PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER...

149
1 Contractor No. of corrections Executive Engineer STANDARD BIDDING DOCUMENT PROCUREMENT OF CIVIL WORKS PART-I COMPLETE BIDDING DOCUMENT NAME OF WORK : Reconstruction & Extension of Existing Jetty and Civil Work (Reclamation Bund, Terminal Building and other onshore work) at Malvan Port, Tal-Malvan, Dist- Sindhudurg. E-TENDER B-II TENDER FORM

Transcript of PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER...

Page 1: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

1

Contractor No. of corrections Executive

Engineer

STANDARD BIDDING DOCUMENT

PROCUREMENT OF CIVIL WORKS

PART-I

COMPLETE BIDDING DOCUMENT

NAME OF

WORK :

Reconstruction & Extension of

Existing Jetty and Civil Work

(Reclamation Bund, Terminal

Building and other onshore work) at

Malvan Port, Tal-Malvan, Dist-

Sindhudurg.

E-TENDER

B-II TENDER FORM

Page 2: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

2

Contractor No. of corrections Executive

Engineer

GOVERNMENT OF MAHARASHTRA

AGREEMENT NO---------------

NATIONAL COMPETITIVE BIDDING

(CIVIL WORKS)

Name of work : Reconstruction & Extension of Existing Jetty and Civil Work (Reclamation Bund, Terminal Building and other onshore work) at Malvan Port, Tal-Malvan, Dist-Sindhudurg.

Tender Issue Date : Date.08.05.2018 at 10.00 hrs.

Time and date of pre-bid

conference

: Date. 18.05.2018 at 15.00 hrs, Maharashtra Maritime

Board, Indian Mercantile Chamber, 3rd floor, Ramjibhai Kamani Marg, Ballard Estate, Mumbai-400 001.

Opening Date

(If possible)

: Date. 04.05.2018 at 12.00 hrs Maharashtra Maritime

Board, Indian Mercantile Chamber, 3rd floor, Ramjibhai Kamani Marg, Ballard Estate, Mumbai-400 001

Officer inviting bids Chief Executive Officer, Maharashtra Maritime Board, Indian Mercantile Chamber, 3rd floor, Ramjibhai Kamani Marg, Ballard Estate, Mumbai-400 001

Page 3: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

3

Contractor No. of corrections Executive

Engineer

GOVERNMENT OF MAHARASHTRA

MAHARASHTRA MARITIME BOARD

INVITATIONS FOR BIDS (IFB)

NATIONAL COMPETITIVE BIDDING

The Chief Executive Officer, Maharashtra Maritime Board, Indian Mercantile Chamber, 3rd floor, Ramjibhai Kamani Marg, Ballard Estate, Mumbai-400 001. Iinvites online bids for the

construction of work detailed in the table.

Sr. No.

Name of Work Approximate

value of work Rs.

Earnest Money Deposit

(Rs.)

Cost of Document

(Rs.)

Period of completion

1 Reconstruction & Extension of

Existing Jetty and Civil Work

(Reclamation Bund, Terminal

Building and other onshore

work) at Malvan Port, Tal-

Malvan, Dist-Sindhudurg.

5,01,28,000/-

2,51,000/- 3,540/-

18 Months

(Including

monsoon)

E-TENDER TIME SCHEDULE

Please Note: All bid related activities (Process) will be governed by the time schedule given under Key Dates

below:

Sr. No.

Activities Date Hour Mins.

1 Publishing Date 08.05.2018 At 15 00

2 Document Download start Date 08.05.2018 At 15 00

3 Document Download End Date 01.06.2018 Up to 17 00

4 Seek clarification start Date 08.05.2018 At 15 00

6 Seek clarification end Date 18.05.2018 Up to 14 00

5 Pre-Bid Meeting 18.05.2018 At 15 00

7 Bid Submission start Date 22.05.2018 At 10 00

8 Bid Submission closing Date 01.06.2018 Up to 17 00

9 Bid Opening Date *(If Possible) 04.06.2018 At 12 00

Page 4: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

4

Contractor No. of corrections Executive

Engineer

*Dates mentioned here, are scheduled dates for Bid Opening Activities. Any changes in dates of opening of technical and commercial tenders shall be notified in 'Press Notice / Corrigendum' section on the e-Tendering sub portal of the department before opening of the same. Note:-

1. All eligible / interested Bidders are required to be enrolled on portal https://mahatenders.gov.in to

participate in e-tendering.

2. Bidders should submit the document related to tender, earnest money and tender document fee under

their digital signature online through payment gateway on the e tendering portal.

3. Other instructions can be seen in the tender form. All or any one of the tender may be rejected by

competent authority without assigning any reason.

PROCEDURE UNDER E-TENDERING INSTRUCTION TO BIDDERS

Tender form, conditions of contract, specifications and contract drawings can be

downloaded from https://mahatenders.gov.in after entering the details payment of

Rs. 3,540/- (Rupees Three Thousand Five Hundred and Forty Only) should be

paid online using payment gateway. The fees of tender document will be non

refundable.

Further information regarding the work can be obtained from the above office.

Affidavit on Rs. 100/- stamp paper in prescribed form given in Annexure I sworn

before Executive Magistrate / Notary, Additional Performance Security Deposit (if

required) scan copy of original should be submitted online. Bids will be opened as per

the Tender Schedule, in the presence of such intending Tenderers or his / their

authorized representatives who may be present at that time.

TENDERING PROCEDURE :

1.1. Blank Tender Forms.

1.1.1 Tender Forms can be downloaded from the e-Tendering portal of Public Works

Department, Government of Maharashtra i.e. https://mahatenders.gov.in after

entering the details of payment towards Tender Fees as per the Tender Schedule.

1.1.2 The tender submitted by the tenderer shall be based on the clarification, additional

facility offered (if any) by the Department, and this tender shall be unconditional.

Conditional tenders will be summarily REJECTED.

1.1.3 All tenderers are cautioned that tenders containing any deviation from the

contractual terms and conditions, specifications or other requirements and

conditional tenders will be treated as non responsive. The contractor should clearly

mention in forwarding letter that his offer (in envelope No.1& 2) does not contain

any condition, deviations from terms and conditions stipulated in the tender.

1.1.4 Tenderers should have valid Class II / III Digital Signature Certificate (DSC)

obtained from any Certifying Authorities. In case of requirement of DSC, interested

Page 5: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

5

Contractor No. of corrections Executive

Engineer

Bidders should go to https://mahatenders.gov.in and follow the procedure

mentioned in the document ;Procedure for application of Digital Certificate.

1.1.5 For any assistance on the use of Electronic Tendering System, the Users may call

the below

Toll Free Ph. No. 1800 30702232/7878107985-86

E-Mail : [email protected]

1.2 PRE-TENDER CONFERENCE: -

1.2.1 Pre-tender conference open to all prospective tenderers who have purchased

tender form before the date of Pre-tender Conference, will be held at Mumbai on

Dated.18.05.2018 at 15.00 hrs Maharashtra Maritime Board, Indian Mercantile Chamber, 3rd

floor, Ramjibhai Kamani Marg, Ballard Estate, Mumbai-400 001, Phone No. (022)

22694475 wherein prospective Tenderers will have an opportunity to obtain clarifications

regarding the work and the Tender Conditions.

1.2.2 The prospective tenderers are free to ask for any additional information or

clarification either in writing or orally concerning the work, and the reply to the same will

be given by the Chief Engineer / Superintending Engineer / Executive Engineer, in

writing and this clarification referred to as Common Set of Conditions/Deviations

(C.S.D.), shall form part of tender documents and which will also be common and

applicable to all tenderers. The point/points if any raised in writing and/or verbally by the

contractor in pre-tender conference and not finding place in C.S.D. issued after the pre-

bid conference, is/are deemed rejected. In such case the provision in NIT shall prevail. No

individual correspondence shall be made thereafter with the contractor in this regard.

1.2.3 The tender submitted by the tenderer shall be based on the clarification, additional

facility offered (if any) by the Department, and this tender shall be unconditional.

Conditional tenders shall be summarily REJECTED.

1.2.4 All tenderers are cautioned that tenders containing any deviation from the

contractual terms and conditions, specifications or other requirements and conditional

tenders will be treated as non responsive. The contractor should clearly mention in

forwarding letter that his offer (in envelope No. 1& 2) does not contain any conditions,

deviations from terms and conditions stipulated in the tender.

1.3 Special Instructions to the Contractors/Bidders for the e-submission of the bids

online through this tender site : https://mahatenders.gov.in

(1) Bidder must register themselves on https://mahatenders.gov.in portal by clicking

“Online Bidder Enrollment” and then map Digital Signature certificate.

(2) Bidder then login to the site giving user id / password chosen during registration.

(3) The e-token that is registered should be used by the bidder and should not be

misused by others.

(4) The Bidders can update well in advance, the documents such as certificates,

purchase order details etc., under My Documents option and these can be selected

as per tender requirements and then attached along with bid documents during bid

Page 6: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

6

Contractor No. of corrections Executive

Engineer

submission.

(5) After downloading / getting the tender schedules, the Bidder should go through

them carefully and then submit the documents as asked, otherwise, the bid will be

rejected.

(6) If there are any clarifications, this may be obtained online through the tender site, or

through the contact details. Bidder should take into account of the corrigendum

published before submitting the bids online.

(7) Bidder, in advance, should get ready the bid documents to be submitted as indicated

in the tender schedule and they should be in PDF/xls/rar/dwf formats. If there is

more than one document, they can be clubbed together.

(8) Bidder should get ready the EMD as specified in the tender. The original should be

posted/couriered/given in person to the Tender Inviting Authority, within the bid

submission date & time for the tender.

(9) The bidder reads the terms & conditions and accepts the same to proceed further to

submit the bids.

(10) The bidder has to submit the tender document online well in advance before the

prescribed time to avoid any delay or problem during the submission process.

(11) After the bid submission, the acknowledgement number, given by the e-tendering

system should be printed by the bidder and kept as a record of evidence for online

submission of bid for the particular tender.

(12) The details of the Earnest Money Deposit document submitted physically to the

Dept and the scanned copies furnished at the time of bid submission online should

be the same otherwise the Tender will be summarily rejected

(13) The Tender Inviting Authority (TIA) will not be held responsible for any sort of

delay or the difficulties faced during the submission of bids online by the bidders.

(14) The bidder may submit the bid documents either by online mode through the site

(https://mahatenders.gov.in) as indicated in the tender.

(15) The tendering system will give a successful bid updating message after uploading

all the bid documents submitted & then a bid summary will be shown with the bid

no, date & time of submission of the bid with all other relevant details. The

documents submitted by the bidders will be digitally signed using the e-token of the

bidder and then submitted.

(16) The bid summary has to be printed and kept as an acknowledgement as a token of

the submission of the bid. The bid summary will act as a proof of bid submission

for a tender floated and will also act as an entry point to participate in the bid

opening date.

(17) Bidder should log into the site well in advance for bid submission so that he submits

the bid in time i.e. on or before the bid submission end time. If there is any delay,

Page 7: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

7

Contractor No. of corrections Executive

Engineer

due to other issues, bidder only is responsible.

(18) The bidder should see that the bid documents submitted should be free from virus

and if the documents could not be opened, due to virus, during tender opening, the

bid is liable to be rejected.

(19) The time settings fixed in the server side & displayed at the top of the tender site,

will be valid for all actions of requesting, bid submission, bid opening etc., in the e-

tender system. The bidders should follow this time during bid submission.

(20) All the data being entered by the bidders would be encrypted using PKI encryption

techniques to ensure the secrecy of the data. The data entered will not viewable by

unauthorized persons during bid submission & not be viewable by any one until the

time of bid opening. Overall, the submitted tender documents become readable only

after the tender opening by the authorized individual.

(21) The confidentiality of the bids is maintained since the secured Socket Layer 128 bit

encryption technology is used. Data storage encryption of sensitive fields is done.

(22) The bidders are requested to submit the bids through online etendering system to the

TIA well before the bid submission end date & time (as per Server System Clock).

(23) The bidder should logout of the tendering system using the normal logout option

available at the top right hand corner and not by selecting the (X) option in the

browser.

(24) The bidder should upload the Technical document in .rar format single file to

upload in Technical cover and then BOQ in .xls format single file to upload in

Finance cover.

(25) For any other queries, the bidders are asked to contact through Mail

: [email protected]

Page 8: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

8

Contractor No. of corrections Executive

Engineer

SECTION 1 – INSTRUCTIONS TO BIDDERS (ITB)

Section – 1 : Instructions to Bidders

A. GENERAL

1. Scope of Bid

1.1 The Employer (named in Appendix to ITB) invites online bids for the constructions of works (as

defined in these documents and referred to as “the works”) detailed in the table given in IFB. The

bidders may submit bids for any or all of the works detailed in the table given in IFB.

1.2 The successful bidder will be expected to complete the works by the intended completion date

specified in the Contract data.

1.3 Throughout these bidding documents, the terms ‘bid’ and ‘tender’ and their derivatives

(bidder/tenderer, bid/tender, bidding/tendering etc.) are synonymous.

2. Sources of Funds

The expenditure on this project will be met from the budget of "IWD - 0317"

3. Eligible Bidders

3.1 This invitation for Bids is open to all bidders.

3.2 All bidders shall provide in Tender part-2 Section 2, Forms of Bid and Qualification Information, a

statement that the Bidder is neither associated, nor has been associated, directly or indirectly, with the

Consultant or any other entity that has prepared the design, specification, and other documents for the

Project or being proposed as Project Manager for the Contract. A firm that has been engaged by the

Employer to provide consulting services for the preparation of supervision of the works, and any of its

affiliates, shall not be eligible to bid.

4. Qualification of the Bidder

4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary

description of the proposed work method and schedule, including drawings and charts, as necessary.

The proposed methodology should include programme of construction backed with equipment

planning and deployment duly supported with broad calculations and quality assurance procedures

proposed to be adopted justifying their capability of execution and completion of work as per

technical specifications, within stipulated period of completion.

4.2 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the

following information and documents with their bids in Section 2.

(a) Copies of original documents defining the constitution or legal status, place of registration

and principal place of business, written power of attorney of the signatory of the Bid to

commit the Bidder ;

(b) Total monetary value of construction work performed for each of the last five years ;

(c) Experience in works of a similar nature and size for each of the last five years and details of

works underway or contractually committed and clients who may be contacted for further

information on those contracts ;

(d) Major items of construction equipment proposed to carry out the Contract.

(e) Qualifications and experience of key site management and technical personnel proposed for

contract ;

(f) Reports on the financial standing of the Bidder, such as profit and loss statements and

auditor’s reports for the past five years ;

Page 9: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

9

Contractor No. of corrections Executive

Engineer

(g) Evidence of access to line(s) of credit and availability of other financial resources facilities

(10% of contract value) certified by the Bankers. (Not more than 3 months old);

(h) Undertaking that the bidder will be able to invest a minimum cash up to 25% of contract

value of work during implementation of work ;

(i) Authority to seek references from the Bidder’s bankers ;

(j) Information regarding any litigation, current or during the last five years, in which the Bidder

is involved, the parties concerned and disputed amount ;

4.3 QUALIFICATION CRITERIA

4.3.1 Qualification will be based on Applicant’s meeting all the following minimum pass/fail criteria

regarding the Applicant’s general and particular experience, personnel and equipment capabilities,

and financial position, as demonstrated by the Applicant’s response in the forms attached to the

Letter of Application. Subcontractor’s experience and resources shall not be taken into account in

determining the Applicant’s compliance with the qualifying criteria.

To qualify for more than one contract, the applicant must demonstrate having experience and

resources sufficient to meet the aggregate of the qualifying criteria for each contract given in the

paragraphs 4.3.4, 4.3.5, 4.3.6 and 4.3.9 below.

4.3.2 Base year and escalation: -The base shall be taken as 2017-18

Following enhancement factors will be used for the cost of works executed and the financial figures to

a common base value for works completed in India.

Year

before

Multiplying

factor

One 1.10

Two 1.21

Three 1.33

Four 1.46

Five 1.61

Applicant should indicate actual figures of costs and amount for the works executed by them

without accounting for the above mentioned factors.

In case the financial figures and value of completed works are in foreign currency, the above

enhanced multiplying factors will not be applied. Instead, current market exchange rate (State

Bank of India BC selling rate as on the last date of submission of bid) will be applied for the

purpose of conversion amount in foreign currency in Indian rupees.

4.3.3 General Experience

The applicant shall meet the following minimum criteria

(a) To qualify for award of the contract, each tenderer in his name should have achieved an

Minimum financial turnover of Rs. 2,50,64,000.00 during last three years ( FY 2014-15 , 2015-

16, 2016-17) at the price level of 2017-2018 information should be given in Performa given

This should be duly audited by Chartered Accountant. Year in which no turnover is shown

would also be considered for working out the average turnover.

(b) Satisfactorily completed as a contractor, at least one similar type of work, Construction of

value Rs. 1,50,38,400.00 at the price level of 2017-2018.

Page 10: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

10

Contractor No. of corrections Executive

Engineer

-: Definition of Similar works :-

Contractor should have constructed a minimum of 2 or more Bund having

60mtr. length + Buildings having 600 Sq.mtr. area.

(c) The Scan copy of Original copy of Valid GST registration certificate from Goods and Service

Tax Act.

(d) Satisfactorily executed in any one year, out of last 3 years preceding March 2017 the following

minimum quantities of work (Information to be given only in Form No. I enclosed herewith on

Page-14.

Sr

no Item Quantity Unit

I Excavation for foundation 1250.00 Cubic Metre

II RCC Quantity

(M-20& Above) 300.00 Cubic Metre

III Filter layer of 20kg trap

stones 450.00 Cubic Metre

IV Core layer of 200kg trap

stones 1200.00 Cubic Metre

V Sub-armour layer of 300-

500kg trap stones 200.00 Cubic Metre

VI Armour layer of above

1000kg trap stones 500.00 Cubic Metre

The works may have been executed by the Applicants as prime contractor.

Substantially completed works means those works which are at least 90 % completed as on the date of

submission (i.e. gross values of work done up to the last date of submission is 90% or more of the

original contract price) and continuing satisfactorily.

For these, a certificate from employer shall be submitted along with application incorporating clearly

the name of the work, contract value, billing amount, date of commencement of works satisfactory

performance of the Contractor and any other relevant information.

4.3.4 Personal capabilities

The Applicant must have suitably qualified personal to fill the following positions. The Applicant will

supply information on a prime candidate and alternate for each position, both of whom should meet

the experience requirements specified below.

List of Key Personnel to be deployed on Contract Work

Sr.

No. Personnel Qualification No. of Personnel

1 Project Manger B.E. Civil + 15 Years Exp. 1 No.

(5 years as Manager)

2 Site Engineer B.E. Civil + 10 Years Exp. 2 Nos.

Page 11: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

11

Contractor No. of corrections Executive

Engineer

3 Electrical

Engineer DEE+3years exp. 1 No.

4 Quantity

Surveyor B.E. Civil + 7 years Exp. or 1 No.

Dip. Civil + 10 years Exp.

5 Survey

Engineer B.E. Civil + 3 years Exp. or 1 No.

Dip. Civil + 5 years Exp.

ITI Civil + 8 years Exp.

Total 6

4.3.5 Equipment capabilities

The Applicant should own or should have assured ownership to the following key items of equipment,

in full working order, and must demonstrate that, best on known commitments; they will be available

for the work in proposed contract.

List of Key Plant &Equipment to be deployed on Contract Work

Sr.No. Type of Equipment

Maximum age as

on 01.4.2017

(Years)

Minimum Requirement

1 Motor Grader 5 1

(Owned/ Hired)

2 Dozer 5 1

(Owned/ Hired)

3 Front end Loader (JCB) 5 1

(Owned/ Hired)

4 Smooth Wheeled Roller 5 2

(Owned/ Hired)

5 Vibratory Roller 5 1

(Owned/ Hired)

6 Water Tanker 5 2

(Owned/ Hired)

7 Concrete Mixes with Integral

Weigh Batching facility 5

1

(Owned/ Hired)

8

Concrete Batching and Mixing

Plant (Minimum capacity – 15

m3/hour)

5 -

Total 9

4.3.6 Financial Position

The Applicant should demonstrate that he has access to, or has available, liquid assets (aggregate of

working capital, cash in hand and uncommitted bank guarantees) and /or credit facilities of not less

than 10 percent of the value of the contract/contracts applied for (construction cash-flow may be taken

as 10 percent of the estimated value of the contract / contracts)

4.3.7 The audited balance sheets for the last five years should be submitted, which must demonstrate the

soundness of the Applicant’s financial position, showing long-term profitability including an

Page 12: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

12

Contractor No. of corrections Executive

Engineer

estimated financial projection for the next two years. If necessary, the employer will make enquiries

with the applicant’s bankers.

4.3.8 Litigation History

The Applicant should provide accurate information on any litigation or arbitration resulting from

contracts completed or under execution by him over the last five years. A consistence history of

awards against the applicant may result in failure of the applicant.

4.3.9 Bid Capacity

Applicant who meets the minimum qualification criteria will be qualified only if their available bid

capacity is more than the total bid value. The available bid capacity will be calculated as under:

Assessed Available Bid capacity = (A x N x 2 - B),

Where,

A = Highest turnover of last five years (updated to the current price level ) rate of inflation may be

taken as 10 percentage per year which will taking into account the completed as well as works in

progress.

B = Value at current price level of the existing commitments and ongoing works to be completed

during the next 11 months, and

N = Number of years prescribed for completion of the works for which bids are invited.

4.4 Disqualification

Even though the applicants meet the above qualifying criteria, they are subject to be disqualified if

they have:

➢ made misleading or false representation in the form, statements submitted; and / or

➢ Records of poor performance such as abandoning the works, rescinding of contract

for which the reasons are attributable to the non-performance of the contractor,

consistent history of litigation awarded against the Applicant or financial failure due

to bankruptcy.

4.5 JOINT VENTURE - DELETED (Not Allowed )

5. One Bid per Bidder

5.1 Each bidder shall submit only one online - bid for one package. A bidder who submits or participates in

more than one Bid (other than as a sub contractor or on cases of alternatives that have been permitted

or requested) will cause all the proposals with the Bidder's participation to be disqualified.

6. Cost of Bidding

6.1 The bidder shall bear all costs associated with the preparation and submission of his bid and the

Employer will in no case be responsible and liable for those costs.

7. Site Visit

7.1 The Bidder, at the Bidder's own responsibility and risk is encouraged to visit and examine the Site of

Works and its surrounding and obtain all information that may be necessary for preparing the Bid and

entering into a contract for construction of the Works. The cost of visiting the Site shall be at the

Bidder's own expense.

Additional Requirements

Bidders should provide any additional information required to fulfil the requirements of clause 4 of

the Instructions to the Bidders, if applicable.

(i) Affidavit

Page 13: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

13

Contractor No. of corrections Executive

Engineer

(ii) Undertaking.

(iii) Affidavit additional performance security must be enclosed

FORM NO. 1

DETAILS OF SIMILAR ITEMS OF WORK CARRIED OUT IN ANY THREE YEAR BY TENDERER

NAME OF TENDERER:

Sr.

No Name of Work

Amount Put

to Tender

Agreement

No.

Date of

Commencement

Quantities of work

in any one year

Year of

Execution

1 2 3 4 5 6 7

Note : This is only a standard form, details are to be furnished in this format in typewritten statements which shall be

enclosed.

Page 14: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

14

Contractor No. of corrections Executive

Engineer

B. BIDDING DOCUMENTS

8. Content of Bidding Documents

8.1. The set of bidding documents comprises the documents listed below and addenda issued in accordance

with Clause 10.

Section Particulars Volume No.

Invitation for Bids

1 Instruction to Bidders

I 2 Qualification information and other forms

3 Conditions of Contract

4 Contract Data

5 Technical Specification II

6 Form of Bid

III 7 Bill of Quantities

8 Securities and other forms

9 Drawings IV

10 Documents to be furnished by bidder V

8.2. Complete bidding document containing volumes - I, II, III and IV are available to the bidders on e-

tendering portal https://mahatenders.gov.in Documents to be furnished by the bidder in compliance to

section 2 will be by him and uploaded online as “ in “general document ” (Refer clause 12) .

8.3. The bidder is expected to examine carefully all instructions, conditions of contract, contract data, forms,

terms, technical specifications, bill of quantities, forms, Annexes and drawings in the Bid Document.

Failure to comply with the requirements of Bid Documents shall be at the bidder's own risk. Pursuant to

clause 26 hereof, bids which are not substantially responsive to the requirements of the Bid Documents

shall be rejected.

9. Clarification of Bidding Documents

9.1. A prospective bidders requiring any clarification of the biding documents may notify the Employer in

writing or by Fax /email at the Employer’s address indicated in the invitation to bid before the date and

time of the pre-bid meeting specified in the Tender Schedule. The Employer will respond to any request

for clarification which he received, earlier than 3 days prior to the Bid due date. Copies of the Employer's

response will be uploaded in “edit attachment option” of concern tender on e-tendering portal and viewable

to all tenderer, including a description of the enquiry but without identifying its source.

Page 15: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

15

Contractor No. of corrections Executive

Engineer

9.2. Pre-bid meeting

9.2.1 The bidder or his official representative is invited to attend a pre-bid meeting which will take place at the

address, venue, time and date as indicated in NIT.

9.2.2 The purpose of the meeting will be to clarify issues and to answer questions on any matter that may be

raised at that stage.

9.2.3 The bidder is requested to submit any questions in writing by fax or by e-mail to reach the Employer well

before the date & time of the pre-bid meeting.

9.2.4 Minutes of the meeting, including the text of the questions raised (without identifying the source of

enquiry) and the responses given will be transmitted by uploading on e-tender portal without delay for

information to all intended bidder. Any modifications of the bidding documents listed in sub clause 8.1

which may become necessary as a result of the pre-bid meeting shall be made by the Employer exclusively

through the issue of an Addendum pursuant to clause 10 and not through the minutes of the pre-bid

meeting.

9.2.5 Non-attendance at the pre-bid meeting will not be a cause for disqualification of a bidder.

10. Amendment of Biding Documents

10.1. Before the deadline for submission of bids online, the Employer may modify the bidding documents by

issuing addenda.

10.2. Any addendum thus issued shall be part of the bidding documents and shall be uploaded in “edit

attachment option” of concern tender on e-tendering portal and viewable to all tenderer, including a

description of the enquiry but without identifying its source. The uploading of addendum on e-tendering

portal shall deemed to be acknowledgement of receipt of each addendum to the employer. The Employer

will assume no responsibility for non cognizance by the bidders.

10.3. To give prospective bidders reasonable time in which to take an addendum into account in preparing their

bids, the Employer may, at his discretion, extend as necessary the deadline for submission of bids, in

accordance with Sub-Clause 20.2 below.

10.4. BID REJECTION CRITERIA:

The bidders are informed about the bid rejection criteria stated as below

10.4.1. Following bids shall be categorically rejected;

10.4.1.1. Bids received after the tender closing date and time.

10.4.1.2. Bids received without EMD as specified in the tender

10.4.1.3. Following bid rejection criteria may render the bids liable for rejection with the

approval of CEO, MMB.

10.4.1.4. Incomplete / misleading / ambiguous/ conditional bids in the considered opinion of

MMB.

10.4.1.5. Bidders not agreeing to furnish required Security Deposit till completion of the

contract.

10.4.1.6. Validity Period indicated by the bidder is shorter than as specified in the tender

document.

10.4.1.7. Bidders not agreeing to furnish Performance Bank Guarantee till the completion of the

contract.

10.4.1.8. Bids not meeting the qualification parameters stipulated in the tender document.

10.4.1.9. Bidders not furnishing additional security deposit in the correct form and amount.

10.4.2. Following bid rejection criteria may render the bids liable for Rejection with the approval of the

tender committee.

Page 16: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

16

Contractor No. of corrections Executive

Engineer

10.4.2.1. Bidder's failure to submit sufficient or complete details for evaluation of the

bids/within the given period depending on the deficiencies noticed in the drawing /

technical data which shall not however conflict with validity period.

10.4.2.2. Incomplete / misleading / ambiguous bids in the considered opinion of tender

committee

10.4.2.3. Bids received without pre-qualification document where required as per the tender.

10.4.2.4. Bids not meeting the pre-qualification parameters stipulated in the tender enquiry.

10.4.2.5. Wherever PVC is allowed as per Tender but the bidder(s) quoted fixed price or vice –

versa

10.4.2.6. Extra Items :

Extra item of Works ; if any, shall be determined supported by a rate analysis on the following

basis:

• Rates derived from similar items of this contract.

OR

• Rates for similar items of work executed through other agencies for MMB

recently.

OR

• Rates mutually agreed.

Page 17: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

17

Contractor No. of corrections Executive

Engineer

C. PREPARATION OF BIDS

11. Language of the Bid

11.1 All documents relating to the bid shall be in the English language.

12. Documents Comprising the Bid

12.1 The bid to be submitted by the bidder as Volume V of the bid document (refer Clause 8.1) shall be in

two separate parts:

Part I shall be named "Technical Bid" and shall comprise

(i) Bid Security in the form specified in section 8

(ii) Qualification Information and supporting documents as specified in Sect. 2.

(iii) Certificates, undertakings, affidavits as specified in Section 2.

(iv) Any other information pursuant to Claus 4.2 of these instructions.

(v) Undertaking that the bid shall remain valid for the period specified in Cl 15.1.

(vi) Acceptance/ non acceptance of Dispute Review Expert proposed in Cl. 36.1.

Part II shall be named "Financial Bid" and shall comprise

(i) Form of Bid a specified in Section 6.

(ii) Priced Bill of Quantities for items specified in Section 7.

12.2 The bidder shall fill and upload the Technical and Financial bid in ‘edit attachment option’ and shall

upload the supporting document in ‘General Document Option’ of e tendering portal and submit the

bid by using his Class III Digital Signature.

12.3 Following documents, which are not submitted with the bid, will be deemed to be part of the bid.

Section Particulars Volume No.

Invitation for Bids (IFB)

1 Instruction to Bidders

} Volume I 3 Conditions of Contract

4 Contract Data

5 Specifications

} Volume II

6 Drawings

13 Bid Prices.

13.1 The contract shall be for the whole works as described in Sub-Clause 1.1, based on the priced Bill of

Quantities submitted by the Bidder.

13.2 The bidder shall fill rates in ‘Rate Column of BOQ Sheet’ in figures only for all items of the Works

described in the Bill of Quantities. Items for which no rate is entered by the bidder will not be paid

for by the Employer when executed and shall be deemed covered by the other rates and prices in the

Bill of Quantities. Corrections of any, shall be made by crossing out, initialing, dating and rewriting.

13.3 All duties, taxes and other levies payable by the contractor under the contract, or for any other cause

shall be included in the rates, prices and total Bid Price submitted by the Bidder.

Page 18: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

18

Contractor No. of corrections Executive

Engineer

13.4 The rates and prices quoted by the bidder shall be fixed for the duration of the Contract and shall not

be subject to adjustment on any account.

14. Currencies of Bid and Payment.

The unit rates and the prices shall be quoted by the bidder entirely in Indian Rupees. All payments

shall be made in Indian Rupees.

➢ The Rates of Items in schedule "B" / (BOQ) on part II of NIT are including of Taxes, Rates,

Cesses and also inclusive of the livable tax in respect of sale by transfer of property in goods

involved in the execution of works Contract under the provision of rule 58 of the Maharashtra

Value Added Tax Act 2005 for the purpose of levy of

➢ The rates quoted by the Contractor shall be rates excluding sales Tax and all other taxes but

shall include GST that the contractor will have to pay for the performance of this Contract.

➢ GST as per Govt. of Maharashtra Finance Department, Marathi Circular No. GST-2017/case 81/Ûú¸üÖ¬Ö®Ö-1 ¯ÖÏ. ÛÎú. 81 / Ûú¸üÖ¬ÖÖ®Ö-1 Mantralaya, Mummbai-32, Dated. 19.08.2017.

➢ Provisional amount of GST @2% i.e.1% C.G.S.T. + 1% S.G.S.T. will be deducted at Source

(TDS) after the enforcement of Sections 51 of Maharashtra Goods and Services Act. 2017.

15. Bid Validity.

15.1 Bids shall remain valid for a period not less than 120 days after the deadline date for bid submission

specified in Clause 20. A bid valid for a shorter period shall be rejected by the Employer as non-

responsive. In case of discrepancy in bid validity period between that given in the undertaking

pursuant to Clause 12.1 (v) and the Form of Bid submitted by the bidder, the latter shall be deemed to

stand corrected in accordance with the former and the bidder has to provide for any additional security

that is required.

15.2 In exceptional circumstances, prior to expiry of the original time limit, the Employer may request that

the bidders may extend the period of validity for a specified additional period. The request and the

bidder's responses shall be made in writing or by cable. A bidder may refuse the request without

forfeiting his bid security. A bidder agreeing to the request will not be required or permitted to modify

his bid except as provided in 15.3 hereinafter, but will be required to extend the validity of his bid

security for a period of the extension, and in compliance with Clause 16 in all respects.

15.3 In the case of contracts in which the Contract Price is fixed (not subject to price adjustment), in the

event that the Employer requests and the Bidder agrees to an extension of the validity period, the

contract price, if the bidder is selected for award shall be the bid price corrected as follows:

The price shall be increased by the factor of 0.2% for each week or part of a week that has elapsed

from the expiration of the initial bid validity to the date of issue of letter of acceptance to the

successful Bidder.

15.4 Bid evaluation will be based on the bid prices without taking into consideration the above correction.

15.5 Hard copy submitting by contractor.

Tenderer must submit the Hard Copy of online submitted copy of the Concerned Executive

Engineer's Office(as specified below)

a) Documents submitted on time in Envelope No. 1 & 2 are put in separate Envelope as Envelope

No.1 (Technical Bid) and Envelope No.2 (Financial Bid) respectively and sealed properly.

Page 19: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

19

Contractor No. of corrections Executive

Engineer

b) The above two sealed Envelopes No.1 and 2 shall be again put together in one common cover

and sealed. The name of work, online Tender Number, Name and full address of Tenderer with

Mobile Number shall be mentioned on the said common cover marked sealed. Common cover

properly covers corner.

c) The above Common Cover containing Envelope No. 1 & 2 must be submit to the Concerned

Executive Engineer, Maharashtra Maritime Board, Mumbai. Within 03 working days start

form next day of after Closing of Bid Submission Date (During Office Hours) Only.

d) No Delay on account of any cause will be entertained for the receipt said Hard Copy.

e) If Tenderer Fails or neglect to Submit Hard Copy His On-Line offer (Tender) will be Not be

considered for further tendering procedure.

16. Bid Security

16.1 Earnest money of minimum Rs.2,51,000/- shall be paid via online payment gateway mode. After

Tender opening, the EMD of the unsuccessful bidder will be returned to account provided by the

bidder during the bid preparation as given in challan under Beneficiary Account Number.

16.2 Earnest Money in the form of cheques or any other form except above will not be accepted.

16.3 The amount will be refunded to the unsuccessful tenderers on deciding about the acceptance or

otherwise of the tender. In case of successful tenderer, it will be refunded on his paying initial

Security Deposit and completing the tender documents in form B-2.

16.4 Joint Venture Not Allowed .

16.5 The Bid Security of the successful bidder will be discharged when the bidder has signed the

Agreement and furnished the required Performance Security.

16.6 The bid Security may be forfeited.

I/We agree that the offer shall remain open for acceptance for a minimum period of 120 days from

the date fixed for opening of envelope No. 2 (Financial Bid) and thereafter until it is withdrawn by

me/ us by notice in writing duly addressed to the authority opening the tenders and sent by registered

post A.D. or otherwise delivered at the office of such authority. of the sum of Rs.2,51,000/-

representing the earnest money is herewith forwarded. The amount of earnest money shall not bear

interest and shall be liable to be forfeited to the Government, should I/We fail to (I) abide by the

stipulation to keep the offer open for the period mentioned above or (II) Sign and complete the

contract documents as required by the Engineer and furnish the security deposit as specified in item

(d) of the memorandum contained in paragraph (1) above within the time limit laid down in clause (1)

of the annexed General Conditions of contract. The amount of earnest money may be adjusted towards

the security deposit or refunded to me/us if so, desired by me/ us in writing, unless the same or any

part thereof has been forfeited as aforesaid.

16.7 I/We have secured exemption from payment of earnest money after executing the necessary bond in

favour of the Government, a true copy of which is enclosed herewith. Should any occasion for

forfeiture of earnest money for this work arise due to failure on my/our part to (I) abide by the

stipulations to keep the offer open for the period mentioned above or (ii) sign and complete the

contract documents and furnish the security deposit as specified in item (d) of the Memorandum

contained in paragraph (1) above within the time limit laid down in clause (1) of the annexed General

Conditions of Contract, the amount payable by me/us may, at the option of the Engineer, be

recovered out of the amount deposited in lump sum for securing exemption in so far as the same may

extend in terms of the said bond and in the event of the deficiency out of any other payments which

Page 20: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

20

Contractor No. of corrections Executive

Engineer

are due or payable to me/us by the Government under any other contract or transaction of any nature

whatsoever or otherwise.

17. Alternative Proposals by Bidders

17.1 Bidders shall submit offers that fully comply with the requirements of the bidding documents,

including the conditions of contract (including mobilization advance or time for completion), basic

technical design as indicated in the drawing and specifications. Conditional offer or alternative

offers will not be considered further in the process of tender evaluation.

18. Format and Signing of Bid

18.1 The bidder shall be required to fill and upload the Technical and Financial Bid by using his Class III

Digital Signature of the person who is authorised to submit the Bid, uploaded

18.2 The documents are required to be uploaded in “Edit Attachment Option” online. The bidder is

required to ensure that the size of each document does not exceed 5 MB.

18.3 In case Bidder would like to provide any Supporting Document(s) as a part of the Bid Response, the

Bidder may upload such Supporting Document(s) under “General Document Option” of tender.

18.4 CASHLESS

Vide GR No. Govt. Of Maharashtra , Public Works Department. Mantralaya Nagpur No. Tender

2016/CN20/shikana/Bldg -2 dated 09/12/2016 Contractor shall submit a certificate to the effect that

all the payments to the labour / staff are made in bank accounts of staff should linked to Unique

Identification Number ( AADHAR Card) . The certification shall be submitted by the contractor

within 60 days from the commencement of the contract. If the time period of contract is less than 60

days than such certificate shall be submitted within 15 days from the date of commencement of

contract.

Page 21: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

21

Contractor No. of corrections Executive

Engineer

D. SUBMISSION OF BIDS

19. Submission of Bids

19.1 The Bidder shall refer to the "Bidder Manual Kit'' for Preparation and Submission of bid on

'https://mahatender.gov.in' portal.

20. Deadline for Submission of the Bids

20.1 The complete Bids (including Technical and Financial) must be received on e-tendering portal not

later than the date indicated in NIT.

20.2 The Employer may extend the deadline for submission of bids by issuing an amendment in

accordance with Clause 10, in which case all rights and obligations of the Employer and the bidders

previously subject to the original deadline will then be subject to the new deadline.

21. Late Bids

21.1 Any bid submitting the Bid Security and Cost of Tender Fee document in Original after deadline

prescribed in NIT will not be accepted and returned. The bid (including technical and financial) will

not be opened. The complete Bids (including Technical and Financial) must be received by the

Employer online not later than the deadline indicated in the schedule.

22. Modification and Withdrawal of Bids

22.1 The bidder may modify or cancel their bid online only before the deadline prescribed in clause 20

i.e..Bid due date.

Page 22: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

22

Contractor No. of corrections Executive

Engineer

E. BID OPENING AND EVALUATION

23. Bid Opening

23.1 The Employer will open all the Technical Bids received of those tenderer who has submitted the Bid

Security and Cost of Tender Fee document through online before the deadline prescribed in Tender

Schedule, in the presence of the Bidders or their representatives who choose to attend at time, date

and the place specified in Appendix in the manner specified in Clause 20 and 23.2. In the event of the

specified date of Bid opening being declared a holiday for the Employer, the Bids will be opened at

the appointed time and location on the next working day.

23.2 The Online "Technical Bid" shall be opened first. The Bid Security and Cost of Tender Fee

documents uploaded online shall be verified with Original documents submitted by bidders as

required as per NIT. The amount, form and validity of the bid security furnished with each bid will be

announced. If the bid security furnished does not conform to the amount and validity period as

specified in the Invitation for Bid (ref. Column 5 and paragraph 3), and has not been furnished in the

form specified in Clause 16, the remaining technical bid online will not be opened .

23.3 (i) Subject to confirmation of the bid security by the issuing Bank, the bids accompanied with valid

bid security will be taken up for evaluation with respect to the Qualification Information and

other information furnished in Part I of the bid pursuant to Clause 12.1.

(ii) After receipt of confirmation of the bid security, the bidder will be asked in writing/ online

(usually within 10 days of opening of the Technical Bid) to clarify or modify his technical bid,

if necessary, with respect to any rectifiable defects.

(iii) The bidders will respond in not more than 7 days of issue of the clarification letter/online

communication, which will also indicate the date, time and venue of opening of the financial

Bid. (usually on the 21st day of opening of the Technical Bid)

(iv) Immediately (usually within 3 or 4 days) on receipt of these clarifications the Evaluation

Committee will finalize the list of responsive bidders whose financial bids are eligible for

consideration.

23.4 At the time of Online opening of "Financial Bid", the names of the bidders who were found

responsive in accordance with Clause 23.3 (iv) will be announced. The bids of only these bidders will

be opened. The remaining bids will be rejected online. The e-tendering system shall communicate to

the rejected bidders along with reasons for their rejection. The responsive Bidder's names, the Bid

prices, the total amount of each bid, will be announced by the Employer at the opening.

23.5 In case bids are invited in more than one package, the order for opening of the "Financial Bid" shall

be that in which they appear in the "Invitation For Bid".

23.6 The Employer shall prepare minutes of the Bid opening, including the information disclosed to those

present in accordance with Sub-Clause 23.4. result of financial bids of all the Bidders shall be made

available e-tendering portal in option “ tender free View”

24. Process to be Confidential

24.1 Information relating to the examination, clarification, evaluation and comparison of Bids and

recommendations for the award of a contractor shall not be disclosed to Bidders or any other persons

not officially concerned with such process until the award to the successful Bidder has been

announced. Any effort by a Bidder to influence the Employer's processing of Bids or award decisions

may result in the rejection of his Bid.

Page 23: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

23

Contractor No. of corrections Executive

Engineer

25. Clarification of Financial Bids

25.1 To assist in the examination, evaluation and comparison of Bids, the Employer may, at his discretion,

ask any Bidder for clarification of his bid, including breakdowns of unit rates. The request for

clarification and the response shall be in writing but no change in the price or substance of the Bid

shall be sought, offered, or permitted except as required to confirm the correction of arithmetic errors

discovered by the Employer in the evaluation of the Bids in accordance with Clause 27

25.2 Subject to sub-clause 25.1, no Bidder shall contact the Employer on any matter relating to his bid

from the time of the bid opening to the time the contract is awarded. If the Bidder wishes to bring

additional information to the notice of the Employer, it should do so in writing/online.

25.3 Any effort by the Bidder to influence the Employer in the Employer's bid evaluation, bid comparison

or contract award decisions may result in the rejection of the Bidder's bid.

26. Examination of Bids and determination of Responsiveness

26.1 During the detailed evaluation of "Technical Bids" the Employer will determine whether each Bid (a)

meets the eligibility criteria defined in clause 3 and 4. (b) has been properly signed, (c) is

accompanied by the required securities and, (d) is substantially responsive to the requirements of the

Bidding documents. During the detailed evaluation of the "Financial Bid", the responsiveness of the

bids will be further determined with respect to the remaining bid conditions, i.e. priced bill of

quantities, technical specifications and drawings.

26.2 A substantially responsive “Financial Bid” is one, which conforms to all the terms, conditions and

specifications of the Bidding documents, without material deviation or reservation. A material

deviation or reservation is one (a) which affects in any substantial way the scope, quality, or

performance of the Works, (b) which limits in any substantial way, inconsistent, with the Bidding

documents, the Employer’s rights or the Bidder’s obligations under the Contract, or (c) whose

rectification would affect unfairly the competitive position of other Bidders presenting substantially

responsive Bids.

26.3 If a “Financial Bid” is not substantially responsive, it will be rejected by the Employer, and may not

subsequently be made responsive by correction or withdrawal of the non-conforming deviation or

reservation.

27. Correction of Errors

27.1 “Financial Bids” determined to be substantially responsive will be checked by the Employer for any

arithmetic errors. Errors will be corrected by the Employer as follows :

(a) where there is a discrepancy between the rates in figures and in words, the rate in

words will govern ; and

(b) where there is a discrepancy between the unit rate and the line item total resulting

from multiplying the unit rate by the quantity, the unit rate as quoted will govern.

27.2 The amount stated in the “Financial Bid” will be corrected by the Employer in accordance with the

above procedure and the bid amount adjusted with the concurrence of the Bidder in the following

manner :

(a) If the Bid price increases as a result of these corrections, the amount as stated in the

bid will be the ‘bid price’ and the increase will be treated as rebate;

(b) If the bid price decreases as a result of the corrections, the decreased amount will be

treated as the ‘bid price’.

Such adjusted bid price shall be considered as binding upon the Bidder. If the Bidder does not accept

the corrected amount the Bid will be rejected and the Bid Security may be forfeited in accordance

with Sub-Clause 16.6(b).

28. Deleted

Page 24: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

24

Contractor No. of corrections Executive

Engineer

29. Evaluation and Comparison of Financial Bids

29.1 The Employer will evaluate and compare only the Bids determined to be substantially responsive in

accordance with Sub-Clause 26.2.

29.2 In evaluating the Bids, the Employer will determine for each Bid the evaluated Bid Price by adjusting

the Bid Price as follows:

a) Making any correction for errors pursuant to Clause 27; or

(b) Making an appropriate adjustments for any other acceptable variations, deviations; and

(c) Making appropriate adjustments to reflect discounts or other price modifications offered in

accordance with Sub-Clause 23.6.

29.3 The Employer reserves the right to accept or reject any variation or deviation. Variations and

deviations and other factors, which are in excess of the requirements of the Bidding documents or

otherwise result in unsolicited benefits for the Employer shall not be taken into account in Bid

evaluation.

29.4 The estimated effect of the price adjustment conditions under Clause 47 of the Conditions of contract,

during the period of implementation of the Contract, will not be taken into account in Bid evaluation.

29.5 If the Bid of the successful Bidder is seriously unbalanced in relation to the Engineers estimate of the

cost of work to be performed under the contract, the Employer may require the Bidder to produce

detailed price analysis for any or all items of the Bill of Quantities, to demonstrate the internal

consistency of those prices with the construction methods and schedule proposed. After evaluation of

the price analysis, the Employer may require that the amount of the performance security set forth in

Clause 34 be increased at the expense of the successful Bidder to a level sufficient to protect the

Employer against financial loss in the event of default of the successful Bidder under the Contract.

29.6 A bid which contains several items in the Bill of Quantities which are unrealistically priced low and

which cannot be substantiated satisfactorily by the bidder, may be rejected as non-responsive.

30. Deleted.

Page 25: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

25

Contractor No. of corrections Executive

Engineer

F. AWARD OF CONTRACT

31. Award Criteria

31.1 Subject to Clause 32, the Employer will award the Contract to the Bidder whose Bid has been

determined.

(i) To be substantially responsive to the Bidding documents and who has offered the lowest

evaluated Bid price and

(ii) To be within the available bid capacity adjusted to account for his bid price which is

evaluated the lowest in any of the packages opened earlier than the one under consideration.

In no case the contract shall be awarded to any bidder whose available bid capacity is less than the

evaluated bid price, even if the said bid is the lowest evaluated bid. The contract will in such cases be

awarded to the next lowest bidder at his evaluated bid price.

32. Employers Right to accept any Bid and to reject any or all Bids.

32.1 Notwithstanding Clause 31, the Employer reserves the right to accept or reject any bid, and to cancel

the Bidding process and reject all Bids, at any time prior to the award of contract, without thereby

incurring any liability to the affected Bidder or Bidders or any obligation to inform the affected

Bidder or Bidders of the grounds for the Employer’s action.

33. Notification of Award and Signing of Agreement

33.1 The Bidder whose Bid has been accepted will be notified of the award by the Employer prior to

expiration of the Bid validity period by cable, telex or facsimile confirmed by registered letter. This

letter (hereinafter and in the Conditions of Contract called the “Letter of Acceptance”) will state the

sum that the Employer will pay the Contractor in consideration of the execution, completion and

maintenance of the Works by the Contractor as prescribed by the Contract (hereinafter and in the

Contract called the “Contract Price”)

33.2 The notification of award will constitute the formation of the Contract, subject only to the furnishing

of a performance security in accordance with the provisions of Clause 34.

33.3 The Agreement will incorporate all agreements between the Employer and the successful Bidder. It

will be signed by the Employer and sent to the successful Bidder, within 28 days following the

notification of award along with the Letter of Acceptance. Within 21 days of receipt, the successful

Bidder will sign the Agreement and deliver it to the Employer.

33.4 Upon the furnishing by the successful Bidder of the Performance Security, the Employer will

promptly notify the other Bidders that their Bids have been unsuccessful.

34. Performance Security and Additional Performance Security :

Performance Security/ EMD

(i) If the tenderer has quoted the offer below the estimated cost put to tender, the

tenderer shall have to submit Additional Performance Security in the form of D.D. / F.D.R. /

Bank Guarantee of any Nationalised or Scheduled Bank in favour of the Chief Executive

Officer, Maharashtra Maritime Board, Mumbai, payable at Mumbai.

The scanned copy of the Demand Draft (Additional Performance Security) shall be

uploaded and submitted in envelop no.2 through e-tendering process. It is mandatory to each

tenderer that he shall submit sealed envelope bearing name of agency, name of work and

Page 26: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

26

Contractor No. of corrections Executive

Engineer

tender notice number which contains the original D.D. / F.D.R. / Bank Guarantee (for which

the photocopy has been submitted online as above) or Slip mentioning “Not Applicable” (If

offer is not below the estimate cost). The envelope shall be submitted to office of the

Executive Engineer within 5 working days from the last date prescribed for the receipt of

tender. Also a self attested affidavit that additional performance security is enclosed in

envelope No.1 (Technical envelope) If the additional performance security is not found

including in Envelope No.2 ( Financial Envelope). The offer shall be treated as non

responsive.

.

(ii)The person/persons whose tender may be accepted (hereinafter called

the Contractor, which expression shall unless excluded by or repugnant to

the context include his heirs, executors, administrators, and assigns ) shall

(A) within 10 days (which may be extended by Superintending Engineer

concerned up to 15 days if Superintending Engineer thinks fit to do so) of

the receipt by him of the notification of the acceptance of his tender

deposit with the Executive Engineer in cash or Government securities

endorsed to the Executive Engineer (if deposited for more than 12 months)

of the sum sufficient which will made up the full security deposit specified

in the tender or (B) (Permit Government at the time of making any

payment to him for work done under the contract to deduct such as will

amount to * FOUR percent of all moneys so payable such deductions to

be held by Government by way of security deposit. ) Provided always that

in the event of the Contractor depositing a lump sum by way of security

deposit as contemplated at above, then and in such case, if the sum so

deposited shall not amount to FOUR percent of the total estimated cost of

the work, it shall be lawful for Government at the time of making any

payment to the Contractor for work done under the contract to make up the

full amount of FOUR percent by deducting sufficient sum from every

such payment as last aforesaid until the full amount of the security deposit

is made up. All compensation or other sums of money payable by the

Contractor to Government under the terms of his contract may be deducted

from or paid by the sale of sufficient part of his security deposit or from

the interest arising there form , or from any sums which may be due or

may become due by Government to the Contractor under any other

contract or transaction of any nature on any account whatsoever and in the

Page 27: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

27

Contractor No. of corrections Executive

Engineer

event of his security deposit being reduced by reason of any such

deduction or sale as aforesaid, the Contractor shall within ten days

thereafter, make good in cash or Government securities endorsed as

aforesaid any sum or sums which may have been deducted from, or raised

by sale of his security deposit or any part thereof. The security deposit

referred to, when paid in cash may, at the cost of the depositor, be

converted into interest bearing securities provided that the depositor has

expressly desired this in writing.

The security deposit will not be accepted in forms of insurance company

bonds as per Government orders contained in No. CCM/PWD/4250

DATED 27/12/1956.

_______________________________________________

Note: This will be the same percentage as that in the tender

If the amount of the security deposit be paid in a lump sum within

the period specified at (A) above is not paid the tender/contract

already accepted shall be considered as cancelled and legal steps

taken against the Contractor for recovery of the amounts. The

amount of the security deposit lodged by a Contractor shall be

refunded along with the payment of the final bill, if the date up to

which the Contractor has agreed to maintain the work in good order

is over. If such date is not over, only 50% amount of security

deposit shall be refunded along with the payment of the final bill.

The amount of security deposit retained by the Government shall be

released after expiry of period up to which the Contractor has

agreed to maintain the work in good order is over. In the event

of the Contractor failing or neglecting to complete rectification

work within the period up to which the Contractor has agreed to

maintain the work in good order, then the amount of Security

Deposit retained by Government shall be adjusted towards the

excess cost incurred by the Department on rectification work.

Additional Performance Security

If the tenderer has quoted the offer below the estimated cost put to tender, the

tenderer shall have to submit Additional Performance Security in the form of Demand

Draft (DD) of any Nationalised or Scheduled Bank in favour of the Chief Executive

Officer, Maharashtra Maritime Board, payable at Mumbai.

The scanned copy of the Demand Draft (DD) (Additional Performance Security)

shall be uploaded and submitted in envelop no.2 through e-tendering process. (Page

No.148) It is mandatory to each tenderer that he shall submit sealed envelope bearing

name of agency, name of work and tender notice number which contains the original

Page 28: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

28

Contractor No. of corrections Executive

Engineer

Demand Draft (DD) (for which the photocopy has been submitted online as above) or Slip

mentioning “Not Applicable” (If offer is not below the estimate cost). The envelope shall

be submitted to office of the Chief Executive Officer within 5 working days from the last

date prescribed for the receipt of tender.

The amount of the (Additional Performance Security) Demand Draft (DD) shall be

calculated by the tenderer in accordance with the following manner.

If the Tenderer is below the Scheduled cost more thann1% it is mandatory to upload

online, the Scanned Copy of Original D.D. in the name of The Chie Executive Officer,

Maharashtra Maritime Board, drawn on Nationalized /Scheduled Bank. D.D. should be valid

for 3 months from the date of submission of the tender in ENVELOPE NO.2 against the

Additional Performance Security Deposited. The Amount of D.D. shall be as per

G.R.No.¤ÉÒb÷ÒVÉÒ2016/|É.úGò.2/<¨ÉÉ- 2,ÊnùxÉÉÆEò12.02.2016 & Govt. Corrigendum No ÃÖß‹™üß /2017 /¯ÖÏ.

08 /‡´ÖÖ.-2, פü. ú 29/06/2017 reproduced on page No. 75-77 & Amendment Dt.17.03.2016. The

Original D.D. along with the hard copy of the tender shall be submitted in the office of the

Executive Engineer within 72 Hrs. from time of bid lock of the tender. The details of

performance security deposit for below tender are given in Clause No.1.5 & 1.9.B on page No.

12, 13 & 14 of this D.T.P.

34.1 If the tenderer has quoted below the estimated rates, the Additional Performance Security

shall be paid additionally as mentioned below.

If the offer submitted is below schedule

“B” rates by more than 1% but less than

10% of the estimated cost put to tender

1% of the estimated cost put to tender

If below by more than 10% of the

estimated cost put to tender

1% of the estimated cost put to tender plus an

amount equal to the percentage by which the

offer is below 10% of the estimated cost put to

tender. (e.g. if the offer is 15.31% below, the

Performance Security will be 1%+(15.31-10) =

6.31% of the estimated cost put to tender.

34.2 The Demand Draft (DD) shall be valid upto 3 months from the date of submission of the

tender.

34.3 After opening the envelope no.1, if it is found that the tenderer is not qualified for opening

his envelope no.2, then his Demand Draft (DD) shall be returned within 7 working days.

Also after opening envelope no.2, except the Demand Draft (DD). of 1st and 2nd lowest

bidders, the Demand Draft (DD). of other bidders shall be returned within 7 working days.

34.4 Demand Draft (DD) of the 2nd lowest bidder shall be returned within 3 working days after

issue of work order to the 1st lowest bidder.

Page 29: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

29

Contractor No. of corrections Executive

Engineer

34.5 In case it is found that the documents/ Demand Draft (DD) submitted by the tenderer are

false or misleading, his earnest money shall be forfeited. Also the registration of the tenderer

shall be suspended for the period of 1 year. Additionally legal action may be initiated

against the tenderer.

34.6 The work order shall be given to the concerned tenderer after the clearance of the Demand

Draft (DD) submitted by him.

Refund of Additional Performance Security.

34.7 The amount of the Additional performance security shall be refunded as per the G.R.No.

Government of Maharashtra, Public Works Department, Mantralaya, Mumbai No.BDG

2016/C.R.2/Bldg-2, Dated 1/04/2017 (i.e. after Completion of Defect Liability Period).

34.8 Non submission of Additional performance security or submission of less amount of the

Additional Performance Security shall be liable to summarily rejection of his tender.

35. Advance Payment and Security

35.1 The Employer will provide an Advance Payment on the Contract Price as stipulated in the Conditions

of Contract, subject to maximum amount, as stated in the Contract Data.

36. Dispute Review Expert

36.1 Except where otherwise specified in the contract and subject to the powers delegated to him

by Government under the code, rules then in the force, the decision of the Superintending

Engineer of the Circle for the time being shall be final, conclusive and binding on all parties

of the contract upon all questions relating to the meaning of the specifications, designs,

drawings and instruction hereinbefore mentioned and as to the quality of workmanship or

materials used on the work, or as to any other question, claim right, matter or things

whatsoever, if any way arising out of, or relating to the contract, designs, drawings,

specifications, estimates , instructions, orders, or other conditions, or otherwise concerning

the works, or the execution, or failure to execute the same, whether arising during the

progress of the work, or after the completion or abandonment thereof.

36.2 The Contractor may within thirty days of receipt by him of any order passed by the

Superintending Engineer of the Circle as aforesaid appeal against it to the Chief Engineer,

concerned with the contract work or project provided that -

(a) The accepted value of the contract exceeds Rs. 10 lakhs

(Rupees Ten lakhs)

(b) Amount of claim is not less than Rs. 1.00 Lakh

(Rupees One Lakh).

36.3 If the Contractor is not satisfied with the order passed by the Chief Engineer as aforesaid,

the Contractor may, within thirty days of receipt by him of any such order appeal against it

to the concerned Secretary, Public Works Department/Irrigation Department who, if

convinced that Prima-facie the Contractors claim rejected by Superintending Engineer/Chief

Engineer is not frivolous and that there is some substance in the claim of the Contractor as

Page 30: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

30

Contractor No. of corrections Executive

Engineer

would merit a detailed examination and decision by the Standing Committee, shall put up to

the Standing Committee at Government level for suitable decision

(Vide PW Circular No. CAT-1086-CR-110/Bldg.2 Dated 7.5.1986).

37. Corrupt or Fraudulent Practices

37.1 The Employer will reject a proposal for award if it determines that the Bidder recommended for award

has engaged in corrupt or fraudulent practices in competing for the contract in question and will

declare the firm ineligible, either indefinitely or for a stated period of time, to be awarded a contract

with National Highways Authority of India / State PWDNH and any other agencies, if it at any time

determines that the firm has engaged in corrupt or fraudulent practices in competing for the

contractor, or in execution.

37.2 Furthermore, Bidders shall be aware of the provision stated in Sub-Clause 23.2 and Sub-Clause 59.2

of the Conditions of Contract.

Page 31: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

31

Contractor No. of corrections Executive

Engineer

APPENDIX TO ITB

Clause Reference

With respect to

Section – I.

1. Name of the Employer is Chief Executive Officer, Maharashtra

Maritime Board, Indian Mercantile Chamber, 3rd floor, Ramjibhai

Kamani Marg, Ballard Estate, Mumbai-400 001

[ Cl. 1.1]

2. The last five years

2017-2018

2016-2017

2015-2016

2014-2015

2013-2014

3. The Average annual financial turnover amount is Rs 2,50,64,000.00

during last three years ( FY 2014-15 , 2015-16, 2016-17) at the

price level of 2017-2018.

[Cl. 4.3.3(a)]

4.

Value of proposed for Satisfactorily completed as a contractor, at

least one similar type of work, Construction of value Rs.

1,50,38,400.00 at the price level of 2017-2018

[Cl. 4.3.3(b)]

5.

Quantity of work are : As per Section 1- Instructions to Bidders,

Clause No. 4.3.3 (d) Page No. 10.

6.

7.

8.

Liquid assets and/or availability of credit facilities is is Rs. ________

(Rupees ________________________________________ only)

Price level of financial year 2017-18

The Pre-bid meeting at Date.18.05.2018 at 15.00 hrs, Maharashtra

Maritime Board, Indian Mercantile Chamber, 3rd floor, Ramjibhai Kamani Marg, Ballard Estate, Mumbai-400 001.

[Cl.4.3.6]

[Cl. 4.3.2]

[Cl. 9.2.1]

9. The technical bid will be opened (if Possible) online at the Office

of the Chief Executive Officer, Maharashtra Maritime Board,

Indian Mercantile Chamber, 3rd floor, Ramjibhai Kamani Marg,

Ballard Estate, Mumbai-400 001 on dt 04.06.2018 at 15.00

Hours.

10. Address of the Employer

Chief Executive Officer,

Maharashtra Maritime Board,

Indian Mercantile Chamber, 3rd floor,

Ramjibhai Kamani Marg,

Ballard Estate,

Mumbai-400 001

11. Identification :

Bid for -

Bid Reference : No. ____________

Do not open before 04.06.2018 up to 15.00 hours

Page 32: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

32

Contractor No. of corrections Executive

Engineer

12. The bid should be submitted latest by 01.06.2018 on or before 17.00

hours.

[Cl. 20.1]

13. The Financial bid will be opened after technical scrutiny at place

Chief Executive Officer, Maharashtra Maritime Board, Indian Mercantile Chamber,

3rd floor, Ramjibhai Kamani Marg, Ballard Estate, Mumbai-400 001.

[Cl.23.3(iii)]

14. The Demand Draft (DD) of any Nationalised or Scheduled Bank in

favour of the Chief Executive Officer, Maharashtra Maritime

Board.

[Cl.34]

15.

The name of Dispute Review Expert is (to be notified later) [Cl.36.1]

16. Escalation factors (for the cost of works executed and financial figure to

a common base value for works completed)

Year before Multiply factor

One 1.10

Two 1.21

Three 1.33

Four 1.46

Five 1.61

Page 33: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

33

Contractor No. of corrections Executive

Engineer

SECTION – 2

QUALIFICATION INFORMATION

The information to be filled in by the bidder in the following pages will be used for purposes

of post qualification as provided for in clause 4 of the Instructions to bidders. This information will

not be incorporated in the contract

1. For Individual Bidders

1.1 Constitution or legal status of Bidder

(Attach Copy)

Place of registration: ----------------------------------

Principal place of business: ----------------------------------

Power of attorney of signatory of bid

(Attach)

1.2 Total value of civil Engineering

1.3 Construction work performed in the last three years.

2016-2017………………….

2015-2016…………………

2014-2015…………………..

(Rupees in Crore)

1.3.1 Work performed as prime contractor, work performed in the past as a nominated sub-

contractor will also be considered provided the Sub-contract involved execution of all main

items of work described in the bid document, provided further that all other qualification

criteria are satisfied (in the same name) on works of a similar nature over the last Three

years.**

Project

Name

Name of

the

Employer

*

Description

of work

Contract

No.

Value of

Contract

(Rs.

Crore)

Date of

Issue of

work

order

Stipulated

period of

completion

Actual date

of

completion

*

Remarks

explaining

reasons for

delay &

work

completed

* Attach certificate(s) from the Engineer(s)-in-charge.

** Immediately preceding the financial year in which bid are received.

β Attach certificate(s) from Chartered Accountant.

# 1.3.2 Quantities of work executed as prime contractor, be considered provided in the bid

document, provided further that other qualification criteria are satisfied (in the same name and style) in

the last three years.**

Page 34: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

34

Contractor No. of corrections Executive

Engineer

Year

Name

of the

work

Name of the

Employer*

Quantity of work performed (Cum) @ Remarks

Remarks*

(indicate

Ref.) Pile

Foundation

Concrete

Steel

Bar

Concrete

Block

(Auto

Clave

Cellular)

Tiles

Flooring

RCC

Quantity

2014-15

2015-16

2016-17

1.4 Information on Bid capacity (works for which bids have been submitted and works which are yet

to be completed) as on the date of this bid.

(A) Existing commitments and on-going works :

Descript

ion of

work

place &

State

Contract

No.

Name &

Address of

employer

Value of

Contract

(Rs. Cr.)

stipulated

period of

completio

n

Value of

works*

remaining

to be

completed

(Rs. Cr.)

Anticipate

d date of

completion

.

1 2 3 4 5 6 7 8

* Attach certificate(s) from the Engineer(s)-in-charge.

@ The item of works for which data is requested should tally with that specified in ITB clause 4.5A(C).

** Immediately preceding the financial year in which bid are received.

# Deleted.

Page 35: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

35

Contractor No. of corrections Executive

Engineer

(B) Works for which bids already submitted:

Description

of work

Place &

State

Name and

Address

of

Employer

Estimated

value of

Works

( Rs. Cr. )

Stipulated

period of

completion

Date when

decision is

expected

Remark,

if any

1 2 3 4 5 6 7

1.5 Availability of key items of Contractor’s Plant &Equipment essential for carrying out the Works

[Ref. Clause 4.4.5]. The Bidder should list all the information requested below. Refer also to Sub-

Clause 4.3(d) of the Instructions to Bidders.

Item of Plant

&Equipment

Requirement

Availability Proposal Remark (from

whom to be

purchased) No. Capacit

y

Owned Nos./

Capacity

Age /

Condition

1.6 Qualification and experience of key personnel required for administration and execution of the

contract [Ref. 4.5.5]. Attach biographical data. Refer also to Sub-Clause 4.3 (e) of instructions to

Bidders and Sub Clause 9.1 of the Conditions of Contract.

Position Name Qualification Year of

Experience

(General)

Year of Experience in

the proposed

position.

Project Manger

Site Engineer

Plant Engineer

Quantity Surveyor

Soil & Material

Engineer

Design/Survey

Engineer

Site Supervisor

Office Assistant

1.8 Financial reports for the last Three years: balance sheets, profit & loss statements, auditor’s reports (in

case of companies /corporation) etc. List them below and attach copies.

Page 36: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

36

Contractor No. of corrections Executive

Engineer

1.9 Evidence of access to financial resources to meet the qualification requirements: cash in hand. Lines

of credit etc. List them below and attach copies of support documents.

1.10 Name, address and telephone, telex and fax numbers of the bidder’s bankers who may provide

reference if contacted by the Employer.

1.11 Information on litigation history in which the bidder is involved.

Other party (ies) Employer Cause of

Dispute

Amount involved Remarks showing

present status

1.12 Statement compliance under the requirements of Sub Clause 3.2of the instructions to Bidders. (Name

of Consultant engaged for project preparation is ** -------------------------------------------------------------

--------------------------------------------------------------------------------------------------------------

2 Deleted

3 Additional Requirements

3.1 Bidders should provide any additional information required to fulfil the requirements of clause 4 of

the Instructions to the Bidders, if applicable.

(iv) Affidavit

(v) Undertaking.

(vi) Affidavit additional performance security must be enclosed.

Page 37: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

37

Contractor No. of corrections Executive

Engineer

AFFIDAVIT

1. I, the undersigned, do hereby certify that all the statements made in the required attachments are

true and correct.

2. The undersigned also hereby certifies that neither our firm M/s. ____________

___________________________ have not abandoned any work on Maharashtra Maritime Board

/ Public Work Department nor any contract awarded to us for such works have not been

rescinded, during last five years prior to the date of this bid.

3. The undersigned hereby authorise(s) and request(s) any bank, person, firm or corporation to

furnish pertinent information deemed necessary and requested by the Department to verify this

statement or regarding my (our) competence and general reputation.

4. The undersigned understand and agrees that further qualifying information may be requested and

agrees to furnish any such information at the request of the Department / Project implementing

agency.

_________________(Signed by Authorised Officer of the Firm)

___________________

Name Title of Officer

____________________

Name of Firm

______________

DATE

Page 38: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

38

Contractor No. of corrections Executive

Engineer

UNDERTAKING

I, the undersigned, do hereby undertake that our firm M/s. __________________________________

would invest minimum cash up to 25 % of the value of work during implementation of the Contract.

__________________

(Signed by Authorised Officer of the Firm)

___________________

Name Title of Officer

____________________

Name of Firm

______________

DATE

Page 39: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

39

Contractor No. of corrections Executive

Engineer

SECTION – 3

CONDITIONS OF CONTRACT

Page 40: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

40

Contractor No. of corrections Executive

Engineer

CONDITIONS OF CONTRACT

A.GENERAL

1. Definitions

1.1 Terms which are defined in the Contract Data are not also defined in the Conditions of Contract but

keep their defined meanings. Capital initial are used to identify defined terms.

The Adjudicator (Synonymous with Dispute Review Expert) is the person appointed jointly by the

Contractor to resolve disputes in the first instance, as provided for in clauses 24. The name of the

Adjudicator is defined in the Contract Data.

Bill of Quantities means the priced and completed Bill of Quantities forming part of the Bid.

Compensation Events are those defined in Clause 44 hereunder.

The Completion Date is the date of completion of the Works as certified by the Engineer in

accordance with Sub Clause 55.1.

The Contract is the contract between the Employer and the Contractor to execute, complete and

maintain the works. It consists of the documents listed in Clause 2.3 below.

The Contract Data defines the documents and other information which comprise the Contract.

The Contractor is a person or corporate body whose Bid to carry out the Works has been accepted by

the Employer.

The Contractor's Bid is the completed Bidding document submitted by the Contractor to the

Employer and includes Technical and Financial bids.

The Contract Price is the price stated in the Letter of Acceptance and thereafter as adjusted in

accordance with the provisions of the Contract.

Day are calendar days; months are calendar months.

A Defect is any part of the Works not completed in accordance with the Contract.

A Defects Liability Period is the period named in the Contract Data and calculated from the

Completion Date.

The Employer is the party who will employ the Contractor to carry out the Works.

The Engineer is the person named in the Contract Data (or any other competent person appointed and

notified to the contractor to act in replacement of the Engineer) who is responsible for supervising the

Contractor, administering the Contract, certifying payments due to the Contractor, issuing the valuing

Variations to the Contract, awarding extensions of time and valuing the Compensation Events.

Equipment is the Contractor's machinery and vehicles brought temporarily to the Site to construct the

Works.

The Initial Contract Price is the Contract Price listed in the Employer's Letter of Acceptance.

The Intended Completion Date is the date on which it is intended that the Contractor shall complete

the Works. The Intended Completion Date is specified in the Contract Data. The intended Completion

Date may be revised only by the Engineer by issuing an extension of time.

Page 41: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

41

Contractor No. of corrections Executive

Engineer

Materials are all supplies, including consumables, used by the contractor for incorporation in the

Works.

Plant is any integral part of the Works which is to have a mechanical, electrical, electronic or

chemical or biological function.

The Site is the area defined as such in the Contract Data.

Site Investigation Reports are those which were included in the Bidding documents and are factual

interpretative reports about the surface and sub-surface conditions at the site.

Specification means the Specification of the Works included in the Contract and any modification or

addition made or approved by the Engineer.

The Start Date is given in the Contract Data. It is the date when the Contractor shall commence

execution of the Works. It does not necessarily coincide with any of the Site Possession Dates.

A Subcontractor is a person or corporate body who has a Contract with the Contractor to carry out a

part of the work in the Contract which includes work on the Site.

Temporary Works are works designed, constructed, installed and removed by the Contractor which

are needed for construction or installation of the Works.

A variation is an instruction given by the Engineer, which varies the Works.

The Works are what the Contract requires the Contractor to construct, install and turn over to the

Employer, as defined in the Contract Data.

2. Interpretation

2.1 In interpreting these Conditions of Contract, singular also means plural, male also means female or

neuter, and the other way around. Headings have no significance. Words have their normal meaning

under the language of the Contract unless specifically defined. The Engineer will provide instructions

clarifying queries about the Conditions of Contract.

2.2 If sectional completion is specified in the Contract Data, references in the Conditions of Contract to

the Works, the Completion Date, and the Intended Completion Date apply to any Section of the

Works (other than references to the Completion Date and Intended Completion date for the whole of

the Works)

2.3 The documents forming the Contract shall be interpreted in the following order of priority:

(1) Agreement

(2) Letter of Acceptance, notice to proceed with the works.

(3) Contractor's Bid

(4) Contract Data

(5) Conditions of Contract including Special Conditions of Contract

(6) Specifications

(7) Drawings

(8) Bill of Quantities and

(9) Any other document listed in the Contract Data as forming part of Contract.

3. Language and Law

3.1 The language of the Contract and the law governing the Contract are stated in the Contract Data

Page 42: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

42

Contractor No. of corrections Executive

Engineer

4. Engineer's Decisions

4.1 Except where otherwise specifically stated, the Engineer will decide contractual matters between the

Employer and the Contractor in the role representing the Employer.

5. Delegation

5.1 The Engineer may delegate any of his duties and responsibilities to other people except to the

Adjudicator after notifying the Contractor and may cancel any delegation after notifying the

Contractor.

6. Communications

6.1 Communications between parties which are referred to in the conditions are effective only when in

writing. A notice shall be effective only when it is delivered (in terms of India Contract Act).

7. Sub-Contracting - DELETED

8. Other Contractors

8.1 The Contractor shall co-operate and share the Site with other contractors, public authorities,

utilities and the Employer between the dates given in the Schedule of other Contractors. The

Contractor shall as referred to in Contract Data; also provide facilities and services for them as

described in the Schedule. The employer may modify the schedule of other contractors and shall

notify the contractor of any such modification.

9. Personnel

9.1 The Contractor shall employ the key personnel named in the Schedule of Key Personnel as referred to

in the Contract Data to carry out the functions stated in the Schedule or other personnel approved by

the Engineer. The Engineer will approve any proposed replacement of key personnel only if their

qualifications, abilities and relevant experience are substantially equal to or better than those of the

personnel listed in the Schedule.

9.2 If the Engineer asks the Contractor to remove a person who is a member of the Contractor's staff or

his work force stating the reasons the Contractor shall ensure that the person leaves the Site within

seven days and has no further connection with the work in the Contract.

10. Employer's and Contractor's Risks

10.1 The Employer carries the risks which this Contract states are Employer's risks, and the Contractor

carries the risks, which this Contract states are Contractor's risks.

11. Employer's Risks

11.1 The Employer is responsible for the excepted risks which are (a) in so far as they directly affect the

execution of the Works in India, the risks of war, hostilities, invasion, act of foreign enemies,

rebellion, revolution, insurrection or military or usurped power, civil war, riot commotion or disorder

(unless restricted to the Contractor's employees), and contamination from any nuclear fuel or nuclear

waste or radioactive toxic explosive, or(b) a cause due solely to the design of the Works, other than

the Contractor's design.

Page 43: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

43

Contractor No. of corrections Executive

Engineer

12. Contractor's Risks

12.1 All risks of loss of or damage to physical property and of personal injury and death which arise during

and in consequence of the performance of the Contract other than the excepted risks are the

responsibility of the Contractor.

13. Insurance

13.1 The Contractor shall provide, in the joint names of the Employer and the Contractor, insurance cover

from the Start Date to the end of the Defects Liability Period, in the amounts and deductibles stated in

the Contract Data for the following events which are due to the Contractor's risks.

(a) Loss of or damage to the Works. Plant and Materials:

(b) Loss of or damage to Equipment:

(c) Loss of or damage of property (except the Works, Plant, Materials and Equipment)

in connection with the Contract; and

(d) Personal injury or death.

13.2 (Contractor shall take out necessary Insurance Policy / Policies (viz. Contractors' All Risks

Insurance Policy, Erection All Risks Insurance Policy etc. as decided by the Directorate of

Insurance) so as to provide adequate insurance cover for execution of the awarded contract work for

total contract value and complete contract period compulsorily from the "Directorate of Insurance,

Maharashtra State, Mumbai" only, Its postal address for correspondence is "264, MHADA, First

floor, Opp. Kalanagar, Bandra (E), Mumbai-400051". (Telephone Number26590403 / 26590690

and Fax Number 26592461 / 26590403). Similarly all workmen's appointed to complete the contract

work are required to insure under workmen's compensation Insurance Policy, Insurance Policy /

Policies taken out from any Insurance Company, the same will not be accepted and the amount of

premium calculated by the Government Insurance Fund will be recovered directly from the amount

payable to the contractor for the executed contract work and paid to the Directorate of Insurance

Fund, Maharashtra State, Mumbai. The Director of Insurance reserves the right to distribute the risks

of insurance among the other insurers. (As per revised circulate issued by Dy. Directorate of

Insurance Maharashtra State vide letter No. |ÉÉÊ´ÉÊxÉ-2310/ºÉÉ.¤ÉÉÆ.Ê´É/ʴɨÉÉ.´ÉºÉÖ±ÉÒ/+ʦÉ-3/ dated 8.9.2010

below mentioned percentage for insurance of contract work shall be added in the recapitulation sheet

while framing the estimate as it is not considered in the D.S.R. while arriving at rates and the

amount incurred by contractors for insurance of work shall be reimbursed on production of

documentary evidence and after checking

a) Work value upto Rs. 25.00 lakhs - 0.50% b) Work value above Rs. 25.00 lakhs = 1.00%.)

13.3 Policies and certificates for insurance shall be delivered by the Contractor to the Engineer for the

Engineer's approval before the Start Date. All such insurance shall provide for compensation to be

payable in the types and proportions of currencies required to rectify the loss or damage incurred.

13.4 If the Contractor does not provide any of the policies and certificates required, the Employer may

affect the insurance which the Contractor should have provided and recover the premiums the

Employer has paid from payments otherwise due to the Contractor or, if no payment is due, the

payment of the premiums shall be a debt due.

13.5 Alterations to the terms of insurance shall not be made without the approval of the Engineer.

13.6 Both parties shall comply with any conditions of the insurance policies.

13.7 CESS ON BUILDING & CONSTRUCTION LABOUR WELFARE

Page 44: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

44

Contractor No. of corrections Executive

Engineer

An amount of equal to one percent on amount of tendered amount shall be deducted from the payment of

contractor as a cess on building & construction labour welfare. The deducted amount shall be remitted in to

account number 00422010000153 in the Bank of India of Chairman, Maharashtra Building & Other

construction labour welfare circle, Mumbai.

14. Site Investigation reports

14.1 The contractor, in preparing the Bid, shall rely on any Site Investigation Reports referred to in the

Contract Data, supplemented by any information available to the Bidder.

15. Queries about the Contract Data

15.1 The Engineer will clarify queries on the Contract Data.

16. Contractor to Construct the Works

16.1 The Contractor shall construct and install the Works in accordance with the Specification and

Drawings.

17. The Works to be completed by the Intended Completion Date

17.1 The Contractor may commence execution of the Works on the Start Date and shall carry out the

Works in accordance with the programme submitted by the contractor, as updated with the approval

of the Engineer, and complete them by the Intended Completion Date.

18. Approval by the Engineer

18.1 The Contractor shall submit Specifications and Drawings showing the proposed Temporary Works to

the Engineer, who is to approve them if they comply with the Specifications and Drawings.

18.2 The Contractor shall be responsible for design of Temporary Works.

18.3 The Engineer's approval shall not alter the Contractor's responsibility for design of the Temporary

Works.

18.3 The Contractor shall obtain approval of third parties to the design of the Temporary Works where

required.

18.5 All Drawings prepared by the Contractor for the execution of the temporary or permanent Works, are

subject to prior approval by the Engineer before their use.

19. Safety

19.1 The Contractor shall be responsible for the safety of all activities on the Site.

20. Discoveries

20.1 Anything of historical or other interest or of significant value unexpectedly discovered on the Site is

the property of the Employer. The Contractor is to notify the Engineer of such discoveries and carry

out the Engineer's instructions for dealing with them.

21. Possession of the Site

21.1 The Employer shall give possession of all parts of the Site to the Contractor. If possession of a part is

not given by the date stated in the Contract Data the Employer is deemed to have delayed the start of

the relevant activities.

22. Access to the Site

Page 45: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

45

Contractor No. of corrections Executive

Engineer

22.1 The Contractor shall allow the Engineer and any person authorized by the Engineer access to the Site,

to any place where work in connection with the Contract is being carried out or is intended to be

carried out and to any place where materials or plant are being manufactured/fabricated/assembled for

the works.

23. Instructions

23.1 The contractor shall carry out all instructions of the Engineer pertaining to works which comply with

the applicable laws where the Site is located.

23.2 The Contractor shall permit the Employer to inspect the Contractor's accounts and records relating to

the performance of the Contractor and to have them audited by auditors appointed by the Employer, if

so required by the Employer.

24. Disputes

DELETED

25. Procedure for Disputes

DELETED

26. Replacement of Dispute Review Expert

DELETED

* Dispute Review Expert to be provided for works costing up to Rs. 50 Crores. Dispute Review

Board of three members (One from Employer, One from Contractor and One to be nominated by IRC

Council and agreed by the representative members of Employer and Contractor) for works costing

more than Rs. 50 crores.

Page 46: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

46

Contractor No. of corrections Executive

Engineer

B. TIME CONTROL

27. Programme

27.1 Within the time stated in the Contract Data the Contractor shall submit to the Engineer for approval a

Programme showing the general methods, arrangements, order and timing for all the activities in the

Works along with monthly cash flow forecast.

27.2 An update of the Programme shall be a Programme showing the actual progress achieved on each

activity and the effect of the progress achieved on the timing of the remaining work including any

changes to the sequence of the activities.

27.3 The contractor shall submit to the Engineer, for approval, an updated Programme at intervals no

longer than the period stated in the Contract Data. If the Contractor does not submit an updated

Programme within this period, the Engineer may withhold the amount stated in the Contract Data

from the next payment certificate and continue to withhold this amount until the next payment after

the date on which the overdue Programme has been submitted.

27.4 The Engineer's approval of the Programme shall not alter the Contractor's obligations. The Contractor

may revise the Programme and submit it to the Engineer again at any time. A revised Programme is to

show the effect of Variations and Compensation Events.

28. Extension of the Intended Completion Date

28.1 The Engineer shall extend the Intended Completion Date if a Compensation Event occurs or a

Variation is issued which makes it impossible for Completion to be achieved by the Intended

Completion Date without the Contractor taking steps to accelerate the remaining work and which

would cause the Contractor to incur additional cost.

28.2 The Engineer shall decide whether and by how much to extend the Intended Completion Date within

35 days of the Contractor asking the Engineer for a decision upon the effect of a Compensation Event

or Variation and submitting full supporting information. If the Contractor has failed to give early

warning of a delay or has failed to co-operate in dealing with a delay, the delay by this failure shall

not be considered in assessing the new Intended Completion Date.

28.3 The Engineer shall within 14 days of receiving full justification from the contractor for extension of

Intended Completion Date refer to the Employer his decision. The Employer shall in not more than 21

days communicate to the Engineer the acceptance or otherwise of the Engineer's decision. If the

Employer fails to give his acceptance, the Engineer shall not grant the extension and the contractor

may refer the matter to the Dispute Review Expert under Clause 24.1

29. Deleted

30. Delays Ordered by the Engineer

30.1 The Engineer may instruct the Contractor to delay the start or progress of any activity within the

Works.

31. Management Meetings

31.1 Either the Engineer or the Contractor may require the other to attend a management meeting. The

business of a management meeting shall be to review the plans for remaining work and to deal with

matters raised in accordance with the early warning procedure.

31.2 The Engineer shall record the business of management meetings and is to provide copies of his record

to those attending the meeting and to the Employer. The responsibility of the parties for actions to be

taken is to be decided by the Engineer either at the management meeting or after the management

meeting and stated in writing to al who attended the meeting.

Page 47: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

47

Contractor No. of corrections Executive

Engineer

32. Early Warning

32.1 The Contractor is to warn the Engineer at the earliest opportunity of specific likely future events or

circumstances that may adversely affect the quality of the work, increase the Contract Price or delay

the execution of works. The Engineer may require the Contractor to provide an estimate of the

expected effect of the future event or circumstance on the Contract Price and Completion Date. The

estimate is to be provided by the Contractor as soon as reasonably possible.

32.2 The Contractor shall co-operate with the Engineer in making and considering proposals for how the

effect of such an event or circumstance can be avoided or reduced by anyone involved in the work

and in carrying out any resulting instruction of the Engineer.

Page 48: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

48

Contractor No. of corrections Executive

Engineer

C. QUALITY CONTROL

33. Identifying Defects

33.1 The Engineer shall check the Contractor's work and notify the Contractor of any Defects that are

found. Such checking neither shall not affect the Contractor's responsibilities. The Engineer may

instruct the Contractor to search for a Defect and to uncover and test any work that the Engineer

considers may have a Defect.

34. Tests

34.1 If the Engineer instructs the Contractor to carry out a test not specified in the Specification to check

whether any work has a Defect and the test shows that it does, the Contractor shall pay for the test and

any samples. If there is no Defect the test shall be a Compensation Event.

35. Correction of Defects

35.1 The Engineer shall give notice to the Contractor of any Defects before the end of the Defects Liability

Period, which begins at Completion and is defined in the Contract Data. The Defects Liability Period

shall be extended for as long as Defects remain to be corrected.

35.2 Every time notice of a Defect is given, the Contractor shall correct the notified Defect within the

length of time specified by the Engineer's notice.

36. Uncorrected Defects

36.1 If the Contractor has not corrected a Defect within the time specified in the Engineer's notice, the

Engineer will assess the cost of having the Defect corrected, and the Contractor will pay this amount.

Page 49: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

49

Contractor No. of corrections Executive

Engineer

D. COST CONTROL

37. Bill of Quantities

37.1 The Bill of Quantities shall contain items for the construction, installation, testing and commissioning

work to be done by the Contractor.

37.2 The Bill of Quantities is used to calculate the Contract Price. The Contractor is paid for the quantity of

the work done at the rate in the Bill of Quantities for each item.

38. Changes in the Quantities

38.1 If the final quantity of the work done differs from the quantity in the Bill of Quantities for the

particular item by more than 25 percent provided the change exceeds 1% of initial Contract Price, the

Engineer shall adjust the rate to allow for the change, duly considering.

(a) Justification for rate adjustment as furnished by the contractor.

(b) Economics resulting from increase in quantities by way of reduced plant,

equipment and overhead costs.

(c) Entitlement of the contractor to compensation events where such events are caused by any

additional work.

38.2 The Engineer shall not adjust rates from changes in quantities if thereby the Initial Contract Price is

exceeded by more than 15 percent, except with the Prior approval of the Employer.

38.3 If requested by the Engineer, the Contractor shall provide the Engineer with a detailed cost

breakdown of any rate in the Bill of Quantities.

39. Variations

39.1 All Variations shall be included in updated Programmers produced by the Contractor.

40. Payments for Variations

40.1 The Contractor shall provide the Engineer with a quotation (with breakdown of unit rates) for carrying

out the Variation when requested to do so by the Engineer. The Engineer shall assess the quotation,

which shall be given within seven days of the request or within any longer period stated by the

Engineer and before the variation is ordered.

40.2 If the work in the Variation corresponds with an item description in the Bill of Quantities and if, in the

opinion of the Engineer, the quantity of work above the limit stated in Sub Clause 38.1 or the timing

of its execution do not cause the cost per unit of quantity to change, the rate in the Bill of Quantities

shall be used to calculate the value of the Variation. If the cost per unit of quantity changes, or if the

nature or timing of the work in the Variation does not correspond with items in the Bill of Quantities,

the quotation by the Contractor shall be in the form of new rates for the relevant items of work.

40.3 If the Contractor's quotation is unreasonable, the Engineer may order the Variations and make a

change to the Contract Price which shall be based on Engineer's own forecast of the effects of the

Variation on the Contractor's costs.

40.4 If the Engineer decides that the urgency of varying the work would prevent a quotation being given

and considered without delaying the work, no quotation shall be given and the Variation shall be

treated as a Compensation Event.

Page 50: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

50

Contractor No. of corrections Executive

Engineer

40.5 The Contractor shall not be entitled to additional payment for costs which could have been avoided by

giving early warning.

41. Cash Flow Forecasts

41.1 When the Programme is updated, the contractor is to provide the Engineer with an updated cash flow

forecast.

42. Payment Certificates

42.1 The Contractor shall submit to the Engineer monthly statements of the estimate value of the work

completed less the cumulative amount certified previously.

42.2 The Engineer shall check the Contractor's monthly statement within 14 days and certify the

amount to be paid to the Contractor after taking into account any credit or debit for the month in

question in respect of materials for the works in the relevant amounts and under conditions set forth in

sub-clause 51(3) of the Contract Data (Secured Advance)

42.3 The value of work executed shall be determined by the Engineer.

42.4 The value of work executed shall comprise the value of the quantities of the items in the Bill of

Quantities completed.

42.5 The value of work executed shall include the valuation of Variations and Compensation Events.

42.6 The Engineer may exclude any item certified in a previous certificate or reduce the proportion of any

item previously certified in any certificate in the light of later information.

43. Payments

43.1 Payments shall be adjusted for deductions for other recoveries in terms of the contract and taxes at

source, as applicable under the law. Contractors the amount certified by Engineer as per availability of

funds and no interest shall be payable in case of any delayed payment.

43.2 If an amount certified is increased in a later certificate as a result of an award by the Adjudicator or an

Arbitrator, the Contractor shall be paid interest upon the delayed payment as set out in this clause.

Interest shall be calculated from the date upon which the increased amount would have been certified

in the absence of dispute.

43.3 Items of the Works for which no rate or price has been entered in will not be paid for by the Employer

and shall be deemed covered by other rates and prices in the Contract.

44. Compensation Events

44.1 The following are Compensation Events unless they are caused by the Contractor.

(a) The Employer does not give access to a part of the Site by the Site Possession Date stated in

the Contract Data.

(b) The Employer modifies the schedule of other contractors in a way which affects the work of

the contractor under the contract.

(c) The Engineer orders a delay or does not issue drawings, specifications or instructions

required for execution of works on time.

(d) The Engineer instructs the Contractor to uncover or to carry out additional tests upon work

which is then found to have no Defects.

Page 51: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

51

Contractor No. of corrections Executive

Engineer

(e) The Engineer does not approve of a sub contract to be let, within 15 days.

(f) Ground conditions are substantially more adverse than could reasonably have been assumed

before issuance of Letter of Acceptance from the information issued to Bidders (including the

Site Investigation Reports), from information available publicly and from a visual inspection

of the site.

(g) The Engineer gives an instruction for dealing with an unforeseen condition, cause by the

Employer, or additional work required for safety or other reasons.

(h) Other contractors, public authorities, utilities or the Employer does not work within the dates

and other constraints stated in the Contract, and they cause delay or extra cost to the

Contractor.

(i) The advance payment is delayed, beyond 28 days after receipt of application and bank

guarantee.

(j) The effect on the Contractor of any of the Employer's Risks.

(k) The Engineer unreasonably delays issuing a Certificate of Completion.

(l) Other Compensation Events listed in the Contract Data or mentioned in the Contract.

44.2 If a Compensation Event would cause additional cost or would prevent the work being completed

before the Intended Completion Date, the Contract Price shall be increased and/or the Intended

Completion Date is extended. The Engineer shall decide whether and by how much the Contract Price

shall be increased and whether and by how much the Intended Completion Date shall be extended.

44.3 As soon as information demonstrating the effect of each Compensation Event upon the Contractor's

forecast cost has been provided by the Contractor, it is to be assessed by the Engineer and the

Contract Price shall be adjusted accordingly. If the contractors forecast deemed unreasonable, the

Engineer shall adjust the Contract Price based on Engineer's own forecast. The Engineer will assume

that the Contractor will react competently and promptly to the event.

44.4 The Contractor shall not be entitled to compensation to the extent that the Employer's interests are

adversely affected by the Contractor not having given early warning or not having co-operated with

the Engineer.

45. Tax

45.1 The rates quoted by the Contractor shall be deemed to be inclusive of the sales and other taxes that the

Contractor will have to pay for performance of this Contract. The Employer will perform such duties

in regard to the deduction of such taxes at source as per applicable law.

46. Currencies

46.1 All payments shall be made in Indian Rupees.

47. Price Adjustment

DELETED

48. Retention

48.1 The Employer shall retain from each payment due to the Contractor the proportion stated in the

Contract Data until Completion of the whole of the Works.

Page 52: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

52

Contractor No. of corrections Executive

Engineer

48.2 On Completion of the whole of the Works half the total amount retained is repaid to the Contractor

and half when the Defects Liability Period has passed and the Engineer has certified that all Defects

notified by the Engineer to the Contractor before the end of this period have been corrected.

48.3 On completion of the whole works, the contractor may substitute retention money with an “on

demand” Bank guarantee.

49. Liquidated Damages

49.1 The Contractor shall pay liquidated damages to the Employer at the rate per day stated in the Contract

Data for each day that the Completion Date is later than the Intended Completion Date (for the whole

of the works or the milestone as stated in the contract data). The total amount of liquidated damages

shall not exceed the amount defined in the Contract Data. The Employer may deduct liquidated

damages from payments due to the Contractor. Payment of liquidated damages does not affect the

Contractor’s liabilities.

49.2 If the intended completion date is extended after liquidated damages have been paid, the Engineer

shall correct any overpayment of liquidated damages by the Contractor by adjusting the next payment

certificate. The Contractor shall be paid interest on the over payment calculated from the date of

payment to the date of repayment at the rates specified in Sub-Clause 43.1.

49.3 If the contractor fails to comply with the time for completion as stipulated in the tender, then the

contractor shall pay to the employer the relevant slum stated in the Contract Data as liquidated

damages for such default and not as penalty for everyday or part of day which shall elapse between

relevant time for completion and the date stated in the taking over certificate of the whole of the

works on the relevant section, subject to the limit stated in the contract data.

The employer may, without prejudice to any other method of recovery deduct the amount of such

damages from any monies due or to become due to the contractor. The payment or deduction of such

damages shall not relieve the contractor from his obligation to complete the works on from any other

of his obligations and liabilities under the contract.

49.4 If, before the Time for completion of the whole of the works, or, if applicable, any section, a Taking-

Over Certificate has been issued for any part of the Works or of a section, the liquidated damages for

delay in completion of the remainder of the works or of that Section shall, for any period of delay

after the date stated in such Taking-Over Certificate, and in the absence of alternative provisions in

the Contract, be reduced in the proportion which the value of the part so certified bears to the value of

the whole of the works or Section, as applicable. The provisions of this Sub-Clause shall only apply

to the rate of liquidated damages and shall not affect the limit there of.

50. Bonus -

DELETED

51. Advance Payment -

DELETED

52. Securities

52.1 The Performance Security (including additional security for unbalanced bids) shall be provided to the

Employer no later than the date specified in the Letter of Acceptance and shall be issued in an amount

and form and by a bank or surety acceptable to the Employer and denominated in Indian Rupees. The

Performance Security shall be valid until a date 28 days from the date of expiry of Defects Liability

Period and the additional security for unbalanced bids shall be valid until a date 28 days from the date

of issue of the certificate of completion.

Page 53: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

53

Contractor No. of corrections Executive

Engineer

53. Deleted

54. Cost of Repairs

54.1 Loss or damage to the Works or Materials to be incorporated in the Works between the Start Date and

the end of the Defects Correction periods shall be remedied by the contractor at the Contractor’s cost

if the loss or damage arises from the contractor’s acts or omissions.

Page 54: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

54

Contractor No. of corrections Executive

Engineer

E. FINISHING THE CONTRACT

55. Completion

55.1 The Contractor shall request the Engineer to issue a Certificate of Completion of the works and the

Engineer will do so upon deciding that the work is completed.

56. Taking Over

56.1 The Employer shall take over the Site and the Works within seven days of the Engineer issuing a

certificate of Completion.

57. Final Account

57.1 The Contractor shall supply to the Engineer a detailed account of the total amount that the Contractor

considers payable under the Contract before the end of the Defects Liability Period. The Engineer

shall issue a Defect Liability Certificate and certify any final payment that is due to the Contractor

within 56 days of receiving the Contractor’s account if it is correct and complete. If it is not, the

Engineer shall issue within 56 days a schedule that states the scope of the corrections or additions that

are necessary. If the Final Account is still unsatisfactory after it has been resubmitted, the Engineer

shall decide on the amount payable to the Contractor and issue a payment certificate, within 56 days

of receiving the Contractor’s revised account.

58. Operating and Maintenance Manuals

58.1 If ”as built” Drawings and/or operating and maintenance manuals are required, the Contractor shall

supply them by the dates stated in the Contract Data.

58.2 If the Contractor does not supply the Drawings and/or Manuals by the dates stated in the Contract

Data, or they do not receive the Engineer’s approval, the Engineer shall withhold the amount stated in

the Contract Data from payments due to the Contractor.

59. Termination

59.1 The Employer or the Contractor may terminate the Contract if the other party causes a fundamental

breach of the Contract.

59.2 Fundamental breaches of Contract include, but shall not be limited to the following

(a) The contractor stops work for 28 days when no stoppage of work is shown on the current

Programme and the stoppage has not been authorized by the Engineer.

(b) The Engineer instructs the Contractor to delay the progress of the Works and the instruction is

not withdrawn within 28 days.

(c) The Employer or contractor is made bankrupt or goes into liquidation other than for a

reconstruction or amalgamation;

(d) A payment certified by the Engineer is not paid by the Employer to the Contractor within 56

days of the date of the Engineer’s Certificate.

(e) The Engineer gives Notice that failure to correct particular Defect is a fundamental breach of

Contract and the Contractor fails to correct it within a reasonable period of time determined by

the Engineer.

(f) The Contractor does not maintain a security, which is required.

Page 55: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

55

Contractor No. of corrections Executive

Engineer

(g) The Contractor has delayed the completion of works by the number of days for which the

maximum amount of liquidated damages can be paid as defined in the Contract Data; and

(h) If the Contractor in the judgment of the Employer has engaged in corrupt or fraudulent

practices in competing for or in executing the Contract

For the purpose of this paragraph: “corrupt practice” means the offering, giving, receiving or

soliciting of anything of value to influence the action of a public official in the procurement process or

in contract executing. “Fraudulent Practice” means a misrepresentation of facts in order to influence a

procurement process or the execution of a contract to the detriment of the Borrower, and includes

collusive practice among Bidders (Prior to or after bid submission) designed to establish bid prices at

artificial non-competitive levels and to deprive the Borrower of the benefits of free and open

competition”.

59.3 When either party to the Contract gives notice of a breach of contract to the Engineer for a cause other

than those listed under Sub-Clause 59.2 above, the Engineer shall decide whether the breach is

fundamental or not.

59.4 Notwithstanding the above, the Employer may terminate the Contract for convenience.

59.5 If the Contract is terminated the Contractor shall stop work immediately, make the site safe and secure

and leave the site as soon as reasonably possible.

60. Payment upon Termination

60.1 If the Contract is terminated because of a fundamental breach of Contract by the Contractor, the

Engineer shall issue a certificate for the value of the work done less advance payments received upon

the date of the issue of the certificate, less other recoveries due in terms of the contract, less taxes due

to be deducted at source as per applicable law and less the percentage to apply to the work not

completed as indicated in the Contract Data. Additional Liquidated Damages shall not apply. If the

total amount due to the Employer exceeds any payment due to the Contractor the difference shall be a

debt payable to the Employer.

60.2 If the contract is terminated at the Employer’s convenience or because of a fundamental breach of

Contract by the Employer, the Engineer shall issue a Certificate for the value of the work done, the

cost of balance material brought by the contractor and available at site, the reasonable cost of removal

of Equipment, repatriation of the Contractor’s personnel employed solely on the Works, and the

Contractor’s Costs of protecting and securing the Works and less advance payments received up to the

date of the certificate, less other recoveries due in terms of the contract and less taxes due to be

deducted at source as per applicable law.

61. Property

61.1 All materials on the site, Plant, Equipments, Temporary Works and Works are deemed to be the

property of the Employer, if the Contract is terminated because of a Contractor’s default.

62. Releases from Performance

62.1 If the contractor is frustrated by the outbreak of war or by any other event entirely outside the control

of either the Employer or the Contractor the Engineer shall certify that the Contract has been

frustrated. The Contractor shall make the site safe and stop work as quickly as possible after

receiving this certificate and shall be paid for all work carried out before receiving it and for any work

carried out afterwards to which commitment was made.

Page 56: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

56

Contractor No. of corrections Executive

Engineer

F. SPECIAL CONDITIONS OF CONTRACT

1. LABOUR

The Contractor shall, unless otherwise provided in the Contract, make his own arrangements for the

engagement of all staff and labour, local or other, and for their payment housing, feeding and

transport. The Contractor shall, if required by the Engineer, deliver to the Engineer a return in detail,

in such form and at such intervals as the Engineer may prescribe, showing the staff and the numbers

of the several classes of labour from time to time employed by the Contractor on the site and such

other information as the Engineer may require.

2. COMPLIANCE WITH LABOUR REGULATIONS

During continuance of the contract, the Contractor and his sub-contractors shall abide at all times bay

all existing labour enactments and rules made there under, regulations, notifications and bye laws of

the state or Central Government or local authority and any other labour law (including rules),

regulations, bye laws that may be passed or notification that may be issued under any labour law in

future either by the State or the Central Government or the local authority. Salient features of some of

the major labour laws that are applicable to construction industry are given below. The Contractor

shall keep the Employer indemnified in case any action is taken against the Employer by the

competent authority on account of contravention of any of the provisions of any Act or rules made

there under, regulations or notifications including amendments. If the Employer is caused to pay or

reimburse,, such amounts as may be necessary to cause or observe or for non-observance of the

provisions stipulated in the notifications/bye laws/Acts/Rules/Regulations including amendments, if

any, on the part of the Contractor, the Engineer/Employer shall have the right to deduct any money

due to the Contractor, including his amount of performance security. The Employer / Engineer shall

also have right to recover from the Contractor any sum required or estimated to be required for

making good the loss or damage suffered by the Employer.

The employees of the Contractor and the Sub-Contractor in no case shall be treated as the employees

of the Employer at any point of time.

3. STATUTORY APPROVALS

Contractor shall obtain all statutory approvals / no objection certificates / commencement /

completion inspection & other permissions as required from all the local & public authorities before

starting of work and on completion of work at his cost.

The statutory charges paid to authorities in connection with this for obtaining all the said permissions

works shall be entirely borne by the contractor. Contractor shall comply with all the approval rules,

regulations, Byelaws, directions given from time to time by any local &/or public authorities in

consideration with this work

Page 57: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

57

Contractor No. of corrections Executive

Engineer

SALIENT FEATURES OF SOME MAJOR LABOUR LAWS APPLICABLE TO

ESTABLISHMENTS ENGAGED IN BUILDING AND OTHER CONSTRUCTION WORK.

a) Workmen Compensation Act 1923: - The Act provides for compensation in case of injury by

accident arising out of and during the course of employment.

b) Payment of Gratuity Act 1972: - Gratuity is payable to an employee under the Act on satisfaction of

certain conditions on separation if an employee has completed 5 years service or more on death, the

rate of 15 days wages for every completed year of service. The Act is applicable to all

establishments employing 10 or more employees.

c) Employees P.F. and Miscellaneous Provision Act 1952 :- The Act provides for monthly

contributions by the employer plus workers @ 10% or 8.33%. The benefits payable under the Act are

:

(i) Pension or family pension on retirement or death, as the case may be.

(ii) Deposit linked insurance on the death in harness of the worker.

(iii) Payment of P.F. accumulation on retirement/death etc.

d) Maternity Benefit Act 1951 :- The Act provides for leave and some other benefits to Women

employees in case of confinement or miscarriage etc.

e) Contract Labour (Regulation & Abolition) Act 1970 :- The Act provides for certain welfare

measures to be provided by the Contractor to contract labour and in case the Contractor fails to

provide ,the same are required to be provided, by the principal Employer by law. The Principal

Employer is required to take Certificate of Registration and the Contractor is required to take license

from the designated Officer. The Act is applicable to the establishments or contractor of Principal

Employer, if they employ 20 or more contract labour.

f) Minimum Wages Act 1948 :- The Employer is supposed to pay not less than the Minimum Wages

fixed by appropriate Government as per provisions of the Act, if the employment is a scheduled

employment. Construction of buildings, Roads, Runways is scheduled employments.

g) Payment of Wages Act 1936 :- It lays down as to by what date the wages are to be paid when it will

be paid and what deductions can be made from the wages of the workers.

h) Equal Remuneration Act 1979: -The Act provides for payment of equal wages for work of equal

nature to male and female workers and for not making discrimination against Female employees in

the matters of transfers, training and promotions etc.

i) Payment of Bonus Act 1965:- The Act is applicable to all establishments employing 20 or more

employees. The Act provides for payments of annual bonus subject to a minimum of 8.33 % of

wages and maximum of 20% of wages to employees drawing Rs. 3500/- per month or less. The

bonus to be paid to employees getting Rs. 2500/- per month or above up to Rs.3500/- per month shall

be worked out by taking wages as Rs. 2500/- per month only. The Act does not apply to certain

establishments. The newly set-up establishments are exempted for five years in certain circumstances.

Some of the State Governments have reduced the employment size from 20 to 10 for the purpose of

applicability of this Act.

j) Industrial Disputers Act 1947 :- The Act lays down the machinery and procedure for resolution of

Industrial disputes, in what situations a strike or lock-out becomes illegal and what are the

requirements for laying off or retrenching the employees or closing down the establishment.

k) Industrial Employment (Standing Orders) Act 1946:- It is applicable to all establishments

employing 100 or more workmen (employment size reduced by some of the States and Central

Government to 50). The Act provides for laying down rules governing the conditions of employment

Page 58: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

58

Contractor No. of corrections Executive

Engineer

by the Employer on matters provided in the Act and get the same certified by the designated

Authority.

l) Trade Unions Act 1926 :- The Act lays down the procedure for registration of trade unions of

workmen and employers. The Trade Unions registered under the Act have been given certain

immunities from civil and criminal liabilities.

m) Child Labour :- Prohibition and Regulation) Act 1986 :- The Act prohibits employment of children

below 14 years of age in certain occupations and processes and provides for regulation of employment

of children in all other occupations and processes. Employment of Child Labour is prohibited in

Building and Construction Industry.

n) Inter-State Migrating Workmen’s (Regulation of Employment & Conditions of Service) Act

1979 :- The Act is applicable to an establishment which employees 5 or more Inter-State migrant

workmen through an intermediary (who has recruited workmen in one state for employment in the

establishment situated in another state). The Inter-State migrant workmen, in an establishment to

which this Act becomes applicable, are required to be provided certain facilities such as housing,

medical aid, traveling expenses from home upto the establishment and back etc.

o) The Building and Other Construction Workers (Regulation of Employment and Conditions of

Services) Act 1996 and the Cess Act of 1996 :- All the establishments who carry on any building or

other construction work and employees 10 or more workers are covered under this Act,. All such

establishments are required to pay cess at the rate not exceeding 2 % of the cost of construction as

may be modified by the Government. The Employer of the establishment is required to provide safety

measures at the Building or construction work and other welfare measures, such as Canteens First Aid

Facilities, Ambulance, Housing accommodations for workers near the work place etc. The Employer

to whom the Act applies has to obtain a registration certificate from the Registered Officer appointed

by the Government.

p) Factories Act 1948 :- The act lays down the procedure for approval of plans before setting up a

factory, health and safety provisions, welfare provisions, working hours, annual earned leave and

rendering information regarding accidents or dangerous occurrences to designated authorities. It is

applicable to premises employing 10 persons or more with aid of power or 20 or more persons

without the aid of power engaged in manufacturing process.

3. Arbitration (GCC Clause 25.3)

3.1 Except where otherwise specified in the contract and subject to the powers delegated to him by

Government under the code, rules then in the force, the decision of the Superintending Engineer of

the Circle for the time being shall be final, conclusive and binding on all parties of the contract upon

all questions relating to the meaning of the specifications, designs, drawings and instruction

hereinbefore mentioned and as to the quality of workmanship or materials used on the work, or as to

any other question, claim right, matter or things whatsoever, if any way arising out of, or relating to

the contract, designs, drawings, specifications, estimates , instructions, orders, or other conditions, or

otherwise concerning the works, or the execution, or failure to execute the same, whether arising

during the progress of the work, or after the completion or abandonment thereof.

3.2The Contractor may within thirty days of receipt by him of any order passed by the

Superintending Engineer of the Circle as aforesaid appeal against it to the Chief Engineer, concerned

with the contract work or project provided that -

(a) The accepted value of the contract exceeds Rs. 10 lakhs

(Rupees Ten lakhs)

(b) Amount of claim is not less than Rs. 1.00 Lakh

(Rupees One Lakh).

Page 59: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

59

Contractor No. of corrections Executive

Engineer

3.3 If the Contractor is not satisfied with the order passed by the Chief Engineer as aforesaid, the

Contractor may, within thirty days of receipt by him of any such order appeal against it to the

concerned Secretary, Public Works Department/Irrigation Department who, if convinced that Prima-

facie the Contractors claim rejected by Superintending Engineer/Chief Engineer is not frivolous and

that there is some substance in the claim of the Contractor as would merit a detailed examination and

decision by the Standing Committee, shall put up to the Standing Committee at Government level for

suitable decision

(Vide PW Circular No. CAT-1086-CR-110/Bldg.2 Dated 7.5.1986).

Page 60: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

60

Contractor No. of corrections Executive

Engineer

SECTION – 4

CONTRACT DATA

Page 61: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

61

Contractor No. of corrections Executive

Engineer

CONTRACT DATA

Items marked “N/A” do not apply in this Contract Clause

Reference with

respect to

Section - 3

1. Name of the Employer is Chief Executive Officer, Maharashtra

Maritime Board, Indian Mercantile Chamber, 3rd floor, Ramjibhai

Kamani Marg, Ballard Estate, Mumbai-400 001.

[Cl.1.1]

2. The Engineer is Executive Engineer, Maharashtra Maritime Board,

Indian Mercantile Chamber, 3rd floor, Ramjibhai Kamani Marg,

Ballard Estate, Mumbai-400 001.

3. The Defects Liability Period is 24 Months from the date of Completion. [Cl.1.1 & 35]

4. The Start Date shall be 7 days from the date of issue of the Notice to

proceed with the work.

[Cl.1.1]

5. The Intended Completion Date for the whole of the works is 11 (Eleven)

months including monsoon period after start of work with the following

milestones:

[Cl.1.1, 17 & 28]

Milestone dates: [Cl.2.2, & 49.1]

Physical Works to be completed Period for Mild Stone Period from the

start date

i) Milestone 1: 30 % of the contract price 3 (Three) Months

3 (Three)

Months

ii) Milestone 2: 30 % of the contract price

5 (Five) Months

8 (Eight)

Months

iii) Milestone 3: 40 % of the contract price 3 (Three) Months

11 (Eleven)

Months

7. The site is Reconstruction & Extension of Existing Jetty and

Civil Work (Reclamation Bund, Terminal Building and other

onshore work) at Malvan Port, Tal-Malvan, Dist-Sindhudurg

[Cl.1.1]

8. The name and identification number of the Contract is :

[Cl.1.1]

Page 62: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

62

Contractor No. of corrections Executive

Engineer

9 Reconstruction & Extension of Existing Jetty and Civil Work (Reclamation Bund, Terminal Building and other onshore work) at Malvan Port, Tal-Malvan, Dist-Sindhudurg

[Cl.1.1]

Scope of Work :

A) Reclamation Bund Construction of bund in tidal condition consist

of filling trap stone in layers such as filter, core,

sub-armour and armour layers of 20kg, 200kg,

300-500kg and 1000kg respectively with

geofabric filter layer over it.

B) Terminal Building Raft foundation with basement.

R.C.C. frame structure with column, beam, slab

& chajja in M35 concrete.

C) UG Tank & Pump

Room

Raft foundation with basement.

R.C.C. Frame structure with column, beam &

slab in M35 concrete.

Shahabad box type waterproofing to the

basement of UG tank.

D) Septic Tank Raft foundation with basement.

RCC walls of 350mm thick in M35 concrete.

10. The following documents also form part of the Contract:

Addendum issued under clause 9.2.4. pursuant to clause 10 if any

[ Cl. 2.3(9) ]

11. The law, which applies to the Contract, is the law of Union of India. [ Cl. 3.1 ]

12. The language of the Contract documents is English [ Cl. 3.1 ]

13. Limit of subcontracting – Not allowed [ Cl. 7.1 ]

14. The Schedule of Other Contractors – NIL- [ Cl. 8 ]

15. The Schedule of Key personnel - As per 4.5.4 to section I [Cl. 9]

16. The minimum insurance cover for physical property, injury and death is

Rs.5 lakhs per occurrence with the number of occurrences limited to

four. After each occurrence, Contractor will pay additional premium

necessary to make insurance valid for four occurrences always.

[Cl. 13]

17. Site investigation report – To be assessed by the contractor [Cl. 14]

18. The site possession Dates shall be within seven days from issue of notice

to proceed with the work.

[Cl. 21]

19. Fees and types of reimbursable expenses to be paid to the Dispute

Review Board (To be inserted later)

[Cl. 25]

20. Appointing Authority for the Dispute Review Board -council, Indian

Roads Congress, New Delhi.

[Cl. 26]

21. The period for submission of the programme for approval of Engineer

shall be 21 days from the issue of letter of Acceptance

[Cl. 27.1]

Page 63: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

63

Contractor No. of corrections Executive

Engineer

22. Deleted [Cl. 27.3]

23. Deleted [Cl. 27.3]

24. The following events shall also be Compensation Events: [Cl. 44]

Substantially adverse ground conditions encountered during the course

of execution of work not provided for in the bidding document –

(i) Removal of underground utilities detected subsequently

(ii) Significant change in classification of soil requiring additional

mobilisation by the contractor e.g. ordinary soil to rock

excavation

(iii) Removal of unsuitable material like marsh, debris dumps etc.

not caused by the contractor

(iv) Artesian conditions.

(v) Seepage, erosion, landslide

(vi) River training requiring protection of permanent work

(vii) Presence of historical, archaeological or religious structures,

monuments interfering with the works

(viii) Restriction of access to ground imposed by civil. judicial, or

military authority.

25. The currency of the Contract is Indian Rupees [Cl. 46]

26. The formula (e) for adjustment of prices are: [Cl. 47]

R = value of work as defined in Clause 47.1 of conditions of Contract

Adjustment For Labour Component :

(i) Price adjustment for increase or decrease in the cost due to labour shall

be paid in accordance with the following formula;

VL = 0.85 x P1 x R x [ (Li – Lo) / Lo ]

100

VL = Increase or decrease in the cost of work during the month under

consideration due to changes in rates for local labour.

Lo = The consumer price index for industrial workers for the state on 28

days preceding the date of opening of bids as published by Labour

Bureau, Ministry of Labour, Government of India.

Li = The Consumer Price Index for industrial workers for the state for

the month under consideration as published by Labour Bureau,

Ministry of Labour, Government of India.

Pl = Percentage of labour component of work.

Adjustment For Cement Component :

(ii) Price adjustment for increase or decrease in the cost of Cement shall be

paid in accordance with the following formula :

Vc = 0.85 x Pc x R x [ (Ci – Co) /Co]

100

Vc = Increase or decrease in the cost of work during the month under

consideration due to changes in rates for cement

Page 64: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

64

Contractor No. of corrections Executive

Engineer

Co = The all India wholesale price index for cement on 28 days

preceding the date of opening of Bids as published by the

Ministry

of Industrial Development, Government of India, New Delhi.

Ci = The all India average wholesale price index for cement for the

month under consideration as published by the Ministry of

Industrial Development, Government of India, New Delhi.

Pc = Percentage of cement component of the work.

Adjustment For Steel Component :

(iii

)

Price adjustment for increase or decrease in the cost of steel shall be paid

in accordance with the following formula :

Vs = 0.85 x PS x R x (Si – So) / So

100

Vs = Increase or decrease in the cost of work during the month

under consideration due to changes in rate for Steel.

So = The all India wholesale price index for4 Steel (Bars & Rods) on 28

days preceding the date of opening of Bids as published by the

Ministry of Industrial Development, Government of India, New

Delhi.

Si = The all India wholesale price index for4 Steel (Bars & Rods) on 28

days preceding the date of opening of Bids as published by the

Ministry of Industrial Development, Government of India, New

Delhi.

Pc = Percentage of cement component of the work.

Note :- For the application of this clause, index of Bars and Rods

has been chosen to represent steel group.

(iv) Adjustment For Bitumen Component :

Deleted

(v) Adjustment of POL (Fuel and Lubricant) Component :

Price adjustment for increase or decrease in the cost of POL (fuel and

lubricant) shall be paid in accordance with the following formula;

Vf = 0.85 x Pf/ 100 x R x ( Fi – Fo ) / Fo

Vf =increase or decrease in the cost of work during the month under

consideration due to changes in rates for fuel & lubricants.

Fo = The official retail price of High speed Diesel at the existing

consumer pumps of IOC depot at nearest centre on the day 28 days

prior to the date of opening of bids.

Fi = The official retail price of HSD at the existing consumer pumps of

IOC at nearest centre for the 15th day of month of the under

consideration..

Page 65: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

65

Contractor No. of corrections Executive

Engineer

Pf =Percentage of fuel & lubricants component of the work.

Note : For the application of this clause, the price of High Speed Diesel &

Oil has been chosen to represent fuel & lubricants group.

Adjustment of Plant and Machinery Spares Component :

Deleted

Adjustment of Other Materials Component :

(vii

)

Price adjustment for increase or decrease in the cost of local materials

other than cement, Steel, bitumen, and POL procured by the contractor

shall be paid in accordance with the following formula;

Vm = 0.85 x Pm/ 100 x R x ( Mi – Mo ) / Mo

Vm = Increase or decrease in the cost of work during the month under

consideration due to changes in rates for local materials other

than cement, Steel, bitumen, and POL .

Mo = The all India wholesale price index (all Commodities) on 28 days

preceding the date of opening of Bids as published by the Ministry

of Industrial Development, Government of India, New Delhi.

Mi = The all India wholesale price index (all Commodities) on for the

month under consideration as published by the Ministry of

Industrial Development, Government of India, New Delhi.

Pm = Percentage of local materials component (other than cement, steel,

bitumen and POL) of the work.

The following percentage will govern the price adjustment for the entire

contract :

1 Labour Pl = 37%

2 Cement Pc = 14 %

3 Steel (TMT+St.steel) Ps = 29 %

5 POL Pf = 7 %

6 Plant & Machinery Spares Pp = --

7 Other Materials Pm = 13 %

Total 100.00 %

27. The Proportion of payments retained (retention money) shall be 6 % from

each bill subject to a maximum of 5 % of final contract price.

[Cl. 48]

Page 66: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

66

Contractor No. of corrections Executive

Engineer

28. Amount of liquidated damages for

delay in completion of works

(I) for Whole of work [Cl. 49]

(1/2000)th of the initial contract

price rounded off to the nearest

thousand per day i.e.

Rs. 25,100.00 per day

(II) for sectional completion

(Whatever specified in Item 6

of Contract Data) - (1/2000)th

of initial contract price for

section of work under

(i) Milestone I rounded off to

the nearest thousand per day

i.e. Rs. 7,530.00 per day.

(ii) Milestone II rounded off to

the nearest thousand per day

i.e. Rs. 7,530.00 per day.

(iii) Milestone III rounded off

to the nearest thousand per day

i.e. Rs.10,040.00 per day.

29 Maximum limit of liquidated

damages for delay in completion of

work.

10% of the Initial Contract

Price rounded off to the

nearest thousand. i.e.

Rs. 50,20,000.00

[Cl. 49]

30. Amount of Bonus for early

completion of whole of the works

DELETED

[Cl. 50]

31. Maximum limit of bonus for early

completion of work

DELETED

[Cl. 50]

32. The amounts of the advance payment

are.

DELETED

[Cl. 51 & 52]

33. The Securities shall be for the following minimum amounts equivalent as

a percentage of the Contract Price:

[Cl. 52]

Page 67: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

67

Contractor No. of corrections Executive

Engineer

Performance Security for 2 percent of contract price plus

Rs....................... (to be decided after evaluation of the bid) as additional

security in terms of ITB Clause 29.5

The Standard form of Performance Security acceptable to the Employer

shall be an unconditional Demand Draft (DD) of the type as presented in

Section 8 of the Bidding Documents.

34. The Schedule of Operating and Maintenance Manuals ................N/A [Cl. 58]

Page 68: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

68

Contractor No. of corrections Executive

Engineer

SECTION – 5

TECHNICAL SPECIFICATION

Page 69: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

69

Contractor No. of corrections Executive

Engineer

TECHNICAL SPECIFICATIONS

1. TEMPORARY WORKS

Where required, the Contractor shall furnish such details of his temporary works as may be called for by the

Engineer and the Contractor shall satisfy the Engineer as to their safety and efficiency. The Engineer-in-charge

may direct that temporary works, which he considers unsafe or inefficient, shall be removed and replaced in a

satisfactory manner.

2. CONTRACTOR’S TEMPORARY STRUCTURES

The Contractor may, at his own expense, and subject to the approval of the Engineer-in-charge and statutory

authorities, construct offices, stores, workshop and accommodation for staff and labourer in the area allocated to

him and remove the same as per the orders of the Engineer-in-charge on completion of the Contract.

3. SURVEY

The Contractor shall, at his own expense, provide and maintain, survey stations which he may require to carry

out the Works and shall remove the same on completion of the Works The Contractor shall, at his own expense,

carry out all the necessary surveys, measurements and setting out of the Works and shall for this purpose engage

qualified and competent engineering surveyors whose names and qualifications shall be submitted to the

Employer for his approval. The Contractor shall provide for the sole use of the Employer and his staff, at his

own expense, all necessary survey instruments and other equipment and all technicians, labourer and attendance,

including the services of minimum of two chainmen per shift, which the Engineer-in-charge may require for

setting out, marking and alignment of the Works. The chainmen shall be selected having appropriate experience,

and as far as possible, the same chainmen shall be provided throughout the Contract period. Before commencing

any work at any location the Contractor shall give the Employer not less than two days notice of his intention to

set out or give levels for any part of the works in order that arrangements may be made for inspection.

4. EQUIPMENT FOR SOLE USE OF EMPLOYER

The contractor shall provide for the sole use of the Engineer-in-charge and his staff, at his own expense, survey

instruments and other, equipment as listed below:

Two theodolites of one-second accuracy, One electronic distance measuring instrument (EDMI) attachable to

theodolite, Self- adjusting leveling instrument with aluminum stalves (numbers as required). The contractor

shall also provide for the use of the Engineer-in-charge, all technicians, labourer and attendants, including the

services of minimum of two chainmen per shift, which the Engineer-in-charge may require for setting out,

marking and alignment of the works. The chainmen shall be selected having appropriate experience, and as far

as possible the same chainmen shall be provided throughout the contract period. Before commencing any work

at any location, the contractor shall give the Engineer-in-charge not less than two days notice of his intention to

set out or give levels for any part of the works in order that arrangements may be made for inspection. The

Contractor shall maintain in good working order at all times during the period of the Contract the instruments

provided by him for the proper setting out of the works. The Contractor shall make available at his own expense

.any poles, pegs and staging templates of profiles required by the Engineer for inspection or measurement of the

Page 70: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

70

Contractor No. of corrections Executive

Engineer

Works. The contractor shall arrange for calibration & permanent adjustments of survey instruments from time to

time.

The cost of the above shall not be paid for separately and shall be deemed to be included in the rates and prices.

5. MATERIALS

5.1. QUALITY:

All materials used in the works shall be procured by the Contractor unless otherwise specified and shall be of

the best quality of their respective kinds as specified herein, obtained from sources and suppliers approved by

the Engineer and shall comply strictly with the tests prescribed in the specification with the requirements of the

latest issues of the relevant Indian Standards or where Indian Standards are not relevant British Standards. Any

materials not fully specified herein and for which there is no relevant Indian or British Standard shall be the best

of their respective kind and to the approval of the Engineer-in-charge.

5.2. INDIAN AND BRITISH STANDARDS

Where Indian and British Standards are named in the specification, the latest current issues, including

amendments, if any, issued by the respective standards Institution ,one month prior to the due date of receipt of

the Tenders are intended unless specifically stated otherwise.

5.3. INSPECTION AND TESTING

All materials used in the Works shall be subjected to inspections and tests as per relevant Indian Standards by

the Engineer. Unless otherwise stated the cost of all the tests required by the specifications or the relevant Indian

or British Standard shall be deemed to be included in the rates and prices named in various sections of the Bill

of Quantities. The Contractor shall carry out all the tests in site laboratory and shall provide testing apparatus,

technicians, helpers and all other facilities at the site. For the tests which cannot be carried out in site laboratory

(not due to failure of the laboratory equipments) the Contractor must select the testing laboratory with the

approval of the Engineer-in-charge and must provide conveyance for the transport of test samples and the

Engineer’s staff. The cost of transporting and testing will be borne by the Contractor No consignment of a

material shall be used unless the tests required by the Engineer-in-charge are carried out and the test reports are

analyzed by him and the material is cleared by him for consumption. The Contractor must schedule ordering and

receipt of consignment with due regard to the time required for sampling, testing and analysis of test reports.

5.4. APPROVAL

No material shall be used in the Works unless it has first been approved by the Engineer-in-charge.

5.5. SAMPLES

Samples of all materials proposed to be employed in the execution of the Works may be called for by the

Engineer and shall be submitted before the materials are brought to site.

Samples provided to the Engineer-in-charge or his representative, are to be in labeled boxes suitable for storage.

The cost of providing such samples shall be borne by the Contractor. Quality of material to be used in the works

shall be at least equal to that of the samples submitted to and approved by the Engineer-in-charge.

Page 71: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

71

Contractor No. of corrections Executive

Engineer

5.6. NAMES OF MANUFACTURES AND SUPPLIERS

Before ordering materials of any description the contractor shall submit for approval of the Engineer the names

of the makers or suppliers proposed, together with the particulars listed under the general heading “Information

to be furnished by the Supplier” where this occurs in the relevant or British Standard or such other particulars as

the Engineer may call for.

5.7. STORAGE AND USAGE OF MATERIAL AT SITE

All materials brought on to the site shall be stored and protected in such a manner that they remain in perfect

condition until such time as they are incorporated in the works. Methods of storage, protection and handling of

materials shall be to the Engineer’s approval. Materials shall be wherever possible and practicable be used in the

order in which they arrive on the site. This is especially important for cement stock.

5.8. DISPATCH OF MATERIALS

Materials shall not be dispatched from the manufacture’s works to the site without written authority from the

Engineer or his representative.

5.9. TEST CERTIFICATES

All manufacturer’s certificates of test, proof sheets, mill sheets etc, showing that the materials have been tested

in accordance with the requirements of this Specification, the appropriate Indian Standard specification are to

be supplied free of charge, on request by the Engineer or his representative.

5.10. CODES:

I.S.

456 2000 Plain and reinforced concrete code of practice

I.S.

1489(PART -1) Codes for cement concrete

I.S. 1121

1124

1122

1974

1974

1974

Codes for stones.

Reference to any code shall always mean reference to the latest revised edition of the code including all its

amendments up to date, unless specified otherwise. In the event of any conflict between the requirements of this

specification and those of the referred codes, the former shall govern

6. CONCRETE AGGREGATES

6.1. INDIAN STANDARDS

Aggregates shall generally comply with the requirements of I.S. 383 except as stated otherwise.

6.2. PRELIMINARY TESTING OF AGGREGATES

Before work is begun, representative samples of the various aggregates from each source of supply shall be

submitted to the Engineer for test and approval. Samples shall be in sufficient quantity to enable the Engineer to

carry out the full range of tests specified in I.S. 2386 and other specifications specified herein. Aggregates shall

be particularly tested for alkali silica reaction. Aggregates which are chemically reactive with alkalies of

Cement shall not be used. Aggregates shall be tested for chloride content as per DIN 4226 Part 3 Clause 3.6.5

Page 72: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

72

Contractor No. of corrections Executive

Engineer

and for sulphate content as per DIN part 3 clause 3.6.4.The aggregates shall be 0.02% by weight water-soluble

chloride (expressed as Chlorine), and maximum permissible sulphate content, expressed as sulfuric anhydrite

(S03) being 1% by weight with respect to the aggregate dried at 105ᵒC. The Engineer's representative will keep

a portion of the samples submitted which have been tested and approved to act as control samples for

comparison with later deliveries. In submitting the samples the contractor shall state the type of aggregate

represented, the source of supply which pass the requisite tests and are approved by the Engineer may

subsequently be used in the Works, and all aggregates used in the Works shall be of at least as good quality as

the approved samples.

6.3. AGGREGATES TO BE CLEAN

Allaggregates shall be delivered to and maintained at the site clean and free from dust and clay, organic and

other deleterious matter.

6.4. STORAGE AT SITE:

Coarse and fine aggregates shall be stored at the site separately on clean and paved and drained areas, which are

not liable to flooding. The various sizes of aggregates shall be separated by solid dividing walls of suitable

height and strength. Details of the layout and details of the storage areas shall be submitted to the Engineer for

approval before these are constructed.

6.5. REJECTED MATERIALS:

Any aggregates brought to site, which is not approved by the Engineer / or his representative, shall be

immediately removed from the site by the Contractor at his own cost.

6.6. FINE AGGRAGATES NATURE AND SOURCE:

Fine aggregates shall consist of natural sand from approved source. The Chlorides, Sulphate and silt content of

sand shall be monitored regularly and continuously and if present, sand shall be washed with fresh potable water

free from silt, Chlorides and Sulphates before use. The aggregates shall be of approved quality, clean, sharp and,

free from injurious amounts of dust, clay lumps, mica shells, flaky particle shells, alkali organic matter, loam or

other deleterious substances. The fine aggregates shall be screened or washed with fresh potable water or both if

ordered by the Engineer’s representative. The limitation of 5 % as well as it’s grading shall be specific as in IS:

383. The fineness modulus of fine aggregates shall also be monitored regularly and continuously and shall not

be less than 2.2 nor more than 3.2. If necessary, sand from different approved sources shall be blended to

achieve the desired fineness modulus.

6.7. COARSE AGGRAGATE NATURE AND SOURCE:

Coarse aggregate shall consist of crushed rock from approved sources. It shall be screened and/or washed with

fresh potable water if so ordered by the Engineer / or his representative. The limitation of percentage of foreign

materials in coarse aggregate shall be as specified in IS 1&383. Flakiness index of coarse aggregates shall not

exceed 15 %.

6.8. GRADING OF FINE AGGREGATE:

For concrete the upper limits for size of aggregates shall be in accordance with IS.-383.The grading of the

various sizes shall, however, be as per the mix design to be determined by laboratory test and approved by the

Engineer's representative. Fine mortar and grout shall comply with IS:383 and its Zone. II of table IV of the said

Standard Sand for masonry mortars shall comply with IS:2116.Sand for plastering and rendering shall conform

to class A grading of IS: 1542.

Page 73: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

73

Contractor No. of corrections Executive

Engineer

6.9. GRADING OF COARSE AGGRAGATE:

The maximum sizes of coarse aggregate for the various classes of concrete shall not exceed 20mmunless stated

otherwise. Notwithstanding the provisions in the IS the grading of the aggregates shall be as approved by the

Engineer's representative.

7. CEMENT

7.1. STANDARD:

Only Portland cement of 43/ 53 grade complying with the requirements of IS:12269 shall be used in the works.

Unless otherwise specified, ordered or permitted in writing by Engineer, Rapid hardening Portland cement, if its

use is permitted by the Engineer, shall conform to IS:8041. Changing of brands of cement within the same

structure will not be permitted without the specific approval of the Engineer.

7.2. SUPPLY OF CEMENT:

Supply of Ordinary Portland Cement for the permanent works shall be arranged by the Contractor at his own

cost from reputed suppliers The procedure for ordering and taking delivery of supplies of Ordinary Portland

Cement shall be submitted by contractor to the Employer before purchase.

7.3. TESTS:

The Engineer’s representative will order such tests as he may consider necessary on each consignment of

cement brought on to the site. The Contractor shall carry out these tests at the site-testing laboratory. The

Cement from the consignment from which the samples have been extracted for testing the samples have been

extracted for testing shall not be used in the works before completion of testing and analysis and until it has

been accepted as satisfactory by the Engineer. If such tests should lead to rejection of the consignment the same

shall not be used in the works but shall be removed from the site to such place as directed by the Engineer.

7.4. CONTRACTOR'S RESPONSIBILITY:

From the time that a consignment of cement is taken delivery by the contractor and tested and approved by the

Engineer's representative and until such time as cement is used in the works, the Contractor shall be acceptable

condition. Any cement which deteriorates while in the Contractor's Custody and is rejected as unsuitable by the

Engineer's representative shall be removed from the site and replaced by the Contractor to the satisfaction of the

Engineer, all at storage for a period of 90 days or longer until the results of such tests are found satisfactory, it

shall not be used in the works. If such cement is rejected as unsuitable by the Engineer's representative it shall

be removed from the site and replaced by the Contractor to the satisfaction of the Engineer, all at the

Contractor’s cost. In such case costs of transportation and testing shall also be borne by the Contractor.

7.5. STORAGE OF CEMENT IN BAGS:

The Contractor shall provide and maintain a cement godown for proper and efficient storage of cernent required

on the works.Cement in bags shall be unloaded under cover and stored in a perfectly watertight and

well-ventilated building accommodating sufficient cement to ensure continuity of the work, and having a floor

raised not less than 30 cm from the ground in order to protect the cement from moisture. An air space shall be

left between the floor and the bottom layer of the bags. Cement bags shall be stored well away from other walls

of the godown and not more than 12 bags shall be stacked in any tier. Each consignment shall be stacked

separately therein to permit easy access for inspection and a record shall be kept so that each consignment may

be identified by a serial number and date of delivery. Cement shall be issued from the godown in the order in

which it is received on site, commencing with the consignment, which has been in the godown for the longest

period of time.

Page 74: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

74

Contractor No. of corrections Executive

Engineer

7.6. PROTECTION FROM RAIN:

Cement shall be adequately protected at all times from rain and spray.

7.7. SET OR PARTIALLY SET CEMENT:

Cement, totally set or partially set, shall not be used.

8. WATER FOR CONCRETE

a) WATER TO BE CLEAN: Clean fresh potable water only shall be used for mixing concrete, grout and mortar.

The water shall be free from deleterious matter in solution or in suspension and shall meet the requirement of

IS:456 and shall be obtained from an approved source. Water samples shall be tested once a week at site and

once a month in an approved laboratory (third party testing).

b) STORAGE: The Contractor shall make adequate arrangements to store sufficient water at the works for use.

9. ADMIXTURES FOR CONCRETE

a) APPROVAL: Admixtures for concrete if proposed by the Contactor and approved by the Engineer shall be

obtained only from the manufactures approved by the Engineer. The Contractor shall obtain full details from the

manufacturer and shall carry out such field tests, as the Engineer shall require before any admixture is used in

the works. Calcium chloride or admixtures containing chloride shall not be used.

b) Water proofing Compound: Waterproofing compound to be used in concrete, plaster, damp proof concrete,

etc where specified shall be~ from approved standard manufactures and shall be approved by the Engineer If

shall comply with the requirements of IS:2645.lt should be mixed as per specifications supplied by

manufacturer but not exceeding 3% by weight of cement and approved and directed by the Engineer.

10. WORKMANSHIP: - CONCRETE

a. DESIGN OF CEMENT CONCRETE MIXES:

All concrete shall be controlled and machine mixed unless otherwise directed by Engineer-In-charge. For

controlled high-grade concrete the grading of aggregates shall be got approved from the Engineer. The correct

proportion and the total amount of water for the mix will be determined by means of preliminary tests and shall

be got approved by the Engineer. However such approval does not relieve the contractor from his responsibility

regarding the minimum strength requirements. Test shall be taken in accordance with relevant codes

specifications to ascertain the strength.' Proportioning of aggregates shall be done by weight, if so ordered by

the Engineer. All mixing shall be done by mechanical means in approved mixers. The Engineer may at his

discretion, allow in writing hand mixing of concrete for minor items where small quantities are involved about

in that case the contractor shall increase the cement content of the mixture by 10% without any extra cost to

Maharashtra Maritime Board. If change of grade of concrete during execution is required only extra/less cost of

cement will be considered for addition or deduction of the main item. No other charges will be considered. The

formwork used shall preferably of steel or with lining of steel. Wooden shuttering may be allowed at the

discretion of the Engineer e.g. that for lintels small slabs and beams, coping etc. The concrete shall be

mechanically vibrated for proper compaction by the method approved by the Engineer-in-charge. The concrete

shall be cured only by sweet potable water for the period specified in the detailed specification or as directed by

Engineer-in-charge.

Page 75: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

75

Contractor No. of corrections Executive

Engineer

b. TRANSPORTATION OF CONCRETE:

The concrete shall be transported from the mixer to its place in the works as rapidly as possible and in such a

manner that there shall be no separation or loss of its ingredients. For such purpose as far as possible, truck

mounted transit mixers shall be used. In no circumstances shall more than half an hour elapse between the time

water is added to the mix and the time when the concrete is finally compacted in position. No concrete shall be

permitted to be used in the works after initial set has taken place. The use of concrete distributing chutes at an

angle of more than 45 degrees from the horizontal will not be permitted without the sanction of the Employer.

c. AUTHORIZATION TO POUR

Authorisation to pour concrete shall be obtained from the Engineer-in-charge at least one day in advance of each

pour. No Concreting shall be started without the authorization of the Employer.

d. COMPACTION OF CONCRETE

The Contractor shall agitate the placed concrete thoroughly into place by means of a sufficient number of

approved mechanical vibrators of adequate power and having a frequency of not less than 6000 impulses per

minute. The vibrator shall be allowed to sink freely of its own weight until it enters the previous lift It shall be

withdrawn immediately at the same rate and used at a new location Concrete once vibrated shall not be vibrated

again. The Contractor shall ensure that the concrete is thoroughly worked around the reinforcement and against

external shutters so that all entrained air is expelled and the concrete surface when exposed is found good and

free from air pockets honey combing or other defects. Retamping of concrete of mortar, which has partially

hardened, shall not be permitted.

e. SCREEDDING

Screeding (Non Structural)over the decking shall be of reinforce concrete of minimum thickness of 75 mm and

rates of providing the same shall be included in rates quoted in the price schedule. All the surface of slabs of

slabs or other members not required to be shutters are to be screeded in an approved manner and within a

tolerance of plus/minus 3 mm of true level and grade. In making such finish care shall be exercised not to work

in excess fines to the top. Surface shall be scrubbed/cleaned and all laitance removed before screed is placed.

Care is to be taken to ensure that the concrete is properly compacted and for this purpose vibrator screed boards

or plates will normally be required.

f. FINISHING

Immediately on removal of forms the cement concrete work shall be examined by the Engineer before any

defects are made good. The work that has sagged or contains honey combing to an extent detrimental to

structural safety or architectural concept shall be rejected. Surface defects of a minor nature shall be rectified

generally as indicated below. Surface defects, which require rectification when forms are removed usually,

consists of bulges due to movement of forms, ridges at form joints, honey-combed areas, damage resulting from

the stripping of forms and bolt hole. Bulges and ridges shall be removed by careful chipping from the tooling

and the surface is then rubbed with grinding stones. Honey combed and other areas shall be chipped out, the

edges being cut as straight as possible and perpendicular to the surface, or preferable slightly under cut to

provide a key at the edge of the patch. Bolt holes shall be closed by cement mortar to ensure thorough filling

shallow patches shall first be treated with a coat of thin grout composed of one part of cement and one part of

Page 76: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

76

Contractor No. of corrections Executive

Engineer

sand and then filled with mortar similar to that used in concrete The mortar is placed in layers not more that 10

mm thick and each layer shall be given a scratch finish to secure bond with the succeeding layer. The last layer

shall be finished to match the surrounding concrete by floating, rubbing or tooling on formed surfaces by

pressing the form material against the patch while the mortar is still plastic. Large and deep patches requires

filling up with concrete held in place by forms Such patches shall be reinforced and carefully dowelled to the

hardened concrete. The same amount of care to cure the material in the patches shall be taken for the whole

structure. Curing shall be started, as soon as possible after the patch is finished to prevent early drying.

Damp Hessian cloth may be used. But in some locations it may be difficult; a membrane-curing compound will

be most convenient.

g. CURING

All concrete shall be protected during hardening from the harmful effects of sunshine moisture and drying

winds. All exposed faces of concrete shall be kept continuously moist for a period of 10 days. In the case of

slabs or other pours of large surface area timber frames, designed to the approval of the Employer, and covered

with two thickness of damp Hessian shall be places -over the concrete, immediately after pouring. When the

concrete has set, the frames shall be removed and the covering laid directly on the concrete. For 10 days

thereafter concrete shall be kept continuously damp by spraying the cover with clean fresh water or by covering

it with not less than 25 mm thickness of sand and kept continuously damp or by founding where practicable. In

very hot weather precaution shall be taken to see that temperature of concrete does not exceed 35º C while

placing. In places where water curing is not possible approved curing compound shall be applied as per the

procedure laid out by the manufacturers cost of which shall be deemed to be included in the rates and prices.

h. Samples from the fresh concrete shall be taken as per IS 1199 and cubes shall be made cured and tested at 28

days in accordance with IS 516. Frequency of sampling shall be as per IS:456-2000. Concrete in a section of

the works shall be considered acceptable strength wise provided:

1. The average 28 days strength of the test cubes relating to the section of the exceeds the specified strength of a

concrete class under consideration, given in table 1.1 of Sub Clause II it above by ten percent (10%)

2. Each of the above individual test cubes exhibits strength greater than eighty five percent (85%) of the strength

specified for a concrete class under consideration and average of the cube strengths.

Favg >fck+ [1.65 -1.65 n]

Where = Standard deviations

N= number of samples tested till date

3. Not more than five percent (5%) of the test result shall fall below the specified strength of a concrete mass under

consideration.

11. Excavation for all works and of material required for filling shall be to the exact width, length and depth shown

on the Drawings or as directed by the Architect. If taken out to greater width, length or depth than required,

extra depth shall be brought up by sound masonry or concrete filling and extra length or width filling in by

rammed earth or murrum, shall be done at the contractor’s expense. Excavation material required for filling

shall be stacked or dumped where indicated by the Architect. Excavation material nor required for filling and

Page 77: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

77

Contractor No. of corrections Executive

Engineer

any surplus material from the stacks or dumps retained for filling shall be removed and spread on the site where

and as directed by the architect. The cost of such removal and site where and as directed by the architect. The

cost of such removal and spreading shall be borne by the contractor and held to be included in the Contractor

Rates.

11.1 The contractor shall at the Contract Rates, provision for all shorting pumping, dredging. Bailing our or draining

water; whether subsoil or rain or other water and the excavation shall be kept free of water while the masonry

work or concrete work is in progress and until the architect considers the work well set. The sides of trenches

shall be kept vertical and the bottom horizontal and shall be run level throughout, or properly stepped as directed

by the Architect. The contractor shall at his own expense, also make level and hard the pit of all excavation and

consolidate the earth about the same at against all walls, pits, drains etc.

11.2

a. Excavation in ordinary soil means excavation in ordinary hard soil including stiff heavy clay or soft

compact murrum, or any other material which can be removed by the ordinary application of picks.

b. Excavation in murrum means excavation in hard murrum or any other hard strata which cannot be removed

by the ordinary application of picks but can be removed by application of crowbars.

c. Excavation in rock means excavation in a material which cannot be removed by application of pickaxe or

crowbars but can only be removed by blasting or by application of chisel and hammer. If the rock is to be

removed by balsting, the work shall include obtaining all necessary permissions, licences etc. for explosives

and complying with all the requirements stipulated by the authorities.

11.3 DISPOSAL OF EXCAVATED EARTH : Where the disposal of excavated earth is specified to be measured

and paid for separately, the quantity of disposal of earth, rock etc. shall not exceed the quantity paid as

excavation i.e. the elements of bulkage is not to be reflected in the measurements for disposal but is to be

accounted for in the rates quoted for disposal. All the materials such as earth, murrum, soft/hard rock, etc. are to

be kept separately for classification and payment of disposal.

No separate payment shall be made for re-excavation or loosening of excavation earth for disposal and

transportation due to its having become hard or consolidated due to passage of time rains or any other cause

whatever. The lead shall be measured by short-test route possible.

11.4 Measurements of excavation rock shall be on the basis of stacks of the excavated materials, with deduction at

15% of voids in stacking. Making of stacks and the subsequent disposal of the excavated rock as directed, shall

be a part of the work under these items.

12. CEMENT : Cement to be used on the works shall comply in every respect with the requirements of the Latest

Indian Standard Specification No. 269 for Portland cement and shall be obtained from approved sources.

Page 78: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

78

Contractor No. of corrections Executive

Engineer

Certificates of tests from an approved, laboratory shall also be obtained at the contractor’s own cost. samples for

testing shall be extracted as in IS : 269 within one week of delivery and the tests shall be made within four

weeks of delivery. All cement shall stored in suitable weatherproof from structures so that it does not come in

contact with ground and is prevented from being damaged by moisture. These buildings shall be provided for

adequate storage of cement bags by the contractor at his own cost5 and placed in locations approved by the

architect.

12.2 AGGREGATES : All aggregates generally conform to the requirements in latest IS : 383. Each size of

aggregate shall be stored on a separate platform or stock-pile shall be sufficiently removed from each other to

prevent the material at the edges of the piles from becoming inter-mixed

12.3 SAND : shall be of an approved quality, clean sharp and free from injurious amount of dust, mica, shells, soft

and flaky particles, shale, alkali organic matter, loam or other deleterious substances. The sand shall be taken

from a source approved by the architect and if required by him it shall be thoroughly washed, screened and

graded by the contractor at his own expense to, his satisfaction.

12.4 The whole of the ingredients of the coarse aggregate shall consist of hard stone free from deleterious substances

and shall contain no soft or elongated pieces.

12.5 MIXING WATER : The water for making concrete shall be first tested at the contractor’s expense for its

suitability by a laboratory approved by the architect. Water shall be reasonably free from such impurities as

suspended solids, organic matter and dissolved salts which are frequently contained in natural water and which

may adverse affecting the properties of the concrete, especially the setting and hardening.

12.6 ORDINARY CONCRETE : The concrete work shall be as per latest I. S. : 456/1978.

12.7 PLACING : It is important that the concrete be placed in its final position before the cement reaches its initial

set. The concrete should normally be compacted in its final position within 30 minutes of leaving the mixer and

once compacted not to be disturbed. Before the concrete is actually placed in position, the insides of the forms

should be inspected to see that they have been cleaned and oiled. Temporary openings should be provided to

facilitate inspection, especially at the bottom of columns, to permit the removal of all sawdust, wood shavings,

cigarette the forms will drain away. No water should be left in the form.

12.8 COMPACTING : The object of compacting concrete is to achieve miximum density. The concrete should

therefore placed a little in excess of its specified depth, so that after proper compaction its final desired depth is

obtained. Manually rodding and tapping the concrete and tapping the actual pouring head, while compacting the

concrete with mechanical vibrations shall be done sufficient distance away from the pouring head, so that the

vibrator is utilized only to compact the concrete and not to spread it. Beams and columns shall be vibrated using

immersion vibrators as per I.S. : 2505 and 3558, thin sections like water tank walls shall be vibrated using

clamp on vibrators and slabs shall be vibrated using surface vibrators. The contractor shall it all times have in

reserve sufficient vibrators of each variety to guard against shut down of the work occasioned by the failure of

the equipment in operation and to permit to equipment to the serviced and overhauled in rotation. No concreting

Page 79: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

79

Contractor No. of corrections Executive

Engineer

will be permitted in the event of power failure or vibrator failure. The Engineer may, however at his absolute

discretion, permit concreting by increasing the slump and correspondingly increasing the cement contents at

contractor’s cost, but in that cost the concrete compacted without mechanical vibration shall be paid for a rate of

10% less than contract rates. Except for shallow or in accessible concrete the vibrator shall be penetrated

vertically and at regular distance interval, not at an angle and nor at haphazard internals. It is better to vibrate at

smaller intervals for shorter periods of time, rather than at wider intervals for longer periods of time. The time

and intervals shall be subject to the approval of the Engineer.

At corners obstructions, embedded fixtures and congested reinforcement areas, the vibrator shall be manipulated

with the almost care and handling only by the most experienced workmen.

12.9 CURING : All freshly placed concrete surfaces shall be protected from the elements and from defacement

during building operations. The contractor shall provide and use. Where directed by the Engineer, enough

tarpaulins or other suitable materials to cover completely or enclose all freshly finished concrete. As soon as the

concrete has hardened sufficiently to prevent damage, it shall be cured by maintaining the concrete in a damp

condition by application wet stacking or other approved moisture retaining covering for a period of 28 days after

placing the concrete.

Extreme care should be taken to ensure that all surfaces are kept in a moist condition and no local area shall be

allowed to dry out intermittently.

13. FORMWORK : -

F) FORMWORK : The term “FORMWORK” OF “SHUTTERING “ shall include all forms, moulds,

sheeting, shuttering, planks, walers, poles, posts, shores, struts, and strutting, tiles uprights, walling

steel roads, bolts, wedges and all other temporary supports to the concrete during the process of setting.

All shuttering planks shall be adequately backed an supported to the satisfaction of the architect by a

sufficient number and size of supporting members to ensure rigidity during concreting. To avoid delay

and unnecessary rejection of forms the contractor shall obtain the approval of the architect for the

design of forms and the type of timber used before fabrication forms.

G) ERECTION OF FORMWORK : Care shall be taken that all formwork is set plump and true to line

and level or camber of batter where required as specified by the architect without links or twists. All

shutters shall be adequately strutted and braced and propped to the satisfaction of the architect to prevent

deflection under the dead weight of concrete and super- imposed liveload of workmen, materials and

plant.

The following tolerances will normally be observed in erecting formwork. But may be varied as directed

by the architect : -

i. For columns, beam, slab or any member dimensions, plus or minus 6 mm.

ii. For column plumb above lowest point in the column, plus or minus 3 mm.

Page 80: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

80

Contractor No. of corrections Executive

Engineer

iii. In beam or slab soffit level, plus or minus 6 mm.

iv. In beam or slab plumb, plus or minus 3 mm.

v. Along any surface, whether face or column or beam or soffit of slab, a deviation from the

true plumb or plus or minus 3 mm in 3 metres.

Formwork shall be so arranged as to permit removal without jarring the concrete. Wedges clamp and bolts

shall be used wherever practicable instead of nails.

H) Timber /Steel surface of forms in contact with concrete shall be oiled with a quality mould oil or clean

diesel oil approved by the architect. Oiling shall be done before reinforcement has been placed and care

shall be taken than no oil comes in contact with reinforcement while it is being places in position. The

formwork shall be kept thoroughly wet during concreting and the whole time that it is left in place.

Immediately before concreting is commenced the formwork shall be carefully examined to see that all

dirt, shaving, sawdust and other refuse have been removed by brushing and washing.

I) REMOVAL OF FORMWORK : The minimum period for keeping formwork in position shall

conform to Indian Standard Specifications and shall be as follows :-

( a ) Vertical sides of beams, walls and columns. … 48 hours.

( b ) Bottom of slabs upto 4.6 M. span… 7 days.

( c ) Bottom of slabs above 4.6 M. span

bottom of beams upto 6 M. span and

arch ribs bottom upto 6 M. span.… 14 days.

( d ) Bottom of beams over 6 M. span and

arch rib bottom above 6 M. span. … 21 days.

The architect may vary the above period if he considers it necessary.

J) HACKING – OUT : Immediately after removal of forms, the concrete surface to be plastered shall be

roughened with brush- hammer or with chisel and hammer as directed by the architect to make the

surfaces sufficiently coarse and rough to provide a key for plaster.

14. REINFORCEMENT :-

(1) STEEL : Mild steel for reinforcement shall conform in every respect to the latest Indian Standard

Specifications for Mild Steel Bars, I.S. : 432 ( Part I ) – 1966. High strength deformed steel bars Grade Fe –

415 conforming to latest I.S. : 1786-1985.

Page 81: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

81

Contractor No. of corrections Executive

Engineer

(2) REINFORCEMENT : All reinforcement for concrete work shall be executed on conformity with the R.C.C.

drawings, supplied and instructions given by the Structural Engineer and shall generally be carried out in

accordance with Indian Standard Specification. Every bar shall be inspected before assembling on the work and

any defective, brittle of burnt bars shall be removed. Cracked ends of bars shall be cut out.

(3) BENDING : All bars shall be carefully and accurately bent by the contractor in accordance with the R.C.C.

drawings and special care shall Cutting and Bending Schedule; AND (B) to see that the rods are placed in

exact positions. The bars should not be bent or straightened in any manner that will injure the material.

(4) LAPPING : As far as possible bars of the maximum length available shall be used. Laps shown on drawing or

otherwise specified by the Structural Engineer will be based on the use by the contractor of bars of maximum

length. In case the contractor wishes to use shorter bars, laps shall be provided at the contractors cost in the

manner and at the locations approved by the structural Engineer. Lap lengths shall be in accordance with

respective I. S. Code.

(5) SPACING, SUPPORTING AND CLEANING : All reinforcement shall be placed and maintained in the

positions shown on the drawings.

The contractor shall provide approved types of supports as specified on the drawings for maintaining the top

bars of the slab in positions during concreting. Precast blocks of cement mortar 1:2 about 40 mm square and

thickness equal to the clearance specified or P.V.C,. moulds of appropriate size shall be used to keep the

reinforcement bars in proper position ensuring the correct cover. Annealed steel wire 18 S.W.G. shall be used

as binding wire. All bars crossing one another shall be bound with this wire twisted tight to make the skeleton or

network righd so that the reinforcement is not displaced during placing of concrete.

Bars must be cleaned before concreting commences. The bars shall be cleaned with dry gunny bags if they are

coated with rust or other impurities. On no account shall the bars be oiled or painted nor shall mould oil used

on the formwork be allowed to come in contact with the bars. Cement wash shall be permitted.

During placing concrete, greatest care shall be taken to prevent any displacement or bending of the bars, ties,

links, strips, or fabric. No person shall be allowed to walk on the reinforcement. Special wooden “ Ghodis "

should be made and used for this purpose.

(6) MEASUREMENTS : The weight of steel to be paid at the contract rates shall be the weight of bars as

mentioned on the drawing or as instructed by the Structural Engineer including stirrups, ties, and all other steel

works specified as reinforcement. Laps as specified on the drawings will be paid for. Laps required because of

the contractor’s use of shorter bars will not be paid for. The chairs, spacers, pins etc. will not be paid for. The

contractor should include the cost of them in his unit rate of item.

Page 82: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

82

Contractor No. of corrections Executive

Engineer

15. BRICK MASONRY WORK :-

(1) BRICKS : All bricks used on the works shall be first class bricks to be approved by the architect and shall be

uniform in quality and size 230 * 115 * .55 mm. The bricks shall be obtained from a source approved by the

architect of uniform size, shape and colour and must be well burnt so as to give a clear ringing sound when

struck. No brick after 24 hours immersion in water shall absorb more water tharn 15% of its own weight when

dry. The bricks shall not break when thrown on the ground or struck against other bricks and shall have sharp

edges and angles and even surfaces. No under-burnt or over-burnt brick shall be used. Samples of all bricks

specified shall be taken at random from the first lot and shall be deposited with the architect or his representative

before being used in the works and all subsequent deliveries of bricks shall conform to the standard of the

approved samples.

(2) All brick work shall be of English bond and all necessary closer bricks etc. necessary to comply with the

requirements of the Bond specified or to break joints effectively shall be procured by the contractor and used

for the works. Ordinary there would be four courses per foot of height or in other words, the horizontal bed

joints shall be worked up into all joints and no hollow space shall be left in any portion of the work. Any brick

dismantled from the work for the purpose of testing the workmanship shall be in case of good work that could

be passed be completely covered with mortar on all sides; if any portion of such dismantled bricks are found not

covered with mortar, the entire work is liable to rejection.

(3) All bricks shall be thoroughly soaked by keeping them under water for atleast 12 hours before use. The practice

of dipping the bricks in water just before use will not be allowed. All necessary water cisterns for this purpose

shall be constructed or tubes brought by the contractor, to the satisfaction of the architect to ensure proper

soaking of bricks.

(4) The joints in brick work shall be regular and level and truly vertical, the work shall be checked with levels,

plumbs bob or square and shall be truly plumb and in all other respects of such a quality as to give entire

satisfaction to the architect or his representative. No bats or broken bricks are to be used other than as closers.

All finished work shall be raked back in course. When new work is to be jointed to unfinished work, the

surfaces of the unfinished work shall be cleaned and thoroughly wetted. The finished work shall be true in line

and level. All uneven, irregular and disturbed brickwork shall be pulled down and rebuilt with fresh brickwork

at the contractor’s expense. Joints in brickwork shall be raked to a depth of 3/4” minimum as the work proceeds.

Raking out of each days work shall be done on the same day. Brickwork shall not be raised by more than 8

single courses per day.

(5) While taking measurements, deductions shall be made for all the openings lintels, cills etc. occupying any

thickness of walls.

16. PLASTERING AND POINTING :-

(1) Cement and sand shall be as described earlier in these specifications, conforming to latest I. S. code.

(2) Preparation of surfaces for application of plaster :-

• ROUGHENING: Concrete surface shall be roughened by wire burshing , hacking or bush-hammering or

chiseling. If the architect is not satisfied with the roughening achieved by these methods he may order other

methods such as washing with acid etc.

Page 83: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

83

Contractor No. of corrections Executive

Engineer

• CLEANING : loose layers of dust etc., on surfaces to be plastered shall be washed. The surfaces shall be

cleaned to remove oil, paint or any other material that might interface with satisfactory bond and saturated

with water so as to be damp when the plaster is applied. All brick work surfaces shall be prepared as

described earlier in clause 5 (4) of these specifications.

(3) PROPORTIONING : The materials used in the preparation of plaster may be measured either by volume

using gauge boxes or by weight.

(4) MIXING : CEMENT AND SAND PLASTER : Cement and sand shall be mixed dry in the required

proportions to be obtain a uniform colour. Water shall then be added to get the required consistency for the

plaster.

(5) APPLICATION : For external plaster. The plastering operations shall be started for the top floor and carried

downwards. For internal plaster, the plastering operations may be started wherever the building frame and

cladding work are ready. For internal plastering , scaffolding be erected independent of walls. No member off

scaffolding shall be allowed to be housed in the wall being treated with plaster. Scaffolding for external plaster

shall also be supported independent of walls as far as possible to avoid patchy appearance.

(6) CEMENT AND SAND PLASTER SMOOTH FINISHED : The cement mortar of the proportions 1 cement

to 4 sand shall be applied on all the walls, bricks or concrete surfaces specified to a uniform thickness and shall

be troweled smooth using a woodfloat. Use of dry cement to obtain smooth finish while troweling shall not be

permitted.

(7) SANDFACED FINISH : Cement and sand mortar shall be applied but troweled rough to receive the final

coat. This shall be kept thoroughly wet for two days.

The cement mortar of the same proportions but with finer and uniform sand, shall be applied on the previously

plastered surface to a uniform thickness of ¼” and shall be troweled to get a uniform surface. A sponge dipped

in cement water shall be used with a circular motion to get sandy appearance.

(8) NEERU FINISHED PLASTER : The plastering shall be troweled to a fair and uniform thickness of ¾”

without any depression. Neeru shall then be applied to a uniform a thickness of 3 mm and thoroughly troweled.

This troweling process shall continue the succeeding day also to get a smooth surface. The plaster wall shall be

kept thoroughly wet by sprinkling water for 3 days when plaster starts drying. One coat of lime wash shall be

given on all the neeru finished surfaces after 10 days to prevent hair cracks.

(9) WETTING AND CURING : Surfaces to be plastered shall be profusely watered well in advance before

plastering so as to keep the surface damp. Plastered surfaces shall be kept thoroughly wet by sprinkling water

for at least 7 days as directed by the architect. Surfaces with craziness or cracks shall be rejected and the

contractor shall dismantle such plaster forthwith and apply plaster all over again. To avoid cracks at the junction

of concrete with brickwork the plaster shall be reinforced at such junction by fixing standard wire mesh as

directed by the architect. The wire mesh shall overlap concrete and brick surface by at least 50 mm.

(10) POINTING : The joints of the masonry either brick or stone to pointed shall be raked to a depth of about 20

mm while the mortar in the joint is still fresh and the joints shall be kept well wetted till the pointing is done.

The mortar for the pointing shall consist of one part cement and two part sand and shall be applied to the wetted

joints uniformly. The lines shall be regular and uniform in breadth. The edges of the pointing shall be cut off

parallel so as to leave well defined lines. The pointing shall be cut off parallel so as to leave well defined lines.

The pointing shall be kept well wetted for five days after the pointing is done.

Page 84: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

84

Contractor No. of corrections Executive

Engineer

(11) THE MODE OF MEASUREMENT : The rate for plastering shall be paid for the area actually plastered

measured prior to plastering. The above applies for cement pointing also.

17. FLOORING : -

1) VITRIFIED TILES :

Vitrified polished floor tiles shall be of 1st quality. These vitrified tiles are classified under group B1a of the

International Standard for ceramic tiles ISO: 13006. Tiles shall be hard, dense, impervious and frost resistant.

Water absorption of tiles shall be less than 0.5% and flexural strength (Modulus of Rupture) shall be more than

35 N/Sqmm. Vitrified polished floor tiles shall be provided of sizes, colour, shades, texture and designs as

indicated and if size not indicated it shall be 600mm x 600 mm/ 605 x 605 mm. The thickness shall be as

specified by the manufacturer but not less than 8mm. 1.2 Heavy duty vitrified unpolished floor tiles for exterior

use shall be of 1st quality. Heavy duty vitrified tiles shall be acid and alkali resistant, weather proof, anti skid

and abrasion resistant as per International Standard for ceramic tiles ISO :13006 and EN 176 requirement. These

tiles shall comply with. the following requirements:

(a) Water absorption<2%

(b) Flexural strength>35 N/Sqmm

(c) Moh's Hardness>6

(d) Abrasion resistance<204mm

Heavy duty vitrified tiles shall be of sizes, colour, texture and designs as indicated but size if not indicated it

shall be of 300mm x 300 mm . The thickness shall be as specified by the manufacturer.

Bedding

The screed bed for laying Vitrified Tiles shall be of cement and sand mortar as indicated. Bedding over which

the tiles shall be laid shall not be less than 10mm at any place.

Laying

Base concrete or RCC slab shall be cleaned and wetted. The bedding shall then be laid evenly over the surface,

tamped and corrected to desired levels and allowed to harden enough to offer a rigid cushion to tiles. Before

laying the tiles, tiles shall be washed and then applied fine cement slurry on the back of the tile to ensure full

and proper bedding. Tiles shall then be placed on bedding, each tile being gently tapped with rubber hammer in

its position till it is properly bedded and in level and line with adjoining tiles. Use of spacers is recommended

for uniformity in joints and better finish. Remove the residual cement or jointing material immediately by a wet

sponge. After 24 hours when the tiles are properly set and cured, fill the joint gaps with joint filler as per

recommendation of manufacturer. The joint gap shall be filled by spreading joint filler paste in the spaces

between the tiles with the help of rubber trowel. Clean the tiles surface immediately with the help of wet sponge.

Vitrified Porcelain Tiles can be laid in flooring over Base concrete or RCC slab directly by using suitable

chemical adhesive as per manufacturer’s instructions if so indicated.

2) CERAMIC TILES

Ceramic Glazed wall tiles shall be of 1st quality and shall conform to IS :13753. The surface of tiles and

components can be smooth, profiled, decorated or finished, glossy, matt or semi-matt as indicated. The tiles

shall be flat true to shape, sound and free from flaws and other manufacturing defects. The top surface of the

Page 85: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

85

Contractor No. of corrections Executive

Engineer

tiles shall be glazed. The underside of the tiles shall be free from glaze in order that the tiles may adhere

properly to the base. The glaze shall be uniform in quality and shall be free from welts, chips, craze, crawling or

other imperfections, detracting from appearance when viewed at a distance of one meter. The texture and colour

of tiles shall be as indicated. Tiles shall be of sizes as indicated. If not indicated size of tile shall be 200mm x

300 mm. The thickness shall be as specified by the manufacturer but in no case it shall be less than 6mm.

Ceramic Glazed floor tiles shall be of 1st quality and shall conform to IS :13755. The surface of tiles and

components can be smooth, profiled, decorated or finished, glossy, matt or semi-matt (anti skid) as indicated.

The tiles shall be flat true to shape, sound and free from flaws and other manufacturing defects. The top surface

of the tiles shall be glazed. The underside of the tiles shall be free from glaze in order that the tiles may adhere

properly to the base. The glaze shall be uniform in quality and shall be free from welts, chips, craze, crawling or

other imperfections, detracting from .appearance when viewed at a distance of one meter. The texture and colour

of tiles shall be as indicated. Tiles shall be of sizes as indicated. If not indicated size of tile shall be 300mm x

300 mm. The thickness shall be as specified by the manufacturer but in no case it shall be less than 6.5mm.

CERAMIC GLAZED TILES FLOORING / CERAMIC GLAZED WALL TILES IN DADO AND

SKIRTING

Bedding

The screed bed for laying Ceramic Glazed floor tiles shall be of cement and sand mortar 1:4. Bedding over

which the tile shall be laid shall not be less than 10mm at any place. Tiles shall be soaked in water before laying.

Laying

Base concrete or RCC slab shall be cleaned and wetted. The bedding shall then be laid evenly over the surface,

tamped and corrected to desired levels and allowed to harden enough to offer a rigid cushion to tiles. Before

laying the tiles, cement slurry of honey like consistency at 3 kg/ sq m shall be applied over the bedding. At a

time area to accommodate about twenty tiles shall be applied with cement slurry. Tiles shall then be washed

clean and fixed in the grout one after the other, each tile being gently tapped in its position till it is properly

bedded and in level and line with adjoining tiles. The joints shall be as thin as possible but not exceeding 1.5mm

wide. The ceramic tiles shall be set, jointed with cement slurry and pointed in neat coloured cement to match the

colour of tiles. The surface shall be cured for seven days and then washed clean. In the cases of skirting and

dado, the wall surface shall be covered with about 10mm thick plaster of cement and sand mortar as indicated

and allowed to harden. The plaster shall be roughened with wire brushes or by scratching diagonal lines. The

back of tiles shall be buttered with cement paste and set on bedding mortar. The tiles shall be gently tapped in

position one after the other. Top of skirting or dado shall be truly horizontal and the joints vertical or as per

required pattern. Joints shall be flush pointed with white cement with pigment to match the colour of tiles.

3) POLISHED KOTAH STONE: Kotah stone shall be obtained from an approved quarry and shall be free from

all defects. The stone shall be approved colour and thickness as specified. The stone shall be machine cut as

specified and dressed square and shall have even fine double machine polished surfaces to a smooth finish. The

stone shall be machine cut as specified and dressed square and shall have even fine double machine polished

surfaces to a smooth finish. The surface to covered with flooring shall be closely picked or hacked in the case of

R.C.C. slabs and shall be thoroughly, cleaned. Lime mortar for bedding shall be of 1:2 and spread not exceeding

Page 86: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

86

Contractor No. of corrections Executive

Engineer

¾” thickness. The stones shall be laid in this bedding immediately and as each stone is laid in shall be tapped

with a heavy wooden mallet and set flush the joints of the work shall be located as specified by the architect and

shall have cement pointing of approved colour. On completion of the work the whole surface shall be cleaned of

dirt, mortar etc. and shall be thoroughly washed. The polishing shall be carried out in situ on the surface to

remove all unevenness.

18. CARPENTRY AND JOINERY :-

1) Timber used for joiner shall be of first quality Indian C.P. Teak wood unless otherwise specified, and shall be

well seasoned, cut square free from excess wane, from sapwood, dead knots or other defects. All timber for

carpentry, joinery, rough framework, backing rounds, fixing strips and the like shall be treated with an approved

wood preservative and the contractor shall strictly observe the manufacturer’s instructions for using this

material.

2) All workmanship shall be of the best quality, scantlings and boardings, shall accurately sawn and shall be of

uniform width and thickness throughout. All carpenter’s work shall be left with a saw surface except where

otherwise described. Work shall be accurately set out in accordance with the drawings and shall be framed

together with properly made joints. All brads, nails screws, screws, plugs, pins, etc. to the provides as necessary

and as directed and approved.

3) Timber is to be approved and purchased at the commencement of the contract for further seasoning on the site.

The preparation of timber is to commence simultaneously with the beginning of the work generally and to

proceed continuously until all the woodwork is prepared and stacked on or near the site. All timber of large

scantlings is to be sawn immediately the building is commenced to allow for any shrinkage that may take place.

4) Joints in various members forming any Timber Frame shall be provided only as shown in the drawings or as

directed by the architect. One sixteenth of an inch will be allowed for each rough face of the sizes specified,

except when described as finished. All work is to be properly tenoned, shouldered, wedged pinned, braced etc.

to the satisfaction of the architect and all properly glued with best quality glue. All joinery shall be finished off

in a proper manner, planed and sandpapered as required. Use of nails shall not be permitted. Fixing of members

shall be done by using screws of round brad heads, which shall be properly punched in ends of timbers builts

into walls shall have half an inch air space left between themselves and the walls. All exposed faces of

woodwork shall be sandpapered once, before erection for approval of the architect. No colour or other

preservations shall be applied without prior approval of the architect.

5) Frames for doors and windows will be provided with M.S. holdfasts made of 40 mm * 3 mm thick flats and

fixed into jambs with 1:2:4 P. C. C. 100 mm thick, 1200 mm high frames will be provided with 4 nos.

holdfasts, 2100 mm high frames with 6 nos. and frames above 2100 mm with 8 nos. holdfasts. For fixing timber

frames to concrete, Rawl plug and galvanized screws of 16 gauge shall be used wherever sprcified. Rawl plugs

and screws of gauge 16 shall also be used for fixing rough grounds, framing, hangers hat hooks, curtain rails etc.

Page 87: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

87

Contractor No. of corrections Executive

Engineer

6) The rate for doors and windows shall include the cost of fittings and fixtures, holdfasts, screws and rawl plugs

etc. and the costs of labour for fixing all the fittings. All fixtures shall be fitted with screws.

7) GLAZING : Glass of required thickness and type shall be fixed in T. W./M. S. sashes by means of glaziers

prigs 75 mm to 150 mm apart. The glaziers putty shall be made by mixing 3 lbs of powdered whiting 2 oz. of

white lead (dry) with 12 oz. of raw linseed

8) MEASUREMENTS : Measurements shall be in square feet measured clear between finished wall surfaces.

19. ALUMINIUM DOORS, WINDOWS , VENTILATORS & PARTITIONS ETC. :-

1) These shall be obtained from approved and established manufacturers, shall be of aluminium alloy conforming

to I.S. : 733 and sections shall generally conform to I.S. : 1948. These shall be fabricated as per the detailed

drawings. Frames for windows, ventilators etc. shall be square and rectangular standard sections. Both fixed and

openable frames shall be constructed of sections which have been cut to length, mitered and welded at corners.

Sub- dividing bars shall be tenoned and riveted into the frames. All frames shall have corner welded to a true

right angle. For side hung shutters, hinges shall normally be of projecting one made out of aluminium alloy and

riveted /welded to frames and shall have stainless steel pins. Handles, pegs and stay etc. shall be approved

quality aluminium or its alloy conforming to is specifications.

All types of shutters shall be fabricated, supplied and fixed as specified in the I.S. : 1948. The rate shall include

supplying and fixing all fittings and fixtures required for proper and safe operation.

The doors shall be fabricated by using standard aluminium alloy extruded sections as specified in I.S. : 1948.

The rate shall include supplying and fixing fittings and fixtures including approved locking arrangements as

directed.

The aluminium fabrication work shall be anodized to the British Standard 1616 : 1961 to give an anode film of

25 micron. The contractor shall take care to stack the fabricated frames etc. on site under bearers and supported

masonry, plaster or dis-similar metals shall be coated with a coat of zinc chromates conforming to I.S. : 104-

1950. The contractor shall cover all anodized finish work with a thick layer or cellulose butyrate to protect

surface from wet cement during installation. This coating shall be removed on completion. Before handing over,

the aluminium work shall be washed with mild solution or non- alkali soap and water.

2) GLAZING : Glazing shall be of approved specially selected quality glass of specified thickness and unless

otherwise directed it shall be provided on the exterior with metal beading.

i. FIXED GLAZING : The fixed glazing shall be of 5.5 mm thicker clear plate glass of Hindustan

Pilkington or other specified in the Bill of quantities other approved manufacture free from any defects etc.

as per general specifications.

Page 88: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

88

Contractor No. of corrections Executive

Engineer

ii. ALUMINIUM DOOR FRAMES AND SHUTTERS AND FIXED GLAZING FRAME WORK: The

aluminium framing members shall be of “ Indal ", “ Jindal ", “ Hindal " or other approved manufacture,

shall be as per I.S. Code of practice. The fabrication work shall be of best workmanship and free of all

defects in jointing in true line and plumb. All corner joints where aluminium shall be mechanically bolted to

neat hairline joints. Where aluminium components come in contact with any other metal or with masonry,

necessary insulating materials such as heavy coat of alkali resistance bituminous paint or zinc chromate

primer shall be provided. The framework shall be assembled with mechanical joints the strength being

assured through pressure die cost aluminium alloy corners. The corners shall be epoxy bonded to ensure

complete water tightness, trueness and strength. Glass beading shall be snapped in or screwed to the shutter

as directed. Pivot pin for doors shall be of steel zinc palted, cleats,jointing plate screws, nuts bolts etc. shall

be of aluminium steel ( Zinc plated ), brass locking arrangements will be provided. All aluminium framing

members shall be of sizes specified or shown on detailed drawing and shall be silvermatt finish anodized or

any other shed to 15 micron thickness. Rubber gasket used shall be of best approved quality.

iii. ALUMINIUM LOUVRS : Aluminium louvers shall be fabricated and pressed to the required shape (as

shown in detailed ) and of aluminium sheets of 18 gauge. The pressed aluminium louvers of required shape

shall be fixed to the aluminium framework in proper indication with sheet metal screws, rivets, nuts bolts,

cleats etc. as required.

Samples of fixed glazing sections and door shutters sections shall be got approved before proceeding with

the work.

20. PAINTING AND POLISHING :-

1) PREPARATION OF SURFACS : Timber Surface : Woodwork to be painted or polished shall be first

cleaned and rendered free from dust and dirt. The surfaces shall be rubbed down dry with sand paper to the

satisfaction of the architect.

2) PLASTERED SURFACE : The plastered surface to be painted shall be absolutely dry and free fro dust or

dirt. If ordered by the architect the surface shall be thoroughly sandpapered and all unevenness removed.

3) CEMENT PAINT : shall be of approved quality and shall be applied as specified by the manufacturer and to

the satisfaction of the architect.

4) WHITE WASH : White wash shall be prepared for fresh burnt white stone lime. The lime shall be dissolved

in a tub with a sufficient quantity of water and thoroughly stired and strained through a clean cloth.

5) The necessary colouring matter of approved quality and colour shall be added to white wash as directed. Only

was sufficient for the day’s work shall be prepared each morning. The wash shall be continuously stirred during

use. If the finished surface is powdery and comes off readily the work shall be rejected and rectified by the

contractor at his own cost to the satisfaction of the architect.

Page 89: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

89

Contractor No. of corrections Executive

Engineer

6) MODE OF MEASUREMENTS : As per the latest editor of I.S.I 1200.

21. METAL WORK :-

1) Steel used in the manufacture of rolled steel sections shall conform to I.S. 226 and I.S. 1977 latest edition or any

alternative quality of steel subject to structural.

2) ROLLING SHUTTERS : Rolling shutters shall be of approved manufacture suitable for fixing in the position

ordered i.e. outside, inside, below lintel or between jambs. Shutters upto 12 Sq.M. in area shall be manually

operated or “ Push Up “ type while bigger size shall be of reduction gear type mechanically operated by chain or

handles. These shall consist of 8 gauge sheet or as specified with 75 cm. M.S. lathes of best quality mild steel

strip machine rolled and straightened with an effective bridge depth of 16 mm and shall have convex

corrugation. These shall be interlocked together through their entire length with end locks. These shall be

mounted on specially designed pipe shaft. The spring shall be approved make coiled type. These shall be

manufactured from tested high tensile spring steel wire or strip of adequate strength to balance the shutters in

position. The spring pipe shaft etc. shall be supported on strong M.S. or malleable cast iron brackets.

Both the side guides and bottom rail shall be jointless and of single pieces in pressed steel, top cover of shaft,

spring etc. shall be of the same material as that of lathe. For rolling shutter and cover etc. shall be painted with

one coat of anticorrosive paint and two coats of synthetic enamel paint of approved quality and shade.

22. ANTI – CORROSIVE TREATMENT TO STEEL STRUCTURES :-Polysulphide epoxy zinc chrome anti-

corrosive primer a two component air drying polysulphide- epoxy composition with polyamino curing and anti-

corrosive chrome pigments as per manufacturers specifications.

23. WATERPROOFING BY APPROVED AGENCY :-

1) BASEMENT WATERPROOFING : The underground structures shall be treated by “ Box Method " 150 mm

thick layer of 1:3:6 cement concrete using No. 2 metal shall be laid with smooth surface finished, with trowel on

well compacted soil or rubble soiling or plum concrete in accordance with the solid strata.

On this ‘ centroof ' waterproof layer on cement base and about 75 mm thick shall be laid, using 1 layer of

shahabad stone placed diagonally with cut joints. After the R.C.C. raft is laid this treatment shall be carried

along with outer surface of the treatment to vertical sides shall be about 40 mm.

2) WATERPROOFING TO TOILET BLOCKS : All toilet blocks at upper floor levels shall be treated with

waterproofing on floors including 1200 mm brick bat coba, in lime mortar 1:2 laid to slope and upto 1000 mm

height of wall dado and shall be made properly watertight around all plumbing work.

3) TERRACE WATERPROOFING : The terrace shall be first treated with waterproofed brick bat coba in

cement mortar 1:2 laid to slope and of thickness as per the detailed drawings. The slopes shall be properly

graded for even flow of water towards the down take pipes. The junction of the slab and the parapet wall shall

Page 90: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

90

Contractor No. of corrections Executive

Engineer

be treated with waterproof flashings or fillet. The treatment of waterproofing shall be carried over the parapet

wall.

4) GUARANTEE FOR ALL WATERPROOFING WORK : The item of waterproofing shall be carried out by

agency to be approved by the consultants and to their specifications. A written guarantee in approved form shall

be furnished to certify that the waterproofing shall be free from defects of materials and workmanship for a

period of 10 years. The leakage, failure to stay in lace, splitting, pulling loose, illegatoring, tearing, undue

expension and contraction shall be judged as defective work.

24. ROAD :-

1) CEMENT CONCRETE PAVEMENT : The pavement shall consist of cement concrete 1:2:4 (1 cement :

2 coarse sand : 4 hand stone ballast 40 mm nominal gauge) or richer mix. as specified laid on the prepared

base including campaction and curing.

Materials such as water, cement, sand and stone ballast shall conform to the materials specification hereto

before mentioned.

The prepared surface shall conform to the line, grade and cross section shown on the plans and for this

purpose the sub-base shall be prepared by scarifying the existing surface where necessary and adding extra

material and consolidating. The forms shall be of steel and shall be of required section and length. They

shall be generally of channel section perfectly straight with a board base of sufficient stiffness to withstand

without displacement or distortion due to placing and compaction of the concrete. They shall be provided

with an efficient looking device to ensure continuity of line and level though joints and with steel pins to

hold them in position.

For mixing, placing in position the cement concrete specification mentioned hero to before shall apply.

The compaction shall be done by vibration. The vibration in the vibrator screed shall be of a frequency not

less than 3500 impulses per minute. Internal vibrator shall also be used when slabs more than 200 mm

thickness is laid. After compaction of the concrete in the base surface level shall be checked by straight

edge longitudinally and by temper transversely. any hollow spot or depression shall be made up with

cement concrete by compaction till a uniform surface is obtained. The surface may also be checked with a

string.

The road surface shall be belt finished. The belt usually consist of a piece of canvas 150 mm wide and one

metre longer than the width of the slab having wooden handles at each end. The process consists of a

preliminary stage when the belt shall be drawn slowly across by a service of long strokes and finally by

short strokes with rapid advance, intermediate stages being used as decided by the architects.

2) KERB STONE : These shall be of precast concrete kerb stones of size 450 * 300 * 100 mm and fixing

in foundation concrete 1:3:6 mix. The joints between each stone shall be cement pointed.

Page 91: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

91

Contractor No. of corrections Executive

Engineer

25. SHORE PROTECTION:

25.1 MATERIALS

(1) The rock used in the reclamation revetment shall comply with the recommendations of the CUR/CIRIA

Manual on the use of rock in coastal and shoreline engineering and shall be placed in accordance with those

recommendations. Alternatively the guidance as given in relevant & equivalent Indian standards shall be

followed subject to the approval of the employer’s representative.

(2) Rock shall be hard and durable. It should be free from laminations, cracks, seams and weak cleavage planes

and must not disintegrate or erode from the action of air, water, wetting and drying and impact due to wave

action. It shall be capable of being handled and placed without undue fracture or damage.

(3) Rock shall be sound, fresh material with the following physical properties

Relative Density (oven dried) 2.50 minimum

Wet Dynamic Crushing Strength 24% maximum

Water Absorption 3.0% maximum

Aggregate Abrasion Value 12% maximum

Magnesium Sulphate Soundness 12% maximum

Average Point Load Index 4.0MPa minimum

Dry Uniaxial Compressive

Strength

150 MN/m2minimum

Block Integrity Drop Test 5% Maximum

Aggregate Impact Value Less than 30% for Standard Fraction

Ten Percent Fines Not less than 100kN

(4) Testing for compliance with rock quality shall be in accordance with the following:

TEST STANDARD TEST

Relative Density BS 812 Relative Density

Wet Dynamic Crushing

Strength

CIRIA Publication 83/CUR

Report 154

Wet Dynamic Crushing

Strength

Water Absorption BS 812 Water Absorption

Aggregate Abrasion

Value

BS 812 Aggregate Abrasion Value

Magnesium Sulphate

Soundness

BS 6349 Part 1 Magnesium Sulphate

Soundness

Average Point Load Index CIRIA Publication 83/CUR

Report 154

Average Point Load Index

Dry Uniaxial

Compressive Strength

CIRIA Publication 83/CUR

Report 154

Dry Uniaxial Compressive

Strength

Page 92: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

92

Contractor No. of corrections Executive

Engineer

Block Integrity CIRIA Publication Block Integrity Drop

Drop Test 83/CUR Report 154 Test

Alternatively the guidance as given in relevant & equivalent Indian standards may be followed subject to the

approval of the employer’s representative.

(5) Rocks shall consist of fragments of approximate cuboidal shape with angular corners and the maximum

dimension should not exceed twice the overall minimum dimension.

25.2 REVETMENT CONSTRUCTION

(1) Revetment shall be placed to the levels and dimensions required by the Contractor’s design to the

approval of the Employer’s Representative. The Contractor shall demonstrate to the approval of the

Employer’s Representative that his method of working ensures that the revetments are founded on a

bearing stratum which provides adequate stability and that no soft or compressible materials are

incorporated within the structure or retained beneath it.

(2) For the construction of the revetment works soft material shall be removed.

(3) The Contractor's attention is drawn to the fact that the toe of the revetment shall be founded on a suitable

bearing stratum. The bearing stratum shall be sufficient to ensure the stability of the revetment and to

prevent post construction settlement of the toe.

(4) Rocks shall be individually placed by grab or equivalent method so as not to detrimentally affect any of

the properties specified above. Rocks shall not be dropped from a height greater than 1.5m and rock in

the primary layer shall be placed to ensure a minimum of three points of contact. Rocks in the revetment

shall not be tipped from vehicles, bull-dozed or dumped from rock trays into position.

(5) Interstices between adjacent armour rocks within the armour layer shall remain free of small rock

particles. The Contractor shall be required to remove and reconstruct the entire armour layer in areas

where the interstices become filled.

(6) Each placed rock layer shall be protected from damage by wave action or other causes as soon as

possible after placement. Material eroded by wave action of other causes shall be made good by removal

and replacing to the approval of the Employer’s Representative. The Contractor shall ensure that layers

interlock with the underlying layer and shall avoid any disturbance to previously placed layers or to the

filter layer when placing overlying layers.

(7) The Contractor shall initially construct a test panel or section which upon acceptance shall become the

model for further placement and shall remain part of the finished works. The length of the section shall

be not less than 10 meters and extend over the full height of the section. The tolerances and survey

methods are as described elsewhere in this specification.

(8) Where rock armour is used, each arriving stone shall be weighed individually and placed into a two

layer section using a mix of block weights representative of the specified gravity and size requirements.

(9) The trial panel shall be re-built if necessary until the values of Kb1 and Kb2 differ by less than 0.2t/m3.

Page 93: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

93

Contractor No. of corrections Executive

Engineer

(10) Upon acceptance of the trial section, the section shall be incorporated in the works and not disturbed. In

the event of the source of armour stone being changed, then the trial section procedure described above

shall again be carried out.

(11) No placing of armour other than the trial section shall be carried out until the trial section has been

accepted by the Employer’s Representative.

(12) Underlayer rock shall be deposited carefully to minimise disturbance to any already placed rock and to

avoid damage to any existing structures.

(13) For placing above mean sea level (MSL) tide level, the rock shall be placed to grade to ensure that the

larger rock fragments are uniformly distributed and the smaller rock fragments serve to fill the space

between the larger rock fragments in such a manner as will result in the resulting structure being well-

keyed, densely packed and of the specified dimensions.

(14) For placing below MSL tide level, handling and placing methods shall be approved by the Employer’s

Representative to minimise segregation of the stone grading and to ensure the specified dimensions are

achieved.

26. RECLAMATION:

The Reclamation fill should consist of sand with less than 12 percent passing 0.075 mm (No. 200) sieve.

However, sand containing between 12 and 30 percent fines may also be used. The minus No. 40 sieve fraction

should have a liquid limit less than 25 and a plasticity index less than 8. Silty gravel or gravel, sand and silt

mixture is also considered a suitable fill material.

Fill placed in paved areas or below specific facilities should be compacted in accordance with recommendations

given below for structural fill. Fill placed for landscaping purposes outside buildings and loaded roadway areas

is considered as general fill. Structural should be compacted to the applicable average in situ densities given

below. Clean sand should be compacted to the following relative densities based on limiting densities

determined in accordance with ASTM D-4253 and D-4254. Sand containing less than 12 percent passing 0.075

mm (No. 200) sieve is considered as clean sand.

• Structural fill consisting of clean sand should be compacted to an average relative density of 75 percent with

no test less than 70 percent, and The following criteria apply to fill containing greater than 12 percent

passing than 0.075 mm (No. 200) sieve.

• Structural fill should be placed slightly wet of optimum moisture content and compacted to 95 percent of

maximum dry density determined in accordance with ASTM D 1557 (modified Proctor)

Page 94: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

94

Contractor No. of corrections Executive

Engineer

SECTION – 6

FORM OF BID

Refer Part-II

Page 95: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

95

Contractor No. of corrections Executive

Engineer

SECTION – 7

BILL OF QUANTITIES

Refer Part-II

Page 96: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

96

Contractor No. of corrections Executive

Engineer

SECTION – 8

SECURITIES AND OTHER FORMS

Refer Part II

Page 97: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

97

Contractor No. of corrections Executive

Engineer

SECTION – 9

DRAWINGS

Refer Part II

Page 98: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

98

Contractor No. of corrections Executive

Engineer

SECTION – 10

DOCUMENTS TO BE FURNISHED BY THE BIDDER

(Attached)

Page 99: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 1 -

Contractor No. of corrections Executive Engineer

STANDARD BIDDING DOCUMENT

PROCUREMENT OF CIVIL WORKS

PART-II

COMPLETE BIDDING DOCUMENT

NAME OF

WORK :

Reconstruction & Extension of

Existing Jetty and Civil Work

(Reclamation Bund, Terminal

Building and other onshore work) at

Malvan Port, Tal-Malvan, Dist-

Sindhudurg.

E-TENDER

B-II TENDER FORM

Page 100: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 2 -

Contractor No. of corrections Executive Engineer

GOVERNMENT OF MAHARASHTRA

AGREEMENT NO---------------

NATIONAL COMPETITIVE BIDDING

(CIVIL WORKS)

Name of work : Reconstruction & Extension of Existing Jetty

and Civil Work (Reclamation Bund, Terminal

Building and other onshore work) at Malvan

Port, Tal-Malvan, Dist-Sindhudurg.

Tender Issue Date : Date. 08.05.2018 at 15.00 hrs

Time and date of pre-bid

conference

: Date. 18.05.2018 at 15.00 hrs, Maharashtra Maritime

Board, Indian Mercantile Chamber, 3rd floor, Ramjibhai Kamani Marg, Ballard Estate, Mumbai-400 001.

Opening Date

(If possible)

: Date. 04.06.2018 at 12.00 hrs Maharashtra Maritime

Board, Indian Mercantile Chamber, 3rd floor, Ramjibhai Kamani Marg, Ballard Estate, Mumbai-400 001

Officer inviting bids Chief Executive Officer, Maharashtra Maritime Board, Indian Mercantile Chamber, 3rd floor, Ramjibhai Kamani Marg, Ballard Estate, Mumbai-400 001

Page 101: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 3 -

Contractor No. of corrections Executive Engineer

SECTION 1 – INSTRUCTIONS TO BIDDERS (ITB)

Refer SECTION 1

Of

PART I

COMPLETE BIDDING DOCUMENT

Page 102: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 4 -

Contractor No. of corrections Executive Engineer

SECTION – 2

QUALIFICATION INFORMATION

Refer SECTION - 2

Of

PART I

COMPLETE BIDDING DOCUMENT

Page 103: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 5 -

Contractor No. of corrections Executive Engineer

SECTION – 3

CONDITIONS OF CONTRACT

Refer SECTION - 3

Of

PART I

COMPLETE BIDDING DOCUMENT

Page 104: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 6 -

Contractor No. of corrections Executive Engineer

SECTION – 4

CONTRACT DATA

Refer SECTION - 4

Of

PART I

COMPLETE BIDDING DOCUMENT

Page 105: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 7 -

Contractor No. of corrections Executive Engineer

SECTION – 5

TECHNICAL SPECIFICATION

Refer SECTION - 5

Of

PART I

COMPLETE BIDDING DOCUMENT

Page 106: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 8 -

Contractor No. of corrections Executive Engineer

SECTION – 6

FORM OF BID

Page 107: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 9 -

Contractor No. of corrections Executive Engineer

FORM OF BID

Description of the Work :- Reconstruction & Extension of Existing Jetty and Civil Work

(Reclamation Bund, Terminal Building and other onshore work) at Malvan Port, Tal-Malvan, Dist-

Sindhudurg.

To,

Executive Engineer, Maharashtra Maritime Board,

Indian Mercantile Chamber, 3rd floor,

Ramjibhai Kamani Marg, Ballard Estate,

Mumbai-400 001

1. We offer to execute the works described above and remedy any defects therein in conformity with the

conditions of contract, specification, drawings, Bill of Quantities and Addenda for the sum(s)

of .....................................................................................................

2. We undertake, if our Bid is accepted, to commence the Works as soon as is reasonably possible after

the receipt of the Engineer’s notice to commence and to complete the whole of the Works comprised

in the Contract within the time stated in the document.

3. We agree to abide by this Bid for the period of 120 days from the date fixed for receiving the same

and it shall remain binding upon us and may be accepted at any time before the expiration of that

period.

4. Unless and until a format Agreement is prepare and executed this Bid, together with your written

acceptance thereof, shall constitute a binding contract between us.

5. We understand that you are not bound to accept the lowest or any tender you may receive.

6. We accept the appointment of Shri. ........................................................ as the Dispute Review Expert.

(OR)

We do not accept the appointment of Shri. .......................... as the Dispute Review Expert and propose

instead that Shri. ........................ be appointed as Dispute Review Expert, whose BIO-DATA is

attached.

Dated this ....................... day of ......................... 20.................

Signature _______________________ in the capacity of _________duly authorised sign bids for and

on behalf of ...................................................................................................... (in block capitals or

typed)

Page 108: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 10 -

Contractor No. of corrections Executive Engineer

Address

..........................................................................................................................................................

Witness

..........................................................................................................................................................

Address

........................................................................................................................................................

Occupation

...................................................................................................................................................

# Note-The bidder will submit this form online without his financial offer. The bidder shall fill the rates online

in the BOQ sheet provided in the e-tender portal only.

Page 109: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 11 -

Contractor No. of corrections Executive Engineer

SECTION – 7

BILL OF QUANTITIES

Page 110: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 12 -

Contractor No. of corrections Executive Engineer

BILL OF QUANTITIES

Preamble

1. The Bill of Quantities shall be read in conjunction with the Instructions to Bidders, Conditions of

Contract, Technical Specifications and Drawings.

2. The quantities given in the Bill of Quantities are estimated and provisional, and are given to provide a

common basis for bidding. The basis of payment will be the actual quantities of work ordered and

carried out, as measured by the Contractor and verified by the Engineer and valued at the rates and

prices tendered in the priced Bill of Quantities, where applicable and otherwise at such rates and

prices as the Engineer may fix within the terms of the Contract.

3. The rates and prices tendered in the priced Bill of Quantities shall, except in so far as it is otherwise

provided under the Contract, include all constructional plant, labour, supervision, materials, erection,

maintenance, insurance, profit, taxes and duties, together with all general risks, liabilities and

obligations set out or implied in the Contract.

4. The rates and prices shall be quoted entirely in Indian Currency.

5. A rate or price shall be entered against each item in the Bill of Quantities, whether quantities are

stated or not. The cost of items against which the Contractor has failed to enter a rate or price shall

deemed to be covered by other rates and prices entered in the Bill of Quantities.

6. The whole cost of complying with the provisions of the Contract shall be included in the terms

provided in the priced Bill of Quantities and where no items are provided the cost shall be deemed to

be distributed among the rates and prices entered for the related Items of Work.

7. General directions and descriptions of work and materials are not necessarily repeated or summarized

in the Bill of Quantities. References to the relevant sections of the contract documentation shall be

made before entering rates or prices against each item in the Bill of Quantities.

8. The method of measurement of completed items of work for payment shall be in accordance with the

specification for Road and Bridge Works published by the Ministry of Road Transport & Highways,

(Vth Revision) April 2013.

9. Errors will be corrected by the Employer for any arithmetic errors pursuant to Clause 29 of the

Instructions to Bidders.

10. Rock is defined as all materials which, in the opinion of the Engineer, require blasting or the use of

metal wedges and sledge hammers or the use of compressed air drilling for its removal and which

cannot be extracted by ripping with a tractor of at least 150 kw with a single rear mounted heavy duty

ripper.

Page 111: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 13 -

Contractor No. of corrections Executive Engineer

BILL OF QUANTITIES

Schedule “B”

Item

No.

Description

Quantity Unit

per

Rate

Amount In

Figures

In

Words

1 Taking trial bores 75 to 100 mm for 53.0 to 88.9 mm

core dia over burden ( by diamond drilling machine )

such as soil of all \sorts, soft murum,hard murum

and boulders and in soft rock including all materials

such as casing pipes and accessories oil, grease,

steel, rods, and such other materials as required

(including conveying the material to site of work) .

Preserving the loose sample in glass jar and core

sample serially on site of work and conveying the

same to HQ of concernring office as directed.

a) over burden 0 to 50 meter.

15.00 Rmt

2 Taking trial bores 75 to 100 mm for 53.0 to 88.9 mm

core dia in rocks as specified below including all

necessary materials such as oil,grease,steel boostan

and such other materials as required (including

conveying the material to site of work) and

Preserving the core sample serially on site of work

and conveying the same to HQ of concernring office

as directed. Quartzite with diamond drill with Nx Bit

0 to 50 metre

4.50 Rmt

3 Providing tun tappa core boxes of jungle wood of

size1.25mx 0.35x 0.15m for preserving core sample

with all fixtures and fastening handles including

locking arrangment etc . complete.

3.90 No

4 Excavation for foundation in earth, soils of all types,

sand, gravel, soft murum including shoring and

strutting as necessary and disposing off excavated

stuff as directed etc. complete

4110.15 Cum

5 Supplying & laying trap stones weighing upto 20

Kg. for filter layer including quarrying,conveying

with all the leads & lifts laying in required line,

level, slope including necessary equipment and

machinerysuch as crane of adequate capacity and

boom length as directed etc complete, in the tidal

conditions.

Spec.No.-Rd-19,Page-187; Rd-29,Page-193; Rd-27,

Page-192.

[Except weight of stone specified in wording of

specification]

1446.41 Cum

Page 112: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 14 -

Contractor No. of corrections Executive Engineer

Item

No.

Description

Quantity Unit

per

Rate

Amount In

Figures

In

Words

6 Supplying & laying trap stones weighing upto 200

Kg. for core layer including quarrying,conveying

with all the leads & lifts laying in required line,

level, slope including necessary equipment and

machinerysuch as crane of adequate capacity and

boom length as directed etc complete, in the tidal

conditions.

Spec.No.-Rd-19,Page-187; Rd-29,Page-193; Rd-27,

Page-192.

[Except weight of stone specified in wording of

specification]

3599.30 Cum

7 Supplying & laying trap stones weighing 300 to 500

Kg. for sub armour layer including

quarrying,conveying with all the leads & lifts laying

in required line, level, slope including necessary

equipment and machinerysuch as crane of adequate

capacity and boom length as directed etc complete,

in the tidal conditions.

Spec.No.-Rd-19,Page-187; Rd-29,Page-193; Rd-27,

Page-192.

[Except weight of stone specified in wording of

specification]

599.70 Cum

8 Supplying & laying trap stones weighing above

1000 Kg. for armour layer including

quarrying,conveying with all the leads & lifts laying

in required line, level, slope including necessary

equipment and machinerysuch as crane of adequate

capacity and boom length as directed etc complete,

in the tidal conditions.

Spec.No.-Rd-19,Page-187; Rd-29,Page-193; Rd-27,

Page-192.

[Except weight of stone specified in wording of

specification]

1635.36 Cum

9 Supplying & spreading geofabric filter layer of

Geotextile of Polypropylene multifilament woven to

the line, evel and grade with pore size less than

0.075 mm and permeability greater than 9.0

litre/sqm/sec. confirming specification IS:1969 and

ASTM standard including conveying to the

site,joining and stitching with proper overlap and

laying at excavated surface in tidal condition as

directed by Engineer- in- charge etc complete .

As directed by Engineer -In- Charge.

4504.10 Sqm

10 Supplying hard murum / kankar at the road side,

including conveying and stacking etc. complete.

Lead upto 50M. (initial lead) (Includig Royalty) 3967.50 Cum

11 Spreading hard murum for side width etc. complete 4275.00 Sqm

Page 113: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 15 -

Contractor No. of corrections Executive Engineer

Item

No.

Description

Quantity Unit

per

Rate

Amount In

Figures

In

Words

12 Compacting the hard murum side widths including

laying in layers on each side with power roller

including artificial watering etc. complete. 3674.87 Sqm

13 Construction of granular sub-base by providing

close graded Material, mixing in a mechanical mix

plant at OMC, carriage of mixed Material to work

site, spreading in uniform layers with motor grader/

Paver on prepared surface and compacting with

vibratory power roller to achieve the desired density,

complete as per clause 401 -- Plant Mix Method and

Grading - III Material

183.30 sqm

14 Wet Mix Macadam -- Providing, laying, spreading

and compacting graded stone aggregate to wet mix

macadam specification including premixing the

Material with water at OMC in mechanical mix plant

carriage of mixed Material by tipper to site, laying in

uniform layers with paver in sub- base / base course

on well prepared surface and compacting with

vibratory roller to achieve the desired density.

Laying By Grader/Paver.

229.13 Cum

15 Providing and laying in situ / ready mix / ready mix

M15 cement concrete of trap/ granite/ quartzite/

gneiss metal in foundation including necessary

centering, formwork, bailing out water, compacting

and curing etc. complete. (with fully automatic

micro processor based PLC with SCADA enabled

with reversible drum type mixer/ concrete batch mix

plant (pan mixer) with natural /artifical sand)

164.32 Cum

16 Pavement Quality Concrete--Providing and laying

in-situ M40 Grade unreinforced plain cement

concrete pavement over a prepared sub base with 43

grade cement , coarse and fine aggregate conforming

to IS 383, using fine and coarse aggregates

combined gradation as per Table 600-3 of MORTH

Specification 2013, mixed in a batching and mixing

plant/ non tilting mixer and Weigh batcher as per

approved mix design, admixtures, transporting to

site, spreading, laying with approved make

paver,compacted and finished in a continuous

operation, finishing to lines and grades as directed

by Engineer-in-charge and curing by curing

compound /by providing cement vata in cement

Mortar 1:8 @0.6m X 0.6m centre to centre,

admeasuring 80 mm at bottom and 40 mm at top

with depth of 75mm and maintaining the same

throughout curing period by any other method

approved by Engineer-in-charge

150.00 Cum

Page 114: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 16 -

Contractor No. of corrections Executive Engineer

Item

No.

Description

Quantity Unit

per

Rate

Amount In

Figures

In

Words

17 Providing and laying in situ / ready mix M30 RCC

of trap/ granite/ quartzite/ gneiss metal for RCC

work of ballast walls, kerbs and box returns

including scaffolding, compaction,

formwork finishing and curing etc. complete.

(excluding reinforcement, with fully automatic

micro processor based PLC with SCADA enabled

concrete batch mix plant / pan mixer with Natural /

VSI standard Artificial Sand)

96.48 Rmt

18 Providing and laying Cast in situ/Ready Mix cement

concrete M- 35 of trap / granite /quartzite/ gneiss

metal for R.C.C. work in foundations like raft, strip

foundations, grillage and footings of R.C.C. columns

and steel stanchions etc. columns as per detailed

designs and drawing or as directed including

centering, formwork, cover blocks, laying/pumping,

compaction finishing the formed surfaces with

cement mortar 1:3 of sufficient minimum thickness

to give a smooth and even surface or roughening if

special finish is to be provided and curing etc.

complete,(Excluding reinforcement and structural

steel).with fully automatic micro processor based

PLC with SCADA enabled reversible Drum Type

mixer/ concrete Batch mix plant (Pan mixer) etc.

complete. With natural sand/V.S.I. quality Artificial

Sand

392.24 Cum

19 Filling in plinth and floors with approved excavated

material in 15cm. to 20cm. layers including watering

and compacting etc. complete. 330.48 Cum

20 Providing soling using 80 mm size trap metal in 15

cm. layer including filling voids with Crushed

sand/grit, ramming, watering etc. complete. 115.84 cum

21 Providing and laying Cast in situ/Ready Mix cement

concrete M-35 of trap / granite /quartzite/ gneiss

metal for R.C.C. columns as per detailed designs and

drawing or as directed including centering,

formwork, cover blocks, laying/pumping,

compaction finishing the formed surfaces with

cement mortar 1:3 of sufficient minimum thickness

to give a smooth and even surface or roughening if

special finish is to be provided and curing etc.

complete,(Excluding reinforcement and structural

steel).with fully automatic micro processor based

PLC with SCAD Aenabled reversible Drum Type

mixer/ concrete Batch mix plant (Pan mixer) etc.

complete. With natural sand/V.S.I. quality Artificial

Sand

39.86 cum

Page 115: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 17 -

Contractor No. of corrections Executive Engineer

Item

No.

Description

Quantity Unit

per

Rate

Amount In

Figures

In

Words

22 Providing and laying Cast in situ/Ready Mixcement

concrete M-35 of trap / granite /quartzite/ gneiss

metal for R.C.C. beams and lintels as per detailed

designs and drawings or as directed including

centering, formwork, cover blocks, laying/pumping,

compactionand roughening the surface if special

finish is to be provided and curing etc. complete.

(Excluding reinforcement and structural steel).with

fully automatic micro processor based

PLC with SCADA enabled reversible Drum Type

mixer/ concrete Batch mix plant (Pan mixer) etc.

complete. With natural sand/V.S.I. quality Artificial

Sand

69.41 Cum

23 Providing and laying Cast in situ/Ready Mix cement

concrete M-35 of trap/ granite / quartzite/ gneiss

metal for R.C.C. slabs and landings as per detailed

designs and drawings including centering,

formwork, cover blocks, laying/pumping,

compactionfinishing the formed surfaces with

cement mortar 1:3 of sufficient minimum thickness

to give a smooth and even surface or roughening if

special finish is to be provided and curing etc.

complete,(Excluding reinforcement and structural

steel). with fully automatic micro processor based

PLC with SCADA enabled reversible Drum Type

mixer/ concrete Batch mix plant (Pan mixer) etc.

complete. With natural sand/V.S.I. quality Artificial

Sand

125.70 Cum

24 Providing and laying Cast in situ/Ready Mix

cement concrete in M-35 of trap / quartzite

/granite /gneiss metal for R.C.C. Waist slab, and

steps of staircases as per detailed design and

drawings or as directed including steel

centering, plywood/ steel formwork, steel props,

laying/pumping, compaction, finishing uneven

and honeycombed surface with C.M. 1:3 of

sufficient minimum thickness to give a smooth

and even surface or roughening the surface if

special finish is to be provided and curing etc.

complete. (Excluding einforcement, including

cover block).(Newly laid concrete shall be

covered by gunny bag, plastic, tarpaulin etc.)

with fully automatic micro processor based PLC

with SCADA enabled reversible Drum Type

mixer/ concrete Batch mix plant (Pan mixer)

etc. complete. With natural sand/V.S.I. quality

Artificial Sand

0.38 Cum

Page 116: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 18 -

Contractor No. of corrections Executive Engineer

Item

No.

Description

Quantity Unit

per

Rate

Amount In

Figures

In

Words

25 Providing and laying in situ / ready mix

controlled grade of M35 of trap /granite

/quartzite /gneiss metal for RCC works in cut

off walls / curtain walls including necessary

scaffolding, centering, compacting by vibrator,

finishing and curing etc. complete. (with fully

automatic micro processor based PLC with

SCADA enabled with reversible drum type

mixer/ concrete batch mix plant (pan mixer)

with natural /artifical sand, excluding

reinforcement)

66.94 Cum

26 Providing, cutting, bending, hooking, tying and

laying in position TMT FE 500 steel bars for

reinforcement for all RCC works as per detailed

drawings etc. complete.

141.31 MT

27 Providing Fusion Bonded Epoxy Coating (FBEC) to

reinforced bars as per IS: 13620-1993 specifications

for a thickness of 175micron Permissible variation

of 50 micron including testing of coating at plant

extra cost for careful handling using PVC coating,

binding wires instead of G. I. wires to and from

Plant) touching up the material supplied repair work

etc complete as per detailed specifications. (Lead

200km from plant) etc complete. (Item shall be used

for new structures.)

141.31 MT

28 Providing and fixing heavy duty inter locking

concrete Gray paving blocks of 60 mm thickness of

having a strength of 300 kg/Sq.cm. of approved

quality and shape on a bed of crushed sand of 25 to

30 mm thick including skirting joints and

cleaningetc. complete.

979.20 Sqm

29 Providing Laterite Stone masonary in Cement

mortar 1.:6 in Foudataion and plinth including

racking out joint when plastering is to be done

/striking joint when no plastering is to be done

watering and scaffolding.

20.12 Cum

30 Providing Laterite Stone masonary in Cement

mortar 1.:6 in Superstructur including racking out

joint when plastering is to be done /striking joint

when no plastering is to be done watering and

scaffolding.

106.67 Cum

Page 117: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 19 -

Contractor No. of corrections Executive Engineer

Item

No.

Description

Quantity Unit

per

Rate

Amount In

Figures

In

Words

31 Providing cement based water proofing treatment to

terraces (Indian water proofing or alike) with brick

bats laid in required slope to drain the water for any

span after cleaning the base surface. Applying a coat

of cement slurry admixed with approved water

proofing compound and laying the brick bats on

bottom layer in C.M.1:5 admixed with approved

water proofing compound filling up to half depth of

brick bats, curing this layer for 3 days, applying

cement slurry over this layer joints of brick bats with

C.M.1:3 admixed with approved water proofing

compound and finally top finishing with average 20

mm. thick layers of same mortar added with jute

fiber at 1 Kg per bag including finishing the surface

smooth with cement slurry admixed with approved

water proofing compound. Marking finished surface

with false squares of 300mm x 300 mm. making the

junctions at the parapet rounded and tapered top for

required height, with drip mould at the junction of

plaster and parapet and curing and covering 10 years

Guarantee against leakproofness on Court fee stamp

paper of Rs. 500/- including ponding test etc.

complete.

591.87 sqm

32 Providing waterproof plaster in W.C. and bath 12

mm thick for dado in cement mortar 1:3 with neat

finishing, floating using waterproofing compound at

the rate of 1 kg. per bag of cement of approved make

and manufacturer and curing etc. complete.

(Excluding Tiles)

(As directed by Engineer in Charge)

5.18 cum

33 Providing internal cement plaster 6 mm thick in a

single coat in cement mortar 1:3 without neeru finish

to concrete surface in all positions including

scaffolding and curing etc. complete. 910.64 sqm

34 Providing sand faced plaster externally in cement

mortar using approved screened sand, in all

positions including base coat of 15 mm thick in

cement mortar 1:4 using waterproofing compound at

1 kg per cement bag curing the same for not less

than 2 days and keeping the surface of the base coat

rough to receive the sand faced treatment 6 to 8 mm

thick in cement mortar 1:4 finishing the surface by

taking out grains and curing for fourteen days

scaffolding etc.complete.

524.95 Sqm

35 Providing and laying machine cut machine polished

machine cut Kota stone slabs 18 to 20 mm thick for

skirting, with rounded nosing for the treads on a bed

of 1:4 cement mortar including cement float, filling

joints with neat cement slurry, curing, polishing and

cleaning etc. complete.

222.90 sqm

Page 118: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 20 -

Contractor No. of corrections Executive Engineer

Item

No.

Description

Quantity Unit

per

Rate

Amount In

Figures

In

Words

36 Providing and laying vitrified mirror / glossy finish

tiles decorative type having size 590 mm to 605 mm

x 590 mm to 605 mm of 8 to 10 mm thickness and

confirming to IS. 15622- 2006 ( group Bla) of

approved make, shade and pattern for flooring in

required position laid on a bed of 1:4 cement mortar

including neat cement float, filling joints, curing and

clearing etc. complete. a) Flooring

346.29 Sqm

37 Providing and laying Antiskid Ceramic tiles of

approved quality of size 30 cm x 30 cm and

confirming to IS 15622-2006 (Group-B IIA) for

antiskid flooring in required position laid on a bed of

1:4 cement mortar including cement float, filling

joint with cement slurry cleaning curing etc.

complete.

90.08 Sqm

38 Providing and applying white-wash in two coats on

old / new plastered or masonry surfaces and asbestos

cement sheets including scaffolding and preparing

the surface by brushing and brooming down etc.

complete.

1267.56 Sqm

39 Providing and applying plastic emulsion paint of

approved quality, colour and shade to new surface in

three coats including scaffolding, preparing the

surface. (excluding primer coat) etc. complete.

1267.56 sqm

40 Providing and applying two coats of exterior

acraylic emulsion paint confirming to corresponding

I.S. of approved manufacture and of approved colour

to the plastered surfaces including cleaning

,preparing the plaster surface, applying primer coat

,scaffolding if necessary , and watering the surface

for two days etc complete.

476.33

sqm

41 Providing and fixing in position, Double shuttered

aluminium extruded powder coated openable door of

specified size with aluminium door frame of powder

coated section 101.60 x 44.75mm , 3.18 mm thick

and shutter comprising of powder coated section

having bottom and lock rail of size 150 mm x 44.5

mm x 3.00 mm thick top rails 47.62 x 44.45 mm x

3.00 mm thick , vertical style 47.62 x 44.45 mm,

3.00 mm thick and for shutter plain glass panes 5

mm thick for top panels and 12mm

13.23 sqm

Page 119: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 21 -

Contractor No. of corrections Executive Engineer

Item

No.

Description

Quantity Unit

per

Rate

Amount In

Figures

In

Words

42 Providing and fixing rolling shutter fabricated from

steel laths of minimum thickness 0.9 mm with lock

plate of 3.15 mm thickness reinforced with 35 x 35 x

5 mm angle section fitted with sliding bolts and

handles for both sides, deep M.S. channel section of

depth and thickness not less than 65 mm and 3.15

mm

respectively with hold fast arrangements, M.S.

Bracket plate 300 x 300 x 3.15 mm minimum size

and shape with square bar, suspension shaft of

minimum 32 mm diameter, hood cover of M.S. sheet

not less than 0.9 mm thickness and of any size at top

and safety devices including mechanical gear

operation arrangement consisting of worm gear

wheels and worms of high grade cast iron or mild

steel and one coat of red lead primer etc. complete.

(I.S. 62481979) (With mechanical gear)

7.20 sqm

43 Providing and fixing 34 mm thick moulded door

shutter consisting of solid core single leaf flush door

of 30 mm thickness lipped with 15 mm ( 5mm x 3)

thick x 30 mm width on one style and top rail and 10

mm (5mm x 2) thick x 30 mm width on other style

and bottom rails. The inner panels laminated with 2

mm thick termite proof, water proof and fire

resistant moulded PVC sheet with 2,4,6 design in

different plain and /or prelim colours on one side

after routing the moulded design on flush doors and

2 mm plain and /or pre lam PVC on other side using

rubber adhesive on flush door and solvent cement

adhesive on the PVC lipping etc. as per direction of

Engineer in charge and manufacturers specification

and drawing etc. complete.

31.90 sqm

44 Providing and fixing Country cut teak wood partly

veneered and partly glazed partition with 75 mm x

50 mm frame at 60 cm center and 9 mm thick

commercial ply on both sides, decorative veneer of 4

mm thick and plain glass 5 mm thick, including

French polishing etc. complete

31.90 sqm

45 Providing and fixing in position (as per 1868 / 1982)

Alluminium sliding window of three tracks with

rectangular pipe 95 x 38.10 x 0.90 mm at weight

0.637 kg/Rmt. with window frame bottom track

section 92 x 31.75 x 1.30 mm at weight 1.070

kg/Rmt.. Top and side track section 92 x 31.75 x

1.30 mm at weight 0.933 kg/Rmt. The shutter should

be of bearing bottom 40 x 18 x 1.25 mm at weight

0.417 kg/Rmt. Inter locking section 40 x 18 x 1.10

mm at weight 0.469 kg/Rmt. and handle and top

section 40 x 18 x 1.25 mm at weight o.417 kg/Rmt.

As per detailed drawings and as directed by

Engineerincharge with all necessary Aluminium

sections fixtures and fastenings such as roller

47.55 sqm

Page 120: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 22 -

Contractor No. of corrections Executive Engineer

Item

No.

Description

Quantity Unit

per

Rate

Amount In

Figures

In

Words

bearing in nylon casting and self locking catch fitted

in vertical section of shutter including 5 mm thick

plain glass and aluminium mosquito net shutter with

stainless steel jail with all required screws and nuts

etc, complete. With colour Anodising with box.

46 Providing and fixing in position powder coated

aluminium louvered windows / ventilator of various

sizes with powder coating as per detailed drawing

and specifications including aluminium frames 80 x

38 mm x 1.22 mm box type, 5 mm thick sheet glass

louvers, of approved quality etc. complete.

3.50 sqm

47 Providing and fixing on walls/ ceiling/ floors, 50

mm dia heavy grade having embossed as ISI Mark

galvanised iron pipes weight of 6.33 Kg/meter with

necessary fittings.and remaking good the demolished

portion and primer of anti corrossive oil paint 2

coats Including necessary scaffolding and removing

existing pipe line if necessary and conveying and

stacking the same in PWD chowky or as directed

etc. complete.

50.00 Rmt

48 Providing, laying and fixing P.V.C. pipe of 32mm

dia. with fittings such as bends, tees, reducers,

clamps, etc. including necessary excavation, trench

filling etc. complete. Including removing existing

pipe line if necessary and conveying and stacking

the same in PWD chowky or as directed etc.

complete...

80.00 Rmt

49 Providing and fixing European type white glazed

earthenware water closet pan with UPVC seat and

lid with chromium plated brass hinges and rubber

buffers including UPVC and vent pipe up to the

outside face of wall 10 litre enameled low level

flushing cistern with fittings pipe stop tap brackets

for fixing cistern 32 mm dia. UPVC flush pipe with

fittings and clamps ,20 mm dia.UPVC overflow pipe

,mosquito proof couplings G.I. chain and pulley,with

water Jet and fitting including cutting and making

good to the walls and floors testing etc.

complete.(prior approval of sample and brand by Ex.

Engineer is necessary

before use)

8.00 No

50 Providing and fixing White Glazed Earthenware full

stall type Urinal with P.V.C. flushing cistern of 5

liters capacity with fitting, inlet pipes and stop tap,

brackets for fixing the cistern, 32 mm dia. P.V.C

flush pipe with fittings and flushing arrangement

including lead soil pipe, lead trap, soil pipe

connectionup to the outside face of the wall

6.00 No

Page 121: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 23 -

Contractor No. of corrections Executive Engineer

Item

No.

Description

Quantity Unit

per

Rate

Amount In

Figures

In

Words

51 Providing and fixing white glazed earthenware Wash

Hand Basin of 63cm x 45cm size including cold

water pillar tap/cold and hot water pillar tap

brackets, rubber plugs and brass chain, stop tap and

necessary pipe connection including P.V.C. waste

pipe and trap up to the outside face of the wall.

Making good the damaged surface, testing etc.

complete

7.00 No

52 Providing and fixing 10 cm PVC nahani trap with

grating etc. complete. 10.00 No

53 Providing and laying for 150 mm dia salt glazed

stoneware pipe including fittings Such as bends,

tees, single junction, double junctions laying,

jointing (including excavation and refilling the

trenches) complete.

50.00 Rmt

54 Providing and fixing 100 mm dia stabiliser pipe/

P.V.C. soil vent/waste pipe and with necessary

fixtures and fitting such as bends, tees, single

junctions, slotted vent, clamps etc. complete.

30.00 Rmt

55 Providing and laying concrete pipes of I.S.NP. class

of 150mm diameter in proper line, level and slope

including necessary collars, excavation, laying,

fixing with collars in cement mortar 1:1 and refilling

the trench complete.

5.00 Rmt

56 Providing and laying concrete pipes of I.S.NP. class

of 300mm diameter in proper line, level and slope

including necessary collars, excavation, laying,

fixing with collars in cement mortar 1:1 and refilling

the trench complete.

10.00 Rmt

57 Providing and constructing Brick Masonry

Inspection Chamber 60cm x 45cm x 90cm including

1:4:8 cement concrete foundation 1:2:4 cement

concrete channels half round G.S.W. pipes, Brick

Masonry, plastering from inside and airtight C. I.

cover of 75 kg with lid and frame fixed in cement

concrete.

19.00 No

58 Providing and constructing Brick Masonry

Inspection Chamber 90cm x 45cm x 90cm including

1:4:8 cement concrete foundation 1:2:4 cement

concrete channels half round G.S.W.pipes, Brick

Masonry, plastering from inside and C.I. lid

cover of 75 kg with lid and frame fixed in cement

concrete.

1.00 No

59 Providing and fixing reinforced cement concrete

cover of size 60 cm x 45 cm with frame over

inspection chamber etc. complete.Medium duty

(100 kg) 4.00 No

Page 122: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 24 -

Contractor No. of corrections Executive Engineer

Item

No.

Description

Quantity Unit

per

Rate

Amount In

Figures

In

Words

60 Aluminum faced composite panels with mounting

system. Panel mounting system including

anchorages, shims, furring, fasteners, gaskets and

sealants, relate flashing adapters, and masking (as

required) for a complete watertight installation.

304.54 Sqm

61 Supplying and providing glass glazing including all

fixtures, fastening and labour costs. Spec. As

directed by Engineer In Charge 473.15 sqm

62 Providing and applying gypsum plaster ( with

Gypsum material of Gypsum India / Mega Sign or

equivalent make ) with finishing with gypsum

material in 10 to 13 millimeter thickness to

previously plastered surface / or on newly brick

surface ( Excluding rough cast plaster ) in all

position including preparing and Finishing the

surface scaffolding etc.complete.

88.66 Sqm

63 Providing and fixing H.D.P container Syntex or

alike one piece moulded water tank made out of

low density polythyler and built corrugation

including of delivery up to destination hoisting

and fixing of accessories such as inlet, outlet

overflow of all tanks capacity above 1000 to

20,000 litres

5000.00 Litre

64 Providing and fixing 20 to 25 mm thick rough

shahabad box type waterproofing for basement or

underground floor on a base of Cement concrete

1:3:6, including sub base of 2.50 centimeter thick

Cement mortar 1:3 with conceal, secrete (RMW),

Algae proof or other alike waterproofing liquids,

raking of joints upto 35 mm depth, filling the joints

with 6 mm size crushed metal, hand grouting with

cement slurry, curing and cleaning, with 7 years

guarantee on court fee stamp of Rs. 100/- with

ponding test etc complete. (excluding Cement

concrete 1:3:6 base concrete )

46.74 Sqm

65 BASIC TEST OF CEMENT

Standard Consistancy Fineness, Specific

Gravity, Setting Time ( Initial & Final ),

Compressive Strength, Soundness

12 No

BASIC TEST OF AGGREGATE

66 Water Absorption, Specific Gravity. Impact

Value Crushing Value. 10 No

67 Sieve Analysis. 10 No

68 Abrasion Value. 10 No

69 Flakiness Index/ Elongation Index. 10 No

70 Stripping Value. 10 No

71 Soundness. 10 No

72 Bulk Density. 10 No

Page 123: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 25 -

Contractor No. of corrections Executive Engineer

Item

No.

Description

Quantity Unit

per

Rate

Amount In

Figures

In

Words

73 FINE AGGREGATES

Fineness Modulus ( Sieve Analysis ), Silt &

Clay Content 1 No

74 Chloride & Sulphate Content. 1 No

75 Silt Factor. 1 No

76 BRICKS

Water Absorption (Set of 5 Bricks),

Compressive Strength( Set of 5 Bricks),

Efflorescence (Set of 5 Bricks).

2 No

77 CONCRETE

Compressive Strength OF C.C. Cube(Set of 3

cubes). 52 No

78 Concrete Mix Design (With all Tests on basic

materials)* 3 No

79 Flexural strength of Beam. 7 No

80 Permeability Test. 2 No

81 Concrete mix design by Accelerated curing

method. (Boiling water method) 3 No

82 Taking of core samples in concrete pavement.

(Excluding Dead Journey Charges) 5 No

83 CONCRETE PAVING BLOCKS

Compressive Strength , Water Absorption, (Set

of 8 Blocks), Flexural Test ( Set of 8 Blocks).

Resistance to wear.( Set of 8 Blocks)

2 No

84 WATER

PH Value, Sulphate & Chloride Content. 1 No

85 STEEL BAR TESTING

upto 16mm (set of 3 bars) 15 No

86 Above 16mm (set of 3 bars) (Tensile strength,

% Elongation, Yield stress, Weight-Per Meter,

Bend / Rebend Test, Proof Stress.) 15 No

87 ROAD SIGN BOARD

Retro Reflective Test. 1 No

88 NON -DESTRUCTIVE TEST Rebound

Hammer Test. 1 No

89 Ultrasonic Pulse Velocity 1 No

Page 124: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 26 -

Contractor No. of corrections Executive Engineer

Item

No.

Description

Quantity Unit

per

Rate

Amount In

Figures

In

Words

ELECTRICAL WORK

90

Supplying and erecting Intelligent flush mounted panel meter three phase four wire (IPM) input voltage measurement range 50-550 VAC (P-P) 415V,Aux supply 90-300 VAC/DC, CT secondary site selectable 1A / 5A, Flush mounting 96 x 96 mm , CT/ PT site programmable, Flush mounted (96 x 96 mm) meter Constant Wh viewing in LCD Multifunction meters in auto scroll mode with Voltage, current, frequency, Power factor kW,kVA, kVAR, KWh,kVAh, kVARh, phase angle, interrupts, THD, Events (high- low) neutral current with LED Display (excluding CT'S) complete with RS 485 communication protocol, class 1 accuracy and wriring connections and mounting hardware on provided panels complete with calibration certificate from manufacture

2.00 Each

91

Supplying and erecting L.T. current transformer with wound / bar primary50/5 to 1000/5A ratio with 15 Vaburden class-I, erected in provided CRCA box duly secured with insulating material and connected to meter with test certificate. -

6.00

Each

92 Supplying and erecting Bus bar chamber triple pole with neutral with four aluminium bars, 500V 100A complete as per specification no. CP-BB -

2.50

Mtr

93 Providing and fixing sheet metal work in CRCA sheet with fabrication of boxes panel boards etc. including cutting, bending, drilling, welding, rivetting etc. treated with anti-rust treament and duly power coated or painted with one coat of red lead paint and 2 coats of enamel paint as directed. -

250.00

kg

94 Providing & erecting 3 Pole MCCB of 200A,415V capacity with S.C. rating 25 kA (Ics=100% of Icu),thermal and magnetic setting with provided leads on iron /G.I.frame as per specification No. SW-SWR/MCCB - 4 POLE For main Panel Incomer -4 POLE MOTORISED MCCB

1.00

Each

95 Providing & erecting 4 Pole MCCB of 100 A, 415V capacity with S.C. rating 25 kA (Ics=100% of Icu), thermal and magnetic setting with provided leads on iron frame as per specification No. SW-SWR/MCCB - 4 POLE For main Panel Incomer -4 POLE MOTORISED MCCB

2.00

Each

96 Supplying, erecting & marking TPMCB 40A to 63A in provided distribution board as per specification No. SW-SWR/MCB -

6.00

Each

97 Supplying, erecting & marking TPMCB 6 A to 32 A in provided distribution board as per specification No. SW-SWR/MCB -

3.00

Each

Page 125: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 27 -

Contractor No. of corrections Executive Engineer

Item

No.

Description

Quantity Unit

per

Rate

Amount In

Figures

In

Words

98 Supplying, erecting, testing and commissioning of Microprocessor based AMF panel suitable for Diesel Generating Set of above 50 kVA upto 62.5 kVA capacity Single/Three phase, 230/415 Volts, 50Hz A.C. with all standard features, safeties etc as per specification no. GEN-AMF.

1.00

Set

99

Supplying, erecting & marking SPMCB 6A to 32A, C-series (for motor/power) in provided distribution board as per specification No. SW-SWR/MCB

38.00

Each

100 Providing, erecting & commissioning RCCB only of electro magnetic type with 30/100/300 mA sensitivity and having capacity of 40A. 4 pole complete as per specification No. SWRCCB/ RCCB

2.00

Each

101 Providing, erecting & commissioning RCCB only of electro magnetic type with 30/100/300 mA sensitivity and having capacity of 25A. 4 pole complete as per specification No. SWRCCB/ RCCB

1.00

Each

102 Supplying & erecting triple pole and neutral

distribution board (TPNDB) with door surface/ flush

mounted SPMCB of 12 ways, on iron / G.I.

frame/wooden board.(Horizontal type) as per

specification No. SW- SWR/MCBDB

3.00

Each

103 Supplying & erecting CRCA sheet metal one way enclosures suitable for D.P.M.C.B. /T.P. M.C.B. /F.P M.C.B. complete erected on angle iron frame.

10.00

Each

104 Supplying and erecting D. O. L. Starter suitable for

250V. single phase, 50 cycleswith overload element with

necessarymaterials and connected to supply upto 2 H.P.

1.00

Each

105 Supplying & erecting Centrifugal water pump (Monoblock), 230V, Single phase 50 cycles A.C. supply of 2 HP of specified discharge head & size of suction, delivery pipes on provided C.C. foundation as per specification No. WPCGP

1.00

Each

106 Supplying & erecting PVC armoured cable 3 1/2 core 70 sq mm aluminium conductor with continuous 12.97 sq mm (8 SWG) G.I. earth wire complete erected with glands & lugs, on wall/ trusses/pole or laid in provided trench/ pipe as per specification no. CB-LT/AL

50.00

m

107 Supplying & erecting PVC armoured cable 3 1/2 core 35 sq mm aluminium conductor with continuous 12.97 sq mm (8 SWG) G.I. earth wire complete erected with glands & lugs, on wall/ trusses/pole or laid in provided trench/ pipe as per specification no. CB-LT/AL

50.00

m

108 Supplying & erecting PVC armoured cable 3 1/2 core 25 sq mm aluminium conductor with continuous 12.97 sq mm (8 SWG) G.I. earth wire complete erected with glands & lugs, on wall/ trusses/pole or laid in provided trench/ pipe as per specification no. CB-LT/AL

30.00

m

Page 126: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 28 -

Contractor No. of corrections Executive Engineer

Item

No.

Description

Quantity Unit

per

Rate

Amount In

Figures

In

Words

109 Supplying, erecting & terminating PVC armoured cable 4

core 6 sq mm copper conductor continuous 5.48 sq mm

(12 SWG) G.I. earth wire complete erected with glands &

lugs, on wall/ trusses/pole or laid in provided trench/ pipe

as per specification no. CB-LT/CU

180.00

m

110 Supplying, erecting & terminating PVC armoured cable 4

core 4 sq mm copper conductor continuous 5.48 sq mm

(12 SWG) G.I. earth wire complete erected with glands &

lugs, on wall/ trusses/pole or laid in provided trench/ pipe

as per specification no. CB-LT/CU

20.00

m

111 Supplying & erecting PVC armoured cable 3 core 4 sq mm copper conductor continuous 5.48 sq mm (12 SWG) G.I. earth wire complete erected with glands & lugs, on wall/ trusses/pole or laid in provided trench/ pipe as per specification no. CB-LT/CU

118

m

112 Making the trench in Hard murum/Tar road of suitable width and depth as per IS for laying provided L.T cable of 25 sq mm & above and covered with Half round hume pipe complete. As per specification no. CW-EXN-CTR

33.00

m

113 Supplying and erecting G.I. strip of required size used for earthing on wall and/or any other purpose with necessary GI clamps fixed on wall painted with bituminous paint in an approved manner with joint required. as per specification No (EA-EP).

519.00

kg

114 Supplying and erecting copper strip of required size used for earthing on wall and/or any other purpose with necessary copper clamps fixed on wall painted with bituminous paint in an approved manner with joints required. As per specification No EA-EP.

68.00

kg

115 Supplying and erecting G. I. Earth Wire of high purity

of different sizes used for earthing or any other purposes

on wall with necessary G. I. Clamps fixed on wall/cable/

conduit with screws in an approved manner.

25.00

kg

116 Supply, Installation, Testing and commissioning of UL Certified / CPRI Tested Maintenance Free Earthing comprising of Electrode of 17.2 mm diameter Low Carbon Steel with 250 micron Molecular Copper Bonded Earthing Rod of Length 3m along with 25 kg Carbon Based environment friendly back fill Ground Enhancing compound required to fill up the excavated earth with required quantity as per specification no EA-MOBI

8.00

Each

117 Providing earthing with Copper earth plate size 60 x 60 x 0.315 cm with funnel with a wire mesh for watering and brick masonry block C.l. cover with minimum 25 kg of maintenance free earth conductivity enhancing mineral earthing compound complete with all materials, testing & recording the results as per specification no ESE -LA

6.00

Each

Page 127: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 29 -

Contractor No. of corrections Executive Engineer

Item

No.

Description

Quantity Unit

per

Rate

Amount In

Figures

In

Words

118 Supplying & erecting conventional spike type air termination suitable to carry lightning stroke made up of heavy gauge 40 mm dia copper pipe of standard length with 5 Nos. copper spikes fixed on copper ball as air terminals duly threaded in copper pipe erected on provided foundation in an approved manner.

1.00

Each

119 Point wiring for light/fan/bell concealed type in min 20 mm PVC conduit with 1.5 sq.mm. FR grade copper wires with moduler type switch and required accessaries as per specification No: WG-PW/CW

63.00

Point

120 Point wiring for independent plug, concealed type in min 20 mm PVC conduit with 1.5 sq.mm FR grade copper wires with moduler type switch and socket and required accessaries as per specification No WG-PW/SW

13.00

Each

121 Wiring for plug on board with Switch socket concealed type and copper wiring, earthing and with modular accessories as per specification No: WG-PW/CW

13.00

Each

122 Supplying and erecting modular type electronic step regulator for fan two module ISI mark approved make duly erected on provided plate and box with wiring connections complete.

28.00

Each

123 Supplying and erecting modular type switch one way 16 / 20 A, ISI mark, approved make duly erected on provided plate and box with wiring connections complete with neon indicator.

7.00

Each

124 Supplying and erecting modular type 3 pin 6 / 16A multi socket with safety shutter ISI mark approved make duly erected on provided plate and box with wiring connections complete.

7.00

Each

125 Supplying and erecting unbreakable concealed type modular switch box with double mounting plate for 3 module duly erected flush to wall with required chiselling and finishing with cement morter / POP as per required to match the background in an approved manner.

7.00

Each

126 Supplying & erecting mains with 2x1.5 sq.mm.and earth wire 1.5 sqmm FRLS PVC copper wire, in rigid PVC conduit min.20mm dia as per specification No: WG-MA/PC, para no. 1.4.1

403

m

127 Supplying & erecting mains with 2x1.5 sq.mm F.R copper PVC insulated wire laid in provided conduit/trunking/inside pole/Bus bars or any other places as per specification No: WG-MA/BW - for Secondary Point Aprox 5 Mtr length per point.

225.00

m

Page 128: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 30 -

Contractor No. of corrections Executive Engineer

Item

No.

Description

Quantity Unit

per

Rate

Amount In

Figures

In

Words

128 Supplying & erecting mains with 2x4 sq.mm.and earth wire 2.5 sqmm FRLS PVC copper wire in rigid PVC conduit min.20mm dia, as per specification No: WG-MA/PC, para no. 1.4.1

118

m

129 Supplying & erecting T8 LED 20W tube light fitting (4

feet) with aluminium housing, heat sink, integrated HF

electronic driver complete( including lamp).

10.00

Each

130 Supplying and erecting Corridor/Passage light fitting (

2 feet) including 18W LED lamp, Comprises of

Extruded channel in Plastic Silver gray Color & With

same Plastic end cap on provided PVC block / wooden

board.

10.00

Each

131 Supplying and erecting square shaped CRCA / die-cast aluminium powder coated housing LED Panel light 600X600mm of PREMIUM RANGE suitable for upto 36 W with provision for plane front frame with translucent cover fixed to the housing complete. Equivalent to CG Make Cat No. LCTLR-36-FO-CDL

10.00

Each

132 Supplying and erecting LED square / circular 16 to

20W downlighter having pressure die- cast aluminimum

housing, opal translucent cover, mounting arrangement

with board for surface type or spring loaded mounting

clips for flush type complete.

20.00

Each

133 Supplying and erecting square shaped CRCA /die-cast

aluminium powder coated housing LED Panel light

(slim edge-lit) 600X600mm suitable for 36 W-40W

with provision for plane front frame with translucent

cover fixed to the housing complete.

18.00

Each

134 Supplying and erecting LED Street light fitting suitable

for 20 to 25W, with PF > 0.95 class IP 65 and above

Housing of pressure die cast alluminium alloy and heat

sink extruded alluminium complete as per specification

No FG-ODF/FLS-2

8.00

Each

135 Supplying and erecting LED street light fitting suitable

for above75 - 90W lamp, including lamp, with PF > 0.95

class IP 65 and above Housing of pressure die cast

alluminium alloy and heat sink extruded alluminium

complete per specification No. FG-ODF/FLS2

8.00

Each

136

Providing & erecting 9 m high (clear height) galvanised

OCTAGONAL pole with foundation bolts having bottom

of 155 mm A/F, top 70 mm A/F on provided foundation

as per specification No.OH-PL/OPL

8.00

Each

137

Supplying and erecting Street light bracket for erection

of Single fitting made from 40 mm. dia ‘B’ class G.I.

pipe 1.0 m in length alongwith pole cap of 300 mm

length 100 mm dia duly welded as perspecification no.

FG-BKT/BPC

8.00

Each

Page 129: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 31 -

Contractor No. of corrections Executive Engineer

Item

No.

Description

Quantity Unit

per

Rate

Amount In

Figures

In

Words

138 Supplying and erecting Five Star Rated Energy Saving Ceiling Fan 440 V A.C. 50 cycles 1200 mm complete erected in position as per specifcation no. FG-FN/CF

28.00

Each

139 Supplying & fixing Anchor type fastener Fan hook, with 2 Nos of 10 mm dia x 75 mm long with necessary materials for Ceiling Fan.

28.00

Each

140 Supplying and erecting ‘B’ grade G.I.pipe/M.S. pipe down rod duly painted for fan complete erected with PVC two core flexible cable 24/0.2 mm copper PVC wire.

28.00

Mtr

141 Supplying and erecting fresh air cum Exhaust fan of light duty 250 V A.C. 50 cycles 225mm. 1400 RPM metallic body, plastic blades, wire mesh, duly erected in an approved manner and marking Sr. No. and date of erection.

4.00

Each

142 Supplying and erecting street light Wall bracket made

from 40 mm.dia ‘B’class G.I. pipe 1.2 m in total length

complete as per specificationno. FG-BKT/WB

8.00 Each

143 Supplying, Erecting and Commissioning of Diesel generating set with alternator of 50 kVA output continuous rating, 3 Phase, 415 V, 50c/s 0.8 p. f. A.C a totally enclosed liquid cooled multi-cylinder diesel engine developing suitable BHP at 1500 rpm with 10% overload for 1 hour in 12 hours, alongwith standard accessories, self excited self regulated,screen protected alternator with static excitation system running at 1500 RPM as per IS 4722-1968 with voltage regulation +/- 5 %. Both the engine and alternator direct coupled on a common fabricated steel base frame and mounted on anti vibratring pads with standard control panel comprising meters, switchgears, indicators connected with suitable wires/cables, the complete set enclosed in composite Acoustic enclosure as fully assembled integral unit made of 16 SWG CRCA Sheet, sound absorbing material to restrict sound level upto 75 dB at 1.0 m, provided with first filling of oil, diesel etc. and obtaining necessary approval from Electrical Inspector as per specification no. GEN-DG

1.00

Set

144 3-5-1 Supplying and erecting ultra violet water purifier with softener for safe drinking water consisting of UV germicidal tube of 8W capacity choke made of copper wire and two indicator lamps with output of purified water 5 Ltr/min with activated carbon filter and softener operating on 230 V single phase A.C. supply.

2.00

Each

Page 130: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 32 -

Contractor No. of corrections Executive Engineer

Item

No.

Description

Quantity Unit

per

Rate

Amount In

Figures

In

Words

147 3-3-5 Supplying, erecting, testing and commissioning self contained water cooler 230/250 Volts 50 cycles nominal cooling capacity of 150 liters per hour and storage capacity 150 liters as per specification No. AP-WCR/WC

2.00

Each

148 Supplying & erecting On line UPS pure sine wave of 2

kVA capacity complete with standard features, along with

necessary SMF batteries for 30 mins battery backup, as

per specification No. AP-UPS

1.00

Each

149 Supplying , erecting, testing & commissioning 11kV, 630A, 21kA/3sec, 3Way Outdoor, Extensible motorised SCADA compatible RMU as per Electric Supply Co. specification consisting of 2Nos. feeder with Load Break Switch and 1No. feeder with VCB. | <2LBS +1VCB+M> as per specifiaation no. SW-HTS / RMU SCADA

1.00

Each

150 Providing transformer plinth 1.5 x 1.5 x 1.5 m in size with necessary excavation in ground at the bottom with 150 mm. thick M- 10 PCC at the bottom and top and 250 mm. thick burnt brick wall constructed at periphery and remaining hollow portion shall be filled with 60mm Hard broken aggregate, external surface duly plastered 15 mm thick including watering etc. complete.

1.00

Each

151 Providing round bottom FIRE Bucket of 9 Litres capacity as per IS : 2546 made out of 24 gauge G.I. sheet with extra handle at bottom duly painted white inside and red outside with FIRE Mark, on provided stand/ wall hook.

4.00

Each

152 Providing floor mounting stand for keeping 4 Nos. of FIRE buckets 1500mm in length, 900mm in height frame made out of 30x30x4 mm angle iron with cross supports for legs, welded with 4 hooks and duly painted with one coat of red lead and two coats of silver paint.

1.00

Each

153 Supplying standard first aid box with necessary antiseptic cream, medicine for use on wounds due burn, crepe bandage, gauge bandage, medicated ready to use bandage (Band-aid) adhesive tape for medicinal use, scissors, anti-septic solution (Savlon or simil

2.00

Each

154 Provided pair of duly tested rubber hand gloves as per IS :340715 suitable for working on 22kV supply.

2.00

Each

155 Providing printed instruction chart for treating persons suffering from electric shock, printed in English & Marathi and duly laminated.

2.00

Each

156 Supplying and erecting ABC powder type fire extinguisher as per IS : 13849 of 6 kg capacity with necessary clamp for erection on wall.

4.00

Each

Page 131: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 33 -

Contractor No. of corrections Executive Engineer

Item

No.

Description

Quantity Unit

per

Rate

Amount In

Figures

In

Words

157 Supplying and Erecting approved make 63 kVA,3 phase,

50 c/s Oil immersed and naturally cooled outdoor

type, Copper wound transformer with Energy Efficieny

Level -2 , BIS Standard with delta connected. on HV side

& star connection on LV side with additional neutral

brought out on load side,Temp rise should not Exceeding

4000 C by thermometer in oil and 4500C by the resistance

in winding at full load rating, voltage rating 11/ 0.433

kV with HV tapping (with off load tap changer) Tappings

on Transformer For Off Load +5 to - 10 in Steps of 2.5%

,with standard accessories complete with Test Certificate

with losses below 340 watts at 50% load, 1140 watts at

100% load as per IS:1180 - 2014 Level II as per

specification No SS- TR.with necessary permission of

Electrical Inspector

1.00

Each

158 Supplying , erecting & terminating 3 x 120 sq mm 11 kV,

XLPE(E) armoured cable on wall/ceiling or laid in

provided trench / pipe in an approved manner as per

specification No. CB-HT

100.00

Mtr

159 Providing and erecting Heat shrinkable indoor termination kit for 11 kV ( E ) XLPE HT cable 3x120 to 185 sq. mm. with necessary material as per specification No. CB-JT/HT

4.00

Each

160 Providing and erecting Heat shrinkable Each outdoor termination kit for 11 kV ( E ) XLPE HT cable 3x120 to 185 sq. mm. with necessary material as per specification no. CB- JT/HT

1.00

Each

161 Supplying and fixing PVC Synthetic elastomer electrically insulating mat with class C insulation conforming to IS: 15652 – 2006 & CPRI tested having 3mm thickness upto 33 kV

8.00

Sq.Mtr

Note:

1. Item for which no rate or price has been entered in will not be paid for by the Employer when

executed and shall be deemed covered by the other rates and prices in the bill of quantities (Refer:

ITB Clause 13.2 and GCC Clause 43.3)

2. Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1]

3. Where there is a discrepancy between the rate in figure and words, the rates in word will govern [ITB

Clause 27.1(a)]

4. Where there is a discrepancy between the unit rate and the line item total resulting from multiplying

the unit rate by quantity, the unit rate quoted shall govern [ITB Clause 27.1(b)]

Page 132: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 34 -

Contractor No. of corrections Executive Engineer

SPECIFICATIONS

Item

No. Description

Ref to Std.

Spn. Book

Item No and

Page No

Additional

Specification

if any

1 Taking trial bores 75 to 100 mm for 53.0 to 88.9 mm core dia

over burden ( by diamond drilling machine ) such as soil of all

\sorts, soft murum,hard murum and boulders and in soft rock

including all materials such as casing pipes and accessories oil,

grease, steel, rods, and such other materials as required

(including conveying the material to site of work) . Preserving

the loose sample in glass jar and core sample serially on site of

work and conveying the same to HQ of concernring office as

directed.

a) over burden 0 to 50 meter.

_

As directed by

Engineer in

charge

3 Providing tun tappa core boxes of jungle wood of size1.25mx

0.35x 0.15m for preserving core sample with all fixtures and

fastening handles including locking arrangment etc . complete. _

As directed by

Engineer in

charge

4 Excavation for foundation in earth, soils of all types, sand,

gravel, soft murum including shoring and strutting as necessary

and disposing off excavated stuff as directed etc. complete

BR.3 Page No.

102

5 Supplying & laying trap stones weighing upto 20 Kg. for filter

layer including quarrying,conveying with all the leads & lifts

laying in required line, level, slope including necessary

equipment and machinerysuch as crane of adequate capacity and

boom length as directed etc complete, in the tidal conditions.

Spec.No.-Rd-19,Page-187; Rd-29,Page-193; Rd-27, Page-192.

[Except weight of stone specified in wording of specification]

Rd-19,Page-

197; Rd-

29,Page-193;

Rd-

27, Page-192.

6 Supplying & laying trap stones weighing upto 200 Kg. for core

layer including quarrying,conveying with all the leads & lifts

laying in required line, level, slope including necessary

equipment and machinerysuch as crane of adequate capacity and

boom length as directed etc complete, in the tidal conditions.

Spec.No.-Rd-19,Page-187; Rd-29,Page-193; Rd-27, Page-192.

[Except weight of stone specified in wording of specification]

Rd-19,Page-

197; Rd-

29,Page-193;

Rd-

27, Page-192.

7 Supplying & laying trap stones weighing 300 to 500 Kg. for sub

armour layer including quarrying,conveying with all the leads &

lifts laying in required line, level, slope including necessary

equipment and machinerysuch as crane of adequate capacity and

boom length as directed etc complete, in the tidal

conditions.Spec.No.-Rd-19,Page-187; Rd-29,Page-193; Rd-27,

Page-192.[Except weight of stone specified in wording of

specification]

Rd-19,Page-

187; Rd-

29,Page-193;

Rd-27, Page-

192.

8 Supplying & laying trap stones weighing above 1000 Kg. for

armour layer including quarrying,conveying with all the leads &

lifts laying in required line, level, slope including necessary

equipment and machinerysuch as crane of adequate capacity and

boom length as directed etc complete, in the tidal conditions.

Spec.No.-Rd-19,Page-187; Rd-29,Page-193; Rd-27, Page-192.

[Except weight of stone specified in wording of specification]

Rd-19,Page-

187; Rd-

29,Page-193;

Rd-27, Page-

192.

Page 133: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 35 -

Contractor No. of corrections Executive Engineer

Item

No. Description

Ref to Std.

Spn. Book

Item No and

Page No

Additional

Specification

if any

9 Supplying & spreading geofabric filter layer of Geotextile of

Polypropylene multifilament woven to the line, evel and grade

with pore size less than 0.075 mm and permeability greater than

9.0 litre/sqm/sec. confirming specification IS:1969 and ASTM

standard including conveying to the site,joining and stitching

with proper overlap and laying at excavated surface in tidal

condition as directed by Engineer- in- charge etc complete .

As directed by Engineer -In- Charge.

_

As directed by

Engineer in

charge

10 Supplying hard murum / kankar at the road side, including

conveying and stacking etc. complete. Lead upto 50M. (initial

lead) (Includig Royalty)

MORTH 408

11 Spreading hard murum for side width etc. complete MORTH 408

12 Compacting the hard murum side widths including laying in

layers on each side with power roller including artificial watering

etc. complete.

MORTH 408

13 Construction of granular sub-base by providing close graded

Material, mixing in a mechanical mix plant at OMC, carriage of

mixed Material to work site, spreading in uniform layers with

motor grader/ Paver on prepared surface and compacting with

vibratory power roller to achieve the desired density, complete as

per clause 401 -- Plant Mix Method and Grading - III Material

MORTH 401

14 Wet Mix Macadam -- Providing, laying, spreading and

compacting graded stone aggregate to wet mix macadam

specification including premixing the Material with water at

OMC in mechanical mix plant carriage of mixed Material by

tipper to site, laying in uniform layers with paver in sub- base /

base course on well prepared surface and compacting with

vibratory roller to achieve the desired density. Laying By

Grader/Paver.

MORTH 406

15 Providing and laying in situ / ready mix / ready mix M15 cement

concrete of trap/ granite/ quartzite/ gneiss metal in foundation

including necessary centering, formwork, bailing out water,

compacting and curing etc. complete. (with fully automatic micro

processor based PLC with SCADA enabled with reversible drum

type mixer/ concrete batch mix plant (pan mixer) with natural

/artifical sand)

BR.5 Page No.

105 and

B.7,Page No.

38

Page 134: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 36 -

Contractor No. of corrections Executive Engineer

Item

No. Description

Ref to Std.

Spn. Book

Item No and

Page No

Additional

Specification

if any

16 Pavement Quality Concrete--Providing and laying in-situ M40

Grade unreinforced plain cement concrete pavement over a

prepared sub base with 43 grade cement , coarse and fine

aggregate conforming to IS 383, using fine and coarse aggregates

combined gradation as per Table 600-3 of MORTH Specification

2013, mixed in a batching and mixing plant/ non tilting mixer

and Weigh batcher as per approved mix design, admixtures,

transporting to site, spreading, laying with approved make

paver,compacted and finished in a continuous operation,

finishing to lines and grades as directed by Engineer-in-charge

and curing by curing compound /by providing cement vata in

cement Mortar 1:8 @0.6m X 0.6m centre to centre, admeasuring

80 mm at bottom and 40 mm at top with depth of 75mm and

maintaining the same throughout curing period by any other

method approved by Engineer-in-charge

MORTH 602

17 Providing and laying in situ / ready mix M30 RCC of trap/

granite/ quartzite/ gneiss metal for RCC work of ballast walls,

kerbs and box returns including scaffolding, compaction,

formwork finishing and curing etc. complete. (excluding

reinforcement, with fully automatic micro processor based PLC

with SCADA enabled concrete batch mix plant / pan mixer with

Natural / VSI standard Artificial Sand)

BR.50 Page

No. 143 and B.

7,

Page No.38

18 Providing and laying Cast in situ/Ready Mix cement concrete M-

35 of trap / granite /quartzite/ gneiss metal for R.C.C. work in

foundations like raft, strip foundations, grillage and footings of

R.C.C. columns and steel stanchions etc. columns as per detailed

designs and drawing or as directed including centering,

formwork, cover blocks, laying/pumping, compaction finishing

the formed surfaces with cement mortar 1:3 of sufficient

minimum thickness to give a smooth and even surface or

roughening if special finish is to be provided and curing etc.

complete,(Excluding reinforcement and structural steel).with

fully automatic micro processor based PLC with SCADA

enabled reversible Drum Type mixer/ concrete Batch mix plant

(Pan mixer) etc. complete. With natural sand/V.S.I. quality

Artificial Sand

Bd.F.3 Page

No. 298 and

B.7,

Page No.38

19 Filling in plinth and floors with approved excavated material in

15cm. to 20cm. layers including watering and compacting etc.

complete.

Bd.A.10 Page

No. 262

20 Providing soling using 80 mm size trap metal in 15 cm. layer

including filling voids with Crushed sand/grit, ramming,

watering etc. complete.

As directed by

Engineer in

charge.

Page 135: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 37 -

Contractor No. of corrections Executive Engineer

Item

No. Description

Ref to Std.

Spn. Book

Item No and

Page No

Additional

Specification

if any

21 Providing and laying Cast in situ/Ready Mix cement concrete M-

35 of trap / granite /quartzite/ gneiss metal for R.C.C. columns as

per detailed designs and drawing or as directed including

centering, formwork, cover blocks, laying/pumping, compaction

finishing the formed surfaces with cement mortar 1:3 of

sufficient minimum thickness to give a smooth and even surface

or roughening if special finish is to be provided and curing etc.

complete,(Excluding reinforcement and structural steel).with

fully automatic micro processor based PLC with SCAD

Aenabled reversible Drum Type mixer/ concrete Batch mix plant

(Pan mixer) etc. complete. With natural sand/V.S.I. quality

Artificial Sand

Bd.F.5 Page

No. 300 and

B.7,

22 Providing and laying Cast in situ/Ready Mixcement concrete M-

35 of trap / granite /quartzite/ gneiss metal for R.C.C. beams and

lintels as per detailed designs and drawings or as directed

including centering, formwork, cover blocks, laying/pumping,

compactionand roughening the surface if special finish is to be

provided and curing etc. complete. (Excluding reinforcement and

structural steel).

Bd.F.6 Page

No. 300 and

B.7, Page

No.38

with fully automatic micro processor based

PLC with SCADA enabled reversible Drum Type mixer/

concrete Batch mix plant (Pan mixer) etc. complete. With natural

sand/V.S.I. quality Artificial Sand

23 Providing and laying Cast in situ/Ready Mix cement concrete M-

35 of trap/ granite / quartzite/ gneiss metal for R.C.C. slabs and

landings as per detailed designs and drawings including

centering, formwork, cover blocks, laying/pumping,

compactionfinishing the formed surfaces with cement mortar 1:3

of sufficient minimum thickness to give a smooth and even

surface or roughening if special finish is to be provided and

curing etc. complete,(Excluding reinforcement and structural

steel). with fully automatic micro processor based PLC with

SCADA enabled reversible Drum Type mixer/ concrete Batch

mix plant (Pan mixer) etc. complete. With natural sand/V.S.I.

quality Artificial Sand

Bd.F.8 Page

No. 302 and

B.7,

Page No.38

Page 136: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 38 -

Contractor No. of corrections Executive Engineer

Item

No. Description

Ref to Std.

Spn. Book

Item No and

Page No

Additional

Specification

if any

24 Providing and laying Cast in situ/Ready Mix cement

concrete in M-35 of trap / quartzite /granite /gneiss metal

for R.C.C. Waist slab, and steps of staircases as per detailed

design and drawings or as directed including steel

centering, plywood/ steel formwork, steel props,

laying/pumping, compaction, finishing uneven and

honeycombed surface with C.M. 1:3 of sufficient minimum

thickness to give a smooth and even surface or roughening

the surface if special finish is to be provided and curing etc.

complete. (Excluding einforcement, including cover

block).(Newly laid concrete shall be covered by gunny bag,

plastic, tarpaulin etc.) with fully automatic micro processor

based PLC with SCADA enabled reversible Drum Type

mixer/ concrete Batch mix plant (Pan mixer) etc. complete.

With natural sand/V.S.I. quality Artificial Sand

Bd. F. 13

Page No. 305

/I.S. 456

(2000)

25 Providing and laying in situ / ready mix controlled grade of

M35 of trap /granite /quartzite /gneiss metal for RCC works

in cut off walls / curtain walls including necessary

scaffolding, centering, compacting by vibrator, finishing

and curing etc. complete. (with fully automatic micro

processor based PLC with SCADA enabled with reversible

drum type mixer/ concrete batch mix plant (pan mixer) with

natural /artifical sand, excluding reinforcement)

_

As directed by

Engineer in

charge

26 Providing, cutting, bending, hooking, tying and laying in position

TMT FE 500 steel bars for reinforcement for all RCC works as

per detailed drawings etc. complete. BR.35 Page

No. 134

27 Providing and fixing heavy duty inter locking concrete Gray

paving blocks of 60 mm thickness of having a strength of 300

kg/Sq.cm. of approved quality and shape on a bed of crushed

sand of 25 to 30 mm thick including skirting joints and

cleaningetc. complete.

_

As directed by

Engineer

incharge

Page 137: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 39 -

Contractor No. of corrections Executive Engineer

Item

No. Description

Ref to Std.

Spn. Book

Item No and

Page No

Additional

Specification

if any

28 Providing cement based water proofing treatment to terraces

(Indian water proofing or alike) with brick bats laid in required

slope to drain the water for any span after cleaning the base

surface. Applying a coat of cement slurry admixed with approved

water proofing compound and laying the brick bats on bottom

layer in C.M.1:5 admixed with approved water proofing

compound filling up to half depth of brick bats, curing this layer

for 3 days, applying cement slurry over this layer joints of brick

bats with C.M.1:3 admixed with approved water proofing

compound and finally top finishing with average 20 mm. thick

layers of same mortar added with jute fiber at 1 Kg per bag

including finishing the surface smooth with cement slurry

admixed with approved water proofing compound. Marking

finished surface with false squares of 300mm x 300 mm. making

the junctions at the parapet rounded and tapered top for required

height, with drip mould at the junction of plaster and parapet and

curing and covering 10 years Guarantee against leakproofness on

Court fee stamp paper of Rs. 500/- including ponding test etc.

complete.

_

As directed by

Engineer in

charge

29 Providing waterproof plaster in W.C. and bath 12 mm thick for

dado in cement mortar 1:3 with neat finishing, floating using

waterproofing compound at the rate of 1 kg. per bag of cement of

approved make and manufacturer and curing etc.complete.

(Excluding Tiles) (As directed by Engineer in Charge)

_

As directed by

Engineer in

charge

30 Providing internal cement plaster 6 mm thick in a single coat in

cement mortar 1:3 without neeru finish to concrete surface in all

positions including scaffolding and curing etc. complete. Bd.L.1 Page

No. 367

31 Providing sand faced plaster externally in cement mortar using

approved screened sand, in all positions including base coat of 15

mm thick in cement mortar 1:4 using waterproofing compound at

1 kg per cement bag curing the same for not less than 2 days and

keeping the surface of the base coat rough to receive the sand

faced treatment 6 to 8 mm thick in cement mortar 1:4 finishing

the surface by taking out grains and curing for fourteen days

scaffolding etc.complete.

Bd.L.7 Page

No. 369

32 Providing and laying machine cut machine polished machine cut

Kota stone slabs 18 to 20 mm thick for skirting, with rounded

nosing for the treads on a bed of 1:4 cement mortar including

cement float, filling joints with neat cement slurry, curing,

polishing and cleaning etc. complete.

Bd.M.22 Page

No. 390

33 Providing and laying vitrified mirror / glossy finish tiles

decorative type having size 590 mm to 605 mm x 590 mm to 605

mm of 8 to 10 mm thickness and confirming to IS. 15622- 2006 (

group Bla) of approved make, shade and pattern for flooring in

required position laid on a bed of 1:4 cement mortar including

neat cement float, filling joints, curing and clearing etc.

complete. a) Flooring

Bd.M. 12 Page

No.385

Page 138: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 40 -

Contractor No. of corrections Executive Engineer

Item

No. Description

Ref to Std.

Spn. Book

Item No and

Page No

Additional

Specification

if any

34 Providing and laying Antiskid Ceramic tiles of approved quality

of size 30 cm x 30 cm and confirming to IS 15622-2006 (Group-

B IIA) for antiskid flooring in required position laid on a bed of

1:4 cement mortar including cement float, filling joint with

cement slurry cleaning curing etc. complete.

Bd. M-12 page

No. 385

35 Providing and applying white-wash in two coats on old / new

plastered or masonry surfaces and asbestos cement sheets

including scaffolding and preparing the surface by brushing and

brooming down etc. complete.

Bd. P. I Page

No. 411

36 Providing and applying plastic emulsion paint of approved

quality, colour and shade to new surface in three coats including

scaffolding, preparing the surface. (excluding primer coat) etc.

complete.

Bd.P.6 Page

No. 414

Preapproval of

Superintending

Engineer

37 Providing and applying two coats of exterior acraylic emulsion

paint confirming to corresponding I.S. of approved manufacture

and of approved colour to the plastered surfaces including

cleaning ,preparing the plaster surface, applying primer coat

,scaffolding if necessary , and watering the surface for two days

etc complete.

_

As directed by

Engineer in

charge

38 Providing and fixing in position, Double shuttered aluminium

extruded powder coated openable door of specified size with

aluminium door frame of powder coated section 101.60 x

44.75mm , 3.18 mm thick and shutter comprising of powder

coated section having bottom and lock rail of size 150 mm x 44.5

mm x 3.00 mm thick top rails 47.62 x 44.45 mm x 3.00 mm thick

, vertical style 47.62 x 44.45 mm, 3.00 mm thick and for shutter

plain glass panes 5 mm thick for top panels and 12mm

_

As directed by

Engineer

incharge

39 Providing and fixing rolling shutter fabricated from steel laths of

minimum thickness 0.9 mm with lock plate of 3.15 mm thickness

reinforced with 35 x 35 x 5 mm angle section fitted with sliding

bolts and handles for both sides, deep M.S. channel section of

depth and thickness not less than 65 mm and 3.15 mm

respectively with hold fast arrangements, M.S. Bracket plate 300

x 300 x 3.15 mm minimum size and shape with square bar,

suspension shaft of minimum 32 mm diameter, hood cover of

M.S. sheet not less than 0.9 mm thickness and of any size at top

BD-T-55

Page No. 510

and safety devices including mechanical gear operation

arrangement consisting of worm gear wheels and worms of high

grade cast iron or mild steel and one coat of red lead primer etc.

complete. (I.S. 62481979) (With mechanical gear)

Page 139: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 41 -

Contractor No. of corrections Executive Engineer

Item

No. Description

Ref to Std.

Spn. Book

Item No and

Page No

Additional

Specification

if any

40 Providing and fixing 34 mm thick moulded door shutter

consisting of solid core single leaf flush door of 30 mm thickness

lipped with 15 mm ( 5mm x 3) thick x 30 mm width on one style

and top rail and 10 mm (5mm x 2) thick x 30 mm width on other

style and bottom rails. The inner panels laminated with 2 mm

thick termite proof, water proof and fire resistant moulded PVC

sheet with 2,4,6 design in different plain and /or prelim colours

on one side after routing the moulded design on flush doors and 2

mm plain and /or pre lam PVC on other side using rubber

adhesive on flush door and solvent cement adhesive on the PVC

lipping etc. as per direction of Engineer in charge and

manufacturers specification and drawing etc. complete.

_

As directed by

Engineer in

charge

41 Providing and fixing Country cut teak wood partly veneered and

partly glazed partition with 75 mm x 50 mm frame at 60 cm

center and 9 mm thick commercial ply on both sides, decorative

veneer of 4 mm thick and plain glass 5 mm thick, including

French polishing etc. complete

_

As directed by

Engineer in

charge

42 Providing and fixing in position (as per 1868 / 1982) Alluminium

sliding window of three tracks with rectangular pipe 95 x 38.10 x

0.90 mm at weight 0.637 kg/Rmt. with window frame bottom

track section 92 x 31.75 x 1.30 mm at weight 1.070 kg/Rmt.. Top

and side track section 92 x 31.75 x 1.30 mm at weight 0.933

kg/Rmt. The shutter should be of bearing bottom 40 x 18 x 1.25

mm at weight 0.417 kg/Rmt. Inter locking section 40 x 18 x 1.10

mm at weight 0.469 kg/Rmt. and handle and top section 40 x 18

x 1.25 mm at weight o.417 kg/Rmt. As per detailed drawings and

as directed by Engineerincharge with all necessary Aluminium

sections fixtures and fastenings such as roller bearing in nylon

casting and self locking catch fitted in vertical section of shutter

including 5 mm thick plain glass and aluminium mosquito net

shutter with stainless steel jail with all required screws and nuts

etc, complete. With colour Anodising with box.

_

As directed by

Engineer in

charge

43 Providing and fixing in position powder coated aluminium

louvered windows / ventilator of various sizes with powder

coating as per detailed drawing and specifications including

aluminium frames 80 x 38 mm x 1.22 mm box type, 5 mm thick

sheet glass louvers, of approved quality etc. complete.

_

As directed by

Engineer

incharge

44 Providing and fixing on walls/ ceiling/ floors, 50 mm dia heavy

grade having embossed as ISI Mark galvanised iron pipes weight

of 6.33 Kg/meter with necessary fittings.and remaking good the

demolished portion and primer of anti corrossive oil paint 2 coats

Including necessary scaffolding and removing existing pipe line

if necessary and conveying and stacking the same in PWD

chowky or as directed etc. complete.

Bd.V.5Page

No. 551

45 Providing, laying and fixing P.V.C. pipe of 32mm dia. with

fittings such as bends, tees, reducers, clamps, etc. including

necessary excavation, trench filling etc. complete. Including

removing existing pipe line if necessary and conveying and

stacking the same in PWD chowky or as directed etc. complete.

_

As directed by

Engineer in

charge

Page 140: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 42 -

Contractor No. of corrections Executive Engineer

Item

No. Description

Ref to Std.

Spn. Book

Item No and

Page No

Additional

Specification

if any

46 Providing and fixing White Glazed Earthenware full stall type

Urinal with P.V.C. flushing cistern of 5 liters capacity with

fitting, inlet pipes and stop tap, brackets for fixing the cistern, 32

mm dia. P.V.C flush pipe with fittings and flushing arrangement

including lead soil pipe, lead trap, soil pipe connectionup to the

outside face of the wall

Bd.V.23 Page

No. 562

47 Providing and fixing white glazed earthenware Wash Hand Basin

of 63cm x 45cm size including cold water pillar tap/cold and hot

water pillar tap brackets, rubber plugs and brass chain, stop tap

and necessary pipe connection including P.V.C. waste pipe and

trap up to the outside face of the wall. Making good the damaged

surface, testing etc. complete

Bd.V.30 Page

No. 565

48 Providing and fixing 10 cm PVC nahani trap with grating etc.

complete. BD.V 32 A

page 551

As directed by

Engineer in

charge

49 Providing and laying for 150 mm dia salt glazed stoneware pipe

including fittings Such as bends, tees, single junction, double

junctions laying, jointing (including excavation and refilling the

trenches) complete.

Bd.V.39, Page

No. 573

50 Providing and fixing 100 mm dia stabiliser pipe/ P.V.C. soil

vent/waste pipe and with necessary fixtures and fitting such as

bends, tees, single junctions, slotted vent, clamps etc. complete. _

As directed by

Engineer in

charge

51 Providing and laying concrete pipes of I.S.NP. class of 150mm

diameter in proper line, level and slope including necessary

collars, excavation, laying, fixing with collars in cement mortar

1:1 and refilling the trench complete.

Bd.V.41, Page

No. 573

52 Providing and laying concrete pipes of I.S.NP. class of 300mm

diameter in proper line, level and slope including necessary

collars, excavation, laying, fixing with collars in cement mortar

1:1 and refilling the trench complete.

Bd.V.41, Page

No. 573

53 Providing and constructing Brick Masonry Inspection Chamber

60cm x 45cm x 90cm including 1:4:8 cement concrete

foundation 1:2:4 cement concrete channels half round G.S.W.

pipes, Brick Masonry, plastering from inside and airtight C. I.

cover of 75 kg with lid and frame fixed in cement concrete.

Bd.V.43, Page

No. 574

54 Providing and constructing Brick Masonry Inspection Chamber

90cm x 45cm x 90cm including 1:4:8 cement concrete

foundation 1:2:4 cement concrete channels half round

G.S.W.pipes, Brick Masonry, plastering from inside and C.I. lid

cover of 75 kg with lid and frame fixed in cement concrete.

Bd.V.43 Page

No. 574

55 Providing and fixing reinforced cement concrete cover of

size 60 cm x 45 cm with frame over inspection chamber etc.

complete.Medium duty (100 kg) _

As directed by

Engineer in

charge

Page 141: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 43 -

Contractor No. of corrections Executive Engineer

Item

No. Description

Ref to Std.

Spn. Book

Item No and

Page No

Additional

Specification

if any

56 Providing and applying gypsum plaster ( with Gypsum material

of Gypsum India / Mega Sign or equivalent make ) with finishing

with gypsum material in 10 to 13 millimeter thickness to

previously plastered surface / or on newly brick surface (

Excluding rough cast plaster ) in all position including preparing

and Finishing the surface scaffolding etc.complete.

_

As directed by

Engineer in

charge

57 Providing and fixing H.D.P container Syntex or alike one

piece moulded water tank made out of low density

polythyler and built corrugation including of delivery up to

destination hoisting and fixing of accessories such as inlet,

outlet overflow of all tanks capacity above 1000 to 20,000

litres

_

As directed by

Engineer in

charge

58 Providing and fixing 20 to 25 mm thick rough shahabad box type

waterproofing for basement or underground floor on a base of

Cement concrete 1:3:6, including sub base of 2.50 centimeter

thick Cement mortar 1:3 with conceal, secrete (RMW), Algae

proof or other alike waterproofing liquids, raking of joints upto

35 mm depth, filling the joints with 6 mm size crushed metal,

hand grouting with cement slurry, curing and cleaning, with 7

years guarantee on court fee stamp of Rs. 100/- with ponding test

etc complete. (excluding Cement concrete 1:3:6 base concrete )

Bd.J.2 Page

No. 355

Page 142: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 44 -

Contractor No. of corrections Executive Engineer

SECTION – 8

SECURITIES AND OTHER FORMS

Page 143: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 45 -

Contractor No. of corrections Executive Engineer

Letter of Acceptance

(Letterhead paper of the Employer)

To,

________________________ [name and address of the Contractor]

Dear Sirs,

This is to notify you that your online bid dated ____________ for execution of the

______________________________________ (name of he contract and identification number, as given in

the Instructions to Bidders) for the Contract Price of Rupees ___________________________

(______________) (amount in words and figures), as corrected and modified in accordance with the

Instructions to Bidders1 is hereby accepted by our agency.

We accept / do not accept that _____________________ be appointed as the Adjudicator2.

You are hereby requested to furnish Performance Security, in the form detailed in Para 34.1 of ITB for an

amount equivalent to Rs. _____________ within 07 days of the receipt of the letter of acceptance valid up to

28 days from the date of expiry of defects Liability Period i.e. up to _______________and sign the contract,

failing which action as stated in Para 34.2 of ITB will be taken.

Yours faithfully,

Authorised Signature

Name and title of Signatory

Name of Agency

1 Delete “Corrected and” or “and modified” if only one of these actions applies. Delete as corrected and

modified in accordance with the Instructions to Bidders, if corrections or modifications have not been

affected.

2 To be used only if the contractor disagrees in his Bid with the Adjudicator proposed by the Employer in the “

Instructions to Bidders”.

Page 144: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 46 -

Contractor No. of corrections Executive Engineer

Issue of Notice to proceed with the work

(Letter head paper of the Employer)

__________________(Date)

To,

________________________ [name and address of the Contractor]

Dear Sirs,

Pursuant to your furnishing the requisite security as stipulated in ITB Clause 34.1 and signing of the

Contract for the

Bid Price of Rs.____________ .

You are hereby instructed to proceed with the execution of the said works in accordance with

the documents.

Yours faithfully,

(Signature, name and title of Signatory

Authorised to sign on behalf of Employer)

Page 145: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 47 -

Contractor No. of corrections Executive Engineer

AGREEMENT FORM

Agreement

This agreement, made the ___________ day of _____________between __________(name and

address of the Employer) [hereinafter called “the Employer] and ______________________ (name and

address of contractor) hereinafter called “the Contractor” of the other part.

Whereas the employer is desirous that the Contractor execute _______________________(name and

identification number of Contractor) (hereinafter called “the Works”) and the Employer has accepted the Bid

by the Contractor for the execution and completion of such Works and the remedying of any defects therein,

at a

cost of Rs____________

NOW THIS AGREEMENT WITNESSTH as follows :

(1) In this Agreement, words and expression shall have the same meanings as are respectively assigned to

them in the conditions of contract hereinafter referred to and they shall be deemed to form and be read

and construed as part of this Agreement.

(2) In consideration of the payments to be made by the Employer to the Contractor as hereinafter

mentioned, the Contractor hereby covenants with the Employer to all aspects with the provisions of

the contract.

(3) The Employer hereby covenants to pay the Contractor in consideration of the execution and

completion of the Works and the remedying the defects wherein Contract Price or such other sum as

may become payable under the provisions of the Contract at the times and in the manner prescribed

by the Contract.

(4) The following documents shall be deemed to form and be ready construed as part of this agreement

viz.

i) Letter of Acceptance

ii) Notice to proceed with the works

iii) Contractor’s Bid

iv) Condition of contract : General and Special

v) Contract Date

vi) Additional condition

vii) Drawings

viii) Bill of Quantities and

ix) Any other documents listed in the Contract Data as forming part of the Contract.

In witnessed whereof the parties there to have caused this Agreement to be executed the day and year

first before written.

The Common Seal of __________ was hereunto affixed in the presence of :

Signed, Sealed and Delivered by the said ___________________________

in the presence of :

Binding Signature of Employer _______________________________________________

Binding Signature of Contractor ______________________________________________

Page 146: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 48 -

Contractor No. of corrections Executive Engineer

UNDERTAKING

[Bid Validity Form]

I, the undersigned do hereby undertake that our firm M/s. _________________

________________________________ agree to abide by this bid for a period _______ days for the date fixed

for receiving the same and it shall be binding on us and may be accepted at any time before the expiration of

that period.

(Signed by an Authorized Officer of the Firm)

Title of Officer

Name of Firm

DATE

Page 147: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 49 -

Contractor No. of corrections Executive Engineer

SECTION – 9

DRAWINGS

Page 148: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 50 -

Contractor No. of corrections Executive Engineer

SECTION – 10

DOCUMENTS TO BE FURNISHED BY THE BIDDER

(Attached)

Page 149: PROCUREMENT OF CIVIL WORKS of... · Malvan Port, Tal-Malvan, Dist-Sindhudurg. E-TENDER B-II TENDER FORM . 2 Contractor No. of corrections Executive Engineer ...

- 51 -

Contractor No. of corrections Executive Engineer

* END OF THE TENDER DOCUMNET *