1 PRODUCTIVE SAFETY NET PROGRAMME PHASE FOUR (PSNP-4) JOINT REVIEW & IMPLEMENTATION SUPPORT MISSION (JRIS) FEDERAL AIDE MEMOIRE June 2018 I. INTRODUCTION 1. The Government of Ethiopia (GoE) and multi-partner Joint Review & Implementation Support (JRIS) Mission met on June 1, 2018 for the kick off meeting to identify and agree on high-level priorities for the mission. This was followed by the Regional and Federal JRIS Missions starting from June 4-14, 2018. The objectives of the Mission were to assess: (i) the progress in implementing the Annual Plan for Ethiopian Fiscal Year (EFY) 2010; (ii) the extent to which the Program is on track to achieve its outputs following the revised logical framework; (iii) the steps taken towards achieving the Government vision of a scalable safety net system; and (iv) the implementation progress of the Action Plans agreed during the previous mission (Nov-Dec 2017). 2. The Mission has a revised structure 1 and streamlined approach that included discussions at federal, regional, woreda level and with kebele officials and beneficiary households on challenges and areas to focus for effective implementation. The Mission at the Regional level primarily focused on visiting representative PSNP implementing woredas and kebeles and assessed the regional progress and challenges. And the Mission at the federal level focused on the field mission findings and federal level issues. 3. The Mission would like to thank H.E. Ato Tesfaye Mengistie (State Minister (SM) RJOCFSS, MoALR); H.E. Mitiku Kassa (Commissioner - NDRMC), H.E. Ato Misganaw Admassu (SM MoLSA); Ato Berhanu W/Michael (MoALR - FSCD); Ato Tefera Taddesse (MoALR - NRMD); Ato Tadesse Aweke (MoALR - CMLFD), Ato Zena Habte Wold (MoALR); Ato Feleke Jember (MoLSA); Ato Tadesse Bekele, Ato Abera Kassa, Ato Ayderus Hassen, (NDRMC); Ato Degu Lakew (MoFEC - COPCD) for their guidance and recognize the active participation from the experts in the various directorates within the Ministry of Agriculture and Livestock Resource (MoALR), the Ministry of Finance and Economic Cooperation (MoFEC), the Ministry of Labour and Social Affairs (MoLSA), the National Disaster Risk Management Commission (NDRMC), and the representatives from the regions and the development partners. 4. Annex 1 includes the complete list of participants in the Mission. Annex 3 details the progress status of the Nov- Dec 2017 agreed actions. The agreed action plan between the Government and development partners is attached as Annex 4. II. CONTEXT 5. The overall PSNP-4 implementation performance is Moderately Satisfactory. The Mission notes improved financial management in the program. All actions agreed during the November- December 2017 JRIS Missions were completed. The progress on graduation is noted. There is Government commitment to ensure graduation is evidence based. Training has been provided to Regions on the Household Economy Analysis (HEA) and how to use the tool. Agreement reached to apply simplified tools 1 The Mission involved one day Kick off meeting at the federal level, discussion and field visits at the regional level and 3-days workshop at the federal level. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Transcript of PRODUCTIVE SAFETY NET PROGRAMME PHASE FOUR ......2 Ethiopian rural productive Safety net project,...

  • 1

    PRODUCTIVE SAFETY NET PROGRAMME PHASE FOUR (PSNP-4)

    JOINT REVIEW & IMPLEMENTATION SUPPORT MISSION (JRIS)

    FEDERAL AIDE MEMOIRE

    June 2018

    I. INTRODUCTION

    1. The Government of Ethiopia (GoE) and multi-partner Joint Review & Implementation Support (JRIS) Mission met on June 1, 2018 for the kick off meeting to identify and agree on high-level priorities

    for the mission. This was followed by the Regional and Federal JRIS Missions starting from June 4-14,

    2018. The objectives of the Mission were to assess: (i) the progress in implementing the Annual Plan for

    Ethiopian Fiscal Year (EFY) 2010; (ii) the extent to which the Program is on track to achieve its outputs

    following the revised logical framework; (iii) the steps taken towards achieving the Government vision of

    a scalable safety net system; and (iv) the implementation progress of the Action Plans agreed during the

    previous mission (Nov-Dec 2017).

    2. The Mission has a revised structure1 and streamlined approach that included discussions at federal, regional, woreda level and with kebele officials and beneficiary households on challenges and areas to focus

    for effective implementation. The Mission at the Regional level primarily focused on visiting representative

    PSNP implementing woredas and kebeles and assessed the regional progress and challenges. And the

    Mission at the federal level focused on the field mission findings and federal level issues.

    3. The Mission would like to thank H.E. Ato Tesfaye Mengistie (State Minister (SM) – RJOCFSS, MoALR); H.E. Mitiku Kassa (Commissioner - NDRMC), H.E. Ato Misganaw Admassu (SM – MoLSA);

    Ato Berhanu W/Michael (MoALR - FSCD); Ato Tefera Taddesse (MoALR - NRMD); Ato Tadesse

    Aweke (MoALR - CMLFD), Ato Zena Habte Wold (MoALR); Ato Feleke Jember (MoLSA); Ato Tadesse

    Bekele, Ato Abera Kassa, Ato Ayderus Hassen, (NDRMC); Ato Degu Lakew (MoFEC - COPCD) for their

    guidance and recognize the active participation from the experts in the various directorates within the

    Ministry of Agriculture and Livestock Resource (MoALR), the Ministry of Finance and Economic

    Cooperation (MoFEC), the Ministry of Labour and Social Affairs (MoLSA), the National Disaster Risk

    Management Commission (NDRMC), and the representatives from the regions and the development

    partners.

    4. Annex 1 includes the complete list of participants in the Mission. Annex 3 details the progress status of the Nov- Dec 2017 agreed actions. The agreed action plan between the Government and

    development partners is attached as Annex 4.

    II. CONTEXT

    5. The overall PSNP-4 implementation performance is Moderately Satisfactory. The Mission notes improved financial management in the program. All actions agreed during the November- December

    2017 JRIS Missions were completed. The progress on graduation is noted. There is Government

    commitment to ensure graduation is evidence based. Training has been provided to Regions on the

    Household Economy Analysis (HEA) and how to use the tool. Agreement reached to apply simplified tools

    1 The Mission involved one day Kick off meeting at the federal level, discussion and field visits at the regional level and 3-days workshop at the federal level.

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

  • 2

    to predict the number of graduates in a woreda based on the HEA data. However, the Mission notes that

    performance targets for the timeliness of transfer during the past year has not been met; off farm and

    employment pathways of the livelihoods component are not performing as required and quality of PW some

    subprojects, such as Social and Water Conservation (SWC) & water, are not up to the required level of

    standard mainly in Somali and Afar regions. There continue to be delays in completion of major

    procurements such as the Management Information System (MIS) development and Public Work (PW)

    reviews, establishment of PW mapped data base, PW baseline study, and independent procurement audit

    of EFY 2009 are delayed. There was low utilization of capital budget. In addition, there continue to be

    difficulties with food management with the agreed Commodity Management Unit (CMU) in the NDRMC

    still not fully functional. The overall review of the November-December 2017 Federal JRIS Action Plans

    shows that (i) 51% of the actions are achieved, (ii) 35% are in process/ongoing, (iii) 5% are partially

    achieved and (iv) 9% are not achieved/pending. Moreover, though it was agreed that, GoE shall prepare

    annual work plan and budget and furnish to the association2 not later than May 30th of each year, this

    deadline is not met. The Mission requests the senior leadership of the MoALR and its implementing partners

    to review and address the priority actions in order to improve the program performance and the rating.

    6. Progress towards the PSNP-4 outcomes remains Moderately Satisfactory. The Mission is pleased to note Government leadership in timely development and approval of the National Integrated Food

    & Cash Plan for 2018. The plan was developed a month after the launch of the Humanitarian Disaster

    Resilience Plan (HDRP). In regions that have consolidated operational management structure for PSNP &

    HFA implementation of integrated response is progressing - with genuine efforts seen to implement the

    joint PSNP-HFA operational procedures. The implementation of joint procedures has resulted in agreement

    and use of single transfer modality in each woreda, guided by PSNP transfer modality, one targeting and

    appeals kebele committee, and use of Payroll and Attendance Sheet System (PASS) for both chronic and

    transitory beneficiary households. However, challenges of low capacity, limited admin budget at woreda

    level, and lack of regular updates of the National Integrated Food Cash Plan hampered effective and timely

    implementation. The DPs look forward to GoE’s decision soon on consolidated operational management

    arrangements for scalable rural safety-net. However, the Mission noted that core elements of the program:

    timeliness of transfer; food management, placement of social protection systems and re-targeting in Afar

    and Somali regions are behind the agreed program performance standard.

    III. PRIORITY STRATEGIC ISSUES

    7. The Mission identified that the core elements of the program are not meeting agreed program performance standards. Timeliness of transfers continues fail to meet the required program

    standards. The timeliness and predictability of the transfers are critical to the PSNP’s outcome. Food and

    cash transfers did not meet the performance benchmarks3 agreed for EFY 2010. Compared to EFY 2009,

    in this fiscal year, timeliness of cash transfers has shown improvement but overall cash transfer still fall

    short of meeting set benchmarks (less than 40% of cash transfer meeting the standard). Food timeliness has

    significantly declined. In EFY 2009 around 45% of food transfers were delivered on time but in EFY 2010

    only 17% of food transfers were delivered on time. Reasons for the delays are attributed to several factors

    presented under the review of Output 2 in the next section. However, no systematic analysis was done in

    the past months to inform the reasons behind the delays in transfers to clients and PSNP wage rate has not

    been updated in more than two years, The Mission agreed that it was critical that timeliness of transfers is

    improved on an urgent basis. It was agreed a third-party assessment will be conducted to provide evidence

    on the bottlenecks to timely transfers and recommend solutions to improve timeliness of payments.

    2 Ethiopian rural productive Safety net project, Page 5, Schedule 2, Section 1G,1, August 23, 2017, 3 20 days from completion of public works for cash, and 30 days for food

  • 3

    8. The purchasing power of cash transfers to beneficiaries decreased by over 25 percent since the last wage rate revision. The current PSNP Wage Rate (WR) has not been updated in more than two

    years, being based on the EFY 2008 Wage Rate Study. At the same time, according to the Central Statistical

    Agency (CSA) in the last 12 months the food prices have increased by 19.9 percent (March 2018 compared

    to March 2017). The increase for bread and cereals was 24.9 percent4. Thus, the current PSNP wage rate

    has considerably lost value in real terms and needs to be reviewed and revised to protect purchasing power

    of cash wages/ benefits, maintain the impact of the transfers to PSNP households, and ensure equity with

    respect to the purchasing power of cash benefits recipients compared to food benefits (i.e., wheat)

    recipients. Development partners discussed with the GoE on the proposed PSNP wage rate increase and

    have agreed on the need for an increase in line with inflation to preserve equity with the value of the food

    transfer for implementation in EFY 2011, though still there are concerns around the level of increase and

    regional consultation processes that the GoE would like to take. To ensure the timeliness of the transfer for

    the permanent direct support, the Mission agreed that FSCD should finalize regional consultation processes

    by July 20, 2018 and submit the revised transfer value included in the EFY 2011 annual work plan and

    budget by July 30, 2018.

    9. Continuous weaknesses in food management. The Program has an eight-consecutive qualified Commodity Audit Report. The Action Plan for Food Management was agreed by GoE and DPs in February

    2018. However, there has been limited progress on implementation of the agreed actions. The CMU at

    NDRMC is not operational as intended and clear working arrangements and lines of accountability have

    not been established (details in Commodity Management section). High level leadership attention is

    required to ensure agreed actions in the plan are implemented and stronger collaboration between

    NDRMC/CMLFD/FSCD are realized. The Mission agreed that (i) the action plan will be revised/ updated;

    and (ii) regular updates on the progress will be shared with development partners. The Mission noted that

    immediate significant improvements are required for DPs to continue to support food purchases for the

    program.

    10. Limited progress on Social Protection Systems Strengthening. The progress on system strengthening activities has been slow. The GoE has committed to put in place a program-based MIS and

    procurement of MIS development has not been completed despite being initiated two years ago. There is a

    need to have a PSNP beneficiary household registry that provides information on the socio-economic

    characteristics of the beneficiary households. Program monitoring and reporting system also remain weak.

    The Mission notes greater leadership and investment is required to put in place social protection systems

    including immediate completion of MIS development procurement process. The Mission has agreed that

    data collection for beneficiary household registry will start in EFY 2011. Terms of References (ToRs) for

    data collection have been drafted and GoE is reviewing data collection options.

    11. Providing Effective Safety Net Support to People in Afar and Somali. Evidence from third-party spot checks has shown improvement in program implementation in both regions. Improvements are

    seen in the areas of retargeting in some woredas, use of payroll and commodity management system,

    coordination between PSNP & HFA using joint targeting, PW planning and Grievance Redress Mechanism

    (GRM) structures and there is strong participation of households in PW planning. The Mission agreed that

    continued leadership both at federal and regional level is required for continued prioritization of program

    implementation most importantly in Afar Region. Though the evidence from the first round of spot check

    reports highlight a modest progress in program implementation, there is a need in both regions for

    improvements in retargeting across all woredas, timeliness and predictability of payments, Environment

    4 The overall Consumer Price Index (CPI) increased by 11.8 percent in March 2018 as compared to March 2017.The country level food CPI increased by 15.6 percent in March 2018 as compared to one year ago

  • 4

    Social Management Framework (ESMF) compliance for PW projects and increased capacity at woreda and

    kebele level to ensure improvements in implementation.

    ---------------------------------------------------

    1V. PRIORITY ISSUES FOR PSNP-4 IMPLEMENTATION

    Output 1. Prioritized Instruments and Tools in Place to Support an Effective System for Social

    Protection and Disaster Risk Management

    12. The development of prioritized instruments and tools to support an effective system of social protection and disaster risk management5 has seen continued slow progress. The GoE planned to graduate

    over 200,000 PSNP households in EFY 2010 and there is commitment to evidence-based graduation.

    However, slow progress was observed in implementation of Household Economy Analysis (HEA) though

    trainings have been conducted in some regions. The mission also noted the continued delay in placement

    of social protection systems including MIS and PSNP beneficiary household registry. The Mission noted

    the importance of MoALR and MoLSA high level officials to give to strengthen the social protection

    systems. Moreover, the Mission discussed on the weak monitoring and evaluation system including poor

    data quality, data management and reporting systems. The Mission recommends (i) to apply HEA tool to

    realize evidence based graduation (ii) to finalize the MIS procurement processes including contractual

    agreement and firm placement as soon as possible (iii) initiate procurement of primary data collection for

    the Household (HH) registry in EFY 2011.

    13. The Mission acknowledged the woreda level monitoring and reporting systems assessment conducted in 20 PSNP woredas by an independent consultancy firm. The findings of the study show that

    low quality of monitoring and reporting is due to i) low attention given to monitoring and reporting activities

    at all levels ii) misalignment of data collection tools to the logframe indicators and iii) poor report writing

    knowledge. The findings were validated through a series of regional meetings and discussion. The mission

    is pleased to note GoE agreement to the findings and recommendations of the report. The Mission agreed

    that FSCD (i) will cascade and sensitize regions and woredas on findings of monitoring and reporting

    assessment (ii) will revise the data collection and reporting templates (iii) will prepare the necessary

    guidance note on how to fill the templates and (iv) will timely submit quality semi-annual reports as per the

    agreed logframe indicators.

    14. The Mission noted that the GoE has prepared PIM Addendum as an interim action to address the legal covenant under RPSNP. However, the Mission discussed and underscored the importance to start

    working on a full-fledged revision of the PSNP 4 PIM. To this effect the Mission agreed that the GoE will

    finalize the revised PIM before the November 2018 JRIS Mission.

    Output 2. Appropriate, Timely and Accessible Transfers Received by Male and Female Clients

    15. As of the third quarter of EFY 2010 (July 2017 – March 2018), PSNP-4 has delivered transfers in cash and/or food to 7,997,218 clients (86% PW and 14% PDS) in 349 woredas. Electronic Payment (E-

    payments) have now reached to 110 woredas (Tigray: 18, Amhara: 30, Oromia 26, SNNP: 30 & Somali: 6)

    which is close to 2.4 million beneficiaries. Thus, more than 50% of cash only woredas are using E-Payment.

    Table 1 summarizes the status of payments as reflected in the EFY 2009 Nine Month progress report:

    Table 1: Nine Months PSNP Transfer Performance

    5 The government cancelled the Hydromet pilot and the agreement reached to phase out the seasonal assessments and to move to a drought EWS based on a combination of remote sensing and ground level validation

  • 5

    Resource

    Description

    9 Months

    Plan

    Amount

    Transferred

    to Regions

    Amount

    Transferred

    to Woreda

    Amount Paid

    to clients as per

    the Woreda

    received

    % of paid

    to clients

    as per

    Woreda

    received

    % of paid

    to clients

    as per the

    9 months

    plan

    Cash to PDS

    Clients (ETB) 1,752,891,155 1,752,891,155 1,752,891,155 1,359,877,458 78% 78%

    Cash to PW

    Clients (ETB) 2,760,176,780 3,744,205,265 2,668,268,655 1,896,036,497 71% 69%

    Food to clients

    (MT) 78,871.55 69,104.85 59,280.65 86% 75%

    Cash to extended

    support and

    emergency clients

    (ETB)

    2,429,725,610

    2,010,383,272 2,010,383,272 1,323,828,907 66% 54%

    Food for

    extended support

    clients (MT)

    23,483.94 23,483.94 23,442.64 100% 100%

    Source: GoE Nine months PSNP performance report, June 2018

    16. However, the Mission noted that the target for the timeliness of transfers was not met as per the performance standard6. The table below compares the timeliness of payments between EFY 2009 and

    2010. Cash payments have improved slightly though still significantly below target, but performance on

    food transfers has worsened

    Table 2: Comparison of the EFY 2009 and EFY 2010 transfer performance

    Target EFY 2009 EFY 2010

    Cash (January – March 2018)

    70% for EFY 2009 and

    80% for EFY 2010

    24% 35%

    Food (January – March 2018) 45% 17%

    Cash (July – December 2017)7 37% 42%

    Source: Computed from the GoE annual performance reports

    6 Monthly transfer completed by 20th of next month for cash and 30th of next month for food 7 This is for the first 6 months (July – December 2017) payment to PDS client and PW clients that shifted their transfer scheduled. The performance from January – March 2018 is stated in the first raw of this table.

  • 6

    17. Development Partners and implementers jointly identified the following primary causes that contributed to the delay of transfers (i) social unrest in some regions; (ii) reshuffling of leaders and other

    competing priorities that resulted in providing low attention and support for the transfers; (iii) retargeting

    leading to changes in the list of clients anytime in the year that mismatch with the original data registry

    (PASS); (vi) Delay in allocation of the budget from federal to regions in the first tranche that led to delay

    in transfers to the PDS clients; (v) delay in submission of attendance sheet and payroll processing due to

    delay in PW implementation and verification, this in turn leading to delay in transfers to PW clients; (vi)

    limited liquidity of banks at woreda level and limited cash holding capacity of government and

    Microfinance Institutions (MFI) cashiers; (vii) problem in operationalizing E-payment related to network,

    low MFI capacity, limited capacity of agents, low commission fee, integration with PASS platform, lack of

    strong oversight and follow-up of decision makers (MoFEC and MoALR) from federal level and regional

    Bureau of Finance and Economic Cooperation (BoFEC) and Bureau of Agriculture and Livestock Resource

    (BoALR); (viii) Weak food management system that led to delay in food transfers; (ix) Ineffective

    functionality of committees under the PSNP coordination structures (Food Security Task Forces/Technical

    Committees (FSTFs/TCs)) at Woreda level due to low awareness and accountability; (xi) shortage of

    administration budget and transportation problem to deliver food to remote Woredas.

    18. The Mission agreed (i) to continue implementing the last November/December 2017 JRIS action plan that says (a) regions should complete retargeting before end of July of each year and (b) the cash

    disbursement schedule should be revised such that the first tranche reaches regions end of July to ensure

    timely payment to PDS clients and the rest of the tranches remain as before (October, January and March);

    (ii) MoALR to reemphasize implementation of the “transfer schedule” stated in the Program

    Implementation Manual (PIM) and tighten accountability mechanisms; (iii) NDRMC and MoALR to fully

    operationalize the CMU to address problems in the overall food management; (iv) MoALR to strengthen

    the capacity of Woreda Information Center (WIC)/RIC and WIC/RIC/FIC should prepare consistent and

    accurate reporting; (v) regions to strengthen the capacity of the FSTFs/TCs at the Woreda level; (vi) MoFEC

    to follow up the implementation of MoFEC’s request sent to Commercial Bank of Ethiopia (CBE) to open

    up additional bank branches (in Somali and Afar) and increase cash liquidity; (vii) MoFEC to explore the

    possibility of increasing the cash holding capacity of government and MFI cashiers.

    19. In order to improve the E-Payment implementation problems the mission agreed (i) MoFEC to evaluate and decide scaling-up of off-line technology to woredas/ kebeles with permanent network

    connectivity problem and explore the possibility of involving other E-payment service providers to allow

    0%10%20%30%40%50%60%70%80%

    Cash (July – December 2017)

    Cash (January – March 2018)

    Food (January –March 2018)

    Timeliness of Transfers EFY 2009 & EFY 2010 Comparison

    Target EFY 2010 EFY 2009 EFY 2010

  • 7

    better competition and improved service; (ii) MoFEC to strengthen coordination among E-Payment key

    stakeholders; (iii) MoFEC and BoFECs to ensure that selection of woredas follows and adheres to the set

    selection criteria going forward;

    Output 3. Sustainable Community Assets Built Up and Access to Social Services Enhanced

    20. The Mission noted that PW has created various community assets which have benefited livelihoods. Around 67% of the planned PW subprojects have potential linkage with livelihoods showing that the PW

    & livelihoods linkage guidance note is being implemented. It is also noted that ESMF implementation has

    significantly improved along with the implementation of the identified mitigation measures.

    21. The Mission noted that quality of some subprojects, such as SWC & water, are not up to the required level of standard mainly in Somali and Afar regions due to persisting skill gaps at frontline staff

    and due to limited monitoring and supervision support from federal level.

    22. The Mission also noted that the extended PW monitoring system is not functioning as per the requirement due to poor communication from federal to regions and lack of understanding of the format by

    some regions.

    23. The Mission noted significant progress in ensuring regional bureaus capacity to plan and implement the Gender and Social Development (GSD) and Nutrition related provisions of the program as per the PIM

    requirement. This included Training of Trainer (ToT) and cascading GSD and nutrition training in 80

    UNICEF supported Comprehensive Integrated Nutrition Service (CINUS) woredas and their kebeles. The

    training materials were translated in to Amharic, Oromiffa and Tigrigna languages, and its contextualization

    process to pastoral realities started. Woreda level GSD experts are recruited in Oromia region. In pastoral

    regions, the absence of PSNP GSD and Nutrition mainstreaming training material as well as Behavioural

    Change Communication (BCC) facilitation job aid which are tailored to the pastoral context posed critical

    challenge to advance the implementation of the provisions as per the PIM. The Mission was briefed that

    the adaptation process of the training manuals; both secondary data review as well as primary data collection

    is finalized. The Mission underscored the need to expedite the process so that implementers will be trained

    before the next round of PW commenced.

    24. To support the capacity development effort of PSNP, financial and technical support was mobilized from United Nations International Children's Emergency Fund (UNICEF) and Promoting Basic Services

    (PBS) Program. Resources from PBS 3 budget were secured to train grass root implementers (Health

    Extension Worker (HEWs), DAs, Social Workers (SWs) and teachers) in 50% highland PSNP woredas on

    GSD and Nutrition mainstreaming. The budget needs to be utilised by the end of December 2018. FSCD is

    in discussion with the Policy and Planning Directorate of MoALR on the budget transfer modality. The

    Mission noted given the limited time for budget utilisation MoALR should finalize the budget transfer

    modality as soon as possible and start the TOT trainings at the regional level. In order to further strengthen

    the coordination between MoALR and Ministry of Health (MoH), agreement was reached in the November

    – December 2017 JRIS to sign a Memorandum of Understanding (MoU). The draft MoU was shared with

    the nutrition case team of MoH and needs to be approved by leadership of MoALR & MoH.

    Output 4. Clients’ Livelihood Opportunities Facilitated Through Three Pathways: Crop and

    Livestock, Off-Farm Income Generation, and Employment

    25. During this reporting period (July- March 2018) livelihood activities: wider community consultation, livelihoods technical support, group formation, financial literacy training, saving

    mobilization, and technical trainings mainly concerning on-farm pathway have shown notable progress,

    though there exist notable regional variations. The Mission noted that in this reporting period (i) livelihoods

  • 8

    capacity building budget is fully released to regions and woredas on time and (ii) better availability of

    loanable fund and saving mobilization which in turn resulted in increased average loan size per client

    household in most regions except Oromia. However, the Mission observed challenges related to (i) slow

    progress in off-farm and employment pathways; ii) diminished livelihoods grant transfer value; and iii)

    ESMF in-compliance.

    26. Slow progress in implementation of off-farm and employment pathways is persisting: The Mission noted persistent slow progress in implementing off-farm and employment pathways is due to (i)

    lack of proper institutional ownership and engagement of implementing agencies at all levels. The Mission

    also noted that the government has not fully implemented the November - December 2017 JRIS agreed

    actions related to the off- farm and employment pathways. The mission recommends proper implementation

    of the November - December 2017 JRIS agreed actions should be implemented immediately.

    27. Diminished livelihoods grant transfer value. The livelihoods transfer sub component of the PSNP 4 has an objective to help the very poor households who are often seen as credit averse by providing

    $ 200 or ETB equivalent. For EFY 2010-2012, the program targets people at the bottom 10% of the public

    works beneficiaries. In EFY 2008 a grant amount of ETB 4,000 per household was transferred to

    beneficiaries in the eight pilots woredas where, more than 85% of the beneficiaries chose to work on rearing

    small ruminants and with that amount, beneficiaries have bought 5-6 small ruminants. Though an

    independent assessment did not yet take place to generate concrete evidence regional and field monitoring

    reports have shown that, the grant helped in increasing the income of targeted households. However, due

    to price increase (inflation), beneficiaries who received ETB 4,000 in EFY 2010 were only able to buy 2-3

    small ruminants, which might compromise the level of effect from the intervention. The mission also noted

    that Non-Government Organizations (NGOs) that are currently providing livelihoods grant in same regions

    are transferring the ETB equivalent of $200. Therefore, the Mission recommends that (i) both for the

    program and NGOs grant amount that will be transferred from EFY 2011 will be the equivalent of $200

    per household based on the exchange rate at July 8, of the new fiscal year (ii) ensure NGOs interventions

    apply and adhere to the livelihoods guidance note.

    28. Livelihoods transfer rollout: Livelihoods grant is being piloted in 43 woredas of Amhara, Tigray, SNNPR and Oromia. International Food Policy Research Institute (IFPRI) has been commissioned to do

    an impact evaluation to be able to build the evidence base on the performance of the grant. A Randomized

    Control Trail (RCT) has been proposed by the consulting firm which was by in large accepted as the most

    appropriate methodology for the purpose. During the mission the CSA had already started collecting

    baseline data in 12 woredas of the four regions. The mission noted, however, that the understanding on the

    Impact Evaluation (IE) design and the implication of the RCT was not consistent across regions. The

    mission agreed that (i) the RCT, as it is designed, will be applied, which means that control kebeles will

    not be getting the livelihoods grant or related interventions until the final impact evaluation surveys are

    done by 2020 (ii) the control kebeles will be selected via a public lottery to ensure that there is transparency

    and fairness in the process and (iii) the consultant (IFPRI) will give trainings to woreda and kebele officials

    as soon as possible to minimize risks that may arise from lack of understanding at various stages of the IE

    process.

    29. Inadequate ESMF compliance of livelihoods interventions. The Mission noted that implementation of ESMF in the livelihoods component remains a concern. It also observed that that livelihoods staff have

    low level of ESMF awareness. Similarly, regions indicate that ESMF training is not given to the staff

    working on livelihoods. In addition, the Mission noted, though there are few attempts made to undertake

    preparatory activities to address the November - December 2017 JRIS agreed actions such as regular ESMF

    monitoring and placement of a verification procedure. Out of 3,620 PSNP kebeles targeted to be monitored

    only 354 (10% of the annual target) have conducted ESMF compliance monitoring. Thus, the Mission

    agreed to (i) fully implement the November - December 2017 JRIS agreed action.

  • 9

    Output 5. Effective Management and Operational Processes in Place to Manage the Programme

    Financial Management (FM)

    30. With regard to the FM of the program, five issues were identified in the November - December 2017 JRIS and it is noted that all of the recommended actions have been implemented. The issues raised in

    the previous JRIS were in relation to i) the concern on repetitive budget revisions - a revised budget has

    been communicated to the DPs in the revised annual plan submitted on March 1, 2018. No further revision

    has been made subsequently ii) the systemic weakness in the internal control mechanism of the programme

    – the Channel One Programs Coordinating Directorate (COPCD) reached an agreement with the Inspection

    Directorate of MoFEC to assign one expert from the Inspection Directorate who regularly reviews the

    Ethiopian Rural PSNP (ERPSNP).

    31. In addition, four experts have been assigned from the same Directorate to participate in the process of addressing long outstanding commodity audit findings. Furthermore, COPCD has communicated in a

    letter to all regional Presidents’ office (as per the MoU) to adequately involve their respective internal

    auditors in the review of the program accounts at the required level and report back to the regional/woreda

    cabinet. iii) Lack of predictable cash resource release from GoE and DPs – FSCD has prepared a draft

    disbursement plan for EFY 2011 but was not officially submitted to DPs due to the on-going discussions

    on wage rate increment. iv) weak financial management and oversight in Afar region evidenced by

    ineligible expenditures in recent audit findings – MoFEC (COPCD) has met with the Afar regional officials,

    woreda officials, and woreda accountants and cashiers to discuss on the Afar 1st FM review report findings,

    previous audit report findings, and the overall FM issues in the region. v) Risks on the physical cash

    safeguard in Somali and Afar regions – MoFEC has in a formal letter communicated to the Commercial

    Bank of Ethiopia (CBE) in order to resolve issues regarding low cash holding limit of woredas’ CBE

    branches and possibilities of opening new branches in Somali and Afar region. MoFEC is awaiting response

    from CBE to take next action.

    Procurement

    32. Delays in procurement is a major challenge at federal level. The delays are critical specifically in relation to the selection of consultants to conduct various studies. Among others, the selection of consultants

    for the design and establishment of PSNP MIS design and establishment of PW mapped data base, PW

    baseline study, and independent procurement audit of EFY 2009 are delayed significantly. The Mission has

    noted that procurement planning at Federal level is carried out through Systematic Tracking Exchange in

    Procurement (STEP; an online planning and monitoring tool for procurement). As per the agreed

    procedures, i.e., all procurement activities are carried out as per the roadmap provided in STEP.

    Procurement activities at regional level are submitted by the Federal level procurement officers and have

    been approved. However, the procurement activities are not being processed through the system and it is

    not clear if the procurement activities are being carried out in accordance with the roadmap provided in

    STEP.

    33. The most significant challenge in regard to procurement planning is the woredas level procurement. As per the agreed procedures all procurement activities have to be submitted and approved through STEP.

    However, so far, no PSNP IV procurement activity at Woreda level is submitted and approved through

    STEP. This is a serious concern which should be addressed at all levels in PSNP as procurement activities

    not submitted and approved through STEP cannot be financed through the project as they are going to be

    considered as ineligible expenditures. The Mission noted that the procurement plans of all woredas should

    be submitted and approved through STEP.

  • 10

    Commodity Management

    34. The major issue during the November - December 2017 JRIS was the lack of improvement in the

    commodity management system of the GoE despite various efforts in the past. As part of the disbursement condition and legal covenant of RPSNP, it was agreed that the GoE will finalize and submit to the DPs the Action Plan developed to ensure robust food management system with the establishment and

    operationalization of the CMU in NDRMC being at the heart of it. It is noted that the Action Plan has been

    finalized and submitted to DPs in February 2018.

    35. With regard to the establishment of the CMU at NDRMC, MoALR and NDRMC established an ad-hoc committee to prepare a Concept Note (CN) on overall establishment, functionality, budgeting,

    staffing and operation of the CMU. The CN has been approved by the NDRMC Commissioner and MoALR

    State Minister. An assessment of a permanent office design and set up has been made by NDRMC and

    World Food Programme (WFP). Until such time that this is finalized, a temporary office space has been

    availed for the CMU at NDRMC. In addition, a proposal has been developed by NDRMC showing budget

    requirements for office set up; staff hiring at federal level, core staff at regional level, and hubs; capacity

    building, Information Technology (IT), stationary, vehicle, etc. This has been shared to the NDRMC and

    MoALR management and is awaiting decision. However, apart from availing temporary office space at

    NDRMC for the existing CMU staff, no major progresses have been made in terms of ensuring the full

    functionality of the CMU. Regarding operational activities, the Mission noted that MoALR and NDRMC

    have now started co-managing warehouse and food resources. It is also noted that Commodity Allocation

    and Tracking System (CATS) is now being used at Federal level.

    36. The Mission identified that only limited improvement has been made on the overall food management system and hence this continues to be a major risk for effective program implementation and

    accountability. The non-implementation of the Food Management Improvement Action Plan has been cited

    as the major obstacle for improving the system. As the Action Plan is comprehensive and covers

    institutional arrangement, staffing, reporting, monitoring and evaluation, procurement and dispatch, audits

    and following up of audit findings; it is expected that the implementation of the measures set in the action

    plan will result in the improvement in the overall food management system. Hence, the Mission agreed that

    i) the management team of MoALR, NDRMC, and MoFEC that is responsible for following up the Action

    Plan should ensure the actions set are implemented and status update is communicated to the DPs; ii) clear

    direction needs to be given by MoALR and NDRMC to the existing CMU staff regarding reporting

    structure, accountability and develop ToR for its implementation ; iii) NDRMC and MoALR should allocate

    the necessary resources to make the CMU fully functional.

    Capacity Development

    37. For Output 1, the mission agreed that (i) the Government will conduct a half day workshop on the woreda- level monitoring and reporting assessment findings and cascade it to the regions, (ii) create

    awareness and sensitize regions and woreda leadership on the recommendations; (iii) revise the data

    collection templates and reporting formats and (iv) provide tailored report writing training to the woreda

    and regional monitoring staff. The Mission also agreed that Technical Assistance to Strengthen Capacity

    Development (TASC) will provide technical support to improve monitoring both at federal and regional

    levels, including supporting the government with the revision of monitoring reporting tools and templates

    as part of its capacity building tasks.

    38. For Output 2, the Mission identified the following capacity development needs to improve the timeliness of transfers (i) Training for WIC/RIC/FIC staff on monitoring and reporting; (ii) E-payment

    training and job embedded support to zonal Implementing Agencies (IAs); (iii) PIM awareness for woreda

    leaders-managers involving updating, production, distribution and use of user friendly PIM Guidance Note;

    (iv) rollout FSTFs/TCs strengthening trainings to Woredas; (v) develop institutional capacity (personnel,

    logistic) for new split zones and woredas and, (vi) develop standard PSNP contract staff management

  • 11

    guideline (recruitment, job description, performance evaluation, handing over, etc.). The Mission also

    agreed that TASC would support the targeting and re-targeting in Afar and Somali regions.

    39. For Output 3, the Mission agreed that the Public Works Coordination Unit (PWCU) will provide tailored training to Afar and Somali region staff and ensure that the training is cascaded to frontline

    implementers and undertake supervision/support mission to these regions at least every quarter. It was also

    agreed that the Natural Resources Management Directorate (NRMD) will write a letter to the regions

    stating urgency of the training and cascading to the frontline implementers. Subsequently, the PWCU

    should provide further training on the format. The Mission agreed that TASC would support the government

    in developing ESMF training materials for public works.

    40. For Output 4, the Mission agreed that the Livelihoods Integration Coordination Unit (LICU) will provide specific and tailored training to livelihoods staff, particularly those working on agri-business. It

    was also agreed that TASC would support the government in developing training materials for business

    plan preparation and ESMF for livelihoods.

    41. TASC’s EFY 2011 work plan will place greater emphasis on addressing technical capacity gaps within PSNP. TASC will develop or update guidance notes for training and support on a number of topics,

    including PIM awareness, targeting/retargeting, PASS applications, commodity management, ESMF for

    public works, HDRP/PSNP linkages, planning and reporting, file management, and the NGO Collaboration

    Framework (once approved). It will develop self-learning guidance notes and video for woreda-based staff,

    as well as a manager’s guide to staff induction, which will be available for existing staff and more

    particularly for new staff coming to work on PSNP.

    DISCLOSURE & PLANNING`

    42. The Government of Ethiopia and all DPs confirm their understanding and agreement to this Aide Memoire. This Aide Memoire will be disclosed publicly.

    LIST OF ANNEXES

    Annex 1: Representatives who participated in the JRIS Mission

    Annex 2: Acronyms used throughout the Aide-Memoire

    Annex 3: Progress in implementing the November - December 2017 JRIS Action Plan

    Annex 4: Action plan from June 2018 JRIS Mission (to be done by FSCD)

    Annex 5: Report on the PSNP-4 and ERPSNP Results Framework Indicators (From GoE Report)

    (waiting for FSCD to submit the revised report)

    Annex 6: Overview of the 9 months PSNP-4 Progress in EFY 2010 (From GoE Report)

  • 12

    ANNEX 1: REPRESENTATIVES WHO PARTICIPATED IN THE JRIS MISSION

    S.N. Name Region Organization

    1 Abate Jijo Addis Ababa CRS

    2 Abdi Ahmed Mohamed Somali DPPB

    3 Abdi Mohamed Sani Dire Dawa Food Security

    4 Abdulkadir Sulaiman Addis Ababa USAID

    5 Abebe G/Medhin Addis Ababa MoLSA

    6 Abenet Mengistu Addis Ababa NRMD

    7 Abera Kassa Addis Ababa NDRMC

    8 Abiyot Wondie Addis Ababa MoALR

    9 Abrham Dissassa Addis Ababa MoALR

    10 Abu Yadetta Addis Ababa World Bank

    11 Addis Alem Addis Ababa USAID

    12 Adeyabeba Mitiku Addis Ababa DCT

    13 Ahmed Abdi Daud Somali BoANR

    14 Ahmed Mohammed Addis Ababa GAC

    15 Aiymro Tegegn Dire Dawa BoA

    16 Aklilu Mesfin Addis Ababa MoALR

    17 Alamaz Giramy Addis Ababa NDRMC

    18 Alema W/Mariam Addis Ababa FSCD-LICU

    19 Alemayehu Tadesse Addis Ababa MoALR

    20 Alembirhan W/Gerima Addis Ababa FSCD

    21 Amare Zerihun Amhara BoFED

    22 Amdissa Teshome Addis Ababa Palladium

    23 Amen Geleta Addis Ababa DCT

    24 Amin Abdulahi Dire Dawa BoA

    25 Amir Negash Harari Women Children and Youth

    26 Andarg Fire Addis Ababa MoLSA

    27 Anne Bakilana Addis Ababa World Bank

    28 Annika Nordin Addis Ababa SIDA

    29 Anwar Arabe Aden Somali BoA

    30 Asrate Tamir Amhara Food Security

    31 Assefa Belachew Addis Ababa FSCD/CMU

  • 13

    S.N. Name Region Organization

    32 Assefa Belay Amhara DPFSCO

    33 Ayalew Abera Amhara Food Security

    34 Ayderus Hassen Addis Ababa NDRMC

    35 Aynalem Gezahegn Amahara BoA

    36 Ayuba Sani Addis Ababa World Bank

    37 Badel Kenadidd Mohamod Somali BoANRD

    38 Bayu Getachew Oromia ADLSA

    39 Begashaw Wukaw Addis Ababa DCT

    40 Behailu Shewangizaw Addis Ababa MoALR

    41 Bekele Hankebo Addis Ababa FH Ethiopia

    42 Berhanu W/Michael Addis Ababa FSCD

    43 Berhane Tafere Tigray BoAND

    44 Beyene Adane Addis Ababa MoALR

    45 Blen Tenaw Addis Ababa MOSS

    46 Calla Mahamad Harari Bureau of Youth Job Creation

    47 Carolyn Maclead Addis Ababa GAC

    48 Cathy Tremblay Addis Ababa GAC

    49 Christian Rogg Addis Ababa DFID

    50 Daisy Demirag Addis Ababa World Bank

    51 Degu Lakew Addis Ababa MoFEC

    52 Demelash Eshete Addis Ababa NDRMFSS

    53 Dereje Getaneh Addis Ababa NDRMC

    54 Dimitar Tsolou Addis Ababa TASC

    55 Dianna Darsney Addis Ababa USAID

    56 Doge Bidaru Afar BoLSA

    57 Elias Getahun Addis Ababa World Vision

    58 Elsabeth Farmer Addis Ababa CARE

    59 Ermias Tadege Dire Dawa BoFED

    60 Fantahun Admassu Amhara Cooperatives

    61 Fatima Naqvie Addis Ababa DCT

    62 Fekadu Kassa Addis Ababa FSCD

    63 Feleke Jember Addis Ababa MOLSA

    64 Fentahun Admassu Amhara CPA

  • 14

    S.N. Name Region Organization

    65 Feysal Yahye Somali WFP

    66 Fikru Denbu Addis Ababa FSCD

    67 Fitsum Teshome SNNPR BoFED

    68 Gared Lebese Amhara BoFEC

    69 Gebeyehu Tilahun Dire Dawa DPCOP

    70 Gebre Telake Addis Ababa FH Ethiopia

    71 Gebrie Adugna Addis Ababa FSCD

    72 Getachew Berhanu Addis Ababa UNICEF

    73 Getahun Shibeshi Addis Ababa FH Ethiopia

    74 Gillian Mellsop Addis Ababa UNICEF

    75 Gossa Fursassa Addis Ababa FH Ethiopia

    76 Guluma Subossa Oromia TASC

    77 Gutema Takele Addis Ababa MoALR

    78 Haile Belay Addis Ababa FSCD

    79 Hailegebriel Ashagre Addis Ababa MoFEC

    80 Haileleul Admasie Addis Ababa World Vision

    81 Hailu Ankiso Addis Ababa FSCD

    82 Halake Bantu Addis Ababa WFP

    83 Hanna Misebo Addis Ababa MoALR

    84 Haregewien Admassu Addis Ababa DCT

    85 Hiwot Mebrate Addis Ababa Irish Aid

    86 Hussien Ahmed Afar BoFED

    87 Ian Campbell Addis Ababa World Bank

    88 Ian de la Rosa Addis Ababa CRS

    89 Ivan Roberts Addis Ababa GAC

    90 John Meyer Addis Ababa CARE

    91 Juan Carlos Rodriguez Addis Ababa USAID

    92 Kadir Abdella Afar DPFSCO

    93 Kamil Ahmed Somali BoFED

    94 Konjit Eshete Addis Ababa USAID

    95 Kris Easter Addis Ababa USAID

    96 Lelisa Merga Addis Ababa MoALR

    97 Leulseged Belay Addis Ababa USAID

  • 15

    S.N. Name Region Organization

    98 Leslie Reed Addis Ababa USAID

    99 Lisa Marie Ouedraogo Addis Ababa UNICEF

    100 Liya Girma Addis Ababa WFP

    101 Liz Trigg Addis Ababa DFID

    102 Loza Kibret Addis Ababa World Bank

    103 Lubi Aahmed Somali BoA

    104 Lucian Pop Addis Ababa World Bank

    105 Luis Lechiguero Addis Ababa EU

    106 Mahamud Yusuf Mealin Somali BoFED

    107 Mamo Dogiso Addis Ababa MoALR

    108 Mary Breen Addis Ababa DCT

    109 Massamo Asele Addis Ababa World Bank

    110 Mekdim Hailu Addis Ababa DCT

    111 Mengistu Maja SNNPR BoLF

    112 Merga Mitike Oromia BoLSA

    113 Meron Tadesse Addis Ababa World Bank

    114 Mesfin Alemnew Addis Ababa FSCD

    115 Mesfin Asnake Addis Ababa FSCD

    116 Mesfin Asnake Addis Ababa MoLSA

    117 Mesfin M/Selassie Oromia BoFEC

    118 Mesfin Woldu Tigray BoARD

    119 Michael Mufood Addis Ababa World Vision

    120 Misganaw Admassu Addis Ababa MoLSA

    121 Mitiku Kassa Addis Ababa NDRMC

    122 Moges Worku Addis Ababa USAID

    123 Mohamed Abdi Somali BoFED

    124 Mohamed Fure Dire Dawa BoLSA

    125 Mohamed Rashid Abdirahman Somali BoLSA

    126 Mohammed Hussein Afar DPFSPCO

    127 Molla Mengesha Addis Ababa MoALR

    128 Muluken Desalegn Addis Ababa WFP

    129 Nesredin Rube Addis Ababa MoA

    130 Nigussie Aynalem Tigray BoARD

  • 16

    S.N. Name Region Organization

    131 Nigussie Tefera Addis Ababa FSCD

    132 Nurhuson Molla Addis Ababa MoALR

    133 Osman Mohammod Somali BoANRD

    134 Patrick McManus Addis Ababa Irish Aid

    135 Paul Derkesen Addis Ababa TASC

    136 Reta Birhanu Dire Dawa PSNP

    137 Robert Chase Addis Ababa World Bank

    138 Saba Girma Addis Ababa MoFEC

    139 Samantha Yates Addis Ababa DFID

    140 Samir Wanmali Addis Ababa WFP

    141 Samrawit Girma Addis Ababa World Bank

    142 Samuel Shifeta FS

    143 Samuel Tegegne Addis Ababa MoFEC

    144 Sebsibe Alemu Addis Ababa FH Ethiopia

    145 Segen Tewelde Addis Ababa WFP

    146 Shamil Hamza SNNPR DRMFS

    147 Shawel Bekele Harari BoA

    148 Shilpa Modi Addis Ababa USAID

    149 Shimelis W/Hawariat Addis Ababa World Bank

    150 Sileshi Ashine Addis Ababa TASC

    151 Sileshi Bekele Addis Ababa MoALR

    152 Sintayehu Demissie Addis Ababa MoALR

    153 Sintayehu Geremew Addis Ababa MoALR

    154 Sintayehu Tadesse Addis Ababa MoLSA

    155 Solomon Alemu Addis Ababa USAID

    156 Solomon Begna Oromia BoANRD

    157 Solomon Mamo Harari FS

    158 Sonja Hyland Addis Ababa Irish Aid

    159 Tadesse Aweke Addis Ababa MoALR

    160 Tadesse Bekele Addis Ababa NDRMC

    161 Tefera Taddesse Addis Ababa NRMD

    162 Tekle Urga Addis Ababa MoALR

    163 Teriessa Jalleta Addis Ababa EU

  • 17

    S.N. Name Region Organization

    164 Tesfaye Lakew Addis Ababa WFP

    165 Tesfaye Mengestie Addis Ababa MoALR

    166 Tesfaye Regassa Addis Ababa MoALR

    167 Tesfaye Shiferaw Addis Ababa MoLSA

    168 Tesfaye Tilahun Addis Ababa DCT

    169 Teshome Mamo Addis Ababa BoLSA

    170 Teta Assegid Addis Ababa USAID

    171 Tewodros Assefa Addis Ababa World Bank

    172 Theodros H/Mariam Addis Ababa MoALR

    173 Tofik Abdulu Dire Dawa BoANR

    174 Tofik Juhar SNNPR Cooperatives

    175 Welela Ketema Addis Ababa REDFS

    176 Wihib W/Senbet Addis Ababa CLMFD

    177 Woinshet Abate Addis Ababa MoFEC

    178 Wolelaw Sendeku Addis Ababa CMU/NDRMC

    179 Wondie Kebede Amhara BoA

    180 Wout Soer Addis Ababa World Bank

    181 Yibeltal Fentie Addis Ababa WFP

    182 Yodit Gebrechiristos Addis Ababa TASC

    183 Zelalem Tadesse Addis Ababa MoLSA

    184 Zena H/Wold Addis Ababa MoANR

  • 18

    ANNEX 2: ACRONYMS USED THROUGHOUT THE AIDE MEMOIRE

    AA Addis Ababa

    AGP Agricultural Growth Programme

    BCC Behavioural Change Communication

    ASAP As Soon As Possible

    BoA Bureau of Agriculture

    BoALR Bureau of Agriculture and Livestock Resource

    BoANR Bureau of Agriculture and Natural Resource

    BoARD Bureau of Agriculture and Rural Development

    BoFEC Bureau of Finance and Economic Commission

    BoLSA Bureau of Labour and Social Affairs

    CASCAPE Capacity Building for Scale Up of Evidence-based Best Practices in Agricultural

    Production in Ethiopia

    CATS Commodity Allocation and Tracking System

    CBE Commercial Bank of Ethiopia

    CBPWDG Community Based Participatory Watershed Development Guideline

    CD Capacity Development

    CDTAC Capacity Development Technical Advisory Committees

    CDSC Capacity Development Steering Committee

    CINUS Comprehensive Integrated Nutrition Service

    CMLFD Commodity Management, Logistics and Finance Directorate

    CMPM Commodity Management Procedure Manual

    CMU Commodity Management Unit

    COPCD Channel One Programs Coordination Directorate

    CPI Consumer Price Index

    CRS Catholic Relief Services

    CSA Central Statistical Agency

    CSI Climate Smart Initiative

    DA Development Agent

    CN Concept Note

    DCT Donor Coordination Team

    DFID Department for International Development

    DPs Development Partners

    DWG Donor Working Group

    E-Payment Electronic Payment

    EFY Ethiopian Fiscal Year

    ERPSNP Ethiopian Rural Productive Safety Net Project

    ESPES Enhancing Shared Prosperity through Equitable Services

    ESMF Environmental and Social Management Framework

    EU European Union

    FDP Food Distribution Point

    FH Food for the Hungry

    FIC Federal Information Center

    FM Financial Management

    FMIP Food Management Improvement Project

    FP Focal Person

    FS Food Security

    FSCD Food Security Coordination Directorate

    FSTF Food Security Task Forces

  • 19

    GAC Global Affairs Canada

    GoE Government of Ethiopia

    GoFAMM Government Owned Fixed Assets Management Manual

    GIS Geographic Information System

    GPS Global Positioning System

    GPS Graduation Prediction System

    GRM Grievance Redress Mechanism

    GSD Gender and Social Development

    HDRP Humanitarian Disaster Resilience Plan

    H.E His/Her Excellency

    HEA Household Economic Assessment

    HEW Health Extension Worker

    HFA Humanitarian Food Assistance

    HH Household

    HR Human Resource

    IFPRI International Food Policy Research Institute

    IE Impact Evaluation

    IT Information Technology

    JRIS Joint Review and Implementation Support

    LICU Livelihoods Integration Coordination Unit

    MFIs Microfinance Institutions

    MIS Management Information System

    MoALR Ministry of Agriculture and Livestock Resources

    MoFEC Ministry of Finance and Economic Cooperation

    MoH Ministry of Health

    MoLSA Ministry of Social and Labour Affairs

    MoU Memorandum of Understanding

    NDRMC National Disaster Risk Management Commission

    NGO Non-Governmental Organization

    NRMD Natural Resources Management Directorate

    PASS Payroll and Attendance Sheet System

    PBS Promoting Basic Services

    PDS Permanent Direct Support

    PIM Programme Implementation Manual

    PMT Proxy Means Test

    PP Procurement Plan

    PPD Policy and Planning Directorate PPPDS Public Procurement and Property Disposal Service

    PSNP Productive Safety Net Programme

    PW Public Work

    PWCU Public Works Coordination Unit

    RCT Randomized Control Trail

    RIC Regional Information Centre

    RJOCFSS Rural Job Opportunity Creation and Food Security Sector

    RPWFU Regional Public Works Focal Unit

    RuSACCOs Rural Savings and Credit Cooperatives

    SA Social Accountability

    SD Social Development

    SD&NTF Social Development and Nutrition Task Force

    SDTF Social Development Task Force

    SLMP Sustainable Land Management Project

  • 20

    SM State Minister

    SNNP Southern Nations, Nationalities and People’s

    STEP Systematic Tracking Exchange in Procurement

    SWs Social Workers

    SWC Social and Water ConservationTA Technical Assistant

    TASC Technical Assistance to Strengthen Capacity Development

    TC Technical Committee

    TDS Temporary Direct Support

    TF Task Force

    ToR Terms of Reference

    ToT Training of Trainer

    TVET Technical, Vocational, Education and Training

    UNICEF United Nations International Children's Emergency Fund

    USAID United States Agency for International Development

    WB World Bank

    WFP World Food Programme

    WIC Woreda Information Center

    WoFEC Woreda Finance and Economic Cooperation

    WR Wage rate

  • ANNEX 3: PROGRESS IN IMPLEMENTING THE NOVEMBER – DECEMBER 2018 JRIS ACTION PLAN

    Action Plan for the Priority Strategic Issues

    Issue

    # Issue Action

    Responsible

    Party Deadline Status

    Actions within the PSNP-4, To be Implemented Within 6 Months

    1 Core elements of the

    program are not meeting

    agreed program

    performance standards

    i) GOE to improve timeliness of transfers and timely cash flow

    planning. The Mission notes that

    MOFEC will have flexible

    budget releases to the PSNP

    based on the needs of the

    program and the DPs hope that

    this flexibility will help to

    resolve the cash flow problems

    going forward. The Financial

    Management and planning

    within FSCD needs to be

    strengthened.

    ii) The MoANR procurement tender committee need to

    improve decision-making and

    timely communication for not

    implementing planned

    procurement/delays in

    procurement decisions.

    iii) The salary issue should be reviewed and resolved soon to

    improve staff motivation and

    reduce staff turnover. This issue

    has been raised with the GoE in

    the past and during the Federal

    Mission it was discussed with

    FSCD/MoFEC

    MoANR tender

    endorsing

    committee

    MoANR/MoFEC

    On going

    On going

    Ongoing

    Partially Achieved

    • FSCD and MOFEC have shown an improvement in terms of cash transfer to

    regions on timely manner;

    • Regions have also transferred the cash resource to the woredas partially on time;

    • However, timeliness of payment to the clients did not meet the target.

    In Progress

    • There is progress in the decision making by the tender committee;

    • There is an improvement in implementing of planned procurement and decision making by

    tender approval committee.

    In Progress

    • The two ministries (MoNAR and MoFEC) have discussed on the issue and agreed to

    harmonize salary differences by conducting an

    assessment;

  • Issue

    # Issue Action

    Responsible

    Party Deadline Status

    Minister Eyasu Abraha from

    MoANR. The DPs hope to see

    early resolution of this issue.

    • Accordingly, MoANR organized a review team composed of directors and experts from Human

    Resource (HR) AGP, PSNP, and SLMP,

    travelled to regions to conduct assessment and

    submit recommendation actions;

    • The review team completed the assessment and submit its draft report to the management for

    review and endorsement.

    2 The development of a

    scalable rural safety net

    system that brings

    together PSNP and

    humanitarian food

    assistance continues to be

    the stated vision of the

    GOE yet decisions to

    implement this vision

    have not been made.

    i) Systematic implementation of the joint operational procedures

    put in place

    ii) A decision to consolidate operational management for

    PSNP and HFA by June 30th,

    2018 (as agreed in the first

    phase of the MTR and

    committed by GOE in the

    August 2017 letter sent to the

    World Bank Country Director

    by MOFEC).

    MoANR/NDRMC

    PSNP GOE

    leadership

    End of January

    2018 onwards

    June 30, 2018

    In progress

    Pending

    3 Difficulties with food

    management

    i) The CMU be made functional as agreed as soon as possible

    Government should submit a

    time bound action plan by

    January 2018 that sets out the

    measures to improve the safety

    net food management system,

    as previously agreed

    RJOCFSS

    /NDRMC

    MoFEC

    January 2018

    January 01,

    2018

    Not Achieved (Refer to the Aide Memoire Text

    Paragraph # 33)

    The Government has submitted a time bound

    action plan to the World Bank.

  • Issue

    # Issue Action

    Responsible

    Party Deadline Status

    4 The need to improve poor

    performance in order to

    provide effective safety-

    net support to people in

    Afar and Somali, as has

    been noted repeatedly in

    previous JRIS Missions.

    ii) The federal government continues to work with the

    regions to improve management

    and oversight as well as the

    implementation of transfers.

    iii) Continued verification of performance improvement

    through the results of the spot

    checks, financial management

    reviews, and mid-line evaluation

    PSNP GoE

    Leadership

    RJOCFSS

    Ongoing

    On Quarterly

    Basis

    Ongoing

    Ongoing

    PRIORITY ISSUES FOR PSNP-4 IMPLEMENTATION

    Output 1. Prioritized Instruments and Tools in Place to Support an Effective System for Social Protection and Disaster Risk Management

    1

    MIS development is

    significantly delayed due

    to procurement issues at

    MoANR.

    Completion of the Management

    Information System (MIS)

    Development procurement as soon

    as possible.

    FSCD/procurement

    and property

    administration

    directorate/

    CMLFD

    March 31, 2018 Delayed

    • RFP prepared and sent for firms;

    • 5 firms submitted financial and technical proposal;

    • Technical evaluation underway.

    2 Gaps observed in the

    quality and content of

    PSNP performance

    monitoring and reports.

    i) Review the paper based monitoring and reporting system

    ii) Strengthen core functionality of the paper based monitoring and

    reporting system at all levels

    FSCD/METT

    FSCD/METT

    February 2018

    Ongoing

    Delayed, in progress

    • Training provided to FIC and RIC.

    Ongoing

    3 Absence of an updated

    graduation guidance note

    to implement evidence-

    based graduation.

    i) Review and update the current graduation guidance note (track

    household asset holding,

    benchmark revisions etc.)

    ii) Cascade and use the Household Economic Analysis (HEA)

    conducted by Save the Children

    (SCF).

    FSCD + TAs

    FSCD

    March 31, 2018

    April 30, 2018

    Achieved

    • Regions are communicated to use HEA data to update GPS.

    Delayed, in progress

    • HEA communicated to Regions.

  • Issue

    # Issue Action

    Responsible

    Party Deadline Status

    4 The implementation of the

    DRM component is

    significantly delayed due

    to i) lack of capacity at

    NDRMC, ii) lack of

    consensus in planning

    between NDRMC and

    FSCD and iii) lack of

    coordination.

    Conduct joint planning of the

    Disaster Risk Reduction (DRR)

    component and reached into

    consensus.

    DRR directorate

    and FSCD

    January 2018

    Achieved

    Output 2. Appropriate, Timely and Accessible Transfers Received by Male and Female Clients

    1 Timeliness and

    predictability of transfers

    Establish and operationalize the

    Commodity Management Unit

    (CMU)

    MoANR and

    NDRMC

    By next JRIS

    (May 2018)

    Not Achieved (Refer to the Aide Memoire Text

    Paragraph # 33 regarding CMU establishment

    and being operational)

    Work together/facilitate to ensure

    timely availability of food resources

    from Federal level and delivery to

    woredas

    MOANR, NDRMC

    and EFSRA

    Ongoing In progress/Ongoing

    Revise the cash disbursement

    schedule –Make the 1st tranche end

    of July and the remaining tranche as

    it is (Oct, Jan & Mar)

    MOANR &

    MoFEC

    July 2018

    Onwards

    Achieved

    • First tranche transferred in early August and the remaining tranches transferred as per

    schedules

    Complete re-targeting before end of

    July

    Regions Ongoing In progress, due to start according to the deadline

    2 Delay in cash transfer to

    PSNP Extended Support

    clients and emergency

    beneficiaries in non-PSNP

    woredas

    All regions complete the extended

    support transfer by the third week

    of December, 2017

    Regions End of

    December,

    2017

    Achieved

    NDRMC and FSCD deploy a

    monitoring team to all the regions

    that are implementing extended

    support in non-PSNP woredas like

    they did for Oromia region

    NDRMC and

    FSCD

    December 2017 Achieved

    The Federal Information Centre

    (FIC) follow-up on the progress and

    FSCD/CMLFD On going In progress

  • Issue

    # Issue Action

    Responsible

    Party Deadline Status

    compile the report on extended

    support;

    NDRMC speed up transporting the

    left-over balance of food to Afar

    and Oromia regions.

    NDRMC Before end of

    December 2017

    Delayed/in progress

    • Carry over food dispatched to Afar • FSCD sent a request to NDRMC to transport

    the remaining food to Oromia FDPs

    MoFEC/FSCD in collaboration with

    WFP to speed-up the

    implementation of the cash pilot in

    Siti and Fafan Zones in Somali

    region.

    MoFEC/MoANR Ongoing (until

    June 2018)

    Delayed/ In progress

    • Top-up payment for supplementary food

    provided by WFP

    3 Five-person household

    cap too low

    Eliminate five-person household

    cap (revise the PIM)

    MOANR March 31, 2018 Achieved

    Regions decide how to better

    support households with family

    members beyond the five-person cap

    within existing caseload and budget

    Regions Ongoing Ongoing

    4 Problem with E-payment Establish compatibility and direct

    linkage between PASS output to E-

    payment platform (PASS upgrade)

    FSCD, MoFEC March 31, 2018 Achieved with delays

    • Upgrading process of PASS addressed the requirements of E-payments

    Explore strengthening the agent

    system including engaging

    RuSACCOs as agents noting the

    success in some woredas in Tigray.

    MoFEC, FCA Ongoing In progress/Ongoing

    • Started in Tigray, Oromia and SNNPR

    Establish an interface between

    MFIs, technology service providers

    and MoFEC to enable MoFEC to

    monitor E-Payment implementation

    better.

    MoFEC March 31, 2018 Delayed/ In progress

    • The World Bank has drafted a reporting template to facilitate the interface, but

    implementation is pending.

    • Hello-Cash is providing real time data on its E-payment operation in Somali to MoFEC,

    however; interface with M-birr in the four

    regions (outside of the reporting template

  • Issue

    # Issue Action

    Responsible

    Party Deadline Status

    descripted above which is yet to be

    implemented) not yet deployed.

    5 RIC/FIC reports not

    timely and accurate

    Implement the new RIC template Regions December 31,

    2017 onwards

    Achieved

    6

    Delay in implementation

    of Proxy Means Test

    (PMT)

    Design a PMT formula FSCD, DPS May 2018 Pending (on HICES data availability)

    Pilot PMT in selected woredas with

    the aim of informing the next phase

    of the PSNP

    FSCD, MOLSA July 2018 Pending

    Output 3: Sustainable community assets built and access to social services enhanced

    3A: Public Works

    1

    Monitoring and

    Evaluation System for PW

    activities –delays in

    system Development

    Implement the ongoing extension of

    PW monitoring system with more

    rigorous follow-up with regions,

    until PSNP MIS system established

    PWCU plus

    RPWFU

    End of April

    2018

    In progress

    • Regions such as Oromia, SNNPR and Dire Dawa submitted the extended M&E for ESMF

    PWCU work with PSNP MIS

    system team to ensure MIS system

    incorporates PW monitoring system

    requirements

    PWCU, FSCD Depends on

    MIS progress

    In progress

    • The PWCU closely working with the FSCD IT Staff to ensure PW monitoring system.

    2

    Joint approach of PW and

    Livelihoods not achieved

    to expected level

    Establish Joint Technical Working

    Group

    PWCU, LICU February 2018 Achieved

    • In the working group 2 PWCU, 2 FSCD and 2 WB staffs are represented

    Revise and update the Guidance note

    taking into account feedbacks from

    Regions.

    PWCU March 2018 Not Achieved

    Design joint planning and reporting

    template

    PWCU, LICU March 2018 In progress

    • Discussions held between Livelihoods and

    PWCU on possible areas of revisions.

    Focus on using water and SSI PW

    subprojects to support most needy

    PSNP individual households

    PWCU, FSCD March 2018 On

    wards

    Achieved

    • Included in the PIM

  • Issue

    # Issue Action

    Responsible

    Party Deadline Status

    Integrate the recommendation of the

    CSI pilot into PW/Livelihood

    programs

    PWCU, LICU October 2018 Ongoing

    • CSI will be included in to CBPWDG and Pastoral PW Guideline.

    3 Limitation in the PW

    implementation in Afar

    and Somali regions, such

    as the level of ESMF

    implementation and

    quality, shortcomings in

    the design and/or

    implementation of certain

    types of PW subproject

    (i) Oversight and support of implementation of the flexible

    PW calendar

    (ii) Roll-out of the new woreda cluster approach, including the

    development of a guideline and

    finalization of the clustering of

    woredas, and

    (iii) Establishment of a Mobile PW Support Team at regional level

    for Afar region

    PWCU

    PWCU

    PWCU in support

    with the regions

    May 2018

    April 2018

    April 2018

    Achieved

    • Implementation already started in Somali Region.

    • PW and transfer calendar including mode of transfer determine Woreda by Woreda in Afar

    Region.

    Delayed/Ongoing

    • Clustering of woredas completed in Afar

    Achieved

    4 Low capacity of frontline

    implementers to

    implement the programme

    as per the design

    Strengthen ESMF compliance and

    monitoring throughout regions as

    required

    PWCU April 2018 Ongoing, field monitoring conducted in Afar and

    Oromia Regions

    3B: GSD and Nutrition

    1 Lack of capacity building

    budget for the GSD and

    nutrition sensitive

    provisions

    (i) Regular allocation of budget for nutrition and GSD related

    training, compiled with other

    training needs under output 3

    (ii) The FSCD systematically use other opportunities presented by

    the ESPES funding, UNICEF’s

    CINUS commitment, DFSA’s as

    FSCD/NRMD

    FSCD/ SD&N TF

    Annually

    January 2018

    Achieved

    • GSD and nutrition ToTs conducted.

    Delayed / ongoing

    • Discussion initiated and proposal/ToR prepared and shared with ESPESP

    stakeholders (MoFEC& MoALR-Policy

  • Issue

    # Issue Action

    Responsible

    Party Deadline Status

    well as other NGOs who are

    working on nutrition and gender

    to leverage resources to provide

    grass root level GSD and

    Nutrition training in PSNP

    woredas (given the resource

    constraints the program faces).

    and Planning Directorate (PPD)) and

    waiting their agreement on fund

    channelling modality

    • In collaboration with UNICEF ToT and cascading to grassroot implementers in 80

    CINUS-PSNP woredas carried out.

    Training materials are translated into

    Oromifa and Tigrigna. Printed training

    materials distributed to regions and

    frontline implementers. 2 The absence of woreda

    level GSD experts in

    Oromia, Amhara and

    Afar Regions resulted in

    weak accountability and

    technical support on GSD

    and Nutrition mainly at

    lower level.

    Identify region specific existing

    government structures (for example

    home economist) that would

    formally take the responsibility of

    advancing and monitoring the GSD

    and Nutrition agenda with initial

    capacity development from the

    program side

    FSCD & Regional

    FS Office with

    SD&N TF

    February 2018 Achieved

    • Regions have been communicated to hire or assign the right person for GSD and

    nutrition;

    • Accordingly, Oromia has hired GSD experts at both worda and regional levels.

    • Identification of existing structure in

    Amhara and Afar is delayed 3 Lack of proper

    guidance/instruction on

    the use of capital budget

    FSCD/NRMD communicate with

    regions with clear direction on the

    use of the capital budget in relation

    to the temporary Child Care Centers,

    specifically request the regions to set

    an annual 15% target per Keble for

    construction of Child Care Center.

    FSCD/NRMD February, 2018 Achieved

    • Communicated to region to allow to use part of the capital budget for Child Care Centre.

    4 Low engagement of MoH

    beyond the nutrition case

    team

    (i) Send letter to Minister of MoH from the Minister of MoANR

    outlining the need for

    agreements on improved

    engagement of other MoH’s

    directorates in PSNP

    MoANR/FSCD

    July 2018

    In process, due to start according to the deadline

  • Issue

    # Issue Action

    Responsible

    Party Deadline Status

    (ii) Sign MoU between the MoANR and MoH at the Federal and

    Regional Levels to ensure the

    active involvement of relevant

    directorates of MoH, to

    institutionalize the role of HEWs

    in PSNP, to capture PSNP HHs

    during the registration of

    children in the health posts, in

    household questionnaires of the

    National Health Accounts and

    the Demographic and Health

    surveys, to include PSNP client

    status of household in its routine

    health and nutrition reporting

    (iii) Once agreements are reached to revise the PIM to outline the

    role and responsibilities of the

    different directorates of the

    MOH.

    MoANR/FSCD and

    MoH

    MoANR/FSCD

    August 2018

    August 2018

    In process, due to start according to the deadline

    • Even though the deadline is ahead, draft MoU has been prepared, Nutrition case team of MoH

    commented on it and MoALR will soon

    formally share it to MoH.

    In process, due to start according to the deadline

    Output 4: Clients’ livelihood opportunities facilitated through three pathways: crop and livestock, off-farm and employment

    1 Weak coordination among

    implementing

    stakeholders (PSNP-4,

    NGO and other

    programs/projects)

    continues to be a

    challenge. The Mission

    noted that livelihoods

    coordination

    (i) The reconsideration of the current coordination arrangement

    where FSCD should continue

    chairing LTC as soon as possible

    (ii) Regions adopt proper coordination arrangement that

    fits to their context as soon as

    possible

    FSCD

    Regions

    January 2018

    onwards

    January 2018

    Achieved

    Achieved

  • Issue

    # Issue Action

    Responsible

    Party Deadline Status

    arrangements vary at

    federal and regional level.

    (iii) Federal LICU provide better technical support to regions

    (iv) Experience sharing among regions be conducted

    (v) Strengthen coordination among PSNP, NGO and other

    programs/projects (CASCAPE,

    PASIDP–II and others) by

    establishing NGO collaboration

    framework

    LICU

    LICU/FSCD

    LICU/FSCD &

    DPs

    Quarterly Basis

    April 2018

    March 2018

    Achieved/ongoing

    • Staffs from FSCD provided field level technical support in addition LICU organized

    one-day workshop and discussed with regions

    on issues related to the disaggregation of

    logframe targets, review of the six months

    performance report, refresh on the employment

    pathway guidance noted and livelihoods

    transfer rollout.

    Achieved

    • Experience sharing conducted with in a region

    • Experiences of each region was shared during the one-day workshop in Addis Ababa

    Delayed/ongoing

    • Concept note prepared and approved. • Preparation is underway and government

    agreed to establish the PSNP-NGO platform

    2

    There has been limited

    progress in

    implementation of off-

    farm and employment

    pathways:

    (i) Regions assess and identify the potential for employment

    opportunities

    (ii) TVET’s ability to provide tailored training to PSNP clients

    be assessed

    (iii) Institutional set up and ownership of the off farm and

    employment pathways be

    assessed and reconsidered

    Regions

    LICU/FSCD

    FSCD/RJOCFSS

    April 2018

    July 2018

    July 2018

    Achieved

    • Discussed during federal workshop held on March 2018

    In process/ due to start according to the deadline

    • Discussion is underway. In some regions (e.g. SNNP) TVET started engaging in PSNP.

    In process/ due to start according to the deadline

    • Discussion is underway.

  • Issue

    # Issue Action

    Responsible

    Party Deadline Status

    (iv) The PSNP-4 midline survey captures key questions on the

    implementation of the off-farm

    and employment pathway

    LICU/FSCD

    June 2018

    On Progress

    3 There is inadequate

    compliance of livelihoods

    business plans with the

    Environmental and Social

    Management Framework

    (ESMF).

    (i) Regularly monitor the environmental profile, the ESMF

    guidance note and to make sure

    that the DAs are using the

    guidance for IGA selection

    (screening)

    (ii) Put in place a verification procedure (to make sure that

    ESMF is rolled out in all

    Woredas)

    (iii) Conduct the joint PW and Livelihoods planning and

    implementation review

    LICU

    LICU

    LICU/PWCU

    February 2018

    February 2018

    March 2018

    Delayed/Ongoing

    • Official letter circulated to regions and training given considering ESMF for pastoral regions

    (including Oromia and SNNPR) by PWCU and

    will continue to other regions

    Delayed/ Ongoing

    • ESMF training given to pastoral Regions including Oromia and SNNP

    • Technical support given to Oromia and Afar regions

    Delayed/ On Progress

    • Expression of interest has been developed and

    screening of consulting firms underway.

    Output 5: Effective Management and Operational processes in place to manage the program

    Output 5A: Financial management, Commodity Management, Procurement and Physical Resource Management

    Financial Management

    1 Repetitive budget revision

    issues

    Budget revision, if required, be done

    once a year in January in line with

    GoE’s budget revision procedures.

    Furthermore, during budget

    revisions, FSCD should consult with

    relevant stakeholders and

    communicate timely the revised

    budget along with the basis for

    revision to all stakeholders

    FSCD

    January 2018

    (Ongoing)

    Achieved

    • Budget revised only once in EFY 2010 and communicated to regions.

  • Issue

    # Issue Action

    Responsible

    Party Deadline Status

    2 Systemic Weakness in the

    internal control

    mechanism of the

    programme

    (i) To overcome repetitive systemic internal control

    weaknesses, MOFEC (COPCD)

    arrange a meeting with the

    Inspection Directorate and

    International Financial

    Institution Cooperation

    Directorate at MOFEC to agree

    on implementable actions to

    ensure ERPSNP is reviewed by

    internal audit at MOFEC. At the

    lower levels, BOFEDs and

    WOFEDs should ensure that the

    internal auditors in their

    respective offices are aware of

    the new program’s features and

    that ERPSNP is consistently

    reviewed by the internal audit

    (ii) MOFEC should write a letter to all regional president’s office

    (as per the MoU) and other

    implementers to adequately

    involve their respective internal

    auditors in the review of the

    program accounts at the

    required level.

    COPCD/MoFEC

    MoFEC

    February 2018

    End of January

    2018

    Achieved

    • Agreement and arrangements made with the Inspection Directorate to audit ERPSNP.

    Achieved

    • A letter is written and communicated to all

    regional governments.

    3 Lack of predictable cash

    resource release from

    GOE and DPs.

    FSCD prepare an annual

    disbursement plan (both GoE &

    DPs’ cash contribution) in April of

    each fiscal year for the subsequent

    Ethiopian fiscal year. The plan

    should then be updated based on the

    FSCD April or each

    Fiscal Year

    Ongoing

    • Draft disbursement plan for EFY 2011 is prepared but waiting decision on wage rate

    increment to submit the final version.

  • Issue

    # Issue Action

    Responsible

    Party Deadline Status

    approved annual plan and budget.

    The Mission noted that MOFEC will

    exercise flexibility in their

    disbursements for the PSNP if there

    are delays in disbursement by the

    DPs

    4 Weak financial

    management and

    oversight in Afar region

    evidenced by ineligible

    expenditures in recent

    audit findings.

    MoFEC to discuss with Afar

    regional officials on the findings of

    the financial management reviews

    conducted by the independent

    consultants and agree time-bound

    action plan to implement the

    recommendations of the review

    MoFEC

    February 2018

    Achieved

    • MOFEC has visited the region and met with regional and woreda officials to discuss on the

    consultants’ findings and other FM challenges

    in the region.

    5 Risks on the physical

    cash safeguard in Somali

    and Afar regions

    (i) MoFEC formally communicate with CBE to resolve issues

    regarding low cash holding limit

    of woredas’ CBE branches and

    possibilities of opening new

    branches in Somali and Afar

    regions

    (ii) MOFEC obtain and review supervision mission reports from

    Afar region to ensure corrective

    actions are taken on the overall

    cash transfer system in the

    region.

    MoFEC

    MoFEC

    February 2018

    When report is

    submitted

    Achieved

    • A letter is written to CBE and expecting response.

    Achieved

    Commodity Management

  • Issue

    # Issue Action

    Responsible

    Party Deadline Status

    1 Despite efforts in

    previous years to improve

    and strengthen the

    commodity management

    system of the GoE,

    minimal improvement has

    been noted so far

    For the actions refer to the

    Priority Strategic Issues # 3

    above

    Not Achieved, refer to the Aide Memoire Text

    Paragraph # 33 for status.

    Procurement and Physical Resource Management

    1 Delays in procurement

    implementation in EFY

    2009 and delay in

    response to procurement

    audit findings.

    (i) Establish an accountability mechanism for the delays in

    decision making and non-

    performing procurement

    activities as per the agreed

    procurement rules and

    procedures

    (ii) Establish a procurement performance reporting and

    monitoring system from woreda

    level to the federal level that is

    linked to performance

    monitoring indicators in the

    logframe

    (iii) Undertake a joint procurement performance monitoring and

    support mission on a quarterly

    basis from federal to regions and

    to woreda levels

    (iv) Assign qualified and dedicated procurement staff at the woreda

    level

    MoANR

    Regions with

    support of FSCD

    FSCD/CMLFD

    Regions with close

    support from

    FSCD/MoFEC

    February 2018

    Onwards

    End of January

    2018

    On Quarterly

    Basis

    February 2018

    Delayed/Pending

    Achieved

    • Quarterly procurement performance reporting format is prepared and shared with the

    Implementing Agencies (IAs)

    Partially achieved

    • Joint support provided to sample Woredas from Afar and Oromia regions.

    Partially Achieved

    • Woreda procurement staff are assigned in all regions except SNNP region.

  • Issue

    # Issue Action

    Responsible

    Party Deadline Status

    (v) Provide continuous and structured training to the

    decision makers, tender

    committee members and the

    procurement staff at all levels

    (vi) Strengthen the internal audit section of the implementing

    agencies and engage to follow up

    the actions to be taken by each of

    the implementing agencies

    (vii) MoFEC and regional finance bureaus follow up and monitor

    the actions taken on the

    procurement audit findings in a

    timely manner

    (viii) Timely submission and approval of Procurement Plan

    (PP)

    MoANR

    Implementing

    Agencies

    (MoANR and

    MoFEC for follow

    up, monitor and

    ensure the actions

    are taken)

    MoFEC and

    regional finance

    bureaus

    FSCD/CMLFD

    February 2018

    On Quarterly

    Basis

    On Quarterly

    Basis

    Every Year in

    July the draft

    PP and the final

    PP immediately

    after the

    approval of the

    annual Plan and

    Budget

    Achieved

    • Training has been provided to 316 participants selected from MoANR, NDRMC, Public

    Procurement and Property Disposal Service

    (PPPDS) Afar and Oromia region IA.

    Ongoing

    Ongoing

    Achieved, Ongoing

    2