Relining of Pohang No.3 Blast Furnace - Home -...

15
Relining of Pohang No.3 Blast Furnace 2017. 5. 22 POSCO, Ho-soon JANG I. Outline II. Relining Criterion III. Relining Strategy IV. Conclusion

Transcript of Relining of Pohang No.3 Blast Furnace - Home -...

Relining of Pohang No.3 Blast Furnace

2017. 5. 22

POSCO, Ho-soon JANG

I. Outline

II. Relining Criterion

III. Relining Strategy

IV. Conclusion

■ Outline

○ Pohang No.3BF(blow-in May, ’06) have been relined from ‘17.2 to ‘17.6

○ Inner volume is enlarged from 4,350 to 5,600m3

■ Compare to P3R2

P3R2 P3R3

Production(t/d)

Po 9,610 (2.21) 14,000 (2.50)

Pmax 10,100 (2.32) 14,280 (2.55)

Inner Volume (㎥) 4,350 5,600

Belly Dia. (m) 14.0 15.6

Throat Dia. (m) 10.1 11.1

Tuyere (Ea) 38 42

Top Pressure (kg/cm2) 2.8 2.8

Gas cleaning D/C+Bischoff Cyclone+Bischoff

Hot stoveOne Dome Type

(Heating Area 76,000m2)One Dome Type

(Heating Area 80,000m2)

Slag granulation 6.0 t/min 9.5 t/min

FC Stave 4 lows

T-1 Stave

P3R2 P3R3

15.9m

4,350㎥CopperStave 6 lows

15.6m

17.9m

FC Stave 8 lows

Dense CoolingPlate 46 lows

FC Stave 4 lows

11.1 m10.1m

14.0m

5,600㎥

10˚ 8˚Copper 1 lows+ FC Stave 3 lows

■ Major schedule

ㅏBlow-off

’17.2.23

Blow-in

’17.6.13

Pre-construction

‘15.8 ’17.1

Approval

‘15.3 ’17.5

Test OperationContract

’15.6

Delivered Facility Construction

’17.2.24

1 / 13

■ Relining Criterion

○ The most critical factor to decide relining is hearth remaining, generally considered the

minimum remaining point is about 600mm

500

750

1000

1250

1500

1750

2000

Design Y+0 Y+1 Y+2 Y+3 Y+4 Y+5 Y+6 Y+7 Y+8 Y+9 Y+10

P3R2 ('06.5/4)

600

(mm)

■ Hearth Remaining (Calculation)

○ It is calculated by factors material heat conductivity, thermocouple temperature,

thermocouple insertion length, heat transfer coefficient, shell thickeness and so on.

2 / 13

■ P3R2 Hearth Remaining (Actual)

Remaining below No.3 TH (132˚) Confirmation of salamander (71˚)

850mm

3 / 13

B

C

D

F

G

H

I

E

Salamander

■ Extending campaign life

○ Replacement of whole belly shell

DateShutdown

TimeQuantity

1st ‘14.3.11 93Hr 17.6m (8EA), 35%

2nd ‘14.5.13 86Hr 15.6m (7EA), 31%

3rd ‘14.7.1 81Hr 17.6m (8EA), 35%

Total - 260Hr 50.8m (23EA), 100%2nd90°

3rd45°3rd

135°

Belly

Bosh

1st220°

1st0°

2nd300°

※ Shell Size : 1,280(H) x 2,239(W) x 65(T)

Cutting deformation shell Setting the new shell Welding the new shell Spray the Belly part

√ Shell installed cooling plate need to be replaced since it happened many cracks and deformation

○ Process of shell replacement

4 / 13

■ Design concept

○ Smooth furnace profile is beneficial to extend a long campaign of BF (POSCO design guideline)

As-Is To-Be

CI Stave CI Stave

High ProductivityCarbon Block

Cu-Stave Dense CP

SuperHigh Productivity

Carbon Block

Bosh angle

Strategy of a long campaign

UpperShaft

- Installed CI Stave for wear resistance and proper cooling ability

Shaft BellyBosh

- Adopted dense Cooling plate with Graphite and SiC refractory for sufficient cooling ability※ Expect a long campaign life (15→30years)

- To decrease mechanical and thermal wear with low bosh and shaft angle

Hearth

- Adopted additional one layer with BC-12SR forextending hearth campaign life

- Adopted larger block compared to the past

- To minimize refractory wear by sufficient pool depth

Shaft angle

Belly

Throat

Pool Depth

Hearth

5 / 13

■ Furnace Profile

○ Decide throat, belly and hearth diameter in line with POSCO design guideline

Belly Dia (m)

Thro

at

Dia

mete

r (m

)

Belly Dia (m)

Heart

h D

iam

ete

r (m

)

P3R3

G5R1

P3R3

G5R1

[Belley Dia. Vs Throat Dia] [Belley Dia. Vs Hearth Dia]

6 / 13

P3R2 P3R2

POSCO

■ Furnace Profile

○ Keep going to find optimal bosh & shaft angle range according to productivity and efficiency

[Bosh Angle Vs Inner Vol.] [Shaft Angle Vs Inner Vol.]

Shaft

Angle

(º)

P3R3

G5R1

Bosh

Angle

(º)

POSCO

Inner Volume (m3)Inner Volume (m3)

P3R3G5R1

7 / 13

■ Furnace Profile

○ Tuyere~T.H Vol/I.V designed about 18% in the latest BFs relining for high productivity

[Pool Depth Vs Heath Dia.] [Tuyere~Taphole Vs Heath Dia.]

Hearth Diameter (m)

Tuyere

-Taphole

(m

)

Hearth Diameter (m)

P3R3G5R1

Pool D

epth

(m

)

8 / 13

P3R3G5R1

POSCO

■ Refractory Design

○ Designed refractory based on region wear factor

○ Install SiC Bricks in the un-softened solid burden area to prevent wear of refractory

Upper Shaft

Lower Shaft & Belly

Bosh

Graphite SiC Brick

Fire Clay

Brass sheet

Wear Factor Bricks Design

Upper Shaft Mechanical ≫ HeatGraphite+SiC 2 layers

Graphite 1 layer

Lower Shaft Mechanical ≒ Heat

Graphite+SiC 1 layers

Graphite 2 layer

Belly Mechanical ≒ Heat

Bosh Mechanical ≪ Heat All Graphite

9 / 13

■ Design of Bosh & Tuyere

√ Reinforced cooling efficiency with graphite

adoption in bosh part for skull formation

√ Minimize the distance between tuyere

cooler and first low of plate coolers to

against abrasion

√ Anti-abrasion with High-Alumina brick

right above tuyere refractory

√ Installed large tuyere Block for

protecting tuyere cooler and tuyere

Skin Brick(FN-1)

High-Alumina Brick

High-Alumina BlockThickening lining

Fire Clay

Graphite

Stamping

Cushion mortar

10 / 13

■ Design of Hearth

√ Reinforced cooling efficiency with the highest

conductivity carbon (BC-12SR) in hearth wall

- additional one layer with BC-12SR

√ Installed larger carbon in hearth corner area

to avoid “elephant foot wear”

√ Upper refractories of bottom with ceramic cup

√ Hearth shell with horizontal CI stave cooling

√ Bottom cooled by water

11 / 13

■ Design of Taphole

Division P4R2 P3R3

Quantityof Block

3Piece 2Piece

Design1

21

2 3

ShellShell

Contact Surface of Refractory

○ Designed 2 piece taphole refractory to minimize contact surface of refractory

12 / 13

■ Summary

○ We are trying to optimally designed large-sized Blast furnace for furnace life

extension through lots of POSCO’s reline experience.

○ We expected to keep going high productivity & efficiency operation for a long time,

as we adopted dense cooling plate at recently relining BFs.

○ We expected that BF Campaign life can be extended at least 10~15 years through

replacement technology of Shell during ordinary shutdown period.

■ Future Plan

○ We are planning to find suitable furnace profile & cooling system when we will do

partial relining with the lowest cost.

○ How long hearth campaign life without intermediate reline? And we need to develop

intermediate hearth repair.

13 / 13

Thank you for listening!