PT. Pelabuhan Indonesia III (Persero), Addendum to EIS, EIM-EIO ...
Transcript of PT. Pelabuhan Indonesia III (Persero), Addendum to EIS, EIM-EIO ...
Addendum to EIS, EIM–EIO Documents
Tanjung Perak Port Development in Lamong Bay
JANUARI 2013
PT. PELABUHAN INDONESIA III (PERSERO)
i
TABLE OF CONTENT Table of Content i List of Tables Iv List of Figures viii CHAPTER 1. INTRODUCTION 1.1. BACKGROUND I-1
1.2. OBJECTIVES AND BENEFITS I-3
1.2.1. Objectives I-3
1.2.2. Benefits I-3
1.3. JURISPRUDENCES I-3
CHAPTER 2. ACTIVITY DESCRIPTION 2.1. IDENTITIES OF INITIATOR OF STUDY AND STUDY REPORT II-1
2.1.1. Identity of Initiator II-1
2.1.2. Study Team II-1
2.2. PROJECT DESCRIPTIONS II-3
2.2.1. Study of Environmental Impact Assessment Study
II-6
2.2.2. Consistency of Business and/or Activities to Master Plan
II-6
2.2.3. Project Site II-6
2.2.4. Project Layout II-6
2.3. PROJECT IMPLEMENTATION PHASE II-9
2.3.1. Activities Studied in Environmental Impact Assessment 2010
II-9
2.3.2. Activities Presently Studies II-13
2.4. OTHER ACTIVITIES SURROUNDING THE PROJECT SITE II-36
BAB III. INITIAL ENVIRONMENT DESCRIPTIONS 3.1. GEO-PHYSICAL CHEMICHAL COMPONENTS III-1
3.1.1. Climate III-1
3.1.2. Air Quality and Noise III-5
3.1.2.1. Air Quality III-5
3.1.2.2. Noise III-8
3.1.3. Seawater Quality III-9
3.1.4. Borlog and Soil Stratigraph III-14
3.1.5. Hidrology dan Hidro-oceanography III-16
3.1.5.1. Hidrology III-16
3.1.5.2. Hidro-Oceanography III-22
3.1.6. Transportation Compenents III-41
3.1.7. Traffic Geometric and Volume Data III-45
3.1.8. Nilam Area III-50
3.1.9. Analysis on Traffic Performance
III-51
ii
3.2. BIOLOGY III-76
3.2.1. Type of Ecosystem III-76
3.2.2. Water Flora and Fauna III-76
3.2.3. Terrestrial Flora and Fauna III-87
3.3 SOCIO-ECONOMIC AND CULTURAL COMPONENTS III-96
3.3.1. Demography III-96
3.3.1.1. Population Number and Density III-96
3.3.1.2. Population Based on Age III-97
3.3.1.3. Population Based on Education Level
III-98
3.3.1.4. Community Welfare Degree III-98
3.3.1.5. Unemployment Data III-100 3.3.2. Social Life in Studied Area III-100 3.3.2.1. Social Interaction III-100 3.3.2.2. Existing Communal Societies III-101 3.3.3. Fisherman Life III-101 3.3.4. Community Perception III-102 CHAPTER 4. SCOPE OF STUDY 4.1 SCOPING PROCESS IV-1
4.1.1. Potential Impact Identification IV-2
4.1.2. Potential Impact Evaluation IV-7
4.1.3. Hypothetical Significant Impact Classification and Priority
IV-22
4.2 BORDERS OF STUDIED AREA AND STUDY TIME LIMIT IV-24
4.2.1. Borders of Studied Area IV-24
4.2.2. Study Time Limit IV-28
BAB V. IMPACT PREDICTION AND EVALUATION 5.1. IMPACT PREDICTION V-1
5.1.1. CONSTRUCTION PHASE V-1
5.1.1.1 On-land Reclamation Material Transportation
V-1
5.1.1.2. Demolition of Erected Temporary Access
V-12
5.1.1.3. Port Construction (Shallow Water Reclamation for constructing connecting bridge, Interchange Area, Causeway, Container Yard, and Trestle)
V-17
5.1.1.4. Planned Port Pool Dredging V-38
5.1.2. Operation Phase V-43
5.1.2.1. Multipurpose Terminal Operation V-43
5.2. IMPACT EVALUATION V-54
5.2.1. Holistic Review to Significant Impacts V-54
5.2.1.1. Change of Coastal Ecology
V-56
5.2.1.2. Change of Community Welfare V-57
iii
5.2.2. Review as Basis for Environmental Impact Management
V-57
5.3. RECOMMENDATION ON ENVIRONMENTAL FEASIBILITY EVALUATION
V-59
CHAPTER VI. ENVIRONMENTAL IMPACT MANAGEMENT PLAN 6.1 GOALS AND OBJECTIVES VI-1
6.2. BENEFITS OF ENVIRONMENTAL IMPACT MANAGEMENT VI-2
6.2.1. Benefits to Project Iniator VI-2
6.2.2. Benefits to the Government and Relevant Institutions
VI-3
6.2.3. Benefits to Surrounding Community VI-3
6.3. ENVIRONMENTAL IMPACT APPROACHES VI-3
6.3.1. Technological Approach VI-4
6.3.2. Socio-Economic Approach VI-5
6.3.3. Institutional Approcah VI-6
6.4. ENVIRONMENTAL IMPACT MANAGEMENT PLAN VI-7
BAB VII. ENVIRONMENTAL IMPACT OBSERVATION PLAN 7.1. OBJECTIVES OF ENVIRONMENTAL IMPACT OBSERVATION VII-1
7.2. BENEFITS OF ENVIRONMENTAL IMPACT OBSERVATION VII-2
7.3. ENVIRONMENTAL IMPACT OBSERVATION VII-3 BIBLIOGRAPHY ANNEXURE: STRATEGIC ENVIRONMENT REVIEW IN LAMONG BAY
iv
LIST OF TABLES Table 1.1 Jurisprudences I-4 Table 2.1. Study Team II-2 Table 2.2. The Activities Covered in Environmental Impact
Assessment (EIA) Year 2010 and Revised Activities to be Reviewed in Addendums of Environmental Impact Statement (EIS), Environmental Impact Management (EIM) and Environmental Impact Observation (EIO)
II-3
Table 2.3. Activity Schedule of Tanjung Perak Port Development in Lamong Bay
II-35
Table.3.1. Data of Rain Volume in Studied Area Year 2007 - 2011 III-2 Table.3.2. Data of Humidity in Studied Area Year 2007 - 2011 III-3 Table.3.3. Data of Air Temperature Humidity in Studied Area Year
2007 - 2011 III-4
Table 3.4. Conditions of Clime During Air Quality Measurement III-6 Table 3.5. Results of Ambient air Quality Measurement
(Secondary Data) III-6
Table 3.6. The results of Air Quality Analysis in Sampling Points (Primary Data)
III-7
Table 3.7. Results of Noise Measurement (Secondary Data) III-8 Table 3.8. Results of Noise Measurement (Primary Data) III-9 Table 3.9. Seawater Sampling Points III-10 Table 3.10. Seawater Quality in Studied Area on 09 April 2012 III-11 Table 3.11. Seawater Quality in Studied Area on 16 Juli 2012 III-12 Table 3.12. Average Monthly Water Flow in Lamong Bay in m³/det III-21 Table 3.13. Wind Speed and Percentage III-23 Table 3.14. Wave Prediction for 5-50 ear cycles based on wind data
2000-2009 III-27
Table 3.15. Tidal Harmonic Constants in Karang Jamuang III-27 Table 3.16. Tidal Harmonic Constants in Karang Kleta III-28 Table 3.17. Tidal Harmonic Constants in Surabaya Seaport III-28 Table 3.18. The Results of Maximum and Minimum Speed
Measurement Year 2001 III-29
Table 3.19. Results of Analysis on Bed Sediment in Studied Area III-34 Table 3.20. Results of Analysis on Floating Sediment in Studied Area III-35
Table 3.21. Results of Traffic Counting during Peak Hour in Margomulyo Junction
III-47
Table 3.22. Results of Traffic Counting during Peak Hour in Romokalisasi Crossroad
III-50
Table 3.23. Results of Traffic Counting during Peak Hour on Jalan Raya Nilam
III-50
Table 3.24. Result of Analysis on Performance of Margomulyo Junction
III-51
Table 3.25. Result of Analysis on Performance of Romokalisari Crossroad
III-52
v
Table 3.26. Results of Analysis on Performance of Jalan Tambak Oso (4/2 UD)
III-52
Table 3.27. Results of Survey on Jalan Nilam Barat ((Entry) 2/2 UD III-53 Table 3.28. Results of Survey on Jalan Nilam Timur (Exit) 2/2 UD III-54 Table 3.29. Results of Survey in Margomulyo Junction 1 III-56 Table 3.30. Results of Survey in Margomulyo Junction 2 III-57 Table 3.31. Results of Survey in Margomulyo Junction 3 III-58 Table 3.32. Results of Survey in Margomulyo Junction 4 III-60 Table 3.33. Results of Survey in Margomulyo Junction 5 III-61 Table 3.34. Results of Survey in Margomulyo Junction 6 III-62 Table 3.35. Results of Survey in Romokalisari Crossroad 1 III-64 Table 3.36. Results of Survey in Romokalisari Crossroad 2 III-65 Table 3.37. Results of Survey in Romokalisari Crossroad 3 III-66 Table 3.38. Results of Survey in Romokalisari Crossroad 4 III-68 Table 3.39. Results of Survey in Romokalisari Crossroad 5 III-69 Table 3.40. Results of Survey in Romokalisari Crossroad 6 III-70 Table 3.41. Results of Survey in Romokalisari Crossroad 7 III-72
Table 3.42. Fish Diversity in Estuary of Lamong River III-79 Table 3.43. Preparation of Finfish in Lamong Bay III-83 Table 3.44. Compositions and Abundance of Bentik Macrofauna
Surrounding Project Site Waters III-85
Table 3.45. Degree of Pllution and Diversity Index III-86 Table 3.46. Mangrove Diversity in Lamong Bay III-88 Table 3.47. Avifauna Diversity in Lamong Estuary III-93 Table 3.48. Population Number and Density in Studied Area III-96 Table 3.49. Population based on Age, Sex and Sex Ratio III-97 Table 3.50. Population Based on Age III-97 Table 3.51. Percentage Based on Education level III-98 Table 3.52. Proportion of Degree of Welfare III-99 Table 3.53. Unemployed and Unemployed Family Heads III-100 Table 4.1. Matrix of Potential Impacts of Tanjung Perak Port
Development in Lamong Bay IV-3
Table 4.2. Potential Impact Evaluation IV-8 Table 4.3. Matrix of Hypothetical Significant Impacts of Tanjung
Perak Port Development in Lamong Bay IV-20
Table 4.4. Study Time Limits for Each Impact IV-28 Table 5.1. % of Pollutant emission from Motorized Vehicles V-2 Table 5.2. Impact of Main Air Pollutants Emitted from Motorized
Vehicle V-3
Table 5.3. Ambient Air Quality Standard V-3 Table 5.4. Estimated Heavy Duty Equipment Emission V-4 Table 5.5. Estimated Motorized Vehicle Emission V-4 Table 5.6. Evaluation on Dimension of Impact on Decreased Air
Quality in Construction Phase V-6
Table 5.7. Noise Standards Based on Area Classifications
V-7
vi
Table 5.8. Evaluation on Dimension of Impact on Increased Noise in Construction Phase
V-9
Table 5.9. Traffic Volumes With and Without Project Activities V-10 Table 5.10. Calculation of Defree of Traffic Satiration With Project
Activities V-10
Table 5.11. Evaluation on Dimension of Impact on Decreased Road Performance in Construction Phase
V-11
Table 5.12. Evaluation on Dimension of Impact on Decreased Seawater Quality in Construction Phase (Demolition of Erected Temporary Access)
V-12
Table 5.13. Evaluation on Dimension of Impact on Disturbance to Sea Biota (Decreased Compositions and Abundance of Plankton in Construction Phase due to Demolition of Erected Temporary Access)
V-14
Table 5.14. Evaluation on Dimension of Impact on Decreased Mangrove Ecosystem Area in Construction Phase due to Demolition of Erected Temporary Access
V-15
Table 5.15. Evaluation on Dimension of Impact on Decreased Fisherman Income due to Demolition of Temporary Access
V-17
Table 5.16. Evaluation on Dimension of Impact on Decreased Seawater Quality in Construction Phase (Port Construction/Shallow Water Reclamation)
V-18
Table 5.17. River Water Volume Flowing into Madura Strait V-20 Table 5.18. Observation Coordinates around Lamong Bay V-30 Table 5.19. Evaluation of Significance of Impact on Change of Water
Current Pattern and Sedimentation V-31
Table 5.20. Elevation Comparisons among Existing River Bank Elevation, Water Surface Elevation Prior Project, Water Surface Elevation After Project, and Planned Water Elevation
V-34
Table 5.21. Evaluation on Dimension of Impact on increased river water surface
V-35
Table 5.22. Evaluation on Dimension of Impact on Disturbance to Sea Biota (decreased compositions and abundance of plankton/nekton) in Construction Phase (Port Construction/Shallow Water Reclamation)
V-36
Table 5.23. Evaluation on Dimension of Impact on Disturbance to Fisherman Activities in Construction Phase
V-37
Table 5.24. Evaluation on Dimension of Impact on Decreased Seawater Quality (Port Dredging)
V-39
Table 5.25. Evaluation on Dimension of Impact on Disturbance to Sea Biota (decreased compositions and abundance of plankton/nekton) in Construction Phase (Port Dredging)
V-41
Table 5.26. Evaluation on Dimension of Impact on Disturbance to Fisherman Activities in Construction Phase
V-42
Table 5.27. Evaluation on Dimension of Impact on Decreased Seawater Quality in Operation Phase
V-44
vii
Table 5.28. Planned Traffic Volume Without Project V-45 Table 5.29. Planned Traffic Volume with Project V-45 Table 5.30. Road Performance in Initial Description, With and
Without Project V-46
Table 5.31. Evaluation on Dimension of Impact on Transportation in Operation Phase
V-46
Table 5.32. Evaluation on Dimension of Impact on Decreased Mangrove Ecosystem Area In Operation Phase
V-48
Table 5.33. Evaluation on Dimension of Impact on Disturbance to Sea Biota (Decreased compositions and Abundance of Plankton) in Operation Phase
V-49
Table 5.34. Evaluation on Dimension of Impact on Job and Business Opportunities in Operation Phase
V-51
Table 5.35. Evaluation on Dimension of Impact on disturbance to fisherman activities in Operation Phase
V-53
Table 5.36. Evaluation on Dimension of Impact on Community Unrest in Operation Phase
V-54
Table 6.1. Matrix of Environmental Impact Management Plan VI-8 Table 7.1. Matrix of Environmental Observation Plan VII-4
viii
LIST OF FIGURES Figure 2.1. Project Plan Layout II-7 Figure 2.2. Project Layout II-8 Figure 2.3. Location of Stockpile dan Cross Area II-14 Figure 2.4. Cut of Girder Cross Section (Middle Girder) II-16 Figure 2.5. Cut of Pile Slab Cross Section II-16 Figure 2.6. Connecting Bridge Layout II-17 Figure 2.7. Interchange Area Layout II-18 Figure 2.8. Typical Cross Section of Interchange Area II-19 Figure 2.9. Causeway Ducts Layout II-21 Figure 2.10. Container yard dan Bulk Area Layout II-23 Figure 2.11. Container Yard and Bulk Area Typical Cross Section II-24 Figure 2.12. Hardening Layers – Container Yard Zone II-25 Figure 2.13. Gate Front View II-26 Figure 2.14. CFS Left Side View II-26 Figure 2.15. CFS Cross Section II-27 Figure 2.16. Typical Hardened Construction of Parking Area II-27 Figure 2.17. Pier Typical Cross Section II-28 Figure 2.18. Photoes of Pier Construction Works II-29 Figure 2.19. Pier Typical Cross Section II-29 Figure 2.20. Grab Dregder II-31 Figure 2.21. Waters Area Border and Administrative Area Border of
Tanjung Perak Port II-37
Figure 2.22. Other Activities II-40 Figure 2.23. Location of Suramadu Bridge in East of Tanjung Perak
Port II-41
Figure 2.24. Locations of Fisherman Activities Surrounding the Project Site
II-42
Figure 3.1. Graph of Rain Volume Per Month Per Annum (Year 2007-2011)
III-2
Figure 3.2. Graph of Average Humidity Per Month Per Annum in Studied Area (2007-2011)
III-3
Figure 3.3. Graph of Average Air Temperature Per Month Per Annum in Studied Area (2007-2011)
III-4
Figure 3.4. Wind Rose in Studied Area III-5 Figure 3.5. Soil Stratigraph in Lamong Bay III-15 Figure 3.6. Rivers having estuary in Lamong Bay III-16 Figure 3.7. Watershed of Lamong River in the System of
Bengawan Solo Managemenet Center III-17
Figure 3.8. Puddle Map of Lamong River Flood on 12 March 2004 III-18 Figure 3.9. Plain Contour in the Midlle, where floods frequently
happen III-19
Figure 3.10. Lamong River Watershed Flow Direction III-19 Figure 3.11. Lamong River Cross Section III-20 Figure 3.12. Windrose Surabaya 2000-2009 III-24 Figure 3.13. Windroses January - June in Studied Area Year 2000 –
2009
III-25
ix
Figure 3.14. Windroses July - December in Studied Area Year 2000 – 2009
III-26
Figure 3.15. Water Current Speed and Direction Measurement Points Around Madura Strait, 2001
III-31
Figure 3.16. Currentrose Around Site of Surabaya Container Terminal (TPS 2012)
III-32
Figure 3.17. Bathymetry Surrounding Project Site in Lamong Bay III-33 Figure 3.18. Seabed Sediment and Floating Sediment Sampling
Points III-36
Figure 3.19. Seabed Sediment Spread in Madura Strait III-37 Figure 3.20. Typical Current Pattern during High Tide (a) and Low
Tide (b) III-38
Figure 3.21. Typical Average Current Speed in Estuaries Close to Lamong Bay
III-39
Figure 3.22. The Average Water Elevation in rivers surrounding Lamong Bay
III-39
Figure 3.23. Sedimentation Pattern for 1 Month III-40 Figure 3.24. Calibration of Current Model with Current
Measurement Data in 2012 III-40
Figure 3.25. Traffic CountingSurvey Points III-41 Figure 3.26. Survey Point on Jalan Nilam Timur III-42 Figure 3.27. Survey Point in Margomulyo Junction III-42 Figure 3.28. Survey Point in Romokalisari Crossroad III-43 Figure 3.29. Traffic Survey Form III-44 Figure 3.30. Cross Section of Jalan Tambak Oso III-46 Figure 3.31. Cross Section of Jalan Greges III-46 Figure 3.32. Cross Section of Jalan Margomulyo III-46 Figure 3.33. Cross Section of Jalan Romokalisari (East) III-48 Figure 3.34. Cross Section of Jalan Romokalisari (North) III-48 Figure 3.35. Cross Section of Jalan Romokalisari (West) III-49 Figure 3.36. Cross Section of Jalan Romokalisari (South) III-49 Figure 3.37. Graph of Vehicles Incoming into Jalan Nilam Barat III-50 Figure 3.38. Graph of Vehicles Outgoing from Jalan Nilam Barat III-51 Figure 3.39. Graph of Compositions and Abyndance of
Phytoplankton Surrounding Pelindo Pier III-78
Figure 3.40. Graph of Compositions and Abundance of Zooplankton Surrounding Pelindo Pier
III-79
Figure 3.41. Compositions and Diversity Index of Benthos in Project Site Waters in Pelindo Pier
III-86
Figure 3.42. General Pattern of Mangrove Zoning in Asia-Pacific Area
III-90
Figure 4.1. Scoping Process Flowchart IV-2 Figure 4.2. Potential Impact Flowchart of Tanjung Perak Port
Development in Lamong Bay IV-4
Figure 4.3. Hypothetical Impact Flowchart of Tanjung Perak Port Development in Lamong Bay
IV-17
Figure 4.4. Summary of Scoping Process IV-21 Figure 4.5. Studied Area Border IV-27 Figure 5.1. Pollutant Dispersion Based on Distance V-5 Figure 5.2. Noise Degree Based on Distance V-8
x
Figure 5.3. Noise Degree Based on Distance After Noise Reduction with Barrier
V-9
Figure 5.4. Rivers flowing into Madera Strait V-20 Figure 5.5. Model 1 (Without Project) and Model 2 (With Project) V-21 Figure 5.6. Typical Water Current Pattern During High Tide V-22 Figure 5.7. Typical Current Pattern in Low Tide V-23 Figure 5.8. 1 Month- Sedimentation V-24 Figure 5.9. Water Current Speed and Sedimentation in Estuary of
Lamong River V-25
Figure 5.10. Observation Points and Sediment V-26 Figure 5.11. Current Speed and Sedimentation in Estuaries V-26 Figure 5.12. Elevation of Water Surface in Eastuaries V-27 Figure 5.13. Sediment Distribution During Construction 60 mg/l
Concentration V-28
Figure 5.14. Sediment Distribution During Construction 70 mg/l Concentration
V-28
Figure 5.15. Sediment Distribution During Construction 80 mg/l Concentration
V-29
Figure 5.16. Sediment Distribution During Construction 90 mg/l Concentration
V-29
Figure 5.17. Sediment Distribution During Construction 100 mg/l Concentration
V-30
Figure 5.18. Simulation of Flood in Lamong River with Water Volume Input 20 m3/detik
V-32
Figure 5.19. Perspective of Resulted River Flood Simulation V-33 Figure 5.20. Effect of Backwater Due to Reclamation Less than
100 m from Upstream V-34
Figure 5.21. Holistic Impact Evaluation Flowchart V-55 Figure 6.1. Environmental Management Site VI-10 Figure 7.1. Environmental Observation Site VII-10
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 1 - INTRODUCTION
I - 1 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
CHAPTER 1 INTRODUCTION
1.1. BACKGROUND
PT Pelabuhan Indonesia III (Persero) has executed Tanjung Perak Port
Development activities in Lamong Bay, Surabaya City, East Java Province.The
activities are supported with Environmental Impact Assessment documents
recommended by virtue of Decision of Minister of environment Number 256 Year
2010 dated 5 October 2010 about Environmental Feasibility for Tanjung Perak
Port Development in Lamong Bay, Surabaya City, East Java Province, by PT.
(Persero) Pelabuhan Indonesia III. However, during the course it its
implementation, it requires necessary adjustments in order to comply with the
following provisions :
- Strategic Environment Review (SER) Year 2010 by Sepuluh
Nopember Institute of Technology (ITS) Surabaya, advocating that
there will be shift of distance between the pier and container yard
from 260 meter to ±970 meter;
- Letter of Mayor of Surabaya City Number
551.43/675/436.7.1/2012, dated 13 February 2012, concerning
plan of Tanjung Perak Port Development in Lamong Bay, i.e. :
recommendation for modification of designed reclamation
distance for the Tanjung Perak Port development to ± 800 meter
from the coastline;
- Decision of Directorate General of Sea Commnication Number BX-
100/PP.008, dated 22 February 2012, about Multipurpose Terminal
Construction in Lamong Bay of Tanjung Perak Port - Surabaya.
In view of the aforementioned, PT Pelabuhan Indonesia III (Persero)
plan to adjust the layout of the Tanjung Perak Port Development in Lamong
Bay. The adjustments comprise :
Adjustment to design and contract of reclamation works for
constructing container yard and causeway (Package B) and
connecting bridge (Package C in consistence with the study final
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 1 - INTRODUCTION
I - 2 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
report recorded in SER database in view of project effectiveness
and efficiency;
The shifted coordinate of reclamation is in accordance with the
borders specified in the SER database, assumed to be proper with
the area of Tanjung Perak Port Development in Lamong Bay, i.e. :
50 Ha;
Due to the adjustments, it entails changes in designs and locations not
covered in the Environmental Impact Assessment Documents that has been
recommended by virtue of Decision of Minister of environment Number 256 Year
2010 dated 5 October 2010. The consequential changes concern with:
1. Shift of coordinates of reclamation for constructing the container
yard due to the result of SER (initially the distance from the pier is
260 meter, and presently corrected into ± 970 meter);
2. Relocation of causeway or interchange area (previously adhered to
the edge of pier and presently shifted ± 800 meter from the edeof
the pier) following the results of SER and Surabaya City
Regulations;
3. Modification of connecting bridge between the interchange area
and container yard from open-pile into massive causeway
construction.
4. Dredging of pool for inter-insular container transportation, located
between the pier and container yard;
5. Change of function from container terminal into multipurpose
terminal;
6. Construction of temporary access ± 1,000 meter with massive
reclamation construction.
In considering the latest status and pursuant to Article 50 Section (1) of
the Indonesian State Regulation Number 77 Year 2012 about Environmental
Permit, it is provided that the officer in charge of business and/or activities shall
file an application for a revision of Environmental Permit. Referring to Section
(3) and (4) thereof, before filing an application for such revision, the officer in
charge of business and/or activities shall file an application for Decision of
Minister of Environment by means of revised or modified Environmental Impact
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 1 - INTRODUCTION
I - 3 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Assessment Documents/amended Environmental Impact Statement Documents,
Environmental Impact Management Documents and Environmental Impact
Observation Documents. Referring to the Letter of Deputy to State Minister of
Environment, Environmental Management Bureau, Number B-
7531/Dep.I/LH/PDAL/07/2012, dated 25 July 2012, PT Pelabuhan Indonesia III
(Persero) is to prepare addendums to Environmental Impact Statement
Documents, Environmental Impact Management Documents and Environmental
Impact Observation Documents.
1.2. OBJECTIVES AND BENEFITS
1.2.1. OBJECTIVES
The objectives of Tanjung Perak Port Development in Lamong Bay are :
Reducing the operation density in Tanjung Perak Port, especially in
container loading and unloading activities and anticipating the exceed
over the existing installed capacity;
Cutting vessel queue to tether in the port;
Creating job opportunities during construction phase and operation one.
1.2.2. BENEFITS
Tanjung Perak Port Development in Lamong bay is favorable to support
the national development, especially by smoothening the port activities
adminitered by PT. (Persero) Pelabuhan Indonesia III. In addition, it is supposed
to strengthen the local economy in the areas surrounding Tanjung Parak Pert
area.
1.3. JURISPRUDENCES
The jurisprudences related with the plan of Tanjung Perak Development
in Lamong Bay are presented in Table 1.1.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 1 - INTRODUCTION
I - 4 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Table 1.1. Jurisprudences
NR JURISPRUDENCES REASONS
A ACTS
1. Indonesian Act Nr. 5 Year 1990 about Biological Natural Resources and Their Ecosystems
Adopted as reference that the activity plans are to be consistent with water resource conservation efforts
2. Indonesian Act Nr. 32 Year 2004 about Local Government
Referring to the authorities of provincial/city/regency government in relation with activity plans
3. Indonesian Act Nr. 26 Year 2007 about Spatial Arrangement.
Adopted as reference in determining activity site
4. Act Nr. 27 Year 2007 about Coastal Area and Small Island Management
Adopted as reference in managing and observing coastal areas and small islands
5. Indonesian Act Nr. 17 Year 2008 about Maritime Affairs
Adopted as reference related with seaport transportation management and operations
6. Indonesian Act Nr. 22 Year 2009 about Surface Traffic and Transportation
Adopted as reference related with hypothetical transportation significant impacts and road damages due to mobolization and operation activities
7. Indonesian Act Nr. 32 Year 2009 about Environment Protection amd Management.
Adopted as reference in environmental management for activity planning
8. Indonesian Act Nr. 45 Year 2009 about Amendment to Indonesian Act Nr. 31 Year 2004 about Fishery
Adopted as reference iin fishery aspects
B STATE REGULATIONS
9. State Regulation Nr. 7 Year 1999 about Protected Rare Bird Species
Adoted as reference related with hypothetica significant impact in water bird habitat decrease
10. State Regulation Nr. 18 Year 1999 about Hazardous and Poisonous Waste Treatment
Adopted as reference in managing hazardous and poisonous waste
11. State Regulation Nr. 19 Year 1999 about Pollution and/or Sea Destruction Control
Adopted as reference in controlling seawater pollution control
12. State Regulation Nr. 41 Year 1999 about Air Pollution Control
Adopted as reference for controlling air pollution
13. State Regulation Nr. 82 Year 1999 about Water and Sea Transportation
Regulating transportation in port waters
14. State Regulation Nr. 85 Year 1999 about : Amendment to State Regulation Nr. 18 Year 1999 about Pollution and/or Sea Destruction Control
Adopted as reference in managing hazardous and poisonous waste
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 1 - INTRODUCTION
I - 5 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
NR JURISPRUDENCES REASONS
15. State Regulation Nr. 74 Year 2001 about Hahardous and Poisonous Materials
Adopted as reference in operational activities
16. State Regulation Nr. 82 Year 2001 About Water Quality Management and Water Pollution Control
Adopted as reference in water environment management and observation
17. State Regulation Nr. 51 Year 2002 about Shipping
Adopted as reference in operation activities
18. State Regulation Nr. 16 Year 2004 about Area Utilization
Adopted as reference in determining proper area utilization and development
19. State Regulation Nr. 38 Year 2007 about Divisions of Authorities among National Government, Provincial Gvernment and City/Regency Government
Determining authorities in environmental management and observation
20. State Regulation Nr. 60 Year 2007 about Fish Resource Conservation as Guides to Fish Resource Preservation
Adopted as reference that activity planning is to be consistent with fish resource conservation efforts
21. State Regulation Nr. 26 Year 2008 about National Spatial Planning
Adopted as reference in determining proper area utilization and development
22. State Regulation Nr. 61 Year 2009 about Ports
Adopted as reference in port activities in general
23. State Regulation Nr. 5 Year 2010 about Navigations
Adopted as reference in port activities, especially in navigations
24. State Regulation Nr. 21 Year 2010 about Maritime Environment Protection and Sea Polution Prevention
Adopted as reference in handling and preventing sea polution
25. State Regulation Nr. 22 Year 2011 about Transportation on Waters
Adopted as reference in port activities, especially transportation operations on waters
26. State Regulation Nr. 32 Year 2011 about Impact Analysis Management and Engineering and Traffic Need Management
Adopted as reference in process of preparation of addendums to EIS, Environmental Impact Management and ENVIRONMENTAL IMPACT OBSERVATION, especially in terms of surface transportation
27. State Regulation Nr. 27 Year 2012 about Environmental Permit
process of preparation of addendums to EIS, ENVIRONMENTAL IMPACT MANAGEMENT and ENVIRONMENTAL IMPACT OBSERVATION
C PRESIDENT DECISIONS
28. Decision of President of Republic of Indonesia Nr. 65 Year 1980 about Ratification of International Convention for The Safety of Life at The Sea 1974 (SOLAS 74)
Adopted as reference in operation activities
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 1 - INTRODUCTION
I - 6 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
NR JURISPRUDENCES REASONS
29. Decision of President of Republic of Indonesia Nr. 46 Year 1986 about Ratification of International Convention for The Prevention of Pollution from Ships 1973 and The Protocol of 1978 Relating to The International Convention for The Prevention of Pollution from Ships 1973 (MARPOL 73/78).
Adopted as reference in operation activities and environmental management
D DECISIONS OF MINISTER OF ENVIRONMENT AND HEAD OF ENVIRONMENTAL IMPACT CONTROL AGENCY
30. Decision of Minister of Environemnt and Head of Environmental Impact Management Agency Keputusan Nr. Kep. 056 Year 1994 about Guides to Significant Impact Measurement.
Adopted as basis for determining significant impacts
31. Decision of Minister of Environemnt and Head of Environmental Impact Management Agency Keputusan Nr. KEP. 299/11/Tahun1996 about Technical Guides to Social Social Aspects in Preparing Environmental Impact Assessment
Adopted as guides in preparing environmental impact assessment in term of social aspects
32. Decision of Minister of Environemnt and Head of Environmental Impact Management Agency Keputusan Nr. 08 Year 2000 about Community Involvement and Information Openess in Environmental Impact Assessment Proces.
Adopted as referrence in community involvement process in preparing environmental impact assessment
33. Decision of State Minister of Environment Nr. KEP 48/MENLH/11/1996 about Noise Standards
Adopted as reference in evaluating degree of noise in an area
34. Decision of State Minister of Environment Nr. 54/MENLH/10/1997 about Air Pollution Index Standards.
Adopted as reference in analyzing impact to air quality
35. Decision of State Minister of Environment Nr. 51 Year 2004 about seawater Quality Standards
Adopted as reference in determining parameters of sewater quality
36. Decision of State Minister of Environment Nr. 201 Year 2004 about Mangrove Damage Criteria
Adopted as reference in determining degree of mangrove destruction.
37. Decision of State Minister of Environment Nr. 45 Year 2005 about Guides to Preparation of Environmental Management Plan and Environmental Observation Plan Reports
Adopted as reference to legal certainty in environmental impact management and environmental impact observation reporting
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 1 - INTRODUCTION
I - 7 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
NR JURISPRUDENCES REASONS
E DECISIONS OF STATE MINISTER OF ENVIRONMENT
38. Regulation of State Minister of Environment Nr. 08 Year 2006 about Guides to Environmental Impact Preparation
Adopted as reference in preparing addendums to EIS, ENVIRONMENTAL IMPACT MANAGEMENT , and ENVIRONMENTAL IMPACT OBSERVATION
39. Regulation of State Minister of Environment Nr. 05 Year 2009 about Waste Management in Port
Adopted as reference in hazardous and poisonous waste handling
40. Regulation of State Minister of Environment Nr. 24 Year 2009 about Guides to Evaluation of ENVIRONMENTAL IMPACT STATEMENT Documents
Adopted as reference in preparing the points in ENVIRONMENTAL IMPACT STATEMENT documents to evaluate
41. Regulation of State Minister of Environment Nr. 5 Year 2012 Business and/or Activities to be provided with ENVIRONMENTAL IMPACT STATEMENT Documents
Adopted as reference in planning business and/or activities to be provided with ENVIRONMENTAL IMPACT STATEMENT Documents
F DECISIONS OF MINISTER OF COMMUNICATION
42. Decision of Minister of Communication Nr. KM 215 Year 1987 about Provision of Reception Facility
Adopted as reference in preventing pollution and observing environment
43. Decision of Minister of Communication Nr. KM 286 Year 2002 about Mandatory Piloting in Waters
Adopted as reference in determining sea transportation routes
44. Decision of Minister of Communication Nr. KM 54 Year 2006 about Tanjung Perak Master Plan
Adopted as reference in preparing addendums to EIS, ENVIRONMENTAL IMPACT MANAGEMENT and ENVIRONMENTAL IMPACT OBSERVATION
G REGULATIONS OF MINISTER OF COMMUNICATION
45. Regulation of Minister of Communication Nr. KM 4 Year 2005 about Prevention of Polution dut to Vessel Waste
Adopted as reference in preventing pollution and observing environment
46. Regulation of Minister of Communication Nr. KM 7 Year 2005 about Voyage Navigation Aids
Adopted as reference in determining sea transportation routes
47. Regulation of Minister of Communication Nr. KM 14 Year 2006 about Surface Transportation Management and Engineering
Adopted as reference in improving traffic network performance routes
H EAST JAVA PROVINCIAL REGULATIONS
48. East Java Province Regulation Nr, 05 Year 2012 about East Java Province Master Plan
Adopted as reference in complying project site and spatial requirements
49. Surabaya City Regulation Nr. 3 Year 2007 about Surabaya City Master Plan
Adopted as reference in planning main facility constructions in Surabaya City
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 1 - INTRODUCTION
I - 8 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
I DECISIONS OF GOVERNOR OF EAST JAVA PROVINCE
50. Decision of Governor of East Java Province Nr. 660.3/25781/025/1986 about Environmental Impact Handling.
Adopted as reference in handling pollution impact
51. Decision of Governor of East Java Province Nr. 08 Year 2004 about Operational Guides to Community Involvement in Information Openness in Environmental Impact Assessment Process in East Java Province
Adopted as reference in community involvement in information openness in environmental impact assessment process in East Java Province
52. Decision of Governor of East Java Province Nr. 61 Year 2006 about Space Utilization in Regional Scale Dense Area in East Java Province.
Adopted as reference in spatial development
53. Regulation of Governor of East Java Province Nr. 10 Year 2009 about Air Ambient Quality Standard and Immovable Pollution Sources in East Java Province.
Adopted as reference in evaluating impact on ambient air quality.
J SURABAYA CITY REGULATIONS
54. Surabaya City Regulation Nr. 4 Year 2010 about Disturbance Permit
Adopted as reference in assuring legal certainly for the project commencement
55. Surabaya City Regulation Nr. 12 Year 2006 about Analysis on Surface Transportation Impacts
Adopted as reference in analyzing impacted road networks due to traffic increase during Tanjung Perak Port Development in Lamong Bay.
K DECISION OF MINISTER OF COMMUNICATION
56. Decision of Director General of Surface Communication Nr. SK 726/AJ.307/DRJD/ 2004 about Technical Guides in Surface Transportation of Heavy Duty Equipment
Adopted as reference in surface transportation of heavy duty equipment
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 1 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
CHAPTER 2 ACTIVITY DESCRIPTION
2.1. IDENTITIES OF INITIATOR OF STUDY AND STUDY REPORT
2.1.1. Identity of Initiator
Name of Company : PT Pelabuhan Indonesia III (Persero)
Address : Jl. Tanjung Perak Timur No 610 Surabaya - 60165,
PO Box 1123
Telephone : 031 – 3298631 through 37
Facsimile : 031-3295204, 3295207
Officer in Charge : Husien Latief
Designation : Director of Business Commerce and Development
2.1.2. Study Team
A. Officer in Charge
The study is prepared by :
CENTER FOR RESEARCH AND COMMUNITY OUTREACH (LPPM) ITS SURABAYA
WITH COMPETENCE REGISTRATION NR.: 0068/LPJ/AMDAL-1/LRK/KLH
Officer in Charge : Prof. Dr.Darminto, MSc.
Designation : Team Leader
Address : Gedung Dr. Angka Lt II Kampus ITS Sukolilo
Jl. Arif Rahman Hakim Sukolilo Surabaya 60111
Telephone : 031 – 5944792
Facsimile : 031 – 5996670
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 2 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
B. Study Team
The study team is detailed in the following table.
Table 2.1. Study Team
Nr Name Designation in
Team Qualification
1. Dr.Ir. Lily Pudjiastuti, MT
Team Leader, Environmental Management Expert
Doctorate Degree Graduate on Chemichal Engineering. Holing EIA Certificate as Designer of EIA. Competence Certificate Nr. 000280/SKPA/LSK-INTAKINDO/X/2010.
2. Ir. Rahmat Budi Santoso, MT
Team Member /Air Quality Expert
Master Degree Graduate on Environmenal Engineering. Competence Certificate Nr. 000222/SKPA/LSK-INTAKINDO/VIII/2010.
3. Ir. Hera Widyastuti, M, PhD
Team member/ Surface Transportation Expert
Doctorate Degree Graduate on Communication Civil Engineering. Certified EIA Designer
4 Cahya Buana, ST, MT
Team Member/ Sea Transportation Expert
Master Graduate on Civil Engineering. Holding EIA Certificates A and C
5. Haryo Dwito Armono, ST, M Eng., PhD.
Team Member/ Hydro-oceanography Expert
Doctorate Degree Graduate on Marine Engineering
6. Sujantoko, ST, MT Team Member/ Hydro-oceanography Expert
Master Graduate on Water Resource Engineering
7. Dr.Ir. Widyastuti, MT
Team Member/ Water Quality Expert
Doctorate Degree Graduate on Chemical Engineeering. Certified EIA Designer.
8. Tatas ST, MT. Team Member/Hydrology Expert
Master Degree Graduate on Civil Engineering. Certified EIA Designer.
9. Dra.Dian Saptarini, M.Sc
Team Member/Biology Expert
Master Degree Graduate on Biology. EIA Certificate A.
10. Dra. Tuti Rumiati, MSc
Team Member/Socio-Economic and Cultural Expert
Master Degree Graduate on Statistics. EIA Certificate A.
11. Rochma Fitri Astuti, ST
Team Member/ Seawater Quaity Expert
Baccalaureate Degree Graduate on Chemical Engineering. EIA Certificate A. Competence Certificate as Member of EIA Team Member Nr. 000226/SKPA/LSK-INTAKINDO/VIII/2010
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 3 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
2.2. PROJECT DESCRIPTIONS
The comparison of activities covered in Environmental Impact Assessment
(EIA) Year 2010 and the revised ones will be reviewed in this document further
detailed Table 2.2.
Table 2.2. The Activities Covered in Environmental Impact Assessment
(EIA) Year 2010 and Revised Activities to be Reviewed in
Addendums of Environmental Impact Statement (EIS),
Environmental Impact Management (EIM) and Environmental
Impact Observation (EIO)
ACTIVITIES COVERED IN IEA YEAR 2010
REVISED ACTIVITIES AS COVERED IN ADDENDUMS OF EIS, EIM AND EIO
CONSTRUCTION
Labor Mobilization
Material and Equipment Mobilization by Sea
Material and Equipment Mobilization by surface transport
- Reclamation Material o Reclamation material for
causeway, reclamation volumes I, II & III 1,100,000 m3
o Reclamation material for interchange area 700,000 m3
o Container yard 3,910,000 m3
- Piling Material
Basecamp Construction
Port Construction Port Construction
a. Connecting Bridge Length : 2,560 m Width : 18 m Area : 32,000 m2 On-pile construction Work Progress 30,8% of Length 800 m x 12,5 m
a. Connecting Bridge Length : 800 m Width : 12,5 m Area : 10,000 m2
Reviewed construction 60,2%
b. Causeway Construction Massive construction and location adhered to edge of pier;
b. Causeway Construction Massive construction with ± 8 Ha area; location shifted 800 meter from the edge of the pier;
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 4 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
ACTIVITIES COVERED IN IEA YEAR 2010
REVISED ACTIVITIES AS COVERED IN ADDENDUMS OF EIS, EIM AND EIO
Design: Length : 500 m Width : 140 m Area : 70,000 m2 Reclamation Volume : 173,000 m3
Work progress : construction of riprap 500 m length and 25 m width (area 13,000 m2)
Design: I. Reclamation for causeway, Phase I
Length 520 m Width 25 m Area 13,000 m2
II. Causeway construction Phase 2 Length 200 m
Width 30 m Area 6,000 m
III. Causeway construction Phase 3 Length 1,231 m
Width 50 m Area 61,550 m2
c. Container Yard Construction
Container yard and supporting facilities Reclamation Volume: 5,844,000 m3 Container Yard size : 387,000 m2 4 blocks @ 96,750 m2 Terminal supporting facilities : 113,000 m2
Distance from Pier 260 m, Area 50 Ha
c. Container Yard Construction I. Container Yard
Area : 250,000 m2 Reclamation Volume : 2,800,000 m3
II. Dry Bulk Yard Area : 100,000 m2 Reclamation Volume : 1,110,000 m3
Distance from Pier ±970 m; Area 25 Ha and 10 Ha. Work Progress 0% Reception Facilities (RF) Construction
d. Trestle Construction
Trestle, 2 units with area 7,872,5 m2 Size 235 m x 9,5 m
On-pile Construction
d. Trestle Construction
Trestle modified into connecting bridge 2 (between container yard and pier) Length : 975 m Width : 16 m Area : 15,600 m2 On-pile Construction Work Progress 0%.
e. Pier Construction Size : 51,299 m2 (1,280 x 40) m Work progress 500 m length 50 m width (outer side)
d. Pier Construction Size 86,400 m2 (1,080 x 80) m.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 5 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
ACTIVITIES COVERED IN IEA YEAR 2010
REVISED ACTIVITIES AS COVERED IN ADDENDUMS OF EIS, EIM AND EIO
Dredging of port pool for inter-insular container transportation, located in between pier and container yard Depth : -13 m LWS Dredging Volume : 2,000,000 m3
Beyond Study 2010
Temporary access Construction Temporary Access Demolition Length : 1,160 m Width : 12 m Area : 13,920 m2 Reclam. Volume: 57,505 m3
Additional Sewage: Type : Corrugated Steel Pipe Diameter : 1 m Length : 18 m Distance : 50 m Amount : 17 unit Total Length : 306 m Massive Length : Constructed.
Interchange Area Construction Interchange Area Construction I. Office Area
Length : 150 m Width : 113 m Area : 16,950 m2
II. Parking Lots Length : 387 m Width : 136 m Area : 52,632 m2 Massive Construction , Area ± 7 Ha Issue to be reviewed : Construction remains (97,5%)
OPERATION
Recruitment of 2,000 truck drivers For Container Terminal 45,000 DWT
Additional recruitment of 300 workers to support dry bulk loading and unloading activities For Multipurpose Terminal 45,000 DWT
Maintenance Dredging
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 6 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
2.2.1. Study of Environmental Impact Assessment Study
The addendum to EIS, EIM and EIO for Tanjung Perak Port Development
in Lamong Bay is executed after the feasibility study on Detailed Engineering
Design and Bathimetry Study have been completed.
2.2.2. Consistency of Business and/or Activities to Master Plan
The project activity plan is consistent with the East Java Provincial
Regulation Number 05 Year 2012 about East Java Province Masper Plan Year
2011-2031.
2.2.3. Project Site
The project site is under the asministrative territory of Surabaya City,
East Java Province (Figure 2.1.)
The borders of the project site are :
North : Madura Strait
East : -
West : Warehousing Estate, Fishponds Madura Strait
South : Jalan Tambak Osowilangun
2.2.4. Project Layout
The project layout is presented in Figure 2.2.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 7 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
U
TA R
A
Page : II – 7
Figure 2.1 Project Plan Layout
Source: DIGITAL INDONESIAN MAP YEAR 1999 (LAND USE) and RESULT OF BATHYMETRY MEASUREMENT IN LAMONG RIVER ESTUARY YEAR 2008
1 0 1 2km SCALE
14’30”
14
’00”
9200
13’30”
13
’00”
12
’30”
12
’00”
11
’30”
11
’00”
9205
10’30”
10
’00”
09
’30”
09
’00”
08
’30”
9210
08’00”
06
9326
7 m
T
44’00” 44’30” 9198242 mU 9198293 mU 38’00” 38’30”
0680
Balongsari 3,5 km
39’00” 39’30” 40’00” 40’30”
0685
Balongsari 1 km
41’00” 41’30” 42’00” 42’30” 43’00”
0690
43’30”
0693
214 m
T
: Project Site Border
Pier 1080 x 80
Connecting Bridge 2 -
975 x 16 m (On Pile Construction)
Dry Bulk Yard 10 Ha
Container Yard 25 Ha Causeway 8 Ha
(Massive Construction)
Connecting Bridge 1 800 x 12,5 m
(On Pile Construction)
Interchange Area 7 Ha
Remarks
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 8 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 2.2 Project layout
Blue : Change on Lay Out of Activity
Plans Reviewed in this Document
PIER 1080 X 80 M
CONNECTING BRIDGE 1 (800 X 12,5 M)
ON PILE CONSTRUCTION
DRY BULK YARD 10 HA
CAUSEWAY 8 HA (MASSIVE CONTRUCTION)
CONNECTING BRIDGE 2 (975 X 16 M)
ON PILE CONSTRUCTION
Accordance with Decision of Minister of Environment Number 256 Year 2010
Strategic Environment Review (SER) Border
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 9 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
2.3. PROJECT IMPLEMENTATION PHASE
2.3.1. Activities Studied in Environmental Impact Assessment 2010
2.3.1.1. Construction Phase
a. Labor Mobilization
Labor mobilization reviewed in the Environmental Impact Asssessment 2010
will be conducted in accordance with the need. The project will need
about 100 comprising : 80 skilled workers and 20 non-skilled workers. The
hiring will be prioritized for the local people in accordance with the
required qualifications. They will be hired during construction phse only
on contract basis.
b. Equipment and Material Mobilization by Sea
The equipment and material transportation by sea has been reviwed in the
Environmental Impact Asssessment 2010. The quarry material is transported
by means of Trailling Suction Hopper Dredger (TSHD) and Cutter Suction
Hopper Dredger (CSD). The total volume of the reclamation material is
5,844,000 m3. In case the production capacities of TSHD and CSD are
respectively 400 - 500 m3/hour and in case the capacity of one barge
transporting the reclamation material is 10.000 m3, there will be increased
sea traffic by 10 vessels per day, crossing the shipping routes in Tanjung
Perak Port.
c. Basecamp Construction
The construction of basecamp has been reviwed in the Environmental Impact
Asssessment 2010. It will be utilized by the labors and spplied by the
contractor . The basecamp will be constructed on the access road, close to
Jalan Raya Tambak Osowilangon. The basecamp is to be supplied by public
washing, bathing and toilet facilities.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 10 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
d. Port Construction
- Connecting Bridge Construction
The connecting bridge has been reviwed in the Environmental Impact
Asssessment 2010, and will be :
Length : 2,560 m
Width : 12,5 m
Area : 32,000 m2
Construction : On Pile
The construction adopts steel pile foundation. The distance between
others of the bridge piles. The interval in between the piles is 40 m.
Yet, the designed has been modified. At present the construction
progress is 30.8% of the total newly designed length (800m x 125 m)
- Causeway Construction
The causeway construction has been reviwed in the
Environmental Impact Asssessment 2010. It is designed for 500 m length
and 140 m width (total 70,000 m2) protruding to the sea. The
construction of the causeway will be quarry with volume + 173,000 m3
and massive construction in a location attached to the edge of the
coast.
However, the designed has been modified. When this study was
prepared, the work progress had been proceeding in riprap construction
with 500 m length and 25 m width, with a total area of 13,000 m2 (new
design).
- Container Yard Construction
The works of container yard construction and terminal supporting
facilities are progressing by reclaiming shallow water area in 260
distance from the pier. The designed of the construction has been
reviwed in the Environmental Impact Asssessment 2010 as detailed
below :
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 11 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
- Area of container yard: 387,000 m2 (4 block @ 96,750 m2)
- Area of Terminal Supporting Facilities : 113,000 m2.
The total volume of the reclamation material is 5,844,000 m3.
The designed has been modified to change the total area of the container
yard and terminal supporting facilities, reclamation volume and distance
from the pier.
- Trestle and Pier Constructions
The constructions of pier and trestle adopt cast in situ method.
The steel reinforcements are sirectly set on site and the concrete
mortar is supplied by raedy mix. The piles are made of steel with 0.711
m diameter (for trestle) dan 0.812 m diameter (for pier). The piers are
constructed on pile foundation. The piles are planted by means of
pontoon on the sea. Next, it is followed with preparation of pore
reinforcement and casting (on the top of the structure to tie some
piles), and preparation of girder reinforcement and pier floor. Then,
they are castled with ready mix concrete. The designs of trestle and
pier reviwed in the Environmental Impact Asssessment 2010 are :
- Trestle, 2 units with an area of 7.872,5 m2 sized 235 m x 9,5 m,
on-pile construction.
- Dermaga, sized: 51.299 m2 (1.280 x 40) m, the current progress :
constructed 500 m length and 50 m width (outer side)
2.3.1.2. Operation Phase
The operation phase has been reviwed in the Environmental Impact
Asssessment 2010. and it is designed for the operation of 45.000 DWT container
yard. It is specially operated for cargo container loading and unloading
activuties.
a. Labor Recruitment
Specifically during the operation phase and due to loading and unloading
services and other related activities, the container terminal existence will drive
better economic activities around the project site. The studied area will develop
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 12 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
towards an industrial, trade and service center. At present the container loading
and unloading services in Tanjung Perak Port are supported by 50 – 100
companies. It is predicted that there will be new companies established to
support the operation of the cargo container loading and unloading activities.
According to the Environmental Impact Asssessment 2010, it is predicted to
require 2the hiring of 2,000 truck drivers.
b. Container Terminal Operation
In the Environmental Impact Asssessment 2010, it designed container
terminal capacity is 1,6 million TEU‟s per year, and it is estimated that there will
be increase of vessel accesses by + 530 vessels per year or + 2 vessels per day.
Tanjung Perak Port Development is supposed to anticipate container loading and
unloading up to year 2030. Next, it will be developed by constructing a new port
in Tanjung Bulu Pandan, Bangkalan, Madura (Results of Study by JICA 2007, The
Greater Surabaya Metropolitan Port).
As a center of distribution of goods, it will turn into a center of cargo
containers in East Java Province. As a center of distribution, it will be much
accessed by incoming and outgoing semi trailer trucks, especially transporting
cargo containers. The traffic volume on the highways in the studied area
accessing Jl. Tambak Osowilangon - Jalan Romokalisari – Romokalisari Toll Road
Gate, will be + 60 trucks per day or + 8 trucks per hour. At present Jl.
Romokalisari is already provided with 4 lanes 2 ways with road median in the
middle of the highway (4/2 D) and Jl. Tambak Osowilangun has already provided
with 6 lanes 2 (6/2 D) with road median in the middle of the highway.
Accordingly, it will not affect the average road performance significantly, i.e. :
0.8.
The ballast water is commonly filled after the vessels have completed
unloading operations to balance the vessels. Such operations seldom take place
in Tanjung Perak Port since, mostly, vessels having completed unloading
operations, they will be straightly loaded. Therefore, in general ballast water
filling practically is not required. The oil usually spills during ballast water
draining. The process ballast water draining is to adopt reception facility (RF).
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 13 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
The container terminal in Lamong Bay share the same RF available in Tanjung
Perak Port in Milam Barat.
2.3.2. Activities Presently Studies
2.3.2.1. Construction Phase
a. Pre Cat Material and Equipment Mobilization and Demobilization
Mobilization of material and equipment for preparing the construction
of connecting bridge, pier and trestle by means of trucks. The construction
materials are transported onland via toll road and Jalan Tambak Osowilangon
until it reaches the the project site.
It adopts pre-cast construction method where the materials for
constructing the pier and other container terminal facilities are directly
installed on site. The piles to be installed are steel piles. The trestle materials
are transported by surface transport and collected in a stockpile on site. The
location of stockpile (a) and stockpile (B) and the truck access road are
presented in Figure 2.3.
The volume of reclamation material required for constructing the
Intercahange Area will be ± 600,000 m3. It is predicted that the mobilized
trucks during 3-month construction phase will be ± 30 units per hour or 355
units per day. The causeway will need ± 1,800,000 m3 reclamation material. In
case the causeway construction can be completed in ± 3 months it is predicted
that the mobilized trucks will be ±55 units per hour or 650 units
b. BasecampConstruction
When this study is prepared, field office (basecamp) has been erected as in
Figure 2.3 (C)).
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 14 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
D. Material Truck Route in
Jl. Raya Tambak Oso Wilangon
A. On Site Stockpile
Figure 2.3. Location of Stockpile and
Cross Area
C. On Site Basecamp
B. Temporary Access
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 15 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
c. Port Construction.
- Temporary Acces
Prior to the preparation of addendum to EIS, EIM and EIO, the temporary
access has been completely constructed but not yet reviewed in the
Environmental Impact Assessment 2010 . The access road is temporary as
it is accessed by material trucks only during the construction of causewy
and interchange area. It is 1,160 m length and 12 m wdth. The temporary
access is constructed bt reclaiming shallow water with a total reclamation
volume of 57,505 m3. To secure the seawater flows, in each 50 m interval
it is provided with a duct. The temporary access is presented in Figure
2.3 (see point D). When the connecting bridge is completely constructed
and can be utilized, the temporary access will be demolished. The
demolition ruins will be dumped in the planned area container yard
construction.
- Connecting Bridge Construction
It used to be planned be constructed with 2.560 m length 18 m width,
yet revised to be constructed with 800 m length 12,5 m with and total
area of 10.000 m2. The construction adopts steel pile foundation. The
distance between poers of the bridge piles. The interval in between the
piles is 40 m. It is designed to anticipate scouring due to seawater
turbulence. At present the construction progress it is estimated it will
be completed in early 2013. The cross section of the typical layout is
presented in Figure 2.4., Figure 2.5 and Figure 2.6.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 16 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 2.4. Cut of Girder Cross Section (Middle Girder)
Figure 2.5. Cut of Pile Slab Cross Section
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 17 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 2.6. Connecting Bridge Layout
- Interchange Area Construction
The construction of interchange area has not been reviewed in the
Environmental Impact Assessment 2010 . It is an area for interchanging modes of
transportation, i.e. : external triler trucks to the internal trucks in the port area.
In the interchange area there are truck parking lots, offices and access gates .
The Interchange Area is constructed by reclaiming shallow waters in point right
before the position of causeway. The total area of Interchange Area will be
5,77Ha, comprising office area (113 m x 170 m = 19,120 m2) and parking lots 135
m x 285 m = 38,475 m2. The total reclamation volume will be 600,000 m3. The
layout and typical cross section of the interchange area are presented in Figure
2.7. and Figure 2.8.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 18 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 2.7. Interchange Area Layout
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 19 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 2.8. Typical Cross Section of Interchange Area
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 20 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
- Causeway Construction
The location of causeway is not right in the coastline, instead it is the
extension of connecting bridge + 800 m distance fromthe coastline.The
location of the causeway is in accordance with the recommendation of
Mayor of Surabaya as addressed in Decision of Mayor of Surabaya Number :
551.43/675/436.7.1/2012 dated 13 February 2012 about Plan of Tanjung
Perak Port Development in Lamong Bay. The shallow water reclamation
for constructing the causeway requires a volume of reclamation as much
as + 1.800.000 m3 material supplied onland and transported to by trucks.
The causeway reclamation is to be provided with ducts installed arrays
with 200 m interval as presented in Figure 2.9. To ease the construction
works, the causeway construction process utilize the available temporary
access (as further detailed in the following activity descriptions).
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 21 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 22 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
- Container Yard Construction
The container yard design detailed in the addendum of EIS, EIM and EIO
2012, is different from the one designed in Environmental Impact
Assessment 2010, where the result of Strategic Environmental Review
2012 by Brawaijaya University show that the planned location of the
Container Yard, as recommended based on the results of Strategic
Environment Review (SER) Year 2012 by Brawijaya University, it is
planned to be 970 m from the pier, instead of 260 based on the
Environmental Impact Assesssment 2010. It will be constructed by
reclaiming the shallow waters with a total volumen of reclamation
material of 2,800,000 m3 for Container Yard and 1,110,000 m3 for dry bulk
yard. It is planned that the reclamation material will be supplied from
mud in shallow waters dredged by means of Trailling Suction Hopper
Dredger (TSHD and Clamshell). The quarry material for constructing the
Container Yard is supplied by third parties holding required and valid
licenses. One of the alternatives to get the quarry material is using the
results of port pool dredging. The quarry material must contain minimal
20% mud (as per construction of Surabaya Container Terminal). It is
supplied from the quarry by means of hopper provided with suction units
and pipeline to draw the material into the causeway area since it is in
shallow water area.
A unit of Trailling Suction Hopper Dredger (TSHD) can transport ± 2,500
m3 reclamation sand while the clamshelll can transport ± 6,000 m3. In
case of 20-hour operation per day, it is estimated that there will be 4-5
trips per day for about 2 month. The operation must be closely piloted
and monitored by the port master to prevent any possible disturbances to
the existing voyage scheduled.
The layout of Container Yard and dry bulk area are presented in Figure
2.10., while its typical cross section is presented in Figure 2.11.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 23 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 2.10. Layout of Container Yard and Bulk Area
Figure 2.10. Container Yard dan Bulk Area Layout
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 24 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 2.11. Container Yard and Bulk Area Typical Cross Section
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 25 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Construction of Terminal Supporting Facilities
(Container Yard Hardening, Gate, CFS, Chasis Parking)
The construction of terminal supporting facilities covers :
a. Container Yard Hardening
The typical hardened construction of the container yard is presented in
Figure 2.12.
Figure 2.12. Hardening Layers – Container Yard Zone
Source: Survey Investigation Design (SID) Container Terminal Development II in Lamong Bay, Tanjung Perak Port, Surabaya, 2008
- 12 Gates
The gates are constucted with steel frames. The front view of the gate
structure is presented in Figure 2.13.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 26 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 2.13. Gate Front View
Source: Survey Investigation Design (SID) Container Terminal Development II in Lamong Bay, Tanjung Perak Port, Surabaya, 2008
c.. 2.500 m2 CFS
The Container Freight Station (CFS) is a warehouse with streel frames.
The typical side view and cross section of the CFS is presented in Figure
2.14 and Figure 2.15.
Figure 2.14. CFS Left Side View
Source: Survey Investigation Design (SID) Container Terminal Development II in Lamong
Bay, Tanjung Perak Port, Surabaya, 2008
Tampak Samping KiriSkala 1:250
667667 667667 667667
4000
± 000
+ 700
+ 1266
- 120
SISI ARAH LAUT SISI ARAH DARATAPRON APRON
300 300300300
+ 517
600600
15°
Off Shore Side Apron
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 27 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 2.15. CFS Cross Section
Source: Survey Investigation Design (SID) Container Terminal Development II in Lamong
Bay, Tanjung Perak Port, Surabaya, 2008
d. 9,141 m2 Chassis Parking Area (150 m x 100 m)
Chassis parking is provided for parking vehicles before they enter the
container yard. The typical hardened construction of the chassis parking
area is presented in Figure 2.16.
Figure 2.16. Typical Hardened Construction of Parking Area
Source: Survey Investigation Design (SID) Container Terminal Development II in
Lamong Bay, Tanjung Perak Port, Surabaya, 2008
Concrete Block K-500
Bedding Sand
BASE
COURSE
CTB K-125
SUB GRADE
CBR 6 %
10cm
5cm
60cm
SUB BASE
AGREGAT B
CBR 30 %
30cm
Potongan A-ASkala 1:250
± 000
+ 700
+ 1266
667667 667667 667667
4000
300
- 120
APRON
360
300300300
15°
APRON ± 000
+ 517
600600
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 28 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
- Trestle Construction
The trestle is constructed with on pile construction with 975 m length and
16 m width (area 15,600 m2). The typical cross section of trestle or
connecting bridge is the same as the previous one (between the mainland
and causeway)
- Pier Construction
In general the multipurpose pier covers pier construction and port pool
dredging as detailed below. it The area of the pier construction is 86,400
m2 (1,080 m x 80 m). Before the preparation of addendum to the EIS, EIM
and EIO the pier construction progress has been 500 m length x 50 m
width. The typical cross sections are presented in Figure 2.17. and the
design of the pier in such a way that the seawater depth under the pier is
14 m LWS . It is designed in such a way up to 14 LWS. The photos of pier
works are presented in Figure 2.18.
Figure 2.17. Pier Typical Cross Section
16000
6500 6500
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 29 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 2.18. Photoes of Pier Construction Works
Figure 2.19. Pier Typical Cross Section
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 30 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
The dredging has not yet reviewed in the Environmental Impact
Assessment 2010. The dredging utilizes a system called Clamshell type Grab
Bucket working with a grab when lifting up from and down into the water (see
Figure 2.20). Method or process of grabbing in 1 Cylus :
Pulling down
The grab with its content is pulled down into the hold/barge, including
the bucket, depending on the closing cables /wires
Opening
The grab weight is shifted to hanging wires. As the Grab opens the
content is poured into the hold of hopper
Swinging
The crane arm (jib) swings again to digging point. The closing wire
loosens to enable the bucket fully open before being dipped into the
water.
Pulling down
The open Bucket/Grab freely drops while the hanging wire is loosen.
Closing
When the bucket reaches the seabed, the hoisting wire is pulled. The
bucket will close with wit a force that is not exceeding the force of
the grab and its content.
Pulling up
When the bucket is closed, the lifting up proceeds by pulling the
hoisting wire.
Swinging
When the Grab is over the water, the jib swing over the hopper. As the
operation system works on the grab weight (freedy drop) , the weight
of the steel grab and its volume will affect its performance to handle
the soil. In case of Mud (=loose soil) it requires large but light bucket.
In case of Hard soil it requires small but heavy bucket.
The spud and anchor are used to tether the dredger. The tagline is
required to control the grab.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 31 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
The dredger is moved by pulling up spud and moves backward especially in
stationary dredgers. In case of self propelled dredger, the it is easy to move in
the same position and direction, i.e. simply by igniting the engine, then it will
move forward.
In case of stationary dredger, it can be attached with one crane and grab only.
Consequently, the dredge will be move frequently. However, the self propelled
dredger can be attached with some cranes simultaneously to increase the
operation capacity.
Figure 2.20. Grab Dregder
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 32 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
The dredging performance depends on the depth of the seabed and
„slewing‟ angle. The dredging speed is about 70 m/minute and the 'slewing' speed
: 1.8 – 2.0 rpm working separately or simultaneusly slewing angle 45o it needs
60 seconds - 3 minutes.
The mud will be poured/dumped into the seabed. The dredging mud will
be dumped to the area of container yard construction.
2.3.2.2. Operation Phase
In general, the activities in the multipurpose terminal in the operation
phase of Tanjung Perak Port Development in Lamong Bay comprise :
a. MultipurposePier Operation
The loading and unloading activities in the multipurpose pier cover
container and dry bulk loading and unloading. The operation of container
terminal in Lamong Bay is closely related with container loading and
unloading activities. The container loading and unloading activities from the
vessels usually transist in a container yard. Next, the container will be
transported to the vessel for container loading or to the truck for container
unloading.
The container terminal capacity is 1,6 million TEU‟s per year, and it is
estimated that there will be increase of vessel accesses by + 530 vessels per
year or + 2 vessels per day. Tanjung Perak Port Development is supposed to
anticipate container loading and unloading up to year 2030. Next, it will be
developed by constructing a new port in Tanjung Bulu Pandan, Bangkalan,
Madura (Results of Study by JICA 2007, The Greater Surabaya Metropolitan
Port). For dry bulk cargo, it is predicted that there will be an increase of
vessel entry by + 1 vessel per day.
As a center of distribution of goods, it will turn into a center of cargo
containers in East Java Province. As a center of distribution, it will be much
accessed by incoming and outgoing semi trailer trucks, especially
transporting cargo containers. The traffic volume on the highways in the
studied area accessing Jl. Tambak Osowilangon - Jalan Romokalisari –
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 33 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Romokalisari Toll Road Gate, will be + 80 trucks per day or + 10 (during peak
time 10.30 – 11.30)
b. Ballast Water Supply and Oil Spill
The ballast water is commonly filled after the vessels have
completed unloading operations to balance the vessels. Such operations
seldom take place in Tanjung Perak Port since, mostly, vessels having
completed unloading operations, they will be straightly loaded. Therefore,
in general ballast water filling practically is not required. The oil usually
spills during ballast water draining. The process ballast water draining is to
adopt reception facility (RF). The container terminal in Lamong Bay share
the same RF available in Tanjung Perak Port in Nilam Barat.
Waste Treatment in Tanjung Perak Development in Lamong Bay
The waste treatment in container terminal in Lamong Bay utilizes the
same waste treatment plant already available in Tanjung Perak Port. The
treated wastes cover :
a. Solid Waste
The treatment of solid wastes in the container terminal will utilize
the same waste treatment plant already available in Tanjung Perak Port.
The rubbish from the container terminal will be transported to and
dumped in Benowo Landfill, so will the rubbish collected from the pools
or pier waters. (See Annex of Working Plan and Technical Requirements
for Transportation of Rubbish Collected from the Port to Benowo Landfill)
b. Liquid Waste and Poisonous and Hazardous Material
The liquid waste and dangerous and hazaordous wasstes from the
container terminal will be treated in the same Reception Facility 9RF)
available in Tanjung Perak Port in Nilam Barat. Pursuant to Annex
IVMARPOL 73/78 Regulation 10, the port administrator or management is
to provide RF in accordance with the vessel needs. The operation of RF is
to refer to the relevant local regulations. In Indonesia, the RF operation
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 34 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
procedures are provided in the Regulation of the Minister of Environment
Number 05 Year 2009 about Waste Treatment in Ports (annexed thereto).
Port Security Management
The port security in the container terminal in Lamong Bay will be
managed under the same standards as the ones applied in Tanjung Perak
Port. Tanjung Perak Port management has applied the international
standards to manage the port security and facilities under International
Ship and Port Facility Security (ISPS Code) since 1 July 2004, and they
periodically provide security trainings to be attended by the relevant
security officers. The trainings provided in consistence with the ISPS Code
involves KP3 Tanjung Perak, Indonesian Army Officers, Indonesian Navy
Officers, Tanjung Perak Port Security Unit, PT Pelindo, Fire Extinguishers
and companies operating in the port. Tanjung Perak Port that serves
foreign vessels, is strictly to follow the international security procedures
as set forth in the ISPS Code. In order to be able to well support the port
security and facility, it requires trainings. In the mean time, to assure
better services and sense of security, as of 01 July 2004 all ports,
especially the ones serving foreign vessels is to apply the ISPS Code. The
consistant application of ISPS Code in Tanjung Perak Port, is initialized by
preparing the required human resources and physical supports in the port,
such as : Close Circuit Television (CCTV), street lights and fences.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 35 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Table 2.3. Activity Schedule of Tanjung Perak Port Development in Lamong Bay
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 36 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
2.4. OTHER ACTIVITIES SURROUNDING THE PROJECT SITE
Tanjung Perak Port
Tanjung Perak Port is geographically located in 112º 43‟ 22” East Longitude
and 7º 11‟ 54” South Latitude, excatly in Madura Strait., North Part of
Surabaya City.
Tanjung Perak Port is under the administration of PT. Pelabuhan Indonesia
III and the borders of Administration Authority of Tanjung Perak Port ,
Surabaya have been set forth based on Collective Decision of Minister of
Home Affairs and Minister of Communication Number 93 Year 1981 and
Number KM.110/AL.106/Phb-81 dated 29 April 1981, and the borders of the
Working Environment of Tanjung Perak Port is in consistant with the Master
Plan prepared by the City Government of Surabaya. With reference to the
borders, the administrative area of Tanjung Perak Port is totally 524.3 Ha,
while the waters area of Tanjung Perak Port is 1,634.03 Ha. Basically, the
administrative area is in the waters area of Tanjung Perak Port (See
Figure 2.21.).
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 37 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 2.21. Waters Area Border and Administrative Area Border of
Tanjung Perak Port
Source: Technical and Environmental Review on Shipping Routes, Seminetation and Phase of Reclamation in Coastal Area in Madura Strait
6°5
5'0
0" L
S
6°5
5'0
0" L
S
7°1
5'0
0" L
S
112°50'00" BT112°35'00" BT
112°50'00" BT112°35'00" BT
DERMAGA PETROKIMIA
DERMAGA PLTU
PELABUHAN GRESIK
DERMAGA PERTAMINA
DERMAGA PLTG
INDRO
KARANG KIRING
TENGGULUNAN
KREMBANGAN
KALI ANAK
GENTING
BABAT JERAWAT
SEGOROMADU
KAMAL
KALI MAS
TANJUNG PERAK
P. MADURA
U
TA R
A
TAMBAK PERIKANAN
TANJUNGAN
JUNGANYAR
DAKIRING
BULUHBARAT
Tg. BULU
SLEMPIT
SEMBILANGAN
Ug. SLEMPIT
SEMBILANGAN
JUNGPIRING BARAT
JUNGPIRING TIMUR
Ug. PIRING
MARTAJASA
BANGKALAN
S. PUCUNG
BANCARAN
SABANEH
SABIYAN
GEBANG
POCOGAN
BARUK
LANCANG
BINTENG
AROSBAYABARAT
Tg.MODUNG
Tg. BULUPANDAN
BATUPORON
KESEK
SEKARBUNGUSUKALELA
KARANGPANDAN
TEBUL
KALI MIRENG
Tg.SAWO
KA
LI M
ER
TA
NI
KALI UJUNG
Tg.WEDORO
KA
LI S
OL
O
MUARA KALI SOLO
KALI RESPATI
PM 2
DERMAGA MASPION
112°40'00" BT 112°45'00" BT
7°0
0'0
0" L
S7
°05'0
0" L
S7
°10'0
0" L
S7
°15'0
0" L
S
0.0
Kilometer
1.0 2.0 3.0 4.0
MASPION
7°0
5'0
0" L
S7
°00'0
0" L
S
7°1
0'0
0"
LS
112°40'00" BT 112°45'00" BT
Waters Area Border
Administrative Area Border
MADURA ISLAND
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 38 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
The progress of traffic accessing Tanjung Perak Port during the last five years
keeps increasing, especially the traffic of cargo containers and passengers. At
present, the vessels visiting Tanjunbg Perak Port take the same shipping routes
that will be accessed when visiting the multipurpose terinal in Lamong Bay.
Consequently, it will be potential to increase the rate of sea traffic addicents
in the routes.
Fish Landing Base Plan in Surabaya City
Surabaya City Development Agency plans to establish a Fish Auction Center -
Fish Landing Base in the estuary of Lamong Bay. However, it is not yet clear
when such plan will be realized. The possibly arising impact will be increase of
traditional fisherman boat traffic loading the existing shipping routes in the
West Part of Madura Strait
Waterfront City Plan in Lamong Bay
Based on the information collected from the East Java Province Environmental
Agency, it is planned to establish a Waterfront City close to Lamong Bay by a
private entity. It is supposed to be a water tourist attraction center.
Theproject will be realized by reclaiming parts of Lamong Bay. It will be
potential to heighten the water surface due to backwater in the estuary when
high tide.
Suramadu Bridge
Suramadu Bridge is in the East of Tanjung Perak Port and relatively remote
from the studied area. The East shipping routes at present are not the ones for
vessels about to tether in Tanjung Perak Port or Container Terminal in Lamong
Bay, since the contour of the routes is too shallow for vessels to access. Since
the location is pretty away (+ 15 km) from the project site, and it is not in the
shipping routes to the port, it does not affect Tanjung Perak Port Development
in Lamong Bay.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 39 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Multiporpuse Terminal and Container Depot Construction Plans by PT Sarana
Mitra Global Nusantara.
The area to be occupied for the multipurpose terminal and Container depot is
125 Ha. These plans certainly will bring impacts as other container terminals in
general do, among other things : increasedd surface transportation and
decreased seawater quality.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY DESCRIPTION
II - 40 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Page: II - 40
Figure 2.22 Other Activities
Source: DIGITAL INDONESIAN MAP YEAR 1999 (LAND USE) and RESULT OF BATHYMETRY MEASUREMENT IN LAMONG RIVER ESTUARY YEAR 2008
1 0 1 2km SCALE
U
TA R
A
14’30”
14
’00”
9200
13’30”
13
’00”
12
’30”
12
’00”
11
’30”
11
’00”
9205
10’30”
10
’00”
09
’30”
09
’00”
08
’30”
9210
08’00”
06
9326
7 m
T
44’00” 44’30” 9198242 mU 9198293 mU 38’00” 38’30”
0680
Balongsari
3,5 km 39’00” 39’30” 40’00” 40’30”
0685
Balongsari 1 km
41’00” 41’30” 42’00” 42’30” 43’00”
0690
43’30”
0693
214 m
T
Water Front City
Teluk Lamong
Surabaya Fish
Market
Tanjung Perak
Port
Mangrove
Galang
Island
Mine-free activity site
Fleet Base and
Armory
Container
Terminal
(TPS)
PT. SMGN
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY IDESCRIPTION
II - 41 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 2.23. Location of Suramadu Bridge in East of Tanjung Perak Port
Source : Detailed Engineering Design of Suramadu Access from Surabaya Side and Madura Side PT PELINDO III (Persero)
Batas Tapak
U
Scale
0 1 2
km
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 2 – ACTIVITY IDESCRIPTION
III - 42 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 2.24. Locations of
Fisherman Activities
Surrounding the Project Site
Fish cages Trawl Shrimp search site Gate house Construction Site Mussel search site Fish ponds Salt ponds
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 1 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
CHAPTER 3 INITIAL ENVIRONMENT DESCRIPTIONS
The presented initial environmental decriptions concern with hypothetical
significant impacts due to the project within the scope of study and data
required for predicting such impacts.
3.1. GEO-PHYSICAL CHEMICAL COMPONENTS
3.1.1. Climate
The data on climate in the studied area are collected from Perak
Meteorology, Climatology and Geo-physics Agency 1 Surabaya, comprising
number and volume of rains and air temperature and humidity. The climate is
classified based on Q value or comparison between number of rains in dry
season (rain volume < 60 mm) and number of rains in wet season (rain volume >
100 mm. Next, it is classified as advocated by Schmidt dan Ferguson (1951). In
year 2007 – 2009, the Q value were successively 140%; 100% and 140%.
Accordingly, the climate is classified E and D (Fair – Slightly Dry). In 2010 the Q
value dropped into 44%, therfore the classification shifted into C (slightly wet)
and in 2011 it shifted into the fair (Q = 71 %).
In year 2007 – 2008, the dry months were July through and the wet
months were November - June. However, in 2010 there were still rains from
January through October. In 2011 the wet months were October through May.
The rain volume per year from 2007 through 2011 were 1,062 mm; 1,143
mm; 1,257 mm; 1,384 mm; 1,390 mm. It shows that the trend of rain volume
kept increasing pretty significaltly. The complete data on the rain volume are
presented in Table 3.1.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 2 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Tabel.3.1. Data of Rain Volume in Studied Area Year 2007 - 2011
Month
2007 2008 2009 2010 2011
Volume (mm)
Max Day Volume
(mm) Mas Day
Volume (mm)
Max Day Volume
(mm) Max Day
Volume (mm)
Max Day
1 111 50 9 142 30 10 324 80 11 300 57 19 190 43 11
2 230 56 11 119 32 7 408 85 17 228 36 15 203 57 7
3 175 70 8 354 76 9 262 74 9 274 59 14 381 103 14
4 71 55 4 - - - 135 35 8 284 62 17 101 30 9
5 30 9 4 54 14 1 - - - 143 28 9 168 47 9
6 53 53 1 6 4 2 13 13 1 25 15 2 - - -
7 - - - - - - - - - 47 25 4 - - -
8 - - - 13 13 1 - - - 13 11 2 - - -
9 - - - - - - - - - 70 22 5 - - -
10 - - - 79 40 6 - - - - - - 38 16 3
11 50 17 6 113 28 8 - - - - - - 176 57 12
12 342 62 12 263 52 9 115 35 6 - - - 133 33 12
Total 1.062 55 1.143 53 1.257 52 1.384 87 1.390 77
Source : Perak Meteorology, Climatology and Geo-physics Agency 1 Surabaya, 2011
Figure 3.1. Graph of Rain Volume Per Month Per Annum (Year 2007-2011) Source: Perak Meteorology, Climatology and Geo-physics Agency 1 Surabaya, 2011
0
50
100
150
200
250
300
350
400
450
1 2 3 4 5 6 7 8 9 10 11 12
Bulan
Ju
mla
h C
ura
h H
uja
n (
mm
)
2007
2008
2009
2010
2011
Month
Tota
l Rai
n V
olu
me
(mm
)
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 3 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
The highest humidity generally took place in February, March and April, while
the lowest one usually dis in September and October. The average humidity
ranged 64% – 83 %. In 2010 the average humidity per year tended to increase,
yet in 2011 it tended to drop.
Table. 3.2. Data of Humidity in Studied Area Year 2007 - 2011
Month 2007 2008 2009 2010 2011
Max Min Aver. Max Min Aver. Max Min Aver. Max Min Aver. Max Min Aver.
January 99 44 77 97 48 79 97 45 79 97 46 79 97 47 82
February 98 58 83 95 55 81 97 52 82 97 52 80 97 54 81
March 97 54 81 98 56 82 92 59 78 97 48 81 97 53 81
April 98 52 81 95 46 77 94 46 77 98 55 82 95 52 81
May 95 45 77 94 35 72 98 38 78 97 54 81 96 45 76
June 97 44 77 93 39 71 98 46 75 96 46 78 97 38 70
July 93 39 72 92 35 67 95 36 69 97 40 75 92 38 70
August 92 40 67 96 40 68 92 37 68 94 42 72 89 35 67
September 90 32 64 89 32 65 89 33 66 97 40 76 91 33 66
October 96 31 67 93 35 68 87 32 66 97 46 77 92 28 66
November 95 36 74 95 49 78 94 35 70 98 41 78 97 44 77
December 97 55 81 98 49 78 95 40 74 98 41 78 97 47 79
Source: Perak Meteorology, Climatology and Geo-physics Agency 1 Surabaya, 2011
Figure 3.2. Graph of Average Humidity Per Month Per Annum in Studied Area (2007-2011)
Source: Perak Meteorology, Climatology and Geo-physics Agency 1 Surabaya, 2011
0
20
40
60
80
100
1 2 3 4 5 6 7 8 9 10 11 12
Bulan
Kele
mb
ab
an
Ud
ara
Rata
-Rata
(%
)
2007
2008
2009
2010
2011
Ave
rage
Hu
mid
ity
(%)
Month
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 4 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
The average highest temperature took place in October - November while
the lowest one did in Februari. During 2007 – 2011, the maximum temperature
ranged 33,4 – 37,6oC while the lowest one did 19,8 – 24,6 oC. The complete
temperature data are presented in the following table.
Table.3.3. Data of Air Temperature Humidity in Studied Area Year 2007 - 2011
Bulan 2007 2008 2009 2010 2011
Max Min Aver. Max Min Aver. Max Min Aver. Max Min Aver. Max Min Aver.
January 35.60 24.00 28.90 34.60 23.00 28.27 34.20 24.00 27.70 35.20 23.40 28.60 34.2 22.8 27.4
February 34.40 23.80 27.80 33.40 22.80 27.00 34.20 23.80 27.30 33.50 24.40 28.40 34.4 23.2 27.7
March 36.60 23.20 28.00 33.70 21.90 27.50 35.00 24.00 28.30 35.20 23.40 28.60 34.2 23.6 27.9
April 35.00 24.20 28.60 34.60 22.60 28.60 35.30 24.40 29.20 35.10 23.80 28.60 34.3 24.0 28.2
May 35.00 23.40 29.00 34.80 20.80 28.70 35.30 22.80 28.70 35.00 24.60 29.00 34.5 24.5 28.9
June 34.60 21.80 27.50 34.60 21.50 28.30 34.60 23.20 28.70 35.00 23.00 28.80 34.8 22.0 28.1
July 34.40 21.20 28.00 33.60 21.40 27.70 34.40 19.80 28.30 34.70 21.60 28.80 33.6 22.0 28.1
August 34.40 20.40 27.90 35.40 22.00 28.50 34.80 20.20 28.50 34.90 22.00 29.20 34.2 21.4 28.0
September 35.60 20.80 28.60 36.20 23.00 29.40 36.40 20.40 29.30 35.80 23.20 28.80 35.2 22.8 28.6
October 35.10 23.80 29.70 36.70 24.40 30.10 37.60 21.80 30.30 35.80 22.20 28.70 36.4 22.8 29.8
November 36.80 22.20 29.40 34.90 24.60 28.70 37.30 27.00 30.10 35.60 23.00 28.80 35.4 23.6 28.9
December 34.70 23.20 27.80 34.80 23.70 27.90 36.60 22.60 29.30 35.60 23.00 28.80 35.4 23.6 28.3
Source: Perak Meteorology, Climatology and Geo-physics Agency 1 Surabaya, 2011
Figure 3.3. Graph of Average Air Temperature Per Month Per Annum in Studied Area (2007-2011)
Source: Perak Meteorology, Climatology and Geo-physics Agency 1 Surabaya, 2011
25
26
27
28
29
30
31
1 2 3 4 5 6 7 8 9 10 11 12
Bulan
Tem
pera
tur
Ud
ara
Rata
-rata
Bu
lan
an
(o
C)
2007 2008 20092010 2011
Ave
rage
Air
Tem
per
atu
re (
C)
Month
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 5 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
To identify the trend of wind direction based on the data of wind speed and
direction in year 2011 in the studied area see Figure 3.4. The figure shows that
the wind tended to blow to East and North East with average speed 4,5 m/s.
Figure 3.4. Wind Rose in Studied Area
Source : Survey on Wind Speed and Direction in Studied Area year 2011
3.1.2. Air Quality and Noise
3.1.2.1. Air Quality
Based on the secondary data from Environmental Impact Assessment
Documents of Tanjung Perak Port Development in Lamong Bay in Year 2010, the
air quality is studied through sampling by Company Hygiene and Occupational
Health Agency , East Java Province. The air quality measurement and test took
place on 19 Pebruary 2008. The conditions of climate when it was mesured are
presented in Table 3.4 and the ambient air quality are presented in Table 3.5.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 6 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Table 3.4. Conditions of Clime During Air Quality Measurement
Nr Locations
PARAMETER
Air Temp. (oC)
Relative Humidity (RH)
(%)
Wind Speed (m/sec)
Wind Direction
Climate
1 Container Terminal Gate 31.6 68.3 0.25-1.01 South East Cloudy
2 Demak Junction, Jl. Gresik 29.7 71.0 1.25-3.22 South East Clear
3 Romokalisari Crossroad 30.9 65.0 1.6-2.9 South East Cloudy
4 Tambak Osowilangun 34.5 62.4 1.9-3.9 South East Cloudy
5 Margomulyo Junction 31.1 67.0 1.6-4.2 South East Cloudy
Source: Air Quality and Noise Survey on 19 February 2008 for Environmental Impact Assessment for Tanjung Perak Port Development towards Lamong River and Lamong Bay
Table 3.5. Results of Ambient air Quality Measurement (Secondary Data)
*Regulation of Governor of East Java Province Nr. 10 Year 2009 ** Indonesian State RegulationNr. 41 Year 1999 about Air Polution Control Source: Air Quality and Noise Survey on 19 February 2008 for Environmental Impact Assessment for Tanjung Perak Port Development towards Lamong River and Lamong Bay
Refering to data presented in Table 3.3, the parameter exceeding the quality
standard is NOx, i.e. : in Jl Demak – Jl. Gresik Junction and Romokalisari
Crossroad. The dust exceeding the quality standards as set forth in the
Indonesian State Regulation 41 Year 1999 is found in Demak Junction,
Romokalisasi Crossroad and Margomulyo Junction. The concentration of
measured gases and dust is predicted to originate from fuel combustion of
automotive vehicles and traffic of automotive transportation activities. In the
locations of measurement, the mobile activities of human beings and goods by
means of automotive vehicles are relatively dense.
Nr Locations
PARAMETER
Carbom Monoxide
(CO) (ppm)
Nitrogen Oxide
(NOx) (ppm)
Sulphur Dioksida
(SO2) (ppm)
Amonia (NH3) (ppm)
Dust g( /N m3)
1 Container Terminal Gate 1.0 0.0453 0.0016 0.0439 0.0658
2 Demak Junction, Jl. Gresik 4.0 0.0593 0.0044 0.0423 0.6482
3 Romokalisari Crossroad 4.0 0.0561 0.0044 0.0044 0.5791
4 Tambak Osowilangun 3.7 0.0441 0.0026 0.0584 0.0662
5 Margomulyo Junction 2.7 0.0420 0.0022 0.0658 0.6857
Quality Standards * 20 0.05 0.10 2.00 0.26
230 µg/Nm3 **
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 7 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
In addition to the secondary data, the sampling on air quality was taken on 11
September 2012 in collaboration with the PT. Envilab Indonesia. The results of
the laboratory analysis arae presented in the followig table.
Table 3.6. The results of Air Quality Analysis in Sampling Points (Primary Data)
Nr. Parameter Analysis Results *) Quality
Standard **)
1 2 3 4
1 Nitrogen Dioxide, NO2 <10 <10 <10 <10 92.5
2 Sulfurdioxide, SO2 <25 27.8 <25 <25 262
3 Ammonia, NH3 215 70 107 57 1.360
4 Hydrogen Sulfide, H2S <2.2 <2.2 2.2 2.8 42
5 Dust 122 73.7 35.2 319.1 260
6 Hydrocarbon, HC** 17.6 17.5 17.6 17.8 160
7 Carbon Monoxide, CO <1.000 <1.000 <1.000 <1.000 22.600
8 Oxidant, O3 <20 27 23 <20 200
9 Lead, Pb <0.2 <0.2 <0.2 <0.2 60
10 Noise 72.9 80.3 74 59.4 -
METEOROLOGY DATA
1 Temperature 38.0 36.1 36.5 35.6 oC
2 Relative Humidity 40.5 55.8 47.1 44 %
3 Wind Direction (to) West West West West -
4 Wind Speed 0.1 – 2.1 0.1 – 2.3 0.1 – 2.8 0.1 – 0.9 m/s
5 Weather Clear Clear Clear Clear -
*) Sampling Points
1 : Kalianak Junction Surabaya (S : 07o13.774‟ E : 112o40.952‟) 2 : In front of Project Site (S : 07o12.931‟ E : 112o39.231‟) 3 : Around Romokalisari (After Bridge) (S : 07o11.782‟ E : 112o38.724‟) 4 : Project Area (Close to the coast) (S : 07o12.646‟ E : 112o39.676‟)
**) The Air Quality Standard pursuant to Regulation of Governor of East Java Province Nr. 10 Year 2009
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 8 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Based on the results of sampling on the air quality in the sampling points it is
found that the in area close to the roads Amonia, H2S, dust and hydrokarbon
were identified. However, they still satisfied the quality standards to the
Regulation of Governor of East Java Province Nr 10 Year 2009. In area close to
the project site, it was found that SO2, NH3, dust, Hydrocarbon, and oxidant
were detected. In general, they satisfied the stadard, saved for dust in area
close to the coast that was relatively thick and exceeded the standard. It was
due to the existing reclamation activities.
3.1.2.2. Noise
Similar to the measurement of air quality, to identify the noise in area
srrounding the project site the mesurement based on the secondary data from
Environmental Impact Assessment Documents of Tanjung Perak Port
Development in Lamong Bay in Year 2010, the noise is studied through sampling
for primary data by PT. Envilab Indonesia on 11 September 2012. The results of
the measurement are presented in the following table.
Table 3.7. Results of Noise Measurement (Secondary Data)
Nr Location Noise Intensity (dB.A)
1 Container Terminal Gate 71.2
2 Demak Junction, Jl. Gresik 75.7
3 Romokalisari Junction 78.4
4 Tambak Osowilangun 74.2
5 Margomulyo Junction 75.8
Quality Standard * 70
*Decision of Minister of Environment Nr. 48/XI/1996 about Noise Standards for Industrial Area Source: Air Quality and Noise Survey on 19 February 2008 for Environmental Impact Assessment
for Tanjung Perak Port Development towards Lamong River and Lamong Bay
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 9 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Table 3.8. Results of Noise Measurement (Primary Data)
Nr. Parameter Analysis Results *) Quality
Standard **)
1 2 3 4
1. Noise 72.9 80.3 74 59.4 -
DATA METEOROLOGY
1 Temperature 38.0 36.1 36.5 35.6 oC
2 Relative Humidity 40.5 55.8 47.1 44 %
3 Wind Direction (to) West West West West -
4 Wind Speed 0.1 – 2.1 0.1 – 2.3 0.1 – 2.8 0.1 – 0.9 m/s
5 Weather Clear Clear Clear Clear - Source: Air Quality and Noise Survey on 19 February 2008 for Environmental Impact Assessment for Tanjung Perak Port Development towards Lamong River and Lamong Bay
*) Sampling Points
2 : Kalianak Junction Surabaya (S : 07o13.774‟ E : 112o40.952‟) 2 : In front of Project Site (S : 07o12.931‟ E : 112o39.231‟) 3 : Around Romokalisari (After Bridge) (S : 07o11.782‟ E : 112o38.724‟) 4 : Project Area (Close to the coast) (S : 07o12.646‟ E : 112o39.676‟)
Based on the aforementioned data, it shows that the condition in the
sampling points is already noisy. In general, such high noise is due to cargo and
passenger transportation by means of motorized vehicles.
3.1.3. Seawater Quality
The observation on seawater quality was conducted in 10 points
surrounding the ptoject site as presented in Table 3.9. The seawater quality data
were secondary ones, collected from the area surrounding the project site in
Lamong Bay and supplied by PT. PELINDO III.In case of activities in ports, the
adopted standard is pursuant to seawater quality standard for seawater quality
pursuant to Decision of Minister of Environment Nr. 51 Year 2004 Annex I about
Seawater Quality Standard on port waters. The measurement took place on 09
April 2012 by the officer of Technical Environmental Health and Disease Control
Management Center. The results are presented in Table 3.10. The test results
show that the whole paramaters of seawater quality in the 10 sampling
pointssatisfied the prevailing standards.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 10 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Since there are fishing activities surrounding the project site, the
parameters of seawater quality are to refer to the seawater quality standard for
seawater quality pursuant to Decision of Minister of Environment Nr. 51 Year
2004 Annex III about seawater quality for sea biota. The sampling took place 16
July 2012 by the officer of Technical Environmental Health and Disease Control
Management Center. The results are presented in Table 3.11. The results of
measurement on the physical parameter of seawater quality for sea biota in
consistence with the Quality Standard pursuant to Decision of Minister of
Environment Nr. 51 Year 2004, it shows that the parameters of turbidity,
phospate and nitrate contents did not satisfy the required standards, except in
point 8 (in the middle of the sea and close to the area of container yard, with a
value of 5.35 mg/l and point 6 for 5.50 mg/l, where the value satisfying the
standard is to be >=5 mg/l. In view of parameter on total suspended solid (TSS),
almost the samples from the whole points exceeded the quality standards,
saved for the ones taken from point 6 and point 9, close to the trestle of Tanjung
Perak Port and water area close to the container yard fase line Jetty where the
value satisfying the standard is to be <=20 mg/l. Basically, phosphate and nitrate
are required for phytoplankton growth as feeds of fish. Unfortunalety, such high
content of phospate and nitrate can lead to low content of dissolved oxygene
and is mainly due to urband, industrial and agricultural wastes drawn by river
water flows.
Table 3.9. Seawater Sampling Points
Nr. Origin of Seawater Sample
Point 1 Point 2 Point 3 Point 4 Point 5 Point 6 Point 7 Point 8 Point 9 Point 10
Estuary of Lamong River, Gresik Estuary of Sememi River, Gresik Estuary of Branjangan River Estuary of Greges River Estuary of Krembangan River In the middle of the sea close to trestle of Tanjung Perak Port In the middle of the sea close to connecting bridge In the middle of the sea close to container yard In the middle of the sea close to container yard (fase line Jetty) Estuary of Kalianak River
Source Survey on Seawater Quality on 09 April 2012 dan 16 Juli 2012 by officer of Technical Environmental Health and Disease Control Management Center
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 11 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Table 3.10. Seawater Quality in Studied Area on 09 April 2012
Parameter Unit Quality
Standard* Detection Limit (DL)
Point 1 Point 2 Point 3 Point 4 Point 5
I. Physical
1. Smell - Natural - Natural Natural Natural Natural Natural
2. Clearity m >=3 - - - - - -
3. Suspended Solid mg/l <=80 1 50 24 25 21 22
4. Floating Object - Nil - Nil Nil Nil Nil Nil
5. Oil Layer - Nil - Nil Nil Nil Nil Nil
6. Temperature °C ±2°C Natural
0.1 29.0 29.0 29.0 29.0 29.0
II. Chemical
1. pH - 6.5-8.5 0.01 7.5 7.5 7.5 7.5 7.5
2. Salinity o/oo
±10%
Natural 0.1 6.71 14.2 16.6 12.1 21.7
3. Amonia as N (NH3) mg/l <=0.3 0.0135 0.0164 0.0859 0.0436 0.0490 0.0418
4. Sulfide (S) mg/l 0.03 0.001 <LD <LD <LD <LD <LD
5. Total Hydrogene mg/l 1 - - - - - -
6. Phenol Compound mg/l <=0.002 0.005 <LD <LD <LD <LD <LD
7. PolichlorinatedBiphenil (PCB)
g/l 0.01 - - - - - -
8. Detergent Surfactant
mg/l <=1.0 0.001 0.544 0.636 0.604 0.607 0.596
9. Oil and Grease mg/l 5 0.5 <LD <LD <LD <LD <LD
10. TBT (Tri Butil Tin) - 0.01 0.01 - - - - -
11. Dissolved Metal
- Quicksilver (Hg) - Cadmium (Cd) - Copper (Cu) - Lead (Pb) - Zinc (Zn)
mg/l mg/l mg/l mg/l mg/l
0.003 0.010 0.050 0.050 0.100
0.001 0.001 0.0153 0.0036 0.0075
<LD <LD <LD <LD <LD
<LD <LD <LD <LD <LD
<LD <LD <LD <LD <LD
<LD <LD <LD <LD <LD
<LD <LD <LD <LD <LD
*Decision of Minister of Environment Nr. 51 Year 2004 Annex I Seawater Quality Standard for Ports
Cont. Table 3.10. Seawater Quality in Studied Area on 09 April 2012
Parameter Unit Quality
Standard* Detection Limit (DL)
Point 6 Point7 Point8 Point9 Point1
0
I. Physical
1. Smell - Natural - Natural Natural Natural Natural Natural
2. Clearity M >=3 - - - - - -
3. Suspended Solid mg/l <=80 1 14 34 26 9 24
4. Floating Object - Nil - Nil Nil Nil Nil Nil
5. Oil Layer - Nil - Nil Nil Nil Nil Nil
6. Temperature °C ±2°C Natural
0.1 30.0 30.0 30.0 30.0 29.0
II. Chemical
1. pH - 6.5-8.5 0.01 7.50 7.50 7.50 7.50 7.50
2. Salinity o/oo
±10%
Natural 0.1 26.2 26.5 26.9 28.0 26.1
3. Amonia as N (NH3) mg/l <=0.3 0.0135 0.0717 0.0639 0.0203 0.0742 0.0784
4. Sulfide (S) mg/l 0.03 0.001 <LD <LD <LD <LD <LD
5. Total Hydrogene mg/l 1 - - - - - -
6. PhenolCompound mg/l <=0.002 0.005 <LD <LD <LD <LD <LD
7. PolichlorinatedBiphenil (PCB)
g/l 0.01 - - - - - -
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 12 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Parameter Unit Quality
Standard* Detection Limit (DL)
Point 6 Point7 Point8 Point9 Point1
0
8. Detergent Surfactant
mg/l <=1.0 0.001 0.664 0.638 0.564 0.648 0.538
9. Oil and Grease mg/l 5 0.5 <LD <LD <LD <LD <LD
10. TBT (Tri Butil Tin) - 0.01 0.01 - - - - -
11. Dissolved Metal - Quicksilver
(Hg) - Cadmium (Cd) - Copper (Cu) - Lead (Pb) - Zinc (Zn)
mg/l mg/l mg/l mg/l mg/l
0.003 0.010 0.050 0.050 0.100
0.001 0.001 0.0153 0.0036 0.0075
<LD <LD <LD <LD <LD
<LD <LD <LD <LD <LD
<LD <LD <LD <LD <LD
<LD <LD <LD <LD <LD
<LD <LD <LD <LD <LD
*Decision of Minister of Environment Nr. 51 Year 2004 Annex I Seawater Quality Standard for Ports
Table 3.11. Seawater Quality in Studied Area on 16 Juli 2012
Parameter Unit Quality
Standard* Detection Limit (LD)
Point 1 Point 2 Point 3 Point 4 Point 5
I. Physical
1. Color TCU <=50 1 14 13 13 15 8
2. Smell - Natural - Natural Natural Natural Natural Natural
3. Clarity m >=5 - - - - - -
4. Turbidity NTU <=5 0.06 28.9 27.3 65.2 88.6 28.7
5. Suspended Solid mg/l <=20 1 36 35 92 102 32
6. Floating Object - Nil - Nil Nil Nil Nil Nil
7. Oil Layer - Nil - Nil Nil Nil Nil Nil
8. Temperature °C ±2°C Natural
0.1 30.0 30.0 30.0 30.0 30.0
II. Chemical
1. pH - 7.0-8.5 0.01 7.0 7.0 7.0 8.0 7.0
2. Salinity o/oo
Natural. coral 33-
34
0.1 29.8 29.3 27.6 27.6 29.4
3. Dissolved Oxigene (DO)
mg/l >=5 0.05 4.73 3.31 3.30 3.19 4.35
4. Bio-Chemical Oxygene Need
mg/l <=20 0.05 5.57 6.89 6.90 7.01 5.95
5. Amonia as N (NH3) mg/l <=0.3 0.0001 0.0846 0.0624 0.0217 0.0632 0.0432
6. Phosphate (PO4P) mg/l 0.015 0.001 0.04 0.133 0.017 0.017 0.021
7. Nitrate as N (NO3) mg/l 0.008 0.0021 0.5799 0.6067 0.9916 0.9859 0.6918
8. Cyanide (CN) mg/l 0.5 0.001 <LD <LD <LD <LD <LD
9. Sulfide (S) mg/l 0.01 0.001 <LD <LD <LD <LD <LD
10. Poliaromatic Hydrocarbon (PAH)
mg/l 0.003 - - - - - -
11. Phenol Compound mg/l <=0.002 0.0050 <LD <LD <LD <LD <LD
12. Pesticide (organoklorin)
g/l <=0.01 - - - - - -
13. PolichlorinatedBiphenil (PCB)
g/l 0.01 - - - - - -
14. Detergem Surfactant mg/l <=1.0 0.001 0.621 0.504 0.601 0.623 0.623
15. Oil and Grease mg/l 1 0.5 <LD <LD <LD <LD <LD
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 13 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Parameter Unit Quality
Standard* Detection Limit (LD)
Point 1 Point 2 Point 3 Point 4 Point 5
16. Dissolved Metal - Quicksilver (Hg)
- ChromHexavalen(Cr6+) - Arsenic (As) - Cadmium (Cd)
- Copper (Cu) - Lead (Pb) - Zinc (Zn) - Nickel (Ni)
mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l
0.001 0.003 0.012 0.001 0.008 0.008 0.05 0.05
0.0010 0.0030
- 0.0010 0.0153 0.0036 0.0075 0.0339
<LD <LD
- <LD <LD <LD <LD <LD
<LD <LD
- <LD <LD <LD <LD <LD
<LD <LD
- <LD <LD <LD <LD <LD
<LD <LD
- <LD <LD <LD <LD <LD
<LD <LD
- <LD <LD <LD <LD <LD
17. Total coliform MPN/100 ml
1000 - 13 1.8 240 920 2
*Decision of Minister of Environment Nr. 51 Year 2004 Annex I Seawater Quality Standard for Ports
Cont Table 3.11 Seawater Quality in Studied Area on 16 Juli 2012
Parameter Unit Quality
Standard*
Detection Limit
(LD) Point 6 Point 7 Point 8 Point 9
Point10
I. Physics 1. Color TCU <=50 1 6 11 12 5 15
2. Smell - Natural - Natural Natural Natural Natural Natural
3. Clarity m >=5 - - - - - -
4. Turbidity NTU <=5 0.06 9.2 28.6 41.7 8.8 48.6
5. Suspended Solid mg/l <=20 1 15 42 62 9 61
6. Floating Object - Nil - Nil Nil Nil Nil Nil
7. Oil Layer - Nil - Nil Nil Nil Nil Nil
8. Temperature °C ±2°C Natural
0.1 30.0 30.0 30.0 30.0 30.0
II. Chemical 1. pH - 7.0-8.5 0.01 7.0 7.0 7.5 7.0 7.0
2. Salinity o/oo
Natural. coral 33-
34
0.1 30.6 30.1 30.4 30.8 24.0
3. Dissolved Oxygenes (DO)
mg/l >=5 0.05 5.50 4.04 5.35 4.46 2.87
4. Bio-Chemical Oxygene Need
mg/l <=20 0.05 4.71 6.06 4.95 5.74 7.33
5. Amonia as N (NH3) mg/l <=0.3 0.0001 0.0482 0.0339 0.0683 0.0237 0.0768
6. Phosphate (PO4P) mg/l 0.015 0.001 1.658 0.090 1.619 0.366 2.116
7. Nitrate as N (NO3) mg/l 0.008 0.0021 0.6561 0.7594 0.6022 0.6658 0.8328
8. Cyanide (CN) mg/l 0.5 0.001 <LD <LD <LD <LD <LD
9. Sulfide (S) mg/l 0.01 0.001 <LD <LD <LD <LD <LD
10. Poliaromatic Hydrocarbon (PAH)
mg/l 0.003 - - - - - -
11. Phenol Compound mg/l <=0.002 0.0050 <LD <LD <LD <LD <LD
12. Pestiside (organochlorine)
g/l <=0.01 - - - - - -
13. PolichlorinatedBiphenil (PCB)
g/l 0.01 - - - - - -
14. Detergent Surfactant mg/l <=1.0 0.001 0.486 0.472 0.455 0.411 0.421
15. Oil and Grease mg/l 1 0.5 <LD <LD <LD <LD <LD
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 14 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Parameter Unit Quality
Standard*
Detection Limit
(LD) Point 6 Point 7 Point 8 Point 9
Point10
16. Dissoled Metal - Quick silver (Hg) - ChromeHexavalen (Cr6+)
- Arsenic (As) - Cadmium (Cd)
- Copper (Cu) - Lead (Pb) - Zinc (Zn)
- Nickel (Ni)
mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l
0.001 0.003 0.012 0.001 0.008 0.008 0.05 0.05
0.0010 0.0030
- 0.0010 0.0153 0.0036 0.0075 0.0339
<LD <LD
- <LD <LD <LD <LD <LD
<LD <LD
- <LD <LD <LD <LD <LD
<LD <LD
- <LD <LD <LD <LD <LD
<LD <LD
- <LD <LD <LD <LD <LD
<LD <LD
- <LD <LD <LD <LD <LD
17. Total coliform MPN/100 ml
1000 - 1.8 1.8 17 240 240
*Decision of Minister of Environment Nr. 51 Year 2004 Annex I Seawater Quality Standard for Ports
3.1.4. Borlog and Soil Stratigraph
Based on the results of “Study on Technical and Environmental Reviews
on Shipping Routes, Sedimentation and Reclamation in Coastal Area in
Madura Strait”, in the waters area of Lamong River with seabed depth –
2.00 m LWS. Averagely in 13 m thickness from the seabed, the soil
layers are dominated with clay and very soft silt with N-SPT value
ranging 0 through 4. (See Figure 3.5).
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 15 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Su
mb
er
:
Ha
sil
Su
rve
y P
en
ye
lid
ikan
Tan
ah
Pekerj
aan
Kajia
n T
ekn
is d
an
Lin
gk
un
ga
n T
erh
ad
ap
Alu
r
Pe
lay
ara
n,
Se
dim
en
tas
i d
an
Tah
ap
an
Rekla
masi
di
Pe
sis
ir S
ela
t M
ad
ura
LA
PO
RA
N A
KH
IR
TU A
RA
KE
TE
RA
NG
AN
:
Ha
lam
an
: IV
- 2
2
Le
mb
ag
a P
en
elitia
n (L
EM
LIT
) - IT
S
PT
. (P
erse
ro
) P
ela
bu
ha
n In
do
ne
sia
III
PE
KE
RJA
AN
:
ST
UD
I A
NA
LIS
IS M
EN
GE
NA
I D
AM
PA
K L
ING
KU
NG
AN
PE
NG
EM
BA
NG
AN
PE
LA
BU
HA
N
TA
NJU
NG
PE
RA
K K
E A
RA
H M
UA
RA
KA
LI L
AM
ON
G D
AN
TE
LU
K L
AM
ON
G
Ga
mb
ar
:
Str
ati
gra
fi T
an
ah
di
Lo
ka
si
Stu
di
TU A
RA
No
me
r G
am
bar
: 4.4
KE
TE
RA
NG
AN
:P
T. (P
erse
ro
) P
ela
bu
ha
n In
do
ne
sia
III
0 0
5 2
11 14 17
13
11
26
18 19 20
18
28
22 2
7 30
0 10 1
8 10 1
4
14 15 2
0 22 25
24 2728
1
5 6
0 0 1 1
5
12
10
21 22 25
17
15 2
0 26 27 3
2
26 26
30
- 6
0
Ver
y S
oft
Cla
ily S
ilt
Soft
Cla
ily S
ilt
Har
d C
lail
y S
ilt
Med
ium
Cla
ily S
ilt
Sti
ff C
lail
y S
ilt
- 2
.00
- 2
.00
- 0
.40
EL
EV
AS
I (
mL
WS
)
TE
NG
GA
RA
BA
RA
T L
AU
T
- 6
5
- 7
025
20
15 10
5 0
- 5
0
- 4
5
- 4
0
- 3
5
- 3
0
- 2
5
- 2
0
- 1
5
- 1
0
- 5
- 5
5
BH
1B
H2
BH
3-
0.0
0
200 m
520 m
90 m
SP
TS
PT
SP
T
Fig
ure 3
.5
So
il S
tra
tig
ra
ph
in
La
mo
ng
Ba
y
Stu
dy o
n T
ech
nic
al
an
d E
nvir
on
men
tal
Revie
ws
on
Sh
ipp
ing
Ro
ute
s, S
ed
imen
tati
on
an
d R
ecla
ma
tio
n i
n C
oa
sta
l A
rea
in
Ma
du
ra S
tra
it,
20
01
SO
UT
H E
AS
T
EL
EV
AT
ION
(m
LW
S)
NO
RT
H W
ES
T
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 16 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
3.1.5. Hydrology and Hydro-Oceanography
3.1.5.1. Hidrology
Watershed
The rivers having estuary in Lamong Bay are Lamong River, Sememi River,
Branjangan River, Greges River and Anak River (Figure 3.6), detailed as follows :
Figure 3.6. Rivers having estuary in Lamong Bay Source : Watershed Map
A. Lamong River
Lamong River is under the control of Bengawan Solo Management Center.
Its upstream is in Kendeng Mountain, in Lamongan Regency and Mojokerto
Regency, while its downstream is in Gresik Regency and Surabaya City. It flows
into into Lamong Bay.The estuary of Lamong River is branced into two due to the
establishment of a small island in between the two branches. The delta slows the
river flow and therefore it is alleged that it is greatly potential to cause serious
sedimentation in that area.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 17 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 3.7. Watershed of Lamong River in the System of Bengawan Solo Managemenet Center
Source: Bengawan Solo Managemenet Center
The area of the watershed of Lamong River is is ± 720 m2. The length of Lamong
River is ± 92 km with 7 tributaries. Floods in Lamong River watershed always
present in wet season every year. Based on the Detailed Designs and
Environmental Impact Assessment concerning Lamong River in Gresik Regency,
2005, the largest floods or the highest puddles were in January and March 2004.
The puddled areas in Gresik Regency covered Cerme Sub-district and Duduk
Sampeyan Sub-district, Cermenlerek Village Gorekan Kidul Village with puddle
height ± 1,5 and puddled ± 600 Ha farm and settlement area as presented in
Figure 3.8.The contour of the flooded part is a relatively wife plain area in the
middle of Lamong River
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 18 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 3.8. Puddle Map of Lamong River Flood on 12 March 2004
Source : Study on Detailed Design and Environmental Impact Assessm,ent for Lamong River in
Gresik Regency, Year 2005
The angle of watershed is relatively high, averagely 0.0181. It enables the
water run into the river. The periphery of Laong River is 240 km with an average
watershed elevation of 44,53 meter. The model of water flows in Lamong Bay is
presented in Figure 3.10. The downstream area of Lamong River is utilized for
fishpon farming. The highest elevation in Lamong River is +0.18 meter over the
sea level.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 19 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 3.9. Plain Contour in the Midlle, where floods frequently happen
Figure 3.10. Lamong River Watershed Flow Direction
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 20 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 3.11. Lamong River Cross Section
Embankment under the
water
surface
Flood Flood
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 21 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
The average monthly water flow rate measured in Boboh Station (location of
AWLR of Lamong River) based on the data collected from the Detailed Design Study
and Environmental Impact Assessment of Lamong River in Gresik Regency, in year
2005, is presented in Table 3.12. The high water flow rate usually takes place from
November to April ranging from 22 m3/sec to 45 m3/sec, while the low water flow
rate does from May to October ranging from 3 m3/sec to 9 m3/sec. Based on the
aforementioned condition, it is found that the difference between the volume of
water flow during dry season and the one during wet season is very significant, it
even 15 times. In addition, it also indicates that there has been a serious damage in
the watershed as during the wet season the volume of water flows is maximal. This
is due to poor water precipitation.
Table 3.12. Average Monthly Water Flow in Lamong Bay in m³/det
Water Flow Rate
(m³/det)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
37 45 39 27 9 7 5 3 4 3 22 28
Source: Detailed Design Study and Environmental Impact Assessment of Lamong River in Gresik Regency, Year 2005,
B. Sememi River
Sememi River is in the South of Lamong River. It is a small river, in term of
hydrology there is no point, such as : water flow rate, etc., to analyze. It is highly
affected by the tide. The area surrounding its downstream is mainly utilized for
fishpond and salt pond. Its upstream is from Gunungsari Primary Channel, Babat
Jerawat Channel and South Sememi Channel.
C. Branjangan/ Kandangan River
Branjangan River is surrounded with fishponds and salt ponds, in some points there
are a few dwellings. The channel is mainly natural and not yet rip rapped. As it is a
small river, it is lack of hydrology and hydraulic measurement data.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 22 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
D. Greges/ Balong River
The channel is mostly riprapped that there is a much sediment in it. There
are alot of dwellings and factories construced along Greges River. The secondary
channels flowing into Greges River are Margomulyo Channel, Darmo Indah Channel,
Darmo Harapan Channel, Lontar Channel, Gadelsari Channel and Balongsari Channel.
E. Anak River
It is a natural channel with a lot of meanders. It is not only utilized as
drainage but also accessed by fisherman boats. Along the rivers sides, there are a lot
of dwelling and fishponds.
3.1.5.2. Hydro-Oceanography
A. Wind Direction and Speed
The results of analysis on the wind direction and speed for 10 years (2000-
2009) by Perak Meteorology, Climatology and Geo-physics Agency 1 Surabaya showed
that the wind had clear seasonal patterns as presented in Table 3.13. The analysis
on monthly wind direction and speed during the 10 (ten) years are presented in
Figure 3.12 and Figure 3.13. The West wind blows from November through
February in coincidence with the blow of North West monsoon wind. The East wind
blows from April through September almost in coincidence with the blow of South
East monsoon wind. The analysis on speed probability during the 12 months
(January – December) , it shows that the speed ranges 3 – 4 knots with the greatest
probability of 18/5% to the East, next 5-6 knots with probability of 9.25% to the
South East in 1-2 knots with probability of 6.91% to the North.
Referring to the data presented in Table 3.13., it shows that the most
dominant wind direction in the studied area is to the East, i.e. : 27,5 %, as the
average monthly wind direction during the 10 (ten) years (2000 – 2009). The greatest
frequency of winblow to the East is found in July with a percetange 56.63 %. The
least frequency of wind direction to North West is 0 % in August August, May, June
and September September, and South West is 0 % in July and September. The
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 23 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
complete data are presented in the windrose per month for 10 (ten) years (Figure
3.13 and 3.14). The windroses during the 10 (ten) years are presented in Figure 3.12.
The monthly windrose in the studied area is presented in monthly windrose.
Based on the wind direction data in certain wind speed interval with reference to
the windroses, it shows that the dominant wind direction from November through
Maret (Wet Season) is from West to North, while from April through October (Dry
Season) from East to South East.
Table 3.13. Wind Speed and Percentage
Wind Direction o (deg)
W N SW NE NW S SE E
Speed: 1-2 knots
102 230 37 81 50 74 58 122
Percentage (%) 3.06 6.91 1.11 2.43 1.50 2.22 1.74 3.66
Speed: 3-4 knots
245 299 25 118 130 91 491 616
Percentage (%) 7.36 8.98 0.75 3.54 3.91 2.73 14.7 18.5
Speed: 5-6 knots
28 8 7 1 8 22 308 178
Percentage (%) 0.84 0.24 0.21 0.03 0.24 0.66 9.25 5.35
Total 375 537 69 200 188 187 857 916
Percentage (%) 11.26 16.13 2.07 6.01 5.65 5.62 25.7 27.5 Source : Perak Meteorology, Climatology and Geo-physics Agency 1 Surabaya and Processing Results
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 24 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 3.12 Windrose Surabaya 2000-2009
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 25 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 3.13. Windroses January - June in Studied Area Year 2000 – 2009
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 26 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 3.14. Windroses July - December in Studied Area Year 2000 – 2009
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 27 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
B. Wave
Based on the resulted wind data during 10 years (2000-2009) supplied by
Perak Meteorology, Climatology and Geo-physics Agency Surabaya and by adopting
Gumbell Statistic Method, and wind speed parameter and fetch length, the wave
height H (m) and wave period T (s) for certain cycle can be predicted.
Table 3.14. Wave Prediction for 5-50 ear cycles based on wind data 2000-2009
C. Tide
The tidal movement is very important to identify for various purposes, inter
alia : determination of sea construction elevation and as input data for analyzing
the current patterns and sediment transportation by means of numerical model.
The calculation of tidal constant is based on data supplied by the Hydro-
Oceanography Service, Year 2012 for 365 days. The following table presents tidal
harmonic constants in the studied area in year 2012 as supplied by the Hydro-
Oceanography Service, i.e. : Tides in Karang Jamuang, Karang Kleta and Surabaya
Seaport.
Table 3.15. Tidal Harmonic Constants in Karang Jamuang
Tidal Constant M2 S2 N2 K2 K1 O1 P1 M4 MS4 Z0
Amplitude (cm) 5 8 - - 54 26 15 - - 110
360o-g 344 4 - - 43 101 41 - -
Source: Hydro-Oceanography Service, 2012
Cycle (Year)
Wave Height H (Meter)
Wave Cycle T (Second)
5 0.689 3.456
10 0.800 3.820
15 0.863 4.024
20 0.906 4.165
25 0.939 4.273
30 0.966 4.360
50 1.039 4.600
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 28 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Table 3.16. Tidal Harmonic Constants in Karang Kleta
Tidal Constant Tidal constant M2 S2 N2 K2 K1 O1 P1 M4 MS4 Z0
Amplitude (cm) Amplitude (cm) 59 29 16 5 45 27 14 - - 180
360o-g 360o-g 41 30 69 29 64 100 41 - - -
Source: Hydro-Oceanography Service, 2012
Table 3.17. Tidal Harmonic Constants in Surabaya Seaport
Tidal Constant Tidal Constant M2 S2 N2 K2 K1 O1 P1 M4 MS4 Z0
Amplitude (cm) Amplitude (cm) 44 26 9 8 47 28 14 - - 150
360o-g 360o-g 31 20 49 18 50 91 47 - - -
Source: Hydro-Oceanography Service, 2012
Where : A : amplitude
g : phase diference
M2 : main component of the moon (semi diurnal)
S2 : main component of the sun (semi diurnal)
N2 : eliptic component of the moon
K2 : component of moon-sun (semi diurnal)
K1 : component of moon-sun (diurnal)
O1 : main component of the moon (diurnal)
P1 : main component of the sun (semi diurnal)
M4 : tidal component of shallow water (quarter – diurnal)
MS4 : tidal component of shallow water (compound tide)
Based on the results of calculation of the main tidal constants, the value of
Formzhal (F) can be identified to determine the tide in the studied area (Defant,
1958). The value of Formzhal is determined by comparing the total amplitude of
components K1 and O1 and the total components of M2 and S2, or in the following
equation :
2S2M
1O1KF
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 29 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
The tidal types are then derived from the resulted Formzhal value. The
classification of Formzhal values is as follows :
F > 3,00 Diurnal Tide
1,50 – 3,00 Mixed, Diurnal Dominant Tide
0,25 – 1,49 Mixed, Semi Diurnal Dominant Tide
F < 0,25 Semi Diurnal Tide
Based on the results of calculation by using the main tidal constants, the
Formzhal constant for Karang Jamuang is 6.15, Karang Kleta is 0.82 and Surabaya
Seaport is 1.07. Based on the Formzhal constant, the tidal type in Karang Jamuang
is Diurnal Tide, in Karang Kleta is Mixed Semi Diurnal Dominant Tide in the sense
that in one day there are 2 high tides and 2 low tides with different heights, and in
Surabaya Port is Mixed Semi Diurnal Dominant Tide.
D. Water Current Speed and Direction
The technical and environmental study on the shipping routes,
sedimentation and reclamation in the coastal area in Madura Strait in 2001, also
covered measurement on shipping routes around the project site. The results of
the measurement are presented in Table 3.18.
Table 3.18. The Results of Maximum and Minimum Speed Measurement Year 2001
Observation Points
Max/Min
Neap Tide Spring Tide
Speed (m/det)
Direction
()*
Speed (m/det)
Direction
()*
AR1 Max 0,50 6 0,45 10
Min 0,04 140 0,03 170
AR2 Max 0,70 290 0,52 350
Min 0,05 190 0,01 300
AR3 Max 0,80 340 0,45 330
Min 0,05 245 0,01 340
AR4 Max 0,62 150 0,55 195
Min 0,01 180 0,02 235
AR5 Max 0,65 320 0,75 290
Min 0,04 130 0,05 350
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 30 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
The results of the measurements show that the maximum current in the
shipping routes is 0.62 m/sec. In other occasions, the current speed in the shipping
routes can reach 1.0 m/sec, while in shallow waters, the average current speed is
relatively small, i.e. : 0.1 m/sec.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 31 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 3.15. Water Current Speed and Direction Measurement Points
Around Madura Strait, 2001 Source : Study on Technical and Environmental Reviews on Shipping Routes, Sedimentation and Reclamation in Coastal Area in Madura Strait, 2001
arus laut
Keterangan :
Lokasi pengukuran
U
AR1
AR4
AR5
AR3
AR2
Water Current
measurement points
Remarks
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 32 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
The current measurement is based not only on the results of survey in year 2001 in 5
observation points along the West Surabaya Shipping Routes , but also the results of
results of measurement in year 2012 by Surabaya Container Terminal. The results of
the measurement show that the current direction is dominantly headed to South
East with speed of 30-40 cm/s (See Figure 3.16). The water current data are then
utilized for calibration purposes and numerical modelling.
Figure 3.16. Currentrose Around Site of Surabaya Container Terminal (TPS 2012)
E. Bathymetry
The Multipurpose terminal project site is in Lamong Bay, an important of
Maudura Strait. The area comprises shallow water with 0.5–2 m depth and is greatly
affected by the tide. (Figure 3.17). During low tide, the area partly looks as seabed
with mud and sand spread. Accordingly, in some points, it is not accessible by the
traditional fishermen. The West Surabaya Shipping Routes with 8 – 13 m depth are
right in front of the project site and some rivers flow into Lamong Bay. Accordingly,
it is very potential to lead to serious sedimentation as observed from the state of
condition of the muddy soil structure surrounding the project site.
The bathymetry of the waters surrounding the project site points to some
references, i.e. : Survey Year 2009, West Surabaya Shipping Routes document year
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 33 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
2010 and Indonesian Coastal Map Year 1993. The supplied data are required for
analyzing the hydro-oceanography models of current, sedimentation, sediment
spread, and increase of water elevation in the estuaries of rivers flowing into
Lamong Bay.
Figure 3.17 Bathymetry Surrounding Project Site in Lamong Bay
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 34 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
F. Sediment Spread
The analysis of sediment in Lamong Bay is based on the resulted sampling
from some points in year 2010, Seabed Sediment Spread Map, Sheet 1608, Year
1998, analysis of grains as samples of seabed sediments year 2005, and
measurement of floating sediment year 2008. The bed sediment gradation as
resulted from the analysis on sample taken in the shipping routes in Lamong Bay is
resented in Table 3.19.
Table 3.19. Results of Analysis on Bed Sediment in Studied Area
Sediment Properties Locations of Samples
S1 S2 S3
Specific Gravity 2.673 2.653 2.674
Finer #200 (%) 19.88 84.15 79.36
Gravel (%) 38.1 2.8 1.1
Sand (%) 42.0 13.1 19.6
Silt (%) 19.9 65.2 56.0
Clay (%) 0.0 18.9 23.3
Source : Study on Technical and Environmental Reviews on Shipping Routes, Sedimentation and Reclamation in Coastal Area in Madura Strait, 2001
The concentration of floating sediments taken from the shipping routes in
Lamong Bay in year 2001 are presented as follows :
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 35 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Tabel 3.20 Results of Analysis on Floating Sediment in Studied Area
Source :Study on Technical and Environmental Reviews on Shipping Routes, Sedimentation and Reclamation in Coastal Area in Madura Strait, 2001
The concentration of average floating sediment in the above table
relatively low both during neap tide, i.e. : 49.45 mg/lt and spring tide. I.e. : 45.91
mg/lt. The sediment concentration in Lamong Bay is relatively low as the samples
were taken in September through October year 2000, during dry season.
The samples of floating sediment were taken from 6 sampling points in
Lamong Bay in February 2008 in the line with Study of Efffect of Waterfront Cilty
Reclamation Plan to Sedimentation in Lamong Bay. The results of analysis in the
saling points , it shows that the average floating sediment is 361 mg/lt. This
concentration is big enough as the samples were taken during wet season.
The sediment analysis is not only based on results of measurements in the
previous (1998, 2001, 2005 and 2008), but also Seabed Sediment Spread Map,
Sheet 1608, Surabaya, as presented in Figure 3.18 (Astjario, and
associates.,1998) showing that that the studied area comprises some surface
sediment layers, i.e. : sand, sandy mud and silty sand. Based on the sediment
spread in the studied area, it shows that sand layer is the most dominant (>50%) of
the studied area and mainly spread in the West and South parts of the studied
area. The rest comprises sandy mud and silty sand (<50%)of the studied area. The
silty sand is found in the East-North and West and East part of the studied area.
The sandy mud spreads in the middle of East side.
Nr. Locations
Floating Sediment Content (mg/l)
Neap Tide Spring Tide
0.2 d 0.6 d 0.8 d 0.2 d 0.6 d 0.8 d
1 S 1 38.71 95.97 88.97 45.29 81.27 121.94
2 S 2 36.47 23.94 72.31 26.11 27.88 28.14
3 S 3 21.63 22.47 44.59 24.57 26.11 31.92
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 36 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
contoh sedimenLokasi pengambilan
Keterangan:
U
S1
S2
S3
Based on the results of analysis on grains against the sample of seabed
sediment (Report of Sedimentation Study – Suramadu Bridge, 2005), it shows that
the sediment in the studied area consists of silt to sandy silt.
The samples of sediment cores from that sampling point show minimally 2
m thickness from the seabed, there is no significant change of grain size. The
difference shown in the Seabed Sediment Spread Map (Astjario, and Associates,
1998) shows that from year 1998 through 2005, there had been changes in the
seabed sediment spread due to sedimentation and erosion.
Figure 3.18. Seabed Sediment and Floating Sediment Sampling Points Source : Study on Technical and Environmental Reviews on Shipping Routes, Sedimentation and Reclamation in Coastal Area in Madura Strait, 2001
Sediment Sampling
Points
Remarks
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 37 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 3.19. Seabed Sediment Spread in Madura Strait Source : Astjario, and Associates,1998
In addition to the aforementioned sediment spread data, it is also provided with
numeric modelling. The methods adopted in the modelling comprises both primary
and secondary data on current, sedimentation and floating sediment spread (water
quality) around the reclamation site as input to the model. The models are
utilized for simulating the current, sedimentation and floating sediment spread by
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 38 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
means of a finite element-based software and prepared in some model scenarios.
In initial scenario concerns about existing models called Model 1 and Model 2 under
post-construction condition.
The results of current pattern modeling during high tide and low tide under pre-
construction condition are presented in Figure 3.20.
(a) High Tide Condition (b) Low Tide Condition
Figure 3.20 Typical Current Pattern during High Tide (a) and Low Tide (b)
As shown in the aforementioned Figure 3.20 (a), under high tide condition,
the current dominantly flows to the coast with average speed range of 0 – 0,05
m/sec. The low speed is distributed along the coast in Lamong Bay from Lamong
River until Branjangan River (represented in purpple in Figure 3.20 (a)), while
along the West Surabaya Shipping Routes the speed varies and ranges 0,3 m/sec to
> 0,5 m/sec (green to red). In the mean time, under low tide condition, the speed
is relatively low when compared to the one during high tide condition as shown in
Figure 3.20 (b) and in the following graph in Figure 3.21.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 39 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 3.21 Typical Average Current Speed in Estuaries Close to Lamong Bay
The average water elevation in rivers surrounding Lamong Bay is presented in
Figure 3.22 below.
Figure 3.22 The Average Water Elevation in rivers surrounding Lamong Bay
0.00
0.02
0.04
0.06
0.08
0.10
0.12
0.14
0.16
0.18
0.20
Lamong Sememi Branjangan Manukan Krembangan Kali mas Mireng Glagah lanjang
Ke
cep
atan
Aru
s (m
/de
t)
Muara Sungai
kec arus pasang
kec arus surut
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
Lamong Sememi Branjangan Manukan Krembangan Kali Mas Mireng Glagah Lanjang
Ele
vasi
Mu
ka A
ir (m
)
Muara Sungai
Curr
ent
Speed (
m/s
)
Estuaries
Estuaries
Wate
r Ele
vati
on
High tide
Low tide
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 40 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 3.23 shows the sedimentation patterns prior to construction
activities. It shows that the sediment is concentrated in estuaries of rivers. The
thickest sediment is found in Lamong River ( 20 cm). Other rivers do not bring
high concentration sediment, as they serve as urban drainages and flow water only
in wet season.
Figure 3.23 Sedimentation Pattern for 1 Month The results of the model have been calibrated in comparison between the
modeling results and current measurement data as shown in Figure 3.24.
Figure 3.24. Calibration of Current Model with Current Measurement Data in 2012
-0.5
-0.4
-0.3
-0.2
-0.1
0
0.1
0.2
0.3
0.4
-0.4 -0.3 -0.2 -0.1 0 0.1 0.2 0.3 0.4
ukur
sm 0.40 Mann 10
Bar
at
Timu
r
Utara
SelatanSOUTH
NORTH
WE
ST
EA
ST
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 41 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
3.1.6. Transportation Components
The traffic data employed in this study are primary traffic counting survaey
data collected from some locations assumed to be influential to the project, i.e. :
Romokalisari Crossroad
Margomulyo Junction
In addition to those locations, the traffic counting survey was also conducted
in tributaries analoguous to the ones surrounding Nilam Terminal in Tanjung Perak
Port. The survey was to count the number of vehicles accessing (in and out) the
gates of Nimal Terminal in Tanjung Perak Port. Some of the survey points are
presented in Figure 3.25 through Figure 3.28.
Figure 3.25. Traffic CountingSurvey Points Source : Google Earth and Observation Result
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 42 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 3.26. Survey Point on Jalan Nilam Timur Source : Google Earth and Observation Result
Figure 3.27. Survey Point in Margomulyo Junction Source : Google Earth and Observation Result
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 43 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 3.28. Survey Point in Romokalisari Crossroad Source : Google Earth and Observation Result
Survey was conducted for 12 hours on 06 September 2012 to count the
number of moving vehicles (any and all kinds). The Survey Form utilized is
presented in Figure 3.29.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 44 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 3.29. Traffic Survey Form
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 45 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
3.1.7. Traffic Geometric and Volume Data
In order to analyze the road performance, some components to be detailed
comprise : Road Geometry (C), Traffic Volume (Q), and Degree of Saturation (DS).
The lattest represents the road performance.
Margomulyo Junction
In order to caunt the road performance, a traffic counting survey was
conducted in Jalan Margomulyo-Greges Junction. The survey points were on Jalan
Raya Margomulyo, Jalan Raya Tambak Oso Wilangun and Jalan Raya Greges. The
following describes the initial traffic condition resulted from traffic caounting survey
conducted surrounding Margomulyo Area.
Jalan Raya Tambak Oso Wilangun that is in the North Surabaya Utara is an
arterial road connecting Gresik Regency and Surabaya City, Margomulyo Junction
as well as Romokalisari Crossroad, where most of the vehicles accessing this road
are from out of town, particulary heavy vehicle (trucks, semi trailers etc.) and
motorcycles. The geometric conditions of the roads are presented in the following
figures (Jalan Tambak Oso Wilangon, in Figure 3.30., Jalan Greges, in Figure 3.31
and Jalan Margomulyo, in Figure 3.32.)
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 46 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 3.30. Cross Section of Jalan Tambak Oso Source: Survey Result
Figure 3.31. Cross Section of Jalan Greges Source: Survey Result
Figure 3.32. Cross Section of Jalan Margomulyo Source: Survey Result
Margo Mulyo Junction (West)
Margo Mulyo Junction (East)
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 47 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
The data on traffic volume during the peak time collected from th traffic
counting on Margomulyo Juntion are presented in Table 3.21.
Table 3.21. Results of Traffic Counting during Peak Hour in Margomulyo Junction Margomulyo Junction
PHV MAX LV HV MC
West-East Direction 810.6 89 2 1,439
West-South Sirection 642.3 101 126 755
East-South Direction 2,659.8 157 101 4,743
South East Direction 1,424.1 145 2 2,553
South-West Direction 3,182.8 207 81 5,741
South-South Direction 237.9 68 48 215
Source: Result of Traffic Counting Survey in Margomulyo Junction
Romokalisari Crossroad
In order to caunt the road performance in Romokalisari Area, a traffic
counting survey was conducted in Jalan Romokalisari – Toll Road Rocssroad. The
survey points were on Jalan Romokalisari and Surabaya-Gresik Toll Road. The
following Figure 3.33 – 3.36.describes the initial traffic condition resulted from
traffic counting survey conducted surrounding Romokalisari Area.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 48 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 3.33. Cross Section of Jalan Romokalisari (East) Source : Survey Result
Figure 3.34. Cross Section of Jalan Romokalisari (North) Source : Survey Result
Romokalisari Crossroad (East)
Romokalisari Crossroad (North)
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 49 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 3.35. Cross Section of Jalan Romokalisari (West) Source : Survey Result
Figure 3.36. Cross Section of Jalan Romokalisari (South) Source : Survey Result
The data on traffic volume during the peak time collected from th traffic
counting on Romokalisari Crossroad are presented in Table 3.22.
Table 3.22. Results of Traffic Counting during Peak Hour in Romokalisasi
Crossroad
Romokalisari Crossroad
PHV MAX LV HV MC
North-East Direction 577.1 437 52 145
North-South Direction 3,481.9 166 148 6,247
Romokalisari Crossroad (West)
Romokalisari Crossroad (South)
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 50 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Romokalisari Crossroad
North-West Direction 40.5 11 0 59
East-South Direction 72.5 7 25 66
East-West Direction 1,695.3 143 16 3,063
South-West Direction 461.4 329 88 36
South-East Direction 42.6 7 17 27
Source: Result of Traffic Counting Survey in Romokalisari Crossroad
3.1.8. Nilam Area
In order to count the fleets of vehicles, analoguous to the activities in
multipurpose terminal in Nilam Area, a traffic counting survey was also conducted
in tributaries analoguous to the ones surrounding Nilam Terminal on Jalan Nilam
Barat and Jalan Nilam Timur. The survey point was on Jalan Raya Nilam during
peak hours.
The results of survey was to count the number of vehicles accessing (in and
out) the gates of Nimal Terminal in Tanjung Perak Port are presented in Table.23.
Table 3.23. Results of Traffic Counting during Peak Hour on Jalan Raya Nilam
Source: Result of Traffic Counting Survey during Peak Hour on Jalan Raya Nilam
The comparisions between incoming vehicles and outgoing vehicles on Jalan Raya
Nilam are presented in Figure 3.37 and Figure 3.38.
Jalan Raya Nilam
West Nilam PHV MAX LV MHV LB LT MC
South-North Direction 115.4 27 0 0 15 98
North-South Direction 200.2 49 6 0 18 186
East Nilam PHV MAX LV MHV LB LT MC
Total 2-Way 357.4 25 16 0 163 33
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 51 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 3.37. Graph of Vehicles Incoming into Jalan Nilam Barat Source: Survey Result
Figure 3.38. Graph of Vehicles Outgoing from Jalan Nilam Barat Source: Survey Result
05
101520253035404550
06
.00
-06
.15
06
.45
-07
.00
07
.30
-07
.45
08
.15
-08
.30
09
.00
-09
.15
09
.45
-10
.00
10
.30
-10
.45
11
.15
-11
.30
12
.00
-12
.15
12
.45
-13
.00
13
.30
-13
.45
14
.15
-14
.30
15
.00
-15
.15
15
.45
-16
.00
16
.30
-16
.45
17
.15
-17
.30
Nu
mb
er o
f V
ehic
le
Time
Nilam Barat (masuk)
Q
05
101520253035404550
06
.00
-06
.15
06
.45
-07
.00
07
.30
-07
.45
08
.15
-08
.30
09
.00
-09
.15
09
.45
-10
.00
10
.30
-10
.45
11
.15
-11
.30
12
.00
-12
.15
12
.45
-13
.00
13
.30
-13
.45
14
.15
-14
.30
15
.00
-15
.15
15
.45
-16
.00
16
.30
-16
.45
17
.15
-17
.30
Nu
mb
er o
f V
ehic
le
Time
Nilam Barat (keluar)
Q
West Nilam (Incoming)
West Nilam (Outgoing)
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 52 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
3.1.9. Analysis on Traffic Performance
The results of survey are used as a basis for measuring the traffic
performance in the studied area. The traffic performance is measured in terms of
performance in non-traffic-lighted junction/crossroad and the one on arteial road.
The parameter adopted in the analysis is Degree of Saturation (DS) and Level of
Service (LoS). The following Table 3.24. through Table 3.26. present the results of
the traffic performance survey.
Table 3.24. Result of Analysis on Performance of Margomulyo Junction
Year Vehicle Q of Total
Traffic emp Q C DS
Classification (Vhcl/hr)
(smp/hr)
1 2 3 4 5 6 7
2012 LV 767 1.00 767 5,124 1,748
HV 360 1.30 468
MC 15,445 0.50 7,723
Σ 16,572 Σ 8,958
Source : Survey Result
Table 3.25. Result of Analysis on Performance of Romokalisari Crossroad
Year Vehicle Q of Total
Traffic emp Q C DS
Classification (Vhcl/hr)
(smp/hr)
1 2 3 4 5 6 7
2012 LV 1,100 1.00 1,100 6,971 0.914
HV 346 1.30 450
MC 9,643 0.50 4,822
Σ 11,089 Σ 6,371
Source : Survey Result
In addition to the above traffic performance, the performance of arteria
road – Jalan Tambak Osowilangon can be measured based on cross data. The
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 53 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
following tables present te performance of Jl. Tambak Osowilangon in front of the
project site.
Table 3.26. Results of Analysis on Performance of Jalan Tambak Oso (4/2 UD)
Year Vehicle Q of Total
Traffic emp Q C DS
Classification (Vhcl/hr)
(smp/hr)
1 2 3 4 5 6 7
2012 MC 8,488 0.50 4,244 6,092 0.807
LV 375 1.00 375
MHV 40 1.30 52
LB 13 1.50 20
LT 114 2.00 228
Σ 9,030 Σ 4,919
Source : Survey Result
The above table shows that in year 2012, during peak hours the arterial road
and juction/crossroad are densely jammed with degree of saturation reaching 0.8.
TRAFFIC DATA:
1. Nilam Gate 2/2 UD (UnDivided)
The Survey is supposed to identify the volume of traffic headed to
particular destination, i.e. : Jalan Nilam that is divided into two : West Nilam and
East Nilam, each with South-North direction (headed to Shipyard) and North-
South direction (leaving Shipyard) . The results of the survey on Jalan Nilam are
presented in Table 3.27. and Table 3.28.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 54 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Table 3.27. Results of Survey on Jalan Nilam Barat ((Entry) 2/2 UD
1 2 3 4 5A 5B 6A 6B 7A 7B 7C 8
06.00-06.15 33 4 0 2 0 0 1 0 3 8 0 2
06.15-06.30 23 1 0 0 0 0 0 0 0 0 1 0
06.30-06.45 20 3 0 0 0 0 3 0 0 0 1 1
06.45-07.00 12 3 0 0 0 0 0 0 0 0 0 0
07.00-07.15 17 1 0 0 0 0 1 0 0 0 0 0
07.15-07.30 14 4 0 2 0 0 1 0 0 0 0 2
07.30-07.45 14 0 0 0 0 0 0 0 0 0 1 0
07.45-08.00 24 3 0 1 0 0 3 1 2 0 1 0
08.00-08.15 27 3 0 0 0 0 2 1 0 0 2 1
08.15-08.30 11 5 0 1 0 0 1 0 0 0 2 2
08.30-08.45 15 3 0 6 0 0 0 0 0 0 6 1
08.45-09.00 13 5 0 2 0 0 3 0 0 0 4 5
09.00-09.15 18 6 1 1 0 0 3 3 1 0 0 3
09.15-09.30 16 3 0 0 0 0 0 2 0 0 4 0
09.30-09.45 13 5 0 2 0 0 0 1 2 0 0 2
09.45-10.00 17 3 0 0 0 0 3 1 0 0 2 2
10.00-10.15 15 4 0 4 0 0 1 0 0 0 3 1
10.15-10.30 11 3 0 0 0 0 2 0 0 0 0 3
10.30-10.45 18 6 0 5 0 0 0 0 0 0 0 0
10.45-11.00 23 0 0 0 0 0 1 0 1 0 1 0
11.00-11.15 21 3 0 3 0 0 3 0 0 0 1 0
11.15-11.30 25 3 0 3 0 0 0 1 1 0 2 1
11.30-11.45 15 1 0 2 0 0 2 2 0 0 0 1
11.45-12.00 11 2 0 1 0 0 1 3 0 0 1 0
12.00-12.15 33 4 0 2 0 0 1 0 3 0 0 2
12.15-12.30 23 1 0 0 0 0 0 0 0 0 1 0
12.30-12.45 20 3 0 0 0 0 3 0 0 0 1 1
12.45-13.00 12 3 0 0 0 0 0 0 0 0 0 0
13.00-13.15 17 1 0 0 0 0 1 0 0 0 1 0
13.15-13.30 14 4 0 2 0 0 1 0 0 0 1 2
13.30-13.45 14 0 0 0 0 0 0 0 0 0 1 0
13.45-14.00 24 3 0 1 0 0 3 1 2 0 1 0
14.00-14.15 27 3 0 0 0 0 2 1 0 0 2 1
14.15-14.30 11 5 0 1 0 0 1 0 0 0 2 2
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 55 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
1 2 3 4 5A 5B 6A 6B 7A 7B 7C 8
14.30-14.45 15 3 0 6 0 0 0 0 0 0 6 1
14.45-15.00 13 5 0 2 0 0 3 0 0 0 4 5
15.00-15.15 18 6 1 1 1 0 3 3 1 0 0 3
15.15-15.30 16 3 0 0 0 0 0 2 0 0 4 0
15.30-15.45 13 5 0 2 0 0 0 1 2 0 0 2
15.45-16.00 17 3 0 0 0 0 3 1 0 0 2 2
16.00-16.15 15 4 0 4 0 0 1 0 0 0 3 1
16.15-16.30 11 3 0 0 0 0 2 0 0 0 0 3
16.30-16.45 18 6 0 5 0 0 0 0 0 0 0 0
16.45-17.00 23 0 0 0 0 0 1 0 1 0 1 0
17.00-17.15 21 3 0 3 0 0 3 0 0 0 1 0
17.15-17.30 25 3 0 3 0 0 0 1 1 0 2 1
17.30-17.45 15 1 0 2 0 0 2 2 0 0 0 1
17.45-18.00 11 2 0 1 0 0 1 3 0 0 1 0
Source : Survey Result
Table 3.28. Results of Survey on Jalan Nilam Timur (Exit) 2/2 UD
1 2 3 4 5A 5B 6A 6B 7A 7B 7C 8
06.00-06.15 6 3 0 3 0 0 6 13 10 0 20 0
06.15-06.30 8 7 0 4 0 0 3 14 9 0 22 0
06.30-06.45 11 4 0 1 0 0 5 7 12 0 17 0
06.45-07.00 8 3 0 0 0 0 2 6 14 0 19 0
07.00-07.15 9 3 0 3 0 0 6 4 7 0 19 0
07.15-07.30 12 6 0 2 0 0 3 1 4 0 13 0
07.30-07.45 14 7 0 5 0 0 1 13 6 0 18 0
07.45-08.00 16 3 0 2 0 0 0 16 8 0 21 0
08.00-08.15 17 11 0 1 0 0 3 5 10 0 16 0
08.15-08.30 21 9 0 - 0 0 5 0 8 0 18 0
08.30-08.45 17 7 0 2 0 0 2 6 12 0 15 0
08.45-09.00 18 11 0 1 0 0 0 4 7 0 9 0
09.00-09.15 17 9 0 1 0 0 3 4 10 1 17 0
09.15-09.30 32 2 0 0 0 0 1 2 6 0 18 0
09.30-09.45 28 8 0 1 0 0 1 5 9 1 22 0
09.45-10.00 29 7 0 2 0 0 0 1 9 1 7 0
10.00-10.15 31 4 0 1 0 0 0 9 4 1 24 0
10.15-10.30 30 4 1 4 0 0 0 7 7 1 1 0
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 56 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
1 2 3 4 5A 5B 6A 6B 7A 7B 7C 8
10.30-10.45 31 3 1 1 0 0 0 3 5 0 17 0
10.45-11.00 17 5 0 1 0 0 2 4 13 2 18 0
11.00-11.15 19 7 0 5 0 0 3 3 8 0 9 1
11.15-11.30 19 6 0 1 0 0 1 0 4 0 19 0
11.30-11.45 19 5 0 0 0 0 2 1 11 0 13 0
11.45-12.00 5 0 0 2 0 0 0 0 2 0 7 1
12.00-12.15 25 8 0 3 0 0 0 0 6 0 15 1
12.15-12.30 22 6 0 1 0 0 0 0 5 0 5 0
12.30-12.45 33 4 0 1 0 0 2 2 2 0 9 1
12.45-13.00 40 5 0 3 0 0 2 0 7 2 8 1
13.00-13.15 31 3 0 1 0 0 00 0 4 1 10 0
13.15-13.30 19 6 0 4 0 0 2 1 9 1 9 0
13.30-13.45 15 3 0 0 0 0 0 0 6 0 13 1
13.45-14.00 13 4 0 0 0 0 3 2 7 1 10 0
14.00-14.15 30 12 0 2 0 0 1 0 9 0 22 0
14.15-14.30 35 14 0 4 0 0 1 0 8 0 26 1
14.30-14.45 37 11 0 2 0 0 2 1 7 1 23 0
14.45-15.00 12 3 0 0 0 0 1 0 3 0 18 0
15.00-15.15 17 7 0 1 0 0 0 2 6 0 21 0
15.15-15.30 17 6 0 0 0 0 3 0 3 2 16 0
15.30-15.45 23 3 0 0 0 0 0 1 7 0 12 0
15.45-16.00 21 2 0 2 0 0 0 2 6 0 19 0
16.00-16.15 23 4 0 1 0 0 2 0 8 0 10 0
16.15-16.30 31 6 0 3 0 0 1 0 13 1 12 0
16.30-16.45 22 4 0 1 0 0 1 0 6 1 16 0
16.45-17.00 27 3 0 3 0 0 0 0 7 0 21 0
17.00-17.15 23 2 0 3 0 0 0 0 11 0 18 1
17.15-17.30 12 1 0 2 0 0 0 0 5 0 16 0
17.30-17.45 17 2 0 2 0 0 0 1 7 0 8 0
17.45-18.00 8 3 0 0 0 0 3 0 4 0 14 0
Source: Survey Result
2. Margomulyo Junction
The survey is supposed to identify the volume traffic pasing the surveyed
area, i.e. : Margomulyo Junction. In this junction, there are 6 traffic movements.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 57 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
The results of the survey in Margomulyo crossroad are presented in Table 3.29 –
Table 3.34.
Table 3.29. Results of Survey in Margomulyo Junction 1
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
06.00-06.15 279 4 21 4 0 2 2 1 3 0 11 0
06.15-06.30 461 4 24 1 0 1 1 2 0 0 5 2
06.30-06.45 709 2 32 3 0 0 0 0 0 1 10 4
06.45-07.00 938 5 30 7 0 0 1 0 1 1 9 9
07.00-07.15 896 1 27 3 0 2 2 1 0 0 8 9
07.15-07.30 1112 5 30 4 0 0 1 4 0 0 10 11
07.30-07.45 1172 1 35 8 0 0 5 6 0 1 12 5
07.45-08.00 1412 2 30 5 0 0 4 6 4 0 14 7
08.00-08.15 1047 5 26 6 0 0 7 4 2 0 21 2
08.15-08.30 770 3 30 9 0 1 12 13 1 0 24 1
08.30-08.45 672 4 44 9 1 1 11 16 2 0 34 2
08.45-09.00 514 4 46 16 0 0 3 24 3 0 35 1
09.00-09.15 385 2 22 14 0 1 7 14 1 0 36 1
09.15-09.30 329 1 29 14 0 0 14 15 6 2 39 2
09.30-09.45 341 3 27 13 0 3 12 12 4 0 44 1
09.45-10.00 329 2 34 18 0 1 10 15 5 2 33 1
10.00-10.15 315 1 27 10 0 0 12 22 6 0 36 0
10.15-10.30 230 5 25 19 0 0 34 21 3 2 44 1
10.30-10.45 267 3 35 11 0 0 14 15 3 1 40 4
10.45-11.00 257 4 26 13 0 0 16 13 9 1 44 1
11.00-11.15 256 6 24 18 0 0 25 13 6 3 33 3
11.15-11.30 265 0 33 18 1 0 22 21 6 0 35 0
11.30-11.45 278 0 27 11 0 0 25 26 20 1 54 0
11.45-12.00 223 2 23 16 0 0 18 22 10 0 34 0
12.00-12.15 250 1 32 10 0 0 9 23 8 0 35 1
12.15-12.30 265 3 31 11 0 0 12 15 9 0 32 2
12.30-12.45 266 2 20 14 0 0 12 14 3 0 11 0
12.45-13.00 230 3 21 12 0 0 13 16 4 0 17 1
13.00-13.15 239 3 36 10 0 0 7 11 3 0 12 2
13.15-13.30 273 1 42 17 0 0 19 23 6 0 24 2
13.30-13.45 255 5 46 11 0 0 11 17 4 2 25 1
13.45-14.00 327 0 43 20 0 0 27 27 7 1 45 1
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 58 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
14.00-14.15 287 0 26 16 0 0 21 24 5 0 27 1
14.15-14.30 308 0 27 20 0 0 20 26 2 0 31 1
14.30-14.45 340 3 36 11 0 0 21 26 10 0 36 1
14.45-15.00 318 2 31 10 0 0 18 14 3 0 28 0
15.00-15.15 395 2 34 25 0 0 22 24 4 0 39 1
15.15-15.30 403 2 37 20 0 0 15 18 10 0 43 1
15.30-15.45 457 2 36 21 0 1 22 26 4 1 57 0
15.45-16.00 478 2 35 19 0 0 25 32 1 2 45 0
16.00-16.15 613 4 40 18 0 2 19 20 1 0 44 2
16.15-16.30 718 2 50 17 0 0 23 15 1 1 23 0
16.30-16.45 688 2 46 20 0 0 22 20 5 0 23 0
16.45-17.00 796 9 27 16 0 0 21 15 6 1 20 0
17.00-17.15 634 2 22 13 0 0 17 11 4 0 26 0
17.15-17.30 587 1 29 8 0 0 15 22 1 1 22 0
17.30-17.45 624 9 34 9 0 0 9 11 1 1 34 0
17.45-18.00 520 2 22 10 0 0 8 13 0 0 13 0
Source : Survey Result
Table 3.30. Results of Survey in Margomulyo Junction 2
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
06.00-06.15 7 0 0 2 0 0 12 0 0 5 3 0
06.15-06.30 8 0 1 4 0 2 4 0 1 2 4 0
06.30-06.45 11 0 4 2 0 2 1 0 0 0 0 0
06.45-07.00 26 0 2 4 0 0 5 0 3 0 3 0
07.00-07.15 21 1 5 3 0 0 5 0 5 0 1 0
07.15-07.30 44 2 5 3 0 0 8 0 1 1 0 0
07.30-07.45 57 1 1 4 1 1 6 0 0 0 1 2
07.45-08.00 59 2 19 9 0 0 7 1 1 0 3 0
08.00-08.15 55 1 14 7 1 1 10 0 4 0 3 0
08.15-08.30 45 2 14 8 2 1 22 0 8 1 2 0
08.30-08.45 53 5 16 5 1 0 25 0 6 0 4 2
08.45-09.00 20 3 8 1`5 0 0 15 0 3 3 4 0
09.00-09.15 24 5 10 11 2 1 16 0 2 0 2 0
09.15-09.30 19 1 8 10 1 0 23 0 7 0 2 1
09.30-09.45 34 3 6 15 1 0 5 0 2 0 5 0
09.45-10.00 19 2 7 13 1 0 23 0 6 4 0 0
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 59 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
10.00-10.15 17 3 7 10 0 0 17 0 5 0 0 0
10.15-10.30 24 2 5 7 0 0 27 0 4 0 4 0
10.30-10.45 18 1 10 15 0 0 12 0 4 0 5 0
10.45-11.00 20 2 11 15 0 0 15 0 4 1 2 0
11.00-11.15 19 6 15 11 0 0 17 0 7 1 9 0
11.15-11.30 9 4 4 12 0 0 13 0 4 1 4 0
11.30-11.45 12 3 7 14 0 0 14 0 5 0 2 0
11.45-12.00 14 1 9 11 0 0 14 0 3 2 2 0
12.00-12.15 15 0 6 5 0 0 11 0 7 0 2 0
12.15-12.30 12 2 7 5 0 1 5 0 2 0 0 0
12.30-12.45 15 3 7 4 1 0 11 0 4 0 0 0
12.45-13.00 12 4 1 9 0 0 9 0 0 2 2 0
13.00-13.15 10 3 11 10 0 0 14 0 3 0 2 0
13.15-13.30 14 3 9 8 0 1 5 0 1 0 1 0
13.30-13.45 11 1 16 16 1 1 11 0 1 3 2 0
13.45-14.00 7 0 11 11 0 0 14 0 4 1 2 0
14.00-14.15 15 2 4 6 0 0 7 0 4 2 1 0
14.15-14.30 8 2 10 13 0 0 15 0 2 0 1 0
14.30-14.45 8 1 9 10 0 0 4 0 4 1 1 0
14.45-15.00 28 1 4 8 0 0 16 0 2 0 3 0
15.00-15.15 16 2 5 9 0 1 8 0 11 0 4 0
15.15-15.30 21 0 11 16 1 0 8 0 3 1 4 0
15.30-15.45 18 0 8 11 0 0 6 0 2 1 5 0
15.45-16.00 14 1 8 7 0 1 7 0 4 0 2 0
16.00-16.15 16 3 7 9 0 0 11 0 4 2 2 0
16.15-16.30 17 1 8 10 0 2 11 0 4 0 1 0
16.30-16.45 15 2 1 11 1 0 8 0 3 0 3 0
16.45-17.00 18 1 10 10 0 1 7 0 3 1 2 0
17.00-17.15 20 1 12 7 0 1 5 0 8 0 5 0
17.15-17.30 32 1 3 5 1 0 5 0 0 0 8 0
17.30-17.45 21 4 3 10 1 2 3 0 0 1 2 0
17.45-18.00 24 1 1 2 0 0 3 0 3 0 6 0
Source : Survey Result
Table 3.31. Results of Survey in Margomulyo Junction 3
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 60 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
06.00-06.15 330 17 18 1 0 0 2 1 0 0 2 1
06.15-06.30 480 19 4 3 0 1 0 0 0 0 0 2
06.30-06.45 462 20 11 0 0 1 1 0 0 0 0 3
06.45-07.00 439 19 20 1 0 1 2 0 0 0 0 1
07.00-07.15 416 16 20 5 0 0 1 0 0 0 0 0
07.15-07.30 478 19 12 0 0 0 0 0 0 0 0 2
07.30-07.45 685 22 15 2 1 0 0 0 0 0 0 1
07.45-08.00 757 14 14 5 0 0 0 0 0 0 0 2
08.00-08.15 633 13 23 6 0 0 0 1 1 0 0 1
08.15-08.30 523 4 16 11 0 1 1 0 0 1 0 2
08.30-08.45 383 7 22 10 0 0 1 1 0 0 0 1
08.45-09.00 286 0 16 12 0 0 3 1 5 1 12 0
09.00-09.15 362 1 15 10 0 2 9 6 4 0 43 0
09.15-09.30 369 0 17 7 0 0 23 10 2 2 31 0
09.30-09.45 209 1 20 7 0 1 13 4 4 1 19 1
09.45-10.00 228 1 15 8 0 0 19 7 3 0 25 0
10.00-10.15 171 6 17 12 0 0 12 5 6 2 32 0
10.15-10.30 191 4 20 26 0 0 20 5 3 1 23 0
10.30-10.45 141 1 12 6 0 1 12 5 3 1 23 0
10.45-11.00 163 3 20 15 0 0 22 3 3 1 22 0
11.00-11.15 137 2 12 19 0 0 19 6 2 0 33 0
11.15-11.30 162 3 18 18 0 0 21 3 3 3 32 0
11.30-11.45 187 2 9 12 0 0 14 8 6 2 22 0
11.45-12.00 143 1 14 18 0 0 12 3 4 1 16 0
12.00-12.15 125 1 9 11 0 0 7 2 6 0 20 1
12.15-12.30 130 2 14 11 0 0 24 4 2 2 14 1
12.30-12.45 127 3 8 13 0 0 19 3 4 1 17 0
12.45-13.00 119 2 9 14 0 0 22 5 1 0 0 0
13.00-13.15 118 5 19 16 0 0 21 7 3 1 12 0
13.15-13.30 114 0 17 23 0 0 20 6 3 1 13 0
13.30-13.45 124 3 9 9 0 0 18 4 4 0 14 1
13.45-14.00 134 4 15 20 0 0 29 3 6 2 20 1
14.00-14.15 116 3 17 16 0 0 19 5 2 0 31 0
14.15-14.30 121 3 15 8 0 0 21 5 4 0 24 1
14.30-14.45 155 4 19 11 0 0 26 4 6 0 29 1
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 61 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
14.45-15.00 151 2 15 23 0 0 16 5 1 0 27 1
15.00-15.15 149 3 15 13 0 0 16 7 6 2 30 1
15.15-15.30 153 1 14 17 0 0 18 4 2 2 35 0
15.30-15.45 167 2 17 14 0 0 17 2 4 2 19 1
15.45-16.00 138 5 19 16 0 0 19 3 2 1 22 3
16.00-16.15 278 3 16 12 0 0 12 0 0 0 9 0
16.15-16.30 320 1 14 6 0 0 9 0 0 0 5 0
16.30-16.45 380 1 19 10 0 0 2 1 1 0 2 0
16.45-17.00 433 2 19 7 0 0 0 0 0 0 2 3
17.00-17.15 472 1 16 12 0 0 1 0 0 0 0 0
17.15-17.30 557 0 5 1 1 0 0 0 0 0 0 0
17.30-17.45 442 6 17 3 0 0 0 0 0 0 1 3
17.45-18.00 433 1 15 6 0 0 0 0 0 0 3 0
Source : Survey Result
Table 3.32. Results of Survey in Margomulyo Junction 4
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
06.00-06.15 512 6 11 3 0 3 2 3 2 1 3 1
06.15-06.30 732 9 14 5 0 4 3 2 1 0 4 1
06.30-06.45 800 13 16 2 2 5 1 3 1 1 4 2
06.45-07.00 1275 12 32 2 0 4 1 4 2 1 6 3
07.00-07.15 1322 8 24 5 0 1 4 8 2 0 6 6
07.15-07.30 1543 12 24 4 0 1 2 2 1 0 6 3
07.30-07.45 1645 17 44 6 1 1 1 2 2 0 8 8
07.45-08.00 1341 21 20 10 0 0 7 4 4 1 4 2
08.00-08.15 1212 19 18 12 0 1 5 4 3 2 20 4
08.15-08.30 1249 16 19 9 3 3 8 3 1 0 25 1
08.30-08.45 1137 18 16 11 0 0 5 1 0 1 18 3
08.45-09.00 1054 15 21 7 2 0 4 3 2 1 22 5
09.00-09.15 971 10 19 4 0 3 11 5 0 0 19 3
09.15-09.30 775 11 23 6 4 0 7 3 1 0 24 1
09.30-09.45 642 13 20 13 1 1 5 4 2 0 17 2
09.45-10.00 611 16 18 8 1 0 6 2 0 3 19 0
10.00-10.15 480 14 15 10 0 3 11 5 4 2 22 1
10.15-10.30 334 11 1 9 0 0 7 2 0 0 25 0
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 62 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
10.30-10.45 270 13 14 13 0 0 15 3 4 4 23 2
10.45-11.00 241 15 11 11 6 0 8 8 1 6 29 3
11.00-11.15 301 18 12 15 1 0 11 6 1 2 33 0
11.15-11.30 281 23 11 11 0 0 5 4 2 1 48 2
11.30-11.45 202 20 12 9 0 0 3 3 0 0 33 0
11.45-12.00 249 22 15 14 0 0 8 1 2 2 39 1
12.00-12.15 512 32 15 28 0 2 3 2 1 1 25 3
12.15-12.30 413 28 18 25 1 0 5 3 0 0 21 0
12.30-12.45 410 32 10 27 0 0 6 2 1 0 24 2
12.45-13.00 363 25 13 23 0 0 7 1 0 0 21 0
13.00-13.15 398 24 18 18 0 0 8 3 0 2 12 0
13.15-13.30 324 17 20 18 1 0 0 0 0 0 22 1
13.30-13.45 395 14 12 15 0 0 6 3 0 0 10 0
13.45-14.00 225 15 16 21 0 0 1 5 1 2 20 0
14.00-14.15 225 12 18 17 2 1 6 7 1 0 22 0
14.15-14.30 231 14 10 19 0 0 4 3 0 0 18 3
14.30-14.45 210 10 12 22 0 0 2 4 0 0 16 1
14.45-15.00 187 15 29 22 0 1 3 3 1 1 19 0
15.00-15.15 174 17 21 25 1 3 5 5 0 0 23 0
15.15-15.30 301 22 25 18 3 0 3 2 0 2 31 0
15.30-15.45 429 19 23 15 0 1 6 5 2 0 36 0
15.45-16.00 559 20 10 17 0 1 4 1 1 0 47 1
16.00-16.15 549 0 12 20 0 0 8 6 0 0 40 0
16.15-16.30 606 0 9 15 0 0 7 2 0 2 25 1
16.30-16.45 851 0 15 15 0 0 4 1 0 0 38 2
16.45-17.00 417 0 4 5 0 0 3 1 0 0 29 0
17.00-17.15 691 0 8 6 0 0 4 2 3 0 32 0
17.15-17.30 479 0 1 5 0 0 2 1 4 2 24 0
17.30-17.45 513 0 0 5 0 0 2 0 2 1 21 0
17.45-18.00 386 5 0 3 0 0 0 0 2 0 17 0
Source : Survey Result
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 63 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Table 3.33. Results of Survey in Margomulyo Junction 5
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
06.00-06.15 150 3 10 3 0 1 7 1 5 7 3 1
06.15-06.30 196 9 15 12 0 1 8 8 7 1 3 0
06.30-06.45 176 5 12 7 0 0 5 3 3 5 2 0
06.45-07.00 251 13 13 12 1 1 4 5 3 3 6 0
07.00-07.15 262 2 10 10 0 2 8 5 1 0 5 0
07.15-07.30 215 12 10 4 0 1 5 5 1 1 10 0
07.30-07.45 263 3 7 13 0 1 12 4 1 1 12 0
07.45-08.00 142 2 9 7 0 0 4 2 5 0 13 2
08.00-08.15 135 10 15 9 0 2 10 7 3 3 23 0
08.15-08.30 176 8 13 17 0 1 16 10 10 4 20 0
08.30-08.45 225 4 14 11 0 1 9 7 4 5 19 0
08.45-09.00 205 11 20 5 0 1 8 5 7 7 34 0
09.00-09.15 75 5 11 9 0 0 3 4 3 4 22 0
09.15-09.30 69 6 15 8 0 0 8 10 5 7 30 0
09.30-09.45 72 12 17 4 0 0 10 15 8 54 0
09.45-10.00 67 8 25 12 0 0 15 10 2 6 32 0
10.00-10.15 110 13 12 8 0 0 13 8 9 0 21 0
10.15-10.30 95 9 25 16 1 0 20 10 10 1 50 0
10.30-10.45 72 8 12 4 0 0 12 4 10 0 25 0
10.45-11.00 67 4 25 15 0 0 17 4 5 1 21 0
11.00-11.15 81 4 19 12 0 0 20 15 5 0 25 0
11.15-11.30 105 16 17 22 0 0 3 5 5 0 26 0
11.30-11.45 67 12 13 8 0 0 11 7 5 1 10 0
11.45-12.00 60 21 7 11 0 0 7 9 7 1 14 0
12.00-12.15 65 13 8 5 0 0 13 3 5 1 12 0
12.15-12.30 35 9 8 7 0 0 6 11 1 1 10 0
12.30-12.45 56 8 12 8 0 0 12 7 7 2 5 0
12.45-13.00 50 10 15 4 0 0 14 12 6 0 12 0
13.00-13.15 55 3 9 6 0 0 7 9 2 0 10 0
13.15-13.30 70 6 14 10 0 0 4 19 8 1 7 0
13.30-13.45 65 12 18 9 0 0 3 13 5 1 15 0
13.45-14.00 59 20 12 8 0 0 12 5 10 2 13 0
14.00-14.15 57 12 9 2 0 0 10 12 12 0 9 0
14.15-14.30 54 13 10 13 0 0 13 9 14 0 15 0
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 64 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
14.30-14.45 67 21 13 8 0 0 12 10 8 0 12 0
14.45-15.00 87 19 15 9 0 0 7 16 3 0 19 0
15.00-15.15 53 17 2 4 0 0 14 2 10 0 23 0
15.15-15.30 65 16 17 13 0 0 13 17 6 0 19 0
15.30-15.45 66 22 11 12 0 0 17 15 8 0 24 0
15.45-16.00 62 15 16 15 0 0 3 5 4 0 12 0
16.00-16.15 170 13 12 11 0 0 13 6 9 3 36 1
16.15-16.30 210 16 8 8 0 0 17 10 12 3 43 2
16.30-16.45 195 9 13 13 0 0 19 7 15 5 21 0
16.45-17.00 230 20 10 10 0 0 21 15 6 2 34 0
17.00-17.15 285 30 15 15 0 0 13 7 2 3 19 0
17.15-17.30 350 32 14 14 0 0 16 19 7 15 22 0
17.30-17.45 300 24 22 12 0 0 12 15 11 3 13 0
17.45-18.00 285 22 19 19 0 0 11 9 14 5 12 0
Source : Survey Result
Table 3.34. Results of Survey in Margomulyo Junction 6
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
06.00-06.15 379 3 5 0 0 0 0 0 0 0 0 0
06.15-06.30 443 2 8 0 0 0 0 0 0 0 0 1
06.30-06.45 258 2 11 0 0 0 0 0 0 0 0 2
06.45-07.00 387 5 12 2 0 0 0 0 0 0 0 2
07.00-07.15 435 6 11 0 0 1 0 0 0 0 0 1
07.15-07.30 367 6 10 0 0 0 1 1 0 0 0 1
07.30-07.45 523 12 12 0 0 0 0 0 0 0 0 1
07.45-08.00 222 6 16 3 0 0 0 0 0 0 0 0
08.00-08.15 326 9 11 4 0 0 0 0 0 0 0 4
08.15-08.30 312 14 15 3 0 0 0 1 0 0 3 1
08.30-08.45 361 5 13 3 0 0 0 0 2 0 3 2
08.45-09.00 226 8 18 7 0 0 2 0 0 0 0 1
09.00-09.15 248 4 7 9 0 0 0 2 0 0 0 0
09.15-09.30 258 10 8 4 0 0 0 2 0 1 2 0
09.30-09.45 235 11 14 6 0 0 0 0 0 0 2 1
09.45-10.00 215 7 10 5 0 0 0 0 0 0 1 1
10.00-10.15 273 9 9 5 0 0 0 3 0 0 5 2
10.15-10.30 244 6 6 9 0 0 2 0 2 0 4 0
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 65 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
10.30-10.45 163 5 9 7 0 0 5 8 5 0 13 2
10.45-11.00 126 9 8 12 0 0 0 7 0 0 16 1
11.00-11.15 168 8 9 13 0 0 3 5 3 0 20 0
11.15-11.30 158 2 7 15 0 0 2 2 2 0 28 1
11.30-11.45 175 13 11 13 0 0 3 6 3 1 12 5
11.45-12.00 136 9 8 19 0 0 0 3 0 0 0 1
12.00-12.15 121 12 4 5 0 0 0 2 0 0 2 0
12.15-12.30 197 7 8 8 0 0 0 2 0 0 0 0
12.30-12.45 169 15 6 12 0 0 0 0 0 0 2 1
12.45-13.00 145 8 8 9 0 0 0 0 0 0 3 0
13.00-13.15 99 6 7 4 0 0 0 1 0 0 6 0
13.15-13.30 93 10 3 6 0 0 0 1 0 0 20 1
13.30-13.45 61 9 2 7 0 0 0 2 0 0 23 1
13.45-14.00 98 10 7 12 0 0 0 6 1 0 24 0
14.00-14.15 134 7 5 15 0 0 0 4 0 0 17 2
14.15-14.30 106 7 5 11 0 0 0 4 0 0 6 1
14.30-14.45 90 5 5 8 0 0 0 3 0 0 5 0
14.45-15.00 115 9 9 7 0 0 0 2 0 0 11 1
15.00-15.15 177 12 12 7 0 0 0 0 0 0 3 0
15.15-15.30 159 9 7 9 0 0 0 0 0 0 4 0
15.30-15.45 204 8 5 8 0 0 0 2 0 0 8 1
15.45-16.00 225 5 4 10 0 0 0 4 0 0 10 2
16.00-16.15 259 4 4 6 0 1 0 0 0 0 2 5
16.15-16.30 141 13 4 4 0 0 0 2 0 0 2 1
16.30-16.45 256 7 6 1 0 0 0 0 0 0 2 3
16.45-17.00 421 7 10 6 0 0 0 0 0 0 0 2
17.00-17.15 541 5 8 7 0 0 0 0 0 2 2 8
17.15-17.30 573 11 7 5 0 0 0 0 0 3 4 2
17.30-17.45 558 16 5 2 0 0 0 0 0 0 6 2
17.45-18.00 472 12 5 3 0 0 0 0 0 0 5 3
Source : Survey Result
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 66 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
3. Romokalisari Crossroad
The survey is supposed to identify the volume traffic pasing the surveyed
area, i.e. : Romokalisari Crossroad. In this crossroad, there are 7 traffic
movements. The results of the survey in Romokalisari Crossroad are presented in
Table 3.35 – Table 3.41.
Table 3.35. Results of Survey in Romokalisari Crossroad 1
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
06.00-06.15 5 68 3 8 0 0 5 4 2 0 3 0
06.15-06.30 8 73 1 6 0 0 9 4 1 1 6 0
06.30-06.45 12 72 0 9 0 1 8 7 3 2 11 0
06.45-07.00 11 81 0 8 0 0 7 5 4 0 5 0
07.00-07.15 14 86 2 7 0 2 13 6 4 2 11 0
07.15-07.30 10 92 0 7 0 0 22 3 5 2 9 0
07.30-07.45 16 105 3 13 0 0 12 6 5 1 9 0
07.45-08.00 11 112 1 11 0 0 20 16 5 2 11 0
08.00-08.15 4 98 0 9 0 0 19 6 5 1 8 0
08.15-08.30 13 103 1 18 2 0 27 10 7 1 6 0
08.30-08.45 9 112 1 25 0 0 26 9 9 2 14 0
08.45-09.00 10 83 2 16 0 0 16 5 9 1 18 0
09.00-09.15 7 104 2 28 0 0 20 9 13 0 13 2
09.15-09.30 10 85 2 32 0 0 12 16 11 1 10 0
09.30-09.45 5 78 3 33 0 1 19 4 13 1 12 0
09.45-10.00 3 100 0 31 0 1 19 6 14 1 15 2
10.00-10.15 9 74 0 30 1 2 21 8 17 4 18 0
10.15-10.30 11 86 6 34 1 0 17 9 14 0 23 0
10.30-10.45 2 82 4 36 0 0 28 9 11 1 19 0
10.45-11.00 6 88 3 32 0 0 22 7 9 1 18 0
11.00-11.15 8 94 0 44 0 3 18 4 12 0 14 0
11.15-11.30 6 89 4 39 0 0 16 7 10 2 16 0
11.30-11.45 4 105 3 28 0 1 22 6 9 0 12 0
11.45-12.00 7 112 0 31 0 2 20 5 11 3 8 0
12.00-12.15 3 96 0 27 0 1 16 6 8 1 13 0
12.15-12.30 8 101 0 34 0 5 14 8 12 0 7 0
12.30-12.45 12 94 2 28 0 2 12 6 13 2 13 0
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 67 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
12.45-13.00 4 102 0 22 0 0 11 9 12 0 5 0
13.00-13.15 4 112 1 19 1 0 9 7 13 2 12 0
13.15-13.30 5 79 3 27 0 3 6 7 15 3 18 0
13.30-13.45 7 82 1 33 0 1 10 10 12 5 8 0
13.45-14.00 6 91 3 26 2 0 14 12 16 4 19 0
14.00-14.15 5 104 0 23 0 2 21 9 8 1 6 0
14.15-14.30 4 97 5 21 0 0 18 7 8 0 5 0
14.30-14.45 5 101 2 28 0 0 14 8 10 3 8 0
14.45-15.00 3 112 0 36 0 0 22 6 7 2 9 0
15.00-15.15 7 89 0 41 0 0 18 6 12 1 13 0
15.15-15.30 6 64 0 33 0 1 16 7 14 0 7 0
15.30-15.45 8 112 0 27 0 0 14 10 9 3 10 0
15.45-16.00 4 124 3 25 0 0 20 5 8 1 8 0
16.00-16.15 2 97 0 21 0 0 12 7 11 1 13 0
16.15-16.30 3 113 2 28 0 1 9 4 13 0 8 0
16.30-16.45 6 108 0 24 0 0 14 8 10 2 7 0
16.45-17.00 9 98 1 19 1 0 8 11 15 3 4 0
17.00-17.15 8 128 0 15 0 0 6 9 13 1 6 0
17.15-17.30 10 133 2 21 0 0 10 7 9 0 3 0
17.30-17.45 12 137 1 14 0 0 7 4 6 0 5 0
17.45-18.00 4 132 0 16 0 0 6 3 7 0 2 0
Source : Survey Result
Table 3.36. Results of Survey in Romokalisari Crossroad 2
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
06.00-06.15 5 2 0 0 0 0 0 0 0 0 0 0
06.15-06.30 10 2 0 0 0 0 0 0 0 0 0 0
06.30-06.45 21 3 0 0 0 0 0 0 0 0 0 0
06.45-07.00 23 4 0 0 0 0 0 0 0 0 0 0
07.00-07.15 30 7 0 0 0 0 0 0 0 0 0 0
07.15-07.30 59 9 0 2 0 0 0 0 0 0 0 0
07.30-07.45 75 10 0 3 0 0 0 0 0 0 0 0
07.45-08.00 78 7 1 3 0 0 0 0 1 0 0 0
08.00-08.15 70 9 0 3 1 0 3 0 0 0 0 0
08.15-08.30 77 6 0 4 0 0 3 0 0 0 0 0
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 68 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
08.30-08.45 86 7 0 2 0 0 4 0 0 0 0 0
08.45-09.00 152 5 0 2 0 0 4 0 1 0 0 0
09.00-09.15 98 6 0 3 0 0 2 0 3 0 0 0
09.15-09.30 87 4 0 4 0 0 3 1 2 0 0 0
09.30-09.45 81 6 0 4 0 0 3 0 2 0 3 0
09.45-10.00 83 5 0 3 0 0 6 1 0 1 0 2
10.00-10.15 65 3 0 2 0 0 3 1 0 0 0 0
10.15-10.30 67 6 0 2 0 0 7 0 1 0 0 0
10.30-10.45 66 3 0 4 0 1 2 0 0 0 0 0
10.45-11.00 61 4 0 3 0 0 2 0 0 0 0 0
11.00-11.15 57 3 0 3 0 0 1 0 1 0 0 0
11.15-11.30 55 5 0 3 0 0 2 0 0 0 0 0
11.30-11.45 49 5 0 4 0 0 1 0 0 0 0 0
11.45-12.00 47 3 0 3 0 0 2 0 1 0 0 0
12.00-12.15 31 4 0 2 0 0 0 0 0 0 0 0
12.15-12.30 29 4 0 4 0 0 0 0 0 0 0 0
12.30-12.45 25 6 0 3 0 0 0 0 0 0 0 0
12.45-13.00 27 5 0 3 0 0 0 0 0 0 0 0
13.00-13.15 24 3 0 2 0 0 0 0 0 0 0 0
13.15-13.30 19 5 0 1 0 0 0 0 0 0 0 0
13.30-13.45 18 7 0 0 0 0 0 0 0 0 0 0
13.45-14.00 16 5 0 0 0 0 0 0 0 0 0 0
14.00-14.15 20 5 0 0 0 0 0 0 0 0 0 0
14.15-14.30 21 4 0 3 0 0 0 0 0 0 0 0
14.30-14.45 17 5 0 4 0 0 0 0 0 0 0 0
14.45-15.00 19 6 0 2 0 0 0 0 0 0 0 0
15.00-15.15 14 5 0 3 0 0 0 0 0 0 0 0
15.15-15.30 27 7 0 3 0 0 0 0 0 0 0 0
15.30-15.45 28 5 0 0 0 0 0 0 0 0 0 0
15.45-16.00 31 8 0 0 0 0 0 0 0 0 0 0
16.00-16.15 35 7 0 0 0 0 0 0 0 0 0 0
16.15-16.30 37 5 0 0 0 0 0 0 0 0 0 0
16.30-16.45 41 4 0 0 0 0 0 0 0 0 0 0
16.45-17.00 46 4 0 3 0 0 0 0 0 0 0 0
17.00-17.15 48 7 0 2 0 0 0 0 0 0 0 0
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 69 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
17.15-17.30 47 6 0 2 0 0 0 0 0 0 0 0
17.30-17.45 51 8 0 0 0 0 0 0 0 0 0 0
17.45-18.00 53 7 0 0 0 0 0 0 0 0 0 0
Source : Survey Result
Table 3.37. Results of Survey in Romokalisari Crossroad 3
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
06.00-06.15 29 113 0 1 0 2 7 5 3 2 1 1
06.15-06.30 36 107 2 1 0 1 1 0 3 0 1 1
06.30-06.45 39 97 3 2 0 0 5 4 2 0 1 1
06.45-07.00 41 106 3 2 0 2 6 5 1 0 0 0
07.00-07.15 40 93 1 1 0 0 5 11 4 1 1 0
07.15-07.30 12 51 0 3 0 0 12 8 2 2 0 0
07.30-07.45 20 79 0 1 0 0 15 10 6 3 3 0
07.45-08.00 13 63 2 7 0 0 19 7 9 3 2 0
08.00-08.15 15 77 0 10 0 0 16 5 7 1 1 0
08.15-08.30 7 57 0 6 0 0 31 10 6 2 1 1
08.30-08.45 4 70 0 12 0 1 16 5 3 0 3 1
08.45-09.00 5 56 2 12 1 0 26 8 8 1 6 0
09.00-09.15 4 78 0 6 0 0 28 6 14 4 12 0
09.15-09.30 7 79 1 6 0 0 32 3 11 2 10 1
09.30-09.45 8 74 1 10 0 0 17 10 13 7 10 0
09.45-10.00 5 76 0 17 1 0 18 8 11 1 20 0
10.00-10.15 12 95 1 11 0 0 15 23 8 0 15 0
10.15-10.30 12 79 0 8 0 0 18 8 9 2 8 0
10.30-10.45 6 63 0 10 1 1 21 10 8 3 12 0
10.45-11.00 14 36 0 11 0 0 25 13 13 5 66 0
11.00-11.15 12 44 1 13 3 2 32 12 16 4 7 0
11.15-11.30 11 28 0 12 2 0 19 13 15 3 10 0
11.30-11.45 9 32 2 10 0 1 8 16 17 4 17 1
11.45-12.00 10 26 0 13 0 0 20 13 10 3 11 0
12.00-12.15 8 14 0 15 0 3 26 17 7 5 13 0
12.15-12.30 6 159 4 8 0 0 17 17 13 7 16 0
12.30-12.45 7 163 0 9 0 1 13 17 9 4 15 0
12.45-13.00 7 120 0 6 0 0 11 15 6 4 9 0
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 70 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
13.00-13.15 6 88 0 11 0 1 14 12 8 3 11 0
13.15-13.30 9 84 2 21 0 2 39 9 20 4 11 0
13.30-13.45 2 68 0 16 0 2 25 5 12 2 6 0
13.45-14.00 8 94 0 22 0 0 16 9 8 3 12 0
14.00-14.15 7 90 0 15 1 4 17 4 23 0 15 0
14.15-14.30 5 97 0 14 1 1 15 7 19 3 16 0
14.30-14.45 5 67 1 32 0 0 17 28 14 3 14 1
14.45-15.00 3 100 0 34 0 2 15 22 18 2 26 0
15.00-15.15 5 119 0 37 0 1 15 16 16 3 23 0
15.15-15.30 4 98 0 36 0 1 22 30 23 1 14 0
15.30-15.45 6 108 0 27 2 2 18 38 14 3 14 0
15.45-16.00 5 121 1 29 3 3 29 18 23 4 19 0
16.00-16.15 5 112 0 19 1 3 37 6 22 2 23 0
16.15-16.30 3 124 0 26 2 2 17 25 22 1 10 0
16.30-16.45 5 100 2 31 0 2 19 26 16 2 11 0
16.45-17.00 4 93 0 31 0 2 29 23 24 3 16 0
17.00-17.15 3 90 1 29 0 1 30 21 22 2 19 0
17.15-17.30 4 88 0 35 1 0 21 7 14 1 16 2
17.30-17.45 4 91 0 24 0 1 10 12 37 3 16 0
17.45-18.00 7 91 0 22 0 0 19 15 18 2 20 0
Source : Survey Result
Table 3.38. Results of Survey in Romokalisari Crossroad 4
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
06.00-06.15 1233 8 10 6 0 9 2 4 8 3 1 3
06.15-06.30 1577 12 17 17 2 13 8 13 3 1 0 2
06.30-06.45 1787 16 32 25 7 21 12 12 6 6 2 0
06.45-07.00 1650 8 10 5 0 13 2 4 4 0 1 0
07.00-07.15 564 14 21 7 0 7 1 0 3 0 0 2
07.15-07.30 686 26 15 7 1 5 0 3 0 0 0 1
07.30-07.45 916 20 18 2 2 1 1 0 0 0 1 0
07.45-08.00 686 23 25 8 1 4 0 1 1 1 1 0
08.00-08.15 675 27 16 14 1 5 0 0 0 0 1 1
08.15-08.30 555 13 18 15 2 3 0 1 0 0 2 0
08.30-08.45 362 16 23 6 2 5 0 1 1 0 1 1
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 71 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
08.45-09.00 492 24 12 5 1 6 4 2 2 1 5 0
09.00-09.15 266 8 14 14 1 4 6 7 5 1 1 0
09.15-09.30 342 19 14 8 0 4 2 4 6 0 6 2
09.30-09.45 404 9 15 9 1 5 2 7 8 0 1 0
09.45-10.00 359 19 18 16 2 6 2 5 12 4 4 3
10.00-10.15 347 12 17 9 1 7 1 11 6 1 7 0
10.15-10.30 276 27 11 20 0 5 1 4 7 0 3 0
10.30-10.45 248 16 17 16 1 3 1 8 6 2 5 0
10.45-11.00 241 20 12 19 0 5 0 1 7 0 4 0
11.00-11.15 272 20 16 9 0 4 1 2 8 0 0 0
11.15-11.30 301 11 12 11 1 10 3 1 4 0 1 0
11.30-11.45 204 26 14 18 1 2 6 1 5 1 3 0
11.45-12.00 211 23 17 23 0 4 2 6 8 0 1 0
12.00-12.15 243 26 7 24 3 11 0 8 13 0 2 0
12.15-12.30 236 26 8 17 0 8 0 11 11 3 0 0
12.30-12.45 261 22 16 31 0 6 0 6 6 0 0 1
12.45-13.00 253 23 32 27 2 11 2 4 7 2 3 2
13.00-13.15 251 18 22 25 0 9 0 4 4 0 1 0
13.15-13.30 263 22 17 30 1 8 0 1 4 0 0 0
13.30-13.45 277 15 21 24 0 13 3 2 7 2 1 0
13.45-14.00 264 26 19 31 3 6 2 0 10 0 4 0
14.00-14.15 266 25 22 27 0 8 1 1 6 0 2 0
14.15-14.30 263 30 13 26 1 6 5 2 4 0 4 0
14.30-14.45 322 30 12 15 1 5 9 5 2 0 5 0
14.45-15.00 355 25 10 15 1 5 3 1 6 0 6 1
15.00-15.15 303 31 14 14 0 5 8 3 4 0 3 2
15.15-15.30 336 29 14 19 1 4 3 2 3 1 6 1
15.30-15.45 334 29 16 20 0 4 3 3 5 1 3 0
15.45-16.00 340 37 13 16 0 7 6 3 7 0 1 0
16.00-16.15 371 33 15 16 0 6 4 4 8 0 3 0
16.15-16.30 362 35 12 17 1 5 4 2 8 0 1 0
16.30-16.45 346 29 16 19 0 5 5 4 5 0 2 1
16.45-17.00 373 34 16 16 0 7 4 1 6 1 1 2
17.00-17.15 0 0 0 0 0 0 0 0 0 0 0 0
17.15-17.30 0 0 0 0 0 0 0 0 0 0 0 0
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 72 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
17.30-17.45 0 0 0 0 0 0 0 0 0 0 0 0
17.45-18.00 0 0 0 0 0 0 0 0 0 0 0 0
Source : Survey Result
Table 3.39. Results of Survey in Romokalisari Crossroad 5
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
06.00-06.15 3 0 1 0 0 1 0 1 0 0 1 0
06.15-06.30 3 1 0 1 0 1 1 2 1 0 0 0
06.30-06.45 3 0 0 2 0 0 0 0 2 0 0 0
06.45-07.00 18 2 0 0 0 6 1 0 0 0 0 0
07.00-07.15 20 11 2 4 0 6 8 1 0 1 1 0
07.15-07.30 62 8 1 2 0 5 2 1 3 0 2 0
07.30-07.45 26 7 0 1 1 1 1 0 1 1 0 0
07.45-08.00 42 6 3 2 2 5 5 1 4 0 1 0
08.00-08.15 26 8 1 6 0 5 3 0 1 0 2 0
08.15-08.30 12 3 1 2 2 2 5 0 0 0 1 0
08.30-08.45 19 12 0 0 1 5 4 2 4 0 1 0
08.45-09.00 12 6 0 1 1 6 3 2 5 0 3 0
09.00-09.15 10 6 0 6 1 3 7 4 5 1 5 0
09.15-09.30 20 3 0 4 0 5 5 2 7 0 1 0
09.30-09.45 9 4 0 4 1 7 3 3 9 0 4 0
09.45-10.00 3 5 0 1 1 3 5 2 6 0 1 0
10.00-10.15 8 2 0 0 0 1 0 0 2 0 0 0
10.15-10.30 3 4 0 3 0 2 6 1 6 1 4 0
10.30-10.45 8 7 0 4 1 1 5 2 6 1 4 0
10.45-11.00 7 16 0 5 0 4 6 0 7 0 3 0
11.00-11.15 5 6 0 5 0 1 4 1 4 0 2 0
11.15-11.30 3 4 0 2 0 1 5 0 2 0 2 0
11.30-11.45 1 8 0 4 1 3 6 1 2 1 1 0
11.45-12.00 4 5 0 1 0 1 3 0 3 0 3 0
12.00-12.15 2 8 1 4 1 2 5 2 3 0 1 0
12.15-12.30 0 2 1 6 0 1 3 1 1 0 3 0
12.30-12.45 5 5 1 2 0 4 5 1 5 1 0 0
12.45-13.00 5 5 1 1 1 2 4 3 3 0 2 0
13.00-13.15 5 6 0 2 0 2 7 3 3 0 4 0
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 73 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
13.15-13.30 7 3 0 6 1 2 5 2 1 0 1 0
13.30-13.45 6 3 0 4 0 0 5 3 4 0 3 0
13.45-14.00 5 8 0 6 0 2 4 3 9 0 4 0
14.00-14.15 8 5 2 4 0 2 6 3 5 0 4 0
14.15-14.30 5 7 0 5 2 3 9 2 3 0 5 0
14.30-14.45 13 17 0 6 0 2 7 2 3 0 9 0
14.45-15.00 6 5 0 1 0 7 6 5 3 0 1 0
15.00-15.15 8 5 1 4 0 4 6 0 5 0 3 0
15.15-15.30 6 5 0 0 1 2 5 5 2 0 5 0
15.30-15.45 4 7 0 3 1 1 5 2 3 0 3 0
15.45-16.00 6 4 0 0 0 0 4 3 3 0 2 0
16.00-16.15 7 5 2 1 2 2 5 0 1 0 0 0
16.15-16.30 4 6 0 2 0 2 5 2 5 0 1 0
16.30-16.45 2 3 0 1 1 1 4 2 1 0 1 0
16.45-17.00 3 5 0 5 1 1 3 0 2 0 0 0
17.00-17.15 8 3 0 3 1 0 4 0 3 0 2 0
17.15-17.30 2 5 0 5 0 2 5 2 0 0 0 0
17.30-17.45 5 5 0 0 1 1 2 1 2 0 2 0
17.45-18.00 5 2 0 2 0 2 3 0 1 0 1 0
Source : Survey Result
Table 3.40. Results of Survey in Romokalisari Crossroad 6
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
06.00-06.15 457 12 10 12 0 0 0 2 0 2 0 8
06.15-06.30 421 11 12 9 0 0 4 0 1 0 0 0
06.30-06.45 754 9 35 0 0 0 0 0 2 0 0 0
06.45-07.00 1431 12 19 2 0 0 1 0 4 0 0 0
07.00-07.15 768 5 6 5 0 0 1 0 1 1 0 0
07.15-07.30 758 7 18 7 0 0 2 1 2 3 0 0
07.30-07.45 584 37 15 8 1 0 8 0 2 0 0 2
07.45-08.00 452 6 19 6 1 0 0 1 1 0 2 1
08.00-08.15 283 12 13 5 1 0 0 0 2 0 1 1
08.15-08.30 324 16 15 4 0 0 2 2 1 0 0 0
08.30-08.45 299 16 16 4 1 0 5 1 1 0 0 0
08.45-09.00 210 27 12 12 0 0 0 0 0 0 0 0
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 74 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
09.00-09.15 300 9 14 9 0 0 2 1 1 0 0 0
09.15-09.30 292 18 10 10 0 0 2 0 1 0 2 0
09.30-09.45 256 6 15 12 0 0 1 0 0 0 0 1
09.45-10.00 246 12 14 11 0 0 1 0 1 0 0 1
10.00-10.15 264 11 20 9 0 0 3 0 0 0 1 0
10.15-10.30 244 26 2 17 0 0 2 0 0 0 0 0
10.30-10.45 209 9 12 10 0 0 4 0 0 0 0 1
10.45-11.00 237 12 10 12 0 0 6 0 1 0 0 2
11.00-11.15 222 12 9 3 0 0 1 0 0 0 0 1
11.15-11.30 117 7 7 5 0 0 0 0 0 0 2 0
11.30-11.45 173 7 9 3 0 0 0 0 0 0 0 0
11.45-12.00 160 20 17 4 0 0 2 0 0 0 0 0
12.00-12.15 154 7 10 3 1 0 1 1 0 0 1 0
12.15-12.30 172 7 14 4 0 0 0 0 0 0 0 0
12.30-12.45 105 12 15 7 0 0 0 0 0 0 0 0
12.45-13.00 188 9 12 3 0 0 7 0 0 0 2 0
13.00-13.15 178 13 12 2 0 0 4 0 0 0 0 0
13.15-13.30 161 13 12 5 1 0 2 0 1 0 0 1
13.30-13.45 251 13 11 11 0 0 4 0 1 0 0 1
13.45-14.00 240 24 39 16 1 0 7 2 0 0 0 0
14.00-14.15 235 20 8 19 0 0 3 0 1 0 0 0
14.15-14.30 238 34 5 9 0 0 0 0 1 0 0 0
14.30-14.45 294 12 12 16 0 0 2 0 0 0 0 2
14.45-15.00 302 18 8 12 0 0 2 0 0 0 0 0
15.00-15.15 342 24 7 14 0 0 1 0 1 0 1 1
15.15-15.30 322 25 8 15 0 0 3 0 1 0 0 0
15.30-15.45 302 22 13 14 0 0 3 0 0 0 0 0
15.45-16.00 347 19 11 12 0 0 2 0 0 0 1 0
16.00-16.15 321 23 8 11 1 0 3 0 1 0 0 1
16.15-16.30 316 26 15 12 0 0 0 0 0 0 0 0
16.30-16.45 324 15 12 19 2 0 2 0 1 0 1 0
16.45-17.00 317 14 9 15 1 0 1 0 1 0 0 0
17.00-17.15 306 28 10 12 1 0 4 0 0 0 0 1
17.15-17.30 311 24 8 13 0 0 1 0 1 0 0 0
17.30-17.45 301 19 10 14 0 0 0 0 0 0 0 0
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 75 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
17.45-18.00 284 20 5 11 0 0 1 0 0 0 0 0
Source : Survey Result
Table 3.41. Results of Survey in Romokalisari Crossroad 7
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
06.00-06.15 5 0 0 0 0 2 0 0 0 0 0 0
06.15-06.30 9 1 0 0 1 2 1 0 0 0 0 0
06.30-06.45 14 2 2 0 1 4 1 0 1 0 2 0
06.45-07.00 38 2 0 0 1 7 3 1 1 0 0 0
07.00-07.15 74 1 1 3 3 3 3 1 0 0 0 2
07.15-07.30 107 1 0 4 1 1 0 1 6 0 0 0
07.30-07.45 96 4 0 4 0 8 2 0 3 0 5 0
07.45-08.00 70 3 0 0 0 5 2 2 1 0 4 1
08.00-08.15 34 3 2 4 2 8 5 0 4 1 4 0
08.15-08.30 18 4 0 6 1 3 12 1 5 0 7 0
08.30-08.45 18 5 0 2 0 3 8 1 4 0 9 0
08.45-09.00 14 3 0 5 1 8 7 5 4 0 8 1
09.00-09.15 13 2 0 6 0 4 9 3 3 0 8 0
09.15-09.30 11 8 0 5 1 4 5 0 7 1 10 0
09.30-09.45 10 3 0 3 1 7 8 2 10 0 7 3
09.45-10.00 3 6 0 4 2 3 6 1 14 1 2 0
10.00-10.15 4 5 0 5 0 3 4 1 8 0 6 0
10.15-10.30 13 3 0 1 1 6 7 2 4 0 7 0
10.30-10.45 5 5 0 5 1 8 15 3 11 0 11 0
10.45-11.00 5 3 1 4 0 3 4 2 7 0 5 0
11.00-11.15 7 4 0 2 1 3 8 3 6 2 5 0
11.15-11.30 7 6 0 3 0 6 6 2 8 0 2 0
11.30-11.45 5 3 1 5 0 3 6 5 11 1 4 0
11.45-12.00 10 4 0 2 2 4 11 6 13 3 8 2
12.00-12.15 12 5 2 5 2 3 3 2 5 1 3 0
12.15-12.30 5 6 0 2 0 5 5 1 2 0 2 0
12.30-12.45 15 3 0 3 0 2 3 1 3 0 1 0
12.45-13.00 3 5 0 6 1 3 6 3 3 1 2 0
13.00-13.15 7 1 3 1 0 6 2 0 8 0 4 0
13.15-13.30 7 2 1 3 0 3 4 1 2 0 5 0
13.30-13.45 3 1 0 2 0 4 1 3 2 2 2 0
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 76 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
1 2 3 4 5 5B 6A 6B 7A 7B 7C 8
13.45-14.00 3 9 0 6 1 5 8 1 10 0 3 0
14.00-14.15 5 5 0 7 1 4 10 1 3 1 2 0
14.15-14.30 6 4 0 7 1 3 8 0 5 0 2 0
14.30-14.45 7 5 0 3 1 5 9 2 2 0 1 1
14.45-15.00 5 3 0 2 1 4 5 1 7 0 9 0
15.00-15.15 3 2 2 5 1 8 8 1 6 0 3 0
15.15-15.30 2 4 1 3 1 8 2 2 6 1 3 0
15.30-15.45 3 2 0 2 1 3 3 2 5 0 3 0
15.45-16.00 2 3 2 2 2 4 5 1 5 1 3 1
16.00-16.15 2 2 0 3 2 3 4 1 3 0 2 0
16.15-16.30 3 1 0 1 1 3 6 1 2 0 4 2
16.30-16.45 4 6 0 5 1 4 5 3 3 2 3 0
16.45-17.00 3 3 0 2 1 5 7 2 1 3 3 0
17.00-17.15 2 1 0 3 0 3 3 1 2 0 1 0
17.15-17.30 2 2 1 3 1 4 3 1 1 2 5 0
17.30-17.45 3 1 0 5 0 3 2 1 3 0 2 1
17.45-18.00 3 5 0 1 2 2 5 3 1 1 2 0
Source : Survey Result
3.2. BIOLOGY
3.2.1. Type of Ecosystem
The location plotted as the project site of Tanjung Perak Port Development
in Lamong Bay is in a coastal area with managed ecosystem : fishpond, salt pond and
mangrove community. There is no ridge of rocks in the studied area.
3.2.2. Water Flora and Fauna
Plankton as Bio-indicator of Seawater Quality
Changes in water quality is closely related to water potencied in terms of
plankton abundance and compositions. The existence of plankton in an area can
supply information in regard with the conditions in the water. Plankton is a
biological parameter that can serve as indicator to evaluate the quality and degree
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 77 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
of fertility in a water area, i.e. : descriptions about the amounts of living
phytoplanktons in an water area and dominating phytoplankton.
The plankton data are the secondary ones and quoted from “Review to
Ecosystem Biodiversity in Lamong Bay, Year 2012”, the samples of which are taken
from 5 sampling points representing Sememi River, waters area surrounding Galang
island and waters area surrounding the project site.
a. Phytoplankton
The dominant phytoplankton in all samping points is Skeletonema sp. In
general, the kinds of phytoplankton found in each sampling point are relatively
indiferent. Saved for Skeletonema sp, the kinds of phytoplanktons commonly found
are Melosira sp., Pseudonitzchia sp., Thalasionema sp., Dytilum brightwellii,
Coscinodiscus sp., dan Thalassiothrix sp. The composition of the kinds, abundance
and diversity index in each sampling point are shown in Figure 3.39.
It is indicated that some kinds of phytoplanktons causing red tide, such as :
Ceratium spp, Peridinium sp, Pseudo-nitzschia sp, Noctiluca sp, and Triceratium sp
are relatively not abundant, less than 2.000 individu/lt of water. The red tide will
take place when when the plankton abundance reaches 2,000,000 individu/lt of
water.
There is a pattern of domination y in the sampling points. The most dominant
family is Skeletonemataceae. With reference to the phytoplankton diversity index,
the classifications of the conditions in the waters area ranges „poor‟ to „good‟ with
diversity index ranging from 0.989 to 2.237. A higher index represents a more stable
community. The more diversified species in a community, the more complex food
chain will be, vice versa.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 78 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 3.39. Graph of Compositions and Abyndance of Phytoplankton Surrounding Pelindo Pier
Source : Secondary Data 2012
b. Zooplankton
In the studied area there are 43 species of zooplanktons found and
comprising : Crustacea, fish larva, gelatinous plankton, larva Mollusca, larva
Polychaeta, Nematoda, Chaetognatha, Protozoa, and Foraminifera. The most
dominant species is Copepoda Calanoida of Acartiidae family and Eucalanidae as
well as Brachyura larva (crab) stadia zoea.
Almost in all sampling points around the estuary, both economically and
uneconomically potential fish larva are found. Accordingly, it is probable that the
areas surrounding the estuary and mangrove in Lamong Bay are hatching grounds
and nursery grounds of fish. The existence of larva is predicted to have relationship
with the existence and abundance of natural food of fish larva, i.e. : Copepoda (of
Acartiidae and Eucalanidae families) and other Crustacea, such as Cirripedia dan
zoea Brachyura larva (crab).
0500
100015002000250030003500400045005000
Bac
illar
iace
ae
Bid
du
lph
iace
ae
Cer
atia
ceae
Ch
aeto
cero
tace
ae
Co
scin
od
isca
ceae
Din
op
hys
iace
ae
Euca
mp
iace
ae
Frag
ilari
acea
e
Lith
od
esm
iace
ae
Mel
osi
race
ae
Mer
ism
op
edia
ceae
Nav
icu
lace
ae
Osc
illat
ori
ace
ae
Pe
rid
inia
ceae
Ple
uro
sigm
atac
eae
Pyr
ocy
stac
eae
Rh
izo
sole
nia
ceae
Skel
eto
nem
acea
e
Suri
rella
ceae
Thal
assi
on
emat
acea
e
Thal
assi
osi
race
ae
Tric
erat
iace
ae
Ulo
tric
has
ceae
Zygn
emat
acea
e
kelim
pah
an (
ni)
famili
Komposisi dan Kelimpahan Fitoplankton Berdasar Famili
perairan p Galang
muara kali Sememi
perairan sisi utara p Galangsisi utara dermaga
Compositions and Abundance of Phytoplankton Based on Family
Family
Abundance (
ni)
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 79 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Fish larvas bringing economic values are gereh/laosan (of Polynemidae
family), milkfish (of Chanidaefamily), tiny sea fish (of Atherinidae family), belanak
(of Mugilidae family), and lemuru (of Clupeidae family). Based on the diversity
index, the waters are categorized „fair‟ to good‟ with relatively stable community
structure. The diversity indexes range from 0.629 to 2.00.
Figure 3.40. Graph of Compositions and Abundance of Zooplankton Surrounding Pelindo Pier
Source : Secondary Data 2012 Remarks : M1 : Waters surrounding Galang Island M2 : Eastuary of Sememi River P1 : Waters in North Side of Galang Island L1 : North Side of Pier, L2: East Side of Pier
0
200
400
600
800
1000
1200
1400
Mys
idae
Oik
op
leu
rid
ae
Aca
rtiid
ae
Cen
tro
pag
idae
Ecti
no
som
atid
ae
ord
o M
on
stri
lloid
a
Cyp
rid
inid
ae
Eup
has
iidae
ord
o F
ora
min
ifer
a
Po
rtu
nid
ae
Bal
anid
ae
Op
hio
tric
hid
ae
Ner
eid
ae
kela
s B
ival
via
ord
o P
roso
bra
nch
ia
Luci
feri
dae
Ecti
no
som
atid
ae
kela
s N
emat
od
a
Cam
pan
ula
riid
ae
Sagi
ttid
ae
Salp
idae
Ke
limp
ahan
Kelas/Famili
Komposisi dan Kelimpahan Zooplankton
M1
M2
P1
L1
L2
Compositions and Abundance of Zooplankton
Class/Family
Abundance
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 80 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
c. Nekton
It is recorded that there are at least 56 fishery commodities found in brackish
waters and seawaters sorrounding the fishpond area and estuary of Lamong River. 45
(80.35%) of the commodities are finfish and the rest 11 (19.64%) are shellfish. Of 45
finfish commodities, 29 of them (64.444%) economically have high value, 10 of them
(22.222%) economically have low value and the rest 6 of them (13.333%) have no
economic value. The detailed compositions of the finfish commodities found
surrounding the estuary of Lamong River are presented in Table 3.42 and their
preparation are presented in Table 3.43.
High economic value finfish commonly caught by the fishermen by means of
seine or dragnet comprise belanak/gereh (Mugil cephalus, Liza subviridis),
keting/manyung (Arius spp), kiper (Scatophagus argus), laosan (Eleutheronema
tetradactylum), teri (Stolephoerus indicus, Escualosa thoracata dan Atherinomorus
duodecimalis) and juwi (Thryssa baelama). Most of them are commnly sold in the
markets as both fresh fish, and only a few are sold as salted or smoked ones. They
are categorized as pelagis fish generally living the water columns.
Table 3.42. Fish Diversity in Estuary of Lamong River
Nr. Species Local Name Family Potential Abnd. Location
Finfish
1 Mugil cephalus gereh Mugilidae HEV A SW-E
2 Chanos chanos bandeng Chanidae HEV A SW-E-FP
3 Thryssa baelama gereh laut Engraulidae HEV F L
4 Scatophagus argus kiper Scatophagidae HEV F L
5 Tetraodon nigroviridis buntek Tetraodontidae NEV F SW-E
6 Arothron manilensis buntek Tetraodontidae NEV R SW-E
7 Tylosurus crocodylus lujung Belonidae HEV F L
8 Elops hawaiiensis selek Elopidae HEV O L
9 Liza subviridis gereh Mugilidae HEV A SW-E
10 Eleutheronema tetradactylum laosan Polynemidae HEV A SW-E
11 Nematolosa come gereh Clupeidae HEV F L
12 Lagocephalus lunaris buntek Tetraodontidae LEV F L
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 81 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Nr. Species Local Name Family Potential Abnd. Location
13 Lagocephalus spadiceus buntek Tetraodontidae LEV F L
14 Anodontostoma chacunda - Clupeidae HEV F L
15 Lobotes surinamensis - Lobotidae HEV O SW-E
16 Brachyamblyopus coecus - Gobiidae NEV O SW-E
17 Boleophthalmus boddarti gelodok Gobiidae NEV A E-FP
18 Periophthalmus argentilineatus gelodok Gobiidae NEV A E-FP
19 Periophthalmus malaccensis gelodok Gobiidae NEV A E-FP
20 Glossogobius aureus belosoh Gobiidae LEV A SW-E
21 Butis butis belosoh Eleotridae HEV F SW-E
22 Esqualosa thoracata teri Engraulidae HEV A L
23 Atherinomorus duodecimalis teri Engraulidae HEV A L
24 Pseudapocryptes lanceolatus - Gobiidae LEV A SW-E
25 Glossogobius biocellatus belosoh Gobiidae LEV A SW-E
26 Arius maculatus keting, manyung Ariidae HEV A SW-E
27 Mystus nemurus keting, manyung Bagridae HEV A SW-E-FP
28 Arius argyropleuron keting, manyung Ariidae HEV A L
29 Arius nenga keting, manyung Ariidae HEV A L
30 Gerres argyreus kapasan Gerreidae LEV A L
31 Cynoglossus lingua ikan lidah Cynoglossidae HEV F SW-E
32 Setipinna taty gereh Engraulidae HEV F L
33 Nibea soldado gulamah Sciaenidae HEV F L
34 Oreochromis niloticus mujair nila Cichlidae HEV A T
35 Monopterus albus belut sawah Synbranchidae HEV F T
36 Channa striata gabus, kuthuk Channidae HEV O T
37 Stolephorus indicus teri Engraulidae HEV F L
38 Leiognathus equulus peperek, gereh Leiognathidae LEV F L
39 Gazza minuta peperek, gereh Leiognathidae LEV O L
40 Arius thalassinus keting, manyung Ariidae HEV O L
41 Terapon jarbua kerong-kerong Terapontidae LEV O L
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 82 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Nr. Species Local Name Family Potential Abnd. Location
42 Paraplagusia bilineata ikan lidah Cynoglossidae HEV O SW-E
43 Leiognathus bindus peperek, gereh Leiognathidae LEV O L
44 Selaroides leptolepis selar Carangidae HEV O L
45 Carangoides sp putihan Carangidae HEV O L
Shellfish
1 Scylla olivacea kepiting bakau Portunidae HEV F SW-E-FP
2 Scylla paramamosain kepiting bakau Portunidae HEV F SW-E-FP
3 Charybdis affinis rajungan Portunidae LEV F SW-FP
4 Tachypleus gigas* mimi Limulidae LEV O SW-E
5 Varuna yui kepiting, yuyu Varunidae LEV A SW-E-FP
6 Varuna literata kepiting, yuyu Varunidae LEV A SW-E-FP
7 Penaeus monodon udang windu Penaeidae HEV O SW-E-FP
8 Metapenaeus ensis udang putih Penaeidae HEV A SW-E
9 Lithopenaeus vannamei udang vanamei Penaeidae HEV A SW-E-FP
10 Penaeus merguiensis udang putih Penaeidae HEV F SW-E
11 Alpheus spp udang Alpheidae NEV F SW-E
Remarks: Potential: Et: High Economic Value; Er: Low Economic Value; NE: No Economic Value Abnd : Abundance; A: abundant; F: frequently found; O: occasionally found; R: rarely found Location : E: Estuary; SW: Sea Waters; FP: Fishpond Waters and Water Channel * Conserved based on State Regulation Nr. 07 Year 1999
One of the finfish having no economic value but frequently caught is buntek
(Tetraodon nigroviridis).
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 83 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Table 3.43. Preparation of Finfish in Lamong Bay
Species Local Name Preparation
Finfish
Mugil cephalus gereh sold in fresh or salted condition
Chanos chanos bandeng sold in fresh or smoked condition
Thryssa baelama gereh laut sold in fresh condition
Scatophagus argus kiper sold in fresh condition
Tylosurus crocodylus lujung sold in fresh condition
Elops hawaiiensis selek sold in fresh condition
Liza subviridis gereh sold in fresh or salted condition
Eleutheronema tetradactylum laosan sold in fresh or salted condition
Nematolosa come gereh sold in fresh condition
Anodontostoma chacunda - sold in fresh condition
Lobotes surinamensis - sold in fresh condition
Glossogobius aureus belosoh sold in fresh condition
Butis butis belosoh sold in fresh condition
Esqualosa thoracata teri sold in fresh or salted condition
Atherinomorus duodecimalis teri sold in fresh or salted condition
Pseudapocryptes lanceolatus - sold in fresh condition
Glossogobius biocellatus belosoh sold in fresh condition
Arius maculatus keting, manyung sold in fresh or smoked condition
Mystus nemurus keting, manyung sold in fresh or smoked condition
Arius argyropleuron keting, manyung sold in fresh or smoked condition
Arius nenga keting, manyung sold in fresh or smoked condition
Gerres argyreus kapasan sold in fresh or salted condition
Cynoglossus lingua ikan lidah sold in fresh or salted condition
Setipinna taty gereh sold in fresh or salted condition
Nibea soldado gulamah sold in fresh or salted condition
Oreochromis niloticus mujair nila sold in fresh condition
Monopterus albus belut sawah sold in fresh condition
Channa striata gabus, kuthuk sold in fresh or salted condition
Lagocephalus lunaris buntek sold in salted
Lagocephalus spadiceus buntek sold in salted condition
Shellfish
Scylla olivacea kepiting bakau sold in fresh condition
Scylla paramamosain kepiting bakau sold in fresh condition
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 84 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Species Local Name Preparation
Finfish
Charybdis affinis rajungan sold in fresh condition
Tachypleus gigas mimi sold in fresh condition
Varuna yui kepiting, yuyu sold in fresh condition
Varuna literata kepiting, yuyu sold in fresh condition
Penaeus monodon udang windu sold in fresh condition
Metapenaeus ensis udang putih sold in fresh condition
Lithopenaeus vannamei udang vanamei sold in fresh condition
Penaeus merguiensis udang putih sold in fresh condition
Source : Survey Result
The low economic value finfish commonly caught by the seine or dragnet are
among other things : buntek (Lagocephalus spp), peperek/gereh (Leiognathus spp,
Gazza spp), kapasan (Gerres filamentosus), kerong-kerong (Terapon jarbua) and
some others from family of Gobiidae (Pseudapocryptes lanceolatus and Glossogobius
spp). In the estuaries surrounfing Lamong Bay, particularly in the estualy of Sememi
River, it commonto find bubu (a kind of fish trap). The finsfish commonly trapped in
the bubu are : belosoh (Butis butis, Glossogobius spp and Pseudapocryptes
lanceolatus), ikan lidah (Cynoglossus lingua, Paraplagusia bilineata) and
belanak/gereh.
The shellfish, such as : crab and shrimp, are generally caught by means of
baits (e.g. : Scylla spp) or bubu in the estuaries (e.g. : Varuna spp, Penaeus spp and
Metapenaeus spp). Scylla is more frequently caught in mangrove vegetation area,
while others are generally caught in estuary waters. Crab (Scylla) and shrimps, such
as : udang windu (Penaeus monodon) and udang putih (Metapenaeus ensis, Penaeus
merguiensis), are of definitely high economic value.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 85 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
d. Bentik Macrofauna
Bentik macrofauna sampling points are the same as the sampling point of
plankton. The benthos found surrounding Lamong Bay comprises 16 species (Table
3.44). In general, the diversity and abundance of the macrofauna are categorized
low. It is alleged that such a condition is due to and related with muddy substrate
that is relatively unstable and contains oxygen (anoxic) and a lot of organic
matters.
The macrofauna diversity index in the studied area ranges from „very bad‟ to
„good‟ (Table 3.45.). Based on the aforementioned descriptions, it is conclusive that
the structure of macrofauna is unstable and vulnerable to disturbances.
Table 3.44. Compositions and Abundance of Bentik Macrofauna Surrounding Project Site Waters
Nr. Species Family P1 L1 M1 M2
1 Schaparca inaequivalvis Arcidae 2 - - -
2 Nereis virens Nereidae 1 - 4 -
3 Buccinum sp Buccinidae 1 1 - 3
4 Tellina Tellinidae 1 20 1 3
5 Schaparca inaequivalvis Arcidae - 1 - -
6 Macrophthalmus sp - - 1 -
7 Oliva sp Olividae - - 4 7
8 Pupina compacta - - 5 -
9 Pictoneritina sp Neritidae - - 4 12
10 Nassarius sp Nassariidae - - 5 98
11 Baruna sp - - 1 -
12 Pupina compacta - - - 34
13 Tellina Tellinidae - - - -
14 Buccinum (pj) Buccinidae - - - -
15 Volema myristica - - - 8
16 Corbicula javanica Corbiculidae - - - 1
Total 5 22 25 166
Indeks Keanekaragaman 1,332 0,452 1,910 1,281
Source : Survey Result
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 86 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Table 3.45. Degree of Pllution and Diversity Index
Degree of Pollution Diversity Index
Not Polluted 2,0
Lightly Polluted 2,0 – 1,6
Fairly Polluted 1,5 – 1,0
Heavily Polluted 1,0
Figure 3.41. Compositions and Diversity Index of Benthos in Project Site Waters in Pelindo Pier
Source: Survey Result
0
20
40
60
80
100
120
140
160
180
P1 L1 M1 M2
4 3 8 85
22 25
166
1,33 0,45 1,91 1,28
Axi
s Ti
tle
Stasiun
Komposisi jenis dan H' Makrobentos
jumlah jenis
Total
Indeks Keanekaragaman
H’ Macrobenthos Compositions
Station
Compositions
Total
Diversity Index
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 87 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
3.2.3. Terrestrial Flora and Fauna
Flora (Mangrove Vegetation)
The initial description of terrestrial flora is focused onmangrove vegetatio as
the project site of port development in Lamong Bay is in coastal ecosystem and the
representative and relevant terrestrial vegetation is mangrove. Mangorove
ecosystem is an ecosystem with tropical community vegetation growing the coastal
area and river estuaries. Mangrove ecosystem is affected by tide and is sensitive to
environmenta changes, such as : salinity, shallowing, oil spills and sedimentation.
The parameters adopted for observing the initial conditions of the mangrove
environment and ecosystem is vegetation density per hectare (tree/Ha), Important
Value Index and Mangrove Coverage Area (%).
The analysis on mangrove vegetation is conducted in 8 observation point in
North Galang Island, South Galang Island, Lamong River Border, Sememmi River
Estuary, Branjangan River Estuary, Project Site, Greges River Estuary, and Anak
River Restuary. The mangrove vegetation is not conserved as the mangrove
conservation in directed to the Eastern Coastal Area of Surabaya City, saved for
Galang Island. The East Java Provincial Government plans to plot Galang Island as a
conservation area for coastal birds.
The are 25 kinds of mangrove vegetations growing in in Lamong Bay, 23 of
them are true mangroves abd the rest 12 are associate mangrove s as presented in
Table 3.46.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 88 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Table 3.46 Mangrove Diversity in Lamong Bay
Nr. Species Indonesian Name Family Denst. Stat.
True Mangrove
1 Acanthus ilicifolius Jeruju, deruju Acanthaceae NA A
2 Acanthus ebracteatus Jeruju, deruju Acanthaceae NA A
3 Avicennia alba api-api Avicenniaceae 134-3367 A
4 Avicennia marina api-api putih Avicenniaceae 167-934 A
5 Avicennia officinalis api-api Avicenniaceae 200-2767 F
6 Rhizopora mucronata tanjang, bakau Rhizoporaceae 67-1534 A
7 Sonneratia alba Bogem Sonneratiaceae 67-200 A
8 Sonneratia caseolaris Bogem Sonneratiaceae 234-1634 F
9 Xylocarpus moluccensis Nyiri Meliaceae 34 F
10 Rhizopora apiculata tanjang, bakau Rhizoporaceae 334-567 A
11 Aegiceras corniculatum gedangan, kacangan Myrsinaceae 134 F
12 Bruguiera gymnorrhiza tanjang, bakau Rhizoporaceae 167 F
13 Exoecaria agallocha kayu wuta Euphorbiaceae NA F
Associate Mangrove
1 Thespesia populnea waru laut, warulot Malvaceae 134 F
2 Hibiscus tiliaceus Waru Malvaceae NA F
3 Sesuvium portulacastrum Alur Portulacaceae NA A
4 Acrostichum aureum paku laut Polypodiaceae NA F
5 Calotropis gigantea Widuri Asclepiadaceae NA A
6 Clerodendrum inerme Keranji Verbenaceae NA O
7 Derris trifoliata Kambingan Fabaceae NA F
8 Finlaysonia maritima basang siap Euphorbiaceae NA F
9 Ipomoea pes-caprae teracak kambing Convolvulaceae NA F
10 Passiflora foetida permot, rombusa Passifloraceae NA A
11 Stachytarpeta jamaicensis pecut kuda Verbenaceae NA A
12 Wedelia biflora seruni laut Asteraceae NA A
Remarks : Desnt. : Density Sta.: Status of Abundance (Qualitative); A: Abundant; F: Frequently Found; O:
occasionally Found; R: Rarly Found
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 89 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
With reference to the mangrove primary data, it shows that the most
abundant is api-api (Avicennia marina) (density 167-934 tress per hectare, INP
35.288%), bogem (Sonneratia alba) (density 67-200 trees per hectare, INP 24.965%),
api-api (Avicennia alba) (density 134-3.367 trees per hectare, INP 114.935%), and
tinjang/bakau (Rhizopora mucronata) (density 67-1.534 trees per hectare, INP
47.053%). Other abundant kinds of magrove are api-api (Avicennia officinalis)
(density 200-2.767 trees per hectare, INP 30.322%) and tinjang (Rhizopora apiculata)
(density 334-567 trees per hectare, INP 26.606%). Although Avicennia marina and
Sonneratia alba have lower density compared to other kinds, these two kinds have
widrer spreadand are found in many points in the studied area.
Most of associate mangroves are found in fishpond areas, instead of in
coastal area directly contacting with the seawater. This is due to physiological
factors, where most of associate mangroves need more supply of water with lower
tidal inundation. They area kayu wuta (Exoecaria agallocha), waru laut (Thespesia
populnea), waru (Hibiscus tiliaceus), rombusa (Passiflora foetida), pecut kuda
(Stachytarpeta jamaicensis) and seruni laut (Wedelia biflora) as well as keranji
(Clerodendrum inerme).
In contrast to those associate mangroves, there are some other kinds that are
more commonly found in inundated mangrove forest on periodical basis, for
instance: kambingan (Derris trifoliata), basang siap (Finlaysonia maritima) and alur
(Sesuvium portulacastrum).
Mangrove Zoning
Mangrove zonation in Lamong Bay generally follows Asia-Pacific zoning ,
ehere the open (front) mangroves are dominated by Avicennia spp mixed with
Rhizopora spp and Sonneratia spp as well as Aegiceras corniculatum.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 90 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
In back of the open (front) zone, there is a middle zone where Bruguiera
gymnorriza, Rhizopora spp, Sonneratia spp, Xylocarpus moluccensis and Aegiceras
corniculatum are commonly found. In back of the middle zone, there is an in-land
associate mangrove zone.
Brackish mangrove zone is found along the borderline of Lamong River and
Sememi River, up to ± 2 km distance from the estuary or the coast. The vegetations
commonly found in brackish mangrove zone in Lamong River are among other things
Avicennia alba, Avicennia marina, Sonneratia caseolaris, Rhizopora mucronata,
Hibiscus tiliaceus and Acanthus spp, while the ones in Sememi River is dominated by
Rhizopora spp, Avicennia officinalis, Avicennia alba, Avicennia marina, Sonneratia
caseolaris and Acanthus spp.
Fauna
The study on fauna covers aviafauna, reptile, mammals and land arthropoda.
The primary data collected from field observation and secondary data collected
from various sources show that the mangrove area and fishpond area surrounding
Lamong Bay become the habitat of at least 50 bird species, 7 reptile species, 6
mammals species and 39 arthropoda species.
Figure 3.42. General Pattern of Mangrove Zoning in Asia-Pacific Area
mangrove terbuka mangrove tengah mangrove daratan
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 91 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
a. Avifauna
Of the 50 bird species found in Lamong estuary , 24 of them (47.059%) are
categorized as water birds, the rest 27 species (52.941%) are categorized as land
birds (terrestrial, arboreal and aerial). The compositions of the birds in Lamong Bay
are presented in Table 3.47.
Most water birds are commonly found in mangrove area along the coasts of
Galang Island. This is due to availability of feeds for the water birds. In the front
East part of Galang Island there is mudflat formed due to sedimentation and
exposed during low tide. The mudflat becomes a perfect habitat for various bentik
macroinvertebrata, such as mollusca, crustacea and polychaeta that serve as source
of foofd for various water birds. Occordingly, during low tide, there are a lot of birds
(in term of diversity and abundance) land on the mudflat to search for food.
The waterbirds commonly found are kuntul kecil (Egretta garzetta), cangak
besar (Ardea alba), kowak-malam kelabu (Nycticorax nycticorax), gajahan pengala
(Numenius phaeopus) and dara-laut biasa (Sterna hirundo). They (saved for dara-
laut) are visible when searching for food on the mudflat and stand on the mangrove
crown. The waterbirds, such as : Sterna spp and Chlidonias spp are more frequently
found flying in the air, since they watch over their preys directly from the air and
quickly dive on the sea water to catch their food.
Cekakak (Halcyon spp), remetuk laut (Gerygone sulphurea) and cipoh kacat
(Aegithina tiphia) lare frequently found in the mangrove area surrounding the
estuary, while tekukur biasa (Streptopelia chinensis), punai gading (Treron
vernans), kacamata biasa (Zosterops palpebrosus), cinenen (Orthotomus spp), caladi
(Dendrocopos spp), dederuk jawa (Streptopelia bitorquata), cucak and merbah
(Pycnonotus spp), kipasan belang (Rhipidura javanica), perenjak (Prinia spp), bondol
(Lonchura spp), raja-udang biru (Alcedo coerulescens) and bubut alang-alang
(Centropus bengalensis) are more frequently found in the West, i.e. : fishpond area
in back of mangrove belts where there are a lot of bushes and semak and clumps.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 92 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
There are 18 bird species (35.94%) in the estuary of Lamong River conserved
by the Indonesian State Regulation Number 05 Year 1990 about Conservation of
Natural Bilological Resources and Their Ecosystem, and Indonesian State Regulation
Number 07 Year 1999 about Species of Conserved Birds. Further, 13 migrant bird
species (25.49%) and 1 endemic bird species (1.96%) are also found.
Bangau bluwok (Mycteria cinerea) is definitely rare and nationally conserved.
It is listed in the Appendix I of CITES, in the sense that it is trictly prohibited to buy
and sell this bird, either in alive, dead or processed state of condition. It is
categorized as Vulnerable/(VU) speciesin the Red List ofIUCN.
Although it is not yet nationally conserved, cerek jawa (Charadrius javanicus)
is an endemic species in Indonesia and categorized as Near Threatened (NT) in the
Red List of IUCN. It has extremely limited spread and population and is only faound
in Java Island. During the field observation, elang bondol (Haliastur indus) nationally
conserved and listed in Appendix II odCITES, is also found. It is categorized as
predator widely spread to India, South China Selatan to Australia. It is fairly
frequent to find it in Sumatera Island and Kalimantan Island, yet, seldom found in
Java Island and Bali Island. It has various food habits; among other things : shrimps,
crabs, fish or alike. It sometimes eat small chickens, some kinds of insects and small
mammals.
The existence of these 3 kinds of birds in the mangrove area in Galang island
shows that the mangrove ecology in Galang Island functions as habitat for bird
community , including water birds and migrantbirds. Some conserved and nearly
threatened birds are sometimes found to nest and the mangrove area in Galang
Island, such as : kowak-malam kelabu, blekok sawah dan kuntul kecil.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 93 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Table 3.47. Avifauna Diversity in Lamong Estuary
Nr. Species Indonesian Name Family Status
UU IUCN CITES Mig. End. Kel.
1 Gerygone sulphurea remetuk laut Acanthiziidae - - - - - A
2 Haliastur indus elang bondol Accipitridae AB - II - - O
3 Aegithina tiphia cipoh kacat Aegithinidae - - - - - F
4 Alcedo coerulescens raja-udang biru Alcedinidae AB - - - - F
5 Halcyon sancta cekakak australia Alcedinidae AB - - - - F
6 Collocalia linchi walet linci Apodidae - - - - - A
7 Ardea alba cangak besar Ardeidae AB - - N<> - A
8 Ardeola speciosa blekok sawah Ardeidae B - - - - F
9 Bubulcus ibis kuntul kerbau Ardeidae AB - - N<> - F
10 Butorides striata kokokan laut Ardeidae - - - - - A
11 Egretta garzetta kuntul kecil Ardeidae AB - - - - A
12 Egretta intermedia kuntul perak Ardeidae AB - - N<> - O
13 Ixobrychus cinnamomeus bambangan merah Ardeidae - - - N< - O
14 Nycticorax nycticorax kowak-malam kelabu Ardeidae - - - N< - A
15 Ixobrychus flavicollis bambangan hitam Ardeidae - - - - - O
16 Ixobrychus sinensis bambangan kuning Ardeidae - - - N<> - R
17 Nycticorax caledonicus kowak-malam merah Ardeidae AB - - - - R
18 Charadrius javanicus cerek jawa Charadriidae - NT - - E O
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 94 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Nr. Species Indonesian Name Family Status
UU IUCN CITES Mig. End. Kel.
19 Mycteria cinerea bangau bluwok Ciconiidae AB VU I - - R
20 Streptopelia bitorquata dederuk jawa Columbidae - - - - - O
21 Streptopelia chinensis tekukur biasa Columbidae - - - - - F
22 Treron vernans punai gading Columbidae - - - - - R
23 Crypsirina temia tangkar centrong Corvidae - - - - - R
24 Centropus benghalensis bubut jawa Cuculidae - - - - - R
25 Dicaeum trochileum cabai jawa Dicaeidae - - - - - O
26 Lonchura leucogastroides bondol jawa Estrildidae - - - - - A
27 Lonchura punctulata bondol peking Estrildidae - - - - - O
28 Lonchura maja bondol haji Estrildidae - - - - - O
29 Hirundo striolata layang-layang loreng Hirundinidae - - - - - F
30 Hirundo tahitica layang-layang batu Hirundinidae - - - - - A
31 Merops philippinus kirik-kirik laut Meropidae - - - - - F
32 Cinnyris jugularis burung-madu sriganti Nectariniidae AB - - - - A
33 Dendrocopos macei caladi ulam Picidae - - - - - O
34 Dendrocopos molluccensis caladi tilik Picidae - - - - - O
35 Pycnonotus goiavier merbah cerukcuk Pycnonotidae - - - - - F
36 Rhipidura javanica kipasan belang Rhipiduridae AB - - - - A
37 Actitis hypoleucos trinil pantai Scolopacidae - - - N<> - F
38 Numenius phaeopus gajahan pengala Scolopacidae AB - - N<> - A
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 95 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Nr. Species Indonesian Name Family Status
UU IUCN CITES Mig. End. Kel.
39 Tringa totanus trinil kaki-merah Scolopacidae - - - N<> - R
40 Chlidonias hybridus dara-laut kumis Sternidae AB - - N<> - F
41 Chlidonias leucopterus dara-laut sayap putih Sternidae AB - - N<> - A
42 Sterna albifrons dara-laut kecil Sternidae AB - - N<> - F
43 Sterna hirundo dara-laut biasa Sternidae AB - - N<> - A
44 Sterna sumatrana dara-laut tengkuk-hitam Sternidae AB - - - - F
45 Orthotomus sepium cinenen jawa Sylviidae - - - - - O
46 Orthotomus sutorius cinenen pisang Sylviidae - - - - - R
47 Prinia flaviventris perenjak rawa Sylviidae - - - - - F
48 Prinia inornata perenjak padi Sylviidae - - - - - A
49 Cisticola juncidis cici padi Sylviidae - - - - - O
50 Zosterops palpebrosus kacamata biasa Zosteropidae - - - - - A
Source: Survey Result (2012)
Remarks : UU : Protection by Indonesian State Regulation A : Abundant
A : Act Nr, 5 Year 1990 F : Frequently Found
B : Act Nr. 7 Year 1999 O : Occasionally Found
IUCN : Threatened Status R : Rarely Found
CITES : International Trade Regulation Status under CIDES
(Convention on International Trade of Endangered Species of Wild Fauna and Flora)
Mig. : Migration Status
End. : Endemicity Status
Kel. : Abundance Status
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 96 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
3.3. SOCIO-ECONOMIC AND CULTURAL COMPONENTS
3.3.1. Demography
3.3.1.1. Population Number and Density
Administratively,the studied area covers Asemrowo Sub-district
(Tambaklangon Village, Greges Village and Kalianak Village), Krembangan Sub-
district (Morokrembangan Village) and Benowo Sub-district (Tambakoso Wilangon
Village and Romokalisari Village). With a total area of about 27,701 km2 and total
polupation of about 56.155, it is conclusive that the polpulation density in the
studied area is pretty high, i.e. : 2,027 persons/km2. The most densely populated
Morokrembangan Village, with population density of 13,244 persons /km2, as
detailed in Table 3.47.
Table 3.48. Population Number and Density in Studied Area Sub-district Village Area
Population Number (Persons)
Population Density (Persons/km2)
Asemrowo Tambaklangon 2.28 2,190 961
Greges 4.19 4,542 1,084
Kalianak 2.02 1,649 816
Krembangan Morokrembangan 3.171 41,997 13,244
Benowo Tambakoso Wilangon
8.46 3,557 420
Romokalisari 7.58 2,220 293
Source : Sub-district in Numbers, Statistical Bureau 2011
The popuations based on gender are presented in Table 3.49, where the
sex ratio in 6 villages in the studied area ranges from 99.72 to 108.77. It shows
that the ratio in Tambaklangon Village and Kalianak Village, Asemrowo Sub-
district and Romokalisari Village, Benowo Sub-district, have more male
residents than the female ones.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 97 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Table 3.49. Population based on Age, Sex and Sex Ratio
Sub-district Village Populations
Sex Ratio Male Female Total
Asemrowo Tambak langon
1,141 1,049 2,190 108.77
Greges 2,283 2,259 4,542 101.06
Kalianak 845 804 1,649 105.1
Krembangan Morokrembangan 21,285 20,712 41,997 102.76
Benowo Tambakoso wilangon
1,776 1,781 3,557 99.72
Romokalisari 1,144 1076 2,220 106.32
Source : Sub-district in Numbers, Statistical Bureau 2011
3.3.1.2. Population Based on Age
More than 50% of the population in the studied area are > 17 years old. In
Tambaklangon Village, most of the populations are aged 26 – 40 years old
(24.38%), aged 41 – 59 years old (21.14%). In Greges village, most of the
population are aged 41 – 59 years old (20.12%), and aged 0 – 5 years old (20.04%).
In Morokrembangan Village 30.89% of the population are aged 41 – 59 years old.
In Romokalisari Village and Tambak Osowilangun Village most of the populations
are aged 26 – 40 years old (28.02% and 24.46%). It is conclusive that based on the
monograph data most of the populations are in productive working age, i.e. : 26 –
40 years old and 41 – 59 year old. The complete data are presented in Table
3.49.
Table 3.50 Population Based on Age
Nr Age Range
Asemrowo Sub-district Krembangan Sub-district
Benowo Sub-district
Tambak Langon
Greges Kalianak Moro
krembangan Tambak
Osowilangun Romokalisari
Percentage (%)
Percentage (%)
Percentage (%)
Percentage (%) Percentage (%)
Percentage (%)
1 0 – 5 8,90 20,04 15,10 9,16 18,39 13,24
2 6 – 9 7,12 10,48 5,03 5,50 8,35 8,51
3 10 – 16 10,27 10,11 9,58 10,29 8,04 10,00
4 17 2,88 6,85 1,88 1,83 4,02 2,03
5 18 – 25 15,07 13,08 10,67 12,13 14,65 14,59
6 26 – 40 24,38 15,46 20,56 24,96 24,46 28,02
7 41 – 59 21,14 20,12 14,68 30,89 17,15 21,04
8 60+ 10,23 3,87 22,50 5,24 4,95 2,57
Total 100 100 100 100 100 100
Source : Sub-district in Numbers, Statistical Bureau 2011
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 98 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
3.3.1.3. Population Based on Education Level
The education levels in the studied Area greatly vary, from illiterate, Not
completing elementary school, elementary school, Junior High School, Senior
High School, Baccalaureate Program and Master Program.
In Tambaklangon Village, most of population graduate from Elementary
School (46.6%), Senior High School (25.76%). In Greges Village, majority of its
populations are graduated from Senior High School (63.86%), Elementary School
(24.41%) and Junior High School (6.41%). In Kalianak Village most of the
population are graduated from Senior High School (65.93%), in Romokalisari
Village the population are graduated from Elementary School (24.52%), Junior
High School (15.54%) and Senior High School (33.68%). In Tambak Osowilangon
Village , most are graduated from Elementary School (31.11%), Senior High
School (25.43%) and Junior High School (19.85%). With reference to those data, it
shows that the education levels in the studied area are pretty good as most of
the population graduate from Senior High School. Unfortunately, the ones
graduated from higher education is still few (< 6%). The complete data are
presented in Table 3.50.
Table 3.51. Percentage Based on Education Level
Nr Education Level
Asemrowo Sub-district Benowo Sub-district
Tambak Langon
Greges Kalianak Tambak
Osowilangun Romokali-
sari
Percentage (%)
Percentage (%)
Percentage (%)
Percentage (%)
Percentage (%)
1 Illiterate 0.00 0.00 0.00 12.55 12.44
2 Not Grad from El. Sch 0.00 0.00 0.00 7.56 8.89
3 Elementary School 46.86 24.41 14.68 31.11 24.52
4 Junior High School 19.82 6.41 18.53 19.85 15.54
5 Senior High School 25.76 63.86 65.93 25.43 33.68
6 Associate Degree 0.00 1.18 0.00 0.40 0.63
7 Baccalaureate Degree 2.07 0.48 0.78 0.40 0.72
8 Master Degree 5.49 3.49 0.07 2.40 2.33
Doctorate Degree 0.00 0.17 0.00 0.31 1.26
Total 100 100 100 100 100
Source : Sub-district in Numbers, Statistical Bureau 2011
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 99 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
3.3.1.4. Community Welfare Degree
Table 3.52 presents welfare classifications a in the community in the
studied area. > 50% of the families in Morokrembangan Village are classified
prosperous II, next 28.79% are classified Prosperous III+. In Kalianak Village the
families classified Prosperous II are 36.56% while in Greges Village 26.08% are
classified the same. The families in Kalianak Village 16. 77% of the families are
classified Pre-Prosperous, but most of them are classified Prosperous II
(36.56%), and the least are classified Prosperous III+ (2.80%). In Tambak
Osowilangun Village and Romokalisari Village the families are successively
classified Prosperous II, Prosperous III and Prosperous I.
Based on the data supplied by Statistical Bureau 2011, the proportion of
poor family is mostly found in
Tambaklangon Village, Morokrembangan Village and Tambak Oso
Wilangon Village, i.e. : > 27%. Further details arepresented in Table 3.52.
Table 3.52. Proportion of Degree of Welfare
Nr
Descriptions
Asemrowo Krembangan Benowo
Tambak Langon
Greges Kalianak Moro
krembangan Tambak
Osowilangun Romokalisari
% % % % % %
Degree of Welfare
1 Pre-Prosperous
11.97 10.84 16.77 8.03 14.30 16.14
2 Prosperous I 27.38 18.77 33.76 11.40 20.06 17.11
3 Prosperous II 37.70 26.08 36.56 51.79 35.55 30.00
4 Prosperous III 17.54 25.99 10.11 0.00 22.54 27.71
5 Prosperous III+ 5.41 18.33 2.80 28.79 7.55 9.04
Total 100 100 100 100 100 100
Poversity
Total Poor Family
240 36 35 2.236 288 127
Percentage (%)
39% 3% 8% 30% 27% 14%
Source : Sub-district in Numbers, Statistical Bureau 2011
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 100 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
3.3.1.5. Unemployment Data
The information on unemployment are presented in Table 3.53. In
Morokrembangan Village, of the 4,792 familiy heads, terdapat 432 of them are
jobless (9%). The similar condition is also found in Romokalisari Village, where
about 11% of the family heads are jobless. In Tambak Osowilangon Village the
proportion is even greated (20%). In short, the degree of unemployment in
Morokrembangan Village, Tambak Osowilangon Village and Kalianak Village are
quite serious.
Table 3.53. Unemployed and Unemployed Family Heads
SUB-DISTRICT Asemrowo Krembangan Benowo
VILLAGE Tambak Langon
Greges Kalianak Moro
krembangan Tambak
Osowilangun Romokalisari
Total Family Head
598 1.304 444 4,792 877 546
Employed Family Heads
*) *) *) 4,360 701 486
Unemployed Family Heads
*) *) *) 432 176 60
Unemployed Residents
80 115 923 1,157 1,314 60
Male *) *) *) 621 510 17
Female *) *) *) 536 804 43
Remarks: *) = No data available
Source : Sub-district in Numbers, Statistical Bureau 2011
3.3.2. Social Life in Studied Area
Ihe information on social life in the studied area was collected from the
results of survey conducted on the first week in September 2012. The total
respondents were 20, majorly male aged 35 - 75 years. The respondent statuses
in the community were, inter alia : village officer (4 respondents), Head or Board
Member of HNSI/Nelayan/PKK (12) respondents and public figures (4
respondents).
3.3.2.1. Social Interaction
The social interactions in the studied area run well in harmonious,
intimate and conducive state of social conditions. Each of the residents knows
each other. Conflicts in the community are very rare. In case of conflicts, they
are is settled through forums of RT/ RW/ village/internal group. Yet, the
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 101 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
conflicts are not serious and do not affect the community order and security as
they are minor ones and concern with seasonal migrants in the studied area.
Most of the public figures well-respected and playing important roles in
settling conflicts are principals of Islamic schools/religious leaders, Head of LKMK
and senior public figures.
The aspirations of the community can be directly or indirectly addressed
to the village administrator/officer. Some are directly addressed to project
officers (in this case Pelindo officers). The aspirations are addressed in form of
oral or written proposals. Indirect proposal are usually addessesed via the
representative (RT)or community. In certain projects, the addresses invlove
related organization/group, such as : LKMK or BKM or fisherman society though
amicable discussion. In case their addresses are not responded, they will address
them through demonstration, as the one conducted in Tambak Langon Village,
due to decreased number of fish in Lamong Bay.
3.3.2.2. Existing Communal Societies
There are 2 (two) communal societies actively operates : LKMK and HNSI.
The earlier is a partner to village government and serves as mediator between
the surrounding community and the village government.
The latter is existing official fisherman society in the studied area,
besides there area some independent fisherman society. This independent entity
is established due to some conflicts with Pelindo. Their function is to
accommodate and facilitate the aspiration/discussion among the fishermen. They
are actively engaged in the line with their societal activities and claims for
reimbursements due to breaches to commitment between Pelindo and the
community.
3.3.3. Fisherman Life
In fishing, the fishermen use 3 (three) fishing instruments, namely :
cager, net and pancal. They use boats called baito (6 x 1,25 m), each with 2-5
crew. The fishing time depends on the tide. Most or > 50% of the caught fish
are directly sold in the market, the rest are sold to brokers. Particulary for
rajungan or jangkang, they buyers will pick them up.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 102 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
The income of the fisherman (per day/month or in accordance with the
method adopted by the fishermen) decreases. They used to take average
income of IDR 50,000 per day, or it ranges between IDR 75.000 to IDR 100,000.
At present, they only earns IDR 20,000 to IDR 30,000 per day, and sometime
even have no gain.
3.3.4. Community Perception
Based on the results of interview with public figures and fishermen, 70%
respondents perceive that the project of PT. Pelindo IIIbadly affect the fishing
activities of the fishermen. During year 2009 – 2012, there had been alot of
change of professionfrom fishermen to salt porter. It was due to drastica drop of
income from fishing. On the other hands, ther are still fishermen keep doing
their jobs, although they frequently do not go fishing. The drop of fisherman
income is significant, from IDR 75.000 to IDR 100,000 per day to IDR 20,000 to IDR
30,000 per day. The change of profession and drop of fisherman income is due to
reclamation in their fishing ground, i.e. Lamong Bay, leading to drastically
getting less fish to catch.
Based on the results of interview, there area 3 (three) perceptions
concerning the port development plan as follows :
Agreeing (55 %), as it is pro project of government that will entail job
openings and bring expectation for better economic conditions in the
community.
Disagreeing (35 %), is it leads to decreased fisherman income due to
less number of fish to catch. Fishermen worry about being loosing their
jobs.
Abstaining (10 %), as they do not know about the project and do not
feel the effects of the project.
The issues worrying the community are :
Damaged sea environments, characterized with loss of fish and ridge
of rocks in the studied area, damaged sea ecosystem, environmental
pollution due to project wastes, less numbe of fish to catch due to
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 103 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
damaged fish habitat, for instance : rebon shrimp habitat. The
protest as the reclamation cuts their fishing ground and make some
of them jobless.
The respondents perceives that PT. Pelindo III has breached the
reclamation commitment. They commit to reclaim for 600 m. In fact
they have dome for 3 km reclamation.
Infrastructure condition : Damaged roads due to heavy dty dump trucks
accessing area surrounding the project site(Kalianak).
Less dwelling area, threats of floods due to narrowing channels to the
sea.
Large vessels potentially hindering fish to go to the coastal area.
Change of function of areas, especially in the coasastline. Ledaing to
problems to fishermen and fishpond farmers.
Shallowing condition in Kandangan River causing problems to
fisherman activities.
The respondents expect that there will be aids to fishermen in form of
supply of modern boats so that they can go fishing in deep sea and job openings
to fishermen in the project or soft working loans, skill trainings, scholarships for
the residents. Besides, the also expect compensation, relocation or new
settlement area, especially for the residents of Romokalisari Village and
mangrove massive planting for saving the environment.
Based on the proposals addessed to PT. Pelindo III, they claim for, inter
alia:
- Compensation (cash and basic needs) for those fishermen having less
income
- Compensation (in form of TV and refrigerator) for tadahan (a kind of
fish catching instrument) to 8 fishermen
- Aids to fisherman cooperative/organization
- Construction of fisherman guard post
- Construction of access to village cemetary in RW 1, Tambakoso
Wilangon Village
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 3 – INITIAL ENVIRONMENT DESCRIPTION
III - 104 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
- Construction of riprap
- Dredging of Kandangan River on Jl Tambakoso Wilangon, RT 01/RW
04
- Dredging of mud in the fisherman boat routes.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 1 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
CHAPTER 4 SCOPE OF STUDY
Tanjung Perak Port Development in Lamong Bay is currently on
construction phase. In view of the on-progress constructions, the impacts to the
surrounding environment are identifiable. Based on the identified impacts,
further predictions of impacts will be studied due to some modifications both
designs and project sites. With reference to the predicted impacts, the
cumulativeness of the impacts driven by the existing activities potential to
change the areas of the impacts and pollutant concentration can be predicted.
4.1. SCOPING PROCESS
In order to assess the significant impacts to be studied (hypothetical
significant impacts) it calls for a scoping process. The scoping process comprises
identification of potential impacts and evaluation of optential impacts to identify
the hypothetical significant impacts to be further classified and prioritized.
Schematically, the scoping is presented in Figure 4.1.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 2 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 4.1. Scoping Process Flowchart
The addendum to EIA, EIM and EIO of Tanjung Perak Port Development in Lamong
Bay, Surabaya City, East Java Province in year 2012 onlt reviews the change of
activities not yet covered in the Environmental Impact Assessment 2010.
recommended by virtue of Decision of State Minister of Environment Number 256
Year 2010 dated 5 October 2010.
4.1.1. Potential Impact Identification
It studies the impacts of the activities due to the modification of designs
and change of project sites not yet covered in the Environmental Impact
Assessment 2010. recommended by virtue of Decision of State Minister of
Environment Number 256 Year 2010 dated 5 October 2010. The identification of
potential impacts of the activities by identifying the series of activities of
Tanjung Perak Port Development in Lamong Bay during the construction phase
and operation one. The identification of potential impacts by means of flowchart
method and matrix one are presented in Figure 4.2. and Table 4.1.
Activity Descriptions
Environment
Descriptions
Potential Impact
Evaluation
Potential Impact
Identification
Classification& Priority
Potential Impact
Hypothetical Significant
Impact
Hypothetical Significant
Impact Priority
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 3 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Table 4.1. Matrix of Potential Impacts of Tanjung Perak Port Development in Lamong Bay
ENVIRONMENTAL COMPONENTS
CONSTRUCTION OPERATION
Material and Equipment Mobilization
and Demobilization
Temporary Access
Port Construction Pier
Construction
Multipurpose Pier
Operation On-land Reclamation Material Transportation
Demolition of Erected
Temporary
Access
Connecting Bridge, Interchange Area,
Causeway, Container Yard and Trestle
Constructions
Dredging of Planned Port Pool
1 2 3 4 5
PHYSICAL- CHEMICAL
- Decreased Air Quality X X
- Increased Noise X X
- Decreased Seawater Quality X X X X
- Increased River Surface due to Runoff X
- Change of Water Current Pattern X X
- Decreased Road Performance X X
BIOLOGY
- Disturbance to Sea Biota X X X X
- Decreased Mangrove Ecosystem Area X X
SOCIO-ECONOMY AND CULTURE
- Community Unrest X X
- Disturbance to Fisherman Activity X X X X
- Job and Business Opportunities X
COMMUNITY HEALTH
- Decreased Health X
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 4 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
ACTIVITIES DIRECT POTENTIAL IMPACTS INDIRECT POTENTIAL IMPACTS
CONSTRUCTION PHASE Pre-Cast Material and Equipment Mobilization and Demobilization
Temporary Access
Figure 4.2. Potential Impact Flowchart of Tanjung Perak Port Development in Lamong Bay
Decreased Road Performance Decreased Air Quality
Community Unrest
Community Unrest
Decreased Health
Decreased Air Quality
On-land Reclamation Material Transportation
Increased Noise Community Unrest
Decreased Seawater Quality Demolition of Erected Temporary Access
Decreased Mangrove Ecosystem Area
Disturbance of Sea Biota
Disturbance to Fisherman Activity
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 5 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
ACTIVITIES DIRECT POTENTIAL IMPACTS INDIRECT POTENTIAL IMPACTS
CONSTRUCTION PHASE Port Construction
Pier Construction
Figure 4.2. Potential Impact Flowchart of Tanjung Perak Port Development in Lamong Bay (Cont.)
Decreased Seawater Quality Disturbance to Sea Biota
Disturbance of Fisherman Activities
Increased River Water Surface Change of Water Current Pattern and
Sedimentation
Constructions of connecting bridge, Interchange Area, Causeway, Container
Yard, and Trestle
Decreased Seawater Quality
Dredging of Planned Port Pool
Change of Water Current Pattern and
Sedimentation
Disturbance of Sea Biota
Disturbance to Fisherman Activity
Decreased Seawater Quality
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 6 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
ACTIVITIES DIRECT POTENTIAL IMPACTS INDIRECT POTENTIAL IMPACTS
OPERATION PHASE
Figure 4.2. Potential Impact Flowchart of Tanjung Perak Port Development in Lamong Bay (Cont.)
Multipurpose Terminal Operation
Decreased Seawater Quality
Decreased Air Quality
Decreased Road Performance
Disturbance to Fisherman Activities
Increased Noise
Decreased Mangrove Ecosystem Area
Disturbance to Sea Biota
Disturbance to Fisherman Activities
Community Unrest
Community Unrest
Community Unrest
Job and Business Opportunities
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 7 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
4.1.2. Potential Impact Evaluation
The potential impacts are evaluated to determine the hypothetical
impacts to the environment regarded relevant to be closely studied by excluding
the environmental components regarded irrelevant to study. The basis for for
determining the hypothetical significant impacts are, among other things, the
issued regarded important by the community surrounding the project site,
institutions in charge and experts.The method adopted is brainstorming by PT
Pelindo III assisted by the consultsnts of the initiator and discussion with exprts.
The descriptions of analysis on the hypothetical significant impacts are presented
in Table 4.2.
The results of the evaluationare presented in the flowchart in Figure 4.3
and matrix as presented in Table 4.3. The summary of the scoping process is
presented in Figure 4.4.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 8 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Table 4.2. Potential Impact Evaluation
PROJECT PHASE
COMPONENTS OF SOURCES OF IMPACTS
IMPACTS POTENTIAL IMPACT EVALUATION HS OR HI
CONSTRUCTION PHASE (Pre-Cast Material and Equipment Mobilization)
On –land Reclamation Material Transportation
Decreased Road Performance
The volume of reclamation material required for constructing the Intercahange Area will be ± 600,000 m3. It is predicted that the mobilized trucks during 3-month construction phase will be ± 30 units per hour or 355 units per day. The causeway will need ± 1,800,000 m3 reclamation material. In case the causeway construction can be completed in ± 3 months it is predicted that the mobilized trucks will be ±55 units per hour or 650 units. Accordingly, the impact on decreased road performance needs to be further assessed.
HS
Decreased Air Quality
It is predicted that the mobilized trucks for constructing the interchnage area during 3-month construction phase will be ± 30 units per hour or 355 units per day. During 3-month construction phase, the causeway construction will need to mobilize ±55 trucks per hour or 650 trucks. It is certainly potentia to decrease the air quality significantly. The decreased air quality is due to not only gas emission the the mobilized trucks as indirect impact but also dusts due to the truck mobility. Accordingly, it needs to be further assessed
HS
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 9 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
PROJECT PHASE
COMPONENTS OF SOURCES OF IMPACTS
IMPACTS POTENTIAL IMPACT EVALUATION HS OR HI
CONSTRUCTION PHASE (Pre-Cast Material and Equipment Mobilization)
On –land Reclamation Material Transportation
Increased Noise
It is predicted that the mobilized trucks for constructing the interchnage area during 3-month construction phase will be ± 30 units per hour or 355 units per day. During 3-month construction phase, the causeway construction will need to mobilize ±55 trucks per hour or 650 trucks.Accordingly, the impact on increased noise needs to be further assessed.
HS
Community Unrest
The decreased road performance, decreased air quality and increased noise due to the on-land reclamation material transportation activities for constructing the causeway and interchange area are jointly potential to drive impact on community unrest. However, the project site is relatively quite distant (±500 m) from the dwelling area. Besides, it is a derivative impact, in the sense that when the primary impact is well managed, it will be well coped with.
HI
Decreased Health
The decreased road performance and increased noise due to the on-land reclamation material transportation activities for constructing the causeway and interchange area are jointly potential to drive impact on community health. However, the project site is relatively quite distant (±500 m) from the dwelling area, and accordingly the impact is categorized to be hypothetical insignificant.
HI
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 10 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
PROJECT PHASE
COMPONENTS OF SOURCES OF IMPACTS
IMPACTS POTENTIAL IMPACT EVALUATION HS OR HI
CONSTRUCTION PHASE (Temporary Access)
Demolition of Erected Temporary Access
Decreased Seawater Quality
The temporary is 1,160 m length and 12 m wdth. It is constructed bt reclaiming shallow water with a total reclamation volume of 57,505 m3. The demolition of the temporary access with such a material volume will increase the Total Suspended Solids (TSS) and lead to turbidity surrounding the studied area. Accordingly, it needs to be further assessed.
HS
Disturbance to Sea Biota
The temporary access demolition is potential to cause turbidity in the waters and lead to decreased seawatwe quality and disturbance to sea biota. It will derive impact on decreased plankton/nekton composition and abundance. Unfortunately, based on the initial description the composition and abundance has relatively been poor (< 2.000 individu/liter of water). Accordingly, it needs to be further assessed.
HS
Disturabance to Fisherman Activities
The construction activities are started with demilition of erected temporary access. It will be potential to distrurb the fisherman activities due to prohibition to access the demolition area. It will lead to community unrest and needs to be further assessed
HS
Decreased Mangrove Ecosystem Area
During the demolition of erected temporary access there will be heavy duty equipment operated in the studied area. It will lead to narrower mangrove ecosystm area. The decreased mangrove ecosystem area will be a prime issue to the community unrest. Accordingly, it needs to be further assessed.
HS
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 11 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
PROJECT PHASE
COMPONENTS OF SOURCES OF IMPACTS
IMPACTS POTENTIAL IMPACT EVALUATION HS OR HI
CONSTRUCTED PHASE (Port Construction)
Constructions of connecting bridge, Interchange Area, Causeway, Container Yard, and Trestle
Decreased Seawater Quality
The decreased seawater quality Is due to shallow water reclamation for constructing some some port facilities as further detailed. The total area of Interchange Area will be 5,77Ha, comprising office area (113 m x 170 m = 19,120 m2) and parking lots 135 m x 285 m = 38,475 m2. The total reclamation volume will be 600,000 m3. The causeway will need ± 1,800,000 m3 reclamation material. The total volume of reclamation material for constructing the container yard is 2,800,000 m3. It also needs 1,110,000 m3 relamation material for constructing dry bulk yard. The activities are jointly potential to decrase the seawater quality. Accordingly, it needs to be further assessed.
HS
Disturbance to Sea Biota
The shallow awater reclamation will certainly lead to loss of sea biota habitat as wide as the reclmated area. It will drive disturbance to sea biota and derive impact on decreased plankton/nekton composition and abundance. Unfortunately, the composition and abundance has relatively been poor (< 2.000 individu/liter of water). Accordingly, it needs to be further assessed.
HS
Disturabance to Fisherman Activities
The shallo water reclamation activities will entail prohibition for fishermen to access the project site. It will be potential to distrurb the fisherman activities due to prohibition to access the demolition area. It will lead to community unrest and needs to be further assessed.
HS
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 12 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
PROJECT PHASE
COMPONENTS OF SOURCES OF IMPACTS
IMPACTS POTENTIAL IMPACT EVALUATION HS OR HI
CONSTRUCTED PHASE (Port Construction)
Constructions of connecting bridge, Interchange Area, Causeway, Container Yard, and Trestle
Change of water current patterns
The shallow water reclamation will hinder the water current moving parallel along the coastline and will affect the movement of sediment drawn by the currents on both sides. In the upstream side, where the current comes from, it will cause agradation, while in the down stream, it will lack of sediment supply and the moving currents will erode the existing sediment and lead to degradation. The shallow water reclamation will change the water current patterns, sedimentation and erosion both in the estuary and along the coastline. It then leads to change of coastline around the studied area. The sedimentation will bring positive impacts to increase of land area. However, it will turn into negative ones, when taking place in the port pool area or shipping routes. In contrast, the erosion will be beneficial when taking place in the shipping routes as it will deepen them, and turn to bring negative impact when eroding sea area where there are facilities constructed thereon. Accordingly, it will be further assessed.
HS
Increased river surface due to runoff
The pier reclamation will decrease the shallow water area but increase the river water surface in the estuary. The increase of water surface in the estuary will affect the river water surface along the river due to runoff. It will lead to wider, higher and longer puddles. Accordingly, it needs to be further assessed.
HS
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 13 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
PROJECT PHASE
COMPONENTS OF SOURCES OF IMPACTS
IMPACTS POTENTIAL IMPACT EVALUATION HS OR HI
Decreased Seawter Quality
The dredging of port pool for inter-insular container transportation, located in between pier and container yard will be for depth : -13 m LWS and Dredging Volume : 2,000,000 m3. It is certianly potential to decrease the seawater quality. The seawater quality decreases in terms of Total Suspended Solids (TSS) and Total Dissolved Solids (TDS) as well as turbidity. Accordingly, it needs to be further assessed.
HS
Disturbance to Sea Biota
The dredging activities will certainly lead worse water and disturb the sea biota. Then, it will derive impact on decreased plankton/nekton composition and abundance. Unfortunately, the composition and abundance has relatively been poor (< 2.000 individu/liter of water). Accordingly, it needs to be further assessed.
HS
Disturbance to Fisherman Activities
The dredging activities will be potential to disturb the fisherman fishing activities . Besides, the decreased compositions and abundance of the plankton will lead to decreased number of nekton. It will certainly make the fishermen unrest. Accordingly, it needs to be further assessed.
HS
Change of Water Current Pattern and Sedimentation
The port pool dredging activities accelerate the water currents and draw the sediment locally. However, it is unlikely to change the water current. The accelerated water current will wash the sediment and affect the sedimentation in other places. Accordingly, it does need to be further assessed.
HI
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 14 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
PROJECT PHASE
COMPONENTS OF SOURCES OF IMPACTS
IMPACTS POTENTIAL IMPACT EVALUATION HS OR HI
OPERATION PHASE
Multipurpose Pier Operation
Job and Business Opportunities
It is estimated that the multipurpose pier operation will need a recruitment of + 2,000 contrainer truck driver. It is certianly a quite number, as job and business opportunities are the main issues in the community. In term of business opportunities, it will require survices to port workers, through food stalls, telecommunication vouchers and others required by port workers. The business opportunities will be for a long term span, i.e. : as long as the multipurpose pier is operated. Accordingly, these two impacts need to be further assessed.
HS
Decreased Mangrove Ecosystim Area
The business opportinities due the multipurpose pier operation will lead narrow the mangrove ecosystem area as part of it will be cleared for community business purposes. Accordingly, it needs to be further assessed.
HS
Decreased Seawter Quality
The operation of the multifpurpose pier covers the operations of container yard, silos for grain food dan grain feed, terminal gates and other supporting port facilities, such as : Container Freight Station (CFS), office buildings, gates and truck parking lots. The loading and unloading activities in the multipurpose pier cover dry bulk loading and unloading activities that are potential to decrease the sewater quality. Accordingly, it needs to be further assessed.
HS
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 15 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
PROJECT PHASE
COMPONENTS OF SOURCES OF IMPACTS
IMPACTS POTENTIAL IMPACT EVALUATION HS OR HI
Disturbance to Sea Biota
The operation of the multifpurpose pier will decrease the seawater quality and disturb the sea biota, particularly decreased compositions and abundance of plankton and nekton. Unfortunately, the composition and abundance has relatively been poor (< 2.000 individu/liter of water). Accordingly, it needs to be further assessed.
HS
OPERATION PHASE
Multipurpose Pier Operation
Decreased Air Quality and Incraesed Noise
The multipurpose terminal operation will decrease the seawater quality and increase the noise due to the transportation activities. The project initiator has prepared the Standard Operating Procedures related with transportation activities in the Multipurpose Terminal area that is relatively remote from the dwelling area. Accordingly, it does not need to be further assessed.
HI
Decreased Road Performance
It is estimated that there will be increase of vessel accesses by + 530 vessels per year or + 2 vessels per day. While increase of dry bulk vessel visit will be + 1 per day. The cargo container loading and unloading operations commonly take place through the container yard first. Nect , it will be proceeded to coargo container loading on board or onto container trucks. The increasing number of container truks operated will certainly decrease the the road performance. Accordingly, it needs to be further assessed.
HS
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 16 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
PROJECT PHASE
COMPONENTS OF SOURCES OF IMPACTS
IMPACTS POTENTIAL IMPACT EVALUATION HS OR HI
Disturbance to Fisherman Activities
The operation of multipurpose terminal will disturb the fisheramn activities, particulary in certain zones restricted for fishermen to access. It will certainly lead to decreased fisherman income. Accordingly, it needs to be further assessed.
HS
Community Unrest
It is probable that there will be decreased environmental quality due to the operation of the multipurpose terminal and potential decrease on fisherman income. It will certainly to communityunrest. Accordingly, it needs to be further assessed.
HS
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 17 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
ACTIVITIES DIRECT POTENTIAL IMPACTS INDIRECT POTENTIAL IMPACTS
CONSTRUCTION PHASE Pre-Cast Material and Equipment Mobilization and Demobilization
Temporary Access
Figure 4.3. Hypothetical Impact Flowchart of Tanjung Perak Port Development in Lamong Bay
Decreased Road Performance
Decreased Air Quality
On-land Reclamation Material Transportation
Increased Noise
Decreased Seawater Quality Demolition of Erected Temporary Access
Decreased Mangrove Ecosystem Area
Disturbance of Sea Biota
Disturbance to Fisherman Activity
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 18 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
ACTIVITIES DIRECT POTENTIAL IMPACTS INDIRECT POTENTIAL IMPACTS
CONSTRUCTION PHASE Port Construction
Pier Construction
Figure 4.3. Hypothetical Impact Flowchart of Tanjung Perak Port Development in Lamong Bay (Cont.)
Decreased Seawater Quality Disturbance to Sea Biota
Disturbance of Fisherman Activities
Increased River Water Surface Change of Water Current Pattern and
Sedimentation
Constructions of connecting bridge, Interchange Area, Causeway, Container
Yard, and Trestle
Decreased Seawater Quality Dredging of Planned Port Pool Disturbance of Sea Biota
Disturbance to Fisherman Activity
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 19 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
ACTIVITIES DIRECT POTENTIAL IMPACTS INDIRECT POTENTIAL IMPACTS
OPERATION PHASE
Figure 4.3. Hypothetical Impact Flowchart of Tanjung Perak Port Development in Lamong Bay (Cont.)
Multipurpose Terminal Operation Job and Business Opportunities
Decreased Seawater Quality
Decreased Road Performance
Disturbance to Fisherman Activities
Decreased Mangrove Ecosystem Area
Disturbance to Sea Biota
Community Unrest
Community Unrest
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 20 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Table 4.3. Matrix of Hypothetical Significant Impacts of Tanjung Perak Port Development in Lamong Bay
ENVIRONMENTAL COMPONENTS
CONSTRUCTION OPERATION
Material and Equipment Mobilization
and Demobilization
Temporary Access
Port Construction Pier
Construction
Multipurpose Pier
Operation On-land Reclamation Material Transportation
Demolition of Erected
Temporary
Access
Connecting Bridge, Interchange Area,
Causeway, Container Yard and Trestle
Constructions
Dredging of Planned
Port Pool
1 2 3 4 5
PHYSICAL- CHEMICAL
- Decreased Air Quality X
- Increased Noise X
- Decreased Seawater Quality X X X X
- Increased River Surface due to Runoff X
- Change of Water Current Pattern X
- Decreased Road Performance X X
BIOLOGY
- Disturbance to Sea Biota X X X X
- Decreased Mangrove Ecosystem Area X X
SOCIO-ECONOMY AND CULTURE
- Community Unrest X
- Disturbance to Fisherman Activity X X X X
- Job and Business Opportunities X
COMMUNITY HEAKTH
- Decreased Health
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 21 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Project Plans : - Construction Plan - Operation Plan
Other Surrounding Activities : - Tanjung Perak Port - Fish Landing Center Plan - Waterfront City Plan in Lamong Bay - Suramadu Bridge
Environmental Plans : - Geo-physical-Chemical Components - Biological Components - Socio-Economic &
Cultural Components
POTENTIAL
IMPACT
IDENTI-
FICATION
POTENTIAL IMPACTS GEO-PHYSICAL CHEMICAL
- Decreased Air Quality
- Increased Noise
- Increased River Water Surface
- Change of Water Current Patterns
& Sedimentation
BIOLOGICAL
- Disturbance to Sea Biota
- Decreased Mangrove Ecological Area
SOCIO-ECONOMIC & CULTURE
- Community Unrest
- Disturbance to Fisherman Activities
- Job & Business Opportunities
COMMUNITY HEALTH
- Decreased Health
POTENTIAL
IMPACT
EVALUATION
HYPOTHET
IC IMPACT
IDENTI-
FICATION
- Consultation & Discussion with Experts
- Inter Study Team Discussion
- Consultation with relevant government officers
- Review to Similar Activities
- Literary Review
- Results of Observation
- Comments & Recommendation
- Literary Review
- Discussion with Study
Team
- Test List & Descriptions
POTENTIAL IMPACTS GEO-PHYSICAL CHEMICAL
- Decreased Air Quality
- Increased Noise
- Increased River Water Surface
- Change of Water Current Patterns
& Sedimentation
BIOLOGICAL
- Disturbance to Sea Biota
- Decreased Mangrove Ecological Area
SOCIO-ECONOMIC & CULTURE
- Community Unrest
- Disturbance to Fisherman Activities
- Job & Business Opportunities
PRIORIZED HYPOTHETICAL SIGNIFICANT IMPACTS
CONSTRUCTION PHASE - Disturbance to Fisherman Activities - Change in Water Current Pattern and Sedimentation - Increased River Water Surface - Decreased Read Performance
- Decreased Seawater Quality
- Increased Noise
- Disturbance to Sea Biota, i.e.
Decreased Compositions and
Abundance of plankton/nekton
OPERATION PHASE
- Job & Business Opportunities
- Community Unrest
- Decreased Seawater Quality
- Decrease Mangrove Ecosystem Area
- Disturbance to Fisherman Activities
- Decreased Road Performance
Figure 4.4. Summary of Scoping Process
PROJECT PHASES : CONSTRUCTION
- Pre-Cast Material and Equipment Mobilization and Demobilization
On-land Reclamation Material Transportation
- Temporary Access
Demolition of Erected Temporary Access
- Port Construction
Construction of Connecting Bridge, Interchange Area, Causeway, Container Yard and Trestle
- Pier Construction
Port Pool Dredging OPERATION
- Multipurpose Terminal Operation
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 22 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
4.1.3. Hypothetical Significant Impact Classification and Priority
Based on the results of aforementioned identification and evaluation,
hypothetical significant impacts to be further classified based of project activity
phases, nature of impacts either positive of negative one, and impacted
environmental components to be further studied.
Hypothetical Significant Impacts in Construction Phase
- Physical-Chemical Components
1. Decreased Air Quality (Encreased dust content)
2. Increased Noise
3. Decreased Seawater Quality (Increased ontent of TDS, TSS and
turbidity)
4. Increased river surface due to runoff
5. Change of water current pattern and sedimentation
- Biological Components
1. Disturbance to sea biota due to decreased plankton/nekton
composition and abundance
2. Decreased mangrove ecosystem area
- Socio-economic and cultural Components
1. Disturbance to fisherman activities
- Transportation Components
1. Decreased road performance
Hypothetical Significant Impacts in Operation Phase
A. Positive Impact :
- Business opportunities
B. Negative Impact :
- Physical-Chemical Components:
1. Decreased Seawater Quality
2. Decreased road construction
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 23 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
- Biological Components:
1. Disturbance to sea biota due to decreased plankton/nekton
composition and abundance
2. Decreased mangrove ecosystem area
- Socio-economic and cultural Components
1. Disturbance to fisherman activities
2. Community Unrest
The classified impacts are further prioritized based on order of
importance, in terms of economic, social and ecological aspects. The set
priorities are as follows:
Construction Phase
1. Disturbance too fisherman activities
2. Change of water current patterns and sedimentation
3. Decreased mangrove ecosystem area
4. Increased river surface due to runoff
5. Decreased Air Quality
6. Decreased road performance
7. Decreased Seawater Quality
8. Disturbance to sea biota , i.e. decreased plankton/nekton
compositions and abundance
Operation Phase
1. Job and business opportunities
2. Community unrest
3. Decreased Seawater Quality
4. Decreased mangrove ecosystem area
5. Disturbance to fisherman activities
6. Decreased road performance
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 24 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
4.2. BORDERS OF STUDIED AREA AND STUDY TIME LIMIT
4.2.1. Borders of Studied Area
The designs and site of Tanjung Perak Port Development in Lamong Bay as
scoped in the Environmental Impact Assessment 2010 of Tanjung Perak Port
Development in Lamong Bay have been modified. Principally, it does change the
borders of the studied area, instead of a minor shift borders.
The borders of studied area are the resultant between the project
borders, ecological border and social border as well as administrative border.
However, it also worth considering the spread of each impact on the physical-
chemical and socio-economic and cultural components in the ecosystem in the
project site and its surrounding. The details of each border are as follows:
a) Project Borders
The project covers reclamation area, causewya, connecting bridge and
pier. The border of the project are :
North : Madura Strait
East : Warehousing Estate, Fishponds Madura Strait
West : Warehousing Estate, Fishponds Madura Strait
South : Jalan Tambak Osowilangun
b) Ecological Border
The ecological border is a combination of borders set based on the waste
(liquid and air) transportation borders and the community area that will change
sue to the acivities of Tanjung Perak Port Development in Lamong Bay. The
ecological borders are as follows :
Surface Ecological Border:
- ± 500 meter on theright and left sides aling arterial road Jalan
Margomulyo (accessed by material and equipment transporting
trucks) to toll road. The distance is the farthest point of the
exposure due to drining speed 100 km/hour.
- ±750 meter to mainland from the project site, when referring to
the modelling of TSS spread.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 25 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
- Estuary of Lamong River to Romokalisari Village, as the area has
been frequently flooded, especially the ones surrounding the
estuary of Lamong River.
Ecological Borders in the sea:
- + 2 km sea waters to north and South. The ecological border
is set based on the seawater current (± 1,7 m/det) that may
reach + 2 km sea waters to the North and South.
- + 2 km sea waters to the East, infront of the East Indonesian
Army waters, as part of the quarry will be supplied from the
waters in the North of Kenjeran Beach.
c) Administrative Border
Administrative border is a space where the community can interact
socially, economically and culturally, in accordance to the prevailing laws and
reulations in the space. It covers Benowo Sub-district, Asemrowo Sub-district and
Krembangan Subdistrict in Surabaya City where the project site in Lamong Bay is
located in.
d) Social Border
Social border is the border where various social interactions with certain
established norms and values take place and predicted to be impacted by the
activities of Tanjung Perak Port Development in Lamong Bay, either positively or
negatively. It covers spme villages in Benowo Sub-district, Asemrowo Sub-district
and Krembangan Sub-district in Surabaya City, as in those villages there are
dwilling areas closest and most impacted by project activities, especially the
residents working as fishermen. Those villages are :
Benowo Sub-district :
Romokalisari Village
Tambak Osowilangon Village
Tambak Langon Village
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 26 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Asemroro wSub-district:
Greges Village (Asemrowo Sub-district)
Kalianak Village (Asemrowo Sub-district)
Morokrembangan Village (Moro Krembangan Sub-district)
e) Border of Studied Area
It is a resultant of the aforementioned 4 borders in view of the
competence to prepare the addendums to the EIA, EIM and EIO, commonly with
constraints on limited resources, such as time, funs, expert, technique and
method of study (See Figure 4.5.).
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
U
TA R
A
Page IV-27 Figure 4.5 STUDIED AREA BORDER
Source: DIGITAL INDONESIAN MAP YEAR 1999 (LAND USE) and RESULT OF BATHYMETRY MEASUREMENT IN LAMONG RIVER ESTUARY YEAR 2008
1 0 1 2km SCALE
14’30”
14
’00”
9200
13’30”
13
’00”
12
’30”
12
’00”
11
’30”
11
’00”
9205
10’30”
10
’00”
09
’30”
09
’00”
08
’30”
9210
08’00”
06
9326
7 m
T
44’00” 44’30” 9198242 mU 9198293 mU 38’00” 38’30”
0680
Balongsari 3,5 km
39’00” 39’30” 40’00” 40’30”
0685
Balongsari
1 km 41’00” 41’30” 42’00” 42’30” 43’00”
0690
43’30”
0693
214 m
T
-1
-0,8
-0,2
-0,6
Studied Area Border
Ecological Border
Administration Border
Social Border
Project Border
10
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 28 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
4.2.2. Study Time Limit
It is the time limit for predicting and evaluating the impacts as studied
in the addendum to EIS, EIM and EIO. It is set based on the length of study time
and progresses in the surrounding environment. Despite the study during
operation phase that normally runs for tens of years, it will not be difficult to
predictth impacts during the operation phase due to dynamic environment
condition. It is further detailed in Table 4.4.
Table 4.4. Study Time Limits for Each Impact
PHASE SUB-ACTIVTIES HYPOTHETICAL
SIGNIFICANT IMPACTS STUDY TIME LIMIT
CONSTRUCTION
Pre-Cast Material
and Equipment
Mobilization n
On-land Reclamation
Material Transportation
Decreased Road
Performance 6 months
Decreased Air Quality
Increased Noise
CONSTRUCTION
Temporary Access
Demolition of Erected
Temporary Acces
Decreased Seawater
Quality
6 months
Disturbance to Sea Biota
Disturbance to Fisherman
Activities
Decreased Mangrove
Ecosystem Area
CONSTRUCTION
Port Construction
Constructions of
connecting bridge,
interchange area,
causeway, container
yard, and Trestle
Decreased Seawater
Quality
24 months
Disturbance to Sea Biota
Disturbance to Fisherman
Activities
Change of Water Current
Patterns and
Sedimentation
Increased River Surface
due to Runoff
CONSTRUCTION
Pier Construction
Pllaned Port Pool
Dredging
Decreased Seawater
Quality
20 months Disturbance to Sea Biota
Disturbance to Fisherman
Activities
OPERATION Multipurpose pier
operation
Job and Business
Opportunities 1 year in early operation
phase Decreased Mangrove
Ecosystem Area
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 4 – SCOPE OF STUDY
IV - 29 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
PHASE SUB-ACTIVTIES HYPOTHETICAL
SIGNIFICANT IMPACTS STUDY TIME LIMIT
CONSTRUCTION
Pre-Cast Material
and Equipment
Mobilization n
On-land Reclamation
Material Transportation
Decreased Road
Performance 6 months
Decreased Air Quality
Increased Noise
Disturbance to Sea Biota
Decreased Seawater
Quality
Decreased Road
Performance
Disturbance to Fisherman
Activities
Community Unrest
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 1 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
CHAPTER 5 IMPACT PREDICTION AND EVALUATION
5.1. IMPACT PREDICTION
The prediction of impact is supposed to identify the predicted
dimension and significance of impact in view of each hypothetical impact
collected from the scoping.
It is predicted by adopting 2 (two) methods, i.e. : formal and informal.
The predicted impact represents diffrence between the expected
environmental quality when the project exists and the one when the project
does not (standard condition). The impact is predicted partially on each of the
environmental components and based on each of the construction phases, i.e. :
Construction and Operation. Besides, it is also worth considering the nature of
the impacts, whether direct or indirect ones.
On the other ahnds, the significance of impacts are predicted based on
6 (six) impact criteria referring to the Guides to Determination of Significant
Impacts.
5.1.1. CONSTRUCTION PHASE
5.1.1.1. On-land Reclamation Material Transportation
A. Decreased Air Quality
Source of Impact
On-land Reclamation Material Transportation for constructing causeway
and interchange area.
Predicted Degree of Impact
In order to generate power, any motorized vehicle will burn fuels and
exert emission gas. The emission gas contains chemical compounds and physical
mixtures mostly categorized as air pollutants. The emission gas exerted from
motorized vehicles mainly contains non-combustible hydrocarbon, carbon
monoxide, sulfur oxide, and particulate substances, including smog. Of the
total uncontrolled hydrocarbon emitted from the motorized vehicles, 20% - 25%
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 2 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
are from engine jackets, 60% are from mufflers and the rest are from fuel tank
and carburetor evaporation. Pollutants from mobile sources are not only
combustion products, but also non-combusted fuel from fuel tanks and loss of
hydrocarbon from crankcase blow.
Tablel 5.1. % of Pollutant emission from Motorized Vehicles
Sources Pollutants (%)
CO HC NOx Particulate
Muffler 100 62 100 90
Engine Chamber 20 10
Fuel Tanks 9
Carburetor 9
The mobilization of trucks for transporting the material and heavy-duty
equipment are very potential to lead to air pollution. The air pollutants emitted
by the motorized vehicles will certainly affect the air quality and endanger the
human health, flora, fauna and various objects.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 3 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Table 5.2. Impact of Main Air Pollutants Emitted from Motorized Vehicle
Pollutants Sources Impacts
CO Imperfect fuel combustion in engine chamber
Poisonous to human beings when inhaled. CO decreases the blood capacity to bind oxygene, and consequently make heart and lungs work harder
HC Fuels, either non-combusted fuel emission or evaporation emission
Irritants, cancer risks, smell, pre-conditioned photochemical smog formation
NOx Sise effect of high temperature combustion, i.e. : increase of nitrogene and oxygene
Irritants, pre-conditioned photochemical smog formation
Lead Additional material to some kinds of fuels
Affecting intellectual development among children
Air Poison Pollutant in fuels and/or resulted from imperfect combustion
Greater cancer risks
Particle Carbon particle formed due to imperfect combustion
Stumulating fog, greater cancer risks, death, worse resporatory disorder
Table 5.3. Ambient Air Quality Standard
Nr Parameter Analysis Method Analysis Equipment
Quality Standard
(g/m3)
1 Sulfur Dioxide (SO2) Pararosanilin Spectrophotometer 220
2 Carbon Monoxide (CO) NDIR NDIR Analyzer 260
3 Nitrogen Dioxide (NO2) Saltzman Spectrophotometer 92.5
4 Hydrocarbon (HC) Flame Ionization Gas Chromatography 98.7
5 Particle < 10 m (PM10) Graphymetric Quantitative Analytic Scale, dust sampler
92.5
6 Dust Graphymetric Quantitative Analytic Scale, dust sampler
230
7 Noise Statistic Sound Level Meter 55* db (A) 70** db (A)
Remarks: Ambient Air Quality Standard pursuant to State Regulation Nr. PP.41/1999 and Decision of Governor of East Java Province Nr.10 Year 2009, and Noise Standard pursuant to Decision of Minister of Environment Nr. KEP-48/MENLH/11/1996; *= Noise Standard in Dwelling Area; **= Noise Standard in Industrial Area.
It is estimated that the reclamation works for constructing causeway,
connecting bridge, and container yards and shallow water reclamation for
constructing container yard, will need 1.000.000 m3 reclamation materials
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 4 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
supplied from the mainland. The reclamation materials are transported
periodically by means of dump trucks, each with 25 m3 capacity and unloaded
at the edge of the project side to be further leveled by means of bulldozer.
When it has been leveled, it will be compacted per 30 cm layer by means of
compaction vibrator.
Table 5.4. Estimated Heavy Duty Equipment Emission
Nr Descriptions Estimated Emission (lb/hour)
CO NOx SO2 Dust
1 Bulldozer 0.793 5.05 0.384 0.165
2 Scrapper 1.46 6.22 0.463 0.406
3 Motor Grader 0.215 1.05 0.086 0.061
4 Others 0.414 2.27 0.143 0.139
Table 5.5. Estimated Motorized Vehicle Emission
Category CO HC NOX PM10 CO2 SO2
(g/km) (g/km) (g/km) (g/km) (g/kg Fuel) (g/km)
Motorcycle 14 5.9 0.29 0.24 3180 0.008
Car (Benzene) 40 4 2 0.01 3180 0.026
Car (Diesel Oil) 2.8 0.2 3.5 0.53 3172 0.44
Bu 11 1.3 11.9 1.4 3172 0.93
Truck 8.4 1.8 17.7 1.4 3172 0.82
It is estimated that the simultaneous operations of 5 units of trucks, 2 units of
bulldozers and 2 units of compaction vibrators, will exert dust emission as
much as 0.309 kg/hour. The calculation of spread of impact on air pollution due
to operations of means of transportation is derived from Gaussian equation with
modification :
2
2/1),( 2
1exp
)2(
2
zz
L
zx
z
u
QC
or, in case the reaod height is the same as the receiving plain, i.e. : H=0, then
z = 0, and:
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 5 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
u
QC
z
Lzx
2/1),()2(
2
where: C = pollutant concentration (ug/m3) Q = emission speed per unit of distance (gr/sec.m) x = distance to receiver (m) z = height of receiving plain (m) u = average wind speed in axis X(m/sec) σ = coefficient of disperse vertical gausian (m)
Figure 5.1. Pollutant Dispersion Based on Distance
The nearest dwelling area is more than 1 km in distance. Based on the Ambient
Air Quality Standards, in case the distance is 0.7 km, the concentration will be
260 µg/m3.
Predicted Dimension of Impact
The evaluation of impact on Decreased Air Quality on based 6 significant
impact criteria is presented in the following table.
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
0,0050,010,020,030,040,050,060,070,080,090,1 0,2 0,3 0,4 0,5 0,6 0,7 0,8 0,9 1
Ko
nse
ntr
asi (
µg/
m3
)
Jarak (km)
Dispersi PM10PM10 DISPERSION
Distance (km)
Con
cen
trati
on
(
m3)
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 6 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Table 5.6 Evaluation on Dimension of Impact on Decreased Air Quality in Construction Phase
Nr. Significant Impact
Criteria Remarks Valuation
1 Number of impacted residents
The safe condition will be away in ± 700 m distance from the reclamation site. The dwelling nearest to the reclamation site is > 1 km distance. Accordingly, the impacted residents are those dwelling around the macadam/ soil access road in the area.
Insignificant
2 Area of Impact Spread
The area covered in the aforementioned concentration of Ambient Air Standard will be 260 µg/m3 in 700 m distance.
Insignificant
3 Impact Duration/Intensity
The impacts will take place during construction phase. In case of air pollution, during the construction phase, , the impact intensity will be + 9.000 µg/m3. It is quite threatening as it can cause respiratory disorder.
Significant
4 Other impacted components
The other impacted component is community unrest due to dust.
Significant
5 Impact Cumulativeness
It is not cumulative. Insignificant
6 Impact recoverability
It is recoverable as dispersed by the ambient air.
Insignificant
With reference to the aforementioned descriptions, the impact on
decreased air quality due to the mobilizations of trucks for transporting
shallow water reclamation materials will be negative significant (NS).
B. Increased Noise
Source of Impact
The source of impact on increased noise in construction phase is
traffic noise due to on-land reclamation material transportation activities.
Predicted Degree of Impact
The dump truck mobilization will not only exert emission but also
noise.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 7 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Referring to the initial descriptions on noise degree in the studied area,
it has exceeded the noise standard due to dense human mobility in transporting
goods and humans by means of motorized vehicles. In in accordance to Noise
Standards set forth in Decision of Minister of Environment Nr.
48/MENLH/II/1996, the noise standard in service/trade area and port is 70 dBA,
while the one in dwelling area is 55 dBA.
Table 5.7. Noise Standards Based on Area Classifications
Area Utilization/Project Site Surrounding Degree of Noise dB(A)
Dwelling Area 55
Service/Trade Area 70
Office/Commercial Area 65
Gren and Open Area 50
Industrial Area 70
Governmentship Area 60
Recreation 70
Airport/.Train Station/Seaport 70
Conservation Area 60
Hospital Area 55
Achool Area 55
Religious Area 55
It is estimated that the simultaneous operations of 5 units of trucks and 2
units of bulldozers, will entail noise calculated with the following equation:
- The acumulated noise degree is measured with the following formula :
2
0
2
2
2
0
2
1log10P
P
P
PLPt
Where: LPt = total noise degree (dBA) P1 = noise intensity from source 1 (N/m2) P2 = noise intensity from source 2 (N/m2) P0 = noise intensity from reference (N/m2)
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 8 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
- Change of noise degree due to change of distance is measered with the
folloeing formula :
2
112 log10
r
rLPLP
Where: LP1 = noise degree in distance r1 (dBA) LP2 = noise degree in distance r2 (dBA) r1 = distance from noise measurement point to source of noise 1 r2 = distance from noise measurement point to source of noise 2
Figure 5.2. Noise Degree Based on Distance
With reference to the aforementioned descriptions and as the area is utilized
for port activities, the prevailing noise standard for the (service/trade) area is
70 dBA within + 70 m distance from the project site. The safe distance for the
dwelling area, i.e. : 55 dBA is in + 2.000 m distance. In case the surrounding
area is provided with barrier or walled with 12 cm thickness, it can reduce the
degree of noise by 4,6 dBA. Accordingly, the safe distance from the dwelling
area is shortened to be + 760 m.
0
10
20
30
40
50
60
70
80
90
5
90
18
0
27
0
36
0
45
0
54
0
63
0
72
0
81
0
90
0
99
0
10
80
11
70
12
60
13
50
14
40
15
30
16
20
17
10
18
00
18
90
19
80
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 9 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 5.3. Noise Degree Based on Distance After Noise Reduction with Barrier
Predicted Dimension of Impact
The evaluation of impact on increased noise based on 6 significant
impact criteria is presented in the following area.
Table 5.8. Evaluation on Dimension of Impact on Increased Noise in Construction Phase
Nr. Significant Impact
Criteria Remarks Valuation
1 Number of impacted residents
The nearest dwelling area is 1 km from the project site. In such a distance, the dwelling area still receives a noise degree of > 55 dBA due to activities in the planned area. Consequently, those likely to be impacted are the ones residing surrounding the project site.
Insignificant
2 Area of Impact Spread The area of Impact Spread is relative minor, i.e. : 760 m.
Insignificant
3 Impact duration/intensity The impacts are continously present in construction phase. The impact intensity is fair.
Significant
4 Other impacted components
The other impacted component is community discomfort. However, the impact is hypothetically insignificant.
Insignificant
5 Impact Cumulativeness The impact is cumulative when related to other sources of impacts derived fron Transportation activities.
Significant
6 Impact recoverability The impact is recoverable when its source stops or recovers.
Insignificant
0
10
20
30
40
50
60
70
80
90
5
90
18
0
27
0
36
0
45
0
54
0
63
0
72
0
81
0
90
0
99
0
10
80
11
70
12
60
13
50
14
40
15
30
16
20
17
10
18
00
18
90
19
80
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 10 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Referring to the aforementioned, the impact on increased noise due to
the material and equipment truck mobilization in the project of Tanjung Perak
Port Development in Lamong Bay is negative significant (NS).
C. Decreased Road Performance
Source of Impact
The impact on Decreased Road Performance is derived from on-land
material and equipment truct mobilization for constructing causeway and
interchange area.
Predicted Degree of Impact
The shallow water reclamation for constructing the causeway and
interchange area will tak e about 8 months with total reclamation volume of
1.7 million m3. The reclamation materials are transported on-land by dump
trucks . The total number of trucks increasing the traffic volume will be 35
units per hour. The calculation of decreased road performance when the
project exist and the one when it does not are presented in Table 5.9.
Table 5.9. Traffic Volumes With and Without Project Activities
Table 5.10. Calculation of Defree of Traffic Satiration With Project Activities
Nr Junction/Crossroad Year 2012
With Project Without Project
1 Romokalisari 0.914 0.921
2 Margomulyo 1.748 1.757
3 Fishpond Tributaries 0.794 0.801
LV HV MC LV HV MC LT 7 25 66 7 33 66 ST 143 16 3063 143 21 3063 LT 437 52 145 437 68 145 ST 166 148 6247 166 148 6247 RT 11 0 59 11 0 59 LT 329 88 36 329 88 36 RT 7 17 27 7 22 27 ST 89 2 1438 89 2 1438 RT 101 126 755 101 147 755
East (Jl. Kali Anak) LT 157 101 4743 157 101 4743 LT 207 81 5741 207 95 5741 RT 145 2 2553 145 2 2553
From Sby to Gresik T-B 190 66 5785 190 89 5785 From Gresik to Sby B-T 185 101 2703 185 113 2703
Nr. Crossroad Closer Access Traffic Movement
Traffic Volume (unit/hour)
With Project Acitivities(2012) Without Project Activities (2012)
1 Romokalisari
East (Jl. Romokalisari)
North (Jembatan Romokalisari sisi Timur)
South (Akses toll Romokalisari)
3 Fishpond Tributaries
2 Margomulyo
West (Jl. Tambak Langon)
South (Jl. Margomulyo)
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 11 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
It shows that the condition (either with or without project activities,
the degree of traffic saturation in those three places is significant, particularly
during peak time : 06.00 - 08.00.
Table 5.11. Evaluation on Dimension of Impact on Decreased Road Performance in Construction Phase
Nr. Significant Impact
Criteria
Remarks Valuation
1 Number of impacted residents
Some traffic users on Jalan Romokalisari and Jalan Tambak Osowilangon, as those are the accesses of reclamation dump trucks from the toll road.
Insignificant
2 Area of Impact Spread Along Jl. Tambak Osowilangon Insignificant
3 Impact Duration/Intensity The impacts will exist during construction phase (3 months) with high intensity, i.e. : degree of traffic saturation 0.8
Significant
4 Other impacted components
The other impacted components are Decreased Air Quality with the volume of additional traffic (+ 95 trucks per hour) and along the roads (Jl. Romokalisari and Tambak Osowilangon) there are 2 way 4 lanes with road median in the middle of the road. Accordingly, the impact significantly lead to Decreased Air Quality
Significant
5 Impact Cumulativeness The impact on decreased road performance is cumulative as it takes place only during peak hour.
Insignificant
6 Impact recoverability The impact is recoverable during the terminal operations.
Insignificant
Referring to the aforementioned descriptions, it shows that the increase on
river water surface is classified negative significant (NS).
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 12 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
5.1.1.2. Demolition of Erected Temporary Access
Impact Descriptions :
A. Decreased Seawater Quality
Source of Impact
The source of impact is demolition of erected temporary access.
Predicted Degree of Impact
The initial environmental conditions in the areas close to the trestle,
connecting bridge and container yard are relatively good, yet the TSS has already
been high. The activity being the source of impact is demolition of erected
temporary access. The demilition volume is assumed to be the same as the one
of reclamation material as much as 57.505 m3. The materials being the source of
impact comprise sand with gravels and mud stratified from the soft to the hard
one. The latter material tends to be heavy with limited spraed area compared
the the earlier. The current from the shipping routes ranges from 0.62 m/sec to
1.0 m/sec. On the other hands, the current is relatively show, i.e. : 0.1 m/sec.
As the reclamation in on shallow water where the current will be relatively
slower with less wide spread.
Predicted Dimension of Impact
Table 5.12. Evaluation on Dimension of Impact on Decreased Seawater Quality in Construction Phase (Demolition of Erected Temporary Access)
Nr. Significant Impact
Criteria Remarks Valuation
1 Number of impacted residents
The impacted residents are the fishermen facing less nekton due to decreased seawater quality
Significant
2 Area of Impact Spread The area of impact spread is relatively limited
Insignificant
3 Impact Duration/Intensity The impacts take place continuously in construction phase. The impact intensity is fair.
Significant
4 Other impacted components
The other impacted components are decreased compositions and abundance of sea boita/nekton and fisherman unrest
Significant
5 Impact Cumulativeness The impact is not cumulative Insignificant
6 Impact recoverability The impact is recoverable the souce stops dy proper management steps.
Insignificant
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 13 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
With reference to the aforementioned descriptions, the impact on decreased
seawater quality will be negative significant (NS).
B. Disturbance to Sea Biota
Source of Impact
The impact on disturbance to sea biota, i.e. : decreased compositions
and abundance of plankton/nekton is a derivative impact from decreased
seawater quality due to demolition of erected temporary access.
Predicted Degree of Impact
The site where the demolition of erected temporary access takes place is
a mangrove area. The status of seawater quality in the site is fair with
phytoplankton diversity index ranging 0,989 – 2,237 and zoo plankton diversity
index ranging 0.629 – 2.01. The dominant phytoplankton is Skeletonema sp, of
bacillariophyceae or dominant diatom. The dominant zooplankton is copepoda
calanoid. The class of plankton found in the sampling area indicates the area is
occupied as nursery ground and source of foods to some sea biota. The
demolition of erected temporary access will lead to water turbidity further
affecting the productivity in the seawater and existence of organisms occupying
the area as nursery ground, feeding ground and spawning ground of fish, shrimps
and shells. The TSS >100 ppm for 21 days will affect the growth of some kinds of
fish and their immunity.
Predicted Dimension of Impact
The evaluation of impact on decreased compositions and abundance of
plankton/nekton based on 6 significant impact criteria is presented in the
following table.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 14 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Tabel 5.13. Evaluation on Dimension of Impact on Disturbance to Sea Biota (Decreased Compositions and Abundance of Plankton in Construction Phase due to Demolition of Erected Temporary Access)
Nr. Significant Impact
Criteria Remarks Valuation
1 Number of impacted residents
The residents in the nearest dwelling area are mainly fishermen. Accordingly, the impacted residents are those residing in that dwelling area.
Significant
2 Area of Impact Spread Area of impact spread is local. In that radius, there are fishing related activities, namely : keramba, netting and shell searching.
Insignificant
3 Impact Duration/Intensity It will take place during the demolition of erected temporary access. The impact intensity is fair.
Significant
4 Other impacted components
The other impacted component is the fisherman community due to their decreased income.
Significant
5 Impact Cumulativeness In addition to other sources of noises, the impact is cumulative.
Significant
6 Impact recoverability The impact is recoverable the source stops by proper management steps.
Insignificant
With reference to the aforementioned, the impact on decreased compositions
and abundance of plankton/nekton due to the demolition of erected temporary
access is categorized negative significant (NS)
C. Decreased Mangrove Ecosystem Area
Source of Impact
The decreased mangrove ecosystem area is due to demolition of erected
temporary acces.
Predicted Degree of Impact
At present in the studied area there are 13 species of mangrove spread
over 8 observation points woth plant density of >2,000 trees/hectare. Pursuant
to Decision of Minister of Environment Number : 201 Year 2004 about Mangrove
Density Standard, the mangrove density of > 1,500 trees/hectare is categorized
to be very dense . The decreased of mangrove ecosystem area is alleged to be
due to demolition of erected temporary access.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 15 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
In addition, the decreased mangrove ecosystem area also lead to
decreased water bird habitat. At present, there are 39 species categorized into
22 families. The identified bird species in the studied area are 14 conserved by
virtue of Indonesian State Regulation Number 7 Year 1999, and IUCN Red list, and
one is included into an Indonesian endemic (Alcedo coerulescens /Blue Shrimp
King). Beside, 1 bird speciesb found in Sememi River, i.e. : Bluwok Heron
(Mycteria cinerea) is internationally conserved.
Predicted Dimension of Impact
The evaluation of impact on decreased mangrove ecosystem area as
habitat of sea biota based on 6 significant impact criteria is presented in the
table below.
Table 5.14. Evaluation on Dimension of Impact on Decreased Mangrove Ecosystem Area in Construction Phase due to Demolition of Erected Temporary Access
Nr. Significant Impact
Criteria Remarks Valuation
1 Number of impacted residents
It is predicted that the decreased mangrove ecosystem area (> 10%) will lead to disturbance to the residents doing activities in the mangrove ecosystem as the area is not only occupied for conservation area but also shrimp and milkfish breeding.
Significant
2 Area of Impact Spread
The spread of the impact will be limited in the studied area, yet it is pretty wide as it covers six village areas, namely : Romokalisari village, Tambak Osowilangun village, Tambak Langon village, Greges village, Kalianak village and Krembangan village
Significant
3 Impact Duration/Intensity
The impact will take pretty long time and the impact intensity is fair.
Significant
4 Other impacted components
Due to decreased mangrove ecosystem area, it will affect more than two environmental components, i.e. : traditional fishpond, water bird habitat and sea biota spawning area.
Significant
5 Impact Cumulativeness
It will be cumulative and takes place during construction phase.
Significant
6 Impact recoverability
The impact will be unrecoverable as the required business space will be getting larger and wider, while the mangrove habitat is getting narrower and probably finished.
Significant
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 16 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Based on the aforementioned descriptions, the impact is categorized to be
negative significant (NS).
D. Disturbance to Fisherman Activities
Source of Impact
The impact on on decreased fisherman income is due to demolition of
erected temporary access.
Predicted Degree of Impact
Based on the results of interview, it is believed that the demolition of
the erected temporary access will disturb the fisherman activities and lead both
less fishermen going fishing and decreased fisherman income. The latter can be
due to damaged fish habitat.
Predicted Dimension of Impact
Referring to the aforementioned descriptions, the evaluation of impact
on decreased fisherman income based on 6 main criteria is presented as
follows.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 17 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Table 5.15. Evaluation on Dimension of Impact on Decreased Fisherman Income due to Demolition of Temporary Access
Nr Criteria Remarks Valuation
1 Number of impacted residents
Fisherman community comprising about 225 household
Significant
2 Area of Impact Spread Relatively widespread, particularly in Tambaksoso Wilangon village, Greges village
Significant
3 Impact Duration/Intensity
It is predicted to be during the construction phase with relatively high intensity.
Significant
4 Other impacted components
Decreased fisherman income Significant
5 Impact Cumulativeness It is cumulative
Significant
6 Impact recoverability It is unrecoverable Significant
Based on the aforementioned descriptions, the impact is categorized to be
negative significant (NS)
5.1.1.3. Port Construction (Shallow Water Reclamation for constructing connecting bridge, Interchange Area, Causeway, Container Yard, and Trestle)
A. Decreased Seawater Quality
Source of Impact
The source of impact is shallow water reclamation for constructing
causeway, interchange area, container yard and trestle.
Predicted Degree of Impact
The initial environmental descriptions in locations close to the trestle,
connecting bridge and container yard the condition is relatively still good.
However, the TSS is already high.
The planned activity being a source of impact is shallow water
reclamation for constructing causeway, interchange area and container yard. The
reclamation material for the causeway is 1,100,00 m3, interchange area is
200,000 m3 and parking lot 400,000 m3. The Container Yard is constructed by
reclaiming the shallow waters with a total reclamation volume of 2,800,000 m3
for the Container Yard and dry bulk yard with a total volume of 1,110,000 m3.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 18 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
The maximum content of mud in the reclamation materials is 20%, while the
reclamation volume is 2,000,000 m3.
The sort of reclamation materials determines the spread in the waters.
The sediment characters like grain size, density, settlement spped, composition,
porosity, shape etc., are adoptable as a basis for presenting the resistence
against the current. The material being a source of impact generally contain sand
and gravels, from soft to coarse ones, and tending to be clayey. This latter
material tends to be heavier and it spread is relatively narrower. The current
speed affects the area of spread. The stronger the current, the wider spread will
be. T
The current from the shipping routes ranges from 0.62 m/sec to 1.0
m/sec. On the other hands, the current is relatively slow, i.e. : 0.1 m/sec. As
the reclamation in on shallow water where the current will be relatively slower
with less wide spread. Analoguous to the reclamation activities in Lamong Bay,
the arising turbidity mainly increases pretty significantly, although it is localized.
Predicted Dimension of Impact
Table 5.16. Evaluation on Dimension of Impact on Decreased Seawater Quality in Construction Phase (Port Construction/Shallow Water Reclamation)
Nr. Significant Impact
Criteria Remarks Valuation
1 Number of impacted residents
The impacted residents are fishermen finding less nekton due to decreased seawater quality
Significant
2 Area of Impact Spread The area of impact spread is relative limited.
Insignificant
3 Impact Duration/Intensity It is predicted to be continuous during the construction phase with high intensity.
Significant
4 Other impacted components
The other impacted compoonents are decreased abundance of sea biota/nekton and fisherman unrest
Significant
5 Impact Cumulativeness It is not cumulative
Insignificant
6 Impact recoverability The impact is recoverable the soruce stops by proper management steps.
Insignificant
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 19 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Based on the aforementioned descriptions, it is found that the decreased
seawater quality is due to port construction activities, particularly shallow
water reclamation. Accordingly the impact is categorized negative significant
(NS).
B. Change of Water Current Patterns and Sedimentation
Source of Impact
The impact on change of water current patterns and sedimentation as
well as elevation of water surface in the estuary of Lamong Bay is predicted to
identify the conditions of waters after the shallow water reclamation.
Predicted Degree of Impact
In order to assess the impacts of the activities to the surrounding
environment, numerical simulation and hydrodynamic modelling are applied.
The modelling is supposed to monitor the conditions prior construction and post
construction.
The data input for the numerical modelling in this assessment adopts
secondary data covering : high tide and low tide, volume and concentration of of
sediment of rivers flowing into Madura Strait, and sea depth detailed as follow :
1. Tidal Predictions (Dishidros, 2012):
Karang Kleta : May 2012
Karang Jamuang : May 2012
2. The data on violume of river water flowing into Madura Strait and the
locations of rivers are presented in the following table and figure.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 20 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 5.4. Rivers flowing into Madera Strait
Table 5.17. River Water Volume Flowing into Madura Strait
Code Name of River Annual Volume (m3/sec)
Suspended Sediment Concentration (kg/m3)
M1 Lamong 19.0 0.0738
M2 Sememi 4.3 0.0278
M3 Branjangan 3.6 0.0125
M4 Manukan 5.8 0.0259
M5 Krembangan 3.6 0.0134
M6 Kali Mas 3.5 0.0129
M7 Mireng 19.0 0.0099
M8 Glagah Lanjang 2.5 0.0278
Source: KLHS 2009
3. Sea Depth Data
- Data The bathimetry (sea depth) data are collected from various
sources, namely, results of survey on waterfront city study year 2009,
APBS 2010 Study Map and the Indonesian Coastal Environment Map
Year 1993.
- m1 = Lamong River
- m2 = Sememi River
- m3 = Branjangan River
- m4 = Manukan River
- m5 = Krembangan River
- m6 = Mas River
- m7 = Mireng River
- m8 = Glagah Lanjang River
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 21 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
The effects of reclamation activities for the construction of multipurpose
terminal of PT. PELINDO III to the environment of Lamong Bay is modelled
through 2 (two) schenarios :
- Scenario Model 1 (Without Project): Existing condition originally, prior to
reclamation activities.
- Scenario Model 2 (With project) : Condition after reclamation of container
terminal in accordance with the layout of roposed by PT PELINDO III.
The modelling of the two ispresented in Figure 5.5
Figure 5.5. Model 1 (Without Project) and Model 2 (With Project)
The water current pattern in Scenarion Model 2 around the studied area during
high tide is presented in Fugure 5.6 below :
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 22 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 5.6. Typical Water Current Pattern During High Tide
As presented in Figure 5.6. above, during high tide, the speed of
dominant current to the coastal area around the project site averagely ranges
between 0 – 0.05 m/sec. The low speed current is distributed along the coastal
area in Lamong Bay until Branjangan River (Figure 5.6.), while along the shipping
routes the spped of the current ranges between 0.3 m/sec to > 0.5 m/sec (green
to red).
In some locations in the South of the estuary of Lamong River, there is an
increasing current speed after the construction of Multipurpose terminal, since
the current is turned due to the blockage by the multipurpose terminal
construction. The increasing speed and change of current distribution are also
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 23 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
found along the coast of Lamong Bay to Branjangan River, ranging between 0 –
0.15 m/sec. In the mean time, during low tide, it relatively low when compared
to the one during high tide, ranging 0 –0.1 m/sec, especially in the shipping
routes in the West. There current speed decreases aroun Lamong River during
low tide as shown in Figure 5.7 below.
Figure 5.7. Typical Current Pattern in Low Tide
In areas protected from reclamation islands, i.e. : in rivers with estuaries in
Lamong Bay the water current speed decreases by 0.05 – 0.1 m/sec. It will affect
the sedimentation pattern. In the mean time, the sedimentation distribution
during 1 month in both with and without project, is presented in Figure 5.8. In
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 24 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
general, there is an increase of sedimentation in Lamong Bay in both with
project and without project. The sediment increase is about 0.1 m from the
estuary and the increase is getting less in Lamong Bay.
Figure 5.8. 1 Month- Sedimentation
When compared to conditions in all estuaries around Lamong Bay, the existing
condition (without project) and the post-construction condition (awith project),
it is found that during the high tide, the current speed post-construction is
always lower compared to the one under existing condition. In the mean time,
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 25 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
there is almost no diffrence in sedimentation in both existing condition and post-
construction condition as shown in Figure 5.9.
Figure 5.9. Water Current Speed and Sedimentation in Estuary of Lamong River
The folowing Figure 5.10 shows the points of observation on sedimentation
thickness in the studied area, while the sedimentation thickness in those points
are shown in Figure 5.11. In general, it shows that three is an increase of
sedimentation thickness post construction, although the increase is not
significant (2 – 4 cm / year). However, it is cumulative and therefore needs not
be managed.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 26 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 5.10. Observation Points and Sediment
Figure 5.11. Current Speed and Sedimentation in Estuaries
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 27 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
The results of observation on elevation of water surface in existing condition and
post-construction condition are presented in Figure 5.12. In general, there is an
increase of elevation of water surface in all estuaries post construction although
the incrase is not significant (about 4 cm).
Figure 5.12. Elevation of Water Surface in Eastuaries
During the construction phase, there are reclamation activities potential
to decrease the sewater quality.The sediment concentration distribution around
the location of dumping scenario range from 60 kg/m3 (mg/l) to 100 mg/l
steadily during 1 week is dispersed. The figures also show the points where
fishermen do their fishing activities (yellow points) where the concentration is 15
mg/l. In the estuary of Lamong River, the sediment concentration is below
15mg/l. Although it aready satisfy the standards, it is still recommended to keep
supressing sedimentation around the project site.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 28 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 5.13. Sediment Distribution During Construction 60 mg/l Concentration
Figure 5.14. Sediment Distribution During Construction 70 mg/l Concentration
K1
K3K2
K4
K5
K12
J1
A1K6
K7
N1
K9
K8
K11
K13
K10
K14
P1
U1
T1K1
K3
K2
K4
K5K12
J1
A1K6
K7
N1
K9
K8
K11
K13
K10
K14
P1
U1
T1
K1
K3K2
K4
K5
K12
J1
A1K6
K7
N1
K9
K8
K11
K13
K10
K14
P1
U1
T1K1
K3
K2
K4
K5K12
J1
A1K6
K7
N1
K9
K8
K11
K13
K10
K14
P1
U1
T1
K1
K3
K2
K4
K5K12
J1
A1K6
K7
N1
K9
K8
K11
K13
K10
K14
P1
U1
T1
K1
K3K2
K4
K5
K12
J1
A1K6
K7
N1
K9
K8
K11
K13
K10
K14
P1
U1
T1K1
K3
K2
K4
K5K12
J1
A1K6
K7
N1
K9
K8
K11
K13
K10
K14
P1
U1
T1
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 29 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 5.15. Sediment Distribution During Construction 80 mg/l Concentration
Figure 5.16 Sediment Distribution During Construction 90 mg/l Concentration
K1
K3
K2
K4
K5K12
J1
A1K6
K7
N1
K9
K8
K11
K13
K10
K14
P1
U1
T1
K1
K3K2
K4
K5
K12
J1
A1K6
K7
N1
K9
K8
K11
K13
K10
K14
P1
U1
T1K1
K3
K2
K4
K5K12
J1
A1K6
K7
N1
K9
K8
K11
K13
K10
K14
P1
U1
T1
K1
K3
K2
K4
K5K12
J1
A1K6
K7
N1
K9
K8
K11
K13
K10
K14
P1
U1
T1
K1
K3K2
K4
K5
K12
J1
A1K6
K7
N1
K9
K8
K11
K13
K10
K14
P1
U1
T1K1
K3
K2
K4
K5K12
J1
A1K6
K7
N1
K9
K8
K11
K13
K10
K14
P1
U1
T1
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 30 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 5.17 Sediment Distribution During Construction 100 mg/l Concentration
The observation coordinates and remarks are presented in the following table.
Table 5.18. Observation Coordinates around Lamong Bay
Kode Keterangan Lintang Bujur X Y A1 Area Nelayan Pencari
Kerang 7°13'02.80"S 112°40'10.33"E 684340.733 9201875.797
J1 Jaring
Ikan 7°12'51.90"S 112°40'02.88"E 684113.398 9202211.485
K1 Keramb
a 7°13'13.60"S 112°40'04.70"E 684166.795 9201544.649
K2 Keramb
a 7°13'12.33"S 112°40'13.97"E 684451.332 9201582.622
K3 Keramb
a 7°13'14.71"S 112°40'19.10"E 684608.447 9201508.931
K4 Keramb
a 7°13'17.18"S 112°40'25.45"E 684802.979 9201432.336
K5 Keramb
a 7°13'15.40"S 112°40'31.32"E 684983.266 9201486.357
K6 Keramb
a 7°13'08.27"S 112°40'15.40"E 684495.660 9201707.186
K7 Keramb
a 7°12'59.19"S 112°39'59.83"E 684019.008 9201987.876
K8 Keramb
a 7°12'40.05"S 112°39'52.75"E 683803.945 9202576.656
K9 Keramb
a 7°12'29.20"S 112°40'04.40"E 684162.579 9202908.666
K10 Keramb
a 7°12'06.10"S 112°40'03.70"E 684143.695 9203618.384
K11 Keramb
a 7°12'21.60"S 112°39'42.70"E 683497.680 9203144.568
K12 Keramb
a 7°13'13.60"S 112°40'04.70"E 684166.795 9201544.649
K13 Keramb
a 7°12'11.34"S 112°39'47.37"E 683642.103 9203459.236
K14 Keramb
a 7°11'56.33"S 112°40'03.51"E 684138.961 9203918.543
N1 Nelayan Pencari
Udang 7°12'50.90"S 112°39'58.00"E 683963.795 9202242.752
P1 Pos
Jaga 7°12'07.30"S 112°40'17.90"E 684579.219 9203579.928
T1 Tambak
Ikan 7°13'14.61"S 112°40'08.63"E 684287.250 9201513.180
U1 Ujung Pembangunan
Dermaga 7°12'02.00"S 112°40'17.90"E 684579.814 9203742.746
K1
K3
K2
K4
K5K12
J1
A1K6
K7
N1
K9
K8
K11
K13
K10
K14
P1
U1
T1
K1
K3K2
K4
K5
K12
J1
A1K6
K7
N1
K9
K8
K11
K13
K10
K14
P1
U1
T1K1
K3
K2
K4
K5K12
J1
A1K6
K7
N1
K9
K8
K11
K13
K10
K14
P1
U1
T1
Code Remarks Latitude Longitudinal X Y
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 31 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Predicted Dimension of Impact
The evaluation of impact on change of water current pattern and
sedimentation based on 6 Significant Impact Criteria is presented in the
following table.
Table 5.19. Evaluation of Significance of Impact on Change of Water Current Pattern and Sedimentation
Nr. Significant Impact
Criteria Remarks Valuation
1 Number of impacted residents
The residents directly impacted by the change of water current pattern and sedimentation are those working as fishermen as their fishing routes will be changed and disturbed by the change of water current pattern and sedimentation
Insignificant
2 Area of Impact Spread The area of impact spread is quite significant as it takes place in the estuaries and around the bay.
Significant
3 Impact Duration/Intensity The impact takes place during the construction phase and operation phase with pretty high intensity.
Significant
4 Other impacted components
The other impacted components are community perception and seawater quality.
Significant
5 Impact Cumulativeness It is permanent. Significant
6 Impact recoverability It is unrecoverable as the construction is permanent.
Significant
Based on the aforementioned description, the change of water current pattern
and sedimentation is categorized negative significant (NS).
C. Increased River Water Surface
Source of Impact
The impact on increased river water surface is predicted by observing the
condition of the river water surface after the reclamation for port construction.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 32 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Predicted Degree of Impact
Without Project
The data required for the analysis is lonitudinal and cross cuts and
maximum volume of flowing into the channal. During this time, along Lamong
River, the areas surrounding the middle part of Laong Bay frequently flooded are
Cerme Sub-district, Benjeng Sub-district, Balongpanggang Sub-ditrict, Duduk
Sampeyan Sub-district. The floods are due to shallowing in the river and critical
river banks.
The river water volume input data under condition prior to project
activities are maximum water volume ever flowing, i.e. : 45 m3/sec. On the
other hands, the average river volume along the year range 3-9 m3/sec during
the dry season, while during the wet season it varies 22-45 m3/sec. The water
volme designed for the river banks is about 20 m3/sec. Based on the simulation,
it is found that the floods frequently take place in Km 12 -14 from the estuary
with the highest river water surface (during high tide), i.e. : elevation +0.18
meter above the sea water surface. Figure 5.14. and 5.15. show the points where
floods often take place.
Figure 5.18. Simulation of Flood in Lamong River with Water Volume Input 20 m3/detik.
Embankment under the
water
surface
Flood Flood
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 33 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Figure 5.19. Perspective of Resulted River Flood Simulation
With Project
After the reclamation activities, the arising impacts are analyzed. It is
assumed that the increase of water surface downstream due to the reclamation
vary and maximally reach an elevation of +0.18 m dpl. Accordingly the
reclamation can increase the water surface by +0.58 m dpl to +1.18 m dpl. It is
still below the river flood surface when referring to the designed volume for 20
m3/sec, i.e. : +1.18 m dpl.
The Elevation Comparisons among Existing River Bank Elevation, Water
Surface Elevation Prior Project, Water Surface Elevation After Project, and
Planned Water Elevation are presented in the Figure of Channel Design.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 34 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Table 5.20. Elevation Comparisons among Existing River Bank Elevation, Water Surface Elevation Prior Project, Water Surface Elevation After Project, and Planned Water Elevation
Tanggul
Kanan
Tanggul
Kiri
Elevasi Selisih Tanggul
KananTanggul Kiri
0 0.84 0.33 0.18 1.18 1.00 1.80 -
500 0.24 -0.18 1.00 1.18 0.18 1.90 1.90
1000 0.09 -0.96 1.20 1.20 0.00 2.17 2.17
1500 0.28 -1.10 1.80 1.80 0.00 2.63 2.63
2000 0.81 -0.22 1.90 1.90 0.00 2.84 2.84
2500 1.03 0.68 2.50 2.50 0.00 3.54 3.54
3000 1.4 0.4 3.00 3.00 0.00 3.97 3.97
3500 2.3 0.64 3.50 3.50 0.00 4.57 4.57
4000 1.91 1.2 4.00 4.00 0.00 4.99 4.99
4500 1.3 1.33 4.20 4.20 0.00 5.24 5.24
5000 1.27 0.99 4.50 4.50 0.00 5.42 5.42
10000 0.74 1.49 5.20 5.20 0.00 6.26 6.26
15000 1.95 2.16 6.00 6.00 0.00 6.32 6.32
20000 5.5 3.32 7.50 7.50 0.00 8.57 8.57
25000 9.45 9.09 9.40 9.40 0.00 10.87 10.87
30000 11.39 12.04 14.00 14.00 0.00 13.90 13.9
35000 14.86 14.47 15.00 15.00 0.00 15.90 15.90
38000 15.26 15.03 15.80 15.80 0.00 16.65 16.65
Rencana Elevasi Tanggul
Rencana Berdasarkan
Gambar Perencanaan
TeknikMeter Ke-
Setelah
Kegiatan
kenaikan 100 cm
(+1,18 m dpl)
elevasi Muka
Air Sungai
Sebelum
Kegiatan
Elevasi Eksisting
The results of the simulation and table of summary show that in spite of
the highest tide and increase of river water surface due to reclamation, there is
no influence to increase of seawater level due to reclamation and it does affect
much to the condition in the estuary of Lamong River. The arising effect will
range from STA 0+0 to STA 1+000. In conclusion, it does not bring any significant
effect (Figure 5 .20).
Figure 5.20. Effect of Backwater Due to Reclamation Less than 100 m from Upstream
0
2
4
6
8
10
12
14
16
18
0 5000 10000 15000 20000 25000 30000 35000 40000
Ele
vasi
Mu
ka A
ir S
un
gai
Meter Ke-
elevasi Muka Air Sungai Sebelum Kegiatan
Setelah Kegiatan kenaikan 100 cm (+1,18 m dpl)
Left
Order
of
Meter
River Water
Surface
Elevation
Prior to
Project
Increase by 100
cm After
Reclamation
(+1.18 m dpl)
Elev | Diff. Right Right Left
Existing Elevation
In Riverbanks
Planned River Bank Elev.,
Plans Based on Technical
Design – In river Banks
Riv
er
Wate
r S
urf
ace E
levati
on
Order of Meter
River Water Elevation Prior to Project Construction
Increase by 100 cm after Construction (+1.18 m dpl)
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 35 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Predicted Dimension of Impact
The evaluation of impact on increased river water surface based on 6
significant impact criteria is presented in the following table.
Table 5.21. Evaluation on Dimension of Impact on increased river water surface
Nr. Significant Impact
Criteria
Remarks Valuation
1 Number of impacted residents
No resident is impacted as the increased water surface is still under the maximum volume of flood surface designed for Lamong River
Insignificant
2 Area of Impact Spread
Area of Impact Spread very limited as it takes place only in the eastuary
Insignificant
3 Impact Duration/ Intensity
The impacts present in both construction and operation phases
Significant
4 Other Impacted Components
Other impacted component is community perception
Significant
5 Impact Cumulativeness
It is cumulative along the project Insignificant
6 Impact recoverability It is recoverable when the river water volume flowing into Lamong River decreases
Insignificant
Based on the aforementioned descriptions, it is conclusive that the impact of
on increased river water surface is categorized negative significant (NS).
D. Disturbance to Sea Biota
Source of Impact
The impact on disturbance to sea biota is characterized with decreased
compositions and abundance of plankton/nekton as derived from Decreased
Seawater Quality due to shallow water reclamation for constructing causeway,
interchange area, container yard and trestle.
Predicted Degree of Impact
The area surrounding the causeway construction site is a mangrove area.
Based on the plankton diversity index, it is categorized fair with an index of
phytoplankton diversity of 0.989 – 2.237 and zooplankton diversity of 0.629 –
2.01. The dominant phytoplankton is Skeletonema sp of class bacillariophyceae
or fair dominant diatom. The dominant zooplankton is copepoda calanoid. The
kinds of planktons found from the sampling points indicate that the area is
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 36 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
occupied as nursery ground and source of food for some sea biota. The
reclamation of shallow waters will entail loss of sea biota habitat as wide as the
reclaimated area and turbidity negatively affecting the sea biota surrounding the
reclaimed area.
Predicted Dimension of Impact
The evaluation of impact on decreased compositions and abundance of
plankton/nekton based on 6 significant impact criteria is presented in the
following table.
Table 5.22. Evaluation on Dimension of Impact on Disturbance to Sea Biota (decreased compositions and abundance of plankton/nekton) in Construction Phase (Port Construction/Shallow Water Reclamation)
Nr. Significant Impact Criteria
Remarks Valuation
1 Number of impacted residents
The residents in the nearest dwelling area are mainly fishermen. Accordingly, the impacted residents are those residing in that dwelling area.
Significant
2 Area of Impact Spread Area of impact spread is local. In that radius, there are fishing related activities, namely: keramba, netting and shell searching.
Insignificant
3 Impact Duration/Intensity It will take place during the reclamation. The intensity is low in view of poor initial environmental condition. However, it will take place for a long time. Therefore, it is assumed to be significant as it affects other organisms.
Significant
4 Other impacted components
The other impacted component is the fisherman community due to their decreased income.
Significant
5 Impact Cumulativeness In addition to other sources of noises, the impact is cumulative.
Significant
6 Impact recoverability The impact is recoverable the source stops by proper management steps.
Insignificant
With reference to the aforementioned, the impact on decreased compositions
and abundance of plankton/nekton due to the shallow water reclamation is
categorized negative significant (NS)
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 37 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
E. Disturbance to Fisherman Activities
Source of Impact
The impact on distubance to fisherman activities is due to port
construction activities , particularly preparation and compaction of area for
constructing causeway, interchange area, container yard and trestle.
Predicted Degree of Impact
Referring to the results of interview about preparation and compaction of
area for constructing causeway, interchange area and container yard it will
entail disturbance to fisherman activities and decrease their income. Their
income used to be minimally IDR 50,000/day , varying from IDR 75,000 to IDR
100,000. However, it now ranges between IDR 20,000 to IDR 30,000/day. They
sometimes even get no income . Dun an unfavorable condition can be due to
damaged fish habitat.
Predicted Dimension of Impact
Based on the aforementioned descriptions, the evaluation of impact on
disturbance to fisherman activities based on 6 main criteria is presented
below.
Table 5.23. Evaluation on Dimension of Impact on Disturbance to Fisherman Activities in Construction Phase
Nr Criteria Remarks Valuation
1 Number of impacted residents
Fisherman community comprising about 225 household
Significant
2 Area of Impact Spread Relatively widespread, particularly in Tambaksoso Wilangon village, Greges village
Significant
3 Impact Duration/Intensity
It is predicted to be during the construction phase with relatively high intensity.
Significant
4 Other impacted components
Decreased community (fisherman) welfare Significant
5 Impact Cumulativeness It is cumulative
Significant
6 Impact recoverability It is unrecoverable Significant
Based on the aforementioned descriptions, the impact on disturbance to
fisherman activities is categorized to be negative significant (NS)
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 38 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
5.1.1.4. Planned Port Pool Dredging
A. Decreased Seawater Quality
Source of Impact
The source of impact is planned port pool dredging.
Predicted Degree of Impact
The initial environmental descriptions in the port pool to be dredged are
relatively still in good condition.
The activity being a source of impact is port pool g=dredging. The
dredging volume will be 2,000,000 m3. The sediment to be dredged will
determine the sediment spread in the water. The sediment characters like grain
size, density, settlement spped, composition, porosity, shape etc., are adoptable
as a basis for presenting the resistence against the current. In case the current is
strong enough, the sediment on the seabed will be drawn in continuous contact.
The smaller size of sediment (such as : mud with low concentration or soft sand
tends to be suspended in speed and direction in accordance with the speed and
direction of the current. The material being a source of impact generally contain
sand and gravels, from soft to coarse ones, and tending to be clayey. This latter
material tends to be heavier and it spread is relatively narrower. The current
speed affects the area of spread. The stronger the current, the wider spread will
be. The current from the shipping routes ranges from 0.62 m/sec to 1.0 m/sec.
On the other hands, the current is relatively slow, i.e. : 0.1 m/sec. As the
reclamation in on shallow water where the current will be relatively slower with
less wide spread.
The monitoring activities in the port will be analoguous to the ones in
TanjunG perak Port. In tanjung Paerak Port, the monitoring takes place in West
Nilam and East Nilam. Based on the monitoring data collected from 2008-2011,
only TSS in quarter 3 yaer 2009 in West Nilam was overthe the quality standard,
i.e. : 137 mg/l , while the standard is 80 mg/l. (Report of Pollution Control in
Coastal Area by Surabaya City Environmental Agency, 2011). However, in
accordance to the results of analysis dated 09 April 2012 about Seawater
Standard Quality in Port where the container yard is going to be constructed is
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 39 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
the TSS drops by 26 mg/l. Accordingly, the condition in the waters in the project
site is still in good condition.
Predicted Dimension of Impact
Table 5.24. Evaluation on Dimension of Impact on Decreased Seawater Quality (Port Dredging)
Nr. Significant Impact
Criteria Remarks Valuation
1 Number of impacted residents
The impacted residents are fishermen finding less nekton due to decreased seawater quality
Significant
2 Area of Impact Spread The area of impact spread is relative limited, not exceeding 30 mg/l in radius of 100 m from the source.
Insignificant
3 Impact Duration/Intensity It is predicted to be continuous during the construction phase with fair intensity as the current in that location is relatively slow (speed 30-40 cm/sec), in accordance to Study by Surabaya Container Terminal , 2012.
Significant
4 Other impacted components
The other impacted compoonents are decreased abundance of sea biota/nekton and fisherman unrest
Significant
5 Impact Cumulativeness It is not cumulative
Insignificant
6 Impact recoverability The impact is recoverable the soruce stops by proper management steps.
Insignificant
Based on the aforementioned descriptions, the impact on decreased seawater
quality due to port dredging is categorized to be negative significant (NS)
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 40 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
B. Disturbance to Sea Biota
Source of Impact
The impact on disturbance to sea biota, i.e. : decreased compositions
and abundance of plankton/nekton is a derivative impact from decreased
seawater quality due to port dredging.
Predicted Degree of Impact
The status of seawater quality in the site is fair with phytoplankton
diversity index ranging 0,989 – 2,237 and zooplankton diversity index ranging
0.629 – 2.01. The dominant phytoplankton is Skeletonema sp, of
bacillariophyceae or dominant diatom. The dominant zooplankton is copepoda
calanoid. The class of plankton found in the sampling area indicates the area is
occupied as nursery ground and source of foods to some sea biota. The
demolition of erected temporary access will lead to water turbidity further
affecting the productivity in the seawater and existence of organisms occupying
the area as nursery ground, feeding ground and spawning ground of fish, shrimps
and shells. The community tends to utilize the area surrounding the pier and
trestle for keramba. The port dredging is predicted to cause turbidity in the
waters and direction of water current affecting the water quality and various
fish habitat. The TSS >100 ppm for 21 days will affect the growth of some kinds
of fish and their immunity.
Predicted Dimension of Impact
The evaluation of impact on decreased compositions and abundance of
plankton/nekton based on 6 significant impact criteria is presented in the
following table.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 41 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Table 5.25. Evaluation on Dimension of Impact on Disturbance to Sea Biota (decreased compositions and abundance of plankton/nekton) in Construction Phase (Port Dredging)
Nr. Significant Impact
Criteria Remarks Valuation
1 Number of impacted residents
The fishermen fishing in coastal area. Insignificant
2 Area of Impact Spread Area of impact spread is local. In that
radius ( 100 m), there are fishing related activities, namely: keramba, netting and shell searching.
Insignificant
3 Impact Duration/Intensity It will take place during the reclamation. The intensity is low in view of poor initial environmental condition. However, it will take place for a long time. Therefore, it is assumed to be significant as it affects other organisms.
Significant
4 Other impacted components
The other impacted component is the fisherman community due to their decreased income.
Significant
5 Impact Cumulativeness In addition to other sources of noises, the impact is cumulative.
Significant
6 Impact recoverability The impact is recoverable the source stops by proper management steps.
Insignificant
Based on the aforementioned descriptions, the decreased compositions and
abundance of plankton/nekton due to port pool dredging is categorized to be
negative significant (NS)
F. Disturbance to Fisherman Activities
Source of Impact
The impact on disturbance to fisherman activities is due to port pool
dredging.
Predicted Degree of Impact
Referring to the results of interview about preparation and compaction
of area for constructing causeway, interchange area and container yard it will
entail disturbance to fisherman activities and decrease their income. Their
income used to be minimally IDR 50,000/day , varying from IDR 75,000 to IDR
100,000. However, it now ranges between IDR 20,000 to IDR 30,000/day. They
sometimes even get no income . Dun an unfavorable condition can be due to
damaged fish habitat.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 42 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
The studied area is part of shallow waters with depth ranging 0.5 – 2 m
and greatly affected by the tide. During low tide, the studied area will be
spread of seabed with mud and sand, and in some points it is not accessible for
fishing routes for the surrounding traditional fishermen.
Predicted Dimension of Impact
Based on the aforementioned descriptions, the evaluation of impact on
disturbance to fisherman activities based on 6 main criteria is presented
below.
Tabel 5.26. Evaluation on Dimension of Impact on Disturbance to Fisherman Activities in Construction Phase
Nr Criteria Remarks Valuation
1 Number of impacted residents
Fisherman community comprising about 225 household
Significant
2 Area of Impact Spread Relatively widespread, particularly in Tambaksoso Wilangon village, Greges village
Significant
3 Impact Duration/Intensity
It is predicted to be during the construction phase with relatively high intensity.
Significant
4 Other impacted components
Decreased community (fisherman) welfare Significant
5 Impact Cumulativeness It is cumulative
Significant
6 Impact recoverability It is unrecoverable Significant
Based on the aforementioned descriptions, the impact on disturbance to
fisherman activities is categorized to be negative significant (NS)
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 43 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
5.1.2 OPERATION PHASE
5.1.2.1 Multipurpose Terminal Operation
A. Decreased Seawater Quality
Source of Impact
Multipurpose Terminal Operation
Predicted Degree of Impact
The initial environmental conditions in the areas close to the trestle, on
connecting bridge and container yard are relatively good and in general satisfy
the standards.
The multifpurpose terminal is operated for container yard, silo of grain
food and grain feed, gate terminal and other supporting facilities, such as :
Container Freight Station (CFS), office buildings, gates and parking lots.
Analoguously, the activities can contribute to decreased seawater quality, due to
either material spills or other activities.
The maximum current from the shipping routes ranges from 0.62 m/sec
to 1.0 m/sec. On the other hands, the current is relatively show, i.e. : 0.1
m/sec. As the reclamation in on shallow water where the current will be
relatively slower with less wide spread.
The monitoring activities in the port will be analoguous to the ones in
TanjunG perak Port. In tanjung Paerak Port, the monitoring takes place in West
Nilam and East Nilam. Based on the monitoring data collected from 2008-2011,
only TSS in quarter 3 yaer 2009 in West Nilam was overthe the quality standard,
i.e. : 137 mg/l , while the standard is 80 mg/l. (Report of Pollution Control in
Coastal Area by Surabaya City Environmental Agency, 2011). Accordingly, the
condition in the waters in the project site is still in good condition. Based on the
aforementioned descriptions, the impact on decreased seawater quality is
relatively significant.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 44 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Predicted Dimension of Impact
Table 5.27. Evaluation on Dimension of Impact on Decreased Seawater Quality in Operation Phase
Nr. Significant Impact
Criteria Remarks Valuation
1 Number of impacted residents
The impacted residents are fishermen finding less nekton due to decreased seawater quality
Significant
2 Area of Impact Spread The area of impact spread is relative limited, not exceeding 30 mg/l in radius of 100 m from the source.
Insignificant
3 Impact Duration/Intensity It is predicted to be continuous during the operation phase.
Significant
4 Other impacted components
The other impacted compoonents are decreased abundance of sea biota/nekton and fisherman unrest
Significant
5 Impact Cumulativeness It is not cumulative Significant
6 Impact recoverability The impact is recoverable the soruce stops by proper management steps.
Insignificant
Based on the aforementioned description, the impact on decreased seawater
quality due to the multipurpose terminal operation the impact is
categorized negative significant (NS).
B. Decreased Road Performance
Source of Impact
Multipurpose Terminal Operation.
Predicted Degree of Impact
To identify the degree of impact, the number arising fleets due to the
multipurpose terminal operation must be identified. The number of fleets in
the multipurpose terminal are calculated by comparing the number of fleets in
the similat activities in Nilam Terminal in Tanjung Perak Port.
In this study, the comparison adopts the area of Nilam Terminal with its
traffic volume due to the operation of this terminal. The area of Nilam Terminal
in Tanjung Perak Port is ±517.180 m2, with the one of multi purpose terminal in
Lamong Bay is 355.000 m2. The traffic flow in Nilam Pier is 200 smp/hour,
therefore the traffic flow in multipurpose terminal in Lamong Bay is assumed to
be smp/hour or 105 trucks/hour. Considering the growth of Regional Domestic
Gross Income of Surabaya City by 6.28%, the traffic growth under the initial
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 45 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
environmental descriptions in year 2012 will significantly increase initial
operation year of 2014 and the one of 2019.
Table 5.28. Planned Traffic Volume Without Project
Next, when the traffic volume driven by the terminal operation is burdened to
the traffic network, the results of calculation of the road performance are
presented in Table 5.29.
Table 5.29. Planned Traffic Volume with Project
The road performance is measured subject to an assumption that the project
does not exist in order to identify the change of road performance.
LV HV MC LV HV MC LV HV MC LT 7 25 66 8 28 75 11 38 101 ST 143 16 3063 162 18 3460 219 25 4691 LT 437 52 145 494 59 164 669 80 222 ST 166 148 6247 188 167 7056 254 227 9568 RT 11 0 59 12 0 67 17 0 90 LT 329 88 36 372 99 41 504 135 55 RT 7 17 27 8 19 30 11 26 41 ST 89 2 1438 101 2 1624 136 3 2203 RT 101 126 755 114 142 853 155 193 1156
East (Jl. Kali Anak) LT 157 101 4743 177 114 5357 240 155 7265 LT 207 81 5741 234 91 6485 317 124 8793 RT 145 2 2553 164 2 2884 222 3 3910
From Sby to Gresik T-B 190 66 5785 215 75 6534 291 101 8861 From Sby to Gresik B-T 185 101 2703 209 114 3053 283 155 4140
No. Junction Connector Traffic Movement
Traffic Volume (Vhcl/hour) 2012 2014 2019
1 Romokalisari
East (Jl. Romokalisari)
North (Romokalisari Bridge – East Side)
South (Toll Road Access Romokalisari)
3 Fishpond Tributaries
2 Margomulyo
West (Jl. Tambak Langon)
South (Jl. Margomulyo)
LV HV MC LV HV MC LV HV MC LT 7 25 66 8 52 75 11 95 101 ST 143 16 3063 162 34 3460 219 62 4691 LT 437 52 145 494 108 164 669 196 222 ST 166 148 6247 188 167 7056 254 227 9568 RT 11 0 59 12 0 67 17 0 90 LT 329 88 36 372 99 41 504 135 55 RT 7 17 27 8 35 30 11 72 41 ST 89 2 1438 101 3 1624 136 20 2203 RT 101 126 755 114 205 853 155 328 1156
East (Jl. Kali Anak) LT 157 101 4743 177 114 5357 240 155 7265 LT 207 81 5741 234 132 6485 317 221 8793 RT 145 2 2553 164 2 2884 222 3 3910
From by to Gresik T-B 190 66 5785 215 144 6534 291 232 8861 From Gresik to Sby B-T 185 101 2703 209 150 3053 283 205 4140
3 Fishpond Tributary
2 Margomulyo
West (Jl. Tambak Langon)
South (Jl. Margomulyo)
1 Romokalisari
East (Jl. Romokalisari)
North (Romoklaisari Bridge – East Side)
South (Toll Road Access toll Romokalisari)
No. Junction Connector Traffic Movement
Traffic Volume (Vhcl/hour) 2012 2014 2019
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 46 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Table 5.30. Road Performance in Initial Description, With and Without Project
It shows that the condition (either with or without project activities, the
degree of traffic saturation in those three places is significant, particularly
during peak time : 06.00 - 08.00.
Predicted Dimension of Impact
Tabel 5.31. Evaluation on Dimension of Impact on Transportation in Operation Phase
Nr. Significant Impact
Criteria Remarks Valuation
1 Number of impacted residents
Some traffic users on Jalan Romokalisari and Jalan Tambak Osowilangon, as those are the accesses of reclamation dump trucks from Container Terminal in Lamong Bay to Tool Road (Gempol – Surabaya – Gresik)
Insignificant
2 Area of Impact Spread Along Jl. Tambak Osowilangon Insignificant
3 Impact Duration/Intensity The impacts will exist during operation phase of container terminal with high intensity, i.e. : degree of traffic saturation 0.8 (Manual Indonesian Capacity Manual), meaning that the traffic on the roads aris alreay dense.
Significant
4 Other impacted components
The other impacted components are Decreased Air Quality with the volume o additional traffic (+ 105 trucks per hour) and along the roads (Jl. Romokalisari and Tambak Osowilangon) there are 2 way 4 lanes with road median in the middle of the road. Accordingly, the impact significantly lead to Decreased Air Quality
Significant
5 Impact Cumulativeness The impact on decreased road performance is cumulative as it takes place only during peak hour.
Insignificant
6 Impact recoverability The impact is recoverable during the terminal operations.
Insignificant
It is conclusive that the impact is negative significant (NS).
LV HV MC LV HV MC LV HV MC LT 7 25 66 8 52 75 11 95 101 ST 143 16 3063 162 34 3460 219 62 4691 LT 437 52 145 494 108 164 669 196 222 ST 166 148 6247 188 167 7056 254 227 9568 RT 11 0 59 12 0 67 17 0 90 LT 329 88 36 372 99 41 504 135 55 RT 7 17 27 8 35 30 11 72 41 ST 89 2 1438 101 3 1624 136 20 2203 RT 101 126 755 114 205 853 155 328 1156
East (Jl. Kali Anak) LT 157 101 4743 177 114 5357 240 155 7265 LT 207 81 5741 234 132 6485 317 221 8793 RT 145 2 2553 164 2 2884 222 3 3910
From Sby to Gresik T-B 190 66 5785 215 144 6534 291 232 8861 From Gresik to Sby B-T 185 101 2703 209 150 3053 283 205 4140
3 Fishpond Tributary
2 Margomulyo
West (Jl. Tambak Langon)
South (Jl. Margomulyo)
1 Romokalisari
East (Jl. Romokalisari)
North (Romokalisari Bridge – East Side)
South (Toll Road Access Romokalisari)
No. Junction Connector Traffic Movement
Traffic Volume (Vhcl/hour) 2012 2014 2019
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 47 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
C. Decreased Mangrove Ecosystem Area
Source of Impact
The decreased mangrove ecosystem area is due to Multipurpose terminal
operation.
Predicted Degree of Impact
The operation of multipurpose terminal will bring impacts on decreased
mangrove ecosystem area. At present in the studied area there are 13 species of
mangrove spread over 8 observation points woth plant density of >2,000
trees/hectare. Pursuant to Decision of Minister of Environment Number : 201
Year 2004 about Mangrove Density Standard, the mangrove density of > 1,500
trees/hectare is categorized to be very dense . The decreased of mangrove
ecosystem area is alleged to be due to demolition of erected temporary access.
In addition, the decreased mangrove ecosystem area also lead to
decreased water bird habitat. At present, there are 39 species categorized into
22 families. The identified bird species in the studied area are 14 conserved by
virtue of Indonesian State Regulation Number 7 Year 1999, and IUCN Red list, and
one is included into an Indonesian endemic (Alcedo coerulescens /Blue Shrimp
King). Beside, 1 bird speciesb found in Sememi River : i.e. : Bluwok
Heron(Mycteria cinerea)is internationally conserved.
The operation of the multiurpose terminal will entail movement of
avifauna to the nearest mangrove area due to noises resulted from the
operations of container trucks.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 48 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Predicted Dimension of Impact
The evaluation of impact on decreased mangrove ecosystem area as
habitat of sea biota based on 6 significant impact criteria is presented in the
table below.
Table 5.32. Evaluation on Dimension of Impact on Decreased Mangrove Ecosystem Area In Operation Phase
Nr. Significant Impact
Criteria Remarks Valuation
1 Number of impacted residents
It is predicted that the decreased mangrove ecosystem area (> 10%) will lead to disturbance to the residents doing activities in the mangrove ecosystem as the area is not only occupied for conservation area but also shrimp and milkfish breeding. The operation of multipurpose terminal sooner or later will decrease or even eliminate the mangrove area.
Significant
2 Area of Impact Spread
The spread of the impact will be limited in the studied area, yet it is pretty wide as it covers six village areas, namely : Romokalisari village, Tambak Osowilangun village, Tambak Langon village, Greges village, Kalianak village and Krembangan village
Significant
3 Impact Duration/Intensity
The impact will take pretty long time and exceed the operation period. It is predicted that the decreased mangrove ecosystem area will be > 50%.
Significant
4 Other impacted components
Due to decreased mangrove ecosystem area, it will affect more than two environmental components, i.e. : traditional fishpond, water bird habitat and sea biota spawning area.
Significant
5 Impact Cumulativeness
It will be cumulative and take place continuously as long as the operation of the terminal entailing multi-level economic effects and community income. Consequently the loss of mangrove area will be getting wider.
Significant
6 Impact recoverability
The impact will be unrecoverable as the required business space will be getting larger and wider, while the mangrove habitat is getting narrower and probably finished.
Significant
Based on the aforementioned descriptions, it conclusive that the impact is
negative significant (NS).
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 49 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
D. Disturbance to Sea Biota
Source of Impact
The impact on disturbance to sea biota, i.e. : decreased compositions
and abundance of plankton/nekton due to multipurpose terminal operation.
Predicted Degree of Impact
The status of seawater quality in the site is fair with phytoplankton
diversity index ranging 0,989 – 2,237 and zooplankton diversity index ranging
0.629 – 2.01. The operation of the multipurpose terminal will be potential to
entail waste spills and oil spills from means of sea transportation. The decreased
water quality will also affect fishery activities along the coastal area close to the
project site for good as the fishermen take sea water for watering their fishpond.
The performance of fishery activities and fish and shrimp abundance are
predicted to decrease due to poor seawater quality in their habitat.
Predicted Dimension of Impact
The evaluation of impact on Decreased compositions and Abundance of
Plankton/Nekton based on 6 significant impact criteria is presented in the
following table.
Tabel 5.33. Evaluation on Dimension of Impact on Disturbance to Sea Biota (Decreased compositions and Abundance of Plankton) in Operation Phase
Nr. Significant Impact
Criteria Remarks Valuation
1 Number of impacted
residents It is predicted that the Decreased compositions and Abundance of Plankton/Nekton will lead to less fish cactching performance and the
fishery activities close to the multipurpose terminal by the local community.
Significant
2 Area of Impact Spread The spread of the impact will be limited in the studied area, yet it is pretty wide as it covers six village areas, namely : Romokalisari village, Tambak Osowilangun village, Tambak Langon village, Greges village, Kalianak village and Krembangan village
Significant
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 50 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Nr. Significant Impact
Criteria Remarks Valuation
3 Impact Duration/Intensity The decreased compositions and abundance of plankton/nekton during the operation of the multi purpose terminal will take pretty long time and the impact intensity is predicted to be >50%.
Significant
4 Other impacted components
Due to decreased mangrove ecosystem area, it will affect more than two environmental components, i.e. : traditional fishpond, water bird habitat and sea biota spawning area, and decreased fisherman income.
Significant
5 Impact Cumulativeness The decreased compositions and abundance of plankton/nekton will be cumulative and take place along the operation since the longer the operation period, the more waste and oil spills will be. This will consistently decrease the seawater quality as their habitat.
Significant
6 Impact recoverability The decreased compositions and abundance of plankton/nekton will be recoverable in case the impact is properly managed.
Insignificant
Based on the aforementioned descriptions, it conclusive that the impact is
negative significant (NS).
E. Job and Business Opportunities
Source of Impact
Multipurpose Terminal Operation
Predicted Degree of Impact
The needs on job and business opportunities in the studied area are
pretty significant. Referring to the secondary data, there are quaite number of
jobless people among 3,650 residents in the studied area. The number of jobless
family heads is 670. The operation of the multipurpose terminal will requre 300
labors to be posted as porters. In 2010, the project opened 2,000 job
opportunities. In addition, its operation will also open business opportunities for
delivering services to the porters and port service users. The job opportunities
can be long lasting, as long as the operation of the multipurpose terminal.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 51 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Based on the aforementioned descriptions, the operation of the
multipurpose terminal based on 6 significant impact criteria is presented in the
following table.
Predicted Dimension of Impact
Tabel 5.34. Evaluation on Dimension of Impact on Job and Business Opportunities in Operation Phase
Nr Criteria Remarks Valuation
1 Number of impacted
residents
The total impacted resident are 3,650. 670 of
the family heads ( about 10%-20% of the
residents) in the community are jobless.
Insignificant
2 Area of Impact
Spread
Pretty widespred as it covers (6 villages), namely : Romokalisari village, Tambak Osowilangun village, Tambak Langon village, Greges village, Kalianak village and Krembangan village.
Significant
3 Impact
Duration/Intensity
The impact on job and business opportunities
will be long lasting, during the operation of
the multipurpose terminal.
Significant
4 Other impacted components
The impacted components are increased
community and business earnings that are
both favorable for coping with the
unemployment problem.
Significant
5 Impact
Cumulativeness
The impact is not cumulative as the activities
are getting dense and require more workers
and open more business opportunities.
Significant
6 Impact recoverability The impact of job and business opportunities
is nor recoverable
Significant
Based on the aforementioned descriptions, it conclusive that the impact is
positive significant (NS).
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 52 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
F. Disturbance to Fisherman Activities
Source of Impact
Multipurpose Terminal Operation
Predicted Degree of Impact
The operation of the multipurpose terminal entails disturbance to
fisherman activities in certain zones not accessible by the fishermen in shallow
waters with depth ranging 0.5 – 2 m and greatly affected by the tide. During
low tide, the studied area will be spread of seabed with mud and sand. In front
of the project site, there are West Surabaya shipping routes in 8 – 13 m depth
sea where some rivers flow into it. Accordingly, it is potential to cause pretty
significant sedimentation. It will certainly reduce the fishing ground and make
the fishermen take longer routes to go fishing on deep sea. Referring to the
results of interview about preparation and compaction of area for constructing
causeway, interchange area and container yard it will entail disturbance to
fisherman activities and decrease their income. Their income used to be
varying from IDR 75,000 to IDR 100,000. However, it now ranges between IDR
20,000 to IDR 30,000/day. They sometimes even get no income .
Predicted Dimension of Impact
Based on the aforementioned descriptions, the evaluation of impact on
disturbance to fisherman activities based on 6 significant impact criteria is
presented in the following table.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 53 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Tabel 5.35. Evaluation on Dimension of Impact on disturbance to fisherman activities in Operation Phase
Nr Criteria Remarks Valuation
1 Number of impacted
residents
Fisherman community comprising about 225 household
Significant
2 Area of Impact Spread Relatively widespread, particularly in Tambaksoso Wilangon village, Greges village
Significant
3 Impact
Duration/Intensity
It is predicted to be during the construction and operation phases with relatively high intensity.
Significant
4 Other impacted
components
Decreased community prosperity (fisherman)
Significant
5 Impact Cumulativeness It is cumulative Significant
6 Impact recoverability It is unrecoverable Significant
Based on the aforementioned descriptions, it is conclusive that the impact on
disturbance to fisherman activities is categorized to be negative significant (NS).
G. Community Unrest
Source of Impact
It is an impact derived from disturbance to fisherman activities and
Decreased Road Performance.
Predicted Degree of Impact
The community unrest is related with decreased fisherman income due to
less caught fish and damaged ecosystem. In addition, the community is worry
about decreased road performance. Based on the predicted components of
transportation, it shows that the condition (either with or without project
activities, the degree of traffic saturation in those three places is significant,
particularly during peak time : 06.00 - 08.00.
Predicted Dimension of Impact
Based on the aforementioned descriptions, the evaluation of impact on
community unrest based on 6 significant impact criteria is presented in the
following table.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 54 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Table 5.36. Evaluation on Dimension of Impact on Community Unrest in Operation Phase
Nr Criteria Remarks Valuation
1 Number of impacted
residents
Particularly the fisherman community in Tambakoso Wilangon village, Greges village
Significant
2 Area of Impact Spread Relatively widespread, particularly in Tambaksoso Wilangon village, Greges village
Significant
3 Impact Duration/Intensity It is predicted to be during the operation phases with relatively high intensity.
Significant
4 Other impacted
components
It will affect the security due to demonstration when the problems are bot well treated.
Significant
5 Impact Cumulativeness It is cumulative
Significant
6 Impact recoverability It is unrecoverable Significant
Based on the aforementioned descriptions, it is conclusive that the impact on
community unrest is categorized to be negative significant (NS).
5.2. IMPACT EVALUATION
5.2.1. Holistic Review to Significant Impacts
The evaluation on significant impacts are holistic reviews. Various
impacted environmental components (either positively or negatively) are
reviewed as an interelated and integrated unit. The holistic analysis on the
possible significant impacts are presented in a flowchart in Figure 5.21. Based
on the results of analysis shown in the flowchart, the significant impacts can be
categorized as significant impacts in view of construction plans and
environmental components that are fundamentally changed as follows :
1. Change of Coastal Ecology
2. Change of Community Welfare
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 55 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Pengangkutan material
urug lewat darat
Pembongkaran
"Temporary Access"
yang telah terbangun
Pekerjaan Jembatan
Penghubung, Interchange
Area, Causeway, Container
Yard dan Trestle
Pengerukan Rencana
Kolam Pelabuhan
Operasioanal Dermaga
Multipurpose
Gangguan Biota
Laut
Penurunan
Kinerja Jalan
Penurunan
Kualitas Udara
Penurunan
Kualitas Air Laut
Penurunan Luasan
Ekosistem mangrove
Gangguan
Aktivitas Nelayan
Peningkatan
KebisinganPenurunan
Kinerja Jalan
Penurunan Luasan
Ekosistem
Mangrove
Tersedianya
kesempatan
kerja &
berusaha
Mobilisasi dan Demobilisasi
Peralatan dan Material Pre - Cast Temporary Access Pembangunan Pelabuhan Pekerjaan Dermaga Tahapan Operasi
Penurunan
kualitas air laut
Gangguan Biota
Laut
Gangguan
Aktifitas
Nelayan
Keresahan
masyarakat
Perubahan Pola
Arus dan
Sedimentasi
Peningkatan Muka
Air Banjir di
Sungai
TAHAP KONSTRUKSI TAHAP OPERASI
Figure 5.21. Holistic Impact Evaluation Flowchart
CONSTRUCTION PHASE OPERATION PHASE
Pre-Cast Material and Equipment
Mobilization and Demobilization
Temporary Access Port Construction Pier Works
On-land Reclamation Material Transportation
Demolition of Erected Temporary Access
Connecting Bridge, Interchange Area, Causeway,
Container Yard and Trestle
Works
Planned Port Pool Dredging
Decreased
Air Quality
Decreased Road
Performance Quality
Increased
Noise
Decreased Seawater
Quality
Decreased Mangrove Ecosystem
Area
Disturbance to Fisherman
Activities
Disturbance to
Sea Biota
Change of Current Pattern and
Sedimentation
Increased River Water
Surface
Operation Phase
Multipurpose Terminal
Operation
Decreased Road
Performanc
e Quality
Disturbance to Fisherman
Activities
Job & Business
Opportunities
Decreased Seawater Quality
Decreased Mangrove Eco-
system Area
Disturbance to Sea Biota
Community
Unrest
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 56 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
5.2.1.1 Change of Coastal Ecology
The aspect of ecological change is related with the impacts of port
development in Lamong Bay to physical and chemical envirinmental
components.
The physical-chemica-biological components impacted by the port
development comprise : decreased air quality and increased noise, decreased
sewater quality, change of current pattern and sediment, increased river water
surface, decreased road performance and decreased mangrove ecosystem
area.
The impacts on decreased air quality and increased noise as well as
decreased water quality due to the activities in construction phase. In the mean
time, the impacts on change of current pattern and sedimentation, change of
river water surface take place during construction phase and they extend to the
operation phase. During the construction phase, the activities affecting the
aforementioned conditions are on-land reclamation material transportation for
constructing causeway, interchange area and container yard. In the operation
phase, the impacts on decreased air quality and increased noise and decreased
road performance take place due to increased mobility of cargo and passenger
transportations.
The impact on decreased seawater quality takes place during both
construction phase and operation one. During the construction phase, the
demolition of erected temporary access for construction works prior to the
erection of causeway (on-pile construction), it is also due to shallow water
reclamation for constructing causeway (massive construction), preparation and
compaction of reclamated area for constructing the container yard and port pool
dredging. The parameter of suspended solid can be acumulative when the
activities proceeed successively. The impact on decreased seawater quality also
take place in operation phase, operation of multipurpose terminal and therefore
accumulative with the one in construction. The increase of decreased seawater
quality will lead to disturbance to sea biota, particularly decreeased
compositions and abundance of plankton/nekton when not properly managed.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 57 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
5.2.1.2. Change of Community Welfare
During the construction phase, it is predicted that there will be
disturbances to Fisherman activities due to demolition of erected temporary
access, reclamation for preparing the construction of causeway (massive
construction), preparation and compaction of reclamated area for constructing
the container yard and port pool dredging. However, during the operation of the
multipurpose terminal, there will be job and business opportunities for the local
people in order to bring favorable impacts to the coommunity. The requirement
of job and business opportunities is pretty significant as the number of jobless
people in the stidied are is pretty many. Besides, the operation of multipupose
terminal will also bring business opportunities delivering services to the porters
and port service users. The job opportunities can be long lasting, as long as the
operation of the multipurpose terminal.
Despite the positive impact during the operation phase, it also bring
negative impact on decreased fisherman income as the operation of the
multipurpose terminal will certainly disturb the fisherman activities as and in
some points it is not accessible for fishing routes for the surrounding traditional
fishermen. Consequently the fishing area will be less and probably they need to
sail longer to go fishing.
5.2.2. Review as Basis for Environmental Impact Management
The impacts on decreased seawater quality, change of current pattern
and sedimentation, change of river water surface, decreased road performance,
decreased compositions and abundance of plankton/nekton, disturbance to sea
biota and disturabance to Fisherman activities as well as community unrest will
take placein both construction phase and operation one. The impact on job and
business opportunities are predicted to present during the operation phase.
Those impacts can be better managed by means of technologies and
environmental management funds. To formulate the management, it needs to
well consider the present environmental conditions.
Based on the initial description of the environmental condition, the
ambient air quality, particularly in sampling points close to the project site
(close to the coastal area) is pretty poor as the dust content is pretty high and
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 58 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
exceeds the standard as stipulated by the Regulation of Governor of East Java
Province Nr.10 Year 2009 about Ambient Air Quality Standard and Immovable
Source of Emission in East Java Province. Such high dust content is due to the
existing reclamation activities. In addition, the degree of noise in the studied
area is already high and exceeds the noise quality standard due to cargo and
passenger transportation activities by means of motorized vehicles
Based on the initial environmental descriptions, the TSS has exceeded the
seawater quality standard for sea biota pursuant to Decision of Minister of
Environment Nr. 51 Year 2004 Annex III. In view of the port, there are two
locations the TSS of which has exceeded the standard, i.e. : estuary of
Branjangan River and the one of Greges River. The performance of roads in some
points will be impacted by the project, i.e. : Romokalisari Junction, Margomulyo
Junction and tributaries analogous to access roads in Nilam Terminal in Tanjung
Perak Port. The performance of the aforementioned roads at present (2012),
particularly in Romokalisari Junction, Margomulyo Junction and tributaries, is
ense during peak time in the morning (06.00-08.00) with degree of saturation of
> 0.8. In terms of change of current pattern and sediment as well as river water
surface, the changes are relatively insignificant, yet it is a major issue to the
community.
Based on the results of interview, it is found that the requirement of job
and business opportunities is pretty significant as the number of jobless people in
the stidied are is pretty many. The existing construction activities have
decreased the fisherman income by 60%-70%). The respondents perceive that it is
due to damaged fish habitat. The community unrest is mainly related with the
decreased fisherman income due to damaged fish habitat leading to loss of fish
and ridged of rock exposed during low tide. They perceive that the sea
ecosystem is damaged by project waste and reclamation in Lamong Bay that
used to be traditionally their fishing ground. Consequently, not may fisherman go
fishing and may of them are presently jobless. Such a condition will lead to
community unrest. They worry about damaged roads,particularly close to the
project site (Kalianak), due to access by heavy trucks, floods due to narrowing
channels to the sea due to reclamation and change of functions of the coast,
that at last badly affect the traditional coastal fishermen and fispond farmers.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 5 – IMPACT PREDICTION AND EVALUATION
V - 59 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
5.3. RECOMMENDATION ON ENVIRONMENTAL FEASIBILITY EVALUATION
The results of significant impact prediction and significant impact
evaluation, the project is environmentally feasible subject to the following
considerations :
1. The technical aspects are designed in such a way that it ensures the
security and safety and accordingly it will be constructed in accordance
to the obtained permits.
2. The impact can be handled by means of the available technology.
Executable designs and measures through technical approach, socio-
economic and cultural approach, and institutional approach to cope with
the arising impacts have been prepared.
3. In veiew of partnership with the community, especially the one directly
impacted by the project, two-way communications have been
endeavored in order to manage the impacts properly and effectively
minimize misunderstanding and conflict with them.
4. In view of spatial aspect, the project complies with the Regulation of
East Java Province Number 05 Year 2012 about East Java Province Master
Plan Year 2011-2031 in order to facilitate both local and regional
economic development programs.
LV HV MC LV HV MC LV HV MC LT 7 25 66 8 28 75 11 38 101 ST 143 16 3063 162 18 3460 219 25 4691 LT 437 52 145 494 59 164 669 80 222 ST 166 148 6247 188 167 7056 254 227 9568 RT 11 0 59 12 0 67 17 0 90 LT 329 88 36 372 99 41 504 135 55 RT 7 17 27 8 19 30 11 26 41 ST 89 2 1438 101 2 1624 136 3 2203 RT 101 126 755 114 142 853 155 193 1156 (Jell. Kali Anak) LT 157 101 4743 177 114 5357 240 155 7265 LT 207 81 5741 234 91 6485 317 124 8793 RT 145 2 2553 164 2 2884 222 3 3910 Dari Sby ke Gresik T-B 190 66 5785 215 75 6534 291 101 8861 Dari Gresik ke Sby B-T 185 101 2703 209 114 3053 283 155 4140 No. Persimpangan Pendekat Pergerakan Lalu lintas Volume lalu lintas (kend./jam) 2012 2014 2019 1 Simpang Romokalisari Timur (Jl.
Romokalisari) Utara (Jembatan Romokalisari sisi
Timur) Selatan (Akses toll Romokalisari) 3 Ruas Jalan Tambak 2 Simpang
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 6 – ENVIRONMENTAL IMPACT MANAGEMENT PLAN
VI - 1 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
CHAPTER 6 ENVIRONMENTAL IMPACT MANAGEMENT PLAN
Referring to the results of reviews in the previous chapters, it is
predicted that Tanjung Perak Port Development in Lamong Bay will significantly
bring both positive and negative impacts to the suttounding environment. The
significant impacts predicted to emerge during the construction phase will be
decreased air quality, increased noise, decreased seawater quality, increased
surface of river runoff, change of water current patterns and sedimentation,
decreased road performance, disturbance to sea biota, decreased mangrove
area, disturbance to fisherman activities and community unrest. In the
operation phase, it is predicted that it will bring impacts to decreased
seawater quality, decreased road performance, disturbance to sea biota,
decreased mangrove area, job and business opportunities, disturbance to
fisherman activities and community unrest. Accordingly, it is necessary to
prepare an Environmental Impact Management Plan as a support to the
available environmental study documents.
6.1. GOALS AND OBJECTIVES
The goal of the preparation of environmental impact management plan is
to prevent, handle, and control any major and significant negative impacts due
to the plans of Tanjung Perak Port Development in Lamong Bay in order that it
can bring greater benefits to all, especially the communities surrounding the
project site.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 6 – ENVIRONMENTAL IMPACT MANAGEMENT PLAN
VI - 2 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
The objectives of the environmental impact management are :
Formulizing the proper actions and measures for avoiding, preventing,
minimizing, handling and controlling the significant negative impacts
due to Tanjung Perak Port Development in Lamong Bay.
Formulizing the proper actions for improving, enhancing and
developing the to improve the positive impacts in order that it bring
greater benefits due to Tanjung Perak Port Development in Lamong
Bay.
Formulizing the executor and supervisor of environmental impact
management activities and receipients of environmental management
performance reports in the line with the activities
Determining the locations and schedules of the implementation of
environmental impact management activities.
6.2. BENEFITS OF ENVIRONMENTAL IMPACT MANAGEMENT
The environmental impact management plan will be beneficial to
PT. Pelindo III, the government or relevant institutions and the community
surrounding the project site.
6.2.1. Benefits to Project Initiator
The environmental impact management plan will be beneficial to PT
Pelindo III for the following reasons :
It will guide to avoid, prevent, minimize, handle and control the negative
signficant impact that may arise due to the activities of Tanjung Perak Port
Development in Lamong Bay.
It serves as a reference when actively participating in efforts to preserve the
environment around the project site.
It is for complying the prevailing laws and regulations promulgated by the
government.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 6 – ENVIRONMENTAL IMPACT MANAGEMENT PLAN
VI - 3 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
6.2.2. Benefits to the Government and Relevant Institutions
The environmental impact management plan will be beneficial to the
government and relevant institutions as it is adoptable as basis for:
Observing the environmental impact management activities, especially
the ones to be undertaken by the project initiator.
Passing policies and granting permits to support the activities of Tanjung
Perak Port Development in Lamong Bay.
Evaluating the implementation of environmental impact surrounding the
project site by the relavant institutions.
Managing the environment surrounding the project site by the relevant
institutions.
6.2.3. Benefits to Surrounding Community
The environmental impact management plan will be beneficial to the
surrounding community as valuabel information so that they can :
Participate in observing the implementation of the environmental impact
management plan in the line with the activities of Tanjung Perak Port
Development in Lamong Bay.
Avoid and anticipate the negative impacts that may affect the surrounding
community.
Contribute to the preservation of the surrounding environment.
6.3. ENVIRONMENTAL IMPACT APPROACHES
To formulate proper environmental impact management plan, it needs to
much consider about control to sources impacts so that the impacts can be
minimized or prevented. The effective measures to minimize and or prevent such
impacts can be by adoption of science, technology and change of human attitude
in implementing the environmental impact management plan. In terms of socio-
economic and cultural aspects, the preventive actions can be adopted through
intensive approaches to the relevant institutions and directly impacted
community at erliest. Next, the environmental impact management plan is
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 6 – ENVIRONMENTAL IMPACT MANAGEMENT PLAN
VI - 4 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
supposed to effectively control the impacts to the surrounding environment.
Accordingly, the preparation of the environmental impact management plan in
the line with the activities of Tanjung Perak Port Development in Lamong Bay
may adopt 3 (three) approaches : technological approach, economic approach
and institutional approach.
6.3.1. Technological Approach
The technological approach is adopted to minimize or cope with the
arising negative impacts by adopting available technological approach in
accordance with the available resources. The technological approach is applied
in various steps, inter alia :
o Before reclaiming the shallow waters, riprap embankment is to be
established to prevent reclamation material spills
o The wastes from the activities for Tanjung Perak Port Development in
Lamong Bay shall be treated properly, by :
- Solid Waste
The rubbish resulted from the operation of multipurpose terminal shall is
to be collected and deposited in a temporary trash deposit before
transported to Benowo Landfill. The wet rubbish collected from the port
pool or seawater will be transported from the pier to Benowo landfill by
truck.
- Liquid Waste and Dangerous and Hazardous Material
The liquid waste and dangerous and hazardous material in the port are to
be treated in a reception facility. Pursuant to Annex IV MARPOL 73/78
Regulation 10, the port administrator is to provide reception facility (RF)
in accordance to the vessel needs. In Indonesia the operation of a
reception facility is provided by Regulation of State Minister of
Environment Number 05 Year 2009 about Waste Treatment in Ports. The
activities in a RF cover collection and storing of dangerous and hazardous
waste and treatment of wastes, supported with : oil separator, Waste
Water Treatment Plant (WWTP) and landfill residu (such as : incinerator).
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 6 – ENVIRONMENTAL IMPACT MANAGEMENT PLAN
VI - 5 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
o Port Security Management
The port administrator will adopt International Ship and Port Facility
Security (ISPS Code), to manage the port security and periodically provide
security training programs for the relevant port security officers and
guards. The adoption of the ISPS Code in Tanjung Perak is supported with
human resource preparation and physical prepartion in the port, such as
installation Close Circuit Television (CCTV), addition of street lamps and
fencing.
o Applying port SOP pursuant to State Regulation No. 61 Year 2009 about
Port.
o In case of oil spills into drainage and trapped in oil catcher, it is to be
suctioned and stored in a special drum and/or tank truck.
o Emergency handling is to be applied in consistence with Standard
Operation Prosedur (SOP).
o Installing navigation signals pursuant to the Indonesian State Regulation
Nr. 5 Year 2010 about Navigation
6.3.2. Socio-Economic Approach
The socio-economic approach is applied to cope with/minimize the
negative impacts due to Tanjung Perak Port Development activities in Lamong
Bay, by :
Approaching and conducting coordination with public figures and
village/sub-district administrators/officers before commencing the
construction activities for Tanjung Perak Port Development in Lamong Bay
Recruitment of local people in accordance with the required qualifications
and cooperation with the relevant Man-Power Service.
Approaching the community in determining the compositions and number of
hires to enter into employment agreement between PT. PELINDO III and the
local hires.
Advocating the fishermen about limited and restricted area in the area of
Tanjung Perak Port Development in Lamong Bay.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 6 – ENVIRONMENTAL IMPACT MANAGEMENT PLAN
VI - 6 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Providing empowerment to those changing professions as fishermen.
Adopting CSR program to provide aids in forms of tools and equipment for
those motivated to sail to deep sea.
Providing open CSR program in favor of the local people.
Submitting reports to Surabaya City Development Agency and East Java
Province Development Bureau concerning the implementation of CSR
programs.
Actively reforestating mangrove, especially in coastal area for preserving
the seawater quality.
6.3.3. Institutional Approach
Proper environmental impact handling requires not only technical
approach and socio-economic approach, but also institutional approach as it
requires coordination among the initiator, supervisor and other competent
authorities through the last approach. The institutional approach will be applied
in connection the following issues :
PT. (Persero) Pelabuhan Indonesia III will be committed to respect the
prevailing environmental regulations both in local and national scale.
PT. (Persero) Pelabuhan Indonesia III will consistently coordinate with the
relevant institutions, especially with the ministry of Environment in
Jakarta, East Java Province Environmental Agency, Surabaya City
Environmental Agency, East Java Province Manpower Service and Surabaya
City Manpower Serviceconcerning with socio-economic and community
problems.
PT. (Persero) Pelabuhan Indonesia III will cooperate with other
stakeholders managing similar activities surrounding the the port territorry
under the administration of PT. (Persero) Pelabuhan Indonesia III and
manage the environmental impacts under the supervision of competent
authorities in environmental management.
Supervision and monitoring on the results of environmental impact
management measures by the competent authorities.
PT PELABUHAN INDONESIA III (PERSERO)
CHAPTER 6 – ENVIRONMENTAL IMPACT MANAGEMENT PLAN
VI - 7 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Establishment of an organization unit to be in charge of environmental
impact management.
PT. (Persero) Pelabuhan Indonesia III consistently prepares semi-annual
reports on the implementation of EIM and EIO plans in accordance with the
prevailing EIM and EIO formats pursuant to the Decision of State Minister
of Environment Nr. 45 Year 2005 about Guide to Reporting of
implementation of EIM and EIO plans and the Indonesian State Regulation
Nr. 27 Year 2012 about Environemental Permit.
Security handling training programs in the line with implementation of ISPS
Code, by involving the Port Security Executive Unit of Tanjung Perak Port,
Indonesian Army, Indonesian Navy, Tanjung Perak Port Security Authority,
PT. Pelindo , Fire Brigade and companies in the port territorry.
6.4. ENVIRONMENTAL IMPACT MANAGEMENT PLAN
The plans for managing the predicted impacts driven by Tanjung Perak
Port Development activities in Lamong Bay is presented in Table 6.1, while the
locations of the management are presented in Figure 6.1.
PT PELABUHAN INDONESIA III (PERSERO) CHAPTER 6 – ENVIRONMENTAL IMPACT MANAGEMENT PLAN
VI - 8 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Table 6.1. Matrix of Environmental Impact Management Plan
Source of Impact
Impacted Environmental Components and Arising Impacts
Environmental Management Parameter
Objective of Environmental Management
Environmental Impact Management Plan Environmental
Management Site Environmental
Management Period
Executor, Supervisor and Environmental Management
Reporting
CONSTRUCTION PHASE
Reclamation material on-land transportation
Physical-Chemical Components
Decreased air quality (increasing dust in the air))
Parameter of dust referring to Regulation of East Java Province Government, Number 10 Year 2009 about Ambient Air Quality
Minimizing dust arousal to the air due to reclamation material transportation
Requiring the material transportation contractors to limit the truck speed for 20 km/hr in the access to the project site
Requiring the material transportation contractors to limit to water the soil roads in the access to the project site passed by the trucks in case the transportation activities take place in dry season. The watering is to be on daily basis.
Providing water pool with 4 m width, 10 m length and 50 cm depth. The pool is located in the exit to be accessed by transportation trucks before leaving the the site.
Requiring the material transportation contractors to prepare SOP for their transportation trucks, requiring that:
The trucks wheels are always free of material remains generating dust when spilled
The trucks are provided with canvas to prevent material spill or loss
Reforestating by planting trees
Soil access road to project site
Soil access road to project site
In project site
In material mobilization location in the studied area
Soil access road to project site g
During reclamation material transportation
Watering on daily basis during
Reclamation material transportation, especially when the activities take place in dry season
During reclamation material transportation when the activities take place in wet season
During reclamation material transportation for constructing causeway and interchange area
During construction activities until operation of multipurpose terminal
-Executor: a. PT. Pelabuhan Indonesia III -Supervisor : a. East Java Province Environmental Agency b. Surabaya City Environmental Agency -Reporting : a. Ministry of Environment b. East Java Province Environmental Agency
c. Surabaya City Environmental Agency
Reclamation material on-land transportation
Physical-Chemical Components
Increased Noise Noise degree in Industrial Estate (70 dB.A)
Dwelling and settlement areas ( 55 dB.A) in accordance to Noise Standards set forth in Decision of Minister of Environment Nr. 48/MENLH/II/1996.
Minimizing the increase of noise due to reclamation material on-land transportation for constructing causeway and interchange area.
Requiring the material transportation contractors to prepare SOP for their transportation truck
In material mobilization location in the studied area
During reclamation material transportation for constructing causeway and interchange area
-Executor: a. PT. Pelabuhan Indonesia III -Supervisor : a. East Java Province Environmental Agency b. Surabaya City Environmental Agency -Reporting : a. Ministry of Environment b. East Java Province Environmental Agency
c. Surabaya City Environmental Agency
PT PELABUHAN INDONESIA III (PERSERO) CHAPTER 6 – ENVIRONMENTAL IMPACT MANAGEMENT PLAN
VI - 9 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Source of Impact
Impacted Environmental Components and Arising Impacts
Environmental Management Parameter
Objective of Environmental Management
Environmental Impact Management Plan Environmental
Management Site Environmental
Management Period
Executor, Supervisor and Environmental Management
Reporting
Demolition of erected temporary access
Physical-Chemical Components
Decreased seawater quality
Referring to Decision of Minister of Environment Nr.51/2004 about Seawater Quality Standard for Port Pool
Minimizing degree of turbidity due to temporary access demolition
Localizing the impacts by means of turbidity spread preventor, such as Environmental bucket, or sediment resistant screen surrounding the dredging
Figure: Example of sediment localization instrument
Location of erected temporary access demolition
During demolition of erected temporary access
-Executor: a. PT. Pelabuhan Indonesia III -Supervisor : a. East Java Province Environmental Agency b. Surabaya City Environmental Agency -Reporting : a. Ministry of Environment b. East Java Province Environmental Agency
c. Surabaya City Environmental Agency
Reclamation material on-land transportation
Physical-Chemical Components
Decreased road performance
Degree Saturation< 0,8.
Minimizing decreased road performance
Scheduling reclamation material transportation out of peak time (06.00-08.00) and delivery schedules to prevent short and coincident deliveries
Providing sticker in reclamation material transporting trucks to ease monitoring and give warnings in case of incosistency with schedule or method of transportation
Posting special officers to regulate truck mobility on the access road
Installing traffic signs signaling the project activities and yellow flashing beacon in front of the access road
Jalan Raya Tambak Osowilangon
Margomulyo Crossroad
Romokalisari Crossroad
During reclamation material transportation for area preparation and compaction for constructing causeway and interchange area.
- Initiator : a. PT. Pelabuhan Indonesia III -Supervisor : a. East Java Province Public Works Service b. National Highway Center (BBPJN) V and Surabaya City Publioc Works Service c. Surabaya City Communication Service -Reporting : a. Ministry of Environment b. East Java Province Environmental Agency
c. Surabaya City Environmental Agency
Demolition of erected temporary access
Biological Components
Disturbance to sea biota
Diversity index and domination of plankton/nekton and abundance of nekton.
Minimizing decrease of quality of water as plankton/nekton habitat and feeding area and spawning ground of sea biota
Following the management of impact on decreased seawater quality in the construction phase
Location of erected temporary access demolition
During demolition of erected temporary access
-Executor: a. PT. Pelabuhan Indonesia III -Supervisor : a. East Java Province Environmental Agency b. Surabaya City Environmental Agency -Reporting : a. Ministry of Environment b. East Java Province Environmental Agency
c. Surabaya City Environmental Agency
PT PELABUHAN INDONESIA III (PERSERO) CHAPTER 6 – ENVIRONMENTAL IMPACT MANAGEMENT PLAN
VI - 10 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Source of Impact
Impacted Environmental Components and Arising Impacts
Environmental Management Parameter
Objective of Environmental Management
Environmental Impact Management Plan Environmental
Management Site Environmental
Management Period
Executor, Supervisor and Environmental Management
Reporting
Demolition of erected temporary access
Biological components
Decreased Mangrove Ecosystem Area
Percentage (%) of mangrove coverage
Minimizing mangrove area conversion
Keeping sea border > 100 m to preserve mangrove area as habitat, feeding ground, spawning ground of sea biota and avifauna/water birds
Planting mangrove (the same to original species by considering high tide and low tide condition). Seed with 4-6 leaves Reforestation area 50 m to the sea and 100 m
= 5.000 m2 or 0,5 Ha (Criteria : very dense and good is 2.000 per Ha) . Therefore requiring 0,5 x 2.000 seeds = 1000 seeds. As the survival rate of the planted seed is not 100% the compensation number will be 1.600 seed. The planting is along the coastline of the location of erected temporary access demolition. Caring the planted mangrove seeds for 6
months, when needed replacing seedlings. Enriching family by using the same genus with
different species.
In coastal area around the location of temporary access demolition
After demolition of erected temporary access
-Executor: a. PT. Pelabuhan Indonesia III -Supervisor : a. East Java Province Environmental Agency b. Surabaya City Environmental Agency -Reporting : a. Ministry of Environment b. East Java Province Environmental Agency
c. Surabaya City Environmental Agency
Demolition of erected temporary access
Siocio-economic and cultural components
Disturbance to Fisherman Activities
Disturbance to Fisherman Activities
Minimizing losses to fishermen due to demilition of erected temporary access
Proving special routes for sishermen sailing to deep sea
Giving componsation relevant to the impacts to the fishermen and disturbance to fishermen activities
Mapping socio-economic and cultural impacts to prepare plans for managing the impacts due to the port construction activities as basis to Comdev/CSR activities surrounding the port area.
Empowering fisherman community through CSR activity programs iun accordance to their skills
Area surrounding the port, namely: • Asemrowo Sub-district : Tambak Langon Vill. and Greges Vill.
• Krembangan Sub-dist. : Morokrembangan Village
• Benowo Sub-dist : Tambak Osowilangon Vill. and Romokalisari Vill.
During demolition of erected temporary access
-Executor: a. PT. Pelabuhan Indonesia III -Supervisor : a. East Java Province Environmental Agency b. Surabaya City Environmental Agency -Reporting : a. Ministry of Environment b. East Java Province Environmental Agency
c. Surabaya City Environmental Agency
Port Construction (Preparation and compaction of area for constructing causeway, interchange area, container yard and trestle)
Physical-chemical components
Decreased seawater quality
Referring to Decision of Minister of Environment Nr.51/2004 about Seawater Quality Standard for Port Pool
Minimizing degree of turbidity due to port construction activities
Activities of reclamation material transportation for area preparation and compaction for constructing causeway and interchange area And container yard by :
Scheduling the reclamation activities gradually by considering the climatic condition (rainy)
Providing drainage for draining rainwater in the reclamation area provided with sedimentation pool for minimizing TSS before flowing to the sea
Location of area preparation and compaction of area for constructing causeway, interchange area, container yard and trestle
During preparation and compaction of area for constructing causeway, interchange area, container yard and trestle
-Executor: a. PT. Pelabuhan Indonesia III -Supervisor : a. East Java Province Environmental Agency b. Surabaya City Environmental Agency -Reporting : a. Ministry of Environment b. East Java Province Environmental Agency
c. Surabaya City Environmental Agency
PT PELABUHAN INDONESIA III (PERSERO) CHAPTER 6 – ENVIRONMENTAL IMPACT MANAGEMENT PLAN
VI - 11 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Source of Impact
Impacted Environmental Components and Arising Impacts
Environmental Management Parameter
Objective of Environmental Management
Environmental Impact Management Plan Environmental
Management Site Environmental
Management Period
Executor, Supervisor and Environmental Management
Reporting
Port Construction (Preparation and compaction of area for constructing causeway, interchange area, container yard and trestle)
Physical-chemical components
Change of seawater current pattern and simultaneusly derining impact on change of sedimentation pattern
Change of coastline
Sedimentation and abrasion.
Managing impact on changes of water current patter to minimize abrasion and sedimentation.
Periodically dredging the area of estuary of Lamong River and coordinating with Bengawan Solo River Management Center
Sea waters, especially in Lamong River.
When the elevation of estuary bed increases minimally by 50 cm.
-Executor: a. PT. Pelabuhan Indonesia III in collaboration with Bengawan Solo River Management Center -Supervisor : a. East Java Province Environmental Agency b. Surabaya City Environmental Agency c. Surabaya City Public Works and Drainage Service -Reporting : a. Ministry of Environment b. East Java Province Environmental Agency
c. Surabaya City Environmental Agency
Port Construction (Preparation and compaction of area for constructing causeway, interchange area, container yard and trestle)
Physical-chemical components
Increased surface of river runoff
Gerring higher and father effect of back water
Controlling the surface of river runoff and minimizing the effect of back water
Following the management of impact on change of water current pattern and sedimentation Supplying information to Bengawan Solo River
Management Center for planning flood control in Lamong River and addressing that the project activities will lead to increase of water surface when flooded in annual recurrent period due to the effect of back water to river management authority
Eastuary of Lamong River
During area preparation and compaction for constructing causeway, interchange area, container yard and trestle until operation phase.
- Executor: a. PT. Pelabuhan Indonesia III in collaboration with Bengawan Solo River Management Center -Supervisor : a.East Java Province Public Works and Water Service b. Bengawan Solo River Management Center c. East Java Province Environmental Agency d. Surabaya City Environmental Agency - Reporting : a. Ministry of Environment b. East Java Province Environmental Agency
c. Surabaya City Environmental Agency
Port Construction (Preparation and compaction of area for constructing causeway, interchange area, container yard and
Biological Components
Disturbance to sea biota
Diversity Index and domination of plankton/nekton and abundance of nekton.
Minimizing decrease of quality of water as plankton/nekton habitat and feeding area and spawning ground of sea biota
Following the management of impact on decreased seawater quality in construction phase
Location of area preparation and compaction for constructing causeway, interchange area, container yard and trestle
During area preparation and compaction for constructing causeway, interchange area, container yard and trestle
-Executor: a. PT. Pelabuhan Indonesia III -Supervisor : a. East Java Province Environmental Agency b. Surabaya City Environmental Agency
PT PELABUHAN INDONESIA III (PERSERO) CHAPTER 6 – ENVIRONMENTAL IMPACT MANAGEMENT PLAN
VI - 12 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Source of Impact
Impacted Environmental Components and Arising Impacts
Environmental Management Parameter
Objective of Environmental Management
Environmental Impact Management Plan Environmental
Management Site Environmental
Management Period
Executor, Supervisor and Environmental Management
Reporting
trestle) -Reporting : a. Ministry of Environment b. East Java Province Environmental Agency
c. Surabaya City Environmental Agency
Port Construction (Preparation and compaction of area for constructing causeway, interchange area, container yard and trestle)
Socio-Economic and Cultural Components
Disturbance to Fisherman activities
Disturbance to Fisherman activities affecting change on fisherman income
Minimizing loss to fishermen due to preparation and compaction of area for constructing causeway, interchange area, container yard and trestle
Proving special routes for sishermen sailing to deep sea
Giving componsation relevant to the impacts to the fishermen and disturbance to fishermen activities
Mapping socio-economic and cultural imoacts to prepare plans for managing the impacts due to the port construction activities as basis to Comdev/CSR activities surrounding the port area.
Empowering fisherman community through CSR activity programs iun accordance to their skills
Area surrounding the port, namely: • Asemrowo Sub-district : Tambak Langon Vill. and Greges Vill.
• Krembangan Sub-dist. : Morokrembangan Village
• Benowo Sub-dist : Tambak Osowilangon Vill. and Romokalisari Vill.
During area preparation and compaction for constructing causeway, interchange area, container yard and trestle
-Executor: a. PT. Pelabuhan Indonesia III -Supervisor : a. East Java Province Environmental Agency b. Surabaya City Environmental Agency -Reporting : a. Ministry of Environment b. East Java Province Environmental Agency
c. Surabaya City Environmental Agency
Pengerukan Rencana Kolam Pelabuhan
Physical-Chemical Components
Decreased seawater quality
Referring to Decision of Minister of Environment Nr.51/2004 about Seawater Quality Standard for Port Pool
Minimizing degree of turbidity due to port dredging
Utilizing high capacity dredger to shorten dredging time
Shortening dredging period to reduce dredging time to minimize the time of mixing between water and dredged materials during overflow.
Minimizing dredging water overflow.
Localizing the impacts by means of turbidity spread preventor, such as Environmental bucket, or sediment resistant screen surrounding the dredging
Figure: Example of sediment localization instrument
Location of planned port pool dredging.
During planned port pool dredging
-Executor: a. PT. Pelabuhan Indonesia III -Supervisor : a. East Java Province Environmental Agency b. Surabaya City Environmental Agency -Reporting : a. Ministry of Environment b. East Java Province Environmental Agency
c. Surabaya City Environmental Agency
PT PELABUHAN INDONESIA III (PERSERO) CHAPTER 6 – ENVIRONMENTAL IMPACT MANAGEMENT PLAN
VI - 13 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Source of Impact
Impacted Environmental Components and Arising Impacts
Environmental Management Parameter
Objective of Environmental Management
Environmental Impact Management Plan Environmental
Management Site Environmental
Management Period
Executor, Supervisor and Environmental Management
Reporting
Dredging of planned port pool
Biological Components
Disturbance to sea biota
Diversity Index and domination of plankton/nekton and abundance of nekton.
Minimizing decrease of quality of water as plankton/nekton habitat and feeding area and spawning ground of sea biota
Following the management of impact on decreased seawater quality in construction phase
Location of planned port pool dredging.
During planned port pool dredging
-Executor: a. PT. Pelabuhan Indonesia III -Supervisor : a. East Java Province Environmental Agency b. Surabaya City Environmental Agency -Reporting : a. Ministry of Environment b. East Java Province Environmental Agency
c. Surabaya City Environmental Agency
Dredging of planned port pool
Socio-Economic and Cultural Components
Disturbance to Fisherman activities
Disturbance to Fisherman activities affecting change on fisherman income
Minimizing loss to fishermen due to activities of dredging of planned port pool
Proving special routes for sishermen sailing to deep sea
Giving componsation relevant to the impacts to the fishermen and disturbance to fishermen activities
Mapping socio-economic and cultural imoacts to prepare plans for managing the impacts due to the port construction activities as basis to Comdev/CSR activities surrounding the port area.
Empowering fisherman community through CSR activity programs iun accordance to their skills
Area surrounding the port, namely: • Asemrowo Sub-district : Tambak Langon Vill. and Greges Vill.
• Krembangan Sub-dist. : Morokrembangan Village
• Benowo Sub-dist : Tambak Osowilangon Vill. and Romokalisari Vill.
During planned port pool dredging
-Executor: a. PT. Pelabuhan Indonesia III -Supervisor : a. East Java Province Environmental Agency b. Surabaya City Environmental Agency -Reporting : a. Ministry of Environment b. East Java Province Environmental Agency
c. Surabaya City Environmental Agency
OPERATION PHASE
Multipurpose Pier Operation
Physical-Chemical Components
Decreased seawater quality
Referring to Decision of Minister of Environment Nr.51/2004 about Seawater Quality Standard for Port Pool
Minimizing the impact on seawater quality
Consistently exercising dry bulk loading and unloading procedures and assigning superviors
Modifying ship unloader by means of close system transfer from ship to hopper to prevent oil spills into the waters
Construction and maintenance of drainage and oil catcher.
Watertight loading and unloading floors completed with duct to storage pool provided with oil catcher.
Preventing oily materials or bulk material spill into drainage
Ordering workers to dump waste and sanitation properly
Ordering vessel operator to minimize dumping contamination by installing oil catcher , fixing leakage, separating water/oil in the ballast water drain pump
Area of Multipurpose terminal and its facilities
During operation of Multipurpose terminal.
-Executor: a. PT. Pelabuhan Indonesia III -Supervisor : a. East Java Province Environmental Agency b. Surabaya City Environmental Agency -Reporting : a. Ministry of Environment b. East Java Province Environmental Agency
c. Surabaya City Environmental Agency
PT PELABUHAN INDONESIA III (PERSERO) CHAPTER 6 – ENVIRONMENTAL IMPACT MANAGEMENT PLAN
VI - 14 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Source of Impact
Impacted Environmental Components and Arising Impacts
Environmental Management Parameter
Objective of Environmental Management
Environmental Impact Management Plan Environmental
Management Site Environmental
Management Period
Executor, Supervisor and Environmental Management
Reporting
Multipurpose Pier Operation
Physical-Chemical Components
Decreased roadperformance
Impact paramer
DS< 0,8
Minimizing decreased road performance
Scheduling reclamation material transportation out of peak time (06.00-08.00)
Posting special officers to regulate truck mobility on the access road
Installing traffic signs signaling the project activities and yellow flashing beacon in front of the access road
Providing clear SOP for operators of incoming and outgoing Multipurpose Terminal, so that the drivers respect traffic signs and regulation, otherwise they will be sanctioned. Cooperating with Bina Marga Public Works
Service to widen Jalan Tambak Osowilangon and accesses in Romokalisari Crossroad to and from Jalan Tambak Osowilangon and providing median for heavy trucks and light vehicles in order to minimize traffic accidents and traffic jam.
Figure : Romokalisari Crossroad Cooperating with Public Works Department
and Toll Road Operating Agency to construct fly over connecting the Multipurpose Terminal in Lamong Bay to both existing and new toll roads to directly exit from Surabaya City territory.
Coordinating with Bina Marga East Java Province Public Works service concerning with the exit and entry accesses that cross arterial roads
Jalan Raya Tambak Osowilangon
Margomulyo Crossroad
Romokalisari Crossroad
Crossroad between access road and jalan Raya Tambak Osowilangon,
During operation of Multipurpose Terminal
-Executor: a. PT. Pelabuhan Indonesia III -Supervisor : a. East Java Province Public Works Service b. East Java Province Environmental Agency c. Surabaya City Environmental Agency -Reporting : a. Ministry of Environment b. East Java Province Environmental Agency
c. Surabaya City Environmental Agency
Derived Impact from Impact on Decreased seawater Quality due to pier operation
Biological Component
Disturbance to sea biota
Diversity Index and domination of plankton/ nekton and abundance of nekton.
Minimizing decrease of quality of water as plankton/ nekton habitat and feeding
Consistently exercising dry bulk loading and unloading procedures and assigning superviors
Modifying ship unloader by means of close system transfer from ship to hopper to prevent oil spills into the waters
Construction and maintenance of drainage and oil catcher.
Environmental management site in the port
During the operation of the port.
-Executor: a. PT. Pelabuhan Indonesia III -Supervisor : a. East Java Province Environmental Agency b. Surabaya City Environmental Agency
PT PELABUHAN INDONESIA III (PERSERO) CHAPTER 6 – ENVIRONMENTAL IMPACT MANAGEMENT PLAN
VI - 15 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Source of Impact
Impacted Environmental Components and Arising Impacts
Environmental Management Parameter
Objective of Environmental Management
Environmental Impact Management Plan Environmental
Management Site Environmental
Management Period
Executor, Supervisor and Environmental Management
Reporting
area and spawning ground of sea biota
Watertight loading and unloading floors completed with duct to storage pool provided with oil catcher.
Ordering workers to dump waste and sanitation properly
Ordering vessel operator to minimize dumping contamination by installing oil catcher , fixing leakage, separating water/oil in the ballast water drain pump
-Reporting : a. Ministry of Environment b. East Java Province Environmental Agency
c. Surabaya City Environmental Agency
Operation of Multipurpose Pier
Biological Component
Decreased Mangrove Ecosystem Area
Prosentage (%) of Mangrove coverage
Minimizing mangrove area conversion. Revegetating Mangrove in conserved area (Galang Island). Keeping sea border > 100 m to preserve mangrove area as habitat, feeding ground, spawning ground of sea biota and avifauna/water birds
Monitoring the impact on decreased seawater quality during operation phase
Planting mangrove (the same to original species by considering high tide and low tide condition). Seed with 4-6 leaves Reforestation area 50 m to the sea and 600 m
= 30.000 m2 or 3 Ha (Criteria : very dense and good is 2.000 per Ha) . Therefore requiring 3 x 2.000 seeds = 6000 seeds. As the survival rate of the planted seed is not 100% the compensation number will be 10,000 seed. The planting is along the coastline between Lamong River and Sememi River. Caring the planted mangrove seeds for 6
months, when needed replacing seedlings. Enriching family by using the same genus with
different species.
Galang Island, Estuary of Sememi River
Estuary of Branjangan River
Along the coast surrounding the project site
During port operation.
-Executor: a. PT. Pelabuhan Indonesia III -Supervisor : a. East Java Province Environmental Agency b. Surabaya City Environmental Agency -Reporting : a. Ministry of Environment b. East Java Province Environmental Agency
c. Surabaya City Environmental Agency
Operation of Multipurpose Pier
Socio-Economic and Cultural Component
Disturbance to Fisherman Activity
Less number of fishermen going fishing
Less number of caught fish and decreased fisherman income
Minimizing losses to fishermen due to mutipurpose pier operation
Mapping socio-economic and cultural imoacts to prepare plans for managing the impacts due to the multipurpose terminal operation activities as basis to Comdev/CSR activities surrounding the terminal area.
Empowering fisherman community through CSR activity programs iun accordance to their skills
Cooperating with Surabaya City Government or Fishery and Marine Service to empower the fisherman community changing profession by building soft skills or training on modern echnoly in deep sea fish catching. (as part of CSR Program)
Area surrounding the port, namely: • Asemrowo Sub-district : Tambak Langon Vill. and Greges Vill.
• Krembangan Sub-dist. : Morokrembangan Village
• Benowo Sub-dist : Tambak Osowilangon Vill. and Romokalisari Vill.
During Multipurpose pier operation
-Executor: a. PT. Pelabuhan Indonesia III -Supervisor : a. East Java Province Environmental Agency b. Surabaya City Environmental Agency -Reporting : a. Ministry of Environment b. East Java Province Environmental Agency
c. Surabaya City Environmental Agency
Socio-Economic and Cultural Component
Community Unrest
Demo, protest and statement by community that can disturb the operation of Multipurpose
Eliminating negative perception to the MultipurposeTerminal operation and anticipating
Social mapping and designing Comdev/CSR programs in accordance with the community needs by involving the community
Designing special CSR program for those directly impacted (fishermen) by involving the community in the program
Opening dialogue with the impacted community (fishermen), especially the ones
Area surrounding the multipurpose terminal, namely: • Asemrowo Sub-district : Tambak Langon Vill. and Greges Vill.
During Multipurpose terminal operation
-Executor: a. PT. Pelabuhan Indonesia III -Supervisor : a. East Java Province Environmental Agency b. Surabaya City Environmental Agency
PT PELABUHAN INDONESIA III (PERSERO) CHAPTER 6 – ENVIRONMENTAL IMPACT MANAGEMENT PLAN
VI - 16 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Source of Impact
Impacted Environmental Components and Arising Impacts
Environmental Management Parameter
Objective of Environmental Management
Environmental Impact Management Plan Environmental
Management Site Environmental
Management Period
Executor, Supervisor and Environmental Management
Reporting
terminal Demo, protest and statement by community that can disturb the operation of Multipurpose terminal
from areas of Tambak Osowilangun, Romokalisari, Greges, etc. to find best solutions in accordance with the needs and skills of the fishermen and accountability of PT Pelindo III
The examples of adoptable CSR programs are : Training provisions : Skill training on
modern fish catching technology, scholarship for fishermen‟s children, soft skills training for fishermen‟s children (English Language, computer, book keeping etc.), free medical service for fishermen , infrastructure construction for fishermen, divinity programs, youth organization programs, (sport and soft skill facilities)
Environment : Planting Mangrove and alike, Reforestration in dwelling area, training on waste treatment and rubbish handling.
• Krembangan Sub-dist. : Morokrembangan Village
• Benowo Sub-dist : Tambak Osowilangon Vill. and Romokalisari Vill.
-Reporting : a. Ministry of Environment b. East Java Province Environmental Agency
c. Surabaya City Environmental Agency
Multipurpose Terminal Operation
Socio-Economic and Cultural Component
Job and Business Opportunities
Number of local people hired in the operation of the Multipurpose
Terminal
Number of local people having chance to open business during the Operation of Multipurpose Terminal
Local people have greater business opportunities and consequently it will eliminate conflicts in the community due to migrant workers.
Prioritizing local people hiring in area surrounding the operated multipurpose terminal
Openly announcing job openings for supporting the operation activities through village officers and advising the required qualifications
Providing advocacy with village administrators about labor recruitement procedures
Transparent recruitmnent process and announcing the results of selectioon via village offices.
Area surrounding the multipurpose terminal, namely: • Asemrowo Sub-district : Tambak Langon Vill. and Greges Vill.
• Krembangan Sub-dist. : Morokrembangan Village
• Benowo Sub-dist : Tambak Osowilangon Vill. and Romokalisari Vill.
During Multipurpose terminal operation
-Executor: a. PT. Pelabuhan Indonesia III -Supervisor : a. East Java Province Environmental Agency b. Surabaya City Environmental Agency -Reporting : a. Ministry of Environment b. East Java Province Environmental Agency
c. Surabaya City Environmental Agency
PT PELABUHAN INDONESIA III (PERSERO) CHAPTER 6 – ENVIRONMENTAL IMPACT MANAGEMENT PLAN
VI - 17 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Page : VI -17
Figure 6.1 Environmental Management Site
Source: DIGITAL INDONESIAN MAP YEAR 1999 (LAND USE) and RESULT OF BATHYMETRY MEASUREMENT IN LAMONG RIVER ESTUARY YEAR 2008
1 0 1 2km SCALE
U
TA R
A
14’30”
14
’00”
9200
13’30”
13
’00”
12
’30”
12
’00”
11
’30”
11
’00”
9205
10’30”
10
’00”
09
’30”
09
’00”
08
’30”
9210
08’00”
06
9326
7 m
T
44’00” 44’30” 9198242 mU 9198293 mU 38’00” 38’30”
0680
Balongsari 3,5 km
39’00” 39’30” 40’00” 40’30”
0685
Balongsari 1 km
41’00” 41’30” 42’00” 42’30” 43’00”
0690
43’30” 06
9321
4 mT
Project Site Border Temporari Access Site
Management Site of Air Quality and Noise Dan kebisingan Management Site of Seawater
Quality and Biology Management Site of Road Performance
Management Site of Decreased Mangrove Ecosystem Area
Management Site of Change of Water Current Patterns and Increased Surface of river runoff
PT PELABUHAN INDONESIA III (PERSERO) CHAPTER 7 – ENVIRONMENTAL IMPACT OBSERVATION PLAN
VII - 1 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
CHAPTER 7 ENVIRONMENTAL IMPACT OBSERVATION PLAN
Referring to the results of reviews in the previous chapters, it is
predicted that Tanjung Perak Port Development in Lamong Bay will significantly
bring both positive and negative impacts to the suttounding environment. The
significant impacts predicted to emerge during the construction phase will be
decreased air quality, increased noise, decreased seawater quality, increased
surface of river runoff, change of water current patterns and sedimentation,
decreased road performance, disturbance to sea biota, decreased mangrove
area, disturbance to fisherman activities and community unrest. In the
operation phase, it is predicted that it will bring impacts to decreased
seawater quality, decreased road performance, disturbance to sea biota,
decreased mangrove area, job and business opportunities, disturbance to
fisherman activities and community unrest. Accordingly, it is necessary to
prepare an Environmental Impact Observation Plan as a support to the available
environmental study documents.
7.1. OBJECTIVES OF ENVIRONMENTAL IMPACT OBSERVATION
The objectives of the Environmental Impact Observation Plan are to :
Provide a guide to the implementation of Environmental Impact
Observation Plan concerning :
- Observed significant impacts
- Objectives of observation
- Observed parameter and observation points
- Observation period
- Observer
Observe the quality/quantity of environment in accordance with the
set parameters.
PT PELABUHAN INDONESIA III (PERSERO) CHAPTER 7 – ENVIRONMENTAL IMPACT OBSERVATION PLAN
VII - 2 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Identify degree of handling, trend and criticality of the impacts to
the environment.
7.2. BENEFITS OF ENVIRONMENTAL IMPACT OBSERVATION
The environmental impact observation plan will be beneficial to :
A. Project Initiator
1. As a guide and direction to the activity of the initiator in
attempts to implement the environmental impact observation
plan in the project site and its surrounding, in both construction
phase and operation one.
2. As earlier dectections to possible change of environmental
quality.
3. As a media to present eco-friendly development and preserve the
environmental supports.
4. Sebagai sarana umpan balik dalam memperbaiki kegiatan
pengelolaan lingkungan yang sudah dilakukan.
B. Government
1. As an early detection to decreased ambient air quality and
decreased seawater quality in coastal area valuable when passing
environmental policies on spatial planning in accordance to the
initial environmentlal description and existing development state
of conditions.
2. As a support to warrant that the development activities will bring
benefits to the community.
3. As an early detection to potential conflicts that may arise
sepecifically with the community and/or other projects.
4. As a basis for decision making.
PT PELABUHAN INDONESIA III (PERSERO) CHAPTER 7 – ENVIRONMENTAL IMPACT OBSERVATION PLAN
VII - 3 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
C. Community
1. To identify the changes in environmental quality during the
construction phase and take favorable opportunities for them
and prevent possible losses and damages arising from the
project.
2. To be better exposed to Tanjung Perak Port Development
activities in Lamong Bay in order to preven misunderstanding and
stimulate mutually beneficial cooperation.
3. To understand the rights and obligations in relation with the
existence of Tanjung Perak Port Development in Lamong Bay.
7.3. ENVIRONMENTAL IMPACT OBSERVATION
The environmental impact observation plan is presented in Table 7.1.,
while the observation points are presented in Figure 7.1.
PT PELABUHAN INDONESIA III (PERSERO) CHAPTER 7 – ENVIRONMENTAL IMPACT OBSERVATION PLAN
VII - 4 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Table 7.1. Matrix of Environmental Impact Observation Plan
Nr. Project Phases as Sources of Impacts
Observed Impacts
Observation Objectives
Environmental Observation Method Environmental Observation Institutions
Descriptions of Arising Impacts
Impacted Environmental Components
Indicator/ Parameter
Method of Data Collection and Analysis Observation Points
Time and Frequency
Executor Supervisor Report Receiver
CONSTRUCTION PHASE
1. Reclamation material onland transportation
Arising dust leading to decreased ambient air quality around the locations accessed by trucks tranporting the material to project site
Physical-Chemical Components: Ambient air quality.
Dust particulate stated the the Regulation of Governor East Java Province Nr. 10 Year 2009 and Indonesian State Regulation Nr. 41 Year 1999 aboutAmbient Air Quality
Indentifying the ambient air quality especially in terms of dust and environmental impact management efectiveness
Measuring dust contents in location surrounding the location of material mobilization and project site and the nesrest dwelling area. Air samples are collected by means of gas sampler to be further analyszed in laboratory.
The results of dust measurement are analyzed in the laboratory and compared to the quality standards.
Monitoring the watering of soil access road to project site on daily basis
1 : Area of Kalianak Surabaya Junction (S : 07o13.774‟ E : 112o40.952‟)
2 : Area in front of Port Dev. Project Site (S : 07o12.931‟ E : 112o39.231‟)
3 : Area surrounding Romokalisari (After bridge) (S : 07o11.782‟ E : 112o38.724‟)
4 : Area of Project Site (Close to Coast) (S : 07o12.646‟ E : 112o39.676‟)
Soil access road to project site
Once in construction phase , during material and equipment mobilization
Every day during construction phase
PT Pelabuhan Indonesia III
- East Java Province Environmental Agency - Surabaya City Environmental Agency
- Ministry of Environment - East Java Province Environmental Agency - Surabaya City Environmental Agency
2. Reclamation material onland transportation
Degree of noise in due to mobilization of trucks tranporting reclamation material to the project site
Physical-Chemical Components: Degree of noise
Degree of noise
Indentifying the degree of noise and environmental impact management efectiveness
Conducting direct measurement in the field by means of sound level meter for 10 minutes for each measurement.The measurement will be for 24 hours to get representative continuous noise. Each measurement is foe a certain period of time, minimally with 4 periods of measurement time in the day and (Ls= period of 06.00 -22.00) and minimallywith 3 periods of measurement time at night (Lm = period of
22.00 – 06.00).
Data Analysis Method
LS:Degree of continuous noise during the day calculated with the equation below :
LM: Degree of continuous noise during the night calculated with the equation below:
LSM : Degree of continuous noise during the day and night calculated with the equation below:
Next, the value of LSM is compared to the Noise Standards as set forth in the Decision of Minister of Environment Nr. KEP-48/MENLH/11/1996 in accordance with specific areas.
1 : Area of Kalianak Surabaya Junction (S : 07o13.774‟ E : 112o40.952‟)
2 : Area in front of Port Dev. Project Site (S : 07o12.931‟ E : 112o39.231‟)
3 : Area surrounding Romokalisari (After bridge) (S : 07o11.782‟ E : 112o38.724‟)
4 : Area of Project Site (Close to Coast) (S : 07o12.646‟ E : 112o39.676‟)
Once in construction phase , during material and equipment mobilization
PT Pelabuhan Indonesia III
- East Java Province Environmental Agency - Surabaya City Environmental Agency
- Ministry of Environment - East Java Province Environmental Agency - Surabaya City Environmental Agency
dBATT LL 4.1,01.1,0 10.4...10.116
1log10
dBATT LL 7.1,05.1,0 10.4...10.18
1log10
dBALMLS )5.(1,0.1,0 10.810.1624
1log10
PT PELABUHAN INDONESIA III (PERSERO) CHAPTER 7 – ENVIRONMENTAL IMPACT OBSERVATION PLAN
VII - 5 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Nr. Project Phases as Sources of Impacts
Observed Impacts
Observation Objectives
Environmental Observation Method Environmental Observation Institutions
Descriptions of Arising Impacts
Impacted Environmental Components
Indicator/ Parameter
Method of Data Collection and Analysis Observation Points
Time and Frequency
Executor Supervisor Report Receiver
3. Reclamation material onland transportation
Decreased road performance
Physical-chemical components : Trans-portation sub-component, especially decreased road performence
Traffic jam on Jl. Raya Tambak Osowilangon, The observed parameter is Degree of Saturation or comparison between traffic volume and road capacity
Identifying Degree of Saturation and environmental impact management effectiveness
Direct observation and traffic counting for 12 hours 06.00 a.m. - 18.00.
Jl. Raya Tambak Osowilangon
Once a week during construction phase
PT Pelabuhan Indonesia III
- East Java Province Environmental Agency - Surabaya City Environmental Agency
- Ministry of Environment - East Java Province Environmental Agency - Surabaya City Environmental Agency
4. Demolition of erected temporary access
Seawater quality after mixed with soil/sand spills affecting total suspended solid (TSS)
Physical-chemical components : Seawater quality
Seawater quality after mixed with soil/sand spills affecting total suspended solid (TSS) referring to Decision of Minister of Environment Nr.51/2004 about Seawater Quality Standard for Port Pool
Observing the changes in seawater qauality due to the construction acrtivities and the planned management programs to identify the environmental impact management effectiveness and trend of change in environmental quality
Seawater random sampling in 5 observation points and laboratory analysis. Sample testing on total suspended solid in laboratory. Total seawater samples : 5, from impacted areas, i.e. :
2 points in the sea waters in the interchange area
2 points around the container terminal
1 point in pier area
Inventorying of environmental impact management implementation on decreased seawater quality and evaluation to the environmental impact management implementation as planned in EIM documents
The results of laboratory test, especially concerning total suspended solid (TSS) are compared to the standards set forth in Decision of Minister of Environment Nr.51/2004 about Seawater Quality Standard for Port Pool
Area of Multipurpose Terminal
Monthly during construction phase
PT Pelabuhan Indonesia III
- East Java Province Environmental Agency - Surabaya City Environmental Agency
- Ministry of Environment - East Java Province Environmental Agency - Surabaya City Environmental Agency
5. Demolition of erected temporary access
Disturbance to Sea Biota
Biological components: composistion, abundance and species of sea biota, especially benthos/nekton
Diversity index and dominant benthos and nekton abundance
Observing water quality/productivity and planned environmental impact management effectiveness and trend of change in environmental quality
Sea biota sampling (benthos/nekton) and inventorying fishery productivity
Inventorying environmental management data to be further evaluated
5 observation points in water area in the area of Multipurpose Terminal in Lamong Bay in accordance with baseline data
During construction phase (minimally once in each activity: Demolition of erected temporary access)
PT Pelabuhan Indonesia III
- East Java Province Environmental Agency - Surabaya City Environmental Agency
- Ministry of Environment - East Java Province Environmental Agency - Surabaya City Environmental Agency
6. Demolition of erected temporary access
Decreased Mangrove ecosystem area
Biological Components: mangrove ecosystem area
Percentage (%) of mangrove coverageand survival rate of mangrove seeds planted based on tree density (trees per ha) during 1 year
Observing the environmental management performance , whether the revegetation is consistent with EIM documents
Direct field observation.
Inventorying data of implemented environmental management for further evaluation
Coastal area ex-temporary access and its surrounding
During 1 year on monthly basis after the Demolition of erected temporary access
PT Pelabuhan Indonesia III Supported by related institution or the ones appointed by the initiator
- East Java Province Environmental Agency - Surabaya City Environmental Agency
- Ministry of Environment - East Java Province Environmental Agency - Surabaya City Environmental Agency
7. Demolition of erected temporary access
Disturbance to fisherman activities
Socio-economic and cultural component : Resident working as fisherman
Coastal fishermen. Deep sea fishermen to take longer voyage
Identifying change of the activities of fisherman leading to change of fisherman income
Method of Data Collection
Observing and interviewing fishermen
Studying fishermen‟s complaints directly addressed to PT Pelindo.
Area surrounding the multipurpose terminal, namely: • Asemrowo Sub-district : Tambak Langon Vill. and Greges Vill.
• Krembangan Sub-dist. : Morokrembangan Village
Once during construction phase
PT Pelabuhan Indonesia III
- East Java Province Environmental Agency - Surabaya City Environmental Agency
- Ministry of Environment - East Java Province Environmental Agency - Surabaya City Environmental
PT PELABUHAN INDONESIA III (PERSERO) CHAPTER 7 – ENVIRONMENTAL IMPACT OBSERVATION PLAN
VII - 6 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Nr. Project Phases as Sources of Impacts
Observed Impacts
Observation Objectives
Environmental Observation Method Environmental Observation Institutions
Descriptions of Arising Impacts
Impacted Environmental Components
Indicator/ Parameter
Method of Data Collection and Analysis Observation Points
Time and Frequency
Executor Supervisor Report Receiver
Method of Data Analysis
Descriptive analysis to some findings from the collected quantitative data (numbers and table) and qualitative data (narration)
• Benowo Sub-dist : ambak Osowilangon Vill. and Romokalisari Vill.
Agency
8. Port Construction (Preparation and compaction of area for constructing causeway, interchange area, container yard and trestle)
Decreased Seawater quality
Physical-chemical components : Seawater quality
Seawater quality after mixed with soil/sand spills affecting total suspended solid (TSS) referring to Decision of Minister of Environment Nr.51/2004 about Seawater Quality Standard for Port Pool
Observing the changes in seawater qauality due to the construction acrtivities and the planned management programs to identify the environmental impact management effectiveness and trend of change in environmental quality
Seawater random sampling in 5 observation points and laboratory analysis. Sample testing on total suspended solid in laboratory. Total seawater samples : 5, from impacted areas, i.e. :
2 points in the sea waters in the interchange area
2 points around the container terminal
1 point in pier area
Inventorying of environmental impact management implementation on decreased seawater quality and evaluation to the environmental impact management implementation as planned in EIM documents
The results of laboratory test, especially concerning total suspended solid (TSS) are compared to the standards set forth in Decision of Minister of Environment Nr.51/2004 about Seawater Quality Standard for Port Pool
Inventorying environmental management data to be further evaluated
Area of Multipurpose Terminal
Monthly during construction phase
PT Pelabuhan Indonesia III
- East Java Province Environmental Agency - Surabaya City Environmental Agency
- Ministry of Environment - East Java Province Environmental Agency - Surabaya City Environmental Agency
9. Port Construction (Preparation and compaction of area for constructing causeway, interchange area, container yard and trestle)
Change of water current patterns
Physical-chemical components : Change of water current patterns
Increased sedimentation rate
Observing the extent of sedimentation
Field observation to identify the preservation of natural channels
Measuring the bed elevation, especially in the estuary of Lamong River
Measuring on-going sedimentation by sampling sediment from the bed by means of bottom grab and analyzing data by means of Grain Size Analysis to get distribution of of sediment diameters.
Waters area in project site in Lamong Bay and estuary of Lamong River
Once a year for bed elevation measurement, while for other measurement after the bed elevation increases by 50 cm.
PT Pelabuhan Indonesia III
East Java Province Public Works and Water Service
Bengawan Solo River Management Centers
East Java Province Environmental Agency
Surabaya City Environmental Agency
- Ministry of Environment - East Java Province Environmental Agency - Surabaya City Environmental Agency
10. Port Construction (Preparation and compaction of area for constructing causeway, interchange area, container yard and trestle)
Increased surface of river runoff
Physical-chemical components : Increased surface of river runoff
Getting higher and father effect of back water
Assuring that information concerning increased surface of river runoff (Lamong River) is received by Bengawan Solo River Management Center
Field observation to identify the increase of height and extend of impact of the river runoff and inventorying reports on the results of measurement on flood data conducted by Bengawan Solo River Management Center
Waters area in project site in Lamong Bay ad Bengawan Solo River Management Center
Once a year PT Pelabuhan Indonesia III
East Java Province Environmental Agency
Surabaya City Environmental Agency
- Ministry of Environment - East Java Province Environmental Agency - Surabaya City Environmental Agency
PT PELABUHAN INDONESIA III (PERSERO) CHAPTER 7 – ENVIRONMENTAL IMPACT OBSERVATION PLAN
VII - 7 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Nr. Project Phases as Sources of Impacts
Observed Impacts
Observation Objectives
Environmental Observation Method Environmental Observation Institutions
Descriptions of Arising Impacts
Impacted Environmental Components
Indicator/ Parameter
Method of Data Collection and Analysis Observation Points
Time and Frequency
Executor Supervisor Report Receiver
11. Port Construction (Preparation and compaction of area for constructing causeway, interchange area, container yard and trestle)
Disturbance to sea biota
Biological components: composistion, abundance and species of sea biota, especially benthos/nekton
Diversity index and domination of plankton/ nekton and abundance of nekton.
Observing water quality/productivity and planned environmental impact management effectiveness and trend of change in environmental quality
Sea biota (benthos/nekton) sampling dan fishery performance inventorying
Inventorying environmental management data to be further evaluated
5 observation points in water area in the area of Multipurpose Terminal in Lamong Bay in accordance with baseline data
During construction (minimally once) in each activity : demolition of erected temporary access, area preparation and compaction for constructing causeway and container yard, port pool dredging)
PT Pelabuhan Indonesia III
East Java Province Environmental Agency
Surabaya City Environmental Agency
- Ministry of Environment - East Java Province Environmental Agency - Surabaya City Environmental Agency
12. Port Construction (Preparation and compaction of area for constructing causeway, interchange area, container yard and trestle)
Disturbance to fisherman activities
Socio-economic and cultural component : Resident working as fisherman
Coastal fishermen. Deep sea fishermen to take longer voyage
Identifying change of the activities of fisherman leading to change of fisherman income
Method of Data Collection
Observing and interviewing fishermen
Studying fishermen‟s complaints directly addressed to PT Pelindo.
Method of Data Analysis
Descriptive analysis to some findings from the collected quantitative data (numbers and table) and qualitative data (narration)
Area surrounding the multipurpose terminal, namely: • Asemrowo Sub-district : Tambak Langon Vill. and Greges Vill.
• Krembangan Sub-dist. : Morokrembangan Village
• Benowo Sub-dist : ambak Osowilangon Vill. and Romokalisari Vill.
Once during construction phase
PT Pelabuhan Indonesia III
- East Java Province Environmental Agency - Surabaya City Environmental Agency
- Ministry of Environment - East Java Province Environmental Agency - Surabaya City Environmental Agency
13. Planned Port Pool Dredging
Decreased seawater quality
Physical-chemical components : Seawater quality
Seawater quality after mixed with soil/sand spills affecting total suspended solid (TSS) referring to Decision of Minister of Environment Nr.51/2004 about Seawater Quality Standard for Port Pool
Observing the changes in seawater qauality due to the construction acrtivities and the planned management programs to identify the environmental impact management effectiveness and trend of change in environmental quality
Seawater random sampling in 5 observation points and laboratory analysis. Sample testing on total suspended solid in laboratory. Total seawater samples : 5, from impacted areas, i.e. :
2 points in the sea waters in the interchange area
2 points around the container terminal
1 point in pier area
Inventorying of environmental impact management implementation on decreased seawater quality and evaluation to the environmental impact management implementation as planned in EIM documents
The results of laboratory test, especially concerning total suspended solid (TSS) are compared to the standards set forth in Decision of Minister of Environment Nr.51/2004 about Seawater Quality Standard for Port Pool
Inventorying environmental management data to be further evaluated
Area of Multipurpose Terminal
Monthly during construction phase
PT Pelabuhan Indonesia III
- East Java Province Environmental Agency - Surabaya City Environmental Agency
- Ministry of Environment - East Java Province Environmental Agency - Surabaya City Environmental Agency
14. Planned Port Pool Dredging
Disturbance to sea biota
Biological components: composistion, abundance and species of sea biota, especially benthos/nekton
Diversity index and domination of plankton/ nekton and abundance of nekton.
Observing water quality/productivity and planned environmental impact management effectiveness and trend of change in environmental quality
Sea biota (benthos/nekton) sampling dan fishery performance inventorying
Inventorying environmental management data to be further evaluated
5 observation points in water area in the area of Multipurpose Terminal in Lamong Bay in accordance with baseline data
During construction (minimally once during port pool dredging)
PT Pelabuhan Indonesia III
- East Java Province Environmental Agency - Surabaya City Environmental Agency
- Ministry of Environment - East Java Province Environmental Agency - Surabaya City Environmental Agency
15. Planned Port Pool Dredging
Disturbance to fisherman activities
Socio-economic and cultural component : Resident working as
Coastal fishermen. Deep sea fishermen to take longer voyage
Identifying change of the activities of fisherman leading to
Method of Data Collection
Observing and interviewing fishermen
Studying fishermen‟s complaints directly addressed to PT Pelindo.
Area surrounding the multipurpose terminal, namely: • Asemrowo Sub-district : Tambak Langon Vill. and Greges Vill.
Once during construction phase
PT Pelabuhan Indonesia III
- East Java Province Environmental Agency - Surabaya City
- Ministry of Environment - East Java Province Environmental Agency
PT PELABUHAN INDONESIA III (PERSERO) CHAPTER 7 – ENVIRONMENTAL IMPACT OBSERVATION PLAN
VII - 8 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Nr. Project Phases as Sources of Impacts
Observed Impacts
Observation Objectives
Environmental Observation Method Environmental Observation Institutions
Descriptions of Arising Impacts
Impacted Environmental Components
Indicator/ Parameter
Method of Data Collection and Analysis Observation Points
Time and Frequency
Executor Supervisor Report Receiver
fisherman change of fisherman income
Method of Data Analysis
Descriptive analysis to some findings from the collected quantitative data (numbers and table) and qualitative data (narration)
• Krembangan Sub-dist. : Morokrembangan Village
• Benowo Sub-dist : ambak Osowilangon Vill. and Romokalisari Vill.
Environmental Agency
- Surabaya City Environmental Agency
OPERATION PHASE
1. Operation of Multipurpose Terminal
Decreased seawater quality
Physical-chemical components : Seawater quality
Seawater quality referring to Decision of Minister of Environment Nr.51/2004 about Seawater Quality Standard for Port Pool
Observing the changes in seawater qauality due to the operation acrtivities and the planned management programs to identify the environmental impact management effectiveness and trend of change in environmental quality
Visual Observation
Seawater random sampling in 3 observation points and laboratory analysis. Sample testing on total suspended solid in laboratory. Total seawater samples : 3, from impacted areas, i.e. :
1 point in the sea waters in the interchange area
1 points around the container terminal
1 point in pier area
Inventorying of environmental impact management implementation on decreased seawater quality and evaluation to the environmental impact management implementation as planned in EIM documents
The results of laboratory test, especially concerning total suspended solid (TSS) are compared to the standards set forth in Decision of Minister of Environment Nr.51/2004 about Seawater Quality Standard for Port Pool
Inventorying environmental management data to be further evaluated
Area of Multipurpose Terminal
Semester basis during the operation of the multipurpose pier
PT Pelabuhan Indonesia III
- East Java Province Environmental Agency - Surabaya City Environmental Agency
- Ministry of Environment - East Java Province Environmental Agency - Surabaya City Environmental Agency
2. Operation of Multipurpose Terminal
Decreased road performance
Physical-chemical components : Trans-portation sub-component, especially decreased road performence
Traffic jam on Jl. Raya Tambak Osowilangon, The observed parameter is Degree of Saturation or comparison between traffic c volume and road capacity
Identifying Degree of Saturation and environmental impact management effectiveness
Direct observation and traffic counting for 12 hours 06.00 a.m. - 18.00.
Jl. Raya Tambak Osowilangon
Semester basis during the operation of the multipurpose pier
PT Pelabuhan Indonesia III
- East Java Province Environmental Agency - Surabaya City Environmental Agency
- Ministry of Environment - East Java Province Environmental Agency - Surabaya City Environmental Agency
3. Operation of Multipurpose Terminal
Disturbance to sea biota
Biological components: composistion, abundance and species of sea biota, especially benthos/nekton
Diversity index and domination of plankton/ nekton and abundance of nekton.
Observing water quality/productivity and planned environmental impact management effectiveness and trend of change in environmental quality
Sea biota (benthos/nekton) sampling dan fishery performance inventorying
Inventorying environmental management data to be further evaluated
5 observation points in water area in the area of Multipurpose Terminal in Lamong Bay in accordance with baseline data
Minimally twice a year to represent each different season
PT Pelabuhan Indonesia III
- East Java Province Environmental Agency - Surabaya City Environmental Agency
- Ministry of Environment - East Java Province Environmental Agency - Surabaya City Environmental Agency
4. Operation of Multipurpose Terminal
Decreased Mangrove ecosystem area
Biological Components: mangrove ecosystem area
Percentage (%) of mangrove coverageand survival rate of mangrove seeds planted based on tree density (trees per ha) during 1 year
Observing the environmental management performance , whether the revegetation is consistent with EIM documents
Direct field observation.
Inventorying data of implemented environmental management for further evaluation
Galang Island
Estuary of Sememi River
Estuary of Branjangan River
Twice a year in June (dry season) and December (wet season)
PT Pelabuhan Indonesia III Supported by related institution or the ones appointed by the initiator
- East Java Province Environmental Agency - Surabaya City Environmental Agency - Surabaya City
- Ministry of Environment - East Java Province Environmental Agency - Surabaya City Environmental
PT PELABUHAN INDONESIA III (PERSERO) CHAPTER 7 – ENVIRONMENTAL IMPACT OBSERVATION PLAN
VII - 9 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Nr. Project Phases as Sources of Impacts
Observed Impacts
Observation Objectives
Environmental Observation Method Environmental Observation Institutions
Descriptions of Arising Impacts
Impacted Environmental Components
Indicator/ Parameter
Method of Data Collection and Analysis Observation Points
Time and Frequency
Executor Supervisor Report Receiver
Agriculture Service - Gresik regency Agriculture Service
Agency
5.
Operation of Multipurpose Terminal
Job and business opportunities working-aged and jobless people in the studied area
Socio-Economoc Component : working-aged and jobless people in the studied area
Number of local people hired in the operation of the multipurpose terminal and the resident running new business due to operation of the multipurpose terminal
Identifying whether local people are hired in the operation of the port
Identifying how many new buinsesses established due to the operation of the port
Method of Data Collection
Holding panel discussions with government officers and public figures in regaed with the labor recruitment in the operation of the port and preparing minutes of meeting with the community
Monitoring the rectruitment process for the interest of the port operation
Interviewing village officers involved in the recruitment process for for the interest of the port operation
Observing the dynamic/protest by the community in the line with the labor recruitment
Method of Data Analysis
Descriptive analysis to some findings from the collected quantitative data (numbers and table) and qualitative data (narration)
Area surrounding the multipurpose terminal, namely: • Asemrowo Sub-district : Tambak Langon Vill. and Greges Vill.
• Krembangan Sub-dist. : Morokrembangan Village
• Benowo Sub-dist : ambak Osowilangon Vill. and Romokalisari Vill.
Observation during recruitment process and on semester basis during the operation of the port
PT Pelabuhan Indonesia III
- East Java Province Environmental Agency - Surabaya City Environmental Agency
- Ministry of Environment - East Java Province Environmental Agency - Surabaya City Environmental Agency
6. Operation of Multipurpose Terminal
Disturbance to fisherman actvivities leading to decreased fishermen income
Socio-economic and cultural component : Resident working as fisherman
Decreased number of caught fish and fishermen income
Identifying change of the activities of fishermanand fish catching performance leading to change of fisherman income
Method of Data Collection
Observing and interviewing fishermen.
Studying the community complaints addressed to PT. Pelindo III.
Method of Data Analysis
Descriptive analysis to some findings from the collected quantitative data (numbers and table) and qualitative data (narration)
Area surrounding the multipurpose terminal, namely: • Asemrowo Sub-district : Tambak Langon Vill. and Greges Vill.
• Krembangan Sub-dist. : Morokrembangan Village
• Benowo Sub-dist : ambak Osowilangon Vill. and Romokalisari Vill.
Semester basis during the operation of the port
PT Pelabuhan Indonesia III
- East Java Province Environmental Agency - Surabaya City Environmental Agency
- Ministry of Environment - East Java Province Environmental Agency - Surabaya City Environmental Agency
7. Operation of Multipurpose Terminal
Community (Fisherman unrest)
Socio-economic and cultural component : Resident working as fisherman
Attitude and perception of the community to the operation of the port
Monitoring the attitude and perception of the comunity towards the operation of the port to anticipate demo, protest and statement by community that can disturb the operation of the port.
Evaluating the decree of satisfaction of the community to CSR activities for coping with the social impacts and operation of the port
Method of Data Collection
Inventorying environmental management implementation data through dialogue and CSR programs.
Interviewing village officer, public figures and fisherman organizations
Observing the dynamic/protest by the community in the line with the operation of the port
Method of Data Analysis
Descriptive analysis to some findings from the collected quantitative data (numbers and table) and qualitative data (narration)
Area surrounding the multipurpose terminal, namely: • Asemrowo Sub-district : Tambak Langon Vill. and Greges Vill.
• Krembangan Sub-dist. : Morokrembangan Village
• Benowo Sub-dist : ambak Osowilangon Vill. and Romokalisari Vill.
Once during the operation of the port
PT Pelabuhan Indonesia III
- East Java Province Environmental Agency - Surabaya City Environmental Agency
- Ministry of Environment - East Java Province Environmental Agency - Surabaya City Environmental Agency
PT PELABUHAN INDONESIA III (PERSERO) CHAPTER 7 – ENVIRONMENTAL IMPACT OBSERVATION PLAN
VII - 10 Addendum to ENVIRONMENTAL IMPACT STATEMENT, ENVIRONMENTAL IMPACT MANAGEMENT, ENVIRONMENTAL IMPACT OBSERVATION Documents Tanjung Perak Port Development in Lamong Bay
Page : VII - 10
Figure 7.1 Environment Observation Site
Source: DIGITAL INDONESIAN MAP YEAR 1999 (LAND USE) and RESULT OF BATHYMETRY MEASUREMENT IN LAMONG RIVER ESTUARY YEAR 2008
1 0 1 2km SCALE
U
TA R
A
14’30”
14
’00”
9200
13’30”
13
’00”
12
’30”
12
’00”
11
’30”
11
’00”
9205
10’30”
10
’00”
09
’30”
09
’00”
08
’30”
9210
08’00”
06
9326
7 m
T
44’00” 44’30” 9198242 mU 9198293 mU 38’00” 38’30”
0680
Balongsari 3,5 km
39’00” 39’30” 40’00” 40’30”
0685
Balongsari 1 km
41’00” 41’30” 42’00” 42’30” 43’00”
0690
43’30”
0693
214 m
T
Observation Site of Air Quality and Noise
Observation Site of Road Performance
Observation Site of Water Quality & Diversity Index and domination of plankton
Observation site of Decreased Mangrove Ecosystem Area Temporari Access Site
Observation Site of Change of Water Current
Patterns & Increased Surface of River runoff
BIBLIOGRAPHY
1. Anonim,1996, Assesment of Noise with Respect to Community
Response, ISO-R
2. Anwar Hadi,2005, Prinsip Pengelolaan Pengambilan Sampel Lingkungan,
Gramedia Pustaka Utama, Jakarta
3. Badan Lingkungan Hidup Propinsi Jawa Timur, 2012, Studi
Keanekaragaman Hayati Kawasan Teluk Lamong
4. Bemmelen, 1949, The Geology of Indonesia Vol II, Martinus Nijhoff, The
Hague
5. Canter, L. W. and G. L. Hill . 1981, Hand Book of Variables for
Environmental Impact Assessment, An Arbor Science Publ. Inc. The
Butterworth Group. Oklahoma
6. Dickinson, 1978, Plate Tectonicand Hydrocarbon Accumulation, , AAPG
ContinuingEducation Course, No. Series 1
7. Dix, H.M, 1991, Enviromental Pollution : Atmosphere, Land, water, and
Noise , John Wiley & Sons. New York
8. ERM, 2010, RKL – RPL Tambahan Pengembangan Lapangan MIGAS Blok
Tuban 2010, ERM
9. Green, R.H., 1979, Sampling Design and Statistical Methods for
Environmental Biologists, John Wiley and Sons, New York.
10. LPPM ITS, 2010, Laporan Pelaksanaan RKl – RPL Studi AMDAL
Pengembangan Lapangan Minyak Dan Gas Bumi Blok Tuban – West
Area, LPPM ITS
11. Marriot, Betty Browers, 1997, Pratical Guide to Environmental Impact
Assessment , McGraw-Hill, New York.
12. Odum, E.P., 1994, Dasar-Dasar Ekologi, Gajah mada University Press,
Yogyakarta.
13. Rau, J.G. and D.C. Wooten, 1980, Environmental Analysis Handbook, Mc
Graw Hill Book Co., New York.
14. Schimdt, F.H, and J.H.A. Ferguson, 1951, Rainfall Type Based On Wet
And Dry Period Ratio For Indonesia With Western New Gurinea ,
Kementerian Perhubungan. Jawatan Meteorologi dan Geofisika, Jakarta
15. Surveyor Indonesia, 2011, Laporan Pelaksanaan RKL & RPL, Semester II,
PT. Surveyor Indonesia.
16. Yulihanto B., Sriwahyuni, L., Situmorang, B., 1995, Peranan Tektonik
Tarikan pada Perkembangan Runtunan Pengendapan Tersier di Bagian
Barat Kawasan Daratan Cekungan Jawa Timur Utara, Pros, Diskusi
ilmiah VIII PPTMGB “Lemigas”.
1
ANNEXURE
STRATEGIC ENVIRONMENT REVIEW IN LAMONG BAY
PT PELABUHAN INDONESIA III (PERSERO) STRATEGIC ENVIRONMENT REVIEW IN LAMONG BAY
1
STRATEGIC ENVIRONMENT REVIEW IN LAMONG BAY
I. CONCLUSION AND RECOMMENDATIONS Study of Strategic Environmental Research Review Database Preparation for Development Programs in Lamong Bay and Madura Strait (Year 2010)
CONCLUSIONS
Strategic environmental issues – In the studied area,, the issues to be well
considered while preparing policies, plans and program are as follow :
1. Flood in Lamong River
2. Sedimentation in Madura Strait
3. Conservation of Galang island
4. Integration of Spatial Designs arount the studied area
The basis of strategic environmental issue determination are briefly described below :
1. Lamong River
- Flood always present in Lamong River Watershed during wet season. The
flooded area covers : Cerme Sub-district and Duduk Sampeyan Sub-district,
Gresik Regency, Cermenlerek Village and Gorekan Kidul Village. The flood
height is ± 1.5 m and flooding ± 600 Ha farms and dwelling areas.
- It is the last drainage for part of Surabaya City, Gresik regency and other areas
surrounding the river.
- The increased sedimentation in the river triggers surface erosion in the area
due to extensive change of forest area into agriculture area.
2. Madura Strait
- The sedimentation at the edge of West Surabaya Shipping Routes takes place
time after time with sedimentation materials originating from
- Process of sedimentation at the edge of Ujung Pangkah, Mireng River and
Lamong River
- The sedimentation in Lamong Bay is greatly affected by mixed tides and tend
to be daily multiple. Accordingly, the period of change of water current
patterns due to the tides is relatively short, i.e. : about 7-8 hours. It lead to a
condition that the suspended materials have not yet been drawn out of the
mouth of the strait, hen they are suspended again into the strait waters.
PT PELABUHAN INDONESIA III (PERSERO) STRATEGIC ENVIRONMENT REVIEW IN LAMONG BAY
2
- The different depths in the coast and shipping routes and the water current
speed makes the concentration of suspended materials vary.
- The most dominant vessel accidents in Madura Strait are vessel crashes and
brushes 48.6% of total accidents). Mostly, the accidents take place around
Tanjung Perak Port (67,5%) and West Surabaya Shipping Routes (14%).
3. Galang Island
- Mangrove is the main vegetaion in Galang Island with an average tree density
of >1500 trees/Ha, mostly dominated by Avicennia alba.
- The mangrove area in Galang Island is occupied by the sea biota as their
habitat, among other things, is avifauna. At least there area 21 bird species
found in this areaand, 11 of them are conserved by Act Number 05 Year 1990
and Indonesian State Regulation Number 07 Year 1999.
- Small heron (Egretta garzetta), buffalo heron (Bubulcus ibis), silver heron
(Egretta sacra) and gray nigh kowak (Nycticorax nycticoraxare) some of the
conserved birds and occupying Galang Island as their nesting and resting area
or habitat
- The community has planned the exploit the mangrove area in the North part of
Galang Island (Site A) as a fishpond area and currently, there are indicators of
digging and fishpond embankments in some points. Besides, there is a
tendency that bird hunting by some people for consumption purposes.
- The middle part of Galang Island (site B) is occupied for an area of nesting
colony for Small heron (Egretta garzetta), buffalo heron (Bubulcus ibis), silver
heron (Egretta sacra) and gray nigh kowak (Nycticorax nycticoraxare). Based
on the results of observation, it is conclusive that The middle part of Galang
Island (site B) is a core area or habitat of coastal birds in Galang Island.
- The mangrove in the South part of Galang island (Site C) is definitely dense,
and accordingly no many water birds occupy this site. May coastal birds are
found in the adge area searching for food.
4. Integration of Spatial Design around Studied Area
- At present, each city government or regency government surrounding the
studied area has developed its own spatial area.
- As a development in an area can stimulate developments in other surrounding
areas, it will lead to spatial conflicts of interests among the city/regency
PT PELABUHAN INDONESIA III (PERSERO) STRATEGIC ENVIRONMENT REVIEW IN LAMONG BAY
3
governments if the development of Lamong Bay is not integrated with the ones
in the surrounding areas.
Having conducted a study to identify the impacts of Development Policy, plan and program
in Lamong Bay and Madura Strait on 4 strategic environmental issues in the studied area, it
is conclusive that :
1. The reclamation in the estuary Lamong Bay and in front of Galang Island will block
the water flow of Lamong Bay.
2. The back water in Lamong River will be getting father, i.e. : ± 20 km toward the
land. The increase of water surface will be ± 1.00 m in the estuary and ± 0.30 m in
area ± 20 km from the estuary, when compared to the previous state of
conditions. It is clear that flood with wider puddles will be more seriously
threatening the area.
3. The quite number of rivers bringing sediment materials and flowing to Madura
Strait accelerates the sedimentation in the West Surabaya Shipping Routes. It will
get worse in case of reclamation in Lamong Bay as the sediment will get thicker,
while the width and depth of Madura Strait have to satisfy the minimum standards
for the cargo vessels and Indonesian Navy Battle Ships to sail across.
4. Galang Island needs to be conserved as the mangrove vegetation is classified
dense (referring to Decision of Minister of Environment Number : 201 Year 2004).
In addition the 21 avifauna species from 12 families exist and 11 of them are
conserved by virtue of are Act Number 5 Year 1990 and Indonesian State
Regulation Number 7 Year 1999, and the rest one is included into an Indonesian
endemic (Alcedo coerulescens /Blue Shrimp King). Beside, 1 bird species: i.e. :
Bluwok Heron(Mycteria cinerea)is internationally conserved. The middle part of
the sea is occupied as habitat by avifauna for food foraging, resting, nesting.
5. Development in Lamong Bay is to be well integrated with the spatial plans in the
surrounding cities or regencies in order to prevent conflict of interest among the
relevant city governments and regency governments, since a development in an
area will stimulate the other developments in its surrounding, In fact, ex=ach city
or regency government has its own master plan.
PT PELABUHAN INDONESIA III (PERSERO) STRATEGIC ENVIRONMENT REVIEW IN LAMONG BAY
4
RECOMMENDATIONS
The results of study offer alternatives actions that can be recommended in
order to be able to minimize the impacts of development in Lamong Bay and Madura
Strait to the 4 (four) strategic environmental issues (as detailed in Chapter 4), i.e.:
1. The West Surabaya Shipping Routes need to be widened and deepened. In
addition, it is necessary to well consider the pools in Tanjung Perak Port as it is
frequent to find vessel accidents (vessel crashing/brushing) in this area (67,5%)
and in West Surabaya Shipping Routes (14%).
2. Design of reclamation ensuring the least impacts in view of sediment volume in
West Surabaya Shipping Routes. The sediment thickness surround the reclamation
area (Lamong Bay, Mireng Bay) and elevation of water surface around the estuary
of Lamong Bay are presented in Figure 1. The reclamation points in Lamong Bay
are as follows :
- Block A (±140 Ha), Block B (±160 Ha), Block C (±540 Ha), Block D (±80 Ha);
- Block A attaches on-shore along ±200 m; while Block B, C, and D are separated
from on-shore by a canal of 140m through 500m width (Figure 1)
- Block A and Block B are separated by a canal of 1,000 m width, while between
Block B and Block C and between Block C and Block D, they are separated a
canal of 500 m width.
3. The canal around Block B, Block C, and Block D needs to be regularly dredged to
reach 2 m depth as it is functioned as a trap fro sediment from the rivers flowing
into Madura Strait. This will prevent the sediment from the rivers flow into the
shipping routes.
4. The reclamation design requires:
Cutting of Galang Island in the North part that is not occupied by
avifauna/birds in the following coordinates:
- West point 7 11‟38.65 ; 11239‟51.30 and
- East point 711‟35.25; 11239‟56.25
The considerations to take when cutting Galang island are :
- Behavior of Birds
- Not breeding season, to prevent death and decrease of bird population
PT PELABUHAN INDONESIA III (PERSERO) STRATEGIC ENVIRONMENT REVIEW IN LAMONG BAY
5
5. Galang Island conservation is definitely in demand to keep the mangrove in good
condition and the existence of 11 Avifauna families / birds are well preserved.
Accordingly, it requires. An habitat conservation zones in Galang Island, namely :
Core Zone – The middle part and South part of the island can be plotted as a
core zone as most birds nest and breed in this part.
Buffer zone – The buffer zone for the core zone in Galang Island is the mudflat
in the East part of the island, estuaries surrounding the island and mangrove
area around Galang island , including estuaries of Sememi River, Branjangan
River and Lamong River.
6. The flood control and handling should not be sectoral and/or physical structural
only, it is to consider the following aspects
Involvement of stakeholders
Considering sicio-economic, legal, politic and ecosystem aspects.
Adoption of participative approach
PT PELABUHAN INDONESIA III (PERSERO) STRATEGIC ENVIRONMENT REVIEW IN LAMONG BAY
6
Figure 1. Reclamation Design Bringing The Least Impacts to Strategic Environmental Issues aroud Studied Area
MADURA ISLAND
JAVA
ISLAND
Madura
MADURA STRAIT
MADURA STRAIT Madura
PT PELABUHAN INDONESIA III (PERSERO) STRATEGIC ENVIRONMENT REVIEW IN LAMONG BAY
7
Figure 2. Zone Division in Galang Island Conservation
7. The flood control is to be well integrated, in terms of : area resources and water
resources, within a context Integrated Water Resource Management to maximize
the flood advantages and minimize disadvantages.
8. The integration between the management of Lamong River flood and management
of drought is badly needed to cope with the problems arising from the change of
utilization of area in Lamong River watershed. The integrated management is
applied by effectively exploiting the flood water to generate maximum
adavantage and/or maximizing the positive aspects of flood, where deep soil
water and rain water are treated as inter-related resources. Accordingly, it
requires artificial precipitation in Lamong River watershed to enrich the deep soil
water and minimize overflows into Lamong River via its tributaries.
9. The general strategies adopted in flood management approach are presented in
Table 1., where the proper selection of the strategies greatly depends on the
characteristics of hydrology and hydraulic aspects of Lamong River System are
areas it passes. The strategy priority are presented in Table 1.
Legend: - Area in red line : core zone
- Area in yellow line : buffer zone
PT PELABUHAN INDONESIA III (PERSERO) STRATEGIC ENVIRONMENT REVIEW IN LAMONG BAY
8
Table 1. Flood Management Strategy
Strategy Options
Reducing Flood Constructing dams and small basins in watershed area
Normalizing rivers (widening and heightening embankments)
Managing watershed
Reducing vulnerability to damages Regulating flooded area
Forecasting flood and providing early warning
Preparing facility designs and locations
Inspecting flood control facilities
Flood Impact Mitigation Information and Education
Disaster Emergency Alert
Post Flood Recovery
Preserving natural resources from flood plain
Regulation and flood plain zoning
Table 2. Strategy Priorities on Management of Flood in Lamong River
Flood Control Activities
Objectives
Methods
Actions Structural Non
Structural
(1) Basic Plan Modification
Slowing Overflow into River
Rainwater Detention/Retention Facility in Watershed: Type Detention/ Retention Storage
Institutional Steps
Emergency Steps
(2) Basic Plan Modification
Flood Prevention
Flood Regulation: - Dam - Small Basin
(3) Increasing River Capacity
Reducing Flood Water
Increasing River Capacity. River Fixing/ Normalization
(4) Decreasing Flood Loss
Reducing Flood Loss
Flood Resistant Buildings
Spatial Regulation
Flood Fighting: - Evacuation - Victim Rescue - Flood Mapping - Fixing Works
PT PELABUHAN INDONESIA III (PERSERO) STRATEGIC ENVIRONMENT REVIEW IN LAMONG BAY
9
10. Descriptions of reclamation area in the studied area are plotted in presented in ..
Areas A, B, C are reclamation areas in Surabaya territory while area D is the one
in Gresik Territory.
11. The spatial concepts in the reclamation area adopt principles of integration,
balance and unity among development areas and environmental insight. There are
two alternatives of recommendations, namely :
1st Alternative
Developments in Surabaya, Gresik and Bangkalan cover the following
reclamation areas :
a. Area A of 138.2 Ha, projected for container depot and warehousing area
b. Area B of 160.7 Ha, projected for eco-friendly office area, eco-frendly
estate area, and recreation area
c. Area C of 539.9 Ha for eco-friendly port area, for eco-friendly office area,
eco-fiendly trading and service area
d. Area D of 80 Ha, projected for eco-friendly office area, eco-frendly estate,
and recreation area
In areas A, B, C, D, a ringroad will be constructed. Areas B,C and D are
connected with bridges. Area A is directly connected to outlet/entrance with an
arterial primary road in Perak. Each of Area A, B, C and D will be connected with a
road integrated to the arterial primary road. In the junction between the laaned
arterial road and arterial primary road, there will be 3 oulets/entrances designed
to be a junction of the planned arterial road and the existing areteial primary
road, i.e. : in Segoromadu Village (Gresik territory), Benowo Sub-district and
Tandes Sub-district (Surabaya territory).
PT PELABUHAN INDONESIA III (PERSERO) STRATEGIC ENVIRONMENT REVIEW IN LAMONG BAY
10
Figure 3. Planned Reclamation Area
Figure 4. Planned Reclamation Area Development in Each Area
GresikTerrito
ry Suarabaya
Territory
Gresik Territory
A
B
C
D MADURA STRAIT
Madura
MADURA ISLAND
Madura
JAVA ISLAND
PT PELABUHAN INDONESIA III (PERSERO) STRATEGIC ENVIRONMENT REVIEW IN LAMONG BAY
11
Figure 5. Concept of Reclamation Area Development (Alternative 1)
PT PELABUHAN INDONESIA III (PERSERO) STRATEGIC ENVIRONMENT REVIEW IN LAMONG BAY
12
2nd Alternative
Developments in Surabaya, Gresik and Bangkalan cover the following
reclamation areas :
a. Area A of 138.2 Ha, projected for container depot and warehousing area
b. Area B of 160.7 Ha, projected for eco-friendly office area, eco-frendly
estate area, and recreation area
c. Area C of 539.9 Ha for eco-friendly port area, for eco-friendly office
area, for eco-friendly industrial area, eco-fiendly trading and service
area
d. Area D of 80 Ha, projected for eco-frendly estate, eco-friendly office
area, and recreation area
In areas A, B, C, D, a ringroad will be constructed. Areas B,C and D are
connected with bridges. Area A is directly connected to outlet/entrance with an
arterial primary road in Perak. In thsi concept, an arterial and flyover will be
constructed. Each of Area A, B, C and D will be connected with a road integrated
to the arterial primary road. The planned flyover will be connected to area B and
C, and directy connected to toll road in 2 outlets/entrances that serve as a
junction between the flyover and toll road , i.e. : Demak Toll Road and
Romokalisari Toll Road. In the arterial road junction, there will be 3
oulets/entrances designed to be a junction of the planned arterial road and the
existing areteial primary road, i.e. : in Segoromadu Village (Gresik territory),
Benowo Sub-district and Tandes Sub-district (Surabaya territory).
PT PELABUHAN INDONESIA III (PERSERO) STRATEGIC ENVIRONMENT REVIEW IN LAMONG BAY
13
Figure 6. Concept of Reclamation Area Development (Alternative 2)
PT PELABUHAN INDONESIA III (PERSERO) STRATEGIC ENVIRONMENT REVIEW IN LAMONG BAY
14
12. The spatial plan refers to the master plan of Surabaya City, Gresik Regency and
Bangkalan Regency. The new area development is projected for a dwelling area
with a concept of waterfront city. Other spatial arrangements cover trade and
service block, industrial block, tourism block as supporting area. Open green space
development is projected for a green belt, especially in the border between
industrial block and dwelling area. The open green space can also be developed as
a tourism attraction.
13. The concepts for alternatives 1 and 2 adopt circular lines offering better
movements. Each of the reclamation areas is separated from the others with 500
m width canal among area B, Area C and area D. Area B and area A is separated
with 1,000 m width canal to accommodate the special Indonesian Navy Base that is
relatively full of massive activities, such as circulations of war ships and other
vessels for military purposes. The reclamation areas B, C and D are separated from
the main land with 150 m w – 500 m width canal designed to trap sediment from
the rivers flowing to Madura Strait so that it will not make the West Surabaya
Shipping Routes shallow. To connect the mainland and reclamation areas
separated by with 150 m w – 500 m width canal, and the connecting access among
the reclamation areas, it will be connected by bridge under which can be accessed
by fishing/ailing boats. The pillars of the bridge are erected with about 4 m
intervals.
14. The structures of the reclamation areas cover a dwelling area are designed with
concepts of waterfront city, office block, industrial block, warehousing area,
utilities, trade and service block, tourist attraction, and education block. As a
dwelling center, it will be projected for dwelling, trading and service, industrial
and warehousing activities. The dwelling center is connected with network
system, facility and utility system, to the reclamation islands planned to be
established in Surabaya City territory, Gresik Regency territory and Bangkalan
Regency territory. The structural functions of each of the areas is directed to
support the main activities, i.e. : dwelling office, industry, trade and service,
utility, warehousing, tourism, and education. The industry is designed to be eco-
friendly industry and the port is designed to be an eco-friendly port.
PT PELABUHAN INDONESIA III (PERSERO) STRATEGIC ENVIRONMENT REVIEW IN LAMONG BAY
15
15. The concepts on structural function of activities in the studied area are detailed
as follows :
The area in Lamong Bay and it surrounding covers area A, area B and area C
that are projected for the following activities :
Area A : Container Depot and warehousing
Area B: eco-friendly office area, for eco-friendly estate area, and tourist
attraction
Area C: eco-friendly port area, for eco-friendly office area, for eco-friendly
industrial area, eco-fiendly trading and service area
Area D (Gresik and its surrounding), for the following activities :
Eco-friendly estate
Eco-friendly office
Tourist attraction
All activities are directed not only to economic aspect but also ecological
one. The activities are supposed to bring minimum impacts to the environment,in
the senes ethat they are safe to the environment. The spatial concept in the
reclamation area stresses on the importance to preserve the environment from
damages. (Eco-friendly area : Eco-industrial park and Eco-estate)
PT PELABUHAN INDONESIA III (PERSERO) STRATEGIC ENVIRONMENT REVIEW IN LAMONG BAY
16
Figure 7. Concept of Activity Function Structure
16. The development of each reclamation area (Areas A, B, C, D) needs to be further
elaborated into more detailed plans with zoning concepts comprising zone
mapping and zone regulation. The zoning regulation serves as a tool for controlling
the spatial utilization in the reclaimated area.
17. Eco-Industrial Park (EIP) is characterized with the following features :
Group of companies adopting eco-friendly technologies
Group of companies manufacturing green products
Industrial park supported with eco-friendly infrastructures
By-product networks
Recycling business cluster
PT PELABUHAN INDONESIA III (PERSERO) STRATEGIC ENVIRONMENT REVIEW IN LAMONG BAY
17
18. Eco-Port is greatly committed to :
Keep port pool cleanliness from rubbish and other wastes
Treat liquid wastes, including dangerous and hazardous materials
Keep the clean, shady and green environment
Provide public service, security, order and public safety
Have incorporated capability to manage the port environment
Maintain service performance and occupational safety in port
19. Eco-estate is a dwelling estate with balanced development in terms of economic,
ecological and social equality aspects. The three aspects can be elaborated in
seven features, namely :
Optimum land use/urban form
Energy efficient building designs
Efficient water consumption,
Air quality (many trees and minimum motorized vehicles)
Green/open space (shady pedestrian, garden, tree density)
Traffic/transportation (safe, comfortable and easily accessible public
transportation)
Green policy (Vision on eco-friendly development, incentives and
disincentives, designs and products, socialization and certification)
20. Drainage concepts in reclamation area :
It is extremely necessary to set ‟flood peil‟ (the highest flood surface
elevation) as a reference to determine the lowest elevation of the floors to
prevent puddles.
The drainage is designed only for draining local rainwater. The main drainage
must be directed to the cannal. There is no drainage draining into the shipping
routes or sea. Consequently, there will be no sediment directly flowing into
the sea . Besides, it is also effective for controlling fluctuation of water
surface in the estuary.
It calls for basin/storage pool in the reclamation area to store the rainwater
for conservation purposes.
PT PELABUHAN INDONESIA III (PERSERO) STRATEGIC ENVIRONMENT REVIEW IN LAMONG BAY
18
21. Concept of Water Supply in Reclamation Area
The plain water from the rain is stored in the basin/pool spcifically provided to
store rain water as additional supply. The supply of fresh water is supposed to
be supplied by Surabaya City Water Enterpriseplanning to take the water from
the sources in Umbulan and Bengawan Solo River.
Lebar dasar
Kebutuhan lebarpenampang
( min. 62.00 m )
Kebutuhan lebar total
Batas
sempadanBatas
sempadan
Jalan
Inspeksi
Parapet
1V : 2H 1V : 2H
Jalan
Inspeksi
Parapet
Figure 8. Sketch of Main Drainage Cross Section.
PT PELABUHAN INDONESIA III (PERSERO) STRATEGIC ENVIRONMENT REVIEW IN LAMONG BAY
19
Figure 9. Example of a Basin in a Real Estate
PT PELABUHAN INDONESIA III (PERSERO) STRATEGIC ENVIRONMENT REVIEW IN LAMONG BAY
20
II. CONCLUSIONS AND RECOMMENDATIONS
Strategic Environmental Review – Lamong Bay (Year 2012)
CONCLUSIONS
Based on the results of Strategic Environmental Review over the Policy, plan and
program concerning Lamong Bay, it is conclusive that :
1. The development of port and waterfront city in Lamong Bay will change the water
current patterns and sedimentation, especially in area close to the estuary of
Lamong River and Morokrembangan Basin. The change of the water current patterns
will change the sedimentation pattern in Madura Strait, especially in Lamong Bay.
The reclamation in the planned points will accelerate sedimentation in the estuary
of Lamong River and consequently hinder the water flow of Lamong River.
2. In Galang Island there are birds conserved by national and international laws.
Accordingly, it is strictly prohibited to disturb them.
3. The constructions of two large scale ports in Lamong Bay will drive the port
activities, especially the planned transportation and port construction activities,
concentrated in that area. In addition, it will be difficult to realize the concept of
wide spread development.
4. In Lamong Bay, there have been some general and special ports. The addition of
port construction in Lamong Bay will increase the sea traffic density that leads to
decreased shipping route service performance.
5. On the seabed of Lamong Bay where the West Surabaya Shipping Routes are
established there are under seawater gas pipelines and electric cables of the State
Electricity Enterprise. It may endanger voyage safety when the sea traffic is pretty
dense.
RECOMMENDATIONS
In order to maintain the environmental condition in Lamong Bay, it is
necessary to take the following measures:
1. Monitoring the construction of multipurpose terminal of PT. Pelindo III in 50
Ha area, so that it will not shift the East.
2. The scope of Spatial Utilization Permit granted to Permit PT. Indosarana Niaga
Perkasa needs to be reviewed so that it will not worsen sedimentation in
PT PELABUHAN INDONESIA III (PERSERO) STRATEGIC ENVIRONMENT REVIEW IN LAMONG BAY
21
Lamong River. The area with minimum impact on the change of water current
pattern and sedimentation is about 60 Ha. When re-designed, the reclamation
plan for optimizing the spatial utilization is recommended to be implemented
in area C maximally with a total area of 516 Ha as presented in Figure 3.4.
3. The spatial utilization permit granted to PT. Sarana Mitra Global Nusantara
needs to be reviewed so that impact on the change of water current pattern
and sedimentation can be minimized by cutting the reclamation edge.
4. It is recommended not to dredge or cut Galang island and immediately
promulgate it as a conservation area, and when possible, extend the island
area until the sedimentation zone.
5. It is necessary to study the impact of the reclamation plans on flood and
sedimentation in Lamong River.
DETERMINATION OF LAMONG BAY DEVELOPMENT ALTERNATIVES
The determination of Lamong Bay development alternatives is set
systematically. First, it is initialized by setting alternatives on the policy, plan and
program jointly with the involved team. Next, it is the policies are to be reviewed to
map the issues to consider and include them to the policy, plan and program
previously set. The policy, plan and program to be further discussed are the ones
perceived to be pretty significantly affecting the strategic environmental issues as
previously formulized. In view of Lamong Bay, the main point to consider is the Master
Plan of East Java Province and Medium Term Development Plan of East Java Province.
The formulation of alternative policy, plan and program in compliance with the
prevailing regulations is established by:
a. Re-formulating or modifying the size, scale and location of proposal, policy, plan,
and program to minimize the arising impacts (intensity, spread, location, duration,
accumulation);
b. Proposing postponement or sequential fixing/set of proposed policy, plan and
program in city/regency Master Plan meetings.
c. Proposing new policy, plan or program.
In view of development in Lamong Bay, the selected alternative is re-formulating
or modifying the size, scale and location of proposal, policy, plan, and program to
minimize the arising impacts (intensity, spread, location, duration, accumulation).
However, taking further steps it needs to be understood that the policy, plan and
program formulation has been closely reviewed based on the environmental
PT PELABUHAN INDONESIA III (PERSERO) STRATEGIC ENVIRONMENT REVIEW IN LAMONG BAY
22
management principles and other environmental problem solving principles,
covering physical area and socio-economic aspects that have been previously
discussed. In short, in regard with the promulgation of policy, plan and program
alternative, it is necessary to first breakdown the other sets of policy, plan and
program related with the one being reviewed since it is probable that the
handling, prevention and balance to the policy, plan, and program alleged to bring
negative impacts to strategic issues actually have been discussed in the other
formulated policy, plan and program. Next, in order to ease the discussion on the
formulation of alternative police, plan and program, it is necessary to gather
comments to the list of prioritized policy, plan and program to find out the
relationship with alternatives to be set.
MITIGATION OF ENVIRONMENTAL IMPACTS OF DEVELOPMENT OF LAMONG BAY
DEVELOPMENT
The next step is formulating mitigation measures or recommendations to cope
with the negative impacts to the environment. The mitigation steps are supposed to
maximize the positive impacts and minimize the negative ones, as well as enhance
sustainability. Yet, it is also necessary to assure that the recommended mitigation
steps do not arise new negative impacts.
The steps to take comprise alternative evaluation based on sustainability
criteria, i.e.: equilibrium, interdependency, and justice. The mitigation in the
Strategic Environmental Review for Lamong Bay Development is the one included in
mitigation list and pertaining to be part of impact review. The mitigation contains
descriptions on preventive steps to minimize impacts/risks from the implementation
of policy, plan, and program.
The alternative policy, plan and program, mitigation/recommendation through
follow up measures are presented in Table 5.1 in the document.