Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16,...
Transcript of Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16,...
![Page 1: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/1.jpg)
1
Program Delivery Committee: Major Projects Update
January 16, 2019
Joe Carpenter, P.E., P3 Director
![Page 2: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/2.jpg)
2
We Will Cover
• Design-Build Program
• P3 Projects
• Northwest Corridor Express Lanes
• Transform 285/400
• Major Mobility Investment Program
![Page 3: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/3.jpg)
3
Design-Build Program Approach
![Page 4: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/4.jpg)
4
Design-Build Approach
Targeted Outcomes Faster Construction Severe Distress/Emergency Impacts
Reduces Lengthy Detours
Economic Impacts
Freight Movement Posting on Weight
!!!
![Page 5: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/5.jpg)
5
Recent DB Developments
Wilkes County, FY16 Bridge Bundle SR 21 Pedestrian Bridge Courtland Street Bridge
![Page 6: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/6.jpg)
6
Recent DB Developments: I-20 at Savannah River Bridge
• DB Team: Superior Construction Company Southeast, LLC and WSP
• Total Budget: $87.4M
• GDOT’s first bi-state DB project; joint effort between SC and GA
Project Let
Construction
Open to Traffic
Legend
2018 2019 2020 2021
10/19/2018
Q3 2019 Q4 2021
![Page 7: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/7.jpg)
7
Recent DB Developments: FY16 Bridge Bundle
• DB Team: 3 Teams
• Total Budget: $50.2M
• Updating aging infrastructure
• 17 of 24 bridges are open to traffic
Bridges In Design: 3
Bridges Under Construction: 4
Bridges Open: 17
Kick-Off
Meeting
Contract Completion
Legend
Construction
starts
Closed
to Traffic
2016 2017 2018 2019
8/16 8/19 1/18 2/18
Example Timeline:
Sandtown Road
![Page 8: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/8.jpg)
8
Recent DB Developments: FY17 Bridge Bundle
• DB Team: United Consulting/ICE
• Total Budget: $24.8M
• Updating aging infrastructure
• Construction on first three bridges begins January 2019
Bridges In Design: 10
Bridges Under Construction: 3
Kick-Off
Meeting
Contract Completion
Legend
Construction
starts
Closed
to Traffic
Example Timeline:
Jones Martin Road
2017 2018 2019 2020
8/17 9/20 9/18
1/19
![Page 9: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/9.jpg)
9
Recent DB Developments: FY18 Bridge Bundle
FY18 Bridge Bundle
• DB Team: 2 Teams
• Total Budget: $25.5M
• Updating aging infrastructure
• First bridge closures: Q3 20192018 2019 2020 2021
8/18 7/21 Q4
Bridges In Design: 11
Kick-Off
Meeting
Contract Completion
Legend
Construction
starts
Example Timeline:
Houston Valley Road
![Page 10: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/10.jpg)
10
Recent DB Developments: I-85 Corridor Bridges
• DB Team: Georgia Bridge & Concrete/Wolverton & Assoc.
• Total Budget: $15.5M
• Updating aging infrastructure and to accommodate for the future widening of I-85
• Upcoming activities
o Old Stagecoach Road closure: January 2019
o Cedar Ridge Road closure: February 2019
2017 2018 2019 2020
9/17 9/20 6/18
6/18
Bridges In Design: 2
Bridges Under Construction: 2
Bridges Open: 1
Kick-Off
MeetingContract Completion
Legend
Construction
starts
Closed to
Traffic
Example Timeline:
Plainview Road
![Page 11: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/11.jpg)
11
Recent DB Developments
SR 135 at Altamaha River
• Total Budget: $21.6M
• Includes TIA Band 2 Funding
• Upcoming activities
• RFP: March 2019
• Letting: July 2019
SR 247 and CR 5813 over Norfolk Southern Bridges
• Total Budget: $6.3M
• New bridge will allow for double-stacking containers
• Upcoming activities
• RFP: April 2019
• Letting: Q3 2019
Houlihan Bridge and Middle River Bridge
• Total Budget: $52.4M
• Degrading structural and foundational integrity
• Upcoming activities
• RFP: February 2019
• Letting: June 2019
SR 53 at Chattahoochee River
• Total Budget: $25.5M
• Design is below the current design standards
• Upcoming activities
• RFP: March 2019
• Letting: July 2019
![Page 12: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/12.jpg)
12
P3 Projects
![Page 13: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/13.jpg)
13
Northwest Corridor Express Lanes
Opened to traffic September 8, 2018
• 39 bridges
• 68 retaining Walls
• 1.9 million square feet of sound barriers
• 13 toll access points
• 11 supplemental agreements
98.8% of total DBF Contract Sum
$35M of developer financing for payment to developer at Final Acceptance
Project will be delivered within $834M budget
$
$
$
![Page 14: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/14.jpg)
14
Northwest Corridor Express Lanes Success
Travel speeds are 30% faster in the express lanes than in the general
purpose lanes
Rush hour has been reduced by 1 hour
Total trips: 1.8 million
Weekday trip average: 23,600
23.6K
Average weekly fare: $1.60
1.8M
![Page 15: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/15.jpg)
15
Transform 285/400
• Upcoming activities
oMount Vernon Highway, phase 1 completion: Q2 2019
o Roadway cuts and fills
oDrainage installation
o Roadway surfacing
o Bridge installation
oMSE walls construction
oNoise barrier construction
o Utility relocations at Abernathy Road
o Blasting on I-285 eastbound
Bridges
• Total: 32
• Under Construction: 10
Retaining Walls
• Total: 152
• Under Construction: 14
Sound Barriers
• Total: 16
• Under Construction: 1
Designed to help reduce traffic congestion and safety in and near the I-285/SR
400 interchange. Adds new flyover ramps, CD lanes, and bridge replacements.
![Page 16: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/16.jpg)
16
Bridge footing work at I-285 westbound
![Page 17: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/17.jpg)
17
MSE wall construction
![Page 18: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/18.jpg)
18
I-285/SR 400 interchange
![Page 19: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/19.jpg)
19
Major Mobility Investment Program
![Page 20: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/20.jpg)
20
11 MMIP Projects
3 Major
Interchange Projects
4 Major
Express Lanes Projects
3 Major
Interstate Widening
Projects
1
Commercial Vehicle
Lanes Project
![Page 21: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/21.jpg)
21
Proactive Outreach to Date
Over 130 meetings in the past 24 months with:
• HOAs
• Cities
• Counties
• Rotary clubs
• CIDs
• Schools
![Page 22: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/22.jpg)
22
I-85 Widening
• DB Team: C.W. Matthews, Infrastructure Consulting & Engineering
• $135M
• Adds 26 new lane miles and replaces three overpass bridges
• Construction start: July 2018
• Open to traffic: 2020
• Second phase to begin in 2025
• Upcoming activities
o Spout Springs Road Bridge detour and demolition: January 21
o Grading
o Median drainage
![Page 23: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/23.jpg)
23
16@95 Improvement Projects
• DB Team: Savannah Mobility Contractors (SMC)
• $308.2M
• Reconstructs directional ramps at I-16/I-95 interchange and widens I-16
• Upcoming activities
o Mobilization of project team to Savannah
o Community/neighborhood outreach
o Project field data collection
o Ceremonial groundbreaking: Q2/Q3 2019
![Page 24: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/24.jpg)
24
SR 400 Express Lanes
• GEC: AECOM
• $1.2B
• Upcoming activities
o ROW impact meetings: February
o PNA: Q2 2019
o RFQs: Q4 2019
o Construction to start late-2021
![Page 25: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/25.jpg)
25
SR 400 Express Lanes Public Involvement Timeline
2024:Open to traffic
2017:Environmental process began
2019:January 14Fulton County Schools meeting
January 16Fulton County Schools meeting
2019:February 28 PIOH 1 & 2
March 5PIOH 3
March 7PIOH 4
March 12PIOH 5
2019-2020:Right-of-way (ROW) acquisition
2021:Q1/Q2 PHOHs
Q3/Q4Final EA
Construction
starts
Continuous Community Involvement
2019:February 5Early ROW meeting
February 7Early ROW meeting
![Page 26: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/26.jpg)
26
I-285 Top End Express Lanes
• GEC: Jacobs
• $4.6B
• Upcoming activities
o TIP Amendment to adjust project limits and budget
o Early ROW acquisitions
o Community meetings: Q1 2019
o Public Information Open Houses (PIOHs): Late-2019/Early-2020
o Construction to start 2022
![Page 27: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/27.jpg)
27
I-285 Eastside Express Lanes
• GEC: Atkins
• $784M
• Upcoming activities
o Finalize Need and Purpose
o Draft Concept report: February
o PIOHs: Q2/Q3 2019
![Page 28: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/28.jpg)
28
I-285 Westside Express Lanes
• GEC: ARCADIS
• $422.6M
• Upcoming activities
o Traffic count collections
o Status meetings with GEC to begin late-January/early-February
o PIOHs: Q2/Q3 2020
![Page 29: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/29.jpg)
29
I-285/I-20 East Interchange
• GEC: Parsons Transportation Group
• $449.7M
• Upcoming activities
o Preparing Alternative Concepts that do not preclude the future I-20 Express Lanes.
o Develop future year traffic volumes
o PIOHs: Q2/Q3 2019
![Page 30: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/30.jpg)
30
I-285/I-20 West Interchange
• GEC: WSP
• $412.5M
• Upcoming activities
• Determining ROW needs
• Status meetings with GEC to start late-January/early-February
• On-board traffic count vendor
• PIOHs: Q2/Q3 2020
![Page 31: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/31.jpg)
31
I-75 Commercial Vehicle Lanes
• GEC: RS&H, Inc
• $1.6B
• Upcoming activities
o Environment survey memos
o Henry County SPLOST/engineering meeting: Q2 2019
o PIOHs: Q2/Q3 2020
![Page 32: Program Committee: Major Projects Meeting Documents...Committee: Major Projects Update January 16, 2019 Joe Carpenter, P.E., P3 Director. 2 We Will Cover ... •GDOT’sfirst bi-state](https://reader034.fdocuments.us/reader034/viewer/2022042217/5ec096171792377357153c23/html5/thumbnails/32.jpg)
32
www.dot.ga.gov/MMIP@GeorgiaDOT @GADeptofTrans @gadeptoftrans
THANK
YOUFor Viewing