AS ON 31.01.2015
-
PERFORMA P-47A
STATUS OF MAJOR DEVELOPMENT WORKS HAVING BUDGET PROVISION OF RS.1.00 CRORE AND ABOVE
(WHICH ARE LIKELY TO BE COMPLETED DURING THE YEAR 2014-2015) UPTO 31.01.2015
HUDA CIRCLE FARIDABAD
Sr.
No.
Name of work Estimated cost / Approval
No. & Date
( Rs. In lacs)
Budget
for the
year
2014-15
( Rs. In
lacs)
Likely
date/
date of
start
Upto
date
Expd.
(Rs. in
lacs)
Likely
date of
completion
Action
Plan
Remarks
1 2 3 4 5 6 7 8 9
Divn.1, Faridabad.
1. ROB on bye pass road between
sector 59 & 61, near Malerna
Railway crossing, Faridabad.
Detail of amount deposited to
Railway Deptt.
i) 08.10.07 Rs. 5.54 crores
ii) 17.10.07 Rs. 2.68 crores
iii) 04.03.08 Rs. 2.04 crores
iv) 31.03.11 Rs. 1.50 crores
v) 31.05.11 Rs. 0.75 crores
vi) 30.06.11 Rs. 0.75 crores
vii)06.01.11 Rs 0.02 crores
viii)29.07.11 Rs. 1.15 crores
Total Rs.14.43 crores
i) For approaches
Revised estimate appvd.
vide CA letter no.6045-48
dt.10.02.11 for Rs.1917.50
lacs. Original estimate
Rs.1220.00 lacs C.A.
No.19745 dt.11.08.2005
ii)For railway portion, revised
estimate apprd. Vide CA
No.628 dt.05.01.2011 for
Rs.1989.42 lacs. Original
estimate Rs.826.12 lacs-
37093 dt. 23.10.07.
iii)Estimate for Rs.1.1768
crores (shifting of
transmission line) appd. vide
CA No.24714-19
dt.19.07.2011 Total =
Rs.4024.60
300.00 10.03.08
3867.57 31.01.2015
Work completed
--
The work of construction of approaches has been allotted with
restricted amount of Rs.932.72 lacs which has been further
increased Rs.2329.00 lacs.
The work for Railway portion completed.
The work in HUDA portion has been completed on
31.01.2015.
Reasons of delay:-
i) Due to increase in height of Railway portion. From 6.5 mtr. to
8.05mtr. GAD approved by Railway Department-27.11.2009.
ii) 132 KVA Transmission line of railway deptt. shifted -
31.01.2013.
iii) Shifting of casted RCC girders by railway (lying in the
alignment of approaches) 30.08.2013.
iv) GAD rechecked and cleared by Railway Department-
16.04.2014.
ContdP/2
-
-:2:-
Sr.
No.
Name of work Estimated cost /
Approval
No. & Date
( Rs. In lacs)
Budget for
the year
2014-15
( Rs. In
lacs)
Likely
date/ date
of start
Upto date
Expd.
(Rs. in
lacs)
Likely date
of
completion
Action Plan Remarks
1 2 3 4 5 6 7 8 9
2 Constn. of Polyclinic
building Sec-55, Fbd.
394.30-CA 14771-
75 dt. 19.04.2012
100.00 19.10.12 468.54 31.03.2015 G.F. slab laid. Brick work on F.F. completed
Revised Estimate approved Rs.580.48 by CA HUDA Pkl. letter
No.17328 dt.11.07.14. Work will be completed upto 31.03.2015.
3 S/R of road Ankhir
Chowk to Surajkund
Road and Guraon Mor
to Ankhir Chowk.
8505 .00
11865-68/
11.03.13
2300.00 11.04.13
05.08.13
3958.00 31.03.2015
31.10.14
Bituminous work :-
Total length = 7.50 Km, 6.50 Km completed & balance work is in
progress.
RMC work has been completed.
Divn.-2, Fbd.
4 Re-constn. of dividing
road Sec-12-15A,12-
15&13-14, Fbd.
746.49/
49779/ 28.12.12.
300.00 05.08.13 561.15 30.11.2014 - Total length - 2.25 Km - Work completed
on both the carriage way and both
the carriage way are made functional
Divn.-3, Fbd.
5 Construction of dual
carriage way on
periphery road of NH-
3, Faridabad.
14.70 Crore CA
20866-69 / 19.8. 14
500.00 09/2014 1410.54 28.02.2015
The DNIT approved for Rs. 13.12 Crore on 28.7.2014 in anticipation of
administrative approval of estimate. Tender approved on 28.8.2014 and
work allotted on 3.9.2014. Approx 95% work completed at site.
Target Achievement
Construction of 3400 Mtr.
x2 x 8.5mtr. each
carriageway
3400 Mtr. road portion
completed.
ContdP/3
-
-:3:-
Sr.
No.
Name of
work
Estimated cost /
Approval
No. & Date
( Rs. In lacs)
Budget for
the year
2014-15
( Rs. In lacs)
Likely
date/ date
of start
Upto date
Expd.
(Rs. in
lacs)
Likely
date of
completion
Action Plan Remarks
6 Consn. of
Master
road Sec-
75 to 89,
Faridabad.
R/C/E for master
road 75-89, Fbd.
approved vide
CA HUDA No.
41719 dated
16.12.2011 for
Rs.391.77
crores.
3500.00 01/04/12 22292.12 30.09.2014
31.03.2015
The work was allotted for restricted amount of Rs.225.98 Crore for 29.50 km of Master roads. At present work is going on in 38.495 km.
Date of start : 01.04.2012
Likely date of completion : 31.03.2015
The total length of Master road Sector 75 to 89, Fbd. is 44.925 km out of which
possession of 38.895 km road length has been given by Estate Office, HUDA Fbd.
The work is held up on 6.03 km & detail is as under :- a) Section -6 notified on 31.12.2013 and award likely
to be announced- - 0.41 km
b) Possession held up as CWP disposed Off with the direction of Honble High Court to provide alternate plot to land Owners - 0.465 km
c) Possession held up due to protect from the Farmers regarding pending CWPS (10514/2009, 10491/2009,
11143/2008, 8243/2009, 16318/2009, 8483/2009,
11165/2008, 8396/2009, 8525/2009, 6782/2009,
13631/2012,13302/2012,20830/2013) in High Court - 1.175 km
d) Possession held up due to protect of farmers regarding land rates. Estate Officer is making efforts to get possession
at an early date - 3.750 km
e) Possession due to dispute between farmers & colonizers. - 0.230 km - 6.03 km
The balance work in 6.03km will be completed in six months from the date of handing over of possession by LAO/EO/STP, Faridabad.
The work in 38.895 Km is likely to be completed upto 31.03.2015 & physical progress is as under:-
Physical Target Revised physical target Achievement
29.50 km road to
be completed in
all respect.
38.895 Km road to be
completed by 31.03.2015
a) Earth work -38.895 km
b) GSB 38.00 km
c) WMM 37.00 km
d) DBM 35.50 km
e) BC - 33.50 Km
ContdP/4
-
-:4:-
Sr.
No.
Name of work Estimated cost
/ Approval
No. & Date
( Rs. In lacs)
Budget for
the year
2014-15
( Rs. In lacs)
Likely date/
date of start
Upto date
Expd.
(Rs. in lacs)
Likely date
of
completion
Action
Plan
Remarks
Divn. Palwal
7 Widening of 18 wide road, Ph-I,
Rojkameo
260.60
2098
dt.11.01.13
50.00 08.04.13 22.38 30.09.2014
31.03.2015
Work in progress & status as under:-
Target Achievement
i)Widening from
(3.66 m to 7 m) = 4.6Km 2 WBM layer completed in
4.00 Km length
ii)S/R with BM &
25mm DBC = 4.6 Km ---
Divn. Elect.
8 Prov. & fixing of HT line with
AB cable 50sqmmx3core on 11
mtr. long PCC pole and T/F for
street light in Sec-75 to 89, Fbd.
2011.00 C.A.
No.40317
dt.11.10.2012
200.00 05.11.2012 216.77 30.09.2014 22.57 Km Work completed.
-
PERFORMA P-48A
STATUS OF MAJOR DEVELOPMENT WORKS HAVING BUDGET PROVISION OF RS.1.00 CRORE AND ABOVE
(WHICH ARE LIKELY TO BE STARTED IN THE YEAR 2014-2015 AND TO BE COMPLETED IN SUBSEQUENT YEAR(S)) UPTO 31.01.2015
HUDA CIRCLE FARIDABAD
Sr.
No.
Name of work Estimated
cost /
Approval No.
& Date
(Rs. In lacs)
Budget for
the year
2014-15
(Rs. In lacs)
Likely
date/ date
of start
Upto date
Expd.
(Rs. in
lacs)
Likely date of
completion
Action
Plan
Remarks.
1 2 3 4 5 6 7 8 9
Divn.-1
1
Const. of Master
Storm Water
Drainage Scheme
Sec-75 to 89, Fbd.
144.40 crores
apprd. vide
CA letter
No.40980-84
dt.18.10.12
5220.00 30.10.13
7378.52 30.06.2015 24.00 Km RCC box drain completed & balance in progress.
Divn.-2
2 Dev. of new sectors
Agra Canal. ( Ext.
Sewer).
5475.00
3781/
30.01.12
1200.00 09/2012 3700.01 15.08. 14
(For completion
of enhanced
work 30.06.15)
The work was allotted for restricted amounts of Rs.32.71 crores for 31.865 Km
of sewerline. At present work is going on in 38.495 Km. length.
Date of start : 30.09.2012
Likely date of completion : 30.06.2015 for 38.495 km complete in all respect.
Total land length of roads for Sec-75 to 89 is 44.56 Km out of which
possession of 38.495 Km has been given by E.O.HUDA Faridabad.
The detail of work is as under:-
Phy.Target Rev.Phy. Target Achievement
31.865 38.495 (clear land) 34.500
Manholes - 813 Nos. 561 Nos.
Revised length 38.495 Km (clear land) sewerline to be completed by
30.06.2015.
Total revised target 45.020 Km to be completed according to clearance of land
ContdP/2
-
-:2:-
Sr.
No.
Name of work Estimated cost /
Approval No. &
Date
(Rs. In lacs)
Budget for
the year
2014-15
(Rs. In lacs)
Likely
date/ date
of start
Upto date
Expd.
(Rs. in
lacs)
Likely
date of
comple-
tion
Action
Plan
Remarks.
1 2 3 4 5 6 7 8 9
Divn. -3, Fbd.
3 Constn. of RUB
Near Old Fbd.
Revised R/C/E
approved vide
C.A. letter
No.6025
dt.10.02.11 for
Rs.1548.00 lacs
300.0 0 9/11/2011 1315.03 30.04.2015 The work was allotted with a restricted amount Rs. 1293.00 lacs. The RUB approaches towards Mathura road , railway station / NIT site and sector -21B &
village Fatehpur Chandila has been completed.
The work on approaches towards village Fatehpur Chandila has been completed recently. Approval received for demolisation of existing school room & reconstruction of the same
within the school premises convey vide Director Secondary Education Haryana memo
No.6/21/14 dt.30.04.2014.
The work has been delayed due to :-
The resentment raised by villagers of Fatehpur Chandila & Sector -21B for change in GAD & Design at various locations i.e. opening of approaches toward village Fatehpur Chandela &
Sector -21B.
The site of sump well is yet to be given by railway department. Efforts are being carried out to get the site of sumpwell.
The case of sump well for transfer of land (Way leave charges) is pending with Sr. Divisional Engineer in the O/o DRM office, New Delhi. A meeting was held up in his office on
20.06.2014 & on 20.09.2014 and it was decided to make a combined scheme for disposal of
storm water of railway yard alongwith RUB. The survey has been carried out & combined
scheme sent to Railway deptt. vide E.E.-3,HUDA Faridabad letter No. 6739 dated 03.07.2014.
Reminder & drawings again submitted personally vide E.E. 3,HUDA Faridabad No. 13155-58
dated 05.12.2014. He ensured that necessary approval will be accorded very soon.
The physical progress of work is as follows : -
Physical Target Achievement
Retaining wall 860 mtr. Completed
RMC approaches 580 mtr. Completed
Service road 550 M Completed
Approach roads from Mathura
road to RUB 120 M
Completed
Shifting of electrical , sewer,
water supply line
Services towards Mathura road already shifted. 900 mm W/S
line of Ranney Well scheme has been dismantled & made
functional.
Const. of sump well, machinery
and drain.
The approval from Railway Authority is awaited.
ContdP/3
-:3:-
-
Sr.
No.
Name of
work
Estimated
cost /
Approval No.
& Date
(Rs. In lacs)
Budget for
the year
2014-15
(Rs. In
lacs)
Likely
date/ date
of start
Upto
date
Expd.
(Rs. in
lacs)
Likely
date of
comple-
tion
Action
Plan
Remarks.
1 2 3 4 5 6 7 8 9
4 Const. of
Indoor
Stadium
Sector -12,
Fbd.
CE No. 11777-
80 dt.11.03.13
for Rs.
1704.00 Lacs.
800.00
Lacs
01/07/2013 739.97 30.09.2015 The vetted drawing has been given to the contractual agency. The work has been started. Fabrication
of structural steel has been started at site. The physical progress is as under:- Physical Target Achievement
Footing 72 Completed upto plinth beam
Fabrication of Major truss 8 Nos. of
size 167 feet span
Completed
Fabrication of Minor truss 4 Nos.
100 feet span
Completed
Fabrication of truss 4 Nos. 105 feet
span
4 Completed
Fabrication of Minor truss 6 Nos.
75 feet span
Completed
Column 72 Completed
Stands (4 Nos.) 3 Nos. stands completed
Brick work 96% work upto ground floor completed &60% at 1st floor.
Entry 4 Nos. 4 Nos. completed upto slab level & 3 No. entry basement slab casted.
Beam at First Floor Height 90% Completed
5 R/C/E for
augmentation
of master
water supply
scheme Zone
I (For
Sectors 33,
34, 39, 41,
42, 45, 91 &
Green Field
colony) Fbd.
55.30 Crores
Secy. HUDA
Pkl. Letter No.
38872-75 dt.
29.9.2013
1000.00 29.11.13
830.37 30.06.2015
2Nos.
Ranney
wells for
Rs.25.26
Crores.
A) The Ranney Well construction status is as under:-
Ranney Well No. Casting ( inmtrs.) Well sinking ( in mtrs.)
1. 21.0 mtr. 16.00 Mtr.
2. 7.3 Mtr. 0.00 Mtr.
Work in progress is as under:- Target Achievement
2 Nos. Ranney Wells work The site for 2 Nos. Ranney wells identified and work is in progress.
400mm DI pipes 3.0 Km D.I. Pipe received
8 VT pump 8 Nos. received at site
8 motors 8 Nos. received at site.
70 Sluice valve 70 Nos. received at site.
10 Non return valves 10Nos. received at site.
Cutting edge 2 Nos.
Reasons of delay:-
Arrangement of land/ selection of site for Ranney Wells.
ContdP/4
-
-:4:-
Sr.
No.
Name of
work
Estimated
cost /
Approval
No. & Date
(Rs. In lacs)
Budget for
the year
2014-15
(Rs. In
lacs)
Likely
date/
date of
start
Upto
date
Expd.
(Rs. in
lacs)
Likely date
of comple-
tion
Action
Plan
Remarks.
1 2 3 4 5 6 7 8 9
05.09.14 04.03.16
B) Consisting of 1 Boosting Stations (BS) and 1 UGT, Providing & Stringing of DI Rising Mains
upto Sectors 19,29,33-34 & 91, Faridabad on EPC Basis amounting to Rs.1428.70 lacs. Rs. 1428.70 lacs allotted to M/s Subhash Infraengineers Pvt. Ltd. on 05.09.2014
Target Achievement
1 UGT (4540 KL) Excavation completed, PCC work in
progress
DI. PIPE
DIA QTY. RECEIVED
250 mm 4500
300 mm 500
350 mm 50
400 mm 50
450 mm 50
500 mm 2500
600 mm 4000
1 Nos. Pump house
2 Nos. Staff Qtr.
(1 BHK 815 Sft.
each
11 KV VCB Panel
630 KV
Transformer
500 KVA DG Set
ContdP/5
-
-:5:-
Sr.
No.
Name of
work
Estimated
cost /
Approval
No. & Date
(Rs. In lacs)
Budget for
the year
2014-15
(Rs. In lacs)
Likely
date/
date of
start
Upto
date
Expd.
(Rs. in
lacs)
Likely date
of comple-
tion
Action
Plan
Remarks.
1 2 3 4 5 6 7 8 9
6 Augmentat
ion of
Master
water
supply
scheme
(Constructi
on of
Ranney
Well &
Tube Well
& Tube
Wells)
Sec-75 to
89,
Faridabad
Rs. 198.50
Crores appd.
vide CA
HUDA
Panchkula
letter No.
40461 dt.
12.10.2012.
3500.00
Lacs.
04/2013
14/08/14
5706.76 30.06.2015
13.11.2015
A)Work of Rs. 63.48 Crores allot vide EE-3, HUDA Faridabad letter No. 2850-57 dated 25.03.2013.
Work in progress.
Target Achievement
Land
procuremen
t
The land for 6 Nos. Ranney Well have been purchased
by the agency and transferred in the name of E.O.
HUDA Fbd.
DI pipe The DNIT quantity 9000 mtr. of 400 mm DI pipes
received at site & 7500 M pipe laid at site.
VT Pump All 24 Nos. VT pumps received
Motors All 24 Nos. Motors received
Sluice valve All 180 Sluice valves received
R/Wells construction status as under:-
R/Wells
Sr. Nos.
Casting
(in mtrs.)
Well sinking
(in mtrs.)
Pushing of laterals
5 30.575 28.50 --
6 19.325 15.00 --
7 32.00 28.0 200 Mtr.
8 36.00 32.50 Ready for pushing
9 28.900 27.00 Platform casted
10 28.90 28.80 Platform work started
B) DNIT approved vide C.E. HUDA Pkl. letter No.6628 dt.04.06.14 for Rs.4835.00 lacs and tender
approved in favour of M/s. Tirupati Cement Products for main boosting station and rising main on
dt.14.08.2014, work allotted and started.
ContdP/6
-:6:-
-
Sr.
No.
Name
of
work
Estimated
cost /
Approval
No. & Date
(Rs. In lacs)
Budget
for the
year
2014-15
(Rs. In
lacs)
Likely
date/
date of
start
Upto date
Expd.
(Rs. in
lacs)
Likely
date of
comple-
tion
Action
Plan
Remarks.
1 2 3 4 5 6 7 8 9
15.10.13
31.03.15
C) The work for Rs.58.96 Lacs for providing and installation of 10 Nos. Tubewells allotted on
15.10.2013.
The work status as under:-
Physical Target Achievement
Drilling of Tubewell
10 Nos.
8 Nos. completed
other 2Nos. are in
progress.
Physical Target Achievement
Purchase of land 7 Acre Land has been purchased.
Const. of Main boosting station with
electrical , mechanical installation and
boundary wall.
i) Pump house -1 No
ii) UGT 4500 KL-2 Nos.
iii) Staff Qtr. 1 BHK -2 Nos.
iv) Staff Qtr. 2 BHK -1 Nos.
v) Office cum lab 1 No.
vi) Guest House-1 No.
D.I. rising main
i) 800mm-6000M 2000 mtr. received and 894 mtr. laid.
ii) 1000mm-9250M 6954 mtr. D.I. pipe received & 3000mtr. laid.
Centrifugal horizontal pumps - 5 Nos.
Independent Feeder 9.0 km
ContdP/7
-:7:-
-
Sr.
No.
Name of work Estimated
cost /
Approval
No. & Date
(Rs. In
lacs)
Budget
for the
year 2014-
15
(Rs. In
lacs)
Likely
date/
date of
start
Upto date
Expd.
(Rs. in
lacs)
Likely
date of
comple-
tion
Action
Plan
Remarks.
1 2 3 4 5 6 7 8 9
03.03.14
06.08.14
06.08.14
21.08.14
30.06.15
31.03.15
31.03.15
31.01.15
D) The Work for Rs.101.00 lacs for the construction of 10 Nos. Pump chambers (16x16) at
sector-75 to 89 Fbd. with boundary wall & 3 Nos. of staff quarters along the green belt of 75M
wide master road Fbd. complete in all respect and all other works contingent thereto allotted on
03.03.14
Physical Target Achievement
Pump chamber 10
Nos.
4 Nos. completed upto slab
4 Nos. ready upto slab level
2 Nos work in progress.
3 Nos. staff qtr. 2 Nos. Under progress
Additional 5 Pump
Chamber & staff
qtrs.
Increased from 10 Nos. to 15 Nos. has been approved vide C.E.-
I HUDA, Pkl. memo No.10293 dt.25.08.2014 and work is in
progress.
E) DNIT approved by C.E-I. HUDA Panchkula vide memo No.5183 dated 15.05.2014 for
Rs.147.22 lacs. Tender approved by CE-I on 1.8.2014 & allotted to M/s. Ajit Singh & Baljit
Singh vide E.E.-3, HUDA Fbd. letter No.8131-38 dt.06.08.2014.
Physical Target Achievement
Approach road 6.0 km Earth work completed in 4500 mtr., GSB work started
F) DNIT for 15 Nos. tubewell machinery approved by C.E-I. HUDA Panchkula vide memo
No.4601 dated 15.04.2014 for Rs.26.46 lacs. Tender approved by CE-I on 26.06.2014 & work
allotted to the agency M/s. Vishwakarma Engg. On dt.06.08.2014.
Physical Target Achievement
Providing and installation of
Machinery for tubewells 15 Nos.
Machinery for
15Nos. tube wells
received at site.
G) Tender for other 5 Nos. T.W. approved on 14.8.2014 & allotted to the agency M/s. B&R
Tubewell Drilling Corporation.
Physical Target Achievement
5 Nos. Tubewells drilling. 5 Nos. tubewell drilled
Work completed
ContdP/8
-:8:-
-
Sr.
No.
Name of work Estimated
cost /
Approval
No. & Date
(Rs. In lacs)
Budget for
the year
2014-15
(Rs. In
lacs)
Likely
date/
date of
start
Upto
date
Expd.
(Rs. in
lacs)
Likely
date of
comple-
tion
Action
Plan
Remarks.
1 2 3 4 5 6 7 8 9
7 Master water supply
Scheme Sector -75 to
89, Fbd.
4785 Lacs.
CA No.
40476 dt.
12.10.2012
1700.00
Lacs.
04/2013 1250.10 30.09.2015 The work amounting to Rs.25.35 crores allotted and status as under:-
The 60180 mtr. DI pipes have been inspected at factory premises in Calcutta by M/s. RITES
Ltd.
The Detail of DI pipe dispatched from factory & received at site is as follows : -
Dia DNIT Qty. Received Laid
200 10725 7673
16000 mtr.
laid
250 2990 2970
300 23300 12609
350 2200 2021
400 3585 3217
450 2370 2119
500 5990 6028
600 4155 4278.50
700 1450 1524
800 1180 1160.50
900 2235 1800
TOTAL 60180 45400
Divn. Palwal
8 Augmentation of
water supply scheme
Rozka Meo & Sohna
(Deposit work of
HUDA- by PHE).
Project Cost.
6430.00 lacs
3267.15
22043-46
18.06.09
5.00 03/2013 3265.00 30.06.2015 Deposit work by PHE Department Rs.3265.00 lacs paid by HUDA to PHE Deptt. And work is in progress.
Remarks:- Canal based scheme for = 27 MLD
Water supply demand for Rojkameo Industrial Area = 8.7 MLD
ContdP/9
-:9:-
-
Sr.
No.
Name of work Estimated
cost /
Approval
No. & Date
(Rs. In lacs)
Budget for
the year
2014-15
(Rs. In
lacs)
Likely
date/
date of
start
Upto
date
Expd.
(Rs. in
lacs)
Likely
date of
comple-
tion
Action
Plan
Remarks.
1 2 3 4 5 6 7 8 9
1. Water works at Ghamroj Target Achievement .
a) Staff quarter 4 Nos. Complete
b) S/S tank 2 Nos. Complete
c) CWT 4 Nos. Complete
d) Pump chamber 1 No. Complete
e) WTP 1 No. Complete
f) Boundary wall 1 No. Complete
g) Clarifloculator 1 No. Complete
h) Pumping machinery & Generation set Complete
i) D/I pipe rising main 12 Km laid
2. Water works at Budhera a) S/S tank 2 Nos. 1 Complete & 1 90% complete
b) Pump chamber 1 No. Complete
c) Staff quarter 4 Nos. Complete
d) Pumping machinery & Generation set Fixing in Progress
e) PSC Pipe line 27 Km 25 Km supplied & 21 Km laid
3. Boosting station at Sohna a) UGT 2 Nos. Complete
b) Pump chamber 2 Nos. Complete
c) DI pipe distribution system In progress
600 mm i/d 10100 mtr.
450 mm i/d 800 mtr.
300 mm i/d 950 mtr.
NOTE :
i) Overall civil works = 90% completed
ii) Overall Pipe line laid = 70% completed
* A supplementary estimate received from E.E. PHED Sohna for balance cost for Rs.1212.75
lacs is under process of approval.
Contd..P/10
-:10:-
-
Sr.
No.
Name of work Estimated
cost /
Approval
No. & Date
(Rs. In lacs)
Budget for
the year
2014-15
(Rs. In
lacs)
Likely
date/
date of
start
Upto
date
Expd.
(Rs. in
lacs)
Likely
date of
comple-
tion
Action Plan Remarks.
1 2 3 4 5 6 7 8 9
9 Construction of Road,
Sector-12, Palwal.
769.79
29549
27.07.2012
Dev. 716.82
Mtc. 52.97
90.00 24.12.12 426.74 30.09.2014
30.06.2015
Work in progress & status as under:-
Target Achievement
Sub Grade -12.64Km
GSB -12.64Km
WMM - 12.64 Km
DBM - 1.91Km
SDBC - 1.91 Km
Premix - 10.73Km
Road SWD - 1.00 Km
Kerb stone -15.20 Km
11.50 Km
11.25 Km
10.66 Km
1.91 Km
1.91 Km
8.75 Km
0.91Km
11.20 Km
Road of 2.00 km road is under encroachment/stay but land for road not made clear,
E.O. HUDA Faridabad has to provide clear land for execution of held up road work.
The case for increase in scope of work has been approved vide C.E. HUDA Pkl.
letter No.12406 dt.16.10.2014.
10 Construction of 45 mtr. Wide
master road in Sec-12,
Palwal
524.80 CA
No.21449-53
dt.26.03.2014
5.00 29.10.14 67.09 28.04.2015 Work of earth work including GSB & WMM in 45 mtr. wide road is in progress.
Divn. Elect.
11 Prov. of fixing of street light
on octagonal pole 9/10 mtr.
long with HPSV fitting 250
watt with underground cable
and high mast Fbd. (EDC)
2011.00
C.A.
No.40317
dt.11.10.2012
200.00 05.11.12 569.27 30.06.2015 29.63 Km.
Increased to
39.63 Km
Street light work has been completed and energized on 29.63 Km road length &
additional work of 3.9 Km out of 10 Km. has been completed & balance work is in
progress.
12. Special repair of Surajkund
road from Gurgaon mode
Ankhir Chowk to Pehladpur
Border, Fbd. (Civil work)
200.00 10.07.14 142.43 30.04.2015 12.0 Km Street light work of 7.5 km completed & energized and balance work is in progress
-
16
PERFORMA P-47A
STATUS OF MAJOR DEVELOPMENT WORKS HAVING BUDGET PROVISION OF Rs.1.00 CRORE AND ABOVE
(WHICH ARE LIKELY TO BE COMPLETED DURING THE YEAR 2014-15)
HUDA CIRCLE-I, GURGAON [01/2015]
Sr.
No.
Name of Work Estimated
Cost /App. No.
& Dt.
(Rs. in Lacs)
Budget for
the year
2014 -15
(Rs. in Lacs)
Likely date/
date of start
Upto date
Expenditure
(01/2015)
(Rs. in Lacs)
Likely date of
completion
Action Plan Remarks.
1 2 3 4 6 5 7 8 9
HUDA DIVISION No. II
1. Prov. Distribution mains for Recycle water for Zone-I, II & III, U/E, Gurgaon.
2465.00
CA 3786
30.01.2012
200.00
a Prov. stringing out, jointing, cutting and testing of D.I. pipes of 200mm to
600mm i/d sizes for recycled water,
prov. and laying M.S. pipe of size
600mm through trenchless method etc.
and all other works contingent thereto.
A/c Rs.8.45Crores (Work enhanced from
Rs.8,08,59,757/- to Rs.11.99Crores)
(Original Time limit 12 Months from
07.01.2013 to 06.01.2014)
07.01.2013 854.52 30.06.2015 -- a) Physical Status i) Total DNIT scope 21.48K.M. & completed
19.00K.M. i.e. 90% work completed.
ii) The work in balance 2.48 K.M. is in progress
and affected by various hindrances such as, Court
Stay, NHAI / IOCL permission, Crossing at
Badshahpur Nallah, Pipe line in Tau Devi Lal
Stadium etc.
iii) 0.92 K.M. crossing by trenchless method is in
progress in thickly populated area & 730 M
completed at site.
b) Bottlenecks / Reasons for Delay
Permission from NHAI / IOCL is under approval.
b Prov. stringing out, jointing, cutting and testing of D.I. pipes of balance 100mm
to 450mm i/d sizes for recycled water,
prov. and laying M.S. pipe of size
300mm to 600mm i/d through trenchless
method, prov. and fixing of sluice valves
haudies and all other works contingent
thereto. A/c Rs.13.00Crores /
Rs.12.25Crores. (Original Time limit 12
Months from 12.09.2014 to 11.09.2015)
12.09.2014 231.40 11.09.2015 -- a) Physical Status Total DNIT scope 41.78 K.M. and 18.32 K.M.
pipes inspected at Kolkata.
Work completed 04 Km. and balance work is in progress
-
17
Sr.
No.
Name of Work Estimated
Cost /App. No.
& Dt.
(Rs. in Lacs)
Budget for
the year
2014 -15
(Rs. in Lacs)
Likely date/
date of start
Upto date
Expenditure
(01/2015)
(Rs. in Lacs)
Likely date of
completion
Action Plan Remarks.
2. Const. of Northern Peripheral Road from Kherki Dula to Dwarka,
Gurgaon
13178.00
CA 20851
24.05.2010
200.00
a) Const. of road in 14 K.M length of available land
A/c Rs.57.00Crores (Work enhanced
from Rs.44,08,14,640/- to
Rs.50,01,99,531/-)
01.04.2011
4554.28 30.06.2015 -- a) Physical Status Work completed in 14.33 K.M. available land and
balance work 300 Mtr held up due to non
availability of land.
b) Bottlenecks / Reasons for Delay
Site Physical possession not given by E.O.-I HUDA GGN in a length of 280 Mtr due to agitation of local
affected residents lead by Rishi Raj Rana.
Removal of 66 K.V. gantry poles by HVPNL in 20 Mtr length.
1.31 K.M. under litigation / Court stay and not clear for want of alternate plots policy by E.O. I,
HUDA, Gurgaon. The next date in Honble High
Court is 18.02.2015.
Auction of malba by E.O.-I, HUDA, Gurgaon for the removal of existing structures in 168Mtr length.
b) Const. of 4 Nos Culverts on NPR Road A/c Rs.5.28Crores. / Rs.5,66,20,537/-
(Original Time limit 09 Months from
28.03.2013 to 27.12.2013)
28.03.2013
401.39 28.02.2015 -- a) Physical Status 04 Nos. culvert completed at R.D. 3373 / 9933 /
13739 / 16403.
c) Const. of SWD in 2 x 14 K.M available land. A/c Rs.20.61Crores (Work
enhanced from Rs.18,62,60,082/- to
Rs.26,91,77,436/-)
(Original Time limit 12 Months from
01.04.2013 to 31.03.2014)
22.03.2013
2083.39 31.03.2015 -- a) Physical Status The original scope 31.50 K.M. and 26.64 K.M.
completed.
b) Bottlenecks / Reasons for Delay
2.00 K.M. SWD work will be completed after completion of road work by M/s Atlas Construction
Co. which cant be taken up due to local hindrances.
2.30 K.M. SWD work held up due to ongoing ROB work at site
560 Mtr SWD work held up due to local hindrance / stay / possession not given by E.O. I, HUDA,
Gurgaon.
d) Const. of Road (2 x 12.5m) of Balance Portion & Cross Drainage etc. (1.0Km
Length)
A/c Rs.980.00Lacs / Rs.783.90Lacs.
01.03.2014 0.00 6 Months after
physical
possession is
-- a) Physical Status Total scope in DNIT 1.00 K.M.Work could not be
started due to site hindrances.
b) Bottlenecks / Reasons for Delay
-
18
(Original Time limit 06 Months from
01.03.2014 to 31.08.2014) made available. Site Physical possession not given by E.O. I
HUDA, Gurgaon in a length of 1.00 K.M. due to
agitation of local affected residents lead by Rishi
Raj Rana (900 M) and Jhanda Singh (100 M).
Sr.
No.
Name of Work Estimated
Cost /App. No.
& Dt.
(Rs. in Lacs)
Budget for
the year
2014 -15
(Rs. in Lacs)
Likely date/
date of start
Upto date
Expenditure
(01/2015)
(Rs. in Lacs)
Likely date of
completion
Action Plan Remarks.
3. Const. Of 120 MLD 2nd. STP & MPS at Behrampur, Gurgaon. Tender Amt. E/m
Rs.90.00Lacs / Rs.98.10Crores.
Const. Cost = Rs.73.58Crores.
10% Commissioning = Rs.9.81Crores
15% O & M Charges = Rs.14.71Crores
Total Cost = Rs.98.10Crores
(Original Time limit 18 Months from
22.03.2012 to 21.09.2013 + 03 Months trial
run)
10078.00
CA 6040
10.02.2011
1000.00 22.03.2012 7923.51 31.03.2015 -- a) Physical Status STP work completed upto tertiary treatment &
under commissioning
b) Bottlenecks / Reasons for Delay
The work was allotted subject to decision of Honble High Court & court decision was
conveyed after 6 months and subsequently
work also delayed by 6 months
4. Const. Of 100 MLD 2nd. STP & MPS at Dhanwapur, Gurgaon Tender Amt. E/m
Rs.80.00Lacs / Rs.79.43Crores
Const. Cost = Rs.59.58Crores.
10% Commissioning = Rs.7.94Crores
15% O & M Charges = Rs.11.91Crores
Total Cost = Rs.79.43Crores
(Original Time limit 18 Months from
22.03.2012 to 21.09.2013 + 03 Months trial
run)
9440.00
CA 5992
Dt.10.02.2011
1000.00 23.03.2012 5855.00 31.03.2015 -- a) Physical Status STP work completed upto tertiary treatment &
under commissioning
b) Bottlenecks / Reasons for Delay
The work was allotted subject to decision of Honble High Court & court decision was
conveyed after 6 months and subsequently
work also delayed by 6 months
5. Providing Distribution mains for recycle water from Sector 58 to 80, Gurgaon.
Providing Distribution mains for recycle
water from Sector 81 to 115 (Zone
VII & VIII), Gurgaon ( M/s L & T Ltd.)
A/c Rs.115.60Crores / Rs.11404.20Lacs.
(Original Time limit 12 Months from
01.05.2013 to 30.04.2014)
7420.00
CA 3068
Dt.23.01.2012
16160.00
CA 3771
Dt.30.01.2012
500.00 01.05.2013 8941.46 30.06.2015 -- a) Physical Status DNIT Scope
(In Mtr)
Pipe Received
(In Mtr)
Pipe laid
(In Mtr)
58400 58241 40200
4.64Km clear site but taken in hand after construction of box drain and manhole.
The overall work progress 93% in clear available site.
b) Bottlenecks / Reasons for Delay
The site unavailable in 13.40 K.M. due to various hindrances such as, road not
constructed at site due to non acquisition of
land / change in alignment (9.54 K.M.), Court
stay (2.50K.M.), encroachment at site (1.23
K.M.), Railway crossing permission (0.13
K.M.).
-
19
Sr.
No.
Name of Work Estimated
Cost /App. No.
& Dt.
(Rs. in Lacs)
Budget for
the year
2014 -15
(Rs. in Lacs)
Likely date/
date of start
Upto date
Expenditure
(01/2015)
(Rs. in Lacs)
Likely date of
completion
Action Plan Remarks.
6. Providing master sewerage scheme of Sector -77 -115 Urban Estate Gurgaon
A/c Rs.124.70Crores /Rs.12002.25Lacs.
(Original Time limit 18 Months from
16.01.2013 to 15.07.2014)
38148.00
CA3776 -80
Dt.30.01.2012
2500.00 21.01.2013 2356.84 01.07.2015 Size - Qty
(i/d) - (in Mtr)
600mm-21625
800mm-20235
900mm-11050
1000mm-36350
1200mm-9000
1600mm-10850
1800mm-3200
2000mm-19400
2400mm-1000
Total 132710
S.W. Pipe
500mm-21475
GTotal-154185
Say-154.19Km.
a) Physical Status
DNIT Scope, only
HUDA, Division No. II,
Gurgaon
(In K.M.)
(RCC Np3 pipe 600mm
to 2000mm i/d, and
500mm S.W. pipes)
Pipe
Received
(In K.M.)
Pipe laid
(In K.M)
47.56 21.00 19.20
Work in progress on clear available site 35.80 K.M. and likely to be completed by 01.07.2015.
The overall work progress 37% in clear available site.
b) Bottlenecks / Reasons for Delay
The sewer line in 11.76 K.M. length is affected due to various hindrances such as, congested
portion on Pataudi Road (4.275 K.M.), Stay
portion (4.855K.M.), land under acquisition and
change of alignment (2.63 K.M.).
The scheme revised due to interference of levels by Master SWD Scheme and
TPI engaged for testing of material after allotment of 6 months by approval from the Chief
Engineer I, HUDA, Panchkula
The above status is for HUDA Division No. II, Gurgaon and total scope is 62.70 K.M., including
the scope of 15.14 K.M. of HUDA Division No.
V, Gurgaon
-
20
HUDA DIVISION No. III
7. Providing master water supply
scheme. Construction of 22MGD
Treatment Plant at Village Chandu
Budhera.
Rs.13200.00Lacs / Rs.12900.00Lacs
Revised
14092.00,
CA20830-33
Dt.24.05.10
800.00 04.12.2009 13191.37 Work
Completed
-- The civil works completed and 22 MGD WTP is commissioned and functional.
Sr.
No.
Name of Work Estimated
Cost /App. No.
& Dt.
(Rs. in Lacs)
Budget for
the year
2014 -15
(Rs. in Lacs)
Likely date/
date of start
Upto date
Expenditure
(01/2015)
(Rs. in Lacs)
Likely date of
completion
Action Plan Remarks.
8. Construction of Master Roads in
New Sector 81 to 95, Gurgaon.
(Different following Seven Nos.
works allotted to different agencies)
27974.00
CA23416
Dt.09.06.2010
500.00 10249.00 As per estimate 75Mtr = 11.33 Km
60Mtr = 31.70 Km
Total = 43.03 Km
As per Allotment 75Mtr = 11.78 Km
60Mtr = 26.83 Km
Total = 38.61 Km
Work Completed 75Mtr = 11.71 Km
60Mtr = 18.67 Km
Total = 30.38 Km
Length under changes of
alignment /
litigation / stay
75Mtr = 0.35 Km 60Mtr = 7.88 Km
Total = 8.23 Km
Work completed in available land.
a D/Road 81A/82A & 81/82 Rs.8.88Cr./Rs.6.95Cr. (21.81% Below)
(M/s Bestech India Pvt. Ltd.)
24.03.2011
Work completed except stay portion.
The stay portion will
be completed within 2 Months after clearance
of litigation/ Stay
b D/Road 90/91, 91/92, 85/89 & 86/90 Rs.23.27Cr./Rs.18.22Cr.(21.70%Below)
(M/s DLF Ltd.)
24.03.2011
Work completed except stay portion.
The stay portion will
be completed within 4 Months after clearance
of litigation/ Stay
c D/Road Rs.75.80Cr./Rs.65.45Cr.(13.55%Below).
(M/s K.C.C. Buildcon)
17.01.2012
30.04.2014
Stay portion will be completed within 4
Months after clearance
of litigation/ Stay
d D/Road 92/95 Rs.11.65Cr./Rs.8.66Cr. (25.60% Below).
(M/s Ram Prastha)
25.01.2012
30.04.2014
Stay portion will be
completed within 4
Months after clearance
of litigation/ Stay
e D/Road 89/93 & 89/94 Rs.10.09Cr./Rs.6.88Cr. (37.45% Below).
(M/s Orries Infrastructure)
12.04.2012
Work completed except stay portion.
The stay portion will
be completed within 4 Months after clearance
of litigation/ Stay
f D/Road 91/92 & 93 and 85/86 07.07.2011 Work completed
-
21
Rs.14.17Cr./Rs.10.76Cr.(24.01%Below)
(M/s DLF Ltd.) except stay portion.
The stay portion 360 M which is under
encroachment/litigation
& work will be completed within 4
Months after clearance
of litigation/ Stay
g D/Road 82/83, 82/85, 84/85, 83/84 and 82/82A
Rs.27.65Cr./Rs.21.62Cr.(21.80%Below)
(M/s Vatika Ltd.)
25.03.2011 Work completed except stay portion.
Stay portion will be
completed within 6 Months after clearance
of litigation/ Stay
Sr.
No.
Name of Work Estimated
Cost /App. No.
& Dt.
(Rs. in Lacs)
Budget for
the year
2014 -15
(Rs. in Lacs)
Likely date/
date of start
Upto date
Expenditure
(01/2015)
(Rs. in Lacs)
Likely date of
completion
Action Plan Remarks.
10. Construction of 2 No. S & S tanks of W.T.P., Basai.
3865.00
C.A. 5987
Dt.10.02.2011
200.00 4134.78 Total scope of work Tank no. 5 = 195 X 400 X 5.00M
Capacity = 335900 KL Tank no. 6 = 650 X
450 X 3.85M
Capacity = 361900 KL Constn of CC road =
3300M
Brick B.Wall = 2600 M
RCC inlet channel =
700M RCC outlet channel =
1150 M
RCC culvert = 7 Nos Provision of CWT =
02Nos
RCC channel for filling of tank by
gravity = 350 M
a) Construction of 2 Nos. RCC Clear Water Tank of 9100 KL capacity each of one
compartments / 20.00Lacs gallons capacity of
size 55x55x3.0 Mtr. (working depth)
Including providing and laying of MS pipe,
specials and sluice valve for connection for
inlet, outlet and overflow pipe etc at site of
WTP Vill. Basai, Gurgaon and all other
works contingent thereto. (Including one
year defect liability period and mtc. free of
15.04.2013 31.12.2014 2 Nos. tank 9100KL capacity
each
Work completed.
-
22
cost) A/C Rs.5.00Crores / Rs.6.80Crores
11. Designing, Construction, Testing, Commissioning, Operation and Maintenance
for 5 years after 12 months defect liability
period of Second Water Works comprising of
Raw Water pumping Machinery, 22MGD
Automated Water Treatment Plant, Clear
Water pumping machinery, Pre & Post
chlorination, lowering of sub soil water,
1000 mm dia. MS Rising Main for Clear
Water up to Basai Water Works, Transformer,
SCADA and all other works contingent there
to complete in all respects on Turn Key basis
for HUDA at Village Chandu Bhudhera,
District Gurgaon, Haryana.(2nd Unit)
Rs.3000.00Lacs / Rs.2693.90Lacs
3840.00
CA - 5982
Dt.10.02.2011
600.00 17.01.2012 3070.53 Work
Completed
i) 22 MGD WTP.
ii) 01No. CWT
9100KL
iii)Raw water
pumping
machinery
iv)Clear water
pumping
machinery
v)Scada System
The civil work completed and 22 MGD WTP is
functional since 31.12.2013
Sr.
No.
Name of Work Estimated
Cost /App. No.
& Dt.
(Rs. in Lacs)
Budget for
the year
2014 -15
(Rs. in Lacs)
Likely date/
date of start
Upto date
Expenditure
(01/2015)
(Rs. in Lacs)
Likely date of
completion
Action Plan Remarks.
13. Dismantling of Raw water pump house No. I with allied and construction of new
Raw water pump house at WTP Basai,
Gurgaon. Construction of Clear Water
Pump House of size 55 X 10 M, Sump
well 40 X 5 X 5.5 M, RCC GWS
Channel, Gen Set Room, C.I. pipes &
specials and all other works contingent
thereto
A/C Rs.348.05Lacs / Rs.382.82Lacs
678.40
CA.37556
Dt.25.09.2012
300.00 25.10.2014 476.25 Work
Completed
i)Pump chamber 55
x 10 M = 01 Nos.
ii)RCC channel
covered 2.75 x
2.45M = 1.60 M
iii) RCC channel
without slab 2.75 x
2.45M = 100 M
iv) Pump 710 LPS
15M head = 07
Nos.
v) V.T. pump 35
cusecs 7.5M head =
03 Nos.
Work completed
14 Providing, cutting & jointing of 450mm i/d pipe line from boosting station Sector-
72 to Gwal Pahari on Faridabad road
815.00
CA. 9244-45 200.00
411.47
i) 450mm DI pipe = 9.00 KM
ii) 250mm DI pipe =
2.15 KM
-
23
a) Providing master water supply scheme (distribution mains) for new sector-58
to 115 (Zone-IV to VIII), U/E, Gurgaon.
Providing, stringing out, jointing,
cutting and testing of 450mm i/d DI pipe,
providing & fixing of sluice valves
construction of sluice valves haudies and
all other works contingent thereto.
(Including A/Mtc. for 3 years) from
sector-51/57 to Gwal Pahari.
A/C Rs.6.36Crores / Rs.5.75Crores
Dt.22.02.2013 07.11.2012 31.03.2015 -- 72% work completed at site (6.00Km 450mm line laid & 3213 Mtr. pipe received at site). Water
supply pipe line laid upto village Baliyawas. For
250mm dia DI pipe = 2.00Km in place of 450mm
i/d is under process for approval and will be laid
simultaneously along with 450mm i/d pipe after
approval of N.S. item.
Action under clause II have been taken for slow
progress. Work is likely to be completed upto
31.03.2015.
HUDA DIVISION No. V
15. a) Master Sewer Leg No. V (58 to 76) Rs.3540.00Lacs
b) Master Sewer Sector 99 to 115,
Gurgaon.
Part of A/C Rs.124.70Crores
11650.00
CA.41727-31
Dt.16.12.2011
1200.00 01.04.2012 2292.63 31.03.2015 As per estimate 66.45Km work
allotted 23.44Km
completed
19.53Km. Balance
2.31 Km. sewer
line laid by MCG
and to be
completed by
31.03.2015
Status of Work
Total Length : 23.44 Km.
Length of sewer work : 19.53 Km. completed (Work completed
on the available land)
Length of sewer line laid : 2.31 Km. by MCG
Bottleneck : 1.60 km a) 0.70 km due to change in alignment of road at
dividing sector 63/64 approved by Director
Town Country Planning. Land is under
acquisition.
b) 0.90 km land litigation
Sr.
No.
Name of Work Estimated
Cost /App. No.
& Dt.
(Rs. in Lacs)
Budget for
the year
2014 -15
(Rs. in Lacs)
Likely date/
date of start
Upto date
Expenditure
(01/2015)
(Rs. in Lacs)
Likely date of
completion
Action Plan Remarks.
16. Construction of Master Roads in New Sector 99 to 115, Gurgaon.
21255.00
CA.23387
Dt.09.06.2010
2000.00
8696.17
Total Road length against approved estimate = 30.88Km.
Work allotted against approved
estimate = Rs.8270.00Lacs
Work completed = 18.00Km
Detail of balance work of 12.88 K.M.
Land not acquired as yet = 8.945K.m. Encroachment of land to be = 2.730K.m. cleared after removing
structures ______________
Total =11.730Km
DNIT amounting to Rs.13.00Crores for sector road between 101/104
involving 1.15 K.M. length
approved recently = 1.15K.m.
a) A/C Rs.82.70Crores, Const. of 60Mtr. & 75 Mtr. Road
20.11.2011 Work completed
except un-
acquired /
litigation area
200Mtr. yet to be
Acquired
Litigation and
encroachments =
85Mtr. b) A/C Rs.856.30Lacs, Const. of 60Mtr. Road recently acquired road.
29.03.2013 Work completed
c) A/C Rs.5.30Crores, Const. of 2 Nos. bridges / culvert
16.04.2013 Work completed
-
24
Tenders are being invited___________ G. Total = 12.88K.m.
17. Construction of Govt. College of
Commerce Balance Sector 51,
Gurgaon.
Rs.2958.00Lacs / Rs.2723.00Lacs
4003.30
CA.24523-27
Dt.17.05.2013
Education
Deptt. =
3450.50Lacs
HUDA =
522.80Lacs
1800.00 15.12.2013 2209.13 31.07.2015 -- The status of Commerce College in Sector-51 Gurgaon is as under.
Main Building: - Structure of main building (Basement + Ground + 4 Floors)
completed up to plaster. Flooring completed of
02 Nos. floors i.e. 3rd
& 4th floor, outer face
plaster 50% completed.
Boys Hostel: - Structure (Ground + 3 Floors) completed up to plaster work.
Girls Hostel: - Structure (Ground + 3 Floors) completed up to plaster work.
Auditorium: - Foundation work (RCC) completed. Roof slab of Balcony, Canteen and
Stage portion laid & columns of double height
roof completed and plaster works in Canteen area
completed. Auditorium roof laid.
Staff Quarters: - 5 Nos. Staff Quarters roof laid, 100% brick work completed. Principal residence
roof laid.
Boundary Wall: - 75% Boundary wall completed.
Superintending Engineer,
HUDA Circle I, Gurgaon.
-
25
PERFORMA P-48A
STATUS OF MAJOR DEVELOPMENT WORKS HAVING BUDGET PROVISION OF RS.1.00 CRORE AND ABOVE
(WHICH ARE LIKELY TO BE STARTED IN THE YEAR 2014-15 AND TO BE COMPLETED IN SUBSEQUENT YEAR(S) HUDA CIRCLE-I, GURGAON
Sr.
No.
Name of Work Estimated
Cost /App. No.
& Dt.
(Rs. in Lacs)
Budget for
the year
2014 -15
(Rs. in Lacs)
Likely date/
date of start
Upto date
Expenditure
(01/2015)
(Rs. in Lacs)
Likely date of
completion
Action Plan Remarks.
1 2 3 4 6 5 7 8 9
HUDA DIVISION No. II
1. Const. of approaches of ROB on Delhi Rewari Railway line.
A/C Rs.63.20Crores.
Restricted Amt. Rs.71.24Crores
(Original Time limit 15 Months from
18.02.2014 to 17.05.2015)
7731.00
CA 39568-71
Dt.07.10.2013
3500.00 18.02.2014 4173.84 30.05.2015 -- a) Physical Status 60% work completed at site & as detail under: - Activity DNIT Qty Progress Balance
Casting of Piles 522 Nos. 522 Nos. 0 No.
Casting of Pile cap 58 Nos. 57 Nos. 1 Nos.
Casting of Piers 250 Lifts 220 Lifts 30 Lifts
Casting of Pier caps
58 Nos. 40 Nos. 18 Nos.
Casting of desk
slabs
54 Nos. 13 Nos. 41 Nos.
Wearing coat on stilted portion
54 Nos. 0 No. 54 No.
Fixing of
expansion joint
54 Nos. 0 No. 54 No.
Casting of RE wall panels
10000 Sqm.
9200 Sqm. 800 Sqm.
Erection of RE
wall panels with earth work
10000
Sqm.
5500 Sqm. 4500
Sqm.
Casting of Friction
slab
2000 Rm 0 Rm 2000
Rm
Casting of crash barriers / railings
3000 Rm 68 Rm 2932 Rm
2. Const. of Railway portion of ROB on Delhi Reweri Railway line.
6391.00
CA 13629
Dt.18.03.2013
3195.00 -- -- 02 Years after
release of funds -- a) Physical Status
Rs.31.96Crores i.e. 50% amount released & deposited to Railway Deptt. by the XEN-II vide his office memo
No. 17757 dated 11.09.2013 for inviting tenders in
C.E. of Railway.
Tender of RUB Rs.5.50Crores is under allotment process by the Railway Deptt.
The consent for RUB sump provision and its maintenance to be conveyed by HUDA to Railway
Department, same under approval.
-
26
Sr.
No.
Name of Work Estimated
Cost /App. No.
& Dt.
(Rs. in Lacs)
Budget for
the year
2014 -15
(Rs. in Lacs)
Likely date/
date of start
Upto date
Expenditure
(01/2015)
(Rs. in Lacs)
Likely date of
completion
Action Plan Remarks.
HUDA DIVISION No. III
3. Designing constructing testing commissioning operation and
maintenance for 5 years after 12
months defect liability period of second
water works comprising of Raw Water
pumping Machinery 22 MGD
Automated Water Treatment plant clear
water tank clear water pumping
machinery Pre and post chlorination
lowering of sub soil water 1000mm
diameter MS rising main for clear
water pumps up to Gurgaon water
supply canal near water works
transformer SCADA and all other
works contingent thereto complete in
all respect on Turnkey basis for HUDA
at village Chandu Budhera District
Gurgaon Haryana.(3rd
unit)
Rs.3000.00Lacs / Rs.2668.25Lacs
3830.00
CA.11802-05
Dt.11.03.13
1500.00 15.04.2013 2575.56 28.02.2015 a) Clarifloculator Complete in all respect except tiles on walkway.
b) Rapid Sand Filler Both side of Raw filter completed.
c) Annexy Building Completed & finishing work is in progress.
d) Chemical House Completed and alum tanks are being
constructed.
e) Clear water reservoir 1 No. UGT completed.
f) Machinery being installed. Work is expected to be completed by 28.02.2015.
4. Augmentation of master water supply scheme (Zone-I), U/E, Gurgaon.
Providing, stringing out, jointing,
cutting and testing of DI pipes (K9) of
200mm to 1200mm i/d sizes,
providing and fixing of sluice valves,
zero velocity valve, scour valve,
double action air valve and
construction of sluice valve haudies
and all other works contingent
thereto." (including A/Mtc. defect
liability period for 3 years).
Rs.852.00Lacs / Rs.948.65Lacs
2649.00
CA.11807-10
Dt.11.03.13
800.00 02.12.2013 1100.06 31.03.2015 Total scope of work
D.I. Pipe =
20.54Km.
Work allotted to M/s Tirupati Cement Product.
9.45Km. pipe laid and work is in progress.
Permission for trenchless crossing of Railway line
is under approval and Nos. of house has come up
adjoining to alignment.
-
27
Sr.
No.
Name of Work Estimated
Cost /App. No.
& Dt.
(Rs. in Lacs)
Budget for
the year
2014 -15
(Rs. in Lacs)
Likely date/
date of start
Upto date
Expenditure
(01/2015)
(Rs. in Lacs)
Likely date of
completion
Action Plan Remarks.
5. Laying of water supply line for new sectors i.e. 58-115
49805.00
CA No. 2655
Dt.19.01.10
7000.00
18296.10
Total scope of work D.I. pipe = 147.15 KM
MS Pipe= 48.74 KM
a) Providing master water supply scheme(distribution mains) for new
Sector-58 to 115 (Zone IV to VIII),
U/E, Gurgaon. Providing, stringing
out, jointing, cutting and testing of
1600mm i/d, 1500mm i/d & 1400mm
i/d M.S. pipe, providing and laying of
sluice valves, construction of sluice
valve haudies and all other works
contingent thereto. (including A/Mtc.
3 years)
Rs.176.10Crores / Rs.144.40Crores
15.12.2012 30.06.2015 Length as per
Agreement
32.21Km.
Worthy Chief Administrator, HUDA PKL had
granted time extension to original agency M/s
SaiSudhir Infrastructures Pvt. Ltd. upto
31.12.2014 for completion of work and latest
progress is as under: -
1600mm & 1500mm i/d MS pipe received =
28000 Mtr.
1600mm & 1500mm i/d MS pipe laid = 20000
Mtr.
b) Providing master water supply scheme for new sector 58 - 115 (distribution
mains) for (Zone-IV to VIII),
Gurgaon. "Providing, stringing out,
jointing, cutting and testing of DI
pipes (K9) of 200mm to 1200mm i/d
sizes and 1200mm MS pipe, providing
and fixing of sluice valves, zero
velocity valve, scour valve, double
action air valve and construction of
sluice valve haudies and all other
works contingent thereto." (including
A/Mtc. for 3 years).
Rs.76.10Crores / Rs.79.78Crores
01.04.2013 30.06.2015 72.925Km. pipe
of various sizes
from 200mm i/d
to 1200mm i/d
46.00Km pipe received at site.
24.00Km pipe laid at site & work is in
progress.
(80% work completed)
Reason of delay: -
Non finalization of slot. Slot finalized recently. Number of hurdles due to
construction stay.
Site adjacent to SWD work & execution is delayed due to heaps of earth of master
SWD.
c) Providing master water supply scheme for new sector 58 - 115 (distribution
mains) for (Zone-IV to VIII),
Gurgaon. "Prov., stringing out,
jointing, cutting and testing 1600mm
&1500mm i/d MS pipe, providing and
29.08.2014 28.08.2015 Total length
13.80Km.
Work recently allotted to M/s Tirupati Cement
Products vide XEN-III memo No. 24160-68
dated 29.08.2014.
Pipe received = 6300 Mtr.
Laid = 1230 Mtr.
-
28
fixing of sluice valves, construction of
sluice valve haudies and all other
works contingent thereto." (including
A/Mtc. for 3 years)
Rs.7630.00Lacs/Rs.7176.84Lacs
Sr.
No.
Name of Work Estimated
Cost /App. No.
& Dt.
(Rs. in Lacs)
Budget for
the year
2014 -15
(Rs. in Lacs)
Likely date/
date of start
Upto date
Expenditure
(01/2015)
(Rs. in Lacs)
Likely date of
completion
Action Plan Remarks.
HUDA DIVISION No. V
6. Internal development of Sector-57
Part-I & II, Gurgaon.
Work allotted = Rs.4590.00Lacs
Work allotted = Rs.5.42Crores
4960.00
CA 27427
Dt.01.08.2007
500.00 15.07.2007
15.07.2014
3753.78 --
31.03.2015
Work rescind &
completed balance
work re-allotted
amounting to
Rs.5.42Crores
Work started & in
progress as per
detail given.
Detail of works: - 1 Road in terms of
3.66Km complete upto
WMM = 5.55Km. Total Road length as per
DNIT = 6.05Km. 2 Sewer line laid
= 2.70Km. Total length of sewer line
as per DNIT = 3.05Km. 3 SWD pipe laid
= 1.15Km. SWD Drain = 2.65Km.
Total length of SWD pipe
line & drain as per DNIT
2.65 + 3.00 = 5.65Km. (SWD Pipe + SWD Drain)
4 Water Supply line laid = 1.25Km.
Kerbs & Channels
= 2.5Km.
Supply of DI pipe in
progress.
Total Water supply line
length as per DNIT
= 4.00Km.
Bottleneck: -
All services such as roads, sewer SWD & water
supply affected due to stay recently awarded by
court and existing jhuggi and encroachments,
approximate length effected due to above
bottlenecks 0.85Km.
Note: -
1. The black top of 6.05Km involves an expenditure of 2.94 Crores which shall be taken
up after the completion of 6.05Km. WMM in
one go.
2. The water supply pipe line has been dispatch from Kolkata and is expected to be received in
3 to 4 Days. (Appx. Rs.75.00Lacs)
Superintending Engineer,
-
29
HUDA Circle I, Gurgaon. PERFORMA P-47A
STATUS OF MAJOR DEVELOPMENT WORKS HAVING BUDGET PROVISION OF RS. 1.00 CRORE AND ABOVE
(WHICH ARE LIKELY TO BE COMPLETED DURING THE YEAR 2014-15) (UPTO 01/2015)
HUDA CIRCLE-II, GURGAON
Sr.
No.
Name of work. Estimate / appd.
No. & Date. cost
(Rs in lacs)
Budget for
the year
2014-15 cost
(Rs in lacs)
Date of Start Upto date
expdt upto
01/2015
(Rs. In
lacs)
Likely date
of
Completion
Action Plan Remarks
1 2 3 4 5 6 7 8 9
Div. No. I, GGN
1 Construction of Southern
Periphery Master Roads from
Sohna Road to NH-8 Gurgaon.
2295.31
CA No 5976-80
Dt. 10.02.2011
300.00 20.09.10 for 0.66 Km
(2nd
lane)
1710.23 Completed
in clear area
and balance
with in 2
months
after
clearance of
site.
Road two lane of 12.50 Mtr
each = 5.28 km
Completed = 5.03 K.M.
Balance portion 150mtr is under stay bearing
CWP No. 2367/2009 (Sh. Rambir Singh Vs.
state of Haryana.
The application for vacation of stay was
listed in Honble High Court on 20.09.2013
for which next date for hearing is on
12.02.2015.
In this case learned Judge Sh. Surya
Kant has forwarded instruction during hearing
05.05.2014 that It appears prima-facie that
the residential house, which is the only social
shelter for petitioners and their family, cannot
be allowed to be demolished to facilitate the
private-builders unless the petitioners are
suitably rehabilitated by allotting them plots
along with residential house of A Class
construction on the equivalent area.
Let learned state counsel shall have
instructions whether the private-builders are
willing to share the responsibility
30.11.13 for 0.66 km
(2nd
lane)
01.5.11 for 1.991km
(1st lane)
22.07.11 for 1.991km
(2nd
lane)
19.09.11 for 1.495km
(1st lane)
16.09.13 for 1.495km
(2nd
lane)
04.06.13 for 1.305
(Two lane)
-
30
Sr.
No.
Name of work. Estimate / appd.
No. & Date. cost
(Rs in lacs)
Budget for
the year
2014-15 cost
(Rs in lacs)
Date of Start Upto date
expdt upto
01/2015
(Rs. In
lacs)
Likely date
of
Completion
Action Plan Remarks
1 2 3 4 5 6 7 8 9
proportionately for the said purpose?
100 mtr under existing structure coming into
alignment at entrance near Sohna Chowk.
2 Up-gradation of 60mtr wide
master road from NH-8 to Sec-
55/56, Gurgaon (Joint venture
of HUDA & DLF )
DLF Share = 42852.00 lacs
HUDA Share= 16678.00 lacs
(Joint venture of
HUDA & DLF)
Revised
Amt = 59500.00
3500.00 23.05.2012 4830.74 31.03.2016 Shifting of utilities. Shifting of services is in progress at site.
Under Pass = 6 Nos. 5 Nos. under construction. The right turn of underpass at Shankar Chowk open up for trial
run of traffic.
The work for shifting of 66 KV line at under pass 2
nd U-turn is completed, but work is held
up due to shifting storm water box drain.
-
31
Sr.
No.
Name of work. Estimate / appd.
No. & Date. cost
(Rs in lacs)
Budget for
the year
2014-15 cost
(Rs in lacs)
Date of Start Upto date
expdt upto
01/2015
(Rs. In
lacs)
Likely date
of
Completion
Action Plan Remarks
1 2 3 4 5 6 7 8 9
lacs Flyover = 1 No.
Flyover completed. Finishing work is in
progress & ready to open for traffic except
some road portion is held up opposite Metro
Station.
Bottlenecks
i) 8 Nos cases existing structure coming into
alignment
ii) Left out pockets of land are under
acquisition.
iii) STP, GGN has been requested vide SE-II,
GGN earlier letter No. 14746 dated
19.12.2013 and latest EE-I, HUDA, No. 950
dated 12.06.2014, 1730 dt. 05.11.2014 &
DB-1997 dt. 22.12.2014 to handover the land
occupied by the colonizers.
iv) The EO-II, HUDA, GGN has been requested
vide SE-II, HUDA earlier letter No. 1109
dated 20.01.2014 and latest EE-I, letter No.
975 dated 12.06.2014, 1733 dt. 05.11.2014
& DB-1992 dt. 22.12.2014 to remove the
encroachments.
Road = 8.30 Km
Widening / diversion 5.00 Km.
43% work completed at site.
3. Strengthening of Road and
const. of RCC surface drain
along 60 Mtr. wide Outer
Master Road from Sohna Road
to Village Ghatta, Gurgaon
2475.40 lacs
CA No. 40444
dt. 12.10.2012
1500.00 03.12.2013 825.19 31.05.2015 Road two lane each of 9.70
Mtr = 6.70 KM.
RCC Surface Drain=13.76 km
11.50 Km drain completed.
4.00 Km DBM completed on one carriage way and balance work is in progress.
The Principle approval received from CE-I, HUDA, PKL vide No. 13533 dt 03.10.13 &
-
32
Sr.
No.
Name of work. Estimate / appd.
No. & Date. cost
(Rs in lacs)
Budget for
the year
2014-15 cost
(Rs in lacs)
Date of Start Upto date
expdt upto
01/2015
(Rs. In
lacs)
Likely date
of
Completion
Action Plan Remarks
1 2 3 4 5 6 7 8 9
detailed enhancement case submitted to CE-I,
PKL vide SE-II, memo No. 15817 dt.
16.12.14.
Enhancement case of work returned vide CE-I, HUDA No. 15354 dated 30.12.2014.
EE-IV, Gurgaon
4 Construction of 60mtr wide
development plan road from
IMT Manesar to Pataudi Road,
Gurgaon.
2495 lacs
CA No. 40477
Dt-24.12.10.2012
200.00 30.10.2012 for
2.85km
1307.01 Completed
Road two lane 12.5 mtr each
with central verge=3.40 Km.
i) Work Completed
External SWD is yet to be finalized by
HSIDC. However the shoots, kerbs &
channels has been provided to dispose off
rain water.
25.02.2014 for
0.55km
EE-VI, GURGAON
5 Up-gradation of master road
from HUDA City Centre to
Subhash Chowk, Gurgaon.
3204.00 Lacs
C.A. No. 40467-
71 Dt.12.10.12
400.00 01.02.2013 1940.26 Completed.
Widening 2.50m both side,
strengthening on 10M existing
road, 2.50M footpath both side
and 5.50M wide service road
both side =4.71 Km
Completed for 4.40 K.M & 0.31 KM comes under flyover Subhash Chowk which is not
required.
6 Prov. Master SWD along
Master Road in new Sectors
from Sec-58 to 67, Gurgaon.
6692.00 Lacs
C.A. No.
40452-56 Dt.
12.10.12
500.00 01.02.2013 2212.16 31.01.2015
(In clear
area)
a) RCC pipe =11.43 km
b) RCC box drain =6.50 km a) 11.50 K.M. completed.
b) Completed upto roof slab = 4.50 K.M.
Bottleneck
There are 8 No. Stay. The Hon'ble High Court
has now ordered to reprocess the acquisition..
The Permission on outer road of Sec-58 not
yet accorded by Forest Department.
The I.O.C Pipe line is passing through the
alignment of Master road of Sec-62/63.
Permission / Acquisition of revised alignment
is in progress.
7 Const. of Master SWD in new
Sectors from Sec-81 to 98,
25302.00
C.A. No. 11786 -
4000.00 09.04.2013 12172.80 07.04.2015
(In clear
a) RCC pipe =27.72 Km
b) RCC box drain =18.81km
a) SWD RCC Pipe = 18.09 KM.
b) RCC box = 7.56 KM
-
33
Sr.
No.
Name of work. Estimate / appd.
No. & Date. cost
(Rs in lacs)
Budget for
the year
2014-15 cost
(Rs in lacs)
Date of Start Upto date
expdt upto
01/2015
(Rs. In
lacs)
Likely date
of
Completion
Action Plan Remarks
1 2 3 4 5 6 7 8 9
Gurgaon. 90 dt. 11.03.2013 area)
Balance
within
6 months
after
clearance of
site.
Bottlenecks:-
Under Gas pipe line, encroachments and electric poles.=3.07 K.M.
Village Aabadi/acquisition of land= 6.30 K.M.
8 Remodeling of Kost Nallah
along SPR, Gurgaon.
8752.00
C.A. 11811-15
dt. 11.03.2013
4000.00 07.06.2013
But actual as on
1.10.13 as per decision
of covered drain
accorded vide CA No.
13223 dt. 26.9.13 &
contr. was asked vide
EE-VI No. 12566 dated
01.10.13, reckoned
from 07.10.13.
6268.21 07.04.2015
In clear
portion and
balance in 6
months
after
clearance of
site
RCC box drain = 7.05 Km
RCC box = 5.59 KM.
Bottlenecks:-
There is a stay granted by Honble High Court CWP No. 11 of 2011 Sh. Prem Singh &
Others on 30 mtr. wide green belt along Sec-
62 RD-2850 to 3040.
9 Remodeling of Badshahpur
Nallah from Sohna Road to
NH-8, Gurgaon.
7723.00
C.A. No. 11781-
85 dt. 11.03.2013
3000.00 09.04.2013 2152.21 30.09.2015 RCC box drain = 5.83 Km RCC box = 2.02 K.M.
10 Const. of Flyover at Subhash
Chowk along Road from
Bhaktawar Chowk to Hero
Honda Chowk, Gurgaon.
3460.00
C.A. No. 11826-
30
dt. 11.03.2013
2000.00 15.04.2013 998.71 04.04.2015 Flyover = 1 No. 2 No. Test Pile laid/Tested.
Load Bearing Test on Test Pile = 2 Nos.
52 No. Piles laid.
Routine Test on working Pile = 4 Nos.
8 No. Pile cap Completed.
4 No. Piers Completed.
Abutment = 4 Nos.
-
34
Sr.
No.
Name of work. Estimate / appd.
No. & Date. cost
(Rs in lacs)
Budget for
the year
2014-15 cost
(Rs in lacs)
Date of Start Upto date
expdt upto
01/2015
(Rs. In
lacs)
Likely date
of
Completion
Action Plan Remarks
1 2 3 4 5 6 7 8 9
Pier Cap = 4 Nos.
Abutment Cap = 4 Nos
2 x1.50 Deck Slab completed, 1 x 0.5 Deck
slab completed & balance is in progress.
Slope towards Hero Honda completed upto
sub grade level by providing RE panel etc
Slip Road upto DBM = 0.70 K.M.
Retaining Wall = 4600 Sqm casted, 2100
sqm erected.
800 M RCC Carrier Drain
Crush Barrier casted = 50M
(Total 55% work completed).
Bottlenecks:-
The progress of work is hampered due to non
shifting of 11KVA Independent Feeder of
various colonizer & STP, Sec-47 Etc. exists
on road dividing Sec-38/47. The matter has
been taken up with the various colonizers as
well as. Underground cable has been got laid
at the cost of colonizer lowering /removing of
HT independent feeder line.
The permission for cutting of trees was
granted by the Deputy Conservator of Forest
vide No. 2984 Dt. 06.12.2013. The matter was
taken up and the deforestation to take place.
EE-HUDA, REWARI.
-
35
Sr.
No.
Name of work. Estimate / appd.
No. & Date. cost
(Rs in lacs)
Budget for
the year
2014-15 cost
(Rs in lacs)
Date of Start Upto date
expdt upto
01/2015
(Rs. In
lacs)
Likely date
of
Completion
Action Plan Remarks
1 2 3 4 5 6 7 8 9
11 Const. of sector dividing road
single carriage way between
Sec-18/24, U/E, Dharuhera.
40987-90 dt.
25.10.13
Const. of sector dividing road single carriage way between
Sec-23/24, U/E, Dharuhera.
40997-11000 dt.
25.10.13
Const. of sector dividing road single carriage way between
Sec-1B/1 & 1 B & 2 B, U/E,
Dharuhera.
40959-62 dt.
25.10.13 200.00 01.06.2014 592.95 31.03.2015
Road 45mtr. wide ( single
carriage way) = 4.70 km. Work completed for 3.20 KM and balance in
progress
Const. of sector dividing road single carriage way between
Sec-22/23, U/E, Dharuhera.
40992-95 dt.
25.10.13
Const. of sector dividing road single carriage way between
Sec-5A/5B & 5, Dharuhera.
40982-85 dt.
25.10.13
12 Roads in Sec-6 & 7 Rewari 998.93
CA No. 17619 dt.
14.7.2014
400.00 Lacs -- -- -- Road = 9.50 KM Work allotted to contractual agency. The
demarcation plan of Sec-6&7, Rewari yet to
be finalized by DTP, Rewari / EO, HUDA,
Rewari.
Executive Engineer, HUDA, Division Rewari
has requested to DTP Rewari & Estate Officer
Rewari vide No. 10456 dated 02.12.2014,
10681-86 dt. 08.12.2014, 10960-64 dt.
17.12.2014, SE-II, HUDA, Gurgaon No.
15209 dated 04.12.2014 and SE-II, HUDA,
GGN endst. No. 15992 dt. 22.12.2014.
-
36
(A. K. Maken)
Superintending Engineer,
HUDA, Circle-II, Gurgaon
-
37
PERFORMA P-48A
STATUS OF MAJOR DEVELOPMENT WORKS HAVING BUDGET PROVISION OF RS. 1.00 CRORE AND ABOVE
(WHICH ARE LIKELY TO BE STARTED DURING THE YEAR 2014-15) (UPTO 01/2015) HUDA CIRCLE-II, GURGAON
Sr.
No.
Name of work. Estimate cost (Rs in
lacs)/ appd. No. &
Date.
Budget for
the year
2014-15
likely date /
date of start.
Upto date
expdt. upto
01/2015
Likely date of
completion
Action Plan Remarks
1 2 3 4 5 6 7 8 9
Div. No. IV, Gurgaon.
1 Master SWD Sec-99 to 115,
Gurgaon.
16498.00
CA No. 19709 dt.
5.8.2014
500.00 24.12.2014 0.20 23.06.2016 RCC box drain = 46.26 KM Work allotted recently.
Structural design & drawing under submission.
2. Const. of 60Mtr & 75 Mtr. Wide
road From IMT Manesar to
Pataudi Road (Service Road),
Gurgaon
1167.00 Lacs
200.00 -- -- -- The estimate is under resubmission with Executive Engineer, HUDA, Div. No. IV,
Gurgaon.
3. Const. of dividing road Sector-
9B & 37C, Gurgaon
807.00 lacs
CA No. 21897
dt. 20.08.2014
300.00 09.09.2014 93.74 08.03.2015 Road in two lane of 12.50 M &
surface drain = 1.70 Km 80% earth work completed.
15% GSB completed.
Now work is held up due to court case.
4. Const. of dividing road Sector-
37C & 37D, Gurgaon
855.77 lacs
CA No. 17210-13
Dt. 10.07.2014
500.00 21.08.2014 69.89 20.02.2015 Road in two lane 12.50M each
and surface drain = 1.47 Km 35% earth work completed.
20% GSB completed.
20% WMM completed.
DIV. NO. VI, Gurgaon.
5 Const. of balance Master Road
dividing Sector 50/57, Gurgaon.
155.45
C. A. No.
1352 dt 14.01.14
100.00 11.04.2014 95.04 Work
completed
7.50mtr wide road both side,
central verge & footpath = 0.405
Km
Work Completed.
(A. K. Maken)
Superintending Engineer,
HUDA, Circle-II, Gurgaon
-
38
P-47A
STATUS OF MAJOR DEVELOPMENT WORKS HAVING BUDGET PROVISION OF RS. 1.00 CRORE AND ABOVE (WHICH ARE LIKELY TO BE
COMPLETED IN DURING THE YEAR 2014-2015)
HUDA CIRCLE, HISAR UPTO 01/2015 Sr. No.
Name of Work
Estimated Cost
(Rs. In
Lacs) App. No. &
Date
Budget for the year 2014
2015 (Rs. In Lacs)
Date of start
Upto date Exp.
(Rs. In
Lacs)
Likely date of completion Action Plan
Remarks
Original
Revised
1. Construction of 20 MLD capacity MPS
& 10 MLD capacity STP based on SBR process at Jind. (including five years
maintenance)
(Phase - I)
1382.00 32072-76
Dt.
5.10.2011
300.00 01.11.12 1118.34 30.06.13 30.09.14 31.12.14
Work completed and functional (Electric connection released on 26.12.2014).
2. Construction of Sports Complex in
sector-9, Jind
1205.00 11855-58
11.03.2013
200.00 01.09.13 609.12
31.03.15 Construction of Various courts and Athletic track:- Construction of Volleyball court, Lawn
Tennis Court, Basket Ball Court, Handball Court, Kho-Kho Court, Kabbadi Court, Through Ball Court Construction of athletic track
Work allotted vide Executive Engineer, HUDA Division No.-I, Hisar letter No. 13372 dated
14.08.2013 and the progress is as under :- Athletic Track = 98% completed. Lawn Tennis Courts (2 No) =
98% completed. Basket Ball Courts (2 No) = 98%
completed.
Volley Ball Courts (2 No) = 98% completed.
Kabbadi Courts (2 No) = 98% completed.
Hand Ball Courts (2 No) = 98% completed.
Throw Ball Court (1 No) = 98% completed.
-
39
Kho-kho Court (2 Nos) = 98%
work completed Overall 98% work completed and in
progress.
Construction of athletic pavilion :- Work allotted E.E.-I, HUDA Hisar letter No. 3060 dated 19.2.2014
The work for construction of
basement completed and further work is in progress. Overall 35% work completed.
Completion of work Construction of Road & parking Work allotted on 19.06.2014.
70% work completed and in progress.
Providing Water Supply, Sewerage & SWD
DNIT approved on 11.07.2014. Tender opened on 14.08.2014.
Work allotted on 13.11.2014 and yet to be started.
HUDA DIVN. NO. II, HISAR
1. Providing internal
water supply scheme sec 11 Fatehabad
392.12 38525-29
dt 18.10.12
200.00 01.8.2014 8.8.2014
58.28 8.8.14 30.11.14 30.04.15
* Excavation of earth work * Laying of pipe lines
Work allotted on 8.8.2014. Pipe arranged.
Work was held up due to agitation of the farmers whose lands has been acquired. Work has been started in January - 2015. 4.50 KM W/S Line laid.
2.
Providing
internal sewerage scheme Sec 11 Fatehabad
274.63
40002-05 dt 10.10.13
150.00 23.12.13 105.34 22.06.14 26.06.14
15.04.15
* Excavation of earth work and
preparation of bed. * Laying of pipe lines and construction of manholes.
90% work completed and in
progress. Reason for delay Work was held up due to agitation of the farmers whose lands has
been acquired. Work restarted recently.
3.
Development of roads in residential area across railway line MT Bhattu.
339.00 30968-71
dt 08.07.13
150.00
13.01.14 257.61 12.07.14 31.10.14 * Earth work and preparation of sub grade. * Providing and laying of GSB * Providing and laying of WMM * Providing and laying of BM&PC * Providing and fixing of K&C
Work completed.
-
40
4. Development
of Road and parking in Auto market
MT Bhattu
360.00
30952-55 Dt 08.07.13
150.00
4.10.13 320.13 03.07.14 10.6.2014 *Providing and laying of BM&PC
* Construction of pavements.
Work completed on 10.6.2014.
PERFORMA P-48A
-
41
STATUS OF MAJOR DEVELOPMENT WORKS HAVING BUDGET PROVISION OF RS. 1.00 CRORE AND ABOVE (WHICH ARE LIKELY TO BE STARTED IN THE YEAR 2014 2015 AND TO BE COMPLETED IN SUBSEQUENT YEAR(S)
HUDA CIRCLE, HISAR UPTO : 01/2015 Sr. No.
Name of Work
Estimated Cost
(Rs.In Lacs)
App. No.&
Date
Budget for the year
201415 (Rs.In
Lacs)
Likely date/
date of start
Upto date Exp. (Rs. In Lacs)
Likely date of
completion
Action Plan
Remarks
1 Providing external
SWD scheme in sector-1,3,4,5,23,
24&MGA, Hisar
1352.45
3465.69 25.01.2012
40.00 10.12.12 541.68 10.12.13
(Work RCC pipe sewer
only) 31.12.15
(For whole work)
RCC Pipe Sewer From sector to
Disposal Work :-
Work completed.
Construction of Disposal & Pumping Machinery
0.5 Acre land is to be got transferred from GLF. The case for which under process with Administrator Hisar/LAO, Hisar (Ref. E.E.-I, No. 7617-20 dated 13.5.2013). The case for transfer of the land stand submitted to CTP HUDA, Pkl. Vide Administrator, HUDA Hisar letter No. 12387 dated 1.10.2013. Case
referred to Director General, Animal Husbandry and Dairying Department, Haryana vide CA, HUDA, Panchkula D.O. reference No. 16143
dated 19.11.2013. Reminder to C.A. HUDA Panchkula (T.P. Wing) vide Admn. HUDA Hisar Letter No. 11029 Dt. 21.08.2014.
Construction of Carrier Channel The work will be taken in Hand after transfer of
land for construction of disposal. and permission of concerned department which has already been applied to forest department vide EE-I, HUDA, Hisar letter No. 9736 dt. 19.06.2013 and NHAI vide EE-I letter No. 10268 dated 28.06.2013 and resubmitted after
doing the needful vide EE-I, No. 18600-03 dated 28.10.2013
2.
Providing internal water supply
scheme in sector-7, Safidon
284.02 C.A. No.
44711-14 Dt. 10.12.13
100.00 - Single tender received, to be recalled.
3. Development of roads in sector-8,
1873.00 CA No.
400.00 -
-
42
Safidon 39636-39
Dt. 02.10.13
Single tender received, to be recalled.
4. Providing internal water supply scheme in sector-8,
Safidon
500.45 CA No.
2216-19
Dt. 22.01.14
120.00 - Single tender received, to be recalled.
5. Providing internal sewerage scheme in sector-8, Safidon
259.07 CA No. 44119
Dt. 02.12.13
100.00 - Single tender received, to be recalled.
6. Providing internal SWD scheme in sector-8, Safidon
372.16 CA No.
1235-38
Dt. 13.01.14
150.00 - Single tender received, to be recalled.
7. Development of roads in sector-9,
Safidon
997.00 Revised to
Rs. 1288.46 Lacs
(U/A)
300.00 - The estimate has been revised amounting to Rs. 1250.20 Lacs as per observations of PWD B&R
Department and under process.
8. Providing internal water supply scheme in sector-9, Safidon
289.26 CA No. 44114
Dt. 02.12.13
100.00 - Single tender received, to be recalled.
HUDA DIVISION NO. II, HISAR
1. Providing external
water supply scheme in sector-
19P, 20 & 21 Sirsa.
2214.00
40462
dt. 12.10.2012
600.00 15.10.13 250.75
15.04.15
31.10.15
Time = 18 months
Action plan as per execution schedule given by the agency on 05.06.2014.
a) Work Upto 31.07.2014. Preparation and approval of hydraulic and structural design
b) Work Upto 31.12.2014. (i) S & S tank:- 50% Excavation work,
Work allotted on 10.10.2013. Hydraulic design
approved structural design approved.
S&S Tank:- 80% work of excavation of earth work
com