PROJECT PRESENTATION · •New Urbanism •Environmental Sustainability •Anti - Monoculture...
Transcript of PROJECT PRESENTATION · •New Urbanism •Environmental Sustainability •Anti - Monoculture...
PROJECT PRESENTATION
Key Distances:
35kms from Jomo Kenyatta International Airport;accessible through the bypassJust 20kms from the Heart of Nairobi CityStrategically located 10kms from the Northern bypass.Situated at the Heart of the Rich Coffee Plantations ofKiambu
Location
‘MIGAA will capture the very essence of Kenya’s natural beauty by creating unparalleled residential community’
Nestled between two rivers and two natural dams,Migaa will provide an astounding array ofamenities such as: an 18-hole Golf Course Sporting & Recreational facilities Hospitality services, Commercial nodes Shopping Centres and restaurants Education Centres Medical Facility Communal facilities.
Overview
•Residential Golf Community
•Value driven catalyst
•Work & Zero commute
•New Urbanism
•Environmental Sustainability
•Anti - Monoculture
•50% Open green space
…An acre of green for every acre of
build…
The Concept - Migaa Philosophy
Master plan
Developer
Corporate Buyer
Residential Buyer
MIGAA has created the below array of products that gives buyers opportunity to own unique and innovative homes complemented by the
18-hole Golf Course and state of the art infrastructure services:
Migaa provides opportunities for wide
array of markets
Products
PLOTS
Plots Available:a) Quarter Acre Plots
•Golf Frontage P lots•Golf View Plots•Water Front plots
b) Eighth Acre Plots
MITINI SCAPES DEVELOPMENT
a) Cottages• 4 Bedroom +DSQ – 210 SQM• 3 Bedroom +DSQ – 160 SQM
b) Apartments• 1Bedroom Apartment – 65 SQM• 3 Bedroom Apartment – 110 SQM• 2 Bedroom Deluxe Apartment – 155 SQM
TAMARIND TREE RESIDENCE, MIGAA
Available Units:a) One Bedroom – 125 SQMb) Two Bedroom – 150 SQMc) Two Bedroom Duplex – 180 SQMd) Three Bedroom – 185 SQMe) Three Bedroom Penthouse – 220 SQM
INFRASTRUCTURE PROGRESS
MIGAA
• Migaa Infrastructure Progress Update
• Overall Progress – 40% Complete
Contents
A. Golf Course
a) Back Nine Holes (10,11,12,13, 14, 15, 16,17 &18)
• Construction and handover of the holes complete
A. Golf Course Photos
B. Golf Course Irrigation
a) Back Nine Holes (10,11,12,13, 14, 15, 16,17 & 18)
• Installation of golf course irrigation system 80% complete; automation of golf course irrigation system ongoing
B. Golf Course Irrigation Photos
C. Gate House
a) Gate House •Construction of the main gatehouse complete
D. Boundary Wall
a) Completed Wall Sections – 5.2 KM• Entrance Walling: Ornamental wall along main Migaa access road• Internal Walling: Separating the public areas ( Commercial Centre, Sports facility, Ubora
Hospital & Primary School) from Residential area• External Walling : Along the Western and Eastern boundary• Sentry boxes: Strategically located along the walls to accommodate security men
We
ste
rn B
ou
nd
ary –
1.6
K
M
Southern Boundary – 3.5 KM
Overall Construction Progress - 60%
Northern Boundary – 2.0 KM
East
ern
Bo
un
dar
y –
1.2
KMN.E
. B
ou
nd
ary
–0
.9 K
M
D. Boundary Wall Photos Cont’d
E. Electric Fence
a) Southern Boundary – 3.5 KMS• Erection of electric fence poles and wiring complete; powering of fence ongoing
b) Northern Boundary – 2.0 KMS• Erection of the poles ongoing
OVERALL CONSTRUCTION PROGRESS - 60%
E. Electric Fence Photos
F. Road Works
a) Main Access Road – 3.4 KM• Main access road constructed up to murram level complete; laying of kerbs/channels, hand packing hardcore and storm water drainage construction 60% done; to be completed in August 2015b) Spine and Feeder Roads – 9 KM• Bulk Earthworks for the roads ongoing; laying of kerbs/channels, hand packing hardcore and storm water drainage construction 20% complete: Road to be fully done by December 2015
F. Road Works Photos
G. Water Supply
a) Borehole• Drilling of 2 No. Boreholes complete and operational: Planned boreholes are 7 No.
Club house - Water capacity yield of 60 CM per hour Golf Hole 18 Borehole - Water capacity yield of 25 CM per hour
b) Water Reticulation – Phase 1 • Trenching water line (Ring mains – along the spine road) ongoing; 15% of ring mains excavation complete; Works to be completed in October 2015
G. Water Supply Photos
H. Sewerage System – Phase 1
a) Sewer Reticulation
•Sewer Reticulation – Phase 1 complete
H. Sewerage System – Construction Photos