MICE Partial Return Yoke PRY Fabrication 06 November 2013 Stephen R. Plate Brookhaven National Laboratory 9/23/2013 1

description

MICE Partial Return Yoke PRY Fabrication. 06 November 2013 Stephen R. Plate Brookhaven National Laboratory. Outline. 6-Section Design Change – update Cost & Procurement Status Work to complete. Center sections (independent removal). Lowered Restraint bars (clear mezz , south). - PowerPoint PPT Presentation

Transcript of MICE Partial Return Yoke PRY Fabrication

Page 1: MICE Partial Return Yoke PRY Fabrication

1

MICE Partial Return YokePRY Fabrication

06 November 2013Stephen R. Plate

Brookhaven National Laboratory

9/23/2013

Page 2: MICE Partial Return Yoke PRY Fabrication

2

Outline

• 6-Section Design Change – update• Cost & Procurement Status• Work to complete

9/23/2013

Page 3: MICE Partial Return Yoke PRY Fabrication

3

Previous design

New designLeft/right symmetry

9/23/2013

Shorter horizontal reach

LoweredRestraint bars(clear mezz, south)

Center sections(independent removal)

Add Hall floor(no leg splices, shorter leg)

New leg arrangement

Page 4: MICE Partial Return Yoke PRY Fabrication

49/23/2013

Tie-down bar apertures repositioned

Waveguide slots to be angled upward

Crossbar positions not final

Page 5: MICE Partial Return Yoke PRY Fabrication

5

Bolted leg-channel connections

9/23/2013

Rail is now intermittent

Jacking screw for disassembly (3)

Page 6: MICE Partial Return Yoke PRY Fabrication

69/23/2013

LC

3306 kg

3490 kg

6-Section Design

1807 kg

1380 kg

4°taper

Lighter color indicates machined areas

Page 7: MICE Partial Return Yoke PRY Fabrication

7

Fabrication Cost & Procurement Status

• JFE steel order (JFE, Kurashiki, Japan)– 100 mm thick main plates, 50 mm backing plates– Steel of magnetic uniformity– Material total ~$70,000 for 12 plates (8 end, 4 ctr, 8 backing plates)– Delivery: ~16 weeks

• Machining– Separate vendor, to be identified– ~$2850, each plate

• Framework drawings– Some dwgs. out for quotation– 3 suppliers queried– Awaiting responses

9/23/2013

Page 8: MICE Partial Return Yoke PRY Fabrication

8

Work to complete • Modifications to shielding plates

– Reposition crossbars– Virostek plate extension mounts and flux leakage mitigation parts– Finalize position and size of slots for tracker waveguides (angled, not

normal to surface)– Add drilled/tapped holes for bolted connections, hoist rings, crossbar

mounts– Assembly and detail drawings for all of the above items

• Deflection/Stress Analysis– Recheck new model in ANSYS Workbench– No surprises expected, but need verification

• Structural Framework– Assembly and detail drawings for restraints bars & lower support arms

9/23/2013

Page 9: MICE Partial Return Yoke PRY Fabrication

9

BACK-UP INFORMATION

9/23/2013

Page 10: MICE Partial Return Yoke PRY Fabrication

10

Assembly Procedure(in progress)

9/23/2013

Page 11: MICE Partial Return Yoke PRY Fabrication

11

Install Section 1

Machined surfaceson channelmate to pink bar

Section 2 is similarly installed

Hoist ring spacer provides correct tilt

Clearance to back of channel

Hoist ring

9/23/2013

NOTE: Slides 11-14 show old design, but technique remains current

Page 12: MICE Partial Return Yoke PRY Fabrication

12

Install Section 3 (and 4)

Lower hoist rings removed;

guide blocks installed

(also shown on isometric, Slide #4)

Plate guided into engagement

during lowering

9/23/2013

Page 13: MICE Partial Return Yoke PRY Fabrication

13

Install Restraint Bars

9/23/2013

All beam-to-channel connections will also be bolted

Page 14: MICE Partial Return Yoke PRY Fabrication

14

(Assembly Technique – continued)

• … Install Virostek plate extensions• Install spectrometer solenoids and AFC• Build and install shielding on north side, same technique as

south side• Install north/south load-sharing cross bars

9/23/2013