project management 10.2 step to success chapter 10
25
Team Project 10.1 • STEPS TO SUCCESS • IE415 • Team members : 1 - Nawaf 2 - Abdul hakim 3 - Ali 4 - Sultan 5 - Ahmed
description
project management 10.2 step to success chapter 10 I want to help you guys with this project hope you enjoy it.
Transcript of project management 10.2 step to success chapter 10
Team Project 10.1
•STEPS TO SUCCESS •IE415
•Team members: 1 -Nawaf
2 -Abdul hakim3 -Ali
4 -Sultan5 -Ahmed
Project Network By (POM)
Project Network By (Excel)
Critical Path
CP= 27.5 Weeks
C
Project Time won’t be Changed, Because C Slack was 1, Changed to be Zero also Project will
Be Finish on the right time.
IFrom 5 to 4
( I )have Slack 4.5 so it’s not going to effect theProject Time
F(iii ) F is going to effect on Project Time.
The new Deadline = 29 weeks.
M(iv )it’s going to effect the project time
The new deadline is 28
• •23 Project Time was 27.5 and crashed to
Project Deadline is 24 weeks now, and
Costing now $59,466.