Project Name
Steering Committee Meeting
Project Manager: Project Manager Name
Program Manager: Program Manager Name
Project Sponsor: Project Sponsor Name
General Guidelines:•Keep words to a minimum - more detail can be added verbally •Highlight changes from the last presentation where appropriate.•Stick to recommended format where possible.•Delete red instruction boxes when complete.•More detailed instructions are in the Speaker Notes. Click on View / Notes Page to view. You can print the ‘Notes View’ by selecting File/Print, then select ‘Notes Page’ in the ‘Print What’ drop down.
General Guidelines:•Keep words to a minimum - more detail can be added verbally •Highlight changes from the last presentation where appropriate.•Stick to recommended format where possible.•Delete red instruction boxes when complete.•More detailed instructions are in the Speaker Notes. Click on View / Notes Page to view. You can print the ‘Notes View’ by selecting File/Print, then select ‘Notes Page’ in the ‘Print What’ drop down.
(To view template instructions – Save this template to project files, reopen and then select View, Notes Page. Delete this note prior to publishing)
Executive SummaryDescription
Schedule
Cost
Risks
Total Project Budget
Actual Cost to Date
Est. at Completion
Variance at Completion
Est. at Completion is the Actual Cost to date plus the estimated remaining cost for the work scheduled.
Cost Variance is the ‘Project Budget’ minus the ‘Estimate at completion’
Current Phase: RequirementsProject Status: GreenProject End Date: mm/dd/ccyyAccomplishments
BusinessRisk 1Risk 2TechnologyRisk 1Risk 2
High level business objective
List the major risks to the project.
High level accomplishments so far
To change status colors, highlight box and select Format/Borders.
For ‘Current Phase’ update, please use standard PM phases (Opp Assessment, Initiating, Planning, Executing & Controlling, Closing) or Lifecycle Phases (e.g Software Development Lifecycle)
For ‘Current Phase’ update, please use standard PM phases (Opp Assessment, Initiating, Planning, Executing & Controlling, Closing) or Lifecycle Phases (e.g Software Development Lifecycle)
Business Need
Project Background
Proposed Solution
Business Benefits
• Benefit 1.
• Benefit 2.
(Example)
Project Costs
Cost
Labor $xxx,xxx
Hardware $xxx,xxx
Software $xxx,xxx
Outside Services $xxx,xxx
Total $xxx,xxx
(Example)
Project ROI
Project Organization
Steering Committee
Sponsor
Program Manager Project Manager
Business Team
IT Mgmt
CIS
Warehouse Infrastructure
Financial Purchasing
TSS CSS
Data Mgmt
DocumentationOther
Other
Database Apps
Please keep same general format. Adjust boxes as necessary. Delete unneeded boxes.
Please keep same general format. Adjust boxes as necessary. Delete unneeded boxes.
Project Schedule & Approach
ID
1
2
3
4
5
6
8
9
10
11
Task Name
Concept
Requirements
Design
Development
Testing
Documentation & Training
Deployment
Task 9
Task 10
Task 11
Start Date
01/01/2001
02/15/2001
02/15/2001
05/01/2001
06/01/2001
06/15/2001
11/06/2001
01/01/2001
01/01/2001
01/01/2001
End Date
03/02/2001
04/30/2001
04/30/2001
06/29/2001
08/30/2001
10/30/2001
01/22/2002
03/01/2001
03/01/2001
03/01/2001
45d53d53d44d65d98d
56d44d44d44d
Qtr 1 Qtr 2 Qtr 3 Qtr 4
2001DurationStatus
Red
Yellow
Green
7Post Deployment
10/31/2001
11/15/2001
12d
Double click the Visio Gantt chart to make changes. Please try to keep standard phases. List special milestones or variations as appropriate per project.
Double click the Visio Gantt chart to make changes. Please try to keep standard phases. List special milestones or variations as appropriate per project.
Example - Other phases may be used depending on project
Communications Management Plan
Monthly
Aug. Sept. Oct. Nov. Dec. Jan. ‘02 Feb. April MayMarch June
SVP Update: 1:1
Exec. Staff Mtgs Monthly
Every 6 weeksExtended Staff Mtgs
Progress Updates
All-Hands Qtrly Qtrly Qtrly
Learning
Formal training for roll-outs
Mentoring as needed
All
All
As NeededSr. Mgmt Staff Mtgs
Information SharingQtrlyOpen House Sessions Qtrly Qtrly
“Hot Sheets” Bi-Mthly Bi-Mthly Bi-Mthly Bi-Mthly Bi-Mthly
E-mails As Needed
Website Update As Needed
Posters As Needed
(Example)
Key Risks and Issues
Risk
(Example)
Too much change to department at one time
Confusion due to multiple initiatives
Competition for resources with other projects
Change readiness assessment and structured communication plan
Mitigation
Structured communication plan across program
Centralized management, dedicated resources, realistic timeframes
Other (Example)
Cost to Utilize Consultant for Project Management
4 consultants, 6 months => $XXX,000
Benefit
Project will be done in 6 months instead of 12 months
Steering Committee Members
• Name
• Name
• Name
• Name
• Name
• Name
• Name
(Example)
Expectations of Steering Committee
• Participate in all Steering Committee meetings
• Take ownership of issues and resolve by assigned date
• Commit resources in department as needed
• Commit 2 - 4 hour per month
• Assign one owner department to handle all changes
(Example)
Key Decisions to Be Made (Example)
Decision Owner Due Date Impact
Third partypackage or customimplementation
Joe Smith October, 2001 Overall projectschedule will beimpacted if notdecided by end ofOctober
# of Salespersonnel that willneed to be trained
Jane Smith December 12,2001
Overall projectschedule will beimpacted if notfinalized by 12/12
# of PC upgradesneeded to supportsoftware
Joe Smith October, 2001 Overall budgetwill be impacted ifnumber exceeds 20PCs
Next Steps
• Revise budget based on decisions
• Finalize make vs. buy decision
• Create detailed change enablement plan
(Example)