Update on task Team Efforts to Resolve RSA/Lesotho Passenger Transport Operations
Progress Report on Efforts to Resolve RSA/Lesotho Passenger Transport Operation
description
Transcript of Progress Report on Efforts to Resolve RSA/Lesotho Passenger Transport Operation
Progress Report on Efforts to Resolve RSA/Lesotho Passenger Transport Operation
Presentation to Select Committee
28 January 2014
PRESENTATION OUTLINE
1. Purpose2. Background 3. Problem Statement4. Model for resolving the impasse5. Implementation Plan6. Conclusion
2
PURPOSEPURPOSE
To brief the Select Committee for Public Services on new developments in relation to the RSA/Lesotho Passenger Transportation Challenges
3
BACKGROUND
Cross border transportation is regulated through legal prescripts;•Cross-Border Transport Act, 4 of 1998 , as amended•National Land Transport Act, 5 of 2009•National Road Traffic Act, 93 of 1996, as amended•Tourism Act, 72 of 1993Additional instruments applicable are;-•Multi-lateral agreements like SADC Protocol on Transport, Communications & Meteorology and SACU Memorandum of Understanding on Road Transport •Bilateral agreements Bilateral Agreements concluded between SA and;
4
PROBLEM STATEMENT
• Economic by-pass; - Act doesn’t cater for local operators and as such it over-saturates the market
• Different regulatory regimes in the manner in which permits are issued; to wit , CBRTAct, NLTA, Provincial Acts
• That resulted in;-• Impeded flow of passenger traffic: cross-border
operations terminating at the ports of entry;• violent practices between operators; • Existence of illegal taxi ranking facilities located at
various ports of entry;• Congestion which leads to compromised border control
operations and security integrity.• Non-compliance to provisions of SACU MoU on Road
Transportation.
5
MODEL FOR RESOLVING THE IMPASSE
• KEY ELEMENTS FOR SUCCESS• Restoration of law and order• Implementation of verification outcomes• Transition window (Testing the framework
developed)• Legislative review• Special Emergency measures
6
MODEL FOR RESOLVING THE IMPASSE
RESTORATION OF LAW AND ORDER•To be a top priority and be implemented with immediate effect; •Minister has already deployed authority to The Premier of the province;•Development of an integrated law enforcement plan;•Joint law enforcement interventions;
7
MODEL FOR RESOLVING THE IMPASSE
IMPLEMENTATION OF VERIFICATION OUTCOMES•Six categories identified;-
Double dipping - total of 31 vehicles identified;Leased vehicle - 15 vehicles identified;Shared registrations – 8 vehicles identified;Cross border operators – 27 vehicles identified;Inter- and intra- provincial operators – total
number yet to be determined;Domestic permits with unauthorised destinations
to border towns - total number to be determined.
8
MODEL FOR RESOLVING THE IMPASSE
IMPLEMENTATION OF VERIFICATION OUTCOMES•Interfacing the different permit/license systems, i.e. OLAS, CBRTS, e-Natis.•Double dipping - stop practise with immediate effect.•Leased vehicle – practice discontinued•Shared registrations – practice discontinued•A moratorium would be applied to all aspiring entrants until the challenges are resolved
9
MODEL FOR RESOLVING THE IMPASSE
TRANSITION WINDOW•Categories 5 & 6 (Inter- and Intra-provincial operators);-
• To normalise those doing 2km radius operation unlawfully in the medium-term,
• Inter/Intra-provincial operators to be exempted from carrying cross border permit,
• Inter-provincial operators to be handled in medium to long term for purposes of engaging operators and acquiring more details,
• Same principle applied in category 5 will apply to category 6 in the medium-term,
10
MODEL FOR RESOLVING THE IMPASSE
LEGISLATIVE REVIEW•There is need to synchronise the C-BRT Act, NLTA and other relevant pieces of legislation;
SPECIAL DISPENSATION MEASURES•The Minister will delegate to The Premier to declare special emergency measures; •Special Regulations will have to be developed setting out the nature of the emergency measures to be implemented.
11
IMPLEMENTATION PLAN
KEY ELEMENT ACTIVITY BY WHOM TIMEFRAME
Restoration of law & order
Development of an integrated law enforcement planPhase 1 : Adoption of Plan
Executive RTI(C-BRTA) & Chief Director : Traffic Management & Transport(DPRT)
Phase 1 – by 30/04/2014
Phase 2 from by 30/06/2014
Phase 2 : Joint law enforcement interventions;
All law enforcement agencies
Continuous
Phase 3 : Workshop all officials and operators on new approach
CBRT & DPR&T 15 - 20 Feb 2014 12
IMPLEMENTATION PLAN
KEY ELEMENT ACTIVITY BY WHOM TIMEFRAME
Implementation of Verification findings
Discontinuation of double-dipping, leased vehicles and shared registration
Executive: Regulatory & Legal Services (C-BRTA)
Leased vehicles & shared registration dealt with from 01/08/2013Double-dipping in progress from 31/10/2013
Transition Window
Systems interfacing
DOT 30/09/2014
13
IMPLEMENTATION PLAN
KEY ELEMENT ACTIVITY BY WHOM TIMEFRAME
Transition window
Review categories 2 & 3 for issuing of permanent permits
Executive:RLS (C-BRTA) and Chief Director :Transport (DPRT)
30/09/2014
Exemption inter/intra- provincial from permits
Executive:RLS (C-BRTA) and Chief Director :Transport (DPRT)
As of 31/10/2013
Category 4 – cross border permit holders be allowed to cross as per CBRTAct
Executive :RTI & Chief Director : Traffic Management
As of 31/10/2013
Category 6 – domestic operators -2km radius
Executive :RTI & Chief Director : Traffic Management
30/09/201414
IMPLEMENTATION PLAN
KEY ELEMENT ACTIVITY BY WHOM TIMEFRAME
Legislative Review
Synchronise Acts including 2km radius
DOT 30/06/2015
Engagement of Kingdom of Lesotho’s Transport Ministry
MEC By 31/03/2014
Special Dispensation Measures
As events present
The Premier As and when need arise
15
CONCLUSION
• The proposed model was presented to MEC on 16/01/2014,• The proposed model presented to Taxi Operators
on 19/01/2014,• MEC commended the team and gave the
approach his blessing,• Matter is due for presentation to both Freetrans
EXCO and C-BRTA Regulatory Committee.
THANK YOU!
16