Project Management-Important Equations

11

Click here to load reader

description

Find the EV,SV,CV,AV ,SPI and CPI of the project

Transcript of Project Management-Important Equations

Page 1: Project Management-Important Equations

Project Management

Important Equations for the Final and Assignment Test

Mahesh Kodituwakku

Page 2: Project Management-Important Equations

EV = budget cost * % of work done

Page 3: Project Management-Important Equations

Scheduled Variance SV = EV - PV

If SV < 0 Project is behind the Scheduled

Page 4: Project Management-Important Equations

Cost Variance CV = EV - AC

If CV < 0 Cost over run

Page 5: Project Management-Important Equations

Account Variance AV = PV - AC

Difference between current budget and the actual expenditure

Page 6: Project Management-Important Equations

Performance Index

Page 7: Project Management-Important Equations

Scheduled Performance Index SPI = EV / PV

Page 8: Project Management-Important Equations

Cost Performance Index CPI = EV / AC

Page 9: Project Management-Important Equations

If SPI and CPI >1.0

Work head of scheduled and under budget

Page 10: Project Management-Important Equations

Study following details given below and find the EV,SV,CV,AV ,SPI and CPI of the project

Page 11: Project Management-Important Equations

Answer