The Main Sites of Activity During the Rising. Jacob's Biscuit Factory ...
PROPOSED UPGRADING OF THE HILLVIEW SEWER RISING MAIN … · Table 6 Sample types being monitored by...
Transcript of PROPOSED UPGRADING OF THE HILLVIEW SEWER RISING MAIN … · Table 6 Sample types being monitored by...
CITY OF MHLATHUZE MUNICIPALITY
INTEGRATED WATER AND WASTE MANAGEMENT PLAN
PROPOSED UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER
PIPELINE IN EMPANGENI, CITY OF UMHLATHUZE MUNICIPALITY, KWAZULU-NATAL
WATER USE LICENCE APPLICATION
Prepared for: Prepared by:
City of uMhlathuze Municipality ACER (Africa) Environmental Consultants
Private Bag X1004 PO Box 503
Richards Bay Mtunzini
3900 3867
February 2017
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENCE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
ii
EXECUTIVE SUMMARY
PURPOSE OF THE IWWMP
In terms of Chapter 4 of the National Water Act, 1998 (Act No 36 of 1998) (NWA), the City of
uMhlathuze is required to apply for water uses in terms of Section 21 of the NWA for construction
activities associated with the upgrading of the Hillview rising main and southern bulk outfall sewer
pipelines, in Empangeni. The existing rising gravity main pipelines are old and operating beyond
capacity resulting in frequent localized sewage overflows and spills.
NEW WATER USES
This application is for the authorisation of water uses in terms of section 21 (c) and (i), required for the
upgrading of the Southern Outfall Sewer System, which will require activities through and within 500m
of a number of wetlands and the Mpangeni River. The water uses below are applicable for the Water
Use Authorisation.
21 (c) impeding or diverting the flow of water in a watercourse:
For construction activities which will take place through parts of and within 500 m of Wetlands
1, 2, 3, 4, 5 and 10 and across the Mpangeni River.
21 (i) altering the bed, banks, course or characteristics of a watercourse;
For construction activities which will take place through parts of and within 500 m of Wetlands
1, 2, 3, 4, 5 and 10 and across the Mpangeni River.
PROJECT MOTIVATION
The proposed upgrade of the Southern Outfall Sewer System in Empangeni is viewed as a necessity.
At present, the existing rising main and the gravity outfall pipelines are old and operating beyond
capacity. As a result, the system is subject to frequent localized sewage overflows and spills, which
left as is, will lead to environmental, public health and safety hazards.
Given the current and planned future development within this area of Empangeni, and the expected
resultant increase in sewerage output, the overflow and spills are expected to become more frequent
and severe. The City of uMhlathuze has, therefore, seen it essential to install an entirely new rising
main and gravity main pipelines of a suitable size to cope with the current and future planned sewer
volumes.
IDENTIFICATION OF IMPACTS
The proposed development is an upgrade of existing infrastructure, taking place, for the most part,
within an existing servitude; therefore negative impacts of high significance are not anticipated.
However, the pipeline does for the most part fall within wetlands and riparian areas on its journey from
the Hillview Pump Station to the Empangeni Waste Water Treatment Works. Therefore potential
impacts will include the disturbance and loss of indigenous vegetation and wetland habitats,
increased surface runoff and the potential pollution of surface and ground water. The loss of
vegetative cover could encourage alien invasive plant species to spread, increase soil erosion,
contaminate and ultimately change the hydrology and resultant diversity of the wetland environments.
These impacts will need to be mitigated and managed, to minimise their long term affect on the
natural environment.
CONCLUSION
The City of uMhlathuze Municipality undertakes to comply with the relevant legislation applicable to
the project, in particular the NWA and applicable Regulations of this Act, as well as the project
Environmental Management Programme (EMPr) and recommendations contained within this
Integrated Water and Waste Management Plan. The Environmental Assessment Practitioner
therefore recommends approval of the proposed project, on condition that all applicable commitments
are adhered to.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENCE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
iii
ABBREVIATIONS AND ACRONYMS
ACER ACER (Africa) Environmental Consultants
Amafa Amafa aKwaZulu-Natali
BA Basic Assessment
DEDTEA Department of Economic Development, Tourism and Environmental Affairs
DAFF Department of Agriculture, Forestry and Fisheries
DOT Department of Transport
DWS Department of Water and Sanitation
EA Environmental Authorisation
ECO Environmental Control Officer
EIA Environmental Impact Assessment
EIS Ecological Importance and Sensitivity
EMPr Environmental Management Programme
EKZNW Ezemvelo KwaZulu-Natal Wildlife
HDPE High Density Polyethylene
I&APs Interested and Affected Parties
IDP Integrated Development Plan
IWULA Integrated Water Use Licence Application
IWWMP Integrated Water and Waste Management Plan
KZN KwaZulu-Natal
NEMA National Environmental Management Act
NEMWA National Environmental Management Waste Act
NFA National Forests Act
NWA National Water Act
PES Present Ecological State
PPP Public Participation Process
RE Resident Engineer
SWMP Storm Water Management Plan
WQMP Water Quality Monitoring Program
WULA Water Use Licence Application
WUL Water Use Licence
WWTW Waste Water Treatment Works
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENCE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
iv
TABLE OF CONTENTS
EXECUTIVE SUMMARY ........................................................................................................................ ii ABBREVIATIONS AND ACRONYMS .....................................................................................................iii TABLE OF CONTENTS ......................................................................................................................... iv LIST OF FIGURES ................................................................................................................................. vi LIST OF TABLES ................................................................................................................................... vi 1. INTRODUCTION .......................................................................................................................... 7
1.1 Activity background ............................................................................................................ 7 1.2 Contact Details ................................................................................................................. 10 1.3 Regional setting and location of activity ........................................................................... 10 1.4 Property description .......................................................................................................... 10 1.5 Purpose of the IWWMP .................................................................................................... 11
2. CONTEXTUALISATION OF THE ACTIVITY .............................................................................. 12 2.1 Description of activity ........................................................................................................ 12 2.2 Extent of the activity ......................................................................................................... 13 2.3 Key activity related processes and products .................................................................... 13 2.4 Activity life description ...................................................................................................... 14 2.5 Activity infrastructure description ...................................................................................... 15 2.6 Key water uses and waste streams .................................................................................. 16 2.7 Organisational structure of activity / company .................................................................. 20 2.8 Business and corporate policies related to the environment ............................................ 21
3. REGULATORY WATER AND WASTE MANAGEMENT FRAMEWORK ................................... 22 3.1 Summary of all water uses ............................................................................................... 22 3.2 Existing lawful water uses ................................................................................................ 25 3.3 Relevant exemptions ........................................................................................................ 25 3.4 Generally authorised water uses ...................................................................................... 25 3.5 New water uses to be authorised ..................................................................................... 26 3.6 Waste management activities (NEMWA) ......................................................................... 29 3.7 Waste related authorisations ............................................................................................ 29 3.8 Other authorisations (EIAs, EMPrs, EAs, Regulations) ................................................... 29
4. PRESENT ENVIRONMENTAL SITUATION............................................................................... 30 4.1 Climate .............................................................................................................................. 30 4.2 Surface water .................................................................................................................... 31 4.3 Socio-economic environment ........................................................................................... 33
5. ANALYSIS AND CHARACTERISATION OF ACTIVITY ............................................................ 35 5.1 Site delineation for characterisation ................................................................................. 35 5.2 Storm water (clean and dirty water management) ........................................................... 36 5.4 Monitoring and Control ..................................................................................................... 41 5.5 Risk Assessment / Best Practice Assessment ................................................................. 43 5.6 Issues and responses from public consultation process .................................................. 45 5.7 Matters requiring attention / problem statement ............................................................... 46 5.8 Assessment of level of confidence of information ............................................................ 46
6. WATER AND WASTE MANAGEMENT ...................................................................................... 47 6.1 Water and Waste Management Philosophy ..................................................................... 47 6.2 Options Analyses and motivation for implementation of preferred option ........................ 47 6.3 IWWMP Action Plan (Priority Actions) .............................................................................. 48 6.4 Control and Monitoring ..................................................................................................... 51
7. CONCLUSION ............................................................................................................................ 54 7.1 Regulatory status of activity .............................................................................................. 54 7.2 Statement on water uses requiring authorisation, dispensing with licensing requirement
and possible exemption from regulations ......................................................................... 54 7.3 Motivation in terms of section 27(1) of the NWA .............................................................. 54
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENCE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
v
7.4 Key Commitments ............................................................................................................ 57 8. REFERENCES ........................................................................................................................... 58 9. LIST OF APPENDICES .............................................................................................................. 59
Appendix 1 – Applicants Company Registration Certificate ....................................................... 59 Appendix 2 – Property Title Deeds ............................................................................................. 59 Appendix 3 – Lease Agreements (N/A) ...................................................................................... 59 Appendix 4 – Property Zoning Documents ................................................................................. 59 Appendix 5 – Land Claims Clearance Letter .............................................................................. 59 Appendix 6 – BBEEE Certificate ................................................................................................. 59 Appendix 7 – DWS Application Forms........................................................................................ 59 Appendix 8 – Site Plans and Maps ............................................................................................. 59 Appendix 9 – Master Layout Plan ............................................................................................... 59 Appendix 10 – Alternatives Report ............................................................................................. 59 Appendix 11 – Basic Assessment Report................................................................................... 59 Appendix 12 – Environmental Authorisation ............................................................................... 59 Appendix 13 – Environmental Management Programme ........................................................... 59 Appendix 14 – Wetland Studies .................................................................................................. 59 Appendix 15 – Geotechnical Report ........................................................................................... 59 Appendix 16 – Aquatic Ecology Report ...................................................................................... 59 Appendix 17 – Geohydrological Studies (N/A) ........................................................................... 59 Appendix 18 – Hydrological Studies ........................................................................................... 59 Appendix 19 – Water Balance (N/A) ........................................................................................... 59 Appendix 20 – Construction Methodology .................................................................................. 59 Appendix 21 – Storm Water Management Plan ......................................................................... 59 Appendix 22 – Civil Designs and Materials Test Report ............................................................ 59 Appendix 23 – Contingency Plans .............................................................................................. 59 Appendix 24 – Monitoring Programme ....................................................................................... 59 Appendix 25 – Financial Provision .............................................................................................. 59
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENCE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
vi
LIST OF FIGURES
Figure 1 General locality of Southern Outfall Sewer ........................................................................ 7 Figure 2 New servitude to be created on the east of MR230 to avoid residential properties through
which the existing rising main runs in a 3 m servitude ....................................................... 9 Figure 3 Gravity main realigned west of the existing servitude to significantly reduce the amount of
pipeline above ground, and bring it outside property boundaries ...................................... 9 Figure 4 New gravity main realigned to bring it outside the property boundaries along Sigma
Crescent ............................................................................................................................. 9 Figure 5 Google Earth aerial photo series showing wetlands and riparian areas found within the
area of interest (1 of 3) ..................................................................................................... 17 Figure 6 Google Earth aerial photo series showing wetlands and riparian areas found within the
area of interest (2 of 3) ..................................................................................................... 18 Figure 7 Google Earth aerial photo series showing wetlands and riparian areas found within the
area of interest (3 of 3) ..................................................................................................... 19 Figure 8 Pipe crossing a steep embankment ................................................................................. 38 Figure 9 Pipe crossing minor drainage line or erosion gully ........................................................... 38 Figure 10 Moderate to steep sloping land causing runoff erosion hazard ........................................ 38 Figure 11 Waste Management Hierarchy ......................................................................................... 39
LIST OF TABLES
Table 1 Properties on which water uses associated with the upgrade of the Southern Outfall
Sewer will be registered ................................................................................................... 11 Table 2 List of applicable water uses to be authorised for the upgrading of the Southern Outfall
Sewer ................................................................................................................................ 26 Table 3 Listed Activities in terms of EIA Regulations .................................................................... 29 Table 4 Monthly rainfall figures for the Richards Bay area from 2010 to 2013 and the minimum,
maximum and average (mm) ............................................................................................ 31 Table 5 Anticipated impacts and proposed mitigation measures for wetlands and riparian areas44 Table 6 Sample types being monitored by WQMP ....................................................................... 53
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
7
EEEmmmpppaaannngggeeennniii
N
2
R34
R102
1. INTRODUCTION
1.1 Activity background
The City of uMhlathuze Municipality is in the process of upgrading the Southern Outfall Sewer
system, which currently serves the southern part of Empangeni. The upgrade requires the
installation of entirely new rising main and gravity outfall pipelines which will, for the most part
fall within the existing pipeline servitude, running from the recently upgraded Hillview Pump
Station, around the west of Empangeni and into the existing Empangeni Wastewater Treatment
Works, south of Empangeni. The pipeline will cross several major roads, wetlands and the
Mpangeni River along its route.
The project consists of a number of elements as described below.
1.1.1 Rising Main
The new 450 mm diameter sewer rising main, will run alongside the existing pipeline for
approximately half of the 1.5 km route, from the Hillview Pumping Station to the discharge
chamber. The section where the new rising main will not follow the route of the existing pipeline
is that which runs next to the R34 (Nkwanazi Street) in a 3 meter servitude through the gardens
of a number of residential properties. The use of a registered servitude which exists for 200
metres on the opposite side of the road, where properties have yet to be built, will be
uncomplicated. This servitude will however need to be extended by approximately 475 metres.
The rising main would then need to cross Nkwanazi Street using a trenchless method, where it
will re-enter and follow the existing servitude to the discharge chamber.
Figure 1 General locality of Southern Outfall Sewer
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
8
1.1.2 Gravity Main
The new 700 mm diameter gravity outfall foul sewer, will fall for the most part within the existing
servitude on its approximately 5.3 km journey from the discharge chamber around the west of
Empangeni and into the existing Empangeni Wastewater Treatment Works, south of
Empangeni. There are various sections, each with their own specific reasons where the new
pipeline will need to deviate from the existing servitude:
1.1.2.1 Elevated Pipe
In the vicinity of Schirra Road, the existing pipeline exists as an above ground steel pipe on
pipe supports, on which it crosses the channelled valley bottom Wetland 5 where it enters the
floodplain Wetland 1. Immediately after which the existing servitude runs through three
residential properties. By moving the pipeline west, significantly less of the pipeline will need to
be above ground and the new pipeline will be realigned to fall outside the property boundaries.
1.1.2.2 Sigma Crescent
At the most southerly end of Sigma Crescent, the existing pipeline servitude runs through
residential properties. The buildings on these properties are very close to the servitude and in
some cases have been extended over the pipeline. The route will be realigned in this area to
bring the pipeline outside the property boundaries. The registration of a new servitude will be
required in this area.
1.1.2.3 Existing servitude
From the record drawings, it appears the existing pipeline does not keep to one side of the
servitude but switches from one to the other along its length. This makes laying the proposed
pipeline within the existing servitude difficult as the new pipeline would have to cross the
existing one. As the proposed pipeline is up to 700 mm in diameter, crossing under existing
pipes would involve a significant increase in trench depth.
It is, therefore, proposed to widen the existing servitude where necessary to accommodate the
proposed pipeline. This will assist with allowing the existing pipeline to remain operational
during construction.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
9
SECTIONS OF PROPOSED PIPELINE THAT WILL DEVIATE FROM THE EXISTING
SERVITUDE
Existing Rising Main
Proposed Rising Main
Proposed Gravity Main
Existing Gravity Main
Existing Gravity Main
Proposed Gravity Main
WL 5
WL 1
WL 3
WL 2
Riparian Area 1
Figure 4 New gravity main realigned to bring it outside the property boundaries along Sigma
Crescent
Figure 2 New servitude to be created on the east of
MR230 to avoid residential properties through which the
existing rising main runs in a 3 m servitude
Figure 3 Gravity main realigned west of
the existing servitude to significantly reduce
the amount of pipeline above ground, and
bring it outside property boundaries
WL 3 WL 5
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
10
1.2 Contact Details
1.2.1 Application for water use licence as per NWA
Applicant: City of uMhlathuze Municipality
Contact: Bestman Mbhamali
Address: 5 Mark Strasse, Central Business District, Richards Bay
Postal: Private Bag X1004, Richards Bay, 3900
E-mail: [email protected]
Tel: 035 907 5463 / 083 635 0803
Fax: 035 907 5452
1.3 Regional setting and location of activity
Southern Outfall Sewer system runs from the Hillview Pump Station around the west of
Empangeni and into the existing Empangeni Wastewater Treatment Works, south of
Empangeni.
1.3.1 Magisterial District, Regional Services Council Authority, Water Management Area
Province: KwaZulu-Natal
Magisterial District: Lower uMfolozi
Local Municipality: City of uMhlathuze Local Municipality
District Municipality: uThungulu District Municipality
Water Management Area: W12H and W12F
1.3.2 Land tenure and use of immediately adjacent land
The land use of the pipeline alignment and land immediately adjacent is predominantly special
residential (~60 – 70 %) with a small amount being public open space (~5 %) and about 25 %
being DFA queries.
1.4 Property description
The proposed development will for the most part fall within the existing sewer servitude, where
the pipeline is forced to deviate from its current route new servitudes will be registered. As is
the case with a linear project of this nature, there are a large number of affected properties.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
11
Table 1 Properties on which water uses associated with the upgrade of the Southern Outfall Sewer
will be registered
Property Description Property Owner Applicable Water Uses
SGKEY ERF and Portion
N0GU00940000396000000 ERF 3960 Hlongwa T J & B B NM
Sections 21 (c) and (1)
N0GU00940000795700000 ERF 7957 Good Deborah Lyn Mrs
N0GU00940000316000000 ERF 3160 Schoeman Don M.
N0GU00940000395700000 ERF 3957
MDV Developments
Pietermaritzburg Pty Ltd
N0GU00940000395800000 ERF 3958
N0GU00940000395900000 ERF 3959
N0GU00940000395700000 ERF 3961
0GU00940000856100000 ERF 8561 New Housing Co M
N0GU00940000856200000 ERF 8562
N0GU00940000891700000 ERF 8917 Provincial Government
of Kwazulu-Natal N0GU00940000316900000 ERF 3169
N0GU00940000795600000 ERF 7956 Quandobyte
Investments (Pty)Ltd
N0GU00940000794800000 ERF 7948
uMhlathuze Municipality
N0GU00940000795500000 ERF 7955
N0GU00940000842100000 ERF 8421
N0GU00940000842200000 ERF 8422
N0GU00940000842300000 ERF 8423
N0GU00940000842400000 ERF 8424
N0GU00940000844600000 ERF 8446
N0GU00940000844900000 ERF 8449
N0GU00940000845300000 ERF 8453
N0GU01690000024600000 ERF RE/246
N0GU00940000795500000 ERF RE/7955
N0GU00940000317500000 ERF 3175
Vision Homes Pty Ltd N0GU00940000712100000 ERF 7121
N0GU00940000712200000 ERF 7122
1.5 Purpose of the IWWMP
This Integrated Water and Waste Management Plan (IWWMP) has been compiled in line with
the Operational Guideline: Integrated Water and Waste Management Plan (February 2010) for
the purpose of documenting all the relevant information required by DWS to enable decision-
making regarding the authorisation of the applicable water uses.
The IWWMP is a legally binding, site specific, implementable, action plan addressing all the
identified water use and waste management related aspects for the widening upgrading of the
Southern Outfall Sewer System. It is in essence a management plan to guide the water user
(City of uMhlathuze Municipality) regarding the water and waste related measures which must
be implemented on site during the construction, rehabilitation and operation phases of the
project.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
12
2. CONTEXTUALISATION OF THE ACTIVITY
2.1 Description of activity
The Applicant, the City of uMhlathuze Municipality, intends to upgrade the current Southern
Outfall Sewer system, which includes the rising main from the Hillview Pumping Station and the
gravity main to the Empangeni Waste Water Treatment Works. This present system is old and
undersized, and subject to frequent spillage and overflows of raw sewage.
The proposed new 450 mm diameter rising main will run largely alongside the existing pipeline,
within the existing 6 m servitude, from the Hillview Pumping Station for approximately 1.5 km to
an existing discharge chamber. The gravity outfall, a 700 mm foul sewer, will also fall for the
most part within an existing servitude and will run from the discharge chamber around the west
of Empangeni for approximately 5.3 km and discharge into the existing Empangeni Wastewater
Treatment Works, south of Empangeni.
2.1.1 Pipeline route
Although the proposed project is an upgrade of existing infrastructure and it would be
preferable to lay the new pipeline alongside the existing pipeline, this is not possible for the
entire route. There are various sections, each with their own specific reasons, where the new
pipeline will need to deviate from the existing servitude:
2.1.1.1 Rising Main
From the Hillview Pumping Station the new rising main will follow the existing servitude in
a westerly direction towards the R34 (Nkwanazi Street).
The existing servitude then crosses under and follows Nkwanazi Street in a 3 m
servitude that runs through the front gardens of a number of residential properties. It
would therefore be less complicated for the new pipeline to make use of a registered
servitude which exists for 200 m on the opposite side of the road; but which will need to
be extended by approximately 475 m.
The new rising main will then cross under Nkwanazi Street, using a trenchless method,
re-entering the existing servitude, which crosses under and follows the MR166, for the
remainder of its journey to the Discharge Chamber in the vicinity of Fukwe Street.
2.1.1.2 Gravity Main
The new gravity main will begin at the Discharge Chamber and remains within the
existing servitude, closely following the Mkumbane River until in the vicinity of Carsdale,
near the Gemini Drive crossing, where still within the existing servitude, the new pipeline
then leaves the Mkumbane River following the outer property boundaries around
Carsdale.
In the vicinity of Schirra Road, the existing gravity main exists as an above ground steel
pipe on pipe supports on which it crosses the channelled valley bottom Wetland 5.
Shortly after crossing Wetland 5 the existing servitude crosses through the corner of
three residential properties. By shifting this section of the new pipeline alignment west, a
significantly lesser amount of the pipeline will need to be above ground, and the new
pipeline will fall outside the property boundaries, after which it will re-enter the existing
servitude.
Continuing within the existing servitude, the gravity main traverses through the newly
built Richem Secondary School.
Immediately after Richem Secondary School, near the most southerly end of Sigma
Crescent, the existing gravity main runs through a number of residential properties. The
buildings on these properties are very close to the servitude and in some cases have
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
13
been extended over the existing pipeline. The new gravity main will thus be realigned in
these areas to bring it outside the property boundaries. As a result of this realignment a
section of the new pipe will be required to be above ground on pipe supports.
For the remainder of the gravity main alignment, the proposed alignment keeps within
the existing servitude before crossing the Mpangeni River using the existing pipe bridge
to enter the Empangeni Waste Water Treatment Works.
2.2 Extent of the activity
2.2.1 Construction servitude
Approximately 6.8 km of new pipe will need to be laid, mostly within the existing servitude, from
the Hillview Pumping Station around the west of Empangeni and into the existing Empangeni
Wastewater Treatment Works, south of Empangeni. The construction servitude will be up to 10
m wide in unrestricted areas and down to 6 m in restricted/sensitive areas (e.g. wetlands and
riparian areas along the Mkumbane and Mpangeni rivers)
2.2.2 Construction camp
A 2 hectare construction camp will be required for the duration of the construction period to
house administrative offices, construction plant and material stockpiles, fuels, storage facilities
and security guard accommodation.
2.2.3 Pipe storage yards
The main storage yard will be at the site camp; however one or two more may need to be
established at various locations along the pipeline route. The location of these storage yards
will need to be carefully selected by avoiding sensitive areas and through negotiations between
the contractor and affected landowners. Each pipe storage yard will be used until that particular
section of pipeline is complete. The pipe storage yards will be rehabilitated progressively
(fencing will be removed and the site will be reinstated with suitable vegetation, etc.).
2.3 Key activity related processes and products
An overview of the anticipated activities that will take place during the pre-construction,
construction, rehabilitation and operation phases of the Southern Outfall Sewer System is
described below.
2.3.1 Pre-construction Phase
Detailed layouts.
Register new servitudes
Detailed geotechnical investigations.
Obtaining of Environmental Authorisation and necessary permits and license.
Procurement process for Contractors.
Tender for various construction works.
Procurement of other necessary materials.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
14
2.3.2 Construction Phase
Appoint Environmental Control Officer (ECO).
Set up site camp with temporary offices, ablutions, access control, security; signage etc.
General materials storage and stockpile areas.
Construction of chemicals storage facilities (oil, grease, solvents, fuel etc.) and
associated infrastructure.
Temporary waste storage areas; these shall be established and managed in accordance
with Environmental management Programme (EMPr).
Sourcing of construction materials and equipment from existing lawful commercial
sources; no direct mining, harvesting or extraction of natural resources.
Removal of existing surfacing material.
Excavations and trenching for laying of pipes.
Horizontal drilling for trenchless road crossings.
Use of general mechanical equipment within construction areas (generators, cutting and
welding equipment, compressors etc.).
2.3.3 Rehabilitation Phase
Removal of temporary structures, infrastructures, stockpiles, waste and rubble.
Excavated material stockpiled within the servitude must be backfilled in the reverse order
from which it was removed viz. subsoil first followed by topsoil and finally the wetland
plants.
Final shaping of the construction site to ensure free flow of run-off and to prevent
damming of water.
Re-vegetation and planting by a suitably qualified Contractor.
Weed and invader plant control.
Monitoring of rehabilitated areas.
2.3.4 Operation Phase
The operation and maintenance of the Southern Outfall Sewer System will be the responsibility
of the City of uMhlathuze Municipality once construction is complete. Anticipated activities
include:
Operation and maintenance of infrastructure.
Ongoing consultation with directly affected parties.
Ongoing management and conservation of adjacent wetlands and other sensitive areas.
2.3.5 Decommissioning Phase
The decommissioning of the Southern Outfall Sewer System is not anticipated. However,
should decommissioning be required the activity will need to comply with the appropriate
environmental legislation and best practices at that time.
2.4 Activity life description
The project will consist of a construction period of approximately 12 months. The rehabilitation
of disturbed areas, where required, will occur concurrently with the construction.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
15
2.5 Activity infrastructure description
The proposed new 450 mm diameter rising main will run largely alongside the existing pipeline,
within the existing 6 m servitude, from the Hillview Pumping Station for approximately 1.5 km to
an existing discharge chamber. The gravity outfall, a 700 mm foul sewer, will also fall for the
most part within an existing servitude and will run from the discharge chamber around the west
of Empangeni for approximately 5.3 km and discharge into the existing Empangeni Wastewater
Treatment Works, south of Empangeni. Construction activities and infrastructure required will
include the following:
2.5.1 Construction camp
A 2-hectare construction camp will be required for the duration of the construction period to
house administrative offices, construction plant and material stockpiles, fuels, storage facilities
and security guard accommodation. Construction workers will not be accommodated at the
construction camp. It will be necessary to select an area that will have minimal environmental
impact, for which compensation may need to be paid. The logical place for this is the vacant
area within the Empangeni Waste Water Treatment Works. The Environmental Control Officer
(ECO) will need to approve the construction camp location.
A suitable number of chemical toilets must be provided on site for the construction staff. Solid
waste will be taken to the uThungulu landfill site in Empangeni.
2.5.2 Construction servitude
The construction servitude will be up to 10 m wide in unrestricted areas and down to 6 m in
restricted/sensitive areas (e.g. wetlands and the Riparian areas along the Mkumbane and
Mpangeni Rivers). All trees and vegetation will need to be removed within the 6 m servitude
area for the trenching and laying of pipes, after which, the area will be rehabilitated using
indigenous herbaceous vegetation with non-invasive root systems.
2.5.3 Pipe storage yards
The main storage yard will be at the site camp; however one or two more may need to be
established at various locations along the pipeline route. The location of these storage yards
will need to be carefully selected by avoiding sensitive areas and through negotiations between
the contractor and affected landowners. Each pipe storage yard will be used until that particular
section of pipeline is complete. The pipe storage yards will be rehabilitated when they are no
longer needed (fencing will be removed and the site will be reinstated with suitable vegetation,
etc.).
2.5.4 Access
The majority of the alignment is accessible via existing district, provincial and old farm roads
and maximum use will be made of existing access roads. During construction however, it may
be necessary to construct temporary access roads, the majority of which will fall within the
construction servitude. The temporary access roads will comprise a simple single lane track
immediately alongside the trench and will be cleared and roughly levelled for vehicular access.
Temporary access roads will have to be identified with the assistance of, and approved by, the
ECO and Resident Engineer (RE) so that they do not infringe on sensitive areas. The
temporary access tracks will be rehabilitated on a progressive basis during the construction
phase.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
16
2.6 Key water uses and waste streams
2.6.1 Key water uses
The key water uses for the upgrading of the Southern Outfall Sewer System are in terms of
section 21 (c) and (i) of the NWA:
Section 21(c) - Impeding or diverting the flow of water in a watercourse; “causing an
obstruction to the flow of water in a watercourse, or diverting some or all of the flow in or
from a watercourse”
Section 21(i) - Altering the bed, banks, course or characteristics of a watercourse; “any
changes affecting the morphology and topography of the watercourse including changes
affecting the riparian and instream habitat characteristics and the dynamics of a
watercourse.”
The following Section 21 (c) and (i) water uses apply for the upgrading of the Southern Outfall
Sewer System:
Section 21 (c) and (i) – For construction of the rising main through parts of Wetland 3.
Section 21 (c) and (i) – For construction of the rising main within 500 m of Wetland 2.
Section 21 (c) and (i) – For construction of the gravity main through parts of Wetland 1.
Section 21 (c) and (i) – For construction of the gravity main within 500 m of Wetland 10.
Section 21 (c) and (i) – For construction of the gravity main within 500 m of Wetland 4.
Section 21 (c) and (i) – For construction of the gravity main through parts of Wetland 5.
Section 21 (c) and (i) – For construction of the gravity main across the Mpangeni River.
Refer to Figure 5 below and the Master Layout Plan (Appendix 9) for a map of the wetland
areas identified with the study area.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
17
LEGEND
Wetland (W) – impacted by
pipeline construction
Wetland (W) – unlikely to be
affected by pipeline construction
Riparian Area (RA)
Pipeline upgrade
Existing pipeline
500 m buffer around pipeline
RA6
W3
W13
W14
W2
RA4
Figure 5 Google Earth aerial photo series showing wetlands and riparian areas found within the area of interest (1 of 3)
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
18
W1
RA5
W12
RA3
W1
W10
W4
Figure 6 Google Earth aerial photo series showing wetlands and riparian areas found within the area of interest (2 of 3)
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
19
RA2
W5
RA1
W6
W7
W9
W11
W8
Figure 7 Google Earth aerial photo series showing wetlands and riparian areas found within the area of interest (3 of 3)
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
20
2.6.2 Waste streams
No waste streams will be generated during the operation of the Southern Outfall Sewer
System, however the following measures must be in place for waste related activities during
construction:
2.6.2.1 Ablution facilities
An adequate number of ablution facilities must be available and not further that 200m
from the construction working area.
Ablution facilities must be situated well above the 1:100 year floodlines and outside
buffer areas around wetlands and riparian areas.
Ablutions must be cleaned/ emptied on a regular basis to avoid contamination of the
environment.
2.6.2.2 Wastewater
Wastewater must not be disposed of into wetlands or any nearby surface water bodies.
All waste water during construction must be disposed at an approved waste disposal
site. Waste disposal slips are to be obtained and kept on site at all times.
Ablution facilities shall be regularly emptied by a reputable service provider.
2.6.2.3 Solid waste
All construction waste such as rubble, cement bags, waste cement, timber, can, other
containers, wire and nails must be collected and stored in designated and demarcated
areas in skips and/or bins.
Waste that is recyclable is to be recycled and separated at site.
Refuse which cannot be recycled shall be disposed of at the nearest DWS-licensed
waste disposal facility within the region (uThungulu regional landfill site in Empangeni).
2.6.2.4 Hydrocarbon and Hazardous waste
All potential hazardous wastes generated at the site must be removed and disposed by
an approved contractor.
Potentially hazardous raw and waste materials shall be handled and stored on-site in
accordance with the manufacturer's specification and relevant legal requirements.
All hydrocarbon (e.g. fuel, oils and contaminated soil/materials) and other hazardous
waste resulting from spills, refuelling and maintenance activities shall be disposed of in a
formally licensed hazardous waste site or, where possible, be removed and disposed by
an approved contractor.
The Contractor shall provide Safe Disposal Certificates to the Construction Safety Officer
and ECO. Safe Disposal Slips shall be kept onsite for record purposes at all times.
Further details on waste management are provided in the Environmental Management
Programme (Appendix 13).
2.7 Organisational structure of activity / company
The City of uMhlathuze Municipality was established on 5th December 2000 after the
demarcation process and the local government elections of that date. As such it encompasses
the towns of Empangeni, Richards Bay, eSikhaleni, Ngwelezane, eNseleni, Vulindlela and
Felixton as well as the Traditional Authority areas under Amakhosi Dube, Mkhwanazi, Khoza,
Mbuyazi and Zungu. The uMhlathuze Local Municipality has been divided into 30 municipal
wards.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
21
2.7.1 Vision
The City of uMhlathuze, as a port city, will offer improved quality of life for all its citizens through
sustainable development. It will be a renowned centre for: Trade, Tourism and Nature-lovers,
Coastal Recreation, Commerce, Industry, Forestry, and Agriculture.
2.7.2 Mission
To develop uMhlathuze as the industrial, commercial and administrative centre within the
natural beauty of the region. Providing a range of efficient municipal services, thereby ensuring
economic development, dynamic investment growth and an improvement in the quality of life
for all.
2.7.3 Department of Infrastructure and Technical Services
The Department Infrastructure and Technical Services in the Municipality is charged with the
responsibility to ensure inter alia provision, development, extension and maintenance of
infrastructural networks and bulk supplies. This is response to the Constitutional mandate of
provision of services to communities in a sustainable manner and promotion of safe and
healthy environment.
2.8 Business and corporate policies related to the environment
The City of uMhlathuze has identified and prioritized the following as key to meeting its
environmental targets and objectives:
To ensure legal compliance of environmental bylaws and legislative requirements by all
(Council, Employees, Contractors).
To ensure sufficient suite of local environmental bylaws and effective enforcement
thereof.
Regulation of land use and enforcement of usage of land in terms of the town planning
scheme and land use management system.
To minimize air pollution (prevention and reduction) in the City of uMhlathuze through
efficient monitoring.
To reduce overall water pollution within the municipality as a result of land use practices
through monitoring hotspots and imposing stringent requirements during EIA and
planning processes.
To ensure management of all water resources in a sustainable manner by adhering to
lake management plans and water services bylaws.
To ensure the management of soil and land resources in a sustainable manner through
environmental and land use planning.
To ensure the protection of habitats and natural resources that would contribute to
conservation targets of the province.
To preserve heritage resources by preventing damage and loss through development
planning processes and through the tourism sector.
Complying with the provisions of the National Environmental Management: Integrated
Coastal Management Act.
Maintaining the biological diversity and productivity of coastal ecosystems through
implementation of coastal management programme and estuary management plans.
To comply with the provisions of National Environmental Management: Waste Act by
appointment of a waste management officer and compilation of a waste management
plan for the City of uMhlathuze.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
22
To improve energy efficiency of existing facilities and reducing demand in terms of the
strategy set out in the energy sector plan, and facilitating renewable energy/co-
generation initiatives and projects.
To be prepared and anticipate disaster management within the municipality.
To ensure that the municipality maintains its environmental assets through environmental
tools such as project specific EIA’s, the EMF and the Environmental Framework of the
SDF.
To increase the knowledge and understanding, and prepare for vulnerability to
environmental changes within the municipality.
3. REGULATORY WATER AND WASTE MANAGEMENT FRAMEWORK
3.1 Summary of all water uses
Construction for the upgrading of the Southern Outfall Sewer System will involve the laying of
entirely new rising main and gravity main pipelines through parts of and within 500 m of several
wetlands, and across the Mpangeni River.
In terms of the NWA these activities constitute Section 21 (c) and (i) water uses for impeding or
diverting the flow of water in a watercourse; and altering the bed, banks, course or
characteristics of a watercourse. The applicant is therefore required to apply for a licence to use
water in terms of these sections as set out in Sections 40 (1) and 41 of the NWA. A summary of
the wetlands and watercourses assessed and the water uses applied for in this IWWMP is
provided below:
3.1.1 Wetland 1
Wetland 1 is described as a floodplain wetland with a Present Ecological State (PES) falling
within category C (Moderately Modified) and an Ecological Importance and Sensitivity (EIS)
category of B (High). The floodplain wetland is closely associated with the banks Mkumbane
River, and approximately 2, 952 m of the new Gravity Main will be constructed through the
delineated wetland area.
A section 21 (c) and (i) water use has therefore been applied for construction through parts of
and within 500 m of this wetland.
3.1.2 Wetland 2
Wetland 2 is a valley bottom wetland with a channel, with a PES category of C (Moderately
Modified) and an EIS of C (Moderate). The new Rising Main will be constructed within 27 m of
the delineated edge of the wetland.
A section 21 (c) and (i) water use has therefore been applied for construction within 500 m of
this wetland.
3.1.3 Wetland 3
Wetland 3 is a valley bottom wetland with a channel with a PES category of C (Moderately
Modified) and an EIS of C (Moderate). The new Rising Main will be constructed through
approximately 197 m of the delineated wetland area.
A section 21 (c) and (i) water use has therefore been applied for construction through parts of
and within 500 m of this wetland.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
23
3.1.4 Wetland 4
Wetland 4 is a valley bottom wetland with a channel with a PES falling within category E (only
some remaining natural habitat features) and an EIS of C (Moderate). The new Gravity Main
will be constructed within 5 m of the edge of the delineated wetland area.
A section 21 (c) and (i) water use has therefore been applied for construction within 500 m of
this wetland.
3.1.5 Wetland 5
Wetland 5 is a valley bottom wetland with a channel with a PES falling within category E (only
some remaining natural habitat features) and an EIS of C (Moderate). Approximately 18 m of
the new Gravity Main will be constructed across the delineated wetland area.
A section 21 (c) and (i) water use has therefore been applied for construction through parts of
and within 500 m of this wetland.
3.1.6 Wetland 6
Wetland 6 is largely an artificial pond excavated out of the floodplain of the Empangeni River.
Although it is an aquatic ecosystem, this system is essentially artificial in nature and use of the
Wet-EcoServices and Wet-Health systems to obtain PES and EIS are unlikely to provide
meaningful results.
The wetland is located approximately 160 m south of new Gravity Main, and on the opposite
bank of the Mpangeni River. It is highly unlikely that the new Gravity Main will impact on the
resource quality of the wetland therefore no water use has been applied for.
3.1.7 Wetland 7
Wetland 7 is a valley bottom wetland with a channel, with a PES category of C (Moderately
Modified).
The wetland is located approximately 70 m south of new Gravity Main, and on the opposite
bank of the Mpangeni River. It is highly unlikely that the new Gravity Main will have any impact
on the resource quality of the wetland therefore no water use has been applied for.
3.1.8 Wetland 8
Wetland 8 is a valley bottom wetland with a channel, with a PES category of C (Moderately
Modified).
The wetland is located approximately 150 m upstream of where the new Gravity Main will cross
the Mpangeni River to enter the Empangeni Waste Water Treatment Works. It is highly unlikely
that the new Gravity Main will have any impact on the resource quality of the wetland therefore
no water use has been applied for.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
24
3.1.9 Wetland 9
Wetland 9 is a valley bottom wetland with a channel, with a PES category of C (Moderately
Modified).
The wetland is located approximately 229 m upstream of where the new Gravity Main will cross
the Mpangeni River to enter the Empangeni Waste Water Treatment Works. It is highly unlikely
that the new Gravity Main will have any impact on the resource quality of the wetland therefore
no water use has been applied for.
3.1.10 Wetland 10
Wetland 10 is a valley bottom wetland with a channel with a PES of D (Largely Modified) and
an EIS of C (Moderate). The new Gravity Main will be constructed within 3 m of delineated
wetland area.
A section 21 (c) and (i) water use has therefore been applied for construction through parts of
and within 500 m of this wetland.
3.1.11 Wetland 11
Possible floodplain wetland area, likely to have experienced historic soil disturbance and is
currently used as a grassed lawn which is regularly mowed for used as a recreational area.
The wetland is located approximately 306 m upstream of where the new Gravity Main will cross
the Mpangeni River to enter the Empangeni Waste Water Treatment Works. It is highly unlikely
that the new Gravity Main will have any impact on the resource quality of the wetland therefore
no water use has been applied for.
3.1.12 Wetland 12
Wetland 12 is a hillslope seepage wetland, with a PES of D (Largely Modified).
The wetland is located approximately 310 m away and upslope of the new Gravity Main and
separated by President Swart Avenue. It is highly unlikely that the new Gravity Main will have
any impact on the resource quality of the wetland therefore no water use has been applied for.
3.1.13 Wetland 13
Wetland 13 is a valley bottom wetland with a channel with a PES of E (only some remaining
natural habitat features).
The wetland is located approximately 292 m away and upslope of the new Rising Main and
separated by Nkwanazi and Gwalagwala Streets. It is highly unlikely that the new Rising Main
will have any impact on the resource quality of the wetland therefore no water use has been
applied for.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
25
3.1.14 Wetland 14
Wetland 14 is a valley bottom wetland with a channel with a PES of E (only some remaining
natural habitat features).
The wetland is located approximately 205 m away and upslope of the new Rising Main and
separated by Nkwanazi and Gwalagwala Streets. It is highly unlikely that the new Rising Main
will have any impact on the resource quality of the wetland therefore no water use has been
applied for.
3.1.3 Mkumbane River – Riparian Area Crossing (Riparian Area 1)
As a result of the realignment of the gravity main pipeline, to bring the new pipeline to the
outside of the boundaries of the properties along Sigma Crescent, approximately 44 m of the
new Gravity Main will need to cross a section of the riparian area associated with the
Mkumbane River.
A section 21 (c) and (i) water use has therefore been applied for the crossing of the delineated
riparian area.
3.1.3 Mpangeni River Crossing (Riparian Area 2)
The new Gravity Main will need to cross the Mpangeni River, on the existing concrete pipe
supports, in order to enter the Empangeni Waste Water Treatment Works.
The riparian habitat through which the Gravity Main will cross has been identified as the
Syzygium cordatum – Bridelia micrantha riverine community (ACER 2014). Although comprised
of mostly early successional trees and shrubs together with alien invasive vegetation due to its
location along the existing sewer pipeline and/or along existing housing infrastructure this
riparian vegetation performs important ecological functions including river bank stabilisation and
flood protection; and also provide important refugia for fauna in the area. In addition, rivers are
considered important movement corridors or ecological linkages within a landscape.
A section 21 (c) and (i) water use has therefore been applied for the crossing of the Mpangeni
River and the associated delineated riparian area.
3.2 Existing lawful water uses
Not applicable, no lawful water uses exist for the existing or proposed infrastructure.
3.3 Relevant exemptions
No exemptions applicable for the upgrading of the Southern Outfall Sewer, or are included in
this application.
3.4 Generally authorised water uses
No generally authorised water uses exist for the upgrading of the Southern Outfall Sewer or are
included in this application.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
26
3.5 New water uses to be authorised
Table 2 List of applicable water uses to be authorised for the upgrading of the Southern Outfall Sewer
No. Water Use HGM Unit Purpose PES EIS Volume / Dimensions Property Description Property Owner Coordinates
1 Section 21
(c) and (i)
Wetland 1
Floodplain
Construction of Gravity
Main pipeline through
and within 500 m of
Wetland 1
C B
2,952 m of Gravity
Main pipeline through
Wetland 1
ERF 8449
uMhlathuze Municipality
Start –
28°44'33.02"S
31°52'53.92"E
ERF 8424
ERF 8453
ERF 8423
ERF 8422
ERF 8421
ERF 8446
ERF 3960 Hlongwa T J & B B NM.
ERF 3959
MDV Developments
Pietermaritzburg Pty Ltd
ERF 3958
ERF 3957
ERF 3961
End –
28°46'14.48"S
31°53'29.91"E
ERF 7956 Quandobyte Investments
(Pty)Ltd
ERF 8917 Provincial Government KZN
ERF 3169
ERF 8561 New Housing Co M
ERF 8562
ERF 7957 Good Deborah Lyn Mrs
ERF 3160 Schoeman, Don,M.
(Richem Secondary School)
ERF 3175
Vision Homes Pty Ltd M ERF 7122
ERF 7121
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
27
2 Section 21
(c) and (i)
Wetland 2
Valley Bottom
(Channelled)
Construction of Rising
Main within 500 m of
Wetland 2
C C
Rising Main pipeline 27
m from edge of
Wetland 2
ERF 7955
uMhlathuze Municipality
Start –
28°44'17.12"S
31°52'51.18"E ERF 7948
End –
28°44'33.02"S
31°52'53.93"E ERF 8449
3 Section 21
(c) and (i)
Wetland 3
Valley Bottom
(Channelled)
Construction of Rising
Main through and
within 500 m of
Wetland 3
C C
197 m of Rising Main
pipeline through
Wetland 3
RE/7955 uMhlathuze Municipality
Start –
28°44'0.26"S
31°52'55.08"E
End –
28°44'24.98"S
31°52'54.70"E
4 Section 21
(c) and (i)
Wetland 4
Valley Bottom
(Channelled)
Construction of Gravity
Main within 500 m of
Wetland 4
E C
Gravity Main pipeline 5
m from edge of
Wetland 4
ERF 8562 New Housing Co M Start –
28°45'46.08"S
31°53'2.66"E ERF 8917 Provincial Government KZN
End –
28°45'46.44"S
31°53'4.09"E ERF 3175 Vision Homes Pty Ltd
5 Section 21
(c) and (i)
Wetland 5
Valley Bottom
(Channelled)
Construction of Gravity
Main through and
within 500 m of
Wetland 5
E C
18 m of Rising Main
pipeline through
Wetland 5
ERF 3175 Vision Homes Pty Ltd
Start –
28°45'52.34"S
31°53'10.03"E
End –
28°45'52.88"S
31°53'10.24"E
6 Section 21
(c) and (i)
Wetland 10
Valley Bottom
(Channelled)
Construction of Gravity
Main within 500 m of
Wetland 10
D C
Gravity Main pipeline 3
m from edge of
Wetland
ERF 8917 Provincial Government KZN
Start –
28°45'37.47"S
31°52'43.70"E
End –
28°45'38.79"S
31°52'46.45"E
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
28
7 Section 21
(c) and (i)
Riparian Area 1
(Mkumbane
River)
Construction of Gravity
Main across the
Riparian Area 1
Gravity Main pipeline
across a section of the
riparian area
associated with the
Mkumbane River.
ERF 7121 Vision Homes Pty Ltd
Start –
28°46'13.05"S
31°53'36.67"E
ERF 3175 Vision Homes Pty Ltd
End –
28°46'12.30"S
31°53'38.07"E
8 Section 21
(c) and (i) Mpangeni River
Construction of Gravity
Main across the
Mpangeni River
Gravity Main through
riparian area and
across the Mpangeni
River.
ERF RE/246 uMhlathuze Municipality
Start –
28°46'17.32"S
31°53'54.81"E
End –
28°46'22.81"S
31°53'53.55"E
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
29
3.6 Waste management activities (NEMWA)
The National Environmental Management: Waste Act, Act 59 of 2008 (NEMWA) follows the
principle that waste generation be avoided, or if it cannot be avoided, that it is reduced, re-
used, recycled or recovered, and as a last resort treated and/or safely disposed of.
No waste management activities NEMWA are required for the upgrading of the Southern Outfall
Sewer System.
3.7 Waste related authorisations
No waste related authorisations are required for the upgrading of the Southern Outfall Sewer
System.
3.8 Other authorisations (EIAs, EMPrs, EAs, Regulations)
3.8.1 Environmental Authorisation (Basic Assessment)
Environmental Authorisation (EA) for the upgrading of the Hillview sewer rising main and
southern outfall bulk sewer pipeline, in Empangeni was issued by the KZN DEDTEA on 6th
August 2015, following a Basic Assessment conducted by ACER (Appendix 11).
Environmental Authorisation via a Basic Assessment (BA) was required as the upgrading of the
Southern Outfall Sewer System triggered activities in both Listing Notice 1 and 3 of the
Environmental Impact Assessment (EIA) Regulations (Government Notice R.543 of 18 June
2010).
Table 3 Listed Activities in terms of EIA Regulations
Activity No (s) (in terms of the
relevant or notice)
Description of each listed activity as per the project description
(and not as per wording of the relevant Government Notice)
Activity 9 of Listing Notice 1: No.
R. 544 of June 2010
The laying of a 0.45 m diameter, rising main pipeline of
approximately 1,500 m in length and; a 0.7 m diameter, gravity main
of approximately 5,300 m, for the bulk transportation of sewage.
The route which will run largely within the servitudes of the existing
pipeline, will however cross several major roads as well as several
streams and the need to establish new servitudes in some places is
likely.
Activity 11 of Listing Notice 1:
No. R. 544 of June 2010
The laying of approximately 6,800 m of pipeline will fall mostly within
an existing servitude however the need to cross several streams and
establish new servitudes within 32 m of a watercourse is likely.
Activity 18 of Listing Notice 1:
No. R. 544 of June 2010
The laying of approximately 6,800 m of pipeline will fall mostly within
an existing servitude however the need to cross several streams in
an above ground steel pipe on pipe supports, will likely result in the
infilling or depositing of material of more than 5 m3 into the
respective watercourse.
Activity 12 of Listing Notice 3:
No. R. 546 of June 2010
The need to widen existing and establish new servitudes in certain
areas, will likely result in the clearance of vegetation where 75% or
more of the vegetative cover constitutes indigenous vegetation.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
30
3.8.2 Licence to destroy Natural Forests and Protected Trees or Plants
According to section 15(1) of the National Forests Act, 1998 (Act 84 of 1998), no person may
cut, disturb, damage, destroy, possess, collect, remove, transport, export, purchase, sell,
donate or in any other manner acquire or dispose of any protected tree or any forest product
derived from a protected tree except under a licence or exemption granted by the Minister of
the Department of Agriculture, Forestry and Fisheries (DAFF).
The vegetation and wetland Assessment (ACER, 2014) recommends that even though the site
has experienced disturbance in the past, a search and rescue operation must undertaken prior
to construction to find any Threatened or Protected species or any other species of concern,
particularly in the riparian habitats.
Following the identification of threatened or protected species, the relevant licence applications
must be submitted to DAFF or Ezemvelo KZN Wildlife (EKZNW), and the licence granted
before construction can commence.
4. PRESENT ENVIRONMENTAL SITUATION
4.1 Climate
4.1.1 Regional Climate
The City of uMhlathuze is characterized by a warm to hot and humid subtropical climate, with
warm moist winters. Average daily maximum temperatures range from 29ºC in January to 23ºC
in July, and extremes can reach more than 40 ºC in summer. The average annual rainfall is
1228mm most of which falls in the summer, from October to March. Extreme rainfall and
thundershowers are occasional occurrences in the Zululand Region, resulting in extensive
flooding.
4.1.2 Rainfall
The average annual rainfall is 1 228 mm and most (~80%) of the rainfall occurs in the summer,
from October to March, although rainfall also occurs in winter (~20%) (uMhlathuze Local
Municipality , 2015).
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
31
Table 4 Monthly rainfall figures for the Richards Bay area from 2010 to 2013 and the minimum,
maximum and average (mm)
Month 2011 2012 2013
January 150.8 54.0 177.8
February 59.4 118.0 122.4
March 78.2 245.2 97.4
April 138.4 49.6 50.6
May 40 15.4 111.6
June 42 43.2 49.2
July 130.2 16.0 27.4
August 39.2 15.8 38.4
September 73.6 206.8 62.0
October 91.2 139.6 137.4
November 119.4 97.2 57.0
December 102.8 158.8 119.4
Minimum 39.2 15.4 27.4
Average 88.8 96.6 87.6
Maximum 150.8 245.2 177.8
4.1.3 Evaporation
Evaporation in the region exceeds the annual precipitation (Germishuyse, 1999), with estimates
ranging between 1300 to 1400 mm/year.
4.2 Surface water
4.2.1 Water Management Area
The Southern Outfall Sewer System spans across two quarternary drainage regions, W12F and
W12H of the Usutu to Mhlathuze Water Management Area.
The Mhlathuze catchment is the most developed catchment in the Usutu-Mhlathuze WMA. It is
this catchment which is seen as the principal income generator providing economic viability to
the Usutu-Mhlathuze WMA.
4.2.2 Surface Water Hydrology
The majority of the rising main pipeline falls within the W12H quarternary drainage region,
which is drained by the Okula River, just north of the Hillview Pump Station. The Okula River
feed the Nseleni River which then feeds the Mhlathuze River.
The last 150 m of the rising main and the entire gravity main falls within the W12F quarternary
drainage region, which is drained by the Mkumbane River which feeds into the Mpangeni River,
both of which eventually feed the Mhlathuze River.
A large portion of the pipeline follows the development boundary delineated along the edge of
the Mkumbane River, the pipeline leaves the edge of the Mkumbane River and then crosses
the Mpangeni River using the existing pipe bridge to enter the Empangeni Waste Water
Treatment Works.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
32
4.2.3 Mean Annual Runoff (MAR)
The runoff from the Mhlathuze catchment is difficult to estimate accurately due to inaccurate
and inadequate gauging within the catchment. Runoff is also obviously affected by
development within the catchment.
The estimated natural runoff from the W12 catchment is 583 million m3/annum, this is
approximately 17.9 % of the mean annual rainfall.
4.2.4 Resource Class (WET-Health)
4.2.4.1 Wetlands
The following wetland hydrogeomorphic (HGM) types were identified within the area of interest
(after Kotze, et. al., 2007) and are shown on Figures 1-3:
One floodplain wetland.
Ten valley bottom with channel wetlands.
One valley bottom without channel wetland.
One hillslope seepage feeding a water course wetland.
An additional area was also identified which possibly could be a floodplain wetland area (W11
on Figure 7). However further detailed studies will be necessary to establish its status as it is
likely to have experienced historic soil disturbance and is currently used as a grassed lawn
which is regularly mowed for used as a recreational area.
The wetland functional assessment took into account those sections of wetlands which extend
beyond the boundary of the 500 m pipeline buffer. Thirteen separate HGM units were identified
within the 500 m pipeline buffer, not all of which are likely to be affected by pipeline
construction (see Appendix 1 for summary of results for each HGM unit). A wide range of
impacts have influenced the results of this assessment due to the mixed nature of the land-use
in this rapidly urbanising area. These include factors associated with urbanisation, commercial
sugarcane farming as well as subsistence agriculture together with impacts associated with
grazing of livestock.
Out of all the wetlands identified on site, wetlands 1, 2, 3, 4, 5 and 10 are either directly
affected or are likely to affected by pipeline construction. Wetlands 6, 7, 8, 9, 11, 12, 13 and 14
are positioned far away enough from the pipeline route that they are unlikely to be affected by
the upgrade, assuming that the provisions of the environmental management plan (EMP) are
enforced. The results below are discussed for those wetlands which are either directly affected
or are likely to affected by pipeline construction.
4.2.5 Receiving Water Quality Objectives and the Reserve
There are no Resource Quality Objectives available for the Usutu-Mhlathuze WMA. However,
according to the Internal Strategic Perspective (ISP) for the WMA (DWAF, 2004), in terms of
actual current water use, there is surplus water available in the catchment while in terms of
allocations the catchment is seriously stressed. The Mhlathuze catchment is the economic
‘powerhouse’ of the Usutu to Mhlathuze WMA and the use and sales of water within this
catchment are critical both for its own good management and for the management of the rest of
the WMA. The Richards Bay/ Empangeni industrial complex is a national growth point still
developing on the basis of national investment in port, rail and road infrastructure. At the same
time the available water within the catchment has been over allocated to users, and water
accounting indicates severe stress conditions.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
33
In practice irrigated agriculture does not use its full allocation during normal years, and
restrictions prevent this use during drought conditions. The most significant water-related
infrastructure is the Goedertrouw Dam, with a capacity of 304 million m 3. This is situated in the
upper catchment. Water can also be transferred into the Goedertrouw Dam from the Thukela
via the Middeldrift transfer scheme at a maximum rate of 34 million m 3/annum. 18 million m 3
of water is also imported into the Mhlathuze catchment from the Mfolozi catchment for use in
mining operations by Richards Bay Minerals each year
4.3 Socio-economic environment
4.3.1 Economic and population profile for City of uMhlathuze Local Municipality
The City of uMhlathuze (KZ 282) is situated on the north-east coast of the province of KwaZulu-
Natal, about 180 kilometres north-east of Durban. The uMhlathuze area covers 795 km² and
incorporates Richards Bay, Empangeni, eSikhaleni, Ngwelezane, eNseleni, Felixton and
Vulindlela, as well as the rural areas under Traditional Councils namely, Dube, Mkhwanazi,
Khoza, and Zungu.
The population is estimated at 334,459 (Census, 2011). The municipality borders a coastline
that spans approximately 45 km. The N2 highway traverses the uMhlathuze Municipality in a
north-east direction towards the Swaziland border and south-west towards Durban. It effectively
forms a division between Empangeni and Richards Bay.
In accordance with the Municipal Structures Act, 1998 (No. 117 of 1998), the City of
uMhlathuze is the Water Services Authority (WSA) and the Water Service Provider (WSP) for
the Municipality. The WSA has a duty to all consumers, or potential consumers, in its area of
jurisdiction to progressively ensure efficient, affordable, economical and sustainable access to
water supply and sanitation (collectively referred to as water services). As a WSA, the City of
uMhlathuze focuses on water services and on providing at least a basic level of service to
consumers in its area of jurisdiction.
4.3.1.1 Water and sanitation
Water and sanitation backlogs have been monitored and are reported on a quarterly basis to
the Council structures by the Infrastructure and Technical Services Department. The City of
uMhlathuze has formulated a level of service policy and this is defined in the Free Basic Water
policy. The policy identifies and deals with the following levels of water services:
Supply of water through communal water services i.e. standpipe.
Supply of uncontrolled volume of water to a household where a water meter is installed.
The City of uMhlathuze has formulated a Level of Service Policy for Sanitation in rural and
urban areas. In formalised urban areas a waterborne system will be implemented and in rural
areas Ventilated Improved Pit Latrines will be installed.
It must be noted that in peri-urban areas or dense settlements adjacent to urban areas, which
are close to a Water Resource, it will be advisable that shallow sewers be installed in order to
protect a water resource.
The City of uMhlathuze in its capacity as the WSA and juristic entity is compelled by the Water
Services Act, 1998 (No. 107 of 1997) and the National Water Act, 1998 (No. 36 of 1998) to
ensure that the quality of the municipality’s water resources, potable water and wastewater
systems are continually monitored in an endeavour to maintain quality and evaluate against set
standards/specifications/guidelines. The Scientific Services section is responsible for the
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
34
effective management of this function within the WSA Division. Various key functional areas
within the Scientific Services contribute to the reliability and credibility of an effective water
quality management system. The two major sections of the Scientific Services is the laboratory
and Water Quality Management section. Together these sections exist in a cooperative
relationship in an endeavour to combat water pollution.
4.3.1.2 Water Quality Management
The City of uMhlathuze has the following Water Quality Functions:
Water and wastewater quality monitoring as per the Water Quality Monitoring Program
(WQMP).
Drinking Water Quality Management (including consumer complaint management).
Industrial Effluent Permit Management.
Industrial Pollution Management.
Water pollution incident investigations.
4.3.1.3 Drinking water and wastewater systems
There are currently two WSPs namely; Water and Sanitation Services of South Africa (WSSA)
and Mhlathuze Water, who are contractually responsible for the water and wastewater
purification and distribution function. An extensive water quality-monitoring program for drinking
water and wastewater quality has been implemented. The monitoring program contains the
following:
Water Treatment Works:
Esikhaleni Water Treatment Works.
Mzingazi Water Treatment Works.
Ngwelazane Water Treatment Works.
Drinking Water Reticulation monitoring: There are a number of test points along the water
networks that serve to ensure that the quality of potable water (to the consumer) complies
with national standards (SANS 241:2011). There are 53 samples tested per week/month by
WSSA and 8 sample points by uMhlathuze Water.
Waste Water Treatment Works includes:
Alton Macerator Station.
Arboretum Macerator Station.
Nseleni Wastewater Treatment Works.
Esikhaleni Wastewater Treatment Works.
Empangeni Wastewater Treatment Works.
Ngwelazane Wastewater Treatment Works.
Vulindela Wastewater Treatment Works.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
35
5. ANALYSIS AND CHARACTERISATION OF ACTIVITY
5.1 Site delineation for characterisation
5.1.1 Water supply
Water for construction will be sourced from the municipality and shall be delivered to site via
tankers as and when required. This activity will not trigger a water use in terms of Section 21 of
the NWA.
5.1.2 Waste Management
5.1.2.1 Process water (water supply, water balance, reuse and recycling, water conservation and
demand management, sewerage management, point source discharges)
The upgrading of the Southern Outfall Sewer System does not require or trigger any formal
waste management activities except the management of waste during the construction phase,
which must be undertaken as per the conditions of the EMPr (Appendix 13):
SOLID WASTE
The Contractor must ensure that personnel make use of the litter bins provided and that
the construction site and the construction camp are kept tidy and litter-free at all times.
All domestic waste must be collected in litter bins.
Litter bins must be equipped with a closing mechanism to prevent their contents from
blowing out and scavengers from getting in.
Litter bins must be emptied weekly (or as required before they reach capacity).
Domestic waste must be taken to a licensed landfill site. Waste must be transported
responsibly, avoiding waste spills en-route.
Where necessary, a storage area must be dedicated on site for the collection of
construction waste.
No solid waste may be burned or buried on site or disposed of by any other method.
Where feasible, waste paper, glass and metal waste must be collected separately and
arranged for collection by recycling Contractors.
No burning of waste is permitted.
LIQUID WASTE
Suitable, sufficient and conveniently located sanitation facilities must be provided as per
the approved construction site layout plan.
Toilets must be regularly emptied and serviced.
The Contractor is entirely responsible for enforcing their use and for maintaining all toilets
in a clean, orderly and sanitary condition to the satisfaction of the ECO.
Sewage must be disposed of at a licensed wastewater treatment site and may under no
circumstances be dumped in the bush or buried.
HAZARDOUS WASTE
Compliance with all national, regional and local legislation must be ensured with regard
to the storage, handling and disposal of hydrocarbons, chemicals, solvents and any other
harmful and hazardous substances and materials.
Hazardous waste must be stored as indicated on the approved construction site layout
plan.
Drip trays must be used where dispensing mechanisms or stored receptacles may leak.
No spillage of hazardous products must be allowed on-site. Special care must be taken
to avoid contamination of surface or groundwater.
Under no circumstances shall the spoiling of hazardous products on site be allowed.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
36
Waste oils and batteries must be retained for recycling by the supplier, wherever
possible.
Used oil and lubricants must be collected in a holding tank and disposed of at a
registered hazardous waste disposal site.
Hazardous waste not earmarked for reuse, recycling or resale must be disposed of at a
registered hazardous waste disposal site.
The repair and/or maintenance of vehicles and equipment on-site is not permitted.
5.2 Storm water (clean and dirty water management)
5.2.1 Groundwater potential sources of pollution
5.2.1.1 Construction Phase
Refuelling construction equipment.
Storm water runoff from increased hard surfaces and exposed surfaces as a construction
phase
Associated materials that could lead to contamination include diesel and/or petrol
hydrocarbon products and greases and oils used and leakages from trucks.
Sewerage spills from the decommissioning of the existing pipes and infrastructure.
5.2.1.2 Operations Phase
Sewerage over flows leakages due to blockages or damage to infrastructure.
5.2.2 Impact prediction
5.2.2.1 Construction Phase
The impact of a hydrocarbon spill to groundwater could have a regional impact should it
migrate with the groundwater flow toward the rivers and wetlands. However, this would
be dependent on the volume and type of hydrocarbon compound released. The intensity
of the impact of a minor hydrocarbon spillage would be medium as the soil and
groundwater conditions would be impacted but processes would continue. The impact
would be medium term (2-15 years) as natural degrading processes in soil and
groundwater would degrade and attenuate the released hydrocarbon naturally over time.
Should the mitigation measures be implemented the low impacts of potential fuel
releases to soil and groundwater would become insignificant and the release would be
contained to the site.
Sewerage spills can introduce a wide range of potentially infectious agents to water that
may result in incidences of waterborne diseases with far reaching socio-economic
implications.
The increase in nutrients caused by sewerage spills can result in an increase in the
growth of algae, such blooms are harmful as they can remove oxygen from the water
resulting in the death of other forms of life.
5.2.2.2 Operation Phase
The potential impact from the contaminated storm water impacts to soil and groundwater
at the site should rainfall and surface water runoff leach compounds into the subsurface.
The intensity of this impact is regarded as low.
Sewerage spills can introduce a wide range of potentially infectious agents to water that
may result in incidences of waterborne diseases with far reaching socio-economic
implications.
The increase in nutrients caused by sewerage spills can result in an increase in the
growth of algae, such blooms are harmful as they can remove oxygen from the water
resulting in the death of other forms of life.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
37
5.2.3 Stormwater Management
The Contractor shall take measures, to the approval of the Engineer or the Environmental
Officer, to ensure that there is no undue stormwater damage and soil erosion resulting from the
construction activities inside and outside the construction camp and Works areas.
Surface stormwater shall, where possible, not be allowed to be concentrated and flow down cut
or fill slopes or along the pipeline route without erosion protection measures being place.
Where stormwater is likely to be channelled along pipeline trenches, the length of open
trenches shall be reduced to minimise the quantity of stormwater concentrated in such a
manner. The Contractor shall provide a suitable escape route for any stormwater collecting in
the trench.
During pipe laying operations the bedding and selected fill shall be protected from stormwater
damage through the placement of temporary across trench bolsters (sandbags) at suitable
intervals to prevent scouring of the bedding / fill material.
Where material excavated from trenches is likely to create high concentrations of stormwater,
suitable escape routes shall be provided to allow stormwater to be channelled into the nearest
natural stormwater flow path.
Where a pipeline crosses a drainage way, the drainage path shall not be fully obstructed during
construction, i.e. a suitable flow path for stormwater shall be provided during the construction
process. At no point shall drainage ways be allowed to drain into open trenches.
At no point shall stormwater from the construction site be allowed to drain into private
residential or commercial properties. All stormwater shall be directed to the nearest suitable
drainage way, be it the municipal stormwater system or other natural drainage way.
Overflow and/or scour channels will be lined with stone pitching along their length and at their
points of discharge to prevent soil erosion. The point of discharge shall be where there is dense
natural grass cover. These channels shall not discharge straight down the contours but shall be
aligned at such an angle to the contours that they have the least possible gradient.
Stormwater deflection berms or stone pitched channels will be constructed at regular intervals
(plus minus every 15-30 m) diagonally across the pipeline servitude on slopes as directed by
the Engineer or Environmental Officer.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
38
Where pipelines cross a steep embankment, a stormwater diversion berm will be constructed at
the top of the embankment to divert water away from the pipeline. The existing land profile will
be reconstructed and the embankment replaced with topsoil and seeded as per specifications.
Where a pipeline crosses minor drainage ways or erosion gulleys, a gabion basket or reno-
mattress will be placed upstream from the crossing at the same level as the pipeline. Stone will
be packed continuously from the gabion across the pipeline to a point where erosion will no
longer occur.
Where moderate to steep sloping land causes a water runoff erosion hazard, stone contour
berms will be constructed at 15 m intervals along the length of the pipeline trench to divert
water away from the pipeline trench.
Figure 8 Pipe crossing a steep embankment
Figure 9 Pipe crossing minor drainage line or erosion gully
Figure 10 Moderate to steep sloping land causing runoff erosion hazard
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
39
Where a high erosion hazard exists due to fluvial erosion at the bottom of stream channels or
dongas, the pipeline shall be encased in concrete to a level not exceeding the natural bed level
and over a distance of at least twice the width of the pipeline trench.
5.2.4 Waste (Waste stream identification, characterisation, reuse, recycling, minimisation)
The upgrading of the Southern Outfall Sewer System will only generate waste stream during
the construction phase. During which phase the concept of the waste hierarchy, illustrated in
Figure 9 must be adopted. The general waste generated during construction must be managed
by a dedicated service provider. Solid waste will be collected from sources and stored in
temporary satellite storage areas before being transported to the central sorting facility. Waste
is then sorted into different recyclable categories, and the remaining waste is disposed of at the
approved landfill site.
Figure 11 Waste Management Hierarchy
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
40
5.3 Operational Management
5.3.1 Organisational structure
The City of uMhlathuze Municipality will resume the responsibilities for the operational
maintenance and management of upgraded Southern Outfall Sewer once construction and
rehabilitation phases have been completed.
5.3.2 Resources and competencies
The technical staff within the City of uMhlathuze Local Municipality, as well as those of the
appointed implementing agent are well qualified to implement the environmental policies and
management plans.
5.3.3 Education and training
The independently appointed ECO must prepare and present an environmental awareness
training programme to the Contractor, Sub-contractors and employees in English and isiZulu.
The environmental awareness training programme must include the following:
The importance of compliance with all environmental policies, procedures, plans and
systems.
Understanding, and importance of, and the reasons why, the environment must be
protected.
Basic awareness and understanding of the key environmental features of the work site
and environs, particularly sensitive habitats.
The significant environmental impacts, actual or potential, as a result of their work
activities.
The mitigation measures required to be implemented when carrying out their work
activities.
The environmental benefits of positive environmental performance.
The various roles and responsibilities in achieving compliance with the environmental
policy and procedures, including emergency preparedness and response requirements.
The potential consequences of departure from specified operating procedures.
Health and safety awareness.
The Contractor must ensure that its Sub-contractors and employees (and any other third
parties) attend the course. At the discretion of the ECO and Environmental Manager,
employees involved in events of non-compliance may be given further relevant training by the
ECO.
A record of the environmental awareness training programme must be kept by the ECO and
RE.
5.3.4 Internal and external communication
Liaison with stakeholders is to be co-ordinated by the Project Engineer and the Contractor. This
will include liaison with the landowners, utility providers, neighbours, and relevant authorities.
Complaints or queries received from stakeholders and actions taken to address complaints
must be addressed in writing (with copies forwarded to the Environmental Manager and ECO).
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
41
5.3.5 Awareness Raising
The purpose of the environmental awareness programme is to promote ongoing environmental
awareness amongst the workforce. This can be addressed by means of the implementation of
the EMPr by the City of uMhlathuze Municipality through to the contractors and the actual
construction staff on site and should include:
General induction
Briefings / training seminars.
Notice boards, graphs, reports, etc.
Toolbox talks.
Mass meetings.
Audio visual / electronic media.
Face to face meetings.
Training on Environmental Hazards and Risks
5.4 Monitoring and Control
Monitoring is required in order to ensure that the wetlands and riparian habitats
associated with the proposed development are maintained in their current ecological
state or improved but incurring no net loss to functionality as a result of the project. It is
recommended that monitoring of the wetland and riparian areas be implemented in
accordance with the following guidelines:
5.4.1 Responsibilities for monitoring
Compliance monitoring will be the responsibility of the independently appointed, suitably
qualified ECO (Environmental Control Officer) with any additional supporting EO’s
(Environmental Officers) having the required competency skills and experience to ensure
that monitoring is undertaken effectively and appropriately.
5.4.2 Construction monitoring objectives
Key monitoring objectives during the construction phase should include:
Ensuring that management and mitigation measure are adequately implemented
to limit the potential impact on the Mkumbane and Mpangeni Rivers and their
associated wetlands and riparian areas.
Ensuring that disturbed areas have been adequately stabilised and rehabilitated to
minimise residual impacts to affected resources.
5.4.3 Record keeping
The ECO shall keep a record of activities occurring on site, including but not limited to:
Meetings attended.
Method Statements received, accepted and approved.
Issues arising on site and cases of non-compliance with the EMPr.
Corrective actions taken to solve problems that arise.
Penalties/fines issued.
Complaints from interested and affected parties.
A photographic record must be maintained throughout.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
42
5.4.4 Construction phase monitoring requirements (ECO)
5.4.4.1 Pre-construction
The pre-construction phase refers to the period following final project planning and the
tender phase, leading up to, but not including, the establishment on site by the appointed
Contractor. This phase will require input from the Environmental Manager and ECO on
items such as:
Ecologically sensitive areas and plants to be conserved.
The extent of the construction servitude in restricted and unrestricted areas.
Site access (including entry and exit points).
Location of the Contractor camp, pipe storage yards, concrete batching areas,
portable toilets, construction materials and fuel storage areas.
Storm water control measures.
Waste management including waste storage and disposal sites.
5.4.4.2 During construction
This involves the monitoring of construction related impacts. Regular monitoring of the
construction activities is critical to ensure that any problems are picked up in a timeous
manner. In this regard, the following potential concerns should be taken into
consideration:
Destruction of habitat outside the construction servitude including ‘No Go’ areas.
Erosion of the bed and banks of rivers/streams.
Signs of intense or excessive erosion and/or sedimentation within, along the edge
and/or immediately downstream of the construction zone.
Erosion of disturbed soils and soil stockpiles by surface wash processes.
Sedimentation of aquatic habitats downstream of work areas.
Altering the hydrology and through flows to downstream habitat during
construction across wetlands and riparian areas.
Pollution of water resources (focus on water turbidity and hazardous substances
such as fuels, oils and cement products).
Poorly maintained and damaged erosion control measures e.g. sand bags, silt
fences and silt curtains.
These risks can be monitored visually on-site by the ECO (together with construction
staff) with relative ease and should be reported on regularly during the construction
process. Any concerns noted should be prioritised for immediate corrective action and
implemented as soon as possible.
5.4.4.3 Post-construction
This involves monitoring the effectiveness of rehabilitation activities. The ECO and
construction staff would need to perform routine checks of rehabilitation effectiveness
with the initial focus on stabilising and vegetating disturbed soils and the restoration of
natural topography. This can also be achieved through basic visual inspections
documenting inadequacies in the rehabilitation outcomes for remediation. Once complete
it is recommended that an independent suitably qualified specialist is consulted to ensure
the success of rehabilitation and to identify shortcomings that will need to be addressed.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
43
5.4.5 Operation phase monitoring requirements
This involves annual monitoring of the wetland and riparian areas affected by the
development in order to ensure that operational impacts are being effectively managed.
This can also be achieved through basic visual inspections by the ECO and support staff,
documenting issues such as:
Alien Invasive Plant invasion.
Erosion headcuts.
Scouring and deposition associated with storm water runoff.
Channel incision downstream of development.
Spills, overflows or leakages from new infrastructure.
Scouring around infrastructure at wetland crossings.
Channel bank erosion and collapse (bank instability concerns).
5.5 Risk Assessment / Best Practice Assessment
This chapter documents the assessment of the potential impacts for the upgrading of the
Southern Outfall Sewer System. The assessment of potential impacts takes into account the
current environment, the proposed construction process and the findings of the specialist
studies.
Spatial extent: A description of whether the impact would occur on a scale limited to the
immediate areas of development activity (local); limited to within 5 km of the development
(area); would affect the region as a whole (region); or would occur at a national or
international scale (national/international).
Duration: A prediction of whether the duration of the impact would be short term (0 to 5
years), medium term (5 to 15 years), long term (> 15 years, with the impact ceasing after
the operational life of the development), or should be considered as permanent.
Probability of occurrence: A description of the probability of the impact actually
occurring as improbable (low likelihood), probable (distinct possibility), high (most likely)
or definite (impact would occur regardless of prevention measures).
Significance: The significance of identified impacts has been expressed qualitatively as
follows:
insignificant - the impact is insubstantial and does not require management.
low - the impact is of little importance, but may require management
medium - the impact is important, management is required to reduce negative
impacts to acceptable levels.
high - the impact is of great importance, negative impacts could render
development options or the entire project unacceptable if they cannot be reduced
to acceptable levels and/or if they are not balanced by significant positive impacts,
management of negative impacts is essential.
Status of the impact: A statement of whether the impact is positive (a benefit), negative
(a cost), or neutral.
Degree of confidence in predictions: A statement of the degree of confidence in the
predictions, based on the availability of information and specialist knowledge.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
44
5.5.1 Wetlands
An assessment of the potential impacts as well as the recommended mitigation measures of
the proposed upgrading of the Southern Outfall Sewer on wetlands and riparian areas
(Appendix 14 – Wetland Studies) are provided in the table below:
Table 5 Anticipated impacts and proposed mitigation measures for wetlands and riparian areas
CONSTRUCTION PHASE
Impacts Mitigations
Disturbance and loss of riparian vegetation
and riparian habitats due to construction
activities
Consider biodiversity offset mitigation where
destruction of riparian habitat is unavoidable
Keep vegetation clearance to a minimum. No
vegetation should be cleared beyond the site itself
A walk down should precede construction to
identify red listed or protected plants
During construction, waste materials should be
stored according to best practice guidelines and
recommendations to prevent contamination of the
riparian ecosystem
Accidental spills should be reported to the ECO
immediately
Disturbance to soil and hydrology with the
resultant siltation of riparian habitats
Install temporary erosion and sediment control
measures before initial disturbance of the soil
Ensure that topsoil removal and storage are done
according to best practice principles
Reclaim and re-vegetate the disturbed areas to
approximately pre-construction capability
Following construction, the disturbed area should
be seeded with locally sourced indigenous seed
mixes to limit erosion
Avoid construction activities during the rainy
season, and especially during episodes of heavy
rains
Cumulative impacts
Cumulative impacts associated with
vegetation clearance will result in
disturbance of soils, spread of alien
invasive species and a reduction of
ecosystem services
Keep vegetation clearance to a minimum
Control soil erosion
Control alien invasive plants
Cumulative impacts associated with
vegetation clearance will result in
disturbance of soils, increased soil erosion,
the river will become silted up, which will
could lead to flooding in certain parts of the
catchment
Keep vegetation clearance to a minimum
Control soil erosion
Reclaim and re-vegetate the disturbed areas with
locally sourced indigenous plants / seed mixes to
limit erosion
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
45
OPERATIONAL PHASE
Impacts Mitigations
Disturbance of riparian habitat.
(Potential pollution from sewerage spills)
Accidental spills should be contained and cleaned
up as soon as possible
Regular maintenance of sewerage line / replace
manhole covers to prevent possible spills /
blockage / vandalism
Cumulative impacts
Cumulative impacts associated with
vegetation clearance will result in
disturbance of soils, increased soil erosion,
reduced habitat for fauna and flora species,
spread of alien invasive species and a
reduction of ecosystem services
Keep vegetation clearance to a minimum
Control soil erosion
Control and eradicate alien invasive plants
Reclaim and re-vegetate disturbed areas with
locally sourced indigenous plants / seed mixes to
limit erosion
Cumulative impacts associated with burst
sewerage pipes or blocked mains that
cause sewerage spills directly into the
rivers. This will be detrimental to the natural
environment, by upsetting the balance of
nutrients and fauna and flora in the system.
Additionally this has human health
implications, since the rivers are in an
urban environment
Regularly maintain sewerage line infrastructure by
replacing manhole covers to prevent blockage of
the system
Accidental spills should be contained and cleaned
up as soon as possible
5.6 Issues and responses from public consultation process
5.6.1 Pre-Application Consultation with the Department of Water and Sanitation (DWS)
A pre-application meeting was held on the 16th November 2015 with Ms Hassina Aboobaker
from DWS. From this meeting and through extensive correspondences with the DWS thereafter
it was confirmed that a section 21 (c) and (i) WULA will need to be submitted for the upgrading
of the Southern Outfall Sewer System. The Department’s requirements, in terms of the WULA
and supporting information were agreed through their subsequent comments submitted during
the environmental authorisation process, and through extensive consultation thereafter.
5.6.2 Other stakeholders
The applicant (City of uMhlathuze Municipality) has engaged with the various landowners and
affected persons which may be impacted on by the proposed upgrading of the Southern Outfall
Sewer System. These interested and affected persons include the following groups or
Departments:
Amafa aKwa-zulu Natali
Department of Forestry and Fisheries
Department of Transport (KZN)
Department of Water and Sanitation (KZN)
Wildlife and Environment Society of South Africa (WESSA)
uThungulu District Municipality
Ezemvelo KZN Wildlife
Department of Planning and Sustainable Development
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
46
Department of Economic Development, Tourism and Environmental Affairs (KZN)
City of uMhlathuze Local Municipality
5.6.3 Public Review
The WULA was made public by way of a written notification sent to all interested and affected
parties (I&AP’s) registered during the Basic Assessment process, and an advert in the Zululand
Observer (date). The notification letter and advert serves to invite all registered and potential
I&AP’s to comment on the WULA, and inform them of their right to submit written objections
within the 60 working day comment period.
All comments and/or objections received will be recorded along with the responses and
submitted to the DWS following the comment period.
5.7 Matters requiring attention / problem statement
The main issues requiring attention as discussed in more detail in Section 5.5.1 are provided
below:
Disturbance and loss of riparian vegetation and riparian habitats due to construction
activities.
Disturbance to soil and hydrology with the resultant siltation of riparian habitats.
Cumulative impacts associated with vegetation clearance will result in disturbance of
soils, spread of alien invasive species and a reduction of ecosystem services.
Cumulative impacts associated with vegetation clearance will result in disturbance of
soils, increased soil erosion, the river will become silted up, which will could lead to
flooding in certain parts of the catchment
Disturbance of riparian habitat and potential pollution from sewerage spills.
Cumulative impacts associated with burst sewerage pipes or blocked mains that cause
sewerage spills directly into the wetlands and watercourses.
5.8 Assessment of level of confidence of information
In general it can be stated that the extent and level of information available is adequate to
support the development of the IWWMP for the upgrading of the Southern Outfall Sewer
System.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
47
6. WATER AND WASTE MANAGEMENT
6.1 Water and Waste Management Philosophy
The environmental philosophy that has been adopted in undertaking the activities are:
To comply with the applicable South African Government’s legislation, strategies and
procedures developed.
To minimise harm to the environment by designing, operating and closing all the
operations in an environmentally responsible manner.
To go beyond compliance over the long term.
The vision for water is:
Protect water quality.
Strive for zero use of potable water for operations.
Dedicated social obligations.
The following have been implemented or are in place to give effect to uMhlathuze’s
environmental philosophy:
An Environmental Management Plan (EMPr) is in place.
Appointment of an ECO.
Environmental training for all new staff.
Promotion of environmental awareness amongst employees and contractors.
Annual environmental auditing and reporting.
Establishment of a legal register.
Maintenance of a complaints register, clearly stating actions taken.
The environmental philosophy is applied to all aspects of water and waste management.
6.2 Options Analyses and motivation for implementation of preferred option
Although the proposed development is an upgrade of existing infrastructure and it would be
preferable to lay the new pipeline entirely alongside the existing pipeline, within the existing
servitude, this is however not entirely possible. There are various sections, each with their own
specific reasons, where the new pipeline will need to deviate from the existing. The following
alternatives were considered:
6.2.1 Route Alternatives
The section of the existing rising main along the western side of the MR230 runs through
the front gardens of residential properties. To avoid this; a registered servitude which
exists for 200 m on the opposite side of the road, and which will need to be extended by
approximately 475 m, will be used. The new rising main will then cross the MR230 using
a trenchless method, where it will join the existing servitude.
In the vicinity of Schirra Road, the existing gravity main is an above ground steel pipeline
on pipe supports which crosses a small stream, immediately after which it crosses
through the corner of three residential properties. By moving the new pipeline west,
significantly less of the pipeline will need to be above ground, and it will fall outside the
property boundaries.
At the most southerly end of Sigma Crescent, the existing gravity main also runs through
residential properties. The buildings on these properties are very close to the servitude
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
48
and in some cases have been extended over the pipeline. The new gravity main will be
realigned in this area to bring it outside the property boundaries.
Other alternative routes have not been considered, as further deviations from the existing
servitude are likely to result in new disturbances to residents, road users, streams and riverine
vegetation. Much of the pipeline passes very close to existing residential properties with limited
room for realignment without causing damage to existing structures and service infrastructure.
As such this assessment focuses primarily on the preferred alternative and no further
alternatives were assessed.
6.2.2 Material Alternatives
The options considered for the pipelines were unplasticised polyvinyl chloride (uPVC) and glass
reinforced polyester (GRP). GRP was considered to be more cost effective for this project and
thus is the recommended material.
6.2.3 Type of Activity
The activity for this project is replacement of the existing sewer pipeline to one of an
appropriate size to be able to cope with current and future flows. This is the only activity with
which a sewer pipeline can be associated and as such, no activity alternatives have been
assessed.
6.2.4 No-go Alternative
If the current pipeline is not upgraded to that of a suitable size, overflows and spills will become
more frequent. This will deny the local community access to adequate sanitation, which is
fundamental to personal dignity, social and psychological well-being, public health, economic
development and environmental sustainability.
It is the professional opinion of the Environmental Assessment Practitioner (EAP) team that the
no-go alternative is undesirable and unrealistic when considering the environment, the basic
needs of the community and future development in the area.
6.3 IWWMP Action Plan (Priority Actions)
This action plan covers the generic design and construction considerations and parameters for
the laying of pipelines for the Southern Outfall Sewer. This is an evolving guideline that needs
to be updated or adapted as progress is made, and successes and failures of procedures are
identified. For successful rehabilitation, it is imperative that this plan is at all times used in
conjunction with the approved EMPr.
The proposed pipelines range in size from 700 mm to 400 mm nominal diameter. All pipes will
be laid, as far as is possible, in existing pipeline servitudes. Pipelines will be laid in trenches
and backfilled to natural ground level, with the exception of the existing pipe bridge over the
Mpangeni River.
This method statement has been prepared to fulfil the Water Use Licence Application (WULA)
requirement of any structure that is to be developed and falls within a 500 m radius of an
existing wetland must apply for a Section 21(c) and (i) WULA.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
49
6.3.1 Planning of Pipelines
In the planning for the design phase of the pipeline, cognisance is taken of the following
reference documents;
SABS 1200 – Standardised Specification for Civil Engineering Construction;
When planning or designing the pipeline, a holistic approach that adheres to all the tenets of
the reference or policy documents listed above will be adopted. The environmental sensitivity of
wetland areas is acknowledged and designs undertaken will take full cognisance of the
proposed impact to these areas. In addition the pipeline follows an existing servitude and runs
at times within residential properties. The rights of access of the landowners is acknowledged
and proper communication with effected persons before, during and post construction will be
maintained and the absolute minimum disruption to effected properties.
The approach to design and construction will encompass the following;
Appropriate and adequate protection of existing manmade and natural structures such as
buildings, fences, river banks, etc. in the vicinity of the pipeline will be incorporated into
the design.
The existing river bank structure will be maintained as far as is possible to reduce
disturbance to the river flow.
Existing fences will be maintained as far as is possible, but if not possible will be
temporarily removed and reinstated to the same or better condition. The time taken will
be kept to a minimum and where necessary temporary fencing will be erected to maintain
the level of security to the effected properties.
Where the pipeline crosses stormwater channels these will be designed to have no
impact on normal stormwater flow in that all pipes and concrete casing will be buried at
least 500 mm below natural channel level in the case of soft material, and level with the
natural channel in the case of hard rock material.
Manholes will be provided at all changes in grade and direction and at intervals not
exceeding 80 m to facilitate maintenance during the lifetime of the pipelines.
6.3.2 Planning of River Crossing
In the planning for the design phase of the pipe crossing, cognisance is taken of the following
reference documents;
SABS 1200 – Standardised Specification for Civil Engineering Construction;
When planning or designing the pipe crossing, a holistic approach that adheres to all the tenets
of the reference or policy documents listed above will be adopted. The environmental sensitivity
of wetland areas is acknowledged and designs undertaken will take full cognisance of the
proposed impact to these areas.
This includes the impact on all, or any, matters relating to water quality, flooding, agricultural
drainage, erosion, flora and fauna and any adjacent topographical features.
The approach to design and construction will encompass the following;
Appropriate and adequate protection of the river banks in the vicinity of the pipeline will
be incorporated into the design.
The existing river bank structure will be maintained to reduce disturbance to the river
flow.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
50
The pipelines will cross rivers on the existing pipe bridge structure.
The pipe crossing has been designed to have no impact on normal river flow.
Where pipes are laid through the flood plain (1:100 year), a minimum cover level of 1
metre will be maintained.
6.3.3 Construction Methodology
Construction methodology will differ slightly depending on the nature of the river being crossed.
Perennial streams will require the temporary diversion of water flow during construction,
whereas non-perennial streams may not require flow diversion depending on the season.
6.3.3.1 A typical construction sequence is summarised hereunder:
Conduct a competent site investigation to build up an informed picture of the task.
Conduct a topographical survey of the pipeline route.
Adequate design of all the stages of construction.
All Environmental and Health and Safety requirements and good practice to be adhered
to.
6.3.3.2 Plant and Resources required for the Construction may include, inter alia:
Excavators;
Crane of sufficient lifting capacity and reach for pipe laying (if required);
Tipper trucks for the delivery of bedding material;
Compaction equipment;
Pneumatic breakers (if required);
On-site concrete batching plant (if required);
Concrete delivery vehicles for wet concrete;
Formwork, reinforcing steel and the necessary equipment and tools for assembly;
Equipment for the construction of concrete ring manholes and concrete encasement of
pipes.
6.3.3.3 Construction Method for Pipes Laid in Trenches:
This method will be used where pipes are conventionally laid in trenches and backfilled to
natural ground level.
Remove topsoil and stockpile for later use.
Excavate trench for pipeline to the design level.
If the material is firm normal excavation techniques will apply. In soft material shoring of
the trench sides may be required. In hard rock material trench excavation may require
the use of pneumatic breakers or blasting.
Install temporary dewatering pumps to keep the excavation dry (if required due to
groundwater ingress).
Construct stormwater diversion berms where required.
Place concrete to encasement if required. The top level will be determined by the
stormwater channel level.
Place bedding, lay pipe, place and compact selected fill over the pipeline.
Construct manholes, where required. Manholes will be constructed along the pipeline
route at changes in grade and direction.
Backfill to specification.
Dress backfill, topsoil and re-vegetate all exposed areas.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
51
6.3.3.4 Construction Method for Crossing the Mpangeni River:
This method will be used where the pipeline crosses the Mpangeni River on the existing
concrete piers. The construction will be completed in stages as described below.
STAGE 1
Manufacture off site of new structural steel beams to be installed between existing piers.
Deliver to site and stockpile new beams for erection.
STAGE 2
Construct temporary platforms for heavy lifting equipment.
Erect and fix new steel beams between existing concrete piers.
Place and fix in place new pipeline onto steel beams.
Test and commission new pipeline.
STAGE 3
Decommission, remove and dispose old pipeline from pipe bridge.
Remove temporary platforms and reinstate the river flow to its normal path.
Dress banks, topsoil and re-vegetate all exposed areas.
6.3.4 Conclusion
All design and construction work will be carried out in accordance with the relevant construction
specifications and in compliance with the Construction Health and Safety Specifications as well
as the Construction Environmental Management Plan.
Post rehabilitation monitoring must be carried out by the onsite ECO to ensure that the wetland
rehabilitation has been successful. Vegetation growth, hydrological functioning, evidence of
erosion and deposition are some of the key areas to be checked regularly. In this way, any
problems can be rectified timeously and managed in an adaptive manner.
6.4 Control and Monitoring
6.4.1 Integrated Water Quality Management System
The Council for Science and Industrial Research (CSIR), as part of the Memorandum of
Understanding signed with the City of uMhlathuze at the end of 2014, is developing an
Integrated Water Quality Management System (IWQMS) for the City of uMhlathuze that could
later be rolled out to assist other municipalities.
As a WSP, the responsibility lies with the Municipality to ensure the provision and sustainable
delivery of safe water to underpin economic and social development. The IWQMS will
capacitate and empower the City's Scientific Services to monitor water quality in the water
distribution network, as well as other water resources, to ensure an acceptable and safe level
of water quality for our community and the protection of our environment. The system will have
components that display the following:
Management Dashboard with indicators of any out of range alerts and that assist with
status tracing of incident investigations.
Overview in geographic and graphic format that summarise bacteriological, physical and
chemical water quality and quick links to regularly used tables/graphs
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
52
Tables and graphs created by trending and query that are updated real time and or
regularly to give status reports to management.
Key water quality results as required for legislative compliance.
6.4.2 Mobile GIS
Linked to the IWQMS is the Mobile Geographic Information System (GIS) project. A GIS is
proven technology that has been used for many years by government departments and other
organisations as a decision support tool and information management system. The City of
uMhlathuze 's GIS is a dynamic example of this technology application in action. The City of
uMhlathuze (Richards Bay) Corporate GIS is aiming to in-cooperate Mobile GIS as part of their
Enterprise GIS service, GIS software and computer infrastructure technology continue to
expand capabilities and introduce new business opportunities.
GIS provides the capability to collect manage, manipulate, analyse and distribute information
that is tied to a location. It layers that information in a map-based environment to provide a
better visual image of location, patterns and relationships. GIS is an enabling and core
technology that complements numerous business processes, systems and data, amongst other
applications. As such, it is an integral part of the computing infrastructure that contributes to the
success of a City’s service delivery and operations.
City of uMhlathuze has identified the following capabilities to meet their mobile GIS System
requirements:
A mobile access service must allow the GIS Mobile application to run on a range of
handheld devices, and provide access to the map contents of a map document through a
web service.
The web service shall be accessible via a GSM network, including MTN and Vodacom as
a minimum.
The Mobile Data Web Access web service must be created and published on a central
GIS server maintained by uMhlathuze Municipality IT personnel.
6.4.3 Laboratory ISO 17025 accreditation
Scientific Services has embarked on a project to get formal recognition that the laboratory is
competent to perform tests and CSIR will offer their services to assist in realisation of the plan.
The CSIR has more than ten accredited laboratories throughout the country and specialise in
the assessment and maintenance of the ISO 17025 accreditation of laboratories, ensuring the
quality and accuracy of results and the service deliverables in terms of lead times required by
legislation or industry.
The laboratory aims to accredit the following tests methods:
Chemistry: Ammonia, Chloride, Nitrates, Cyanide, COD, Phenols, Ortho-Phosphates,
TDS, Turbidity, pH, Conductivity.
Microbiology: E.coli, Total Coliforms, Faecal Coliforms, Faecal streptococcus,
Heterotrophic Plate Count.
The laboratory is currently undergoing method development and validation as well as phased
implementation of ISO 17025. The laboratory is also participating in Proficiency Testing
Schemes for chemistry and microbiology in order to continually improve accuracy and precision
when compared to other laboratories.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
53
As a prelude to ISO 17025 accreditation, the municipal laboratory currently meets the
requirements to register for DWS-approval per method. Future plans for the laboratory include:
Completion of the Method Validation/Verification process.
Introduction of new methodology.
Introduction of new tests.
6.4.4 Water pollution management
The Water Quality Monitoring Program (WQMP) (CR4711, 7 August 2008) has been developed
and implemented, so that council meets the statutory requirements and for the sustainability of
water resources within its area of jurisdiction.
The WQMP is the monitoring programme that the laboratory follows to conduct its testing. The
WQMP comprises the standards/guidelines and regulations that are required to effectively and
efficiently monitor the entire city’s water sources. Trend analyses will in future assist the council
to detect from early on the water quality status of the water sources and timeously put in
mitigation measures.
The WQMP will not only be utilised as a tool in decision making on water resource
management but will also be an invaluable database of reference data of individual sample
locations. The programme has been developed taking into consideration work currently being
performed in other departments. The areas detailed in Table 5 are being monitored for possible
pollution.
Table 6 Sample types being monitored by WQMP
SAMPLE TYPE DESCRIPTION
Surface Water Lakes (Cubhu and Mzingazi)
Rural/Urban Suburbs (stormwater streams)
Rivers/Streams/Canals
Industrial (stormwater streams)
Pump-stations (Streams close to pumpstations)
Coastal Water
Groundwater Municipal Cemetery
Landfill Site
Sewage Industrial Effluent (Sewage Network)
6.4.5 Monitoring of change in baseline
The monitoring of change in baseline information will be achieved through the implementation
of the EMPr (Appendix 13) and the Wetland and Riparian Area Monitoring Programme
(Appendix 23) outlined in section 5.4 of this IWWMP.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
54
6.4.6 Audit and report on performance of measures
Auditing against the EA, the approved EMPr and the WUL conditions will be required during
construction of Southern Outfall Sewer upgrade. During the construction, monthly site
inspections will be undertaken and the findings and observations made during the audit site
inspection will be documented in monthly audit reports. The objectives of the environmental
audit are:
To monitor compliance with the EA, WUL and EMPr.
To ensure that construction aspects and activities have been / are being managed
appropriately.
To ensure that any potential negative impacts associated with the construction phase are
addressed.
To determine the appropriateness and adequacy of the EMPr and WUL conditions, and
the need for any licence revisions or amendments.
Internal and external audits against the water use licence must be conducted annually and the
reports submitted to DWS, who may conduct a scheduled site visit to verify the audit findings
and assess licence compliance.
The IWWMP action plan must be reviewed and updated annually, or as stipulated in the
conditions of the WUL, once issued.
6.4.7 Audit and report on relevance of action plan
Once the WULA has been approved, audits against the IWWMP and WUL will be conducted for
the duration of the construction phase of the upgrade of the Southern Outfall Sewer system.
7. CONCLUSION
7.1 Regulatory status of activity
The water uses as set out in this document require approval in order to ensure all applicable
legislation is being adhered to. This document is compiled to align with the other legal
requirements (NEMA) and should therefore be implemented in conjunction with the other
reports, specialist studies, licences and approvals.
7.2 Statement on water uses requiring authorisation, dispensing with licensing requirement
and possible exemption from regulations
In terms of Section 22(1) of the NWA, the City of uMhlathuze Municipality may only use water
without a licence if the responsible authority (DWS) has dispensed with a licence requirement.
Water use licence forms for those water uses described in Table 1 are included in this
document.
7.3 Motivation in terms of section 27(1) of the NWA
7.3.1 Existing lawful water uses
The City of uMhlathuze Municipality has no existing lawful uses applicable to the proposed
upgrading of the Southern Outfall Sewer System in Empangeni.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
55
7.3.2 Contributions to redress the results of past racial and gender discrimination
The benefits of upgrading the Southern Outfall Sewer System, and having a system operating
without spills or overflows will reduce the negative aesthetics, environmental impacts and
potential risks to human health. It also allows known future planned developments to proceed
unhindered, as the pipelines’ capacities have been calculated to cope with the predicted
increase in flows.
7.3.3 Efficient and beneficial use of water in the public interest
The proposed upgrading of the Southern Outfall Sewer System is expected to have a number
of benefits for society in general both during the construction and operational phases.
Benefits to society associated with the construction phase include:
Stimulation of local economy through the provision of construction materials.
Job creation during the construction phase.
Investment into the area.
The benefit to society associated with a sewer system operating without spills or overflows is
the reduced negative aesthetics, environmental impacts and potential risks to human health.
The upgraded Southern Sewer System will also allow known future planned developments to
proceed unhindered, as the pipelines’ capacities have been calculated to cope with the
predicted increase in flows
7.3.4 The socio-economic impact of the water use/s if authorised
Through job creation and capacity building, construction is expected to result in socio economic
benefits. During the operational period, the upgrade will result in reduced negative aesthetics,
environmental impacts and potential risks to human health. It also allows known future planned
developments to proceed unhindered, as the pipelines’ capacities have been calculated to cope
with the predicted increase in flows
7.3.5 The socio-economic impact of the water use if not authorised
If the water uses applied here are not authorised and the current pipeline is not upgraded to
that of a suitable size, overflows and spills will become more frequent. This will deny the local
community access to adequate sanitation, which is fundamental to personal dignity, social and
psychological well-being, public health, economic development and environmental
sustainability
Future planned development within this area of Empangeni will also be hindered as the existing
system is already operating beyond capacity. The City of uMhlathuze Municipality has,
therefore, seen it essential to install an entirely new rising main and gravity main pipelines of a
suitable size to cope with the current and future planned sewer volumes.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
56
7.3.6 Relevant catchment management strategies and local government planning frameworks
that support the proposed water use/s
The uMhlathuze Strategic Catchment Assessment and Environmental Services Management
Plan (ESMP) identified 8 main catchments in the uMhlathuze municipality: Nseleni River, Lake
Mzingazi, Harbour, City, Estuary, Lake Cubu, uMlalazi Tributaries, and the uMhlathuze River.
The aim of the ESMP is to provide the municipality with a clear understanding of activities that
need to be undertaken to protect and enhance the supply of environmental services in the area.
Each of the listed catchments has been analyzed in terms of an environmental service asset
design concept. Subsequently, three tiers of analysis have been identified:
Level 1 is the Conservation Zone and represents areas of high
biodiversity/environmental significance that need or warrant legal protection. In this zone
are included unique areas, natural habitats such as wetlands, natural forests and areas
within the 1:100m floodline.
Level 2 is the Open Space Linkage Zone and includes natural buffers for level 1 areas as
well as those areas linking level 1 areas.
Level 3 represents the Development Zone and includes those areas not included in
levels 1 and 2. Care should still be taken that development does not negatively impact on
level 1 and 2 areas. In other words, development or transformation is allowed but should
not adversely impact on environmental sustainability.
7.3.7 The likely effect of the water use on the water resource and on other water users
The implementation of this IWWMP and the EMPr, together with the upgraded sewer system,
operating without spills or overflows, will improve the functioning and integrity of the affected
wetland and riparian habitats, but ongoing management would be required to sustain these
benefits.
7.3.8 Class and resource quality objectives (rqo’s) of the water use/s
Not applicable.
7.3.9 Investments already made and to be made by the water user in respect of the proposed
water use
The City of uMhlathuze has already:
Upgraded the Hillview Pump Station ahead of the anticipated pipeline upgrade.
Undertaken the necessary engineering and civil design work for the new infrastructure.
Undertaken the Environmental Authorisation process required for the pipeline upgrade.
Undertaken much of the WULA process required for the pipeline upgrade.
The expected capital value of the proposed development upon completion
will be R 28,000,000.00.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
57
7.3.10 The strategic importance of the water use/s to be authorised
The upgrading of the Southern Outfall Sewer System is required because the infrastructure has
reached the end of its design life and is operating beyond capacity. This is resulting in frequent
spillage and overflows of raw sewage.
7.3.11 The quality of water in the water resource which may be required for the reserve
and for meeting international obligations
The proposed development will have no impact on the water quantity and through proper
implementation of this IWWMP and the EMPr, the upgraded sewer system, operating without
spills or overflows, will greatly improve the current quality, functioning and integrity of the
affected wetland and riparian habitats.
7.3.12 The probable duration of any undertaking for which a water use is to be authorised
The construction impact will be of short duration (12 months).
7.4 Key Commitments
The City of uMhlathuze, is committed to the implementation of the conditions of the WUL, once
issued, which should include, but not be limited to the following conditions:
An ECO must be appointed for the duration of the construction phase to monitor and
ensure that the appropriate mitigation and rehabilitation measures are implemented.
Mitigation measures as contained in this IWWMP and the related management plans
must be adhered to.
All conditions of the Environmental Authorisation (Appendix 12) must be adhered to.
All mitigation measures contained in the approved EMPr (Appendix 13) must be adhered
to.
Construction must take place in accordance with the Construction Methodology as
provided in Appendix 20.
The implementation of the Stormwater Management Plan as provided in Appendix 21.
Construction must take place in accordance with the Civil Designs as approved by DWS
(Appendix 22).
The implementation of the monitoring requirements as provided in Wetland and Riparian
Area Monitoring Programme (Appendix 23).
The implementation of the Environmental Emergency Contingency Plan (Appendix 24)
as and when it is required.
All relevant Health and Safety legislation as required in South Africa must be strictly
adhered to.
All construction and operational related activities should comply with applicable National
and Local Legislation as well as any relevant municipal plans, by-laws/ regulations.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
58
8. REFERENCES
ACER, (2014). Final Basic Assessment Report for the proposed upgrading of the Hillview
sewer rising main and southern outfall bulk sewer pipeline in Empangeni, Kwazulu-Natal.
Unpublished report.
ACER, (2014). Vegetation Assessment and Wetland Delineation for the proposed upgrading of
the Hillview sewer rising main and southern outfall bulk sewer pipeline in Empangeni, Kwazulu-
Natal. Unpublished report.
ACER, (2015). Wetland Functional Assessment for the proposed upgrading of the Hillview
sewer rising main and southern outfall bulk sewer pipeline in Empangeni, Kwazulu-Natal.
Unpublished report.
Resources Assessment (March 2000). Strategic Environmental Assessment for Water Use
Mhlathuze Catchment. Water.
uMhlathuze Local Municipality, (2015). uMhlathuze Local Municipality Integrated Development
Plan. Richards Bay: uMhlathuze Local Municipality.
SRK Consulting, (2016). Integrated Water and Waste Management Plan: Proposed Empangeni
Mega Integrated Residential Development Project: Phase 1. Unpublished report.
CITY OF UMHLATHUZE MUNICIPALITY
UPGRADING OF THE HILLVIEW SEWER RISING MAIN AND SOUTHERN OUTFALL BULK SEWER PIPELINE IN EMPANGENI WATER USE LICENSE APPLICATION – INTEGRATED WATER AND WASTE MANAGEMENT PLAN
59
9. LIST OF APPENDICES
Appendix 1 – Applicants Company Registration Certificate
Appendix 2 – Property Title Deeds
Appendix 3 – Lease Agreements (N/A)
Appendix 4 – Property Zoning Documents
Appendix 5 – Land Claims Clearance Letter
Appendix 6 – BBEEE Certificate
Appendix 7 – DWS Application Forms
Appendix 8 – Site Plans and Maps
Appendix 9 – Master Layout Plan
Appendix 10 – Alternatives Report
Appendix 11 – Basic Assessment Report
Appendix 12 – Environmental Authorisation
Appendix 13 – Environmental Management Programme
Appendix 14 – Wetland Studies
Appendix 15 – Geotechnical Report
Appendix 16 – Aquatic Ecology Report
Appendix 17 – Geohydrological Studies (N/A)
Appendix 18 – Hydrological Studies
Appendix 19 – Water Balance (N/A)
Appendix 20 – Construction Methodology
Appendix 21 – Storm Water Management Plan
Appendix 22 – Civil Designs and Materials Test Report
Appendix 23 – Contingency Plans
Appendix 24 – Monitoring Programme
Appendix 25 – Financial Provision