Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project...

51
Project Management Project Management ERT461: Biosystems ERT461: Biosystems Engineering Design I Engineering Design I ERT424: Bioprocess Plant Design I ERT424: Bioprocess Plant Design I

Transcript of Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project...

Page 1: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Project Management Project Management

ERT461: Biosystems ERT461: Biosystems Engineering Design IEngineering Design I ERT424: Bioprocess Plant Design I ERT424: Bioprocess Plant Design I

Page 2: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Project DefinedA complex, non-routine, one-time effort limited by time, budget, resources, and performance specifications designed to meet customer needs.

Major Characteristics of a ProjectHas an established objective.Has a defined life span with a beginning and an end.Typically requires across-the-organizational participation.Involves doing something never been done before.Has specific time, cost, and performance requirements.

PS Introduction: What Is a Project ?PS Introduction: What Is a Project ?

Page 3: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Project Management Body of Project Management Body of KnowledgeKnowledge

PMBOK® Guide identifies generally recognized Project Management “Good practices”◦Correct application of “Good practices” can enhance the

chances of success over a wide range of different projects

Project Life Cycle Definition

Project Management Life Cycle

Five Project Management Process Groups

Nine Knowledge Areas

Page 4: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Project Management Body of Project Management Body of KnowledgeKnowledge

Project Life Cycle Definition

Project can be divided into phases to provide better management control with appropriate links to the ongoing operations of the performing organizations

Completion and approval of one or more deliverables (Scope definition) characterizes a project phase

Some deliverables can correspond to project management process groups (Initiating, Planning, Executing, Monitoring and Controlling, Closing), others are the end products or components of end products for which the project was conceived.

Page 5: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Project Management Life Cycle in the Project Management Life Cycle in the PMBOKPMBOK® ® GuideGuide

Five Project Management Process Groups (not necessarily phases)

◦Initiating◦Planning◦Executing◦Monitoring and Controlling

◦Closing

Page 6: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Knowledge areas in Knowledge areas in PMBOKPMBOK® ® GuideGuide

There are 42 project management processes organized into 9 knowledge areas

The Knowledge Areas are:

• Integration Management

• Scope Management• Time Management• Cost Management

• Quality Management• Human Resources Management• Communications Management• Risk Management• Procurement Management

Page 7: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

PMBOKPMBOK® ® GuideGuide Knowledge Areas Knowledge Areas

◦Charter & Scope Management

◦Project structures, WBS, Activities and Networks

◦Cost and Revenue Planning

◦Budget

◦Time Management

◦Customizing Activities and Networks

◦Date Planning

Page 8: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

PMBOKPMBOK® ® GuideGuide Knowledge Areas Knowledge Areas

◦Cost Management

◦Cost and Revenue Planning

◦Budget

◦Progress Analysis Workbench

◦Quality Management

◦Resource Planning

◦Material Planning

◦Assigning Documents, Procurement Processes, and Claim Management

Page 9: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

PMBOKPMBOK® ® GuideGuide Knowledge Areas Knowledge Areas–Procurement Management

–Material Planning–Assigning Documents, Procurement Processes

–Integration Management–Estimation and development of complete Project Plan

–Customizing Activities and Networks–Progress Analysis Workbench

Page 10: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Project SuccessProject Success

There are different ways to define project success:

◦The project met scope (understood technical functionality), time, and cost goals.

◦The project satisfied the customer/sponsor.◦The project produced the desired results

(expected technical functionality).

Page 11: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Typical Project ConstraintsTypical Project Constraints

Page 12: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Description of Process GroupsDescription of Process Groups

Initiating processes include actions to begin projects and project phases

Planning processes include devising and maintaining a workable scheme to ensure that the project meets its scope, time, and cost goals as well as organizational needs

Executing processes include coordinating people and other resources to carry out the project plans and produce the deliverables of the project or phase.◦A deliverable is a product or service produced or

provided as part of a project

Page 13: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Description of Process GroupsDescription of Process GroupsMonitoring and controlling processes

measure progress toward achieving project goals, monitor deviation from plans, and take corrective action to match progress with plans and customer expectations

Closing processes include formalizing acceptance of the project or phase and bringing it to an orderly end

Page 14: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Guidelines for Time Spent in Each Guidelines for Time Spent in Each Process GroupProcess GroupThe best or “alpha” project managers spend

more time on every process group than their counterparts except for execution, as follows:◦ Initiating: 2% vs. 1%◦ Planning: 21% vs. 11%◦ Executing: 69% vs. 82%◦ Controlling: 5% vs. 4%◦ Closing: 3% vs. 2%*

*Andy Crowe, Alpha Project Managers: What the Top 2% Know That Everyone Else Does Not, Velociteach Press(2006).

Page 15: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

PMBOKPMBOK® ® GuideGuide Framework Framework

Page 16: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Stakeholders and InfluencersStakeholders and Influencers• Project Stakeholders

–Project Manager–Customers and/or users–Performing organization–Project team members–Sponsor– Influencers–PMO

• Organizational Influences–Organizational Cultures and

styles–Organizational systems–Organizational structure

• Functional• Matrix• “Projectized”• Project manufacturing

Page 17: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

PMBOK® Guide PMBOK® Guide project project Management IntegrationManagement Integration

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fourth Edition, Project Management Institute, Inc., 2008, Figure 4-1, Page 73.

Page 18: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Initiating Process SummaryInitiating Process Summary

Senior management work together to:

Determine scope, time, and cost constraints

Identify the project sponsor

Select the project manager

Develop a business case for the project

Review processes/expectations

Determine if the project should be divided into two or more smaller projects

Project managers lead efforts to:

Identify and understand project stakeholders

Create the project charter

Hold a kick-off meeting

Page 19: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Inputs to develop Project CharterInputs to develop Project Charter

Charter should explicitly state “what” the project is about: Features and functions that characterize a product, service or result.

◦Product or Service description◦Strategic plan◦Statement of work◦Enterprise environmental factors◦Organizational process assets

Page 20: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Project Charter contentsProject Charter contents• Project Overview• Project Objectives• Requirements• Business Justification

– Strategic– Other

• Preliminary Resources Allocation• High-level time and cost estimates• Roles and Responsibilities• Sign-off• Attachments

Page 21: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Project Charter within SAP PSProject Charter within SAP PSUse Project Builder to create the following:

◦Project Overview◦Project Objectives◦Preliminary Resources Allocation◦High-level time and cost estimates (Root time and cost estimates)

◦Roles and Responsibilities◦Attachments

Page 22: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Project BuilderProject Builder

Page 23: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

PMBOK® Guide PMBOK® Guide Project Scope Project Scope ManagementManagement

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fourth Edition, Project Management Institute, Inc., 2008, Figure 5-1, Page 104.

Page 24: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Creating the Work Breakdown Creating the Work Breakdown StructureStructureA work breakdown structure (WBS) is

a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project

The WBS is a document that breaks all the work required for the project into discrete tasks, and groups those tasks into a logical hierarchy

Page 25: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Hierarchical Breakdown of the Hierarchical Breakdown of the WBSWBS

Page 26: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Work PackagesWork PackagesA Work Package is the Lowest Level of the WBS

◦ It is output-oriented in that it:

Defines work (what)

Identifies time to complete a work package (how long)

Identifies a time-phased budget to complete a work package (cost)

Identifies resources needed to complete a work package (how much)

Identifies a single person responsible for units of work (who)

Page 27: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

WBS DictionaryWBS DictionaryDescription of WBS work packages that includes:

◦ Statement of Work◦ Responsible organization◦ Schedules milestones◦ Quality requirements◦ Contract information ◦ Technical references◦ Resource requirements◦ Estimated cost

Page 28: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

PMBOK® Guide PMBOK® Guide Project Time Project Time ManagementManagement

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fourth Edition, Project Management Institute, Inc., 2008, Figure 6-1, Page 131.

Page 29: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Project Time Management Project Time Management Planning Tasks Planning Tasks Project Time Management occurs within SAP PS in

two levels, at the WBS Element, and at the Network activities

In some projects the work components are handled by others, or outsourced. In those situations, a project may be comprised of only WBS elements. Those elements can have time components attached to them.

If components within the WBS element will be carried out and monitored by the organization, then Networks and Activates are created for closer monitoring.

Page 30: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Project Time Management Project Time Management Planning TasksPlanning Tasks

Project time management involves the processes required to ensure timely completion of a project

The main planning tasks performed include defining activities, sequencing activities, estimating activity resource, estimating activity durations, and developing the project schedule

The main documents produced are an activity list and attributes, a milestone list, a network diagram, the activity resource requirements, the activity duration estimates, and a project schedule

Page 31: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

The Project NetworkThe Project NetworkA flow chart that graphically depicts the

sequence, interdependencies, and start and finish times of the project tasks/activities ◦ Provides the basis for scheduling labor and equipment◦ Provides an estimate of the project’s duration◦ Provides a basis for budgeting cash flow◦ Highlights activities that are “critical” and should not be delayed◦ Help managers get and stay on plan

Page 32: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Creating a Milestone ListCreating a Milestone List

• A milestone is a significant event in a project• It often takes several activities and a lot of work to

complete a milestone, but the milestone itself is like a marker to help identify necessary activities

• Project sponsors and senior managers often focus on major milestones when reviewing projects

• Sample milestones for many projects include:– Sign-off of key documents– Completion of specific deliverables– Completion of important process-related work, such as

awarding a contract to a supplier

Page 33: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Sequencing ActivitiesSequencing Activities

• Sequencing activities involves reviewing the activity list and attributes, project scope statement, and milestone list to determine the relationships or dependencies between activities

• A dependency or relationship relates to the sequencing of project activities or tasks– For example, does a certain activity have to be finished

before another one can start? – Can the project team do several activities in parallel?– Can some overlap?

• Sequencing activities has a significant impact on developing and managing a project schedule

Page 34: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Reasons for Creating Reasons for Creating DependenciesDependencies

• Mandatory dependencies are inherent in the nature of the work being performed on a project– You cannot hold training classes until the training materials are ready

• Discretionary dependencies are defined by the project team– A project team might follow good practice and not start detailed design work

until key stakeholders sign off on all of the analysis work

• External dependencies involve relationships between project and non-project activities– The installation of new software might depend on delivery of new hardware

from an external supplier. Even though the delivery of the new hardware might not be in the scope of the project, it should have an external dependency added to it because late delivery will affect the project schedule

Page 35: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Further defining Activities/TasksFurther defining Activities/Tasks• Task Sequencing and Predecessors

• Establishing durations– Expert judgment– Parametric estimating

• Establishing dependencies– Finish to Start– Finish to Finish– Start to Start– Start to Finish

Page 36: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Dependency TypesDependency Types

Page 37: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Constructing a Project NetworkConstructing a Project Network

Terminology

◦Path: a sequence of connected, dependent activities.

◦Critical path: the longest path through the activity network that allows for the completion of all project-related activities; the shortest expected time in which the entire project can be completed. Delays on the critical path will delay completion of the entire project.

Page 38: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

PMBOK® Guide PMBOK® Guide Project Cost Project Cost OverviewOverview

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fourth Edition, Project Management Institute, Inc., 2008, Figure 7-1, Page 167.

Page 39: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

PMBOK® Guide PMBOK® Guide Project Cost Project Cost OverviewOverview

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fourth Edition, Project Management Institute, Inc., 2008, Figure 7-1, Page 167.

Page 40: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

PMBOK® Guide PMBOK® Guide Project Cost Project Cost OverviewOverview

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fourth Edition, Project Management Institute, Inc., 2008, Figure 7-1, Page 167.

Page 41: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

PMBOK® Guide PMBOK® Guide Project Quality Project Quality Management OverviewManagement Overview

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fourth Edition, Project Management Institute, Inc., 2008, Figure 8-1, Page 191.

Page 42: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

PMBOK® Guide PMBOK® Guide Project Human Project Human Resource Management OverviewResource Management Overview

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fourth Edition, Project Management Institute, Inc., 2008, Figure 9-1, Page 217.

Page 43: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

PMBOK® Guide PMBOK® Guide Project Project Communications Management Communications Management OverviewOverview

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fourth Edition, Project Management Institute, Inc., 2008, Figure 10-1, Page 244.

Page 44: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

PMBOK® Guide PMBOK® Guide Project Risk Project Risk Management OverviewManagement Overview

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fourth Edition, Project Management Institute, Inc., 2008, Figure 11-1, Page 274.

Page 45: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

PMBOK® Guide PMBOK® Guide Project Project Procurement Management Procurement Management OverviewOverview

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fourth Edition, Project Management Institute, Inc., 2008, Figure 12-1, Page 314.

Page 46: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Change is a ProcessChange is a Process

PresentState

TransitionState

DesiredState

Driving Forces Resisting Forces

Unfreezing Changing Refreezing

Page 47: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Summary of Project Closing OutputsSummary of Project Closing OutputsKnowledge area Closing process Outputs

Project integration management

Close project or phase Final product, service, or result transitionOrganizational process assets updates

Project procurement management

Close procurements Closed procurementsOrganizational process assets updates

Page 48: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

The Quadruple ConstraintThe Quadruple Constraint

Page 49: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Project Management Tools and Project Management Tools and TechniquesTechniquesProject management tools and techniques assist

project managers and their teams in various aspects of project management.

Note that a tool or technique is more than just a software package.

Specific tools and techniques include:◦Project charters, scope statements, and WBS (scope

deliverables)◦Gantt charts, network diagrams, critical path analyses

(time)◦Net present value, cost estimates, and earned value

management (cost)

Page 50: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Common Project Management Common Project Management Tools and Techniques by Tools and Techniques by Knowledge AreasKnowledge Areas

Schwalbe, Information Technology Project Management, Sixth Edition, 2010

Page 51: Project Management ERT461: Biosystems Engineering Design I ERT424: Bioprocess Plant Design I Project Management ERT461: Biosystems Engineering Design I.

Common Project Management Common Project Management Tools and Techniques by Tools and Techniques by Knowledge AreasKnowledge Areas

Schwalbe, Information Technology Project Management, Sixth Edition, 2010