Progress Report NHA Punjab North

57
PROJECTS IN PUNJAB M-2 M-3 E-4 Murree ISLAMABAD (00) Rahimyar Khan (655) Sadiqabad (637) Okara (1134) Bahawalpur (844) Sahiwal (1102) Rawalpindi (1540) Kharian (1412) Gujranwala (1328) Gujrat (1380) Jhelum (1432) Km 608 Sardar Garh (693) Zahirpir (707) Ahmedpur East (792) Khan Bela (734) T. M. Panah (756) Nurpur Nauranga (814) Lodhran N-5 (860), E-5 (100) Mianchannu (1026) Chichawatni (1062) Pattoki (1180) Renala Khurd (1151) Bahi Pheru (1204) Gujar Khan (1491) Sohawa (1473) Shahdara (1268) Jampur (668) Ramak (872) Retra (824) Taunsa (798) Shadan Lund (767) M-1 Faisalabad M-3 (53), E-4 (0) Muzaffargarh (32) Multan N-5 (937), N-70 (00) LAHORE (1260) M-6 E-5 N-75 N-5 Khanewal N-5 (980), E-4 (180), E-5 (0) Km 1630 Kamoke (1307) Kashmor (495) Rajanpur (604) N-5 Sahianwala (32) Millat (48) Thokar Niaz Baig M-5 N-80 Lar (915) Manga (1220) Kala Shah Kaku Wazirabad (1362) Bewata (181) N-55 N-55 M-2 Pindi Bhattian M-2 (119), M-3 (0), E-3 (0) E-3 Kot Sabzal (612) Chakri (316) Bhang Bhatar (25) National Highway/Strategic Road Expressway Road Proposed for Federalization Motorway (Operational) Motorway (Under construction) Motorway (Planned) National Capital Provincial Capital City/Town Interchange Province Boundary River N-70 Km (868)

Transcript of Progress Report NHA Punjab North

Page 1: Progress Report NHA Punjab North

PROJECTS IN PUNJAB

M-2

M-3

E-4

Murree

ISLAMABAD (00)

Rahimyar Khan (655)

Sadiqabad (637)

Okara (1134)

Bahawalpur (844)

Sahiwal (1102)

Rawalpindi (1540)

Kharian (1412)

Gujranwala (1328)

Gujrat (1380)

Jhelum (1432)

Km 608

Sardar Garh (693)

Zahirpir (707)

Ahmedpur East (792)

Khan Bela (734)

T. M. Panah (756)

Nurpur Nauranga (814)

Lodhran N-5 (860), E-5 (100)

Mianchannu (1026)Chichawatni (1062)

Pattoki (1180)

Renala Khurd (1151)

Bahi Pheru (1204)

Gujar Khan (1491)

Sohawa (1473)

Shahdara (1268)

Jampur (668)

Ramak (872)

Retra (824)

Taunsa (798)

Shadan Lund (767)

M-1

FaisalabadM-3 (53), E-4 (0)

Muzaffargarh (32)

Multa

n N-

5 (93

7), N

-70 (0

0)

LAHORE (1260)

M-6

E-5

N-75

N-5

Khan

ewal

N-5 (

980),

E-

4 (18

0), E-

5 (0)

Km 1630

Kamoke (1307)

Kashmor (495)

Rajanpur (604)

N-5

Sahianwala (32)

Millat (48)Thokar Niaz Baig

M-5

N-80

Lar (915)

Manga (1220)

Kala Shah Kaku

Wazirabad (1362)

Bewata (181)

N-55

N-55

M-2

Pindi BhattianM-2 (119), M-3 (0), E-3 (0)

E-3

Kot Sabzal (612)

Chakri (316)

Bhang Bhatar (25)

National Highway/Strategic Road

Expressway

Road Proposed for Federalization

Motorway (Operational)

Motorway (Under construction)

Motorway (Planned)

National Capital

Provincial Capital

City/Town

Interchange

Province Boundary

River

N-70

Km (868)

Page 2: Progress Report NHA Punjab North

Road/

BridgeProject/Section Km

PC-1

Cost

Contract

CostPSDP

2012-13Progress

Expected

Completio

n

1. Sutlej Musa Pak Shaheed Bridge 0.6 2130 1616 150 Subst. Completed

2.Chena

bHead Muhammadwala Bridge 1 2508

712 (P1)

405 (P2)

970 (P3)

50 Subst. Completed

3. N-5 Jinnah Chowk - Bahawalpur Chowk 8 1078234 (P1)

532 (P2)70 Subst. Completed

4. Sutlej Baba Farid Bridge 8.6 1108 513 24 Subst. Completed

5. N-5 Wah Gate Underpass at Taxila 1.27 993 873 70 Subst. Completed

6. IMDC Islamabad Murree Dual Cariageway 4213,60

03414 50 Subst. Completed

7. N-5 Khiali Flyover at Gujranwala Bypass 1.1 996 888 RMA 90% Jun-2013

8. N-115 Nag Shah Chowk Flyover (4-Lane) 1 1530 835 1259 74% Jul-2013

9.Link to

BZU

Khanewal- Multan Inter District

Road (Bosan Road) (2x Packs)7.5 4570

461 (P1)

531 (P2)750 79% Jul-2013

Rs in Million

ONGOING DEVELOPMENT PROJECTS

PUNJAB

(Return……)

Page 3: Progress Report NHA Punjab North

Road/

Bridg

e

Project/Section K

m

PC-1

Cost

Contract

Cost

PSDP

2012-

13

ProgressExpected

Completion

10.Link to

Jinnah

Chowk

Rasheedabad Flyover of Inner Ring

Road Multan-- 1204 1204 200 Subst. Completed

11. N-115

Tri District Link (Jalalpur Pirwala -

Uch Sharif) (total 3x packs,2

completed)

42 31711566

(Pack-3)550

44%

(Pack-3)Sep-2013

12.Chena

b

Sultan Bahoo Bridge (Shorkot - Garh

Maharaja) (4x Packs)1 1603

770 (P1)

570 (P2)

572 (P3)

150 53% Dec-2013

13 IndusNishtar Ghat Bridge (Shaheed Benazir

Bhutto) (2 x Packs)1.2 5459 929 70 33% Jun-2014

14

Link to

Muzafa

rGhad-

Jhang

2 Lane Link road Head Muhammad

wala to Band Bosan Road

3.8

5189 189 50 Subst. Completed

15 M-2 Hiran Minar Interchange 0.5 260 234 -- Subst. Completed

16 Ravi Syedwala Bridge -- 1164 829 500 Recently awarded

17 N-1156 Lane Highway from Double Phatak –

Chowk Naagshah (Old Shujabad Road)8 4160 1440 1000 2%

18

Link to

Northe

rn

bypass

Multan

Dehar Road (Khad Factory to Pul

Khadal) Multan (5.6 Km) 22 809 211 300 13% Jul-2013

Rs in Million

ONGOING DEVELOPMENT PROJECTS

PUNJAB

(Return……)

Page 4: Progress Report NHA Punjab North

PROJECTS IN KP

Abbottabad (70)

Khunjrab Pass (806)

Gilgit (540)

Batgram(165)

BeshamN-35 (218), N-90 (64)

Batkhela (81)

Dir (200)

Chitral (309)

Drosh

Malakand (74)

Chakdara N-45 (91), N-95 (0)

Tamergara (129)

Sher Ghargh (52)

Jalkhad 162

Naran (127)

Passu (683)

Aliabad (630)

ChilasN15 (240), N-35 (416)

Sazin (352)

Dasu (294)

Sust (720)

Haripur (33)

Dambu Das (102)

Jaglot N-35 (500), S-1 (0)

Skardu (167)

MuzaffarabadS-2 (40), S-3 (0)

Kohala (0)

ISLAMABAD

Torkham (1756)

Mughal Kot (397)

Daraban (467)DI Khan N-50 (531), N-55 (931)

Bannu (1073)

Ramak (872)

Pezu (990)

Malana

Sarai Gambila (1032)

Latambar (1101)

Lachi (1169)

Dara Ademkhel (1220)

Khushal Garh (108)

MansehraN-15 (0), N-35 (94)

S-1

N-35

N-45

PESHAWARN-5 (1700), N-55 (1264)

M-1 (155)

NowsheraN-5 (1657), N-45 (0)

Kalam (135)

Chakothi (55)

S-2

N-35

N-5

N-50

Balakot (40)

Srinagar

Kohat N-55 (1196), N-80 (146)

N-90

N-95

Pattan (257)Madyan

Bahrain

Yarik (964)

Dhanasar (388)

N-80

N-55

S-3Hatian

Km (868)

Paroa (896)

Jehangira(1638)

Rahimabad (570)

Gulmit (669)

Sassi (26)

Shangash (51

Bagicha (114)

Swabi (72)

National Highway/Strategic Road

Expressway

Road Proposed for Federalization

Motorway (Operational)

Motorway (Under construction)

Motorway (Planned)

National Capital

Provincial Capital

City/Town

Interchange

Province Boundary

River

Page 5: Progress Report NHA Punjab North

Road Project Km

PC-1

Cost Contract Cost PSDP

2012-13Progress

Expected

Completion

1. N-15 Naran - Jhalkhad 43 53451369

50 Subst. Completed

2. N-15Jhalkhad - Babusar Top - Chillas

(2x Sections)66 4017

1206 (P1)

1313 (P2) 175 75% Sep-2014

3. M-14x Interchanges on M-1

(1 completed)- 1067

212 (Ghazi)

148 (Chach)

259 (Capt. Col

Sher Khan)

1205 (N-5)

50 80% Jul-2013

4. N-45 Lowari Tunnel 9 18,132 5450 1200 45% Jul-2017

5. E-2 Peshawar Northern Bypass (Pack-I) 7.6 1960 2219 1318 42% Jun-2013

6. N-80 Khushalgarh Bridge (Pack-I, Indus) 2.9 1,538 981 100 68% Oct-2013

7.Pak –

AfghanTorkham Jalalabad ACW 73 4,341 4341 -- 58%

FWO

Demobilized

8. N-45 Takht Bhai – Shergarh-Dargai 30 917 917 5093%

Subst. Completed

9. KKH Shatial Thor Nala Bypass (KKH) 37 3844 3518 DW 3% Sep-2014

Rs in Million

ONGOING DEVELOPMENT PROJECTS

KHYBER PAKHTUNKHWA

(Return……)

Page 6: Progress Report NHA Punjab North

Road/

RiverConstruction Project Km Cost

PSDP

2012-13Progress

Expected

Completion

1. N-105 Larkana-Naudero-Lakhi (2 Packs) 61 4000 250Completed, Inaugurated

by President of Pakistan

on 28th Dec, 20122. N-305 Sakrand-Benazirabad (DCW) 20 1419 100

3. N-655 Ratodero -Naudero (Rehab) 14.7 847 100

4. DWHyderabad – Badin Road to Mir Wah Sanjar

Chang Road (2 Packs)52 1385 400

Completed,

Inaugurated by

President of Pakistan

5. N-155Larkana- Mohenjodaro upto Airport

(2 Packs)28 3041 500 82% May-2013

6.N-455

Larkana- Kamber 20.5 829 70 72% June-2013

7. Kamber- Shahdadkot 29 1043 250 38% Sep-2013

8. N-110 Gharo-Keti Bunder (3 Packs) 84 3300 350 74% May-2013

9. Indus Qazi Ahmed - Amri Bridge (2 Packs) 18 3683 500 59% Jun-2013*

10. N-255 Larkana-Nasirabad (Rehab) 34 1214 250 35% Dec-2013

11. LEP Lyari Expressway 32 10443 1200 74% Dec-2013

Rs in MillionONGOING GoP FUNDED PROJECTS

•Main Bridge is expected to be completed by June 2013

(Return……)

Page 7: Progress Report NHA Punjab North

ONGOING DEVELOPMENT PROJECTS

BALOCHISTAN

Road/

BridgeProject/Section Km

PC-I

Cost

Contract

Cost

PSDP

2012-

13

Date of

start

Progres

s

Expected

Comp

1 N-65Nuttal - Sibbi –

Dhaddar 106 3,262

P-I 1,575

P-II 452

P-III 180

5 Dec-01 Completed

2 N-65Jacobabad &

Dera Allahyar 27 671 526 5 Jun-03 Completed

3 N-10Lyari- Gwadar-

Gabd (MCH)653 17,262 13,886 175 Jul-00 Completed

4 N-65 Kolpur Bypass 5.7 696 659 116.7 Dec-10 50% Jun-2013

5 N-70Waigum Rud -

Khajuri132 3473 1331 750 Sep-07 49% Sep-2013

6 M-8

Gwadar -Turbat-

Hoshab (3

Packs)

193 18379

P-I 2494

P-II 3687

P-III 3166

3302.5 Sep-04 68% Dec-2013

7 M-8

Khuzdar-

Ratodero

(3 Packs)

143 6672P-I 2207

P-II 1908

P-III 2306

1100 Apr-04 73% Dec-2013

8 N-85Hoshab- Basima

- Sorab454 22412 17,454 1100 Sep-07 22% Jun-2014

Rs in Million

(Return……)

Page 8: Progress Report NHA Punjab North

ISSUES

Delay in completion of the projects is

mainly due to:

Shortage of Funds.

Law & order issues (Balochistan Projects).

Land Acquisition problems.

Page 9: Progress Report NHA Punjab North
Page 10: Progress Report NHA Punjab North

10

Multan

Shujaabad

Uch

Jalalpur Pirwala

TMP

Lodhran

Bahawalpur

Ahmedpur East

Chani Goth

Moosa Pak Shaheed Bridge

Moosa Pak

Shaheed Bridge

Khanewal

DISTANCE SAVING 41 KM

Page 11: Progress Report NHA Punjab North

CONSTRUCTION OF TWO LANE MOOSA PAK SHAHEED BRIDGE AND APPRACH ROADS OVER RIVER SUTLEJ AT AIMANWALA, DISTT. BAHAWALPUR

Length (KM) : 610 m (approach length 2.8 km and 1.7 km)PC-I Cost (Original) : Rs. 1,148 M

(Revised) : Rs. 2,131 MContract Cost (Original) : Rs. 1,415 M

(Revised) : Rs. 1,616 MPSDP Allocations (2012-13) : Rs. 150 MConsultant : M/s REC (Pvt.) LtdContractor : M/s Karcon / Mishal Sania (JV)Date of Start : Jul - 2009Date of Completion (Original) : May – 2011

Overall Progress (Actual) : Subst. Completed

Current Status:

Project completed and open to traffic.

Page 12: Progress Report NHA Punjab North

Multan

Khanewal

Kabirwala

Abdul Hakim

Garh Maharaja

Atharan Hazari

Layyah

Muzaffargarh

Shorkot11km

1.5km

2.4km

N-70

Chowk Azam

Head MuhammadwalaBridge

Chaubara

Existing Sher Shah Bridge

Head Muhammadwala Bridge Project

DISTANCE SAVING 40 KM

Page 13: Progress Report NHA Punjab North

CONSTRUCTION OF TWO LANE BRIDGE OVER RIVER CHENAB AT HEAD MUHAMMAD WALA DISTT. MULTAN

Length (KM) : 1.010 Km (Bridge)3.34 Km (Right Approach)7.37 Km (Left Approach)

PC-I Cost (Original) : Rs 2,377 M (Global)(Revised) : Rs 2,508 M (Global)

PSDP Allocations (2012-13) : Rs. 50 M (Global) Contract Cost (Original) : Rs 755.638 M (Pkg-I)

Rs 457.117 M (Pkg-II)Rs 940.742 M (Pkg-III)

(Revised) : Rs 712.078 M (Pkg-I)Rs 405.568 M (Pkg-II)Rs 907.74 M (Pkg-III)

Consultant : M/s EA ConsultingContractor : M/s GRC (Pkg-I)

M/s Hidayatullah & Co. (Pkg-II)M/s Zarghoon (Pkg-III)

Date of Start : Jun - 2009Date of Completion (Original) : Dec – 2011Overall Progress (Actual) : Completed (All packages)

Current Status:Project completed and open to traffic.

Page 14: Progress Report NHA Punjab North

14

N-5

N-5

JINNAH Chowk

(kumharawal)

Page 15: Progress Report NHA Punjab North

KUMHARANWALA–VEHARI–BAHAWALPUR CHOWK (N-5)

(DUALIZATION / STRENGTHENING OF N-5, DISTRICT MULTAN)

Length (KM) : 8.2 KmPC-I Cost (Original) : Rs. 966 M (Global)

(Revised) : Rs. 1078 M (Global)PSDP Allocations (2012-13) : Rs. 70 M (Global)Contract Cost (Original) : Rs. 120.834 M (Pkg-I: Jinah Chowk-Vehari Chowk)

Rs. 532 M (Pkg-II: Bahawalpur Chowk-Vehari Chowk)(Revised) : Rs. 234.371 (Pkg-I)

N/A (Pkg-II)Consultant : M/s Asif Ali & AssociatesContractor : M/s Watan Builders (Pkg-I)

M/s CH. Abdul Latif & Co. (Pkg-II)Date of Start : Jul - 2008Date of Completion (Original) : Jul - 2009

(Revised) : Dec - 2010(Actual) : Jun - 2011

Overall Progress : Completed

Current Status:Project completed.

Page 16: Progress Report NHA Punjab North

PAKPATTAN

MINCHINABAD

Location of

Pakpattan Bridge

Harunabad

Chishtian Mandi

Hasilpur

VIHARI

Mandi Burewala

Arifwala

SAHIWAL

OKARA

Dipalpur

LOCATION OF BABA FARID BRIDGE ACROSS RIVER SUTLEJ

LINKING PAKPATTAN WITH MINCHINABADA

nnex-A

Page 17: Progress Report NHA Punjab North

BRIDGE OVER RIVER SUTLEJ CONNECTING PAKPATAN WITH MINCHINABAD (BABA FARID BRIDGE)

Length : 572 Meter (Main Bridge) 8 Km (Approach Road)PC-I Cost (Original) : Rs. 453.6 M

(Revised) : Rs. 1,108 M PSDP Allocations (2012-13) : Rs. 24.128 MContract Cost (Original) : Rs. 912.575 M

(Revised) : Rs. 913.470 M Consultant : M/s EA Consulting (Pvt) LtdContractor : M/s Kingcrete Builders Date of Start : Feb-2008Date of Completion (Original) : Jan-2010

(Revised) : Sep-2010(Actual) : Jan-2010

Overall Physical Progress : 87 % (Subst. Completed)

Project Status:

Bridge completed in Jan 2010. Work on approaches is in progress.

Page 18: Progress Report NHA Punjab North

Hattar Road

Thatta Khalil Road

POF WahGate-1

Peshawar

4-LANE UNDERPASS AT WAH GATE NO. 1 (1286 M)

LOCATION MAP

Page 19: Progress Report NHA Punjab North

CONSTRUCTION OF 4-LANE UNDERPASS AT WAH GATE NO. 1

Length (KM) : 1.286 Km (Barrel 127 m, Underpass 760 m)PC-I Cost (Original) : Rs 493 M

(Revised) : Rs 993 M (Approval under process)

Contract Cost (Original) : Rs 758.966 M(Revised) : Rs 872.500 M

PSDP Allocations (2012-13) : Rs 70 M Consultant : M/s EA ConsultingContractor : M/s GRCDate of Start : Dec - 2008Date of Completion (Original) : Jun - 2010

(Revised) : Feb - 2011(Actual) : Oct - 2011

Overall Progress (Actual) : Subst. Completed

Current Status:

Project has been completed and opened to traffic.

Page 20: Progress Report NHA Punjab North

ISLAMABAD – MUZAFFARABAD ROAD PROJECT SATRA

MILE – LOWER TOPA SECTION

Jhika Gali

Page 21: Progress Report NHA Punjab North

ISLAMABAD – MUZAFFARABAD DUAL CARRIAGEWAYSATRA MILE TO LOWER TOPA SECTION (N-75)

Length (KM) : 43KmPC-I Cost (Original) : Rs 8,242 M

(Revised) : Rs 12,666 M (approval under process)

Contract Cost (Original) : Rs 2,187 M(Revised) : Rs 3,414 M

PSDP Allocations (2012-13) : Rs 200 MConsultant : M/s NESPAKContractor : M/s HAKASDate of Start : Sep - 1999Date of Completion (Original) : July - 2001

(Actual) : Dec - 2010Overall Progress : Subst. Completed

Project Status:Project Section (Km 0 ~ 33) : Operational since May, 2008 (Taken over by Operation Wing NHA)

Project Section (Km 33 ~ 43) : Operational since Jan, 2011

Remarks:Project has been completed and opened to traffic.

Page 22: Progress Report NHA Punjab North

KHIYALI FLYOVER PLAN

Page 23: Progress Report NHA Punjab North

CONSTRUCTION OF KHIALI FLYOVER BRIDGE AT GUJRANWALA BYPASS (N-5)

Bridge Length : 330 MRamps Length : 359 MTotal length of flyover : 689 MApproach/Slip Roads Length : 850M PC-I Cost : Rs. 996 Million (under process)Contract Cost (Original) : Rs. 498 Million

(Revised) : Rs. 888.9 Million (VO # 1 yet to be concurred by Finance wing)

Consultant : M/s KNKContractor : M/s RECDate of Start : Nov-09Date of Completion (Original) : Feb-11

(Revised) : Sep-13PSDP Allocations (2012-13) : Nil (RMA Funded)

Overall Progress : 90%

Current Status:

Project has been completed and opened to traffic in May, 2013.

Page 24: Progress Report NHA Punjab North

ROAD BETWEEN DOUBLE PHATTAK

AND NAAG SHAH CHOWK FLYOVERS

Page 25: Progress Report NHA Punjab North

N-70/M-4 LINK INTERCHANGE (NAAG SHAH CHOWK FLYOVER)

PC-I Cost (Original) : Rs 364 M(Revised) : Rs 1,734 M

Contract Cost (Original) : Rs 602.940 M(Revised) : Rs 834.50 M

PSDP Allocations (2012-13) : Rs 1259 MConsultant : M/s NESPAKContractor : M/s Ch. Abdul Latif & Co.Date of Start : Jul - 2010Date of Completion (Original) : Jul - 2011

(Revised) : Dec - 2011(Expected) : Jul- 2013

Overall Progress (Actual) : 76%

Current Status:

Project is completed in May 2013. Asphaltic work on service roads is in progress.

Page 26: Progress Report NHA Punjab North

LOCATION PLAN

BOSAN ROAD MULTAN

Page 27: Progress Report NHA Punjab North

KHANEWAL – MULTAN INTER DISTRICT (BOSAN) ROAD MULTAN

Length (KM) : 7.5 KmPC-I Cost (Original) : Rs 4570.022 M (Global)PSDP Allocations (2012-13) : Rs 750 M (Global)Contract Cost (Original) : Rs 460.82 M (Pkg-IA)

Rs 530.60 M (Pkg-IB)(Revised) : N/A

Design Consultant : M/s Loya / ZeerukContractor : M/s Khalid Rauf & Co. (Pkg-IA)

M/s FWO (Pkg-IB)Date of Start : Mar - 2011 Date of Completion (Original) : Oct - 2011

(Revised) : Mar – 2013(Expected) : Jul- 2013

Overall Progress (Actual) : 75% (Pkg-1A)87% (Pkg-1B)

Issues & Impediments:

Pending liabilities.

Page 28: Progress Report NHA Punjab North

6 x INTERCHANGES ON INNER RING ROAD MULTAN

Pack Flyover Rs in M Progress

I.Jinnah Chowk

1204Completed

Rasheedabad Chowk Completed

II. Chungi 81210 Completed

Chungi 9

III.Kalma Chowk

1597 CompletedDouble Phatak

Total 4011

Page 29: Progress Report NHA Punjab North

INNER RING ROAD MULTAN WITH 6 X INTERCHANGES

PC-I Cost (Original) : Rs 6,445 M (Global)(Revised) : Rs 7,909 M (Global)

PSDP Allocations (2012-13) : Rs 200 M (Global)Contract Cost (Original) : Rs 1144.04 M (Pkg-I: Flyover at Jinah chowk &

Rasheedabad Chowk)

Rs. 1209.45 M (Pkg-II: Flyover at chungi # 8&9)Rs. 1262.19 M (Pkg-III: Flyover at Kalma chowk & Double phatak chowk)

(Revised) : Rs 1203.72 M (Pkg-I)N/a (Pkg-II)Rs. 1596.07 M (Pkg-III)

Consultant : M/s EA (Pvt.) Ltd.Contractor : M/s RMC (Pvt.) Ltd (Pkg-I)

M/s Maqbool Associate (Pkg-II)M/s Sarco-MSL (JV) Pkg-III)

Date of Start : Feb - 2010Date of Completion (Original) : Aug - 2011

(Actual) : Jan - 2013Overall Progress : Subst. Complete (Pkg-I)

Subst. Complete (Pkg-II)Subst. Complete (Pkg-III

Current Status:Project has been completed and opened to traffic.

Page 30: Progress Report NHA Punjab North

Multan

Shujaabad

Uch

Jalalpur Pirwala

TMP

Lodhran

Bahawalpur

Ahmedpur East

Chani Goth

MULTAN - SHUJAABAD - JALALPUR

PIRWALA - UCH - TM PANAH ROAD (138 KM)

Aminwala Bridge

Khanewal

Page 31: Progress Report NHA Punjab North

JALALPUR PIRWALA – UCH ROAD (N-115)

(REHABLITATION/UP GRADATION OF TRI DISTRICT LINK, SOUTHERN PUNJAB)

Length (KM) : 42 KmPC-I Cost (Original) : Rs 2,289.29 M (Global)

(Revised) : Rs 3,171 M (Global)PSDP Allocations (2012-13) : Rs 550 M (Global)Contract Cost (Original) : Rs 641.849 M (Pkg-I)

Rs 774.633 M (Pkg-II)Rs 1,565.570 M (Pkg-III)

(Revised) : Rs 827.526 M (Pkg-I)Rs 796.692 M (Pkg-II)N/A (Pkg-III)

Consultant : M/s ACCContractor : M/s Friends Enterprises (Pkg-I)

M/s RMC (Pkg-II)M/s SKB (Pkg-III)

Date of Start : Dec - 2009Date of Completion (Original) : Nov - 2010

(Revised) : Jun - 2012(Expected) : Sep - 2013

Overall Progress (Actual) : Subst. Complete (Pkg-I)Subst. Complete (Pkg-II)44% (Pkg-III)

Issues & Impediments:Package III delayed due to pending liabilities.

Page 32: Progress Report NHA Punjab North

SHORKOT- GARH MAHARAJA BRIDGE ACROSS RIVER CHENAB

PROPOSED BRIDGE

SHORKOT

FAISALABAD

LAHOREJHANG

GARH MAHARAJA

Page 33: Progress Report NHA Punjab North

CONSTRUCTION OF BRIDGE ACROSS RIVER CHENAB LINKING SHORKOT AND GARH MAHARAJA

Length (Package-I) : 855 M(Package-II) : 3.2 Km(Package-III) : 4.097 Km

PC-I Cost (Original) : Rs. 1603 MPSDP Allocations (2012-13) : Rs. 150 MContract Cost (Package-I) : Rs. 770 M (Main Bridge)

(Package-II) : Rs. 678 M (Revised) Rs. 570 M (Garh Maharaja Side Approach Rd) (Package-III) : Rs. 572 M (Shorkot side Approach Road & Drainage & Erosion Work)

Supervisory Consultant : M/s REC (Pvt) LtdContractor (Package-I) : M/s SARCO-Mishal Sania (JV)

(Package-II) : M/s Hidayat-Ullah Khan & Co.(Package-III) : M/s Friends Enterprise &HNAC (JV)

Date of Start (Package-I) : June, 2010(Package-II) : September, 2010 (Package-III) : September, 2011

Date of Completion : Dec, 2013 (Expected)Overall Progress (Package-I) : 76 %

(Package-II) : 42% (Package-III) : 40 %

Issues & Impediments:

Project suffered due to paucity of funds and resultant delay in payment to contractors.

Page 34: Progress Report NHA Punjab North

34

BENAZIR SHAHEED BRIDGE ACROSS

RIVER INDUS AT NISHTAR GHAT

Page 35: Progress Report NHA Punjab North

SHAHEED BENAZIR BHUTTO BRIDGE OVER RIVER INDUS LINKING N-5 WITH N-55 AT NISHTAR GHAT

PC-I Cost (Original) : Rs. 5459 M PSDP Allocations (2012-13) : Rs. 70 MContract Cost (Package-II) : Rs. 929 M (Main Bridge)

(Package-III) : Rs. 594 M (Approach Rd Zahir Pir To Chachran Sharif)Design Consultant : M/s EA Consulting (Pvt) LtdSupervisory Consultant : M/s REC (Pvt) LtdContractor (Package-II) : M/s FWO (Main Bridge)

(Package-III) : M/s RMC (Approach Rd ZP to CS)Date of Start : Jan 2012Expected Date of Completion : Jun 2014Overall Progress (Package-II) : 35% (Main Bridge)

(Package-III) : 30% (Approach Rd ZP to CS)

Current Status:Procurement of approach road from Rajanpur & River bed approx. 18 Km and Guide Banks / Training Works yet to be completed.

Page 36: Progress Report NHA Punjab North

LINK ROAD FROM MUHAMMADWALA

BRIDGE – BUND BOSAN ROAD

Page 37: Progress Report NHA Punjab North

CONSTRUCTION OF 2 LANE LINK ROAD FROM HEAD MUHAMMAD WALA BRIDGE TO BAND BOSAN ROAD

PC-I Cost (Original) : Rs. 189 M PSDP Allocations (2012-13) : N/AContract Cost : Rs. 189 MSupervisory Consultant : M/s EA Consulting (Pvt) LtdContractor : M/s Hidayat Ullah Khan & Co.Date of Start : Dec 2011Date of Completion (Original) : Jun 2012

(Expected) : Dec-2012Overall Progress : Subst. completed

Project Status:

Substantially completed.

Page 38: Progress Report NHA Punjab North

1a: Location Plan

Page 39: Progress Report NHA Punjab North

HIRAN MINAR INTERCHANGE ON M-2

PC-I Cost (Original) : Rs. 260 M(Revised) : N/A

Contract Cost (Original) : Rs. 234.073 M(Revised) : N/A

PSDP Allocations (2011-12) : Rs. 50 MPSDP Allocations (2012-13) : NilConsultant : M/s RECContractor : M/s Luqman BrothersDate of Commencement : Jul - 2010Date of Completion (Original) : Jan - 2011

(Revised) : Apr - 2011(Expected) : Dec – 2012 (Subject to availability of funds)

Overall Progress (Actual) : 83% (Substantially completed)

Present Status:

Project is completed in Dec-2012.

Page 40: Progress Report NHA Punjab North

KKH

THAKOT (190)

PATTAN (257)

Chillas(417)

BATGRAM (160)

BARSEEN (307) RAIKOT

JAGLOT (500)

DANYORE(545)

HASSANABAD (624)

MARKHUN

(712)

DIH (750)

KHUNJERAB (806)

HASSAN ABDAL (0)

Jhalkhad (162)Babusar Pass

TATTAPANI

(468)

BESHAM (218)

DASSU (290)

Balakot (40)Attarshisha (14.5)

Kaghan (99)

Naran (122)

Ganool (57)

BATAKUNDI

(228)

Ht 14000 ft

DHODIAL

GARHI HABIBULLAH (28)

MUZAFFARABAD (62)

MansehraHAZARA UNIVERSITY

PROPOSED ALIGNMENTLEGEND

8 Kms

12 Kms

MANSEHRA - NARAN - JHALKHAD - CHILLAS (N-15)

Section Km Rs in M Progress

Mansehra – Naran 123 2741 Completed

Naran - Jhalkhad 40 1369 Subst.

Completed

Jhalkhad Babusar 29 1206 68%

Babusar Top-Chillas 38 1643 82%

Total 230 6959

Page 41: Progress Report NHA Punjab North

Mansehra-Naran-Jalkhad Road

Naran-Jhalkhad Section

Length (KM) : 43.30PC-I Cost (Original) : Rs. 5346MContract Cost (Original) : Rs. 992M

(Revised) : Rs. 1,369MPSDP Allocations (2012-13) : Rs. 50 MConsultant : M/s RECContractor : M/s FWODate of Start : May-2002Date of Completion (Original) : Dec-2006

(Actual) : Dec-2008Overall Progress (Actual) : Subst. Complete

Current Status:

Substantially completed. Asphaltic Work and construction of drainage structure is in progress.

Page 42: Progress Report NHA Punjab North

Jalkhad–Chillas Road (N-15)

Jhalkhad-Babusar Top Section

Length (KM) : 28.5PC-I Cost (Original) : Rs. 4,017 MContract Cost (Original) : Rs. 977M

(Revised) : Rs. 1206 MPSDP Allocations (2012-13) : Rs. 175 MConsultant : M/s RECContractor : M/s FWODate of Start : Oct-2004Date of Completion (Original) : Dec-2006

(Revised) : Dec-2010(Expected) : Dec-2014

Overall Progress (Actual) : 68.4%

Issues & Impediments:

FWO demobilized from site in 2009 due to non-release of funds to FWO and they have served notice to re-start thework on Jhalkhad – Chillas Section of Kaghan Valley road (N-15) and work is expected to complete by Dec-2014.

Page 43: Progress Report NHA Punjab North

Jalkhad–Chillas Road (N-15)

Babusar Top-Chillas Section

Length (KM) : 38PC-I Cost (Original) : Rs. 4,017 MContract Cost (Original) : Rs. 1313M

(Revised) : N/APSDP Allocations (2012-13) : Rs. 175 MConsultant : M/s RECContractor : M/s FWODate of Start : Jan-2005Date of Completion (Original) : Dec-2006

(Revised) : Dec-2010(Expected) : Dec-2014

Overall Progress (Actual) : 82.5%

Issues & Impediments:

FWO demobilized from site in 2009 due to non-release of funds to FWO and they have served notice to re-start thework on Jhalkhad – Chillas Section of Kaghan Valley road (N-15) and work is expected to complete by Dec-2014.

Page 44: Progress Report NHA Punjab North

LOWARI TUNNEL PROJECT (8.5 KM)

• Rail Tunnel excavation completed in Jan-2009

• Highway Tunnel (1.9 km) completed in Oct-2010

• North & South access roads (18 km) completed in 2007 & 2009

• Rail Tunnel converted into Road Tunnel

• PC-I cost is Rs 18 B

• Physical progress is 45%

SOUTH PLATFORMNORTH PLATFORM

SNOW

Page 45: Progress Report NHA Punjab North

South Link Access Road

(0.8 Km)

Lowari Top

South Platform

North Platform

North Road Bridge

South Road Bridge

Main Road Tunnel (8500 M)Highway Tunnel

(1900 M)

CHITRAL DIR

North Link Bridge

North Link Access Road

Baradam Bridge

Highway Tunnel BridgeNorth Link

Access Road (4 Km)

South Access Road (7.3

Km)

North Access Road (6.9

Km)

Deleted from M/s SAMBU Contract

LEGEND:

Tunnel Works

LOWARI TUNNEL PROJECT (8.5 KM)

See next slide…….

Page 46: Progress Report NHA Punjab North

Lowari Tunnel Project/N-45

Length (Tunnels) : 8.5 Km + 1.9 KmPC-I Cost (Original) : Rs. 7,984M

(Revised) : Rs. 18,132MContract Cost (Original) : Rs. 5,429M

(Revised) : Rs. 6,047MPSDP Allocations (2012-13) : Rs. 1200MConsultant : Geo-ConsultContractor : Geo-Consult/Typsa JVDate of Start : Sep-2005Date of Completion (Original) : Sep-2008

(Revised) : May-2012(Expected) : Jul-2017

Overall Progress (Civil works) : 44.5%(Whole Project) : 36.7%

Issues & Impediments:

Excuvation of 8.5 Km Tunnel has been completed as 14th Jan, 2009 and that of 1.9 Km on 2nd Oct, 2010. The Governmentof Pakistan has conveted Lowari Rail Tunnel into Road Tunnel in anticipation of traffic from Central Asian State owing topropose extension of road from Chitral to Tajikistan.Revised PC-I accordingly approved by ECNEC on 11th Nov, 2011. Conversely the contract between NHA and M/s SAMBU isunder dispute due to funds shortage. Amicable settlement between the parties are underway.

Page 47: Progress Report NHA Punjab North

PESHAWAR NORTHERN BYPASS (32 KM)

NOWSHERA

JAMRUD

Railway line

(N-5)

START

GRAVE

YARD

TEHKAL

PAYANPESHAWAR

CITY

NASIR BAGH

REFUGEES

CAMP

HAYATABAD

TOWN UNIVERSITY

TOWN

RAILWAY TRACK

SURKAMAR

END

PESHAWAR

CANT

N

(N-55)

2.

• Bypass will reduce congestion in Peshawar City

• Project cost is Rs 9 billion

• Work on first 8 km is ongoing

• Current progress is 42%

• Land acquisition for balance 26 km ongoing

Page 48: Progress Report NHA Punjab North

Peshawar Northern Bypass

(Package-I)

Length (KM) : 7.6 PC-I Cost (Original) : Rs. 9,003 M

(Revised) : N/AContract Cost (Original) : Rs. 1,962 M

(Revised) : Rs. 2,219 MPSDP Allocations (2012-13) : Rs. 1,318 MConsultant : M/s EAContractor : M/s MatraconDate of Start : Feb-2010Date of Completion (Original) : May-2011

(Revised) : Jul-2012(Expected) : Jul-2013

Overall Progress (Actual) : 47%

Issues & Impediments:

Rs. 300 million released against to Land of Mouza Nassapa.

Page 49: Progress Report NHA Punjab North

Loya Associates, Karachi. 49Wednesday, June 19, 2013

KHUSHALGARH BRIDGE ACROSS RIVER INDUS (N-80)

Page 50: Progress Report NHA Punjab North

• Existing rail-cum-road Bridge constructed in 1905

• Work on New Bridge commenced in Nov-2011

• Project cost is Rs 1.5 B

• Physical progress is 50%

NEW KHUSHALGARH BRIDGE ACROSS RIVER INDUS

Page 51: Progress Report NHA Punjab North

Khushal Garh Bridge over River Indus

(N-80), (Bridge 0.358 Km, approach 2.46 Km)

Length (KM) : 0.35 + 2.4PC-I Cost (Original) : Rs. 1,538 Million

Contract Cost (Original) : Rs. 981 Million(Revised) : Rs. 1008 Million

PSDP Allocations (2012-13) : Rs. 100 MillionConsultant : M/s Loya AssociatesContractor : M/s Usmani Associates Date of Start : Oct -2011Date of Completion (Original) : Oct-2013 Expenditure todate : 694 Million

Overall Physical Progress (Actual) : 70%

Current Status:

Progress of work is satisfactory.

Page 52: Progress Report NHA Punjab North

TORKHAM- JALALABAD ACW (75 KM)

Landi Kotal

F A T A

JALALABAD

Start PointECW

ACW

• Progress: 58%

• Cost: Rs 4.9 B

• Start: Jan-2007

• Work suspended since Aug-2008

• Non payment issue

• PSDP 2012-13: Nil

Page 53: Progress Report NHA Punjab North

TORKHAM JALALABAD ADDITIONAL CARRIAGEWAY

AFGHANISTAN

Length (KM) : 73.69Contract Cost (Original) : Rs. 4341 M

(Revised) : NilConsultant : M/s NESPAKContractor : M/s FWO Date of Start : Jan - 2007Date of Completion (Original) : Jul - 2009

(Revised) : N/A(Expected) : --

Overall Progress (Actual) : 58%

Issues & Impediments:

Work was stopped by the contractor since Aug 2008 due to non payment of their bills. Meeting has been arrange inP&D Division for re-mobilization of Contractor M/s FWO and Minutes of Meeting has also been issued. Re-mobilizationplan is submitted by M/s FWO on 13th of December, 2012.

Page 54: Progress Report NHA Punjab North

Chitral

Drosh

Mirkhani

Lowari PassUpper Dir

Lower Dir

Timergarah

Bajur

Malakand

DargaiTakhtbai

Chakdara

UP-GRADATION OF N-45 (NOWSHERA – DIR - CHITRAL)

Mardan

Page 55: Progress Report NHA Punjab North

Nowshehra-Chakdara-Dir-Chitral N-45

PACKAGE-I, Dualization of Takht Bahi-Shergarh-Dargai Section

Length (KM) : 30PC-I Cost (Original) : Rs. 1,620M

(Revised) : Rs. 2,399MContract Cost (Original) : Rs. 622 M

(Revised) : Rs. 933 MPSDP Allocations (2012-13) : Rs. 50 MConsultant : M/s ACEContractor : M/s NLCDate of Start : Aug-2010Date of Completion (Original) : June-10

(Revised) : Nov-12 (approval Under process)(Actual) : Dec-12

Overall Progress (Actual) : 93% (Subst. Completed)

Issues & Impediments:

Subst. completed.Only 11 km Asphalt Wearing Course is left. EOT of Contractor M/s NLC is in process.

Page 56: Progress Report NHA Punjab North

Nowshehra-Chakdara-Dir-Chitral N-45

PACKAGE-II, Rehab.of Dargai-Chakdara Section

Length (KM) : 25PC-I Cost (Original) : Rs. 1,620M

(Revised) : Rs. 2,399MContract Cost (Original) : Rs. 622M

(Revised) : NilPSDP Allocations (2012-13) : Rs. 50 MConsultant : M/s ACEContractor : M/s NLCDate of Start : Dec-2005Date of Completion (Original) : May-2006

(Revised) : Mar-2009(Actual) : Mar-2009

Overall Progress (Actual) : Substantially Complete

Current Status:

Substantially completed.

Page 57: Progress Report NHA Punjab North

Nowshehra-Chakdara-Dir-Chitral N-45

PACKAGE-III, Improvement and widening of Timergara-Akhagram Road

Length (KM) : 25PC-I Cost (Original) : Rs. 1,620M

(Revised) : Rs. 2,399MContract Cost (Original) : Rs. 501M

(Revised) : Rs. 570 MPSDP Allocations (2012-13) : Rs. 50 MConsultant : M/s KCEIContractor : M/s NLCDate of Start : Jun-2006Date of Completion (Original) : Nov-2007

(Revised) : Dec-2009(Actual) : Sep-2010

Overall Progress (Actual) : Subst. Complete

Current Status:

Substantially completed.