James A Morrison PE Kiewit Infrastructure Engineers
Risk Management in Deep Foundation Construction
Gerenciamento de Risco na Construção de Fundações Profundas
1. Design error 2. Changed conditions 3. Build it wrong 4. Final cost exceeds budget 5. Product does not work 6. Third party damage
Deep Foundations Institute
What could go wrong ? O que poderia dar errado?
“The party in the best position to manage the risk owns it.”
North American Common Law…. Direito Comum Norte Americano…
Designer Contractor Owner
Design error X Changed conditions X Build it wrong X Final cost exceeds budget X X X Product does not work X Third party damage X X
Who can best manage the risk? Quem pode gerenciar melhor o risco?
Insurance Contract Quality Control
Design error X X Changed conditions X Build it wrong X Final cost exceeds budget X X Product does not work X X Third party damage X
Best vehicle for managing risk Melhor meio de gerenciamento de risco
Ris
k O
wne
rshi
p R
isk Ow
nership
Lump Sum Design-Build
Time & Materials
0 0
50 %
100 % 100 %
50 %
Owner Contractor
Contract Relationship Relação Contratual
Owner gets . . .
GAMBLERS
If Contractor owns all risk… Se o empreiteiro possui todos os riscos...
Owner gets . . .
ACCOUNTANTS
If Owner owns all the risk…. Se o proprietário possui todos os riscos...
1) Contract type • Bid-build • Design build • Public/private partnership (P3)
2) Changed condition clause 3) Geotechnical baseline reports 4) Risk register
Key Contract Provisions Cláusulas Principais dos Contratos
1) Design Errors and Omissions 2) Owner Provided Insurance Programs 3) Public Liability 4) Builders Risk Insurance
Key Insurance vehicles for construction Principais meios de seguro para a construção
1) Select best Contracting Method for the Project
2) Align Contract Provisions with party best able to manage risk
3) Changed Conditions Clause – clear and fair
4) Geotechnical Baseline Report - to establish fair basis of contract
5) Strong Quality Control program
Summary Resumo
James A Morrison PE Kiewit Infrastructure Engineers
Risk Management in Deep Foundation Construction