QUARTERLY IR UPDATES - MHBmhb.com.my/wp-content/uploads/2018/10/MHB-Analyst...Job scope: Dry docking...
Transcript of QUARTERLY IR UPDATES - MHBmhb.com.my/wp-content/uploads/2018/10/MHB-Analyst...Job scope: Dry docking...
-
QUARTERLY IR UPDATES
3rd Quarter 2018 Financial Results & Updates
24th October 2018
-
Disclaimer
2
This Presentation is not intended to form the basis of any investment decision with respect to Malaysia Marine and
Heavy Engineering Holdings Berhad (MHB). Neither this presentation nor anything contained herein shall form the basis
of, or be relied upon in connection with, any contract or commitment whatsoever. No representation or warranty, express
or implied, is or will be made by MHB in relation to, and no responsibility or liability is or will be accepted by MHB as to
the accuracy and completeness of, the Information made available, and any liability therefore is expressly disclaimed.
This Presentation may contain “forward-looking statements”. Forward-looking statements by their nature involve known
and unknown risks, uncertainties and other factors that are in many cases beyond MHB’s control. Although MHB
believes that the expectations of its management as reflected by such forward-looking statements are reasonable based
on information currently available to it, no assurances can be given that such expectations will prove to have been
correct. Accordingly, you are cautioned not to place undue reliance on such forward-looking statements. In any event,
these statements speak only as of their dates, and MHB undertakes no obligation to update or revise any of them,
whether as a result of new information, future events or otherwise.
This Presentation and its contents are strictly confidential and must not be copied, reproduced, distributed, summarized,
disclosed referred or passed on to others at any time without the prior written consent of MHB. Except for the yard
facilities in the photographs, none of the vessels/structures belong to MHB.
-
Contents
• Business Highlights
• Projects
• Financials
• Shareholding Information
• Key Focus Areas
3
-
4
Key Highlights
FINANCIALS
• Revenue of RM701.1 mil
• Pre-tax loss of RM97.8 mil
Heavy Engineering Unit (HEU) milestones:
• Sail-away of five units of Dangote CALM Buoy
• Completion of centralised piping fabrication for RAPID
Package 5
• Completion of FSO Benchamas 2 turret
• Sail-away of Sepat-A jacket and topside
Marine Business Unit (MBU) milestones:
• Sail-away of FSO Benchamas 2
• Sail-away of FSO Bergading
• Completed repair & maintenance of 66 vessels
• Secured 82 new jobs
-
Contents
• Business Highlights
• Projects
• Financials
• Shareholding Information
• Key Focus Areas
5
-
6
Sailed away on 6th March 2018
Dangote CALM Buoy
-
7
Completed on 5th January 2018
RAPID Package 5 - Centralised Piping Fabrication (CPF)
-
8
Sailed away in April 2018
Sepat-A WHP Topside & Substructure
-
9
Sailed away on 9th April 2018
FSO Benchamas 2
-
10
Sailed away on 28th June 2018
FSO Bergading
-
11
Progress at 25.1% as at September 2018
Bokor Phase 3 Re-Development CPP
-
12
Progress at 91.9% as at September 2018
RAPID Package 5 – Refinery of Gas (ROG)
-
13
Progress at 98.0% as at September 2018
RAPID Package 3 Area 2
-
14
Progress at 81.9% as at September 2018
RAPID Package 14
-
15
Notable Marine Repair Projects delivered in Q3 2018 (1/2)
Vessel owner: Eaglestar Marine Holdings (L) Pte. Ltd
Deadweight: 76,229 tonnage
Job scope: Dry docking and repair
Delivery date: 11 July 2018
LNG Carrier Puteri Mutiara Satu LNG Carrier Seri Alam
Vessel owner: Eaglestar Marine Holdings (L) Pte. Ltd
Deadweight: 83,482 tonnage
Job scope: Dry docking and repair
Delivery date: 22 July 2018
-
16
Notable Marine Repair Projects delivered in Q3 2018 (2/2)
Vessel owner: Eaglestar Marine Holdings (L) Pte. Ltd
Deadweight: 89,953 tonnage
Job scope: Dry docking and repair
Delivery date: 20 August 2018
LNG Carrier Seri Bijaksana LPG Carrier Astomos Venus
Vessel owner: Idemitsu Tanker Co., Ltd.
Deadweight: 55,209 tonnage
Job scope: Dry docking and repair
Delivery date: 19 September 2018
-
17
Progress at 41.3% as at September 2018
Dry Dock 3 (DD3)
-
Contents
18
• Business Highlights
• Projects
• Financials
• Shareholding Information
• Key Focus Areas
-
• Revenue
• HEU – Higher revenue mainly due to commencement of
new order intake and from ongoing projects
• MBU – Increase in revenue from higher dry docking
activities in the current quarter
• Operating
• HEU – Lower operating loss mainly due to finalisation of
completed projects in the current quarter
• MBU – Lower operating loss mainly from recognition of
VO revenue offset with higher cost for conversion works
in the current quarter
• Pre-tax loss
• Lower loss in tandem with higher revenue from both HEU
and MBU
19
Financial Updates
Income Statement, Sequential Quarter
Income Statement (RM 'm) 3Q 2018 2Q 2018
Revenue
Heavy Engineering
Marine
289.8
178.4
111.4
223.0
137.7
85.3
Operating Profit/ (Loss)
Heavy Engineering
Marine
Others
(22.7)
(4.1)
(16.0)
(2.6)
(49.5)
(24.0)
(25.6)
0.1
Share of Profit/ (Loss)
of JV - (0.2)
Pretax Profit/ (Loss) (22.7) (49.7)
Taxation (0.1) (0.1)
Net Profit/ (Loss) (22.8) (49.8)
EPS/ (LPS) (1.4) sen (3.1) sen
Note : Due to rounding, numbers may not tally with the total
-
20
Financial Updates
Income Statement, Year-on-Year
• Revenue
• HEU – Lower revenue recognised on the back of fewer
ongoing projects in hand
• MBU – Lower revenue due to lesser dry docking repair
works secured
• Operating
• HEU – Lower operating loss due to finalisation of
completed projects
• MBU – Recorded an operating loss mainly due to
additional costs incurred on conversion works where
revenue recognition are still pending verification and
lower margins earned on dry docking works
• Share of results of JVs
• Lower loss following planned cessation of operations in a
JV
• Pre-tax loss
• Higher pre-tax loss due to operating loss incurred in MBU
Income Statement (RM 'm) 9M 2018 9M 2017
Revenue
Heavy Engineering
Marine
701.1
427.4
273.7
708.5
429.0
279.4
Operating Profit/ (Loss)
Heavy Engineering
Marine
Others
(97.0)
(40.6)
(48.8)
(7.7)
(9.3)
(48.3)
40.7
(1.7)
Share of Profit/ (Loss)
of JV (0.8) (6.0)
Pretax Profit/ (Loss) (97.8) (15.3)
Taxation (0.5) 0.6
Net Profit/ (Loss) (98.3) (14.7)
EPS/ (LPS) (6.1) sen (0.9) sen
Note : Segmental Revenue and Operating Profit is post inter-segment eliminations
: Due to rounding, numbers may not tally with the total
-
21
Financial Updates
Balance Sheet
• Total assets of RM3.1bil
• Higher Non-Current Assets – PPE, mainly due to
investment in DD3
• Lower Receivables & Payables – Ongoing projects are
still at early stages
• Lower Cash – Dividend payout and investment in DD3
• NTA per share of RM1.5
Note : Due to rounding, numbers may not tally with the total
Balance Sheet (RM 'm) Sep 2018 Dec 2017
Non-Current Assets 1,884.7 1,839.4
Inventories 5.1 2.4
Receivables 640.0 819.3
Cash 593.1 675.0
Others 20.3 20.9
Total Assets 3,143.3 3,356.9
Shareholders' Funds 2,434.3 2,579.7
Non-Controlling Interests 0.3 1.2
Payables 708.7 776.0
Total Equity & Liabilities 3,143.3 3,356.9
NTA per share RM1.5 RM1.6
-
22
Financial Updates
Backlog & Order Intake
2,559
356652
182
1,145
37Dec13 Dec14 Dec15 Dec16 Dec17 Sep18
420105
130
Order Intake RM million
2,556
1,5751,023
6291,273
932
Dec13 Dec14 Dec15 Dec16 Dec17 Sep18
Backlog RM million
New Order Intake
Call Out Contract
Backlog
Backlog
Note: New Order Intake excludes marine business
Marine Business UnitF12PFLNG Turret
CPP Bokor
Benchamas TurretBesar A
Rapid
CPOC
Others
September 2018
RM932 mil
-
Contents
23
• Business Highlights
• Projects
• Financials
• Shareholding Information
• Key Focus Areas
-
Foreign Investors 2.50%
Other Malaysian Shareholders
12.43%
EPF 1.54%
PNB & PNB Unit Trust
Funds 1.84%
Lembaga Tabung Haji
6.69%
Technip 8.50%
As of
30 Jun 2018
Foreign Investors 2.50%
Other Malaysian Shareholders
12.43%
EPF 1.54%
PNB & PNB Unit Trust
Funds 1.84%
Lembaga Tabung Haji
6.69%
Technip 8.50%
24
Corporate Updates
Shareholding Information
As of
30 Sep 2018
28-Sep-18
Share Price (RM)
21/09/2018
0.800.6225/07/2018
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1.40
1.60
1.80
2.00
29-Jun-18 29-Jul-18 29-Aug-18
-
Contents
25
• Business Highlights
• Projects
• Financials
• Shareholding Information
• Key Focus Areas
-
26
Key Focus Areas
• Tenders worth ~ RM6.0 billion have been submitted as of September 2018
• Strategy & Initiatives
• Continue pursuing existing business of Marine & Heavy Engineering, seizing available
Floaters Conversion opportunities and expanding marine capacity through additional dry dock
• Develop new business, namely Onshore Construction & Fabrication and expanding Oil & Gas
Services for onshore and offshore
• Execute Bid Cost Reduction exercise to achieve better cost competitiveness
• Implement productivity improvement initiative to achieve operational excellence
• Up-skill manpower through Capability Development programme
-
27