Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

58
County of Fairfax, Virginia Reston Network Analysis Existing Conditions Stakeholders Meeting November 20, 2015 Kristin Calkins Fairfax County Department of Transportation

Transcript of Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

Page 1: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Reston Network AnalysisExisting Conditions

Stakeholders MeetingNovember 20, 2015

Kristin CalkinsFairfax County Department of Transportation

Page 2: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Agenda• Project Overview• Overview of Modeling Process

– Data Collection– Modeling Methodology– Analysis and Results

• Existing Conditions

• 2050 & 2030 Trip Reductions

• 2050 Model Runs

• Next Steps

• Questions And Answers

Department of Transportation 2

Page 3: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Reston Transportation RecommendationsImprovements from Reston Phase I Plan Amendment

• An Enhanced Street Network to increase connectivity• Three additional Toll Road Crossings

– Town Center Parkway Underpass – Soapstone Drive Overpass– South Lakes Drive Overpass

• Grade Separate Fairfax County Parkway/Sunrise Valley Drive

Department of Transportation3

Page 4: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Enhanced Street Network• Maintains a balance between land use and transportation• Provide alternate routes through the TSAs for all modes• Ensures pedestrian mobility & connectivity throughout

the Transit Station Areas (TSAs)• Provides connectivity for bikes• Support bus service to Metrorail• Strengthened by a strong Transportation Demand

Management (TDM) program in the TSAs

Department of Transportation 4

Page 5: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Study Area

Department of Transportation5

Page 6: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Purpose of Study• Conduct a detailed analysis of the grid of streets to

determine:– Signal Control– Number of lanes between and at intersections– How to best serve pedestrians, bikes and transit– Right-of-way needs

• Assign urban street types and modal emphasis based on Department of Rail and Public Transportation Multimodal System Design Guidelines

• Conduct a phasing analysis of when larger projects are needed

Department of Transportation 6

Page 7: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Reston Network Analysis Tasks1. Data Collection – done2. Existing Conditions – being finalized3. Future Conditions – coordination beginning

– Determine Grid of Streets

4. Phasing Analysis 5. DRPT Classifications6. Specific location improvements for additional study

– Reston Parkway– Sunrise Valley Drive @ Fairfax County Parkway– Spring Street @ Fairfax County Parkway– Rock Hill Road Bridge

Department of Transportation 7

Page 8: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

Data Collection• Traffic

Counts in June 2015

• Travel Time Runs

Existing Conditions• Cap

acity Analysis

• Level of Service

Test Grid of Streets (2030 & 2050)• Traffic

Forecasting Capacity Analysis

• Level of Service

Mitigation• Signal

re-timing

• New links

• Turn lanes

• Additional lanes

Roadway Classification• DRPT

Design Guidelines• B

ike lanes

• Sidewalks/ Pedestrian routes

• On-Street Parking

• Transit Routes

Finalize Grid of Streets (2030 & 2050) Based on:• Advis

ory Group input

• Stakeholder input

• Community input

Phasing Analysis• Priori

tization of larger projects

Network Analysis Project Process

Advisory Group input, Stakeholder input, Community input

Page 9: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Data Needs• Completed

– Intersections Turning Movement Counts (TMCs)– Intersections for Queue Measurement– Speed Run Routes– Synchro input and output files– Driveway Locations– Future Grid of Street Plans

• Future– Mitigation Plans

Department of Transportation9

Page 10: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Data Needs – 7 Speed Run Routes

Department of Transportation 10

Page 11: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Department of Transportation

Data Needs – 40 TMC/20 Queue Lengths

Page 12: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Data Needs – SYNCHRO Network

Department of Transportation12

Page 13: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Data Inputs to VISUM Model Process• MWCOG / Fairfax County Models• GIS Layers (Traffic Analysis Zones; Parcels;

Aerial Imagery)• Traffic Counts (Freeways & Arterials)• Other Available Traffic Counts• Traffic Signal Timings• SYNCHRO for Signal Optimization

Department of Transportation 13

Page 14: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Modeling Flowchart Base ConditionMWCOG 2.3

Fairfax CountyTDM

(Reston Meso

Model VISUM)

UpdateTime

VISSIMSYNCHRO

GIS

Slicing 30 minTAZ Disagg

Department of Transportation 14

Page 15: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Department of Transportation

Modeling Flowchart Future Condition

UpdateTime

MWCOG 2.3

Fairfax CountyTDM

)

Slicing 30 minTAZ Disagg

ITE TGTOD credit

Land Use

(Reston Meso

Model VISUM)

VISSIMSYNCHRO

GIS

Page 16: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Methodology• County Model

– Seed trip tables• VISUM

– Model development at mesoscopic (local roadway system & driveway ) level.

• VISUM model input– Traffic volumes and O-D trip tables– SYNCHRO for signal timing optimization

• VISUM model output– Seamlessly translated to the VISSIM simulation model at the

microscopic (roadway intersection) level.• VISSIM model – DTR Only

– Microscopic analyses – adds intersection and driveway level details

Department of Transportation 16

Page 17: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Land Use & Transportation• Test transportation improvements needed to support the

land use potential approved in the Reston Phase I Comprehensive Plan

Department of Transportation17

Page 18: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

MWCOG Regional Model

TysonsReston

Department of Transportation 18

Page 19: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Reston VISUM Model

Tysons

Reston

Department of Transportation 19

Page 20: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

TAZ Zonal Split – Block Level

Department of Transportation 20

Page 21: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

TAZ Zonal Split – Driveway Entrances

Department of Transportation21

Page 22: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Base Calibration Procedure

Network Model

Demand Matrix

Assignment TFlowFuzzy

Count Data

VISSIM

Department of Transportation23

Page 23: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Calibration Parameter/Procedure• VISUM/VISSIM

– Field Observed Volume– Field Observed Queue– Field Observed Corridor Travel Time

• VISSIM (DTR only)– VDOT Traffic Operation Tool Guidebook– Formula– Number of Model Runs– Confidence Level– Tolerance Level

Department of Transportation 24

Page 24: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Analysis and Results• Measure of Effectiveness (MOE) from VISSIM

– Field Observed vs. Model Volume– Field Observed vs. Model Queue– Field Observed vs. Model Corridor Travel Time

• Measure of Effectiveness (MOE) from VISUM– Network Wide R2 Value– Field Observed vs. Model Volume– Intersection LOS

Department of Transportation25

Page 25: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

VISSIM Results

Department of Transportation 26

Page 26: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Dulles Toll Road AM Mainline Volumes

7:00-8:00 6:00-9:000

1000200030004000500060007000

WB DTR Mainline east of Route 28 split

Field Vissim

7:00-8:00 6:00-9:000

2000400060008000

100001200014000

WB DTR Mainline east of Hunter Mill Road off ramp

Field Vissim

7:00-8:00 6:00-9:000

5000

10000

15000

20000

EB DTR Mainline east of Route 28/Airport merge

Field Vissim

7:00-8:00 6:00-9:000

5000

10000

15000

20000

25000

EB DTR Mainline east of Hunter Mill Road on ramp

Field Vissim

Department of Transportation 27

Page 27: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Dulles Toll Road Exit Ramp Queues7:00 AM – 8:00 AM

ID Westbound Exit Ramp VISSIMVolume

FieldVolume GEH

VISSIM Max Queue Field Max Queue Ramp

Length (ft)Vehicles Feet Vehicles Feet

2 Centreville Road & DTR WB ramps 703 700 0.1 12 298 15 375 1460

16 Fairfax County Parkway & WB DTR ramps

552 575 1.0 7 167 6 150 1315

27 Reston Parkway & WB DTR ramps 717 815 3.5 8 190 7 175 1700

36 Wiehle Avenue & WB DTR ramps 312 405 4.9 8 195 9 225 1175

40 Hunter Mill Road & WB DTR ramps 354 360 0.3 11 251 8 200 1520

ID Eastbound Exit Ramp VISSIMVolume

FieldVolume GEH

VISSIM Max Queue Field Max Queue Ramp

Length (ft)Vehicles Feet Vehicles Feet

3 Centreville Road & DTR EB ramps 397 450 2.6 12 282 11 275 1515

17 Fairfax County Parkway & EB DTR ramps

919 875 1.5 22 539 9 225 1230

28 Reston Parkway & EB DTR ramps 521 540 0.8 10 240 5 125 1160

37 Wiehle Avenue & EB DTR ramps 680 535 5.9 14 332 17 425 850

41 Hunter Mill Road & EB DTR ramps 355 360 0.3 15 352 5 125 975

Department of Transportation 28

Page 28: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Dulles Toll Road AM Travel Times

Direction Field VISSIM DifferenceWestbound 06:33 05:44 -00:49

Eastbound 08:32 08:30 00:03

Centreville Road – Hunter Mill Road

Department of Transportation29

Page 29: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Dulles Toll Road AM Animation

Department of Transportation 30

Page 30: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Dulles Toll Road PM Mainline Volumes

17:00-18:00 16:00-19:000

5000

10000

15000

20000

WB DTR Mainline east of Route 28 split

Field Vissim

17:00-18:00 16:00-19:000

5000

10000

15000

20000

25000

WB DTR Mainline east of Hunter Mill Road off ramp

Field Vissim

17:00-18:00 16:00-19:000

2000

4000

6000

8000

10000

EB DTR Mainline east of Route 28/Airport merge

Field Vissim

17:00-18:00 16:00-19:000

2000400060008000

100001200014000

EB DTR Mainline east of Hunter Mill Road on ramp

Field Vissim

Department of Transportation 31

Page 31: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Dulles Toll Road Exit Ramp Queues5:00 PM – 6:00 PM

ID Westbound Exit Ramp VISSIMVolume

FieldVolume GEH

VISSIM Max Queue Field Max Queue Ramp

Length (ft)Vehicles Feet Vehicles Feet

2 Centreville Road & DTR WB ramps 976 1055 2.5 29 721 16 400 1460

16 Fairfax County Parkway & WB DTR ramps

1172 1215 1.2 19 465 13 325 1315

27 Reston Parkway & WB DTR ramps 522 815 11.3 14 336 9 225 1700

36 Wiehle Avenue & WB DTR ramps 540 580 1.7 9 222 11 275 1175

40 Hunter Mill Road & WB DTR ramps 486 570 3.7 25 618 24 600 1520

ID Eastbound Exit Ramp VISSIMVolume

FieldVolume GEH

VISSIM Max Queue Field Max Queue Ramp

Length (ft)Vehicles Feet Vehicles Feet

3 Centreville Road & DTR EB ramps 228 310 5.0 9 222 12 300 1515

17 Fairfax County Parkway & EB DTR ramps

630 675 1.8 34 834 10 250 1230

28 Reston Parkway & EB DTR ramps 461 500 1.8 17 403 5 125 1160

37 Wiehle Avenue & EB DTR ramps 218 150 5.0 7 164 7 175 850

41 Hunter Mill Road & EB DTR ramps 342 430 4.5 23 563 6 150 975

Department of Transportation 32

Page 32: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Dulles Toll Road PM Travel Times

Direction Field VISSIM DifferenceWestbound 07:00 7:24 00:24

Eastbound 05:26 05:49 00:23

Centreville Road – Hunter Mill Road

Department of Transportation33

Page 33: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Dulles Toll Road PM Animation

Department of Transportation 34

Page 34: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

VISUM Results

Department of Transportation35

Page 35: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Link Base Confidence LevelAM Peak (7:00 – 8:00) Area-wide

Department of Transportation36

Page 36: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Link Base Confidence LevelPM Peak (5:00 – 6:00) Area-wide

Department of Transportation 37

Page 37: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Turning Movement Confidence LevelAM Peak (7:00 – 8:00) Area-wide

Department of Transportation38

Page 38: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Turning Movement Confidence LevelPM Peak (5:00 – 6:00) Area-wide

Department of Transportation39

Page 39: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

0

4000

8000

12000

Field Count vs. Assigned Vol-umes

EB DTR Mainline & Ramps (7:00 - 8:00 AM)

Field Count (7:00-8:00 AM)Assignment Volumes (7:00-8:00 AM)

Department of Transportation40

Page 40: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

DTR Eas

t of H

unter

Mill

Rd

DTR WB to

Wieh

le Ave

Wiehle

Ave to

DTR W

B

DTR WB to

Res

ton P

kwy

Reston

Pkw

y to W

B DTR

DTR WB to

Fairfax

Cou

nty P

kwy

Fairfax

Cou

nty P

kwy t

o WB D

TR

DTR WB to

Cen

trevil

le Rd

Centre

ville

Rd to D

TR WB

DTR WB ju

st ea

st of

Rt28/R

t267 s

plit

0100020003000400050006000700080009000

10000

Field Count vs. Assigned VolumesWB DTR Mainline & Ramps (5:00 -

6:00 PM)

Field Count (5:00 - 6:00 PM)Assignment Volumes (5:00 - 6:00 PM)

Department of Transportation41

Page 41: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Fox M

ill Roa

d

Sunris

e Vall

ey D

rive

South

of DTR E

B Ram

ps

Betwee

n DTR R

amps

North o

f DTR W

B Ram

ps

Ramp t

o Spri

ng S

treet

New D

omini

on P

arkway

Baron C

amero

n Ave

nue

0

500

1000

1500

2000

2500

3000

Field Count vs. Assigned VolumesNB Fairfax County Pkwy (7:00 -

8:00 AM)

Field Count (7:00-8:00 AM)Assignment Volumes (7:00-8:00 AM)

Department of Transportation42

Page 42: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

0500

10001500200025003000

Field Count vs. Assigned VolumesSB Fairfax County Pkwy (5:00 -

6:00 PM)

Field Count (5:00 - 6:00 PM)Assignment Volumes (5:00 - 6:00 PM)

Department of Transportation43

Page 43: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

McLea

ren R

oad/L

awye

rs Roa

d

Fox M

ill Roa

d

Glade D

rive

South

Lake

s Driv

e

Sunris

e Vall

ey D

rive

South

of DTR E

B Ram

ps

Betwee

n DTR R

amps

North o

f DTR W

B Ram

ps

Bluemon

t Way

New D

omini

on P

arkway

/Tempo

rary R

oad

Baron C

amero

n Ave

nue

0

500

1000

1500

2000

2500

Field Count vs. Assigned VolumesNB Reston Pkwy (7:00 - 8:00 AM)

Field Count (7:00-8:00 AM)Assignment Volumes (7:00-8:00 AM)

Department of Transportation44

Page 44: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Baron C

amero

n Ave

nue

New D

omini

on P

arkway

/Tempo

rary R

oad

Bluemon

t Way

Reston

Pkw

y SB - N

orth o

f DTR W

B Ram

ps

Reston

Pkw

y SB - b

etwee

n DTR R

amps

Reston

Pkw

y SB - S

outh

of DTR E

B Ram

ps

Sunris

e Vall

ey D

rive

South

Lake

s Driv

e

Glade D

rive

Fox M

ill Roa

d

McLea

ren R

oad/L

awye

rs Roa

d0

500

1000

1500

2000

2500

3000

3500

Field Count vs. Assigned VolumesSB Reston Pkwy (5:00 - 6:00 PM)

Field Count (5:00 - 6:00 PM)Assignment Volumes (5:00 - 6:00 PM)

Department of Transportation45

Page 45: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Existing Conditions

Department of Transportation46

Page 46: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Existing Intersection LOSIndividual Movements may have a lower Level of Service

Department of Transportation47

Page 47: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Existing Intersection LOS (Cont’d)Individual Movements may have a lower Level of Service

Department of Transportation48

Page 48: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Existing Intersection LOS (Cont’d)Individual Movements may have a lower Level of Service

Department of Transportation49

Page 49: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Existing Wiehle-Reston East Walkshed

Department of Transportation 50

Page 50: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Existing Reston Town Center Walkshed

Department of Transportation 51

Page 51: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Existing Herndon Walkshed

Department of Transportation52

Page 52: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Existing Reston TSA Walk-shed

Department of Transportation53

Page 53: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

DevelopmentPeak Hour – Future Trips

0-1/4 Mile ¼ to ½ MileBeyond ½

Mile

  2030 2050 2030 2050 2030 2050

Office 40% 45% 35% 40% 30% 35%

Residential 40% 45% 35% 40% 20% 25%

Technological Advancement for all Trips

- 7.5% - 7.5% - 7.5%

TDM Vehicle Trip Reduction Goals

Reductions based off of ITE Trip Generation Rates

Department of Transportation54

Page 54: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Information Available at Request• 2030 Land use• 2050 Land use• 2050 Grid - # lanes• 2014 Trip Generation• 2030 Trip Generation• 2050 Trip Generation

Department of Transportation55

Page 55: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

2050 Model Runs• Test 2050 Comp Plan Build Out• Mitigation Measures - Tiered Approach

• No right of way impact – Trip Re-assignment– Optimize Signal Timing and Phasing– Modify the Lane Configuration– Evaluate 4-way Stop vs. 2-way Stop– Traffic Signal Addition

• Some right of way impact– Turn lanes– Additional through lane– Additional grid link

• Large scale mitigations if needed– Discussion with Advisory Group and Stakeholders Group

Department of Transportation 56

Page 56: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Next Steps• 2030 Model Runs • DRPT Guidelines Roadway Classification• Phasing Analysis• Reston Comprehensive Plan Amendment

• If needed to integrate finalized grid of streets• Four Specific Study Locations

• Reston Parkway• Fairfax County Parkway at Spring Street • Fairfax County Parkway at Sunrise Valley Drive• Rock Hill Bridge

Department of Transportation 57

Page 57: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Schedule

Department of Transportation 58

Task Description

1A Land Use and Networks - Task is Complete

1B Traffic Counts - Task is Complete

2A Establish Existing Conditions - Task is Complete

2B Calibrate Against Existing Conditions - Task is Complete

3A2 Analyze Future Conditions (2050)

3A1 Analyze Future Conditions (2030)

3B Simulation of the Dulles Toll Road

3C Microsimulation - Optional

4A Meetings/Presentations

5A Phasing Analysis - Existing Conditions

5B Phasing Analysis - 2050 - Optional

6 Determination of DRPT Guidelines Roadway Classification

7 Documentation

8 Reston Parkway Capacity Improvements

9 Fairfax County Parkway & Spring Street Interchange

10 Fairfax County Parkway & Sunrise Valley Drive

11 Rock Hill Bridge at Sunrise Valley Drive

12A Meetings/Presentations

Feb-15May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Sep-16 Oct-16Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16

11/17/15

Page 58: Reston Network Analysis - Existing Conditions - Stakeholders Meeting: Nov. 20, 2015

County of Fairfax, Virginia

Questions & Comments

For questions and comments about the study please contact:

Kristin Calkins: [email protected](703) 877-5710

Department of Transportation 59