Rajesh Panicker October 2013 Wind Turbine Installation Vessels – Classification Concepts...
-
Upload
sonya-alderman -
Category
Documents
-
view
213 -
download
0
Transcript of Rajesh Panicker October 2013 Wind Turbine Installation Vessels – Classification Concepts...
Rajesh PanickerOctober 2013
Wind Turbine Installation Vessels – Classification Concepts
Supporting Sustainable Energy
© Det Norske Veritas AS. All rights reserved.
October 2013
Agenda
Introduction
Offshore Wind Developments
Classification Concepts
WTI Vessel concept – Driver for Rule and Flag requirements
DNV Rules for Wind Turbine Installation vessels
Class notations + Considerations
In-operation phase
2
© Det Norske Veritas AS. All rights reserved.
October 2013
DNV GL – The leading Classification society
InnovationHigh dedication to, and investment in, research & development
NetworkA world leading classification society with a dense station network across more than 80 countries
ExpertiseCombined leading technological expertise across all ship segments
ServiceWider and deeper service offering across all ship segments
© Det Norske Veritas AS. All rights reserved.
October 2013
Electricity Generating Costs in EU, 2015 and 2030
4
© Det Norske Veritas AS. All rights reserved.
October 2013
Offshore Wind potential – new installations The European Wind Energy Association (EWEA) increased its 2020 target to 230 GW
wind power capacity, including 40 GW offshore wind (March, 2009)
To reach 40 GW of offshore wind capacity in the EU by 2020
Average growth in annual installations of 28% - from 0.4 GW in 2008 to 6.9 GW in 2020.
Assumption - 1 vessel installs 100 turbines per year, each turbine = 4 MW
5
+ maintenance and repair
20-25 vessels needed in Europe
MarketUK 50%Germany 25%Rest 25%
© Det Norske Veritas AS. All rights reserved.
October 2013
Europe Wind Potential
6
© Det Norske Veritas AS. All rights reserved.
October 2013
7
© Det Norske Veritas AS. All rights reserved.
October 2013
8
WTI units in the market
>60-70% can not be used for future offshore developments- Insufficient crane capacity or - Insufficient size of vessel to support a large crane- weather restrictions
- Can not cope with the offshore environment – to much motions- No self propulsion or slow speed
May be used for support, maintenance and close to shore operation
© Det Norske Veritas AS. All rights reserved.
October 2013
9
WTI units in the market
During 2012 a number of new installation vessels were delivered, including.
• Northwind Installer by NorWind
• Pacific Orca by Swire Blue Ocean
• Seajacks Hydra and Zaratan by Seajacks
• Seafox 5 by Seafox Group
• Friedrich Ernestine by RWE Innogy
• Innovation by HGO InfraSea Solutions
Bold Tern by Fred Olsen Windcarrier
These purpose-built vessels, therefore, both reduce the number of harbour to wind farm site trips required during the installation process and increase the “weather window” during which offshore work can be carried out.
© Det Norske Veritas AS. All rights reserved.
October 2013
10
© Det Norske Veritas AS. All rights reserved.
October 2013
11
© Det Norske Veritas AS. All rights reserved.
October 2013
12
© Det Norske Veritas AS. All rights reserved.
October 2013
13
Growth in size of commercial wind turbine designs
© Det Norske Veritas AS. All rights reserved.
October 2013
14
© Det Norske Veritas AS. All rights reserved.
October 2013
15
Wind Turbine Foundations – Fixed
© Det Norske Veritas AS. All rights reserved.
October 2013
16
Summary
Purpose built vessels are the future for Offshore Wind
Huge investment is required for construction and maintenance of fleet
Decommissioning of old offshore wind platforms to start from 2020.
About 20 new vessels under construction/ delivery 2012-13 - € 2.5 billion investment.
Douglass Westwood forecasts average € 15 billion per year investment over next ten years (2013-2022) in offshore wind sector.
UK Round 3 provide sufficient scale for this size of investment
US Offshore Wind Potential – Assessment in Progress
© Det Norske Veritas AS. All rights reserved.
October 2013
17
Classification as a concept
Classification is required when building a flagged vessel such as a WTI unit
Classification has gained world wide recognition as an adequate level of safety and quality process which provides a sound basic safety standard
Classification serves as a verification system for a number of parties who have special interest in the safety and quality of MOUs, such as:- National Authorities- Insurance underwriters- Owners- Building yards and
sub-contractors- Finance institutions- Charterers
© Det Norske Veritas AS. All rights reserved.
October 2013
18
Owner, OperatorOwner, Operator
DNV-Class
Work ScopeWork Scope
Req
uir
emen
tsR
equ
irem
ents
Flag, Shelf, other
Classification Scope - Verification of Requirements
Clarification:
What is applicable for a wind turbine installation unit?
Statutory services based on delegated authority
from flag state
© Det Norske Veritas AS. All rights reserved.
October 2013
19
Classification of WTI vessels – dependant on how they operate
Type A)
”Ship shaped” Mobile Units
© Det Norske Veritas AS. All rights reserved.
October 2013
20
A) Mobile Operation - Features Designed both for transportation and installation of equipment.
Upload equipment at delivery port and sail fully loaded at high speed to installation site.
Effective propulsion and Dynamic Positioning system both for- Self propulsion - Positioning before jacking up
The vessel is designed to perform the complete installation cycle without assistance.
Main Characteristics
Ship-shaped hull.
Good/reasonable forward speed capabilities (+10 knots).
Unrestricted seagoing capabilities (without equipment).
May not be designed to survive heavy weather at site in elevated condition.
May choose to jack down and escape heavy weather.
© Det Norske Veritas AS. All rights reserved.
October 2013
21
Classification of WTI vessels – dependent on how they operate
Type B) Stationary
© Det Norske Veritas AS. All rights reserved.
October 2013
22
B) Stationary Operation Vessel stays continuously at the installation site
May be non-self propelled or have DP system, but then only for - Accurate positioning - Shorter field moves
Wind Turbine equipment are supplied to site by feeder vessels
WTI equipment installation implies offshore lifting
Long voyages of WTI vessel only by support of tugs or on deck of heavy lift transporter
Characteristics
Triangular or box shaped
Limited forward speed capabilities
Limiting/restricted seagoing capabilities
Capable of surviving heavy weather at site in elevated condition
© Det Norske Veritas AS. All rights reserved.
October 2013
23
Offshore Unit or a Maritime Vessel in DNV?
Different type of offshore vessels or units
- Self Elevating Unit
DNV-OS-C104STRUCTURAL DESIGN OF SELF-
ELEVATING UNITS (LRFD METHOD
- Column Stabilized Unit
DNV-OS-C103STRUCTURAL DESIGN OF COLUMN
STABILISED UNITS (LRFD METHOD)
Ship Shaped Vessel
DNV-OS-C107SHIP SHAPED DRILLING AND
WELL SERVICE UNITS
Self elevating or Column Stabilized?
YesNo
Offshore StandardsShip Rules
DNV-OS-C104DNV-OS-C103DNV-OS-C107
or DNV Ship Rules Requirements related
to exploration and production of
HydrocarbonesX
© Det Norske Veritas AS. All rights reserved.
October 2013
24
Definition of Class Rules & Statutory Certificates
i) Offshore Support/Crane Unit
• Offshore Rules• MODU code
ii) Self-elevating ”Cargo Ship”
• Ship Rules• MODU + SOLAS
+
The vessel will be a mix of the two regimes
Regime based on planned
operation.Decision by Flag State
+ SPS
”Stationary”
”Mobile”
© Det Norske Veritas AS. All rights reserved.
October 2013
25
Definition of Class Rules & Statutory Certificates
Type A) Ship-shaped ”Mobile” Operation
”Cargo vessel” with self-elevating capabilities.
Enters ports to pick up equipment on regular basis.
DNV Rules for Classification of Ships to be used for all ship related items.
MODU code for the elevating phase
SOLAS certificates required because of the operation as a cargo ship.
Type B) ”Stationary” Operation
Well known concept from Oil & Gas Industry.
Designed and operated as a conventional Support/Crane Unit.
Can be designed according to MODU Code and DNV Offshore Standards.
SOLAS certificates may not be required, but this cut put limitations on how the vessel can be operated.
© Det Norske Veritas AS. All rights reserved.
October 2013
26
Principles of classification WTI vessels
May not be designed to survive a 100y storm at location.
Then additional operational procedures to be established and followed:- Continuous monitoring of weather forecast- Preparedness for jack-down and escape
Robustness of jacking system to guarantee successful jack-down
© Det Norske Veritas AS. All rights reserved.
October 2013
DNV Notation 1A1 Self-Elevating Wind Turbine Installation Vessel/ Unit
27
Service notation introduced by DNV (October 2009) – OSS-101
Main motivation To provide a set of technical requirements. Recognition of vessels operational capabilities.
The requirements for the notation shall capture the primary functions and operations that are typical for these vessels.
May combine this with ”Crane Unit” This makes it easier for designers to meet our
requirements and for us to undertake the classification of the units.
© Det Norske Veritas AS. All rights reserved.
October 2013
Ship-shaped self-elevating wind turbine installation vessels
Class assumptions:
Mix of offshore jack-ups and cargo ships
NO Oil & Gas in scope and price!!
Design assumptions
Vessels carry out repeated operations in restricted waters
Established practice is to allow for limited design conditions (unlike the design and class requirements for vessels used in the offshore oil and gas business).
The design requirements needs to be consistent in order to ensure robust designs that are capable to withstand the relevant design loads for all design/operational conditions,
or being able to escape in case of bad weather.
28
© Det Norske Veritas AS. All rights reserved.
October 2013
Basic principle
Hull & structure DNV OS-C107
(Section 1 A101)
DNV-OS-C104
The hull strength may be assessed according to DNV Rules for Classification of Ships Pt.3 Ch.1 for all transit and operational conditions.
Jack-up specific items (legs, jacking gear, guides, steel categorization, elevated conditions, overturning stability, preload capacity, fatigue)
Electrical systems DNV OS-D201 Same as DNV Ship rules Part 4 Chapter 8, hence no difference.
Marine and Machinery systems
DNV OS-D101 Same requirements as for ships Offshore refers back to Ship Rules Pt. 4
Preloading and piping arrangement, water intake
DP systems SHIP Rules
Pt.6 Ch. 7
Same requirements for ship and offshore
Instrument systems Ship control systems, engine control, ballast, bilge etc there are no differences between ship and offshore
Stability & watertight integrity
DNV OS-C301 Same requirements for ship and offshore
29
Self-Elevating Unit
© Det Norske Veritas AS. All rights reserved.
October 2013
Basic principle
Hull & structure DNV OS-C103 DNV Ship rules not relevant
Electrical systems DNV OS-D201 Same as DNV Ship rules Part 4 Chapter 8, hence no difference.
Marine and Machinery systems
DNV OS-D101 Same requirements as for ships but adjustments for Semi-specific items (ballast).
Offshore refers back to Ship Rules Pt. 4
DP systems SHIP Rules
Pt.6 Ch. 7
Same requirements for ship and offshore
Instrument systems: DNV OS-D202 Ship control systems, engine control etc there are no differences between ship and offshore
Ballast & bilge special for Semi design
Stability & watertight integrity
DNV OS-C301 Special for Semi design
30
-
Column Stabilized Unit
© Det Norske Veritas AS. All rights reserved.
October 2013
31
DNV Class Notation ”Wind Turbine Installation Unit”
May be assigned to different types of vessels- A) Semi-submersible type- B) ”Stationary” Self-elevating units- C) Ship-shaped self-elevating units - D) Ships with crane or other equipment specialised for WT Installation
Purpose of the new notation is to identify the main function of the unit and to develop classification rules which cover this function
Specific DNV ”WTI” Rules developed – first release October 2010, covering self-elevating units (B+C).
© Det Norske Veritas AS. All rights reserved.
October 2013
Jacking system
Extended fatigue requirements to the jacking system because of many load cycles. (10 years operations x 100 moves per year)
Design and construction of jacking system should ensure the possibility for the vessel to go into a floating condition and escape from site.
It is a requirement to conduct an FMECAs (Failure Mode and Effect Criticality Assesment) with involvement of Class to highlight the critical issues with regard to jacking down and escape.
Specific Accidental Load criteria may be defined through the FMECA.
32
© Det Norske Veritas AS. All rights reserved.
October 2013
33
Requirements to the jacking and control system
DNV-OS-D202 AUTOMATION, SAFETY, AND TELECOMMUNICATION SYSTEMS
Ch.1 Sec.1 208 An essential system A system supporting equipment, which needs to be in continuous operation or continuous available for on demand operation for maintaining the unit's safety. (Example propulsion and steering)
Ch.1 Sec.1 209 An important system A system supporting functions in order to perform in accordance to class equirement
B 500 Repairable systems (R3)501 A system serving a function of category R3 shall be designed to provide restoration of the function within a repair time specified for R3 in case of system failures .
Guidance note:Restoring a function may involve a number of manual operations, including minor replacements or repair of equipment.
© Det Norske Veritas AS. All rights reserved.
October 2013
Hull Strength
Transit criteria
For the normal transit condition we advice the hull strength to be adequate for un-restricted operations – i.e. designed for a 20-year North Atlantic storm criterium.
This is in line with the +1A1 notation which is relevant as many vessels need to - Sail long distance from i.e. construction site in South East Asia to Europe. - Also the vessels may sail longer distances to operate in new geographical areas or the
voyage they travel for picking up equipment to the wind farm may be substantial.
34
© Det Norske Veritas AS. All rights reserved.
October 2013
Strength considerations
Deck strength
Large cargo weights require special strengthening of deck storage area.
Future increase in wind turbine weights should be accounted for.
Localized loads from cargo seafastening may apply.
Deck box often designed in consideration of moderate draught combined with large vessel width and long span between legs. Global bending and torsional stability of deck box to be documented.
35
© Det Norske Veritas AS. All rights reserved.
October 2013
Strength considerations due to Crane loads
For Crane Notation – crane must be certified by DNV.
Large crane loads must be accounted for in global analysis of vessel and combined with relevant environmental loading (waves, wind, current)
All relevant crane positions to be checked for.
Location of main crane around one leg will imply that this legs will see the highest utilization.
Interaction between crane, leg and jack house to be investigated and accounted for.
Insufficient stiffness of deck hull/jack house will imply that crane loads are supported/taken by the leg.
36
© Det Norske Veritas AS. All rights reserved.
October 2013
Design and construction of legs
Leg solutions vary substantially
37
Circular legs Truss legs Square legs
© Det Norske Veritas AS. All rights reserved.
October 2013
Leg design con’t
Vessels designed for restricted waters are also weight and strength optimized.
Fabrication tolerance requirements (as for ordinary jack-up legs)
High strength materials used in legs.
Welding qualification is important (procedures, testing etc).
Wear and tear from repeated jacking operations is important.
38
© Det Norske Veritas AS. All rights reserved.
October 2013
Spudcan design
39
• Spudcan design affects the leg design and also the design of the hull.• Larger spudcans requires larger recess in the hull but implies less
seabed penetration.• Solution becomes a compromise.
© Det Norske Veritas AS. All rights reserved.
October 2013
Statutory Compliance
SOLAS compliance needed for vessels operating between ports.
Large non-maritime crew requires additional SPS requirements to be fulfilled. This implies stronger requirements to stability and life saving.
MODU code requirements still valid for the elevated condition.
Flag state to decide level of compliance
DNV will assist in communication with flag state.
40
© Det Norske Veritas AS. All rights reserved.
October 2013
41
Bringing the unit into operation – focus of Class Support
Drivers : Flexibility and Zero downtime
In operation:- Vessel is continuously mobilized with full crew and service personnel onboard - Operations costs are running…..
Concerns raised by owners:- They do not want to be constrained by a prescriptive survey schedule.
In order for DNV to support our client’s success factor we have developed and implemented suitable survey procedures
that can be done “on location” and without interrupting planned operations.
In order for DNV to support our client’s success factor we have developed and implemented suitable survey procedures
that can be done “on location” and without interrupting planned operations.
The most important success factor for the MOU or WTI unit owners: “zero downtime”
The most important success factor for the MOU or WTI unit owners: “zero downtime”
© Det Norske Veritas AS. All rights reserved.
October 2013
42
Increased Client Focus
Dedicated rig-coordinator for each unit (Germany/Holland/Norway/UK)- Available - acts as a single point of contact - Takes lead in initiating, planning, executing and controlling surveys- Acts as a part of a wide network that benefits Owner and DNV- Able to decide and resolve issues efficiently- Manages approvals related to modifications and upgrades
Dedicated fleet responsible for the owner in the head office (located in Oslo)
Reduced interruption to the operation.
Renewal survey on location if necessary
Continuous survey scheme (Hull, Jacking System, Crane..) – no surprises'
Approved Service Suppliers (NDE, chain, radio surveys…)
Bottom surveys
© Det Norske Veritas AS. All rights reserved.
October 2013
43
Risk of Down time may be because of a too marginal design:
Down time or waiting time due to limitations in:- Elevated storm capacity- Jacking capacity- Sailing capacity- Deck payload capacity - Speed limitations- Vessel Stability- Capacity of crane
Robustness and design according to a well established design specification is a key to success.
Less may cost more….
© Det Norske Veritas AS. All rights reserved.
October 2013
44
Improved Availability and Reliability – Class SupportHow can Class contribute?
Design phase Early involvement in design phase – review of Design Basis Specific class notation considering operational requirements Assist on clarification of Flag and other essential design requirements
In-service phase Optimized In-service Inspection Program – included in class fee (IIP) Systemize knowledge and sharing Class integrating with the owners maintenance scheme Partnership with the owners in developing new inspection methods Alternative risk based approaches
© Det Norske Veritas AS. All rights reserved.
October 2013
45
Service
Thank You
Questions??
© Det Norske Veritas AS. All rights reserved.
October 2013
46
Service
Designs & Concepts
© Det Norske Veritas AS. All rights reserved.
October 2013
47
DNV Recent and Ongoing Projects
Fred Olsen Windcarrier – Brave
Tern & Bold Tern
MPI Adventure & Discovery
DDW Batam
2 units
1 unit
A2SEA Sea Installer
1 +1 unit
© Det Norske Veritas AS. All rights reserved.
October 2013
48
New projectsInwind – Stavanger
Yard selection in progress
Concept Approval
MPI - Holland
2 newbuilds at Cosco Nantong
Option for 2 more considered
Van Oord - Holland
Another NG-9000 unit
Quotation given to IHC Merwerde yard - Holland?
Züblin – Germany
1 newbuild
© Det Norske Veritas AS. All rights reserved.
October 2013
49
New designs
Houlder (Gaoh) – UKApproval in PrincipleDNV London
Ulstein Sea of Solutions - Holland
Approval in Principle
© Det Norske Veritas AS. All rights reserved.
October 2013
Existing Wind turbine installation units
50
Knud E. Hansen –
Hull length 161.2 m Hull width 42.00 m Hull depth 7.40 m Hull draft 6.20 m Leg length max. (incl. spud-can) 70.00 m
MPI Resolution
Hull length 130.5 m Hull width 38.0 m Hull depth 8.0 m
Leg length max. (incl. spud-can) 70.00 m
© Det Norske Veritas AS. All rights reserved.
October 2013
GustoMSC designs
51
NG-5300-HPE
Hull length 92.99 m Hull width 36.00 m Hull depth 7.40 m Hull draft 3.50 m Leg length max. (incl. spud-can) 71.00 m
Hull length 95.00 m Hull width 39.60 m Hull depth 8.00 m Hull draft 4.60 m Leg length max. (incl. spud-can) 73.00 m
NG-7500-HPE
Hull length 128.79 m Hull width 39.00 m Hull depth 9.00 m Hull draft 5.00 m Leg length max. (incl. spud-can) 74.10 m
NG-9000-HPE
© Det Norske Veritas AS. All rights reserved.
October 2013
52
© Det Norske Veritas AS. All rights reserved.
October 2013
53
Huisman SWATH
Approval in Principle to be undertaken by DNV
• Structural strength• Vessel motions• Stability
© Det Norske Veritas AS. All rights reserved.
October 2013
54
WTI R&D project in France
Independent verification of concept• Structural strength• Hydrodynamic analysis• Global motions• Vessel stability
Project delivery:”statement of feasibility”
© Det Norske Veritas AS. All rights reserved.
October 2013
55
Safeguarding life, property and the environment
www.dnv.com