– Favorable bidding climate
– Few unanticipated expenses – Less extensive original work scope
Project
Initial
Budget Final Budget Savings
McKillop Field $1,604,751 $931,505 $673,246Aquebogue $3,807,996 $3,130,834 $677,162
Riley $5,666,831 $5,346,251 $320,580
These funds were transferred to other projects, including RHS and RMS.
All
figures
are
subject
to
adjustment. 10/13/15
-
8/20/2019 RIverhead school board presentation construction progress and budget
28/32
All
figures
are
subject
to
adjustment. 5
Change Orders?
• A change order is an agreement between the
contractor and the District to alter the originalcontract of work to either add or delete work.
• Change orders are funded through contingency
funds that were built into the $78,334,247approved by the voters.
• Change orders are for: – Discovery of unanticipated conditions
– Design changes necessitated by building code or practical realities
All
figures
are
subject
to
adjustment. 10/13/15
-
8/20/2019 RIverhead school board presentation construction progress and budget
29/32
All
figures
are
subject
to
adjustment. 6
Bond Expenditures as of Oct. 1, 2015by School
Project
Original
Estimate
Current
Budget
Expenditures as
of 10/1/15
Encumbrances
Outstanding
Unencumbered
Balance
Aquebogue $3,807,996 $3,130,834 $3,130,834 $0 $0
Phillips $4,025,891 $4,109,168 $4,109,168 $0 $0
Riley $5,666,831 $5,346,251 $5,346,251 $0 $0
McKillop Field $1,604,751 $931,505 $842,803 $88,702 $0
High School $32,129,979 $33,256,165 $30,719,942 $2,391,599 $144,623
Middle School $15,426,347 $16,171,341 $12,571,836 $3,546,546 $52,959
Roanoke $7,791,777 $8,356,284 $2,077,150 $6,121,974 $157,159
Pulaski $7,880,675 $7,032,699 $2,213,081 $4,427,487 $392,133
Total $78,334,247 $78,334,247 $61,011,065 $16,576,308 $746,874
The above figures do not include money appropriated by the
Board from the Repair Reserve, which are not capital expenses
even when such work is performed by the same contractor.
All
figures
are
subject
to
adjustment. 10/13/15
-
8/20/2019 RIverhead school board presentation construction progress and budget
30/32
All
figures
are
subject
to
adjustment. 7
Bond Expenditures as of Oct. 1, 2015by Category
Miscellaneous costs include printing costs during the bidding
process, professional movers who pack buildings in and out,
temporary signage, temporary relocation of utilities, etc.
Category
Expenditures as
of 10/1/15
Encumbrances
Outstanding
Unencumbered
Balance
Attorney $143,478 $102,000 $9,803
Misc. Costs $361,766 $85,369 $17,177
Survey/Engineering $905,138 $170,068 $176,748
Construction Mgr. $1,610,125 $262,485 $4,569
Architect $3,855,187 $270,775 $16,342Furniture/Equipment $2,967,162 $1,229,187 $101,064
Construction $51,168,209 $14,456,424 $421,171
Total $61,011,065 $16,576,308 $746,874
Grand Total: $78,334,247
All
figures
are
subject
to
adjustment. 10/13/15
-
8/20/2019 RIverhead school board presentation construction progress and budget
31/32
All
figures
are
subject
to
adjustment. 8
Bond Revenue
• The Riverhead CSD has
financed the projects byissuing three series of bonds, spaced out toensure that money is
only borrowed when itis needed.
• Bonds are sold on theopen market to the
bidder offering thelowest interest rate.
Official Statement issued for bonds
All
figures
are
subject
to
adjustment. 10/13/15
-
8/20/2019 RIverhead school board presentation construction progress and budget
32/32
All
figures
are
subject
to
adjustment. 9
Bond Revenue• November 2012
– $13,500,000 bonds
– 20 year repayment – 2.65% average interest rate
• March 2014 – $32,572,000 bonds
– 20 year repayment – 3.1625% average interestrate
• November 2015 – $32,262,247 bonds
– 15 year repayment – Interest TBD at closing
Moody’s Investors Service rating of Aa2.