Public Disclosure Authorized - World Bankdocuments.worldbank.org/curated/en/...(ii) 11 km power...
Transcript of Public Disclosure Authorized - World Bankdocuments.worldbank.org/curated/en/...(ii) 11 km power...
1
Siddhirganj Power Project, Credit No. 4508-BD
Implementation Review Mission: September 28 to October 2, 2014
Aide Memoire
1. An implementation review mission1 of Siddhirganj Power Project was carried out during
September 28 to October 22, 2014. The mission met with the officials of Ministry of Power, Energy and
Mineral Resources, External Resources Division of the Ministry of Finance, Power Grid Company of
Bangladesh (PGCB) Limited, Energy Generation Company of Bangladesh (EGCB) Limited, and Gas
Transmission Company Limited (GTCL). Key officials met are listed in Annex-1. This aide memoire
was discussed at a wrap-up meeting chaired by Mr. Monowar Islam, Secretary Power Division,
Ministry of Power, Energy and Mineral Resources on October 19, 2014. At that time it was decided to
classify this aide-memoire as a public document under the Bank’s Access to Information policy.
2. Mission Objectives
The objectives of the mission were to (i) review the implementation of the project specially the 335
MW combined cycle power plant (CCPP) towards achieving the project development objective (PDO);
(ii) review project issues; and (iii) agree on the next steps. Specifically, the mission would review
progress of the construction of the 335 MW CCPP, undertake site visit, track key dates of construction
schedule and assess likelihood of achieving the commercial operations date (COD) of the Simple Cycle
power plant on time. The mission would further review whether the project ratings should be
considered for upgrading on current implementation progress and an extension of project deadline to
enable PDO indicators to be monitored. The mission would further review the borrower’s additional
financing plan in moving forward this high priority power generation project.
3. Key Project Data and Ratings
Project Data Project Performance Ratings
Board Approval Date: 10/30/2008 Summary Ratings: At MTR Now
Effectiveness Date: 03/31/2009 Achievement of Project
Development Objectives (PDO)
MU MU
Original Closing Date: 03/31/2016
Revised Closing Date:
MTR Date
N/A
02/12/2014
Implementation Progress (IP) MU MS
Original Credit Amount:
SDR 222.6 million
($350 million)
Other Ratings:
Financial Management
MS
MS
Amount Disbursed: SDR 116.497 million
($173.085 million)
Project Management S S
Disbursement 52.33% Procurement S S
Performance Trend Deteriorating Improving
Notes: HS= Highly Satisfactory; S=Satisfactory; MS=Moderately Satisfactory; U=Unsatisfactory; MU=Moderately Unsatisfactory;
HU=Highly Unsatisfactory; NA= Not Applicable
4. Achievement of Project Development Objective (PDO)
Increase supply of electricity to Bangladesh grid network: Since May 2014, there is an improved
progress of the construction of the 335 MW CCPP and an overall steady progress of the project. The
commercial operations date (COD scheduled for 13 February 2016) for the CCPP can be achieved
within the project deadline (March 31, 2016), with the current trend of continued construction progress.
1 The mission consisted of Messrs. Md. Iqbal (Senior Energy Specialist and Task Team Leader), Tanvir Hossain (Senior
Procurement Specialist), Yusuf Salauddin (STC, Technical Expert), Bazlul Kadir (STC, Procurement and Contract
Management), Mohammed Atikuzzaman (Financial Management Specialist), Shakil Ahmed Ferdausi (Senior Environment
Specialist), Sabah Moyeen (Social Development Specialist), Md. Faijul Islam (Information Analyst) and Md. Tafazzal Hossain
(Program Assistant). 2 Key executives of the MPEMR were not available to meet. So, the mission was extended a few days after the Eid vacation.
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
2
However, the PDO can’t be achieved as the targeted energy (2.49 billion kWh per annum) can’t be
delivered and monitored within the project deadline. The Project performance in terms of the PDO
level result indicators is as follows (details given at Annex-2).
5. (a) PDO Indicator: Not met
2.49 billion kWh additional electricity delivered to grid (in peak and off-peak period): Not
met. No energy generated yet as the CCPP is still being built.
(b) Intermediate Indicators: Partially met.
(i) 335 MW conventional power generation capacity, constructed under the project- Not
yet built; presently under construction and 50% completed.
(ii) 11 km power transmission lines constructed under the project: Met. 11 km, 230 kV
transmission line and two 600 MVA substations built and under load test.
(iii) 60 km gas supply line constructed under the project: Partially met. 85% of the contract
completed; pre-commissioning of pipeline completed, upstream gas will flow in end-October
2014.
(iv) 218.6 billion MJ projected lifetime fuel saved: Not met. No fuel saved as the CCPP is
still under construction and can’t burn fuel.
(v) O&M contracts budgeted and implemented: Partially met. The O&M for 2x120 MW
peaking units of EGCB is contracted and operating the power plants. The second O&M for the
335 MW CCPP is under procurement. This O&M is expected to be onboard in March/April
2015.
(vi) ERP functional and generating reports: Not met. Two ERPs designed and selection of
vendors is under process.
Based on the above results, there are notable improvements of performance against the Intermediate
Indicators. Therefore, the IP rating has been upgraded to moderately satisfactory (MS). However, the
project is not on track to deliver the PDO by end of the project closing date (March 31, 2016), therefore
the PDO rating will remain moderately unsatisfactory (MU).
6. Implementation Review
The mission reviewed with the Government and the IAs (EGCB, GTCL and PGCB) the present
implementation performance of the project and concluded that steady progress is being made in the
construction of the 335 MW CCPP, the installation of the two small infrastructures (230 kV power
evacuation system and 60 km 30 inch diameter gas transmission pipeline) and the implementation of
the Technical Assistance component. Presently, 90% of the IDA funds have been committed; the rest
($28.50 million) covers outstanding institutional development support that is under procurement. The
project has achieved 63% overall progress of physical infrastructure and the TA is providing steady
institutional development support to the IAs. They are acquiring a wide range of utility improvement
capabilities through this. The mission concluded that an extension of the project closing date by at-least
one year would be required to be able to monitor and measure whether the integrated gas-to-power
project would deliver the targeted 2.49 billion kWh per annum of energy to the grid (and thus achieve
the PDO). However, additional progress (see Annex 3) would be needed before such an extension could
be considered.
7. Progress of Physical Infrastructure
Physical and financial progress of the main project infrastructure works are given below:
3
Components: At MTR
Physical
Progress
At MTR
Financial
Progress
Current
Physical
Progress
Current
Financial
Progress
(a) 335 MW CCPP 30% 19.7% 50% 59%
(b) 230 kV Power Evacuation System 98% 84% 100% 95%
(c) 60 km Gas Transmission Pipeline 75% 60% 85% 65%
Overall Progress 46% 34.5% 63% 52.3%
The mission noted the above impressive progress and recognized that these are results of a few positive
steps the Government and EGCB took during and after the mid-term review (MTR) of the project in
January 20143. The mission was informed that since then, Isolux has been responding to the contractual
obligations, expanding volume of construction/erection activities and mobilizing increased resources to
meet the construction schedule. An improved project monitoring, especially on the construction of
CCPP, is in place. Isolux has been submitting informative monthly progress reports elaborating on all
aspects of the EPC; Fichtner has started to forward monthly Owner’s Engineer’s report providing
professional review on various project issues; and EGCB is holding monthly PIC (project
implementation committee) meetings with all stakeholders and providing issue-wise updates and or
decisions. The Power Division is holding PSC (project steering committee, chaired by Power Secretary)
meetings periodically to review and resolve critical issues of the project.
The mission paid a visit to the CCPP construction site and observed an accelerated rate of construction
and erection works. They were pleased to note an increasing activities being performed at the site and
that several construction/heavy erection activities were ongoing at the same time. The gas turbine and
gas turbine generator have been placed onto the GT pedestal and they were in the process of
assembling. This is a major milestone of the CCPP construction works. The storage needs of the CCPP
have exceeded the available storage capacity impeding progress of the erection works. However, Isolux
has been found coordinating the various activities efficiently and mobilizing various resources
effectively to catch up the schedule.
The other two small infrastructure components of the project have also made steady progress; PGCB’s
power evacuation system is 100% complete and is on load test at 132 kV since several months. GTCL
has so far completed 85% of the gas line contract, completed the hydro test and waiting for nitrogen
supply to neutralize the pipe prior to the Gas-In. The Upstream gas is expected to be available in the
Pipeline around October 31. GTCL confirmed that they target to provide metered and regulated gas
from the Siddhirganj gas RMS to the CCPP in March 2015. This coincides with the commissioning gas
flow schedule of the CCPP. The mission noted that Isolux has started some preparatory works to
connect the Siddgirganj RMS.
The mission informed that a few critical activities identified in July 2014 as benchmarks for upgrading
of the project rating have been met (for example, monthly actual construction progress rating of CCPP
(5%) crossed the monthly average of 3.3%; soil consolidation works completed; more than 90% of
piling works completed; more than 30% of concreting completed; GT and GTG have been placed onto
the GT pedestal and are in process of assembling etc.). Consequently the IP rating has been upgraded
from MU to MS (see para 5). The mission is of the opinion that the project implementation is back on
track and the current implementation performance trend is expected to continue.
3 In the MTR, the Government took the right message that unless the CCPP (the central piece of the project and the largest
contract) is back on track there is no point to move this large infrastructure project. They directed EGCB to accelerate the
project implementation and work seriously to achieve the PDO. The three IAs agreed to the CCPP schedule as the baseline for
the integrated gas-to-power project completion and the accomplishment of the PDO. Isolux (EPC for the CCPP) at that time
agreed to a revised construction schedule for the CCPP and restart the construction works in full swing. Simultaneously,
Fichtner (Owner’s Engineer for the CCPP) agreed to mobilize increased resources to the construction site and committed to
provide faster professional review of the contractual issues.
4
8. Progress of Institutional Components
The institutional development supports (Part: D Technical Assistance) have been making good
progress. Three Owner’s Engineers are providing technical, supervision and contract/project
management advice to the IAs and NTPC is providing O&M services to EGCB’s 2x120 MW
Siddhirganj peaking units (37% of contracted man-months achieved). Procurement of the rest three
large contracts (an ERP for each of EGCB and GTCL; and an O&M for 335 MW CCPP for EGCB) is
progressing well. These consultants are scheduled to be onboard by March/April 2015, well in time to
interface with commissioning of the Simple Cycle Power plant.
The other institutional progress includes the establishment of an Environment and Social Units (ESU)
in the IAs, to build the relevant capacity. EGCB Board has approved an organogram for EGCB’s ESU,
which includes 4 positions for Environmental, Health and Safety (EHS) Unit with 1 Deputy General
Manager, 1 Manager, 1 Deputy Manager and 1 Assistant Manager. The organogram is waiting for final
approval of Power Division. The mission recommends revisiting the organogram to keep provision of
Laboratory Staff under the EHS for smooth monitoring of the environmental parameters agreed in the
Environmental Management Plan (EMP) under the Environment Impact Assessment (EIA). On the
other hand, PGCB delayed in finalizing the organogram for ESU. This has been prepared and approved
by the PGCB Board in the mission. The organogram includes 5 positions, 1 Deputy General Manager
(Environment and Social) to lead the Unit, 1 Manager (Environment), 1 Manager (Social/Resettlement)
and two Deputy Managers, one for each discipline. PGCB agreed to complete the selection of ESU
positions by January 31, 2015.
With the help of the TA, all the agencies have made good progress in acquiring a range of institutional
capabilities including in contract design and procurement, environmental and social impact assessment
and management action plans, financial management, construction supervision and project
management, and enterprise resource planning and management. The mission informed the IAs about
the scope of training, support for analytical work, and creation of social facilities (EGCB only) included
in the project restructuring in April 2014 and encouraged them to utilize these resources. The mission
elaborated that the Training will finance reasonable costs of training, seminars, workshops, conferences
and study tours conducted locally or abroad, and will cover fees, local/international travel, lodging and
subsistence for both trainers and trainees, rental of facilities, and training materials.
9. Project Issues
The mission looked at the critical path of the integrated gas-to-power project construction schedule and
suggested EGCB to adhere to this rigorously to achieve the Simple Cycle Commissioning and Simple
Cycle PAC (provisional acceptance certificate), scheduled for May 30, 2015. All the Steam Cycle
construction works should go in parallel and as per schedule.
CCPP Construction Schedule and Recovery Strategy: Isolux has been following the revised
construction schedule4 discussed in the 3
rd Project Steering Committee (PSC) meeting on February 12,
2014. The mission noted 47 day delay in this schedule. The Power Secretary confirmed that there is no
scope for rescheduling and any delay should be recorded. In the wrap-up meeting he categorically
requested Isolux to recover the lost days because there will be an increased need for electricity in the
irrigation season in April 2015. The mission suggested that Isolux should not slide or revise the total
schedule every month rather show the exact status of each activity. Fichtner in July opined that the
revised construction schedule is optimistic and has limited floats for time recovery. However, the
mission advised that based on an improved construction management (based on an effective
coordination (both within utility and inter-utility) and continued increased construction trend) the lost
days could be recovered. Fichtner should proactively track the lost days on weekly basis and guide
Isolux and EGCB accordingly.
4 Simple Cycle COD for May 30, 2015 and Combined Cycle COD for February 13, 2016.
5
Simple Cycle Installation and Commissioning Plan: The purpose of this Plan is to regularly track the
scheduled activities; identify activities behind schedule; and take timely steps or corrective measures to
accelerate the work for achieving the SC PAC. The mission explained to EGCB, Fichtner and Isolux
the crucial need of the Plan and that without the Plan, the CCPP construction may face an unanticipated
deficiency that can jeopardize the commissioning of the SC as well the PAC. The mission emphasized
that the Plan does not only track the scheduled activities or milestones, but it incorporates factors that
can affect construction of the CCPP and Fichtner’s views on how to address them. The methodology for
preparation of the Plan includes Fichtner’s professional review of the following factors and
recommendations to catch up the schedule and achieve the quality:
i) Present construction trend, its state of affairs, and EPC’s preparedness to achieve the
schedule and quality,
ii) EPC materials on site and shipping schedule,
iii) Availability of construction tools, tackles/equipment; and scheduled deployment to site,
iv) Site productivity,
v) Isolux skills deployment schedule,
vi) Payment schedule vs. progress payments, and
vii) A separate list of activities to achieve PAC for SC.
The Task Team reviewed a draft Plan with Fichtner and EGCB and they have been advised to provide a
final one in terms of the above para, with associated layout drawing showing equipment boundary and
data, for Bank’s review. The Plan must flag also the status of a few critical activities during the next
three months (see below). These should be tracked to find out beforehand if any one of them is or likely
to be behind schedule and take appropriate measures to accelerate:
Circulating Water and Cooling Water Erection works to start from November 2014
Fuel Gas Connection with Siddhirganj Gas RMS to start in October 2014
Fire Fighting System and Clarifier Water Tank Erection to start in November 2014
GT Generator and other scheduled Electrical works to start in November 2014
GT Commissioning to start on February 2, 2015
The mission further urged EGCB and Fichtner to specifically track the following major Milestones to
achieve the SC PAC for May 30, 2015:
Gas Turbine and Auxiliaries Mechanical Completion February 01,2015
First Fire Fuel Gas GT March 23, 2015
GT Commissioning to start February 2, 2015
First Syncronisation of GTG March 31, 2015
Provisional Acceptance Test Simple Cycle May 30, 2015
The mission further suggested that the following technical issues need to be reviewed within Isolux,
Fichtner and EGCB and confirmed by November 15, 2014:
EGCB and Isolux to finalise inclusion of automatic condenser cleaning equipment;
Waste water composition limit to be determined as per the standards of DOE and World Bank’s
relevant Guidelines; and
Water Treatment Plant design to consider quality of DM water and quality river water.
Electrical Substation Availability and Connection with CCPP: The Siddhirganj Substation is
available, and EGCB and PGCB should coordinate to achieve electrical connectivity with the CCPP for
power evacuation. Fichtner and Isolux should work out short-term plan to achieve this and inform
PGCB about the plan, including access to substation and shutdown/isolation of bay.
Gas Supply Availability and Connection with Siddhirganj Gas RMS: EGCB/Fichtner needs to
coordinate the gas supply issue with GTCL and Titas Gas, including RMS connectivity with the CCPP.
6
The mission noted considerable delay and inaction in executing the GSA. The mission urged the Power
Secretary to intervene and ensure that Titas Gas and EGCB sign the GSA expeditiously. The Power
Secretary advised EGCB to sit with Titas and GTCL to finalize the issue. The EMR Secretary also
agreed to look into the issue. EGCB informed in the wrap up meeting that they have sent a draft GSA
with revision of clauses (regarding LD clauses) for Bank review. The mission required that the GSA
should be executed no later than December 31, 2014.
O&M Responsibility of Haripur and Siddhirganj Gas RMSs: As per project arrangement, it was
agreed that GTCL would construct the two Gas RMSs (at Haripur and Siddhirganj) with project
funding, and upon completion, would hand over the RMSs to Titas Gas for O&M, as Titas Gas is the
authorized and licensed distributor of natural gas within its franchise territory. GTCL has been
communicating with Titas Gas on this since August 2014. However, Titas Gas has declined to take over
the two RMSs and carry out the O&M. The mission raised the issue with the Energy Secretary and he
agreed that Titas Gas will have to take over the assets as per its mandate and carry out the O&M. The
mission asked Titas Gas to be in touch with GTCL in this regard.
10. Procurement
The mission reviewed the progress of ongoing procurement of three large contracts with EGCB and
GTCL. The bid submission of EGCB’s ERP and O&M are in mid and late October 2014 respectively.
The ERP pre-bid minutes cleared by Bank, have been circulated. GTCL’s ERP bid document has been
revised based on Bank’s review. This is under preparation of an RPM case. The EOI notice is to be
floated in late-October. Implementation of two small contracts on EGCB’s ERP infrastructures
continues. The mission requested both GTCL and EGCB to forward an updated procurement plan for
Bank’s review.
11. Financial Management (FM)
There is an overall improvement in the project FM. However, delays in submission of the FM reports
have remained in some cases. The mission raised non-compliance of a few FM covenants (accounts
receivables for EGCB, and 10-year business plan for all three IAs). The mission suggested PGCB to
strengthen its institutional capacity and fixed asset management. Key actions agreed with PGCB are:
Appointment of Director Finance of PGCB by December 2014;
Appointment of financial consultant (IC) to prepare the 10-year business plan as per the TOR,
by November 30, 2014;
Preparation of TOR for consultant for Fixed Asset valuation, tracking, and audit trail and
submission of a cost estimate of the work upon discussion with an internationally affiliated
firm, by October 31, 2014; and
Submission of a Training proposal on financial modelling work (with skill gap analysis,
training needs, and business benefits) by October 31, 2014.
The mission also noted similar deficiencies in EGCB and GTCL, discussed the need for the 10-year
business plan and urged both to appoint a financial consultant (IC) by November 30, 2014. The mission
conveyed that the costs of the capacity building initiatives in FM for the three IAs have been included
in Part D 6: Technical Assistance, of the restructured project.
12. Disbursement
The current disbursement of the project is $ 173.09 million (52.3%). $ 19.9 million has been disbursed
in FY15 Q1 which is 36.85% of the FY 15 disbursement projection ($ 54 million). The mission noted
that a few contracts (2 O&Ms; 2 ERPs, 1 OE, CCPP EPC) have scheduled payment dates (and end
contract dates) after the IDA Credit closing date. Payments due after the closing date (March 31, 2016)
amount to $46 million, indicating that the most that can be disbursed from the Credit if the closing date
remains unchanged is 85% of Credit proceeds (or about $ 304 million).
7
13. Governance Reporting and GAAP
Two IAs (EGCB and PGCB) have submitted the annual governance reporting for the current year on
time. Only GTCL’s reporting is outstanding, which means that the entity is out of compliance with the
Credit legal covenant. The mission urged GTCL to submit it by November 15, 2014. There is no
pending governance reporting of past years. The mission was informed that the IAs were monitoring
the GAAP in procurement and contract execution stages and no alerts or early warnings have been
identified or reported as per Action Plan. The Action Plan however needs an updating as there should
be increased focus on contracts implementation as the current risks of the project arise through contract
execution mainly.
14. Environment and Social Action Plans
Environmental Safeguards
EGCB: The mission reviewed the overall environmental management progress of the power plant
construction. The mission was informed that the EPC contractor has set up a HSE section and has a
full-time International HSE Manager, two Safety Officers and other staff. They have established a
clinic in June 01, 2014 to provide first-aid facility. According to the record up to September 30, 2014,
70 persons including officers, staff and workers have taken first-aid owing to minor injuries and no
major injuries have been recorded. Although the Health and Safety issues have been dealt carefully in
the project, the environmental monitoring has not been recently carried out properly. It has been agreed
and that a tripartite meeting among the EGCB, Owners’ Engineer (Consultant) and EPC contractor was
held during mission to review and finalize the Environmental Action Plan. Actions must be taken for air
quality, water quality and noise monitoring mitigation measures (if the values are above the national
level). The final Environmental Action Plan will be submitted to the World Bank by November 07,
2014. PGCB: The mission requested PGCB to deliver the final environment and social compliance
report of PGCB’s component by November 7, 2014.
GTCL: The mission was informed that the contractor has made reasonable progress on environment
issues through mobilizing environmental teams and periodic monitoring of standard parameters of air,
noise, soil and water etc. at Bangladesh University Engineering and Technology (BUET) laboratory. It
was also informed that at-least 300 trees at different locations of the RoW and RMSs sites will be
planted. It has been agreed that an environmental compliance report will be submitted with analysis of
all monitoring data within one month of the completion of the physical work.
Social Safeguards
EGCB: Since the project activities are well within the power plant compound and there is no
displacement or resettlement related activities or impacts on tribal/indigenous people, neither OP 4.12
nor OP 4.10 has been triggered for the EGCB component. However, keeping the development agenda
in mind the project has initiated a process of identifying specific activities to enhance social benefits
within the power plant. Preliminary discussions with EGCB has led to a focus on improving the school
currently existing within the Siddhirganj compound; not only does the school provide services to the
residents and workers within the plant, but people from surrounding areas also send their children to the
school as it is the only one in the area. The school would benefit from infrastructure improvement and
the addition of a library and computer center. An auditorium could also be added which would help the
schools recreational activities and also be a source of income (be renting out) for maintaining and
improving the premises beyond the project period. EGCB will prepare a preliminary cost estimate of
the proposed social activities for review by the social specialist for finalization. PGCB: The RAP under
this component has been fully implemented; all compensations have been paid and this has been
confirmed in the field by the Bank.
GTCL: The RAP for GTCL has been implemented approximately 85% across the three districts on
average. GTCL has appointed an NGO for the purposes of RAP implementation and for regular
reporting on implementation progress to the Bank. The reports have been received timely and are
satisfactory. The Pipeline works has been completed after payment of due compensation as per RAP.
8
Construction of the three gas metering stations (RMSs) is ongoing but all resettlement activities related
to these have been completed. According to the reports, the gap in implementation is attributable to
absence of entitled people; their reluctance to travel to the District Commissioner’s office to collect the
compensations; and mismatch in titles and/or dispute within them. As GTCL and the NGO have
demonstrated sufficient efforts in implementing the RAP, including repeated interactions with the PAPs
and the relevant DC’s offices, it was agreed that the remaining money for resettlement activities will be
available up to December 2014 in a designated account.
15. Additional Financing (AF)
The mission met with ERD, updated them about the accelerated progress of CCPP and the overall
steady progress of the project. The mission discussed with ERD the additional financing of the project
and requirements to process the AF. This includes: i) an enhanced anti-corruption and fiduciary risk
mitigation commitment of Government on the EPC contract for CCPP; ii) a cumulative environment
impact assessment (CEIA) for greater Siddhirganj power hub; and iii) a satisfactory project rating. The
mission noted that Power Cell has undertaken the CEIA work, financed under the TA of RERED-II
project. Power Cell updated that they have received 26 EOIs and are finalizing a short-list. The mission
asked Power Cell to expedite the procurement, to appoint the consultants by December 31, 2014 and to
make the CEIA report available no later than March 31, 2015. ERD recognized that the project will
need an extension of the closing date for the PDO to be monitored within the project life time and to
allow some contracts to be completed. To enable the mission to recommend an extension of the closing
date, some benchmark actions were agreed that the implementing agencies would complete by the end
of December 2014 (see Annex 3). ERD confirmed that they would forward the AF-proposal addressing
the Bank’s requirements by November 15, 2014.
16. Next Steps
a) Submission of Simple Cycle Installation and Commission plan to Bank by November 7, 2014.
b) Soil Consolidation Report of Isolux, certified by Fichtner and endorsed by EGCB, for Bank’s
review by October 31, 2014.
c) Titas Gas to sign the Gas Supply Agreement with EGCB, by December 31, 2014.
d) O&M Responsibility of Gas RMSs: Titas Gas to take over assets and O&M responsibility of both
Siddhirganj and Haripur RMSs, upon commissioning by GTCL, by March 31, 2015.
e) CEIA Consultants for greater Siddhirganj power hub to be onboard by December 31, 2014; the
CEIA report to be available by March 31, 2015.
f) ERD to forward to Bank its AF proposal by November 15, 2014.
g) Appointment of Executive Director (Finance) of PGCB by December 31, 2014.
h) PGCB to complete selection of ESU positions by January 31, 2015.
i) GTCL to submit to Bank annual governance reporting for the current year by November 15, 2014.
j) EGCB to comply with the covenant on accounts receivables not to exceed 3 months of billing, by
March 2015. The three IAs should comply with the covenant on preparing a 10- year business
plan by April 2015.
17. Next Mission
The next mission is scheduled for late-December 2014/early January 2015, to review progress in
meeting the Next Steps and to monitor completion of the Benchmarks agreed for recommending an
extension of the closing date. The mission noted that the benchmarks are feasible to be delivered by
December 2014.
9
Annex 1
Siddhirganj Power Project
Implementation Review Mission
September 28 – October 2, 2014
List of Persons Met Ministry of Power, Energy and Mineral Resources Mr. Md. Abubakar Siddique, Secretary, EMR Division Mr. Monowar Islam, ndc, Secretary, Power Division Economic Relations Division Mr. Kazi Shofiqul Azam, Additional Secretary, ERD Mr. Md. Anwar Hossain, Deputy Secretary, ERD Power Cell Mr. Mosaddeque Ahmed, Director (Private Power) Mr. Mohit, Deputy Director Electricity Generation Company of Bangladesh (EGCB) Mr. Md. Mostafa Kamal, Managing Director Mr. Alimuddin Ahmed, Executive Director (Finance) Mr. Santi Ram Roy, Executive Director (Technical) Mr. Md. Nazmul Alam, Project Director Engr. Poritosh Kumar, Manager Mr M. Mustafizur Rahman, Manager Procurement Mr. Kazi M.H.Kabir, Manager Environment Mr. Curd Ettischer, Project Manager, Fichtner GmbH & Co. KG Mr. Mohammad Golam Zillani, Deputy Project Manager, Fchtner GmbH &Co. KG Mr. Arturo Jose Munguia Tirado, Site Manager, Isolux Power Grid Company of Bangladesh (PGCB) Mr. Masum-Al-Beruni, Managing Director Mr Choudhury Alamgir Hossain, Executive Director (P&D) Engr. Pranab Kumar Roy, Project Director Mr. Md. Ismail Hossain, Manager Transmission Mr. Md. Emdadul Islam, Chief Engineer (Transmission) Gas Transmission Company Limited (GTCL) Mr. Jameel A Aleem, Managing Director
Mr Malik Md. Nizamul Hasan Sherif, Director Operations (in-Charge)
Engr. Md. Ainul Kabir, Project Director
Mr.Md. Abdul Azim, Deputy Manager
Mr. Hasnain Ali, Manager HSE
Site Manager, Dorsch International Consultant
10
Siddhirganj Power Project
ANNEX 2: RESULTS FRAMEWORK
Project Development Objective
Restructured Project Development Objective: Increase supply of electricity to Bangladesh grid network.
Project Development Objective Indicators
Indicator Name Unit of Measure Baseline Actual (Current) End Target
Annual contribution of at least 2.49 billion kWh
delivered to grid: Peak: 0.624 billion kWh; Off-peak:
1.87 billion kWh
Text Value Shortages of
electricity during
peaking period.
Power shortages
continued, about 1,500
MW of supply gap.
At least 2.49 billion kWh
delivered to grid;
Peak: 0.624 billion kwh; Off-
peak :1.87 billion kWh
Date 01-Apr-2009 16 October 2014 31-Mar-2016
Comment No kWh generated as
project works still under
construction.
Intermediate Results Indicators
Indicator Name Unit of Measure Baseline Actual(Current) End Target
Generation Capacity of Conventional Generation
constructed under the project
Megawatt Value 0.00 0.00 335.00
Date 30-Sep-2009 16 October 2014 31-Mar-2016
Comment 335 MW Siddhirganj CCPP
under construction.
335 MW Siddhirganj CCPP
constructed
11
Indicator Name Unit of Measure Baseline Actual(Current) End Target
Transmission lines constructed or rehabilitated
under the project
Kilometers Value 0.00 11.00 11.00
Date 30-Sep-2009 16 October 2014 31-Mar-2016
Comment Siddhirganj-Maniknagar-
Transmission line with
associated two substations
commissioned; the power
evacuation system under
partial load- test.
Transmission lines constructed under the project Kilometers Value 0.00 11.00 11.00
Date 31-Mar-2009 16 October 2014 31-Mar-2016
Comment 11 km 230 kV Power
evacuation system built,
now under load test.
11 km 230 kV Power
evacuation system built
60 km gas transmission line constructed Kilometers Value 0.00 60.00 60.00
Date 31-Mar-2009 16 October 2014 31-Mar-2016
Comment 85% contract completed;
pipeline pre-commissioning
completed, waiting for
upstream gas flow; other
associated works ongoing.
60 km gas transmission line
constructed
12
Indicator Name Unit of Measure Baseline Actual(Current) End Target
Projected lifetime fuel savings MJ Value 0.00 0.00 218.60 billion MJ
Date 30-Sep-2009 16 October 2014 31-Mar-2016
Comment
O&M Contracts budgeted and implemented Text Value O&M for 2x120 MW
ongoing and O&M for CCPP
under bidding.
EGCB capacity on O&M for
CCPP achieved
Date 30-Sep-2009 16 October 2014 31-Mar-2016
Comment
ERP functional and generating reports Value EGCB’s ERP bids received,
under evaluation; GTCL’s
ERP bid document under
RPM review.
ERP go life
Date
Comment 30-Sep-2009 16 October 2014 31-Mar-2016
13
Annex 3
Benchmarks to be completed by December 31, 2014
Completion of the following benchmarks are required to enable the mission to recommend to Bank
management an extension of the closing date of the project:
1). EGCB to forward to the World Bank the Simple Cycle Installation and Commissioning plan for
review. (Fichtner has drafted a first-hand plan).
2). EGCB to provide a bid evaluation report (BER) of at- least one large contract for Bank review. (2
large contracts are under bidding).
3). EGCB to provide the World Bank with a soil consolidation report certifying that the required soil
consolidations have been achieved. The report is to be certified by qualified experts/engineers of
Isolux; reviewed and accepted by Fichtner, and endorsed by EGCB. The report will contain design,
methodology, soil consolidation results and technical analysis. (Isolux’s draft soil consolidation report
is under review of Fichtner).
4). Circulating and Cooling Water Systems erection works to start in November 2014.
5). Fuel Gas Connection works with Gas RMS to start in October 2014.
6). Fire Fighting System/Clarifier Water Tank erection works to start in December 2014.
7). Titas Gas to sign the Gas Supply Agreement with EGCB by December 31, 2014.