Quality Assurance Update for the EFCOG ISM & QA Working Group 2011 Spring Meeting
Quality Assurance Update for the EFCOG ISM & QA Working Group 2011 Spring Meeting Sonya Barnette...
-
Upload
baldwin-wood -
Category
Documents
-
view
214 -
download
0
Transcript of Quality Assurance Update for the EFCOG ISM & QA Working Group 2011 Spring Meeting Sonya Barnette...
![Page 1: Quality Assurance Update for the EFCOG ISM & QA Working Group 2011 Spring Meeting Sonya Barnette Office of Quality Assurance Policy and Assistance Office.](https://reader036.fdocuments.us/reader036/viewer/2022062519/5697bffc1a28abf838cc1436/html5/thumbnails/1.jpg)
Quality Assurance Update for theEFCOG ISM & QA Working Group
2011 Spring Meeting
Sonya BarnetteOffice of Quality Assurance Policy and Assistance
Office of Nuclear Safety, Quality Assurance and EnvironmentApril 26-28, 2011
![Page 2: Quality Assurance Update for the EFCOG ISM & QA Working Group 2011 Spring Meeting Sonya Barnette Office of Quality Assurance Policy and Assistance Office.](https://reader036.fdocuments.us/reader036/viewer/2022062519/5697bffc1a28abf838cc1436/html5/thumbnails/2.jpg)
DOE Quality Assurance Update Topics
• DOE Federal Quality Council (QC)• Results of 2009 Survey on Quality Assurance
(QA) Implementation• DOE O 414.1D and Associated Guide• Safety Software Quality Assurance • QA Exchange Newsletter
2
![Page 3: Quality Assurance Update for the EFCOG ISM & QA Working Group 2011 Spring Meeting Sonya Barnette Office of Quality Assurance Policy and Assistance Office.](https://reader036.fdocuments.us/reader036/viewer/2022062519/5697bffc1a28abf838cc1436/html5/thumbnails/3.jpg)
DOE Federal Quality Council
• DOE Federal QC members include federal representatives from HSS, EE, EM, FE, LM, MA, NA, NE, SC, BSO, ID, LASO, ORP, RL, SRO, SC-CH, IM, HC and SPRO
• The DOE Federal Quality Council 2010 Annual Report is in concurrence for issuance to DOE Field and HQ Offices
3
![Page 4: Quality Assurance Update for the EFCOG ISM & QA Working Group 2011 Spring Meeting Sonya Barnette Office of Quality Assurance Policy and Assistance Office.](https://reader036.fdocuments.us/reader036/viewer/2022062519/5697bffc1a28abf838cc1436/html5/thumbnails/4.jpg)
DOE Federal Quality Council
Current QC Task Planning Document (TPD) Teams: Commercial Grade Dedication QA Program Performance Metrics HQ QA Training ISM/QA Integration Template Suspect/Counterfeit Items (S/CI) Task Force
Plans of the Council include working more closely with EFCOG and piloting efforts for joint products
DOE Quality Council Websitehttp://www.hss.energy.gov/nuclearsafety/qa/council
4
![Page 5: Quality Assurance Update for the EFCOG ISM & QA Working Group 2011 Spring Meeting Sonya Barnette Office of Quality Assurance Policy and Assistance Office.](https://reader036.fdocuments.us/reader036/viewer/2022062519/5697bffc1a28abf838cc1436/html5/thumbnails/5.jpg)
Commercial Grade Dedication (CGD)
• Pilot on CGD started jointly with EFCOG• Office of Environmental Management (EM)
has developed a draft guide for CGD based on NQA-1 Subpart 2.14
5
![Page 6: Quality Assurance Update for the EFCOG ISM & QA Working Group 2011 Spring Meeting Sonya Barnette Office of Quality Assurance Policy and Assistance Office.](https://reader036.fdocuments.us/reader036/viewer/2022062519/5697bffc1a28abf838cc1436/html5/thumbnails/6.jpg)
Performance Metrics
• Conference calls with QC TPD members are being used to discuss path forward (Last call was in March 2011)
• Currently developing a strawman process for generically developing a performance metric
6
![Page 7: Quality Assurance Update for the EFCOG ISM & QA Working Group 2011 Spring Meeting Sonya Barnette Office of Quality Assurance Policy and Assistance Office.](https://reader036.fdocuments.us/reader036/viewer/2022062519/5697bffc1a28abf838cc1436/html5/thumbnails/7.jpg)
QA Training
• Original pilot held in August last year• Based on that pilot, the training was revised
and scenarios used in the exercise portion of were updated; additional scenarios have been written
• Follow up 3 hour pilot at Forrestal postponed until issuance of DOE O 414.1D
• TPD Team will solicit input and guidance from the NTC on the venue for final training module
7
![Page 8: Quality Assurance Update for the EFCOG ISM & QA Working Group 2011 Spring Meeting Sonya Barnette Office of Quality Assurance Policy and Assistance Office.](https://reader036.fdocuments.us/reader036/viewer/2022062519/5697bffc1a28abf838cc1436/html5/thumbnails/8.jpg)
ISM/QA Template
• Final comments are being incorporated by team lead
• Final product will require QC majority vote
• Template to be available by the end of FY 2011
8
![Page 9: Quality Assurance Update for the EFCOG ISM & QA Working Group 2011 Spring Meeting Sonya Barnette Office of Quality Assurance Policy and Assistance Office.](https://reader036.fdocuments.us/reader036/viewer/2022062519/5697bffc1a28abf838cc1436/html5/thumbnails/9.jpg)
S/CI Task Force
• A QC TPD is being drafted• In March 2011 the Executive Office of the
President formed interagency working group• An HS-23 QC member (Duli Agarwal) is
participating on working group• Contact for details on the Anti-Counterfeit
Working Group is [email protected]
9
![Page 10: Quality Assurance Update for the EFCOG ISM & QA Working Group 2011 Spring Meeting Sonya Barnette Office of Quality Assurance Policy and Assistance Office.](https://reader036.fdocuments.us/reader036/viewer/2022062519/5697bffc1a28abf838cc1436/html5/thumbnails/10.jpg)
Results of 2009 Survey
• Report on the 2009 Survey on QA Implementation in the Department of Energy was issued on December 7, 2009
• Twelve areas for improvement were identified in the report and are being addressed by the QC
http://www.hss.doe.gov/nuclearsafety/qa/2009_QA_Implementation_Survey_Report.pdf/
10
![Page 11: Quality Assurance Update for the EFCOG ISM & QA Working Group 2011 Spring Meeting Sonya Barnette Office of Quality Assurance Policy and Assistance Office.](https://reader036.fdocuments.us/reader036/viewer/2022062519/5697bffc1a28abf838cc1436/html5/thumbnails/11.jpg)
Examples of Areas for Improvement
• Ensure that all DOE offices have approved QAPs
• Ensure training of Federal and contractors staff to QAPs
• Ensure approved work processes are established
• Ensure safety software meets the expectations for its validation and use
• Verify that QA requirements have been appropriately flowed down to subcontractors
11
![Page 12: Quality Assurance Update for the EFCOG ISM & QA Working Group 2011 Spring Meeting Sonya Barnette Office of Quality Assurance Policy and Assistance Office.](https://reader036.fdocuments.us/reader036/viewer/2022062519/5697bffc1a28abf838cc1436/html5/thumbnails/12.jpg)
Management Assessment Assistance
• QC is working to develop management assessment assistance tools
• HS-23 will work with a team of QC members and interested parties to develop a path forward
12
![Page 13: Quality Assurance Update for the EFCOG ISM & QA Working Group 2011 Spring Meeting Sonya Barnette Office of Quality Assurance Policy and Assistance Office.](https://reader036.fdocuments.us/reader036/viewer/2022062519/5697bffc1a28abf838cc1436/html5/thumbnails/13.jpg)
DOE O 414.1D
• QA Order Revision team completed all actions• No unresolved comments from DNFSB• Non-concurrence from some DRB members• Non-concurring offices are drafting position
papers (i.e., considering an integrated management system)
• Deputy Secretary will make final decision
13
![Page 14: Quality Assurance Update for the EFCOG ISM & QA Working Group 2011 Spring Meeting Sonya Barnette Office of Quality Assurance Policy and Assistance Office.](https://reader036.fdocuments.us/reader036/viewer/2022062519/5697bffc1a28abf838cc1436/html5/thumbnails/14.jpg)
DOE G 414.1-2B
• New title - DOE G 414.1-2B, Quality Assurance Program Guide
• Entered REVCOM on March 31, 2011
• Comments due by May 16, 2011
• Issue before September 30, 2011
14
![Page 15: Quality Assurance Update for the EFCOG ISM & QA Working Group 2011 Spring Meeting Sonya Barnette Office of Quality Assurance Policy and Assistance Office.](https://reader036.fdocuments.us/reader036/viewer/2022062519/5697bffc1a28abf838cc1436/html5/thumbnails/15.jpg)
Safety Software Quality Assurance
Safety Software Communication Forum (SSCF)• Developed as an electronic medium to disseminate
safety software information and enhance user interaction– Central Registry will contain a link to the SSCF
http://www.hss.doe.gov/nuclearsafety/qa/sqa/central_registry.htm
• Provides an access-controlled platform that facilitates interaction among safety software users
• Serves as a centralized source of safety analysis and safety design code usage information
15
![Page 16: Quality Assurance Update for the EFCOG ISM & QA Working Group 2011 Spring Meeting Sonya Barnette Office of Quality Assurance Policy and Assistance Office.](https://reader036.fdocuments.us/reader036/viewer/2022062519/5697bffc1a28abf838cc1436/html5/thumbnails/16.jpg)
Safety Software Quality Assurance
Safety Software Communication Forum (contd.)• Serves as a forum for communicating on specific
codes– Problems and errors encountered– Lessons Learned – Efficient usage and workarounds
• Provides a vehicle to disseminate code information to users
• Provides links to code developer / owner websites• Contact information– Subir Sen (301) 903-6571 or [email protected]
16
![Page 17: Quality Assurance Update for the EFCOG ISM & QA Working Group 2011 Spring Meeting Sonya Barnette Office of Quality Assurance Policy and Assistance Office.](https://reader036.fdocuments.us/reader036/viewer/2022062519/5697bffc1a28abf838cc1436/html5/thumbnails/17.jpg)
Safety Software Quality Assurance
• Safety Software Expert Working Group (SSEWG) Activities:
• Toolbox code evaluations in progress• HotSpot V2.07.01 added to Central Registry• GENII V2.10 evaluation in progress
• Evaluation templates developed• Configuration Management Plan• V&V Test Plan
• DOE-STD-1172-2011 SQA FAQ Standard issued• Functional Area Qualification (FAQ) Standard for Federal
Software Quality Assurance Personnel
17
![Page 18: Quality Assurance Update for the EFCOG ISM & QA Working Group 2011 Spring Meeting Sonya Barnette Office of Quality Assurance Policy and Assistance Office.](https://reader036.fdocuments.us/reader036/viewer/2022062519/5697bffc1a28abf838cc1436/html5/thumbnails/18.jpg)
QA Exchange Newsletter
• Keeps QA community informed • Articles submitted by you are welcome• To view the latest newsletter go to
http://www.hss.doe.gov/nuclearsafety/qa/newsletters/QualityAssuranceExchange_March_2011.pdf
• HS-23 contact for the newsletter is Debbie Rosano at [email protected]
18
![Page 19: Quality Assurance Update for the EFCOG ISM & QA Working Group 2011 Spring Meeting Sonya Barnette Office of Quality Assurance Policy and Assistance Office.](https://reader036.fdocuments.us/reader036/viewer/2022062519/5697bffc1a28abf838cc1436/html5/thumbnails/19.jpg)
In Conclusion
• The DOE Federal QC is continuing to work to strengthen its partnership with EFCOG
• The QC expects to pilot joint tasks with EFCOG• 2009 Survey on QA Implementation found areas for
improvement in QA programs• DOE O 414.1D is in the concurrence process for
issuance• SSCF is nearing startup
19