Learn More: www.wauwatosaschools.org/referendum REFERENDUM CONSTRUCTION UPDATE Wilson/WSTEM Elementary School February 2021 RECENTLY COMPLETED WORK Steel stud framing in the administration area is complete. All slab on metal deck has been poured. Exterior building sheathing is complete. The performance platform slab on grade is complete. CONSTRUCTION QUESTIONS? Please contact Dan Nash, Site Superintendent, or Ryan Kaplanek, Project Manager, at 262-542-9000. CURRENT & UPCOMING WORK Exterior sheathing is ongoing. Mechanical, Plumbing and Electrical (MEP) overhead rough-in is ongoing. Remaining slab on metal deck and slab on grade pours to take place in the upcoming weeks. Roofing activities are ongoing. Brick install is upcoming. Administration Wing Steel Stud Framing Building South East Elevation Student Commons Community Room When complete, Wilson/WSTEM will stand roughly 45’ high at its tallest point. The worlds littlest skyscraper, the Newby-McMahon Building, stands at a whopping 40’ tall. That means, despite being an elementary school and not a high rise, Wilson/WSTEM is taller than a skyscraper! DID YOU KNOW?

Transcript of REFERENDUM CONSTRUCTION UPDATE Wilson/WSTEM … · 2021. 2. 25. · REFERENDUM CONSTRUCTION UPDATE...

Page 1: REFERENDUM CONSTRUCTION UPDATE Wilson/WSTEM … · 2021. 2. 25. · REFERENDUM CONSTRUCTION UPDATE Wilson/WSTEM Elementary School February 2021 RECENTLY COMPLETED WORK • Steel stud

Learn More: www.wauwatosaschools.org/referendum

REFERENDUM CONSTRUCTION UPDATEWilson/WSTEM Elementary SchoolFebruary 2021

RECENTLY COMPLETED WORK• Steel stud framing in the administration area is

complete.• All slab on metal deck has been poured.• Exterior building sheathing is complete.• The performance platform slab on grade is complete.

CONSTRUCTION QUESTIONS? Please contact Dan Nash, Site Superintendent, or Ryan Kaplanek, Project Manager, at 262-542-9000.

CURRENT & UPCOMING WORK• Exterior sheathing is ongoing.• Mechanical, Plumbing and Electrical (MEP) overhead

rough-in is ongoing. • Remaining slab on metal deck and slab on grade

pours to take place in the upcoming weeks.• Roofing activities are ongoing.• Brick install is upcoming.

Administration Wing Steel Stud FramingBuilding South East Elevation

Student Commons Community Room

When complete, Wilson/WSTEM will stand roughly 45’ high at its tallest point. The worlds littlest skyscraper, the Newby-McMahon Building, stands at a whopping 40’ tall. That means, despite being an elementary school and not a high rise, Wilson/WSTEM is taller than a skyscraper!