PROJECT C (ORD5) DATE: February 12th, 2021 WEEKLY SUMMARY REPORT Facility Address: 7001 Vollmer Rd., Matteson 60443

Transcript of PROJECT C (ORD5) - Village of Matteson

PROJECT C (ORD5)DATE: February 12th, 2021

WEEKLY SUMMARY REPORT

Facility Address: 7001 Vollmer Rd., Matteson 60443

PROGRESS UPDATEVideos Link (Updated 02-02-21):https://www.dropbox.com/s/d5lzghkdmlcp6f4/V2.mp4?dl=0Arial Photos & Stills (Updated 02-02-21):https://www.dropbox.com/sh/gnio568au1bph6e/AACIpjelpTKsLAKJGOssa1Oia/2021-02-02?dl=0&subfolder_nav_tracking=1

Jobsite Webcam Link:https://app.oxblue.com/open/wtc/projectc

Site Construction:Building Exterior:o All American Began Installing Roof on the SW (CL 18-12 / S-T) – Weather

Permittingo All American Began Installing Roof on the SE (CL 12-6 / S-T) – Weather

Permittingo All American Continued Installing Office Roof – Weather Permittingo Levy Began Installing CFMF Studs – CL 8 – 9 o Levy Began Installing CFMF Studs/Clips – CL 9 – 12o Levy Continued Installing CFMF Clips/Studs – CL 15 – 12 o UISC Continued Installing IMP Panels – Area 7W –CL 19 – 16 – Weather

Permittingo UISC Began Installing IMP Panels – Area 7E – CL 2.5 – 5

Building Interior Continued:o Connelly Began Installing VRC Power in Shaft Bo Otis Continued Prepping and Welding Rails at VRC – Shafts B, C, Do F.E. Moran Continued Installing Upper System Bump Outso F.E. Moran Continued Installing Sprinklers on Floors 2 & 3o F.E. Moran Began Installing Sprinkler 1st Floor – 14 & 15o F.E Moran Continued Working Under AFE Platformo F.E. Moran Began Working Under Inbound Platformo AMS Continued to Install Bathroom Piping in Wall – Bump Outs 10o AMS Began to Install Bathroom Piping in Wall – Bump Outs 55o AMS Began to Install Bathroom Piping – Ground Floor Bathroomso AMS Continued Installing Domestic Water Distributiono AMS Began Installing Pump Room Build Outo State Mechanical Continued to Install 1st Floor Refrigeration Lines – Main Runso State Mechanical Continued Work on High Roof Unit Duct and Tie-Inso State Mechanical Continued Work on Gas Line Distributiono State Mechanical Continued Installing BMS Wiring – Ground Floor & Floors 2 & 3o State Mechanical Continued Installing Ductwork – 1st Flooro State Mechanical Continued Installing VRF Systems – Under AFE & Under Inboundo State Mechanical Continued Installing Gas Line UG to Generatoro State Mechanical Continued to Install Ductwork & Insulate – Perimeter Shafts All Floorso State Mechanical Continued to Install Ductwork & Insulate – Middle Shafts All Floorso Thorne Continued Work on Shafts A & B – Framing and Drywallo Thorne Began 1st Floor VRC Shaft Framingo SuperFlat Began 2nd Floor Concrete Remediation

Building Interior:o Connelly Continued 2nd Floor Fence Line Rough-in and Distributiono Connelly Continued Working on 2nd ,3rd ,4th & 5th floors – North Electrical Roomso Connelly Continued Working on 2nd ,3rd ,4th & 5th floors – South Electrical Roomso Connelly Continued 4th Floor Distributiono Connelly Continued Installing Lights In Area 4o Connelly Continued Installing Fire Alarms In Area 4o Connelly Continued Distribution & Wire Puling In Area 4o Connelly Continued 5th Floor Rough-in & Distributiono Connelly Continued Installing Lights In Area 5o Connelly Continued Installing Fire Alarms In Area 5o Connelly Continued Distribution & Wire Puling In Area 5o Connelly Continued Installing Light Fixtures – West 2nd ,3rd ,4th & 5th Floorso Connelly Continued Installing Light Fixtures – East 4th Flooro Connelly Began Tap Box Install

PROGRESS UPDATESteel – East Side (Sub-Sequence 92):o Area Erectors Continued Erecting, Detailing and Installing Studs

Steel – Subsequence 104 – SLAM Platformo Area Erectors Continued Erecting, Detailing, Decking and Installing Studs - Delayed

Steel – Subsequences 98-103 – AR Sort :o Area Erectors to Continued Erecting, Detailing, Decking and Installing Studs on 99o Area Erectors to Continued Erecting, Detailing, Decking and Installing Studs on 100o Area Erectors to Continued Erecting, Detailing, Decking and Installing Studs on 101o Area Erectors to Continued Erecting, Detailing, Decking and Installing Studs on 102

1st Floor Mezzanines:o AIS Continued Installing AFE Platformo AIS Continued Installing In-Bound Platformo AIS Continued Installing Shipping Sorter Platformo Thorne Continued Installing Resin deck In-Boundo Thorne Began to Install Resin Deck AFE

Concrete – East Side:o Scurto Continued to Prep & Pour SOD – 2E12o Scurto Began to Prep & Pour SOD 3E12o Scurto Began to Prep & Pour SOD 4E11/12o Scurto Began to Prep & Pour SOG 25 – Pending Ground Thawo Scurto Began to Prep & Pour – SLAM o AMS to Complete UG MEP/Stub Up – SOG 25

Concrete – West Side:o Scurto Continued to Prep & Pour SOD – 2W12o Scurto Continued to Prep & Pour SOD – 3W12o Scurto Began to Prep & Pour SOD – 4W11/12o Scurto Continued to Prep & Pour SOD – 5W9/10

PROJECT LOOK AHEADBuilding Interior Look Ahead Continued 02/19/2021:o Connelly to Continue 2nd Floor Fence Line Rough-in & Distributiono Connelly to Continue 2nd Floor Electrical Rooms – North & Southo Connelly to Continue 3rd Floor Electrical Rooms – North & Southo Connelly to Continue 4th Floor Electrical Rooms – North & Southo Connelly to Continue 4th Floor Rough-in and Distributiono Connelly to Continue 5th Floor Rough-in and Distributiono Connelly to Continue 5th Floor Electrical Rooms – North & Southo Connelly to Continue Installing Light Fixtures on the 4th & 5th Floors –Westo Connelly to Continue Installing Light Fixtures on the 4th Floor - Easto Connelly to Continue Installing Tap Boxo Connelly to Continue Installing Lights in Area 5o Connelly to Continue Installing Fire Alarms in Area 5o Connelly to Continue Distribution & Wire Pulling in Area 5o AMS to Continue Installing Domestic Water Distributiono AMS to Continue Installing Bathroom Piping in Wall – Bump Outs 10, 55, Ground Flooro AMS to Begin Pump Room Build Outo AMS to Begin Bathroom Test & Insulate – Bump Outs 8 & 54o State Mechanical to Continue Installing High Roof Duct & Tie-inso State Mechanical to Begin Installing VRF Systems – Under Inbound & AFEo State Mechanical to Continue Installing 1st Floor Refrigeration Lines – Main Runso State Mechanical to Continue Gas Line Distributiono State Mechanical to Continue Installing Gas Line UG to Generatoro State Mechanical to Continue Installing High Roof Unit Duct & Tie-Inso State Mechanical to Continue Installing BMS Wiring – Ground Floor & Floors 2 & 3o State Mechanical to Continue Ductwork and Insulating – Perimeter Shafts All Floorso Thorne to Continue Shaft A Framing & Drywallo Thorne to Close Up Restroom/ Break Room Wallso Thorne to Continue 1st floor VRC Shaft Framingo Thorne to Begin Mechanical Duct Shaft Framing & Drywallo SuperFlat to Continue 2nd Floor Concrete Floor Remediation

Building Exterior Look Ahead 02/19/2021:o All American to Continue Installing Roof – SW (CL 18-12 / S-T)o All American to Begin Installing Roof – Remaining Bump Out Do All American to Continue Installing Roof on Officeo Levy to Continue Installing CFMF Studs/Clips – CL 9 – 12o UISC to Continue Installing IMP Panels – Area 7E CL 2.5-5, CL 6-8 o Trout to Begin Installing Windows – 94 & 55

1st Floor Mezzanines Look Ahead 02/19/2021:o Thorne to Continue Installing Resin Deck AFEo Thorne to Begin Installing Shipping Sorter

Concrete – East Side Look Ahead 02/19/2021:o Scurto to Continue to Prep & Pour SOD 2E12o Scurto to Continue to Prep & Pour SOD 3E12o Scurto to Continue to Prep & Pour SOD 4E11/12o Scurto to Begin to Prep & Pour SOD 5E11/12

Concrete – West Side Look Ahead 02/19/2021:o Scurto to Begin Prepping & Pouring SOG – 25o Scurto to Begin Prepping and Pouring SOD - SLAMo Scurto to Continue to Prep & Pour SOD 2W12o Scurto to Continue to Prep & Pour SOD 4W11/12o Scurto to Begin to Prep & Pour SOD 5W11/12

Interior Steel – Subsequences 98-103 – AR Sort 02/19/2021:o Area Erectors to Continue Erecting, Detailing and Installing Studs on 99o Area Erectors to Continue Erecting, Detailing and Installing Studs on 100o Area Erectors to Continue Erecting, Detailing and Installing Studs on 101o Area Erectors to Continue Erecting, Detailing and Installing Studs on 102o KCI to Begin Scan & Analysis

Building Interior Look Ahead 02/19/2021:o Otis to Continue Installing Shafts B, C & D – VRC Installo F.E. Moran to Continue Work Under AFE Platformo F.E. Moran to Continue Installing 2nd & 3rd Floor Sprinkler System

ON-SITE MANPOWER

Average Number of On-Site Workers:Whiting-Turner 18

Dematic 50

Testing Service Corporation 3

Windy City Drones 2

V3 Companies 0

PirTano Construction 3

Crystal Clear Cleaners 1

Jobsite Safety 3

Scurto 78

Connelly Electric 96

AMS Mechanical Systems 16

DMAC Security 2

Installed Building Products 4

Illinois Central Sweeping 0

Gallagher 0

Powers & Sons 29

Cooper Steel 85

Duco 2

ATMI Precast 6

Schuepfer, Inc. 4

The Levy Co. 0

State Mechanical 33

F.E. Moran Fire Protection 7

Ascher Brothers Co. 5

Airy’s Inc. 0

United Insulated Structures Corp. 11

Whiting-Turner Safety Notes:Observations 346

Violations 17

Recognitions 0

Incidents 11

Lost Time Incidents 0

Site Safety Orientations 1,816

Total Project Man Hours to Date 490,434

Average Man Hors Per Day 4,200

Average Number of On-Site Workers:

Thorne Associates 19

Advantage Industrial Systems 16

All American Exterior Solutions 0

Safway Atlantic 1

Otis Elevator Company 14

Trout Glass & Mirror, Inc. 0

Installed Building Products, LLC 1

DuPage Overhead Door 0

ASI Signage 2

Ohio Valley Concrete Polishing 2

Total 512

LOCAL MANPOWER (COOK COUNTY)Local Participation (Cook County):

Arlington Heights 9 Workers

Rolling Meadows 1 Worker

Rosemont 1 Worker

Glenview 2 Workers

Northbrook 2 Workers

Palatine 9 Workers

Streamwood 12 Workers

Hanover Park 5 Workers

River Forest 1 Worker

Broadview 2 Workers

Melrose Park 11 Workers

Berkeley 1 Worker

Northlake 1 Worker

Hoffman Estates 8 Workers

River Grove 1 Worker

Schaumburg 10 Workers

Berwyn 4 Workers

Calumet City 6 Workers

Chicago Heights 11 Workers

Chicago Ridge 3 Workers

Homewood 9 Workers

Lemont 9 Workers

Midlothian 12 Workers

Maywood 2 Workers

Golf 1 Worker

Lansing 7 Workers

Glenwood 1 Worker

Blue Island 6 Workers

Dolton 2 Workers

Des Plaines 7 Workers

Riverdale 3 Workers

Elmwood Park 2 Workers

Hickory Hills 3 Workers

Burbank 8 Workers

Orland Park 22 Workers

Palos Park 4 Workers

Palos Hills 7 Workers

Park Forest 2 Workers

Posen 3 Workers

South Holland 1 Worker

Tinley Park 33 Workers

Country Club Hills 4 Workers

Willow Springs 3 Workers

Worth 5 Workers

LaGrange Park 7 Workers

Chicago 185 Workers

Alsip 9 Workers

Cicero 23 Workers

Evergreen Park 11 Workers

Oak Forest 23 Workers

Oak Lawn 22 Workers

Skokie 1 Worker

Matteson 2 Workers

Total Number of Workers from Cook County 539

Facility Address: 7001 Vollmer Rd., Matteson 60443

PROJECT AWARDED SUBCONTRACTORAwarded Subcontractors & Suppliers:(Package # - Description - Trade Contractor Name)

o 01A – Trailers – Williams Scotsman

o 01B – Temporary Fencing – Industrial Fencing

o 01C – Webcam Services – Ox Blue

o 01D – Site Security – DMAC Security

o 01F – Drone Service – Windy City Drones

o 01G –Office Copier – Proven IT

o 01H – Preventative Cleaning Services – Luse Holdings

o 01I – Safety Professional – Job-Site Safety

o 01J – COVID-19 Technician - Job-Site Safety

o 01K – Material Hoist/Scaffolding – Safway Atlantic

o 01P – Temporary Heaters – Sunbelt Rentals

o 01R – Propane – Ferrellgas

o 02A – Surveying – V3 Companies

o 03A – Concrete – Scurto Cement

o 03B – Precast – ATMI Precast

o 03C – Concrete Expansion Joints – Golf Construction

o 03D – Floor Remediation – Ohio Valley Concrete Polishing

o 03E – Site & Pad Restoration/Material Handling – Schuepfer

o 04A – Masonry – Midwest Masonry

o 05A – Steel Fabricators – Cooper Steel

o 05A – Steel Erectors – Area Erectors, Inc.

o 05B – Prefabricated Mezzanines - Advantage Industrial Systems, LLC

o 06B – CFMC – The Levy Co

o 06C – Casework – CMI

o 07A – Roofing – All American Exterior Solutions

o 07B – IMP – United Insulated Structures Corp.

o 08A – Exterior Glass & Glazing – Trout Glass & Mirror, Inc.

Awarded Subcontractors & Suppliers:(Package # - Description - Trade Contractor Name)

o 08B – Doors, Frames, Hardware – Block Iron

o 09A – Rough & Finish Carpentry – Thorne Associates

o 09B – Interior & Exterior Painting – Ascher Brothers Co.

o 09F – Epoxy Flooring – Artlow Systems

o 10A – Specialties – Prestige Distribution

o 10B – Signage – ASI Signage

o 10C – Site & Street Shelters – Shelters Direct

o 10D – Kiva Rail System – NPSG Global

o 10E – Operable Partition – Modernfold Chicago, Inc.

o 11A – Loading Dock Equipment & OH Doors - Entermatic

o 12A – Window Blinds – Everything Div. 12

o 13A – Pre-Engineered Structures – Shelters Direct

o 14A – Elevators – Kone

o 21A – Fire Protection – FE Moran

o 22A – Plumbing – AMS

o 22B Underground Plumbing – AMS Mechanical Systems Inc.

o 23A – HVAC – State Mechanical

o 23B – Testing & Balancing – Fulton

o 23C – Controls – CBRE

o 26A – Electrical & Fire Alarm – Connelly Electrical

o 26B – Temporary Power – Block Electric

o 26C – Underground Electrical – Connelly Electric

o 27A – Low Voltage/Telecom – IES

o 28A – Security – IPS

o 31A – Ground Improvements – Michels Corp.

o 31B – Sitework – Plote Construction

o 32A – Asphalt Paving – Gallagher Asphalt

o 32B – Site Fence – Action Fence

o 32C – Landscape & Irrigation – Classic Landscape, Ltd.

o 32D – Site Concrete – DUCO

o 33A – Site Utilities – PirTano Construction

PROJECT MILESTONES AND TENANT EARLY ACCESS

PROJECT MILESTONES:Award Project to WT 03/09/20

Notice to Proceed 03/10/20

Start Construction 04/15/20

Deliver Building Pad & Subgrade Column Lines 12-24 05/01/20

Deliver Building Pad & Subgrade Column Lines 1-12 05/21/20

Start SOG MEP Under Slab Work 06/11/20

Start Steel Erection 08/03/20

Start Precast Erection 10/06/20

Start Slab on Grade Pours 10/09/20

Start Roofing 11/04/20

Permanent Power Available 11/04/20

Concrete Slab on Grade Substantially Complete 02/17/21

Main Building Structural Steel Substantially Complete 02/22/21

Demarc Construction Complete 02/22/21

Concrete Slab on Deck Pours Substantially Complete 02/26/21

Precast Substantially Complete 03/04/21

MDF Construction Complete (Includes Owner Low Voltage Room Fit Out)

03/08/21

Roofing Substantially Complete 03/29/21

Substantial Completion 08/15/21

Tenant Go Live/First Receive Date 08/29/21

TENANT EARLY ACCESS:Ground Floor Bump A

Ground Floor Area 101/18/21

Mezzanine Level Area 2 01/25/21

Ground/Mezzanine Area 3 02/08/21

Ground/Mezzanine Area 4 02/22/21

Ground Floor Bump D

Ground/Mezzanine Area 503/15/21

RSP G+1 through 4 South Available for AR Survey 03/29/21

Ground/Mezzanine Area 6

Area A RSP G+1 East04/12/21

Area C RSP G+2 East 04/19/21

Ground Floor Bump C

Area B RSP G+1 West 04/26/21

Area D RSP G+2 West 05/03/21

Ground Floor Bump B

Area E RSP G+3 East05/10/21

Area G RSP G+4 East 05/17/21

Area F RSP G+3 West 05/24/21

Area H RSP G+4 West 05/28/21

Ground Floor Area 7 07/02/21

PERMIT LOG

PERMIT LOG:

Permit Type Permit Number Date Submitted Current Status Date Received Notes

MWRD 20031 02/21/20 Approved 04/16/2020

Foundations/ UG Utilities N/A 04/06/20 Approved 04/30/2020

Shell 1120955 04/16/20 Approved 05/28/2020

Water Main Extension - Onsite (IEPA) 1140-FY2020 05/29/2020 Approved 07/01/2020

Water Main Extension - Offsite (IEPA) 1261-FY2020 07/01/2020 Approved 07/06/2020

T.I. ILR-10BG72 04/15/2020 Approved 05/21/2020

Cook County Highway Permit Offsite Utilities

20-07-10067-C 05/19/2020 Approved 08/03/2020

Building PermitBP2020-1249 04/15/2020 Approved 08/01/2020

Permanent Site FencingBP2020-564 04/15/2020 Approved 08/01/2020

Off-Site MWRD20-116 05/20/2020 Approved 09/10/2020

Partial Operating Permit1140-FY2020, Partial A Approved 10/19/2020

Off-Site Ridgeland Ave20-07-10067-C 11/11/2020 Approved 11/17/2020

WEATHER TRACKING

Month Calendar DaysPlanned Weather

DaysActual

Weather Days

December ’20 21 9 6

January ‘21 18 12 8

February ’21 19 9 8

Contractor(s) Loss Day of Work*

02/04/2021 Snow Started at Noon. Exterior Activities Shutdown

02/05/2021 Extreme Cold Shut Down Exterior Activities

02/06/2021 Extreme Cold Shut Down Exterior Activities

02/08/2021 Extreme Cold Shut Down Exterior Activities

02/10/2021 Extreme Cold Shut Down Exterior Activities

02/11/2021 Extreme Cold Shut Down Exterior Activities

02/12/2021 Extreme Cold Shut Down Exterior Activities

*Contractors still performed work these days, specific items impacted

Precipitation

02/04/2021 4.00 Inches

02/08/2021 0.50 Inches

02/10/2021 0.25 InchesAverage High 21 Average Low 11

0 0 0

4

0 0 00.5

00.25

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 00000

1

2

3

4

5

2/1

/20

21

2/2

/20

21

2/3

/20

21

2/4

/20

21

2/5

/20

21

2/6

/20

21

2/7

/20

21

2/8

/20

21

2/9

/20

21

2/1

0/2

2/1

1/2

2/1

2/2

2/1

3/2

2/1

4/2

2/1

5/2

2/1

6/2

2/1

7/2

2/1

8/2

2/1

9/2

2/2

0/2

2/2

1/2

2/2

2/2

2/2

3/2

2/2

4/2

2/2

5/2

2/2

6/2

2/2

7/2

2/2

8/2

PRECIPITATION (INCHES)

-10

-5

0

5

10

15

20

25

30

35

40

2/1

/20

21

2/2

/20

21

2/3

/20

21

2/4

/20

21

2/5

/20

21

2/6

/20

21

2/7

/20

21

2/8

/20

21

2/9

/20

21

2/1

0/2

02

1

2/1

1/2

02

1

2/1

2/2

02

1

2/1

3/2

02

1

2/1

4/2

02

1

2/1

5/2

02

1

2/1

6/2

02

1

2/1

7/2

02

1

2/1

8/2

02

1

2/1

9/2

02

1

2/2

0/2

02

1

2/2

1/2

02

1

2/2

2/2

02

1

2/2

3/2

02

1

2/2

4/2

02

1

2/2

5/2

02

1

2/2

6/2

02

1

2/2

7/2

02

1

2/2

8/2

02

1

High/Low TemperaturesFebruary

High Temp Low Temp

UNDERGROUND UTILITIESUG Utilities Progress:

100%

0%

Sanitary Progress

Complete Remaining

90%

10%

Domestic Water Progress

Complete Remaining

100%

0%

Fire MainProgress

Complete Remaining

95%

5%

Storm Progress

Complete Remaining

SLAB ON GRADE PROGRESS

78%

22%

Rebar Progress

Complete Remaining

SOG Progress:

78%

22%

Poured Concrete Progress

Complete Remaining

STEEL ERECTION G+0.5 (Mezzanine) PROGRESS

68%

32%

Column & Beams Progress

Complete Remaining

Mezzanine Progress:

19%

81%

Metal Deck Progress

Complete Remaining

65%

35%

Resin Deck Progress

Complete Remaining

PERMANENT LIGHT FIXTURES G+0.0 (Level 1) PROGRESS

Light Fixture Progress:

44%56%

Light Fixture Progress

Complete Remaining

OVERHEAD SPRINKLER G+0.0 (Level 1) PROGRESS

Sprinkler Progress:

71%

29%

Sprinkler Progress

Complete Remaining

STEEL ERECTION G+1.0 (Level 2) PROGRESS

Steel Erecting Progress:

92%

8%

Column & Joist Progress

Complete Remaining

91%

8%

Deck & Detail Progress

Complete Remaining

98%

2%

Nelson Stud Progress

Complete Remaining

SLAB ON METAL DECK G+1.0 (Level 2) PROGRESS

SOMD Progress:

99%

1%

Bar Matt Progress

Complete Remaining

99%

1%

Poured Slab Progress

Complete Remaining

PERMANENT LIGHT FIXTURES G+1.0 (Level 2) PROGRESS

Light Fixture Progress:

65%

35%

Light Fixture Progress

Complete Remaining

OVERHEAD SPRINKLER G+1.0 (Level 2) PROGRESS

Sprinkler Progress:

59%

41%

Sprinkler Progress

Complete Remaining

STEEL ERECTION G+2.0 (Level 3) PROGRESS

Steel Erecting Progress:

100%

0%

Column & Joist Progress

Complete Remaining

99%

1%

Deck & Detail Progress

Complete Remaining

99%

1%

Nelson Stud Progress

Complete Remaining

PERMANENT LIGHT FIXTURES G+2.0 (Level 3) PROGRESS

Light Fixture Progress:

65%

35%

Light Fixture Progress

Complete Remaining

OVERHEAD SPRINKLER G+2.0 (Level 3) PROGRESS

Sprinkler Progress:

12%

88%

Sprinkler Progress

Complete Remaining

SLAB ON METAL DECK G+2.0 (Level 3) PROGRESS

SOMD Progress:

92%

8%

Bar Matt Progress

Complete Remaining

85%

15%

Poured Slab Progress

Complete Remaining

STEEL ERECTION G+3.0 (Level 4) PROGRESS

Steel Erecting Progress:

100%

0%

Column & Joist Progress

Complete Remaining

99%

1%

Deck & Detail Progress

Complete Remaining

99%

1%

Nelson Stud Progress

Complete Remaining

PERMANENT LIGHT FIXTURES G+3.0 (Level 4) PROGRESS

Light Fixture Progress:

61%

39%

Light Fixture Progress

Complete Remaining

SLAB ON METAL DECK G+3.0 (Level 4) PROGRESS

SOMD Progress:

84%

16%

Bar Matt Progress

Complete Remaining

84%

16%

Poured Slab Progress

Complete Remaining

STEEL ERECTION G+4.0 (Level 5) PROGRESS

Steel Erecting Progress:

100%

0%

Column & Joist Progress

Complete Remaining

99%

1%

Deck & Detail Progress

Complete Remaining

99%

1%

Nelson Stud Progress

Complete Remaining

SLAB ON METAL DECK G+4.0 (Level 5) PROGRESS

SOMD Progress:

85%

15%

Bar Matt Progress

Complete Remaining

74%

26%

Poured Slab Progress

Complete Remaining

PERMANENT LIGHT FIXTURES G+4.0 (Level 5) PROGRESS

Light Fixture Progress:

9%

91%

Light Fixture Progress

Complete Remaining

STEEL ERECTION ROOF PROGRESS

Steel Erecting Progress:

100%

0%

Column & Joist Progress

Complete Remaining

98%

2%

Deck & Detail Progress

Complete Remaining

ROOF PROGRESS

Roof Progress:

85%

15%

TPO Progress

Complete Remaining

35%

65%

EPDM Progress

Complete Remaining

54%46%

RTU Progress

Complete Remaining

SOUTH-WEST BUILDING SKIN PROGRESS

South-West Building Skin Progress:

80%

20%

Clips Progress

Complete Remaining

80%

20%

Stud Progress

Complete Remaining

65%

35%

IMP Progress

Complete Remaining

0%

100%

Precast Progress

Complete Remaining

SOUTH-EAST BUILDING SKIN PROGRESS

South-East Building Skin Progress:

90%

10%

Clips Progress

Complete Remaining

65%

35%

Stud Progress

Complete Remaining

15%

85%

IMP Progress

Complete Remaining

15%

85%

Precast Progress

Complete Remaining

SITE ELECTRICAL PROGRESS

91%

9%

UG ElectricalProgress

Complete Remaining

SITE Electrical Progress:

73%

27%

Light PolesProgress

Complete Remaining

SITE IMPROVEMENTS PROGRESS

76%

24%

CurbProgress

Complete Remaining

Site Improvements Progress:

90%

10%

Base AsphaltProgress

Complete Remaining

0%

100%

Top Coat AsphaltProgress

Complete Remaining

45%55%

Side WalkProgress

Complete Remaining

52%48%

Site ConcreteProgress

Complete Remaining

OFF-SITE IMPROVEMENTS PROGRESS

Off-Site Improvements Progress:

100%

0%

Fire HydrantProgress

Complete Remaining

100%

0%

Valve VaultProgress

Complete Remaining

100%

0%

Water LineProgress

Complete Remaining

50%50%

Sanitary Lift Station

Complete Remaining

OVERALL PROGRESS

72%

28%

Overall Project Progress

Complete Remaining

90%

10%

Domestic Water Progress

Complete Remaining

95%

5%

Storm Progress

Complete Remaining

91%

9%

UG ElectricalProgress

Complete Remaining

76%

24%

CurbProgress

Complete Remaining

90%

10%

Base AsphaltProgress

Complete Remaining

45%55%

Side WalkProgress

Complete Remaining

0%

100%

Top Coat AsphaltProgress

Complete Remaining

98%

2%

Overall SteelProgress

Complete Remaining

73%

27%

Light PolesProgress

Complete Remaining

35%

65%

EPDM Progress

Complete Remaining

85%

15%

TPO Progress

Complete Remaining

PROGRESS PHOTOSPROJECT C (ORD5)

PROGRESS PHOTOS

Photo Taken February 1st, 2021

Photo TakenFebruary 12th, 2021

PROGRESS PHOTOS

PROGRESS PHOTOS

Monday, June 8th, 202011:51AM Temperature 80° F

Friday, February 12th, 20219:42AM Temperature 10° F

PROJECT TEAM CONTACT LIST

• Thomas Huntzinger

• Vice President

• p. 410-337-6924

• e. [email protected]

• Eric Harris

• Project Manager

• p. 443-506-2398

• e. [email protected]

• Richard Fellinger

• Senior Superintendent

• p. 813-287-9700

• e. [email protected]

• Jerry Sorenson

• Superintendent

• p. 443-540-3234

• e. [email protected]

• Sean Armbruster

• Project Manager

• p. 410-918-7413

• e. [email protected]

• David Burke, CCM

• Project Manager

• p. 410-365-3916

• e. [email protected]

• Sean Compton

• Project Manager

• p. 443-250-7092

• e. [email protected]

• Logan Wible

• Assistant Project Manager

• p. 443-275-8921

• e. [email protected]

• Regan Smiley

• Assistant Project Manager

• p. 630-297-1054

• e. [email protected]

• Rob Branch

• Superintendent

• p. 410-365-6349

• e. [email protected]

• Nick Murphy

• Project Engineer

• p. 630-310-1774

• e. [email protected]

• Carrie Zillman

• Project Engineer

• p. 630-487-6294

• e. [email protected]

• Brett Schenkel

• Field Engineer

• p. 309-838-0065

• e. [email protected]

• Rachel Dziewatkoski

• Project Engineer

• p. 630-541-1100

• e. [email protected]

• Jose Herrero

• MEP Superintendent

• p. 302-292-0676

• e. [email protected]

• Dan Ford

• 3rd Party Safety Manager – Jobsite Safety

• p. 847-899-9732

• e. [email protected]

• Stephen Kuta

• Senior Field Engineer

• p. 815-404-4682

• e. [email protected]