PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l...

17
PRY Base - Contents PRY Support/Base/Platform in the MICE Hall Requirements Environment Design Structural Integrity Preparation Installation Absorber Change Schedule Conclusion Jason Tarrant – Integration Engineering

Transcript of PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l...

Page 1: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.

PRY Base - Contents

PRY Support/Base/Platform in the MICE Hall Requirements Environment Design Structural Integrity Preparation Installation Absorber Change Schedule Conclusion

Jason Tarrant – Integration Engineering

Page 2: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.

PRY Base - Requirements Requirements – Load (before cross-bars added)

Fix to floor

~25 tonnes (self weight)

Overturning

Compression

Tension

NO CAPACITY FOR SIGNIFICANT OVERTURNING

FROM MAGNETIC LOAD – This will be taken by the

cross-bars, leg ties & link plate connections

Page 3: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.

PRY Base - Environment Requirements

– North side

Plate roof on north

side

Edge of floor / trench

Services in trench on wall and

ceiling

Services trench directly under leg

Trench ends

False floor

Page 4: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.

PRY Base - Environment Requirements

– South side

South mezzanine

uprights

Services trench

Ramp

Walkway

Page 5: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.

PRY Base - Environment Requirements

- Services

Tracker Cryo

South mezzanine

Vacuum system

Page 6: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.

PRY Base - Design TD-1189-2090 - North East Quadrant

Existing Base

PRY Legs

PRY Connector

Tie down bars and bases

Support Bridge

Trench & trench services

Trench edge

Page 7: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.

PRY Base - Design TD-1189-2090 – North West Quadrant

Existing Base (shown cutaway)

PRY Legs

PRY Connector

Tie down bars and bases

Support Bridge

Trench & trench services

Trench edge

Short columns

where raised

floor endsVacuum system (installed later)

Page 8: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.

PRY Base - Design TD-1189-2090 – South West Quadrant

New base / platform

PRY Legs

PRY Connector

Vacuum system

Support Bridge

Short columns where raised floor ends

Tie down bars and bases

Brackets and floor anchors

Page 9: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.

PRY Base - Design TD-1189-2090 – South East Quadrant

New base / platform

PRY Legs

PRY Connector

Support Bridge

Services trench

Brackets and floor anchors

Vacuum system

South mezzanine

supports

Page 10: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.

PRY Base – Structural Integrity Testing

Floor anchor pull out (TD-1189-1922)

Component load tests

Analysis & calculation

Page 11: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.

PRY Base - Preparation South Mezzanine

Full length of hinged platforms

Raised platformsReduced

leading edge & cut beams

Removable section for easy absorber change

Fit around PRY

Page 12: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.

PRY Base - Preparation Trench

Water circuit move

Ladder move and change

North-east tie bars pass between trench services (water and

ISIS cables

Page 13: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.

PRY Base - Installation Bases

Floor anchors (TD-1189-2152) Pillars, tie plates & sub-floor (TD-1189-2153)

Top plate installation (blue)

& hole drilling (TD-1189-2136)

Page 14: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.

PRY Base - Installation Installation

Survey inside bridges into place Add legs & connectors(+ bespoke shims to set position)

Add outer bridges

Add tie downs / bolt to floor

Page 15: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.

PRY Base – Absorber Change Absorber change

Page 16: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.

PRY Base – Schedule Schedule

Prep for frame by July 2014, PRY install by end Aug 2014

Page 17: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.

Conclusion Design done (top level = TD-1189-2152,2153,2136 & 2090) Calculation and analysis shows OK for self weight only (not

magnetic load) in terms of stress and strain Piece parts out for manufacturing quotation South mezzanine structural engineering drawings near

completion (OPUS) RFS placed for floor quality tests Load testing on critical parts will be undertaken Possibility of strain gauges on critical parts as per main PRY (H

Witte investigating) Schedule currently predicting manufacture, prep and install to

coincide with PRY delivery (final install dependant on PRY frame delivery)