Renewable Generation Studies
description
Transcript of Renewable Generation Studies
January 28, 2009
1/28/09 FERC / WestConnect Webinar
Renewable Generation Studies
1/28/09 FERC / WestConnect Webinar 2
Types of Renewable Resource Studies in 2008
Individual Utility Studies
– PNM’s 2008 Collector System Study
State Study Requirements
– Colorado Senate Bill 100
– Nevada RETAAC Study
– Arizona Corporation Commission BTA Renewable
Subregional Study
– SWAT Renewable Transmission Taskforce
January 28, 2009
1/28/09 FERC / WestConnect Webinar
2008 Colorado SB 100 Study
Tom Green,Public Service Company of Colorado
1/28/09 FERC / WestConnect Webinar 4
Senate Bill 100 Status2
Dec 18, 2008 CPUC workshop on SB-100 plans to allow stakeholder input and feedback on priority.
Jan 12, 2009 CPUC workshop for stakeholder response
Feedback from CPUC on priority of CPCN’s on transmission plans
Future CPCN process for SB-100 projects
2. Colorado Senate Bill SB 07-100, codified at C.R.S. § 40-2-126
1/28/09 FERC / WestConnect Webinar 5
Zone 4Zone 5
Zone 1
Zone 2
Zone 3
VilasCalumet
Missile Site
Ault
Cherokee
Pawnee
Smoky Hill
Daniels Park
ComancheLamar
345kV
230kV
SB-100 Transmission Plan
1/28/09 FERC / WestConnect Webinar 6
7
Renewable EnergyTransmission in
Nevada
Brian WhalenTransmission Planning Manager
WestConnect Planning Webinar with FERC January 28th, 2009
8
WHY? RPS and NV Energy’sGreen Attitude
6 new projects (135 MW) in-service 2007-08
8 geothermal projects (~280 MW) under development
2 of the U.S.’s largest solar plants now in Southern Nevada
Plan to add 200 to 400 MW of wind. Joint Ventures in place.
Current portfolio consists of 36 projects totaling 586 MW
1,000 MW by end of 2012
8
9
Solar Power
Mojave Desert, centered in Southern CA and extending into Southern NV is the U.S. prime solar resource
Nevada is a leader in solar power per capita
Solar technologies improving
Cost per kWh is relatively high but declining
9
10
Local NV Energy Initiatives
Public Utilities Commission of Nevada approved permitting of
both 250 miles of 500 kV and 40 miles of 345 kV, plus siting studies for over 600 miles of new backbone transmission
10
11
State / NV Energy Initiatives
“RETAAC”
Renewable Energy Transmission Access Advisory Committee
Global resource mapping tool for NV developers
– Land use
– Exclusion area
– Resource areas
– Transmission
Phase II Investigation of
funding alternatives
– Merchant
– New State Agency
– Existing State Agencies
– Open season Recommendation of
specific collector systems to pursue.
12
RETAAC
BLM & NVE queues
4 types of resources
Trunk line development
Multi- stakeholder Effort BLM NDOW Municipals IOU IPP State Agencies Environmental
Groups
12
13
Regional / Federal / NV Energy Initiatives
WestConnect / SWAT renewables studies (presented by P. Krzykos)
Nevada Siting Issues Significant Constrained
Areas (environmental or government use)
> 80% of Nevada is controlled by Federal Government
Nevada has BLM, USFWS, DOE, DOD, BIA, DOI, …
• Problems with any single agency can stop an entire project.
Potential Solutions Draft DOE §386 Corridor
Process1/3 of total in Nevada
(2000 miles) Federal master agreements
14
Questions
14
January 28, 2009
1/28/09 FERC / WestConnect Webinar
PNM’s 2008 Collector System Study
Tom Duane,Public Service Company of New Mexico
Stage 4Continue transmission expansion into wind resource zones
Complete wind collector system for up to 2400 MW
WillardWillardWillardWillard
GuadalupeGuadalupeGuadalupeGuadalupe
Ft. CraigFt. CraigFt. CraigFt. Craig
BABABABA
BelenBelenBelenBelen
VL TapVL TapVL TapVL Tap
Total WindGuadalupe/Willard/Duran: 2450 MW
Existing 345 kV line
New stationExisting stationProposed wind projectExisting or committed wind project
Existing 115 kV line
New 345 kV line
• Expand Willard, Duran and Guadalupe 345 kV stations• Build Duran – Guadalupe 345 kV (two lines) (55 mi)• Build Willard – Duran 345 kV (second line) (50 mi)
Total Cost for Stages 0-4: ~$670M
100
200
DuranDuranDuranDuran
700
250
650
GladstoneGladstoneGladstoneGladstone 1200
150
400
Stage 5+Integration with High Plains Express
WillardWillardWillardWillard
Ft. CraigFt. CraigFt. CraigFt. Craig
BABABABA
BelenBelenBelenBelen
GladstoneGladstoneGladstoneGladstone
VL TapVL TapVL TapVL Tap
Total WindGuadalupe/Willard/Duran:
> 4000 MW (?)
• Build HPX 500 kV lines (may not need two circuits from Guadalupe to Ft Craig)• Install 500/230 kV transformer at Gladstone• Install 500/345 kV transformer at Guadalupe• Install 500/345 kV transformer Ft Craig• Install 500/345 kV transformer at Duran
100
200
DuranDuranDuranDuran
>1000250
>1000
150
400
Existing 345 kV line
New stationExisting stationProposed wind projectExisting or committed wind project
Existing 115 kV line
New 345 kV line
1200
January 28, 2009
1/28/09 FERC / WestConnect Webinar
SWAT Renewable Transmission Task Force
Peter Kryzkos,Arizona Public Service
Potential Resource Location
1/28/09 FERC / WestConnect Webinar 20
SWAT Renewable Transmission Task Force 2009 Study Plan
Renewable potential in Arizona
– Update queue
• Interconnection queue has exceeded Arizona Renewable Energy Assessment results in some areas
– Arizona solar queue is now ~12,000 MW
– Utilize regional renewable data (NREL, etc.)
Update potential transmission circuits in Arizona
– Refine conceptual corridors based on resources and development potential
1/28/09 FERC / WestConnect Webinar 21
Arizona Solar Queue Comparison (Page 1 of 2)
Company COD POI County
MW Size
July 2008 Queue December 2008 Queue
TEP 2012 South-Green Valley 138 kV line Pima 250 250
APS 2011 Harquahala Jnc Maricopa 110 110
APS 2011 Panda Liberty line Maricopa 102 102
APS 2010 North Gila Sub Yuma 400 400
APS 2012 Proposed Harquahala Junction Maricopa 400 400
APS 2012 Proposed Harquahala Junction Maricopa 800 800
APS 2008 North Gila Sub Yuma 250 250
APS 2012 Proposed Harquahala Junction Maricopa 500 500
APS 2013 Proposed PV-NG2 500 kV line Yuma 500 500
APS 2011 Gila Bend 230 kV Sub Maricopa 280 280
SRP 2012 Pinal Central Pinal 0 125
SRP 2010 Hassayampa Maricopa 0 180
SRP 2011 Hassayampa Maricopa 0 180
SRP 2012 Hassayampa Maricopa 0 180
SRP 2014 Hassayampa Maricopa 0 180
SRP 2012 Jojoba Maricopa 0 500
SRP 2011 Hassayampa Maricopa 0 125
SRP future Hassayampa Maricopa 0 62.5
SRP future Hassayampa Maricopa 0 40
SRP 2012 Hassayampa Maricopa 0 250
1/28/09 FERC / WestConnect Webinar 22
Arizona Solar Queue Comparison (Page 2 of 2)
Company COD POI County
MW Size
July 2008 Queue December 2008 Queue
WAPA 2012 ED4 Pinal 0 80
WAPA 2012 ED5 Pinal 0 80
WAPA 2012 Harcuvar 115kV LaPaz 0 125
WAPA 2014 Harcuvar 230kV Maricopa 0 250
APS 2013 Gila Bend 230 kV Sub Pinal 0 250
APS 2012 Casa Grande 69kV Pinal 0 80
APS 2012 Laguna and Yucca 69kV Yuma 0 80
APS 2012 Milligan 69kV Pinal 0 80
APS 2012 Santa Rosa 69kV Pinal 0 80
APS 2012 San Manuel 115kV Pinal 0 320
APS 2011 Pollock Yavapai 0 74
APS 2012 Harquahala Junction Maricopa 0 300
APS 2013 Harquahala Junction Maricopa 0 600
CAISO 2015 Devers - Palo Verde La Paz 0 900
CAISO 2014 Devers - Palo Verde La Paz 0 900
CAISO 2015 Devers - Palo Verde Maricopa 0 900
CAISO 2011 North Gila - Hassayampa Maricopa 0 300
CAISO 2014 Devers - Palo Verde 2 La Paz 0 250
CAISO 2014 Devers - Palo Verde 2 Maricopa 0 250
CAISO 2014 Mohave Switchyard La Paz 0 250
CAISO 2012 Hassayampa - North Gila Yuma 0 280
TOTAL 3592 12043.5
1/28/09 FERC / WestConnect Webinar 23
National Renewable Energy Laboratory (NREL)
Taken Directly from NREL website: http://www.nrel.gov/csp/images/1pct_csp_az.jpg
Concentrating Solar Power Prospects in
Arizona
Quality of Wind Resources In Arizona
*Developed by DOE and NREL
• At 50m elevation, Class 4 or higher is typically used for utility scale wind generation (NREL).
• At 80m elevation, Class 3 areas could have higher wind power class because of possible wind shear (NREL)
• Arizona has predominately Class 3 or lower wind resources
Taken Directly from the United States Department of Energy website: http://www.eere.energy.gov/windandhydro/windpoweringamerica/maps_template.asp?stateab=az
Taken Directly from NREL website: http://www.nrel.gov/csp/images/1pct_csp_az.jpg
+
Co. COD POI County
MW Size
July 2008 Queue
Dec. 2008 Queue
TEP 2012
South-Green Valley 138 kV line Pima 250 250
APS 2011 Harquahala Jnc Maricopa 110 110
APS 2011 Panda Liberty line Maricopa 102 102
APS 2013
Proposed PV-NG2 500 kV line Yuma 500 500
APS 2011 Gila Bend 230 kV Sub Maricopa 280 280
SRP 2012 Pinal Central Pinal 0 125
SRP 2010 Hassayampa Maricopa 0 180
SRP 2011 Hassayampa Maricopa 0 180
SRP 2012 Hassayampa Maricopa 0 180
SWAT Renewable Transmission Task Force Refining Solar Resource and Transmission Potential in Arizona
As and Example
Overlay SWAT RTTF conceptual transmission and injection Overlay SWAT RTTF conceptual transmission and injection points with solar resource datapoints with solar resource dataCombine with information from interconnection queue of Combine with information from interconnection queue of regional utilitiesregional utilities
1/28/09 FERC / WestConnect Webinar 26
1510 MW1510 MW
530 MW530 MW
8835 MW8835 MW
845 MW845 MW
Conceptual Refined Arizona Solar Resource Zones
DRAFT
1/28/09 FERC / WestConnect Webinar 27
SWAT Renewable Transmission Task Force Next Steps
Refine renewable potential / locations
– Analyze regional renewable resource data
– Evaluate interconnection queue information
– Refine injection points and transmission corridors
– Conduct these efforts throughout SWAT footprint
Evaluate transmission plans for 20% (2018 case year) of total projected renewable generation built and potentially a 40% (2025 case year) scenario.
Technical Study