Profiling Working Group January xx, 20051 PWG Update Report By Ernie Podraza of Reliant Energy ERCOT...

14
January xx, 2005 1 Profiling Working Group Profiling Working Group PWG Update Report By Ernie Podraza of Reliant Energy ERCOT PWG Chair for RMS Meeting January ??, 2006

Transcript of Profiling Working Group January xx, 20051 PWG Update Report By Ernie Podraza of Reliant Energy ERCOT...

Page 1: Profiling Working Group January xx, 20051 PWG Update Report By Ernie Podraza of Reliant Energy ERCOT PWG Chair for RMS Meeting January ??, 2006.

January xx, 20051

Profiling Working GroupProfiling Working Group

PWG Update Report

By

Ernie Podrazaof Reliant Energy

ERCOT PWG Chair

for

RMS Meeting

January ??, 2006

Page 2: Profiling Working Group January xx, 20051 PWG Update Report By Ernie Podraza of Reliant Energy ERCOT PWG Chair for RMS Meeting January ??, 2006.

January xx, 20052

Profiling Working GroupProfiling Working Group

2005 Goals

1. Evaluate Profile ID assignment responsibilities – June2. Annual Validation 2005 – make changes and complete – December3. AV 2006 – review of 2005 changes per long term –

Business (June), cut point (Dec.)4. Evaluate Lagged Dynamics – Dec.5. Bring Load Profiling Guides current – Dec.6. Processing new profile requests – Oil & Gas, Convenience Store – Dec.7. Collaboration with UFE TF – Dec.8. Writing PRRs as required – Dec.9. LRS sample selection round two – Dec.10. IDR Analysis – 2 issues left – Dec.11. Agreement between decision tree language and LPG – Dec.

Page 3: Profiling Working Group January xx, 20051 PWG Update Report By Ernie Podraza of Reliant Energy ERCOT PWG Chair for RMS Meeting January ??, 2006.

January xx, 20053

Profiling Working GroupProfiling Working Group

1. Evaluate Profile ID assignment responsibilities – June Status – pending

a) Two full day workshops (4 million est. total change & 1 million

partial)Several conference calls

b) Oct. 14, 2005 conference call achieved consensus on option 2c) Nov. 17, 2005 PWG to reviewed option 2d) Dec. 15, 2005 PWG to try to reach consensus on option 2 (partial)

2005 Goals

Page 4: Profiling Working Group January xx, 20051 PWG Update Report By Ernie Podraza of Reliant Energy ERCOT PWG Chair for RMS Meeting January ??, 2006.

January xx, 20054

Profiling Working GroupProfiling Working Group

2. Annual Validation 2005 – make changes and complete – DecemberStatus – Complete

a) TDSPs and ERCOT instituted several algorithm changes per

2005 planb) Decision Tree updatedc) TDSPs and ERCOT completed all transactionsd) RMS suspended Residential Transactions per ERCOT

Residential Analysise) ERCOT conducted a Residential Surveyf) October 29, 2005 PWG recommends the flow of residential

transactionsg) November 7, 2005 RMS recommends partial flow of residential

transactionsh) December 1, 2005 TAC approved RMS recommendation

Italics are unplanned

2005 Goals

Page 5: Profiling Working Group January xx, 20051 PWG Update Report By Ernie Podraza of Reliant Energy ERCOT PWG Chair for RMS Meeting January ??, 2006.

January xx, 20055

Profiling Working GroupProfiling Working Group

3. AV 2006 – review of 2005 changes per long term – Business (June), cut point (Dec.)

Status – pending

a) PWG has consensus on four changes for 2006b) PWG to reviewed specifics on the four decision tree changes for 2006 in

Decemberc) Possibility of ERCOT having partial responsibility for profile id

assignmentd) Possibility of new residential profile id assignment algorithm

Italics are unplanned

2005 Goals

Page 6: Profiling Working Group January xx, 20051 PWG Update Report By Ernie Podraza of Reliant Energy ERCOT PWG Chair for RMS Meeting January ??, 2006.

January xx, 20056

Profiling Working GroupProfiling Working Group

4. Evaluate Lagged Dynamics – Dec.Status – on schedule

Have had several discussions to educate and discuss possibility

2005 Goals

Page 7: Profiling Working Group January xx, 20051 PWG Update Report By Ernie Podraza of Reliant Energy ERCOT PWG Chair for RMS Meeting January ??, 2006.

January xx, 20057

Profiling Working GroupProfiling Working Group

5. Bring Load Profiling Guides current – Dec.Status – on going

a) LPGRR005 Remove 1000 kW references approved.

b) LPGRR006 Retail Market Guide Reference - withdrawnc) LPGRR007 IDR Requirement Changes pending approval of

RMGRR031d) LPGRR008 Profile ID Assignment Effective Date approved by

RMS 11/9d) Additional drafts being written by PWG sub-teams

2005 Goals

Page 8: Profiling Working Group January xx, 20051 PWG Update Report By Ernie Podraza of Reliant Energy ERCOT PWG Chair for RMS Meeting January ??, 2006.

January xx, 20058

Profiling Working GroupProfiling Working Group

6. Processing new profile requests – Oil & Gas, Convenience Store – Dec.Status – pending

a) Convenience Store request withdrawnb) Oil & Gas request is in data validation phase of evaluation by ERCOT Staff

2005 Goals

Page 9: Profiling Working Group January xx, 20051 PWG Update Report By Ernie Podraza of Reliant Energy ERCOT PWG Chair for RMS Meeting January ??, 2006.

January xx, 20059

Profiling Working GroupProfiling Working Group

7. Collaboration with UFE TF – Dec.Status – ongoing

a) 2003 UFE report by ERCOT staff issued

b) 2004 UFE report pending ERCOT resource allocationc) COPS has suggested PWG evaluate affects of Hurricane Ritad) COPS has suggested PWG evaluate TDSP meter estimation processes

Italics are unplanned

2005 Goals

Page 10: Profiling Working Group January xx, 20051 PWG Update Report By Ernie Podraza of Reliant Energy ERCOT PWG Chair for RMS Meeting January ??, 2006.

January xx, 200510

Profiling Working GroupProfiling Working Group

8. Writing PRRs as required – Dec.Status – on going

a) PRR488 Weather Responsiveness Determination Eff. 05

b) PRR514 Twelve Month Window for Non-IDR Scaling Eff. 05c) PRR536 lower IDR Mandatory Installation Threshold Eff. 05d) PRR544 12-Month Window for Scaling NIDR to IDR Eff 05e) PRR565 Calculation of Losses for Settlement Eff 05f) PRR566 Implementation of IDR Optional Removal Threshold Eff 05g) PRR572 Weather sensitivity classification Eff 05h) PRR617 IDR Optional Removal Eff 05i) To review a draft of Historical Usage Requirement for Opt-In Entitiesj) To review a draft of Transmission language for IDR Optional Removal

2005 Goals

Page 11: Profiling Working Group January xx, 20051 PWG Update Report By Ernie Podraza of Reliant Energy ERCOT PWG Chair for RMS Meeting January ??, 2006.

January xx, 200511

Profiling Working GroupProfiling Working Group

9. LRS sample selection round two – Dec.Status – pending

a) Report on sample evaluation developedb) Data review with TDSPs in processc) 12 months of data for most meters as of October 2005e) Tentative Milestone Targets

03/31/06: Analysis of current profile models complete.04/30/06: Sample Point selection for round 2 complete.06/30/06: Complete profile model building.09/30/06: Stakeholder process completion.02/28/07: 150 day notification completed.

2005 Goals

Page 12: Profiling Working Group January xx, 20051 PWG Update Report By Ernie Podraza of Reliant Energy ERCOT PWG Chair for RMS Meeting January ??, 2006.

January xx, 200512

Profiling Working GroupProfiling Working Group

10. IDR Analysis – 2 issues left – Dec.Status – pending

Needs LRS project data analysis

2005 Goals

Page 13: Profiling Working Group January xx, 20051 PWG Update Report By Ernie Podraza of Reliant Energy ERCOT PWG Chair for RMS Meeting January ??, 2006.

January xx, 200513

Profiling Working GroupProfiling Working Group

11. Agreement between decision tree language and LPG – Dec.Status – pending

LPGRR discussed and extensive draft in process

2005 Goals

Page 14: Profiling Working Group January xx, 20051 PWG Update Report By Ernie Podraza of Reliant Energy ERCOT PWG Chair for RMS Meeting January ??, 2006.

January xx, 200514

Profiling Working GroupProfiling Working Group

2006 Goals

1. LRS sample selection round two2. Existing Profile Evaluation and New Profile Recommendation3. Processing new profile requests – Oil & Gas4. Evaluate Profile ID assignment responsibilities 5. Annual Validation 2006 – make changes and complete

a) Possibility including new residential tool 6. Annual Validation 2007 review for any additional changes7. UFE evaluation of Hurricane Rita and affects of TDSP meter read estimates 8. Evaluate Lagged Dynamics9. IDR Analysis – 2 issues outstanding from original analysis10. Agreement between decision tree language and LPG11. Load Profiling Guides updates12. Writing PRRs as required