Public Involvement Meeting June 11, 2014. Introduce the project Provide history and current status...

12
WIS 29 Proposed Service Road Public Involvement Meeting June 11, 2014

Transcript of Public Involvement Meeting June 11, 2014. Introduce the project Provide history and current status...

WIS 29 Proposed Service Road

Public Involvement MeetingJune 11, 2014

Introduce the project Provide history and current status of the project Explain the benefits of the project Review service road alternatives Present the upcoming project schedule Discuss opportunities for public input

Overview of presentation

2

Project Introduction WIS 29 is a primary route

with large traffic volumes The purpose of the project

is to correct geometric deficiencies associated with accesses to WIS 29

The project need is to provide reasonable access to WIS 107 and to WIS 29

3

E. 13th Ln

Big

Rib

Riv

er

E. 15th St Highland Dr

Cattail Ave

152n

d A

ve

Maratech AveWeisenberger Rd

Krautkramer Rd

NORTH

The WIS 107 interchange was originally constructed in 1992; with an asphalt overlay placed in 2011.

Improvements to WIS 29, east of WIS 107, were completed in 2013.

The proposed service road is an outcome of the ongoing WIS 29 freeway conversion study.

History

4

During the past eight months: initial data collection.

Met with local officials from the surrounding communities.

Next, we will gather input on the alternatives, and prepare preliminary environmental documentation.

Current status

5

Removal of access on WIS 29, near the WIS 107 interchange ramps, will help reduce an emerging safety concern.

Benefits

6

1,800 feet

900 feet

NORTHE. 13th Lane

Acc

ess

Traffic Volumes

7

WIS 29 Service RoadExisting: 80 vehicles per dayForecasted (2036): 2000 per day

WIS 107Existing: 2800 vehicles per dayForecasted (2036): 4100 per day

WIS 29Existing: 16500 vehicles per dayForecasted (2036): 21100 per day

WIS 29Existing: 19100 vehicles per dayForecasted (2036): 24200 per day

E. 13th Ln

Big

Rib

Riv

er

E. 15th St Highland Dr

Cattail Ave

152n

d A

ve

Maratech AveWeisenberger Rd

Krautkramer Rd

NORTH

Proposed Typical Section

8

WIS 29 Service Road Alternatives

9

Obtain public input Review the displays Ask questions Provide comments

Continue design process Review public and agency comments Prepare draft environmental document Select preferred alternative

More public involvement Second public involvement meeting - late 2014 Right of way acquisition - 2015 and 2016 Construction - 2017

Next steps

10

11

Any Questions?

Jed Peters, P.E. Brian Andreas, P.E.

WisDOT Project Manager Strand Associates, Inc.

715-365-5731 608-251-4843

[email protected] [email protected]

www.dot.wisconsin.gov

Contacts and resources

12