Pssc v2 u23_ppt_v1.4

16
Welcome to the Session on Welcome to the Session on Steps in Meter Steps in Meter Installation and Single Installation and Single Phase Connection Phase Connection (Meter Installation Process) (Meter Installation Process)

Transcript of Pssc v2 u23_ppt_v1.4

Page 1: Pssc v2 u23_ppt_v1.4

Welcome to the Session onWelcome to the Session on

““Steps in Meter Installation and Steps in Meter Installation and Single Phase ConnectionSingle Phase Connection””

(Meter Installation Process)(Meter Installation Process)

Page 2: Pssc v2 u23_ppt_v1.4

Learning Objectives

By the end of this session, you will be able to:•List the steps to give single phase connection and install an electricity meter•Explain the safety norms that should be followed for mounting ladder

Page 3: Pssc v2 u23_ppt_v1.4

Has knowledge to minimize the risks

Understands the risks and hazards at work place

Has the ability to take decision, lead and guide

Is capable of taking up the job efficiently within the given time

Motivates the team of workers working under him

Qualities of a Supervisor

Page 4: Pssc v2 u23_ppt_v1.4

Let Us Watch

Click the video icon to play the video.

Page 5: Pssc v2 u23_ppt_v1.4

Supervisor

Lineman

Meter installer

Meter Installation Team

Page 6: Pssc v2 u23_ppt_v1.4

Steps Involved In Meter Installation > Step 1

Check the Physical Condition of the PoleStep 1

Lineman to check the physical condition of the pole.

Click the video icon to play the video.

Page 7: Pssc v2 u23_ppt_v1.4

Steps Involved In Meter Installation > Step 2

Check Pole with Tester For Current LeakageStep 2

Lineman to check the pole for current leakage, if any.

Click the video icon to play the video.

Check the Physical Condition of the PoleStep 1

Page 8: Pssc v2 u23_ppt_v1.4

Steps Involved In Meter Installation > Step 3

Check if the Distribution Box is Fixed on the PoleStep 3

The lineman to check if the distribution box is fixed on the pole.

Click the video icon to play the video.

Check Pole with Tester For Current LeakageStep 2

Check the Physical Condition of the PoleStep 1

Page 9: Pssc v2 u23_ppt_v1.4

Steps Involved In Meter Installation > Step 4

Check Load and Condition of Distribution Box

Step 4

The lineman to check the load and condition of the distribution box.

Click the video icon to play the video.

Check if the Distribution Box is Fixed on the PoleStep 3

Check Pole with Tester For Current LeakageStep 2

Check the Physical Condition of the PoleStep 1

Page 10: Pssc v2 u23_ppt_v1.4

Steps Involved In Meter Installation > Step 5

Meter installer to select the place where the meter has to be fixed.

He should maintain the height of meter as per the safety norms.

Click the video icon to play the video.

Analyse the place and height where the meter has to be fixed

Step 5

Check Load and Condition of Distribution Box

Step 4

Check if the Distribution Box is Fixed on the PoleStep 3

Check Pole with Tester For Current LeakageStep 2

Check the Physical Condition of the PoleStep 1

Page 11: Pssc v2 u23_ppt_v1.4

Meter Installation

Meter has been installed

Page 12: Pssc v2 u23_ppt_v1.4

Check the physical condition of the poleStep 1

Check the pole with tester for current leakage, if anyStep 2

Check if the distribution box is fixed on the poleStep 3

Check the load and condition of the distribution boxStep 4

Analyse the place and height where the meter has to be fixedStep 5

Meter Installation Steps > Quick Recall

Page 13: Pssc v2 u23_ppt_v1.4

Let Us Watch

Click the video icon to play the video.

Page 14: Pssc v2 u23_ppt_v1.4

Giving Single Phase Connection > Precautions to be Taken

A rubber mat has to be laid at the foot of the ladder.

Check the metallic part for current leakage.

Maintain the distance between the pole and the ladder in the ratio of 1:4.

Wear full body harness

Page 15: Pssc v2 u23_ppt_v1.4

Giving Single Phase Connection > Precautions to be TakenUse the double line harness to climb the ladder.

Hook the double line harness onto a support at the top of the pole.

Tie the rope at the top end of the ladder around the pole.

Page 16: Pssc v2 u23_ppt_v1.4

• The steps involved in meter installation are:– Checking the physical condition of the pole– Checking the pole with the tester for current leakage, if any– Checking if the distribution box is fixed– Checking the load and condition of the distribution box– Taking care of the place where to fix the meter

• Some of the precautions to be taken while giving single phase connection are:– Ensure rubber mat is laid at the foot of the ladder– Maintain the distance between the pole and the ladder in the ratio of 1:4 – Check the metallic part for current leakage – Wear full body harness– Hook the double line harness onto a support at the top of the pole– Tie the rope at the top end of the ladder around the pole

Key Learning Outcomes