Project Delivery Method Selection Tool
-
Upload
center-for-transportation-research-ut-austin -
Category
Engineering
-
view
300 -
download
3
Transcript of Project Delivery Method Selection Tool
COLLABORATE. INNOVATE. EDUCATE.
Project Delivery Method Selection Tool
2016 CTR Annual SymposiumApril 13, 2016
COLLABORATE. INNOVATE. EDUCATE.
Project Delivery Selection Tool• History
– TxDOT received legislative authority in 2012 to use Design-Build
• Other approaches (CMAR) had been considered• TxDOT previously limited to design-bid-build (DBB) method or
limited application of comprehensive development agreements
• Need– Decision tool as projects are developed– Objective analysis for determining project delivery method– Specific to Texas
COLLABORATE. INNOVATE. EDUCATE.
AGENDA
• Motivation and goals• Relation to prior work• Selection approach• Expert input and validation• Tool demonstration• Concluding remarks
COLLABORATE. INNOVATE. EDUCATE.
Motivation: Main Goals of the Tool• Help decision makers make an objective choice of project
delivery method, driven by:– weighted project goals
– applicable project characteristics
• Transparent and flexible
• Modifiable and updateable (based on MS Excel)
• Recommendations will be consistent across projects and users
COLLABORATE. INNOVATE. EDUCATE.
Project Delivery Method Selection Tool
• Design - Bid - Build• Design - Build• Future – CMAR, others
These alternatives only represent major approaches. Specific contract strategies (such as A+B, multiple primes, Incentives, Operate & Maintain) should be analyzed after determining the delivery method, and are out of the scope at this time.
Project Delivery Alternatives
COLLABORATE. INNOVATE. EDUCATE.
Project Team
CTR/UT Team
• Nabeel Khwaja, P.E
• Mayra Martinez
• Bill O’Brien, Ph.D., P.E.
• Jim O’Connor, Ph.D., P.E.
TxDOT Team
• Bill Hale, P.E. (sponsor)
• Richard Kirby, P.E.
• Tracey Friggle Logan, P.E.
• Duane Milligan, P.E.
• Katie Nees, P.E.
COLLABORATE. INNOVATE. EDUCATE.
Prior Work• TRB – Evaluation of Project Delivery Methods• Colorado DOT Methodology• CII – Project Delivery Contract Strategy• Georgia DOT Tool• Florida DOT• Virginia DOT• Minnesota DOT• New York DOT• Washington DOT• NTTA Model• AASHTO
COLLABORATE. INNOVATE. EDUCATE.
Transit Cooperative Research ProgramFramework for Texas Model
3 stages:- Tier 1 – Qualitative (Like CDOT)
Structured discussion
- Tier 2 – Quantitative (Texas model)Decision Matrix
- Tier 3 – Risk Analysis (contracting strategies)Detailed analysis of specific risks
Objective: “To assist transit agencies in evaluating and selecting the most appropriate project delivery method for their projects and in documenting this decision in a Project Delivery Decision Report”
COLLABORATE. INNOVATE. EDUCATE.
Tier 1 Qualitative ToolsCDOT matrix
COLLABORATE. INNOVATE. EDUCATE.
Tier 2 Qualitative Tools
GDOT Design-Build Suitability Assessment
11 7 8 6 12 2 5 3 9 4 1 1030.0
40.0
50.0
60.0
70.0
80.0
90.0
PDCS Rating
CII’s Delivery Methods’ Ranking
COLLABORATE. INNOVATE. EDUCATE.
Prior Work: Our Findings
• All mix dependent and independent variables:– Mix Cause: project characteristics, and – Effect: Project goals
• Commonality among factors• Extracted a list of 34 factors that owners
consider when selecting a delivery method• Factor list was consolidated with TxDOT input
COLLABORATE. INNOVATE. EDUCATE.
34 Factors from existing methods & literature review
INDEPENDENT VARIABLES
PROJECT CHARACTERISTICS
Inherent to the project. Cannot be
changed.
DEPENDENT VARIABLES
PROJECT GOALS
Owner objectives. Achievement will
depend on the project
characteristics and the delivery method
chosen.
COLLABORATE. INNOVATE. EDUCATE.
Selection Approach – Method Overview
Delivery methods
Project performance by objectives and priorities.
Project characteristics
Hinder or leverage
Influence
2. Choose outcomes1. Score characteristics
3. Recommend method(heat map – not absolutes)
COLLABORATE. INNOVATE. EDUCATE.
Project Delivery Selection Tool: Project Goals
Lower capital cost
The contractual cost of the project must be the lowest reasonable; the budget available is tight.
Higher cost predictability
The project must be completed within the budget. The agency wants to avoid cost growth.
Higher schedule predictability
The project must be completed within the target schedule. The agency wants to avoid schedule growth.
Lower capital maintenance costs
The agency is concerned about minimizing the maintenance costs during the life cycle of the project.
-Safety & Quality are always considered target objectives-Target duration can be met with any Delivery Method and the proper incentives
COLLABORATE. INNOVATE. EDUCATE.
Project Delivery Selection Tool: Project Characteristics
-34 Characteristics from review of prior work-The team refined the list based on:
• Scope definition characteristics • Overlaps• Non-differentiating factors• Applicability to TxDOT projects
COLLABORATE. INNOVATE. EDUCATE.
Project Delivery Selection Tool: Project Characteristics
1 Project has well known site conditions that won't cause significant field changes.
2 The project will benefit from the introduction of innovative methodologies early in the planning/design phase.
3 The project design (PS&E) is currently at an advanced stage; the agency wants to avoid changes or rework in design.
4 The project requires the benefit of designer-contractor integration to reduce coordination challenges.
5 Prescriptive project requirements for methods, materials, and/or procedures limit contractor innovation in terms of alternatives.
6For this project, alternate delivery methods shall create incremental agency efforts and expenses that are expected to be greater than the savings in capital expenses.
COLLABORATE. INNOVATE. EDUCATE.
Project Delivery Selection Tool: Project Characteristics
7 Early completion will add significant extra value for key project stakeholders.
8 The agency is better equipped than the contractor to manage third party issues.
9 The project is likely to benefit from shifting the risk of third party issues to the contractor
10 Completion date of ROW acquisition is highly uncertain.
11Utility relocations have not been completely identified and are likely to result in important changes in the design, cost, and/or schedule of the project.
12 The project includes permits requiring coordination and regulatory approval during the design and/or construction phases of the project
COLLABORATE. INNOVATE. EDUCATE.
Obtaining Data to Assess Weightings
TxDOT
FHWA
AGC
ACEC
Workshop Participants
Two workshops• Refine characteristics• Weight characteristics against
goals for each method• Validation and review of
responses – understand outliers
• Weightings reflect summary wisdom of community
COLLABORATE. INNOVATE. EDUCATE.
Project Delivery Selection Tool
1. Project characteristics
2. Project objectives.
INPUT
COLLABORATE. INNOVATE. EDUCATE.
Project Delivery Selection Tool
3. Delivery methods
OUTPUT
COLLABORATE. INNOVATE. EDUCATE.
Project Delivery Selection ToolDesign- Build Delivery Method (Most Suitable)
Most Supportive Characteristics Least Supportive Characteristics
The project will benefit from the introduction of innovative methodologies early in the planning/design phase.
The agency is better equipped than the contractor to manage third party issues.
The project requires the benefit of designer-contractor integration to reduce coordination challenges.
Prescriptive project requirements for methods, materials, and/or procedures limit contractor innovation in terms of alternatives.
Early completion will add significant extra value for key project stakeholders.
For this project, alternate delivery methods shall create incremental agency efforts and expenses that are expected to be greater than the savings in capital expenses.
Design- Bid-Build Delivery Method (Least Suitable)
Most Supportive Characteristics Least Supportive Characteristics
The project has well-known site conditions that won’t cause significant field changes.
Completion date of ROW acquisition is highly uncertain.
The agency is better equipped than the contractor to manage third party issues.
Utility relocations have not been completely identified and are likely to result in important changes in the design, cost, and/or schedule of the project.
The project will benefit from the introduction of innovative methodologies early in the planning/design phase.
The project includes permits requiring coordination and regulator approval during the design and/or construction phases of the project.
Most and least supportive
characteristics for each
delivery method
OUTPUT
COLLABORATE. INNOVATE. EDUCATE.
Tool Validation• Case-study based• Tool should reproduce human decision making• To ensure the tool gives recommendations aligned with
experts’ expectations
1
• Projects’ characteristics & objectives provided by PM
2
• Project ran through the tool
3
• Final recom-mendation is discussed
COLLABORATE. INNOVATE. EDUCATE.
Tool Validation
• Projects Tested Project DBB DB Dif. Recommendation
1 75 Rehabilitation 0.32 -0.07 0.39 DBB
2 I-69 0.08 -0.02 0.1 Tier 3
3 Roger Deck Park 0.16 0.18 -0.02 Tier 3
4 SH 360 0 0.13 -0.13 Tier 3
5 Midtown Express (SH183) -0.07 0.27 -0.34 DB
6 LBJ East -0.16 0.32 -0.48 DB
7 SH-146 -0.26 0.24 -0.5 DB
COLLABORATE. INNOVATE. EDUCATE.
Tool Demonstration
COLLABORATE. INNOVATE. EDUCATE.
Concluding Remarks• Creation of an objective MS Excel-based decision-support
tool (Tier 2)– Including and differentiation of project goals and projects’
characteristics– Giving quantitative measures for each alternative: DBB and DB
• Developed with the input of experienced TxDOT personnel• Weighted with input from broad community of experts in
TxDOT projects• Validated with range of TxDOT projects• Flexible tool: easily auditable and modifiable