Page 1 of 61 Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management Authority (KSCZMA) held on 18.03.2017 at 11.00 A.M. at Room No. 252, 2 nd Floor, 2 nd Gate, M. S. Building, Bengaluru under the chairmanship of Additional Chief Secretary to Government, Forest, Ecology & Environment Department. Members Present: As per the list enclosed The Chairman welcomed the members present. All the files were placed before the Authority for perusal and the subjects were deliberated as per the Agenda. 16.1 A Brief Presentation on CRZ Notification, 2011. Presentation on CRZ Notification, 2011 was made before the Authority by the Member Secretary highlighting the salient features of the said notification and the powers and duties of the Authority in enforcing the provision of the notification, 2011. 16.2 Confirmation of the proceedings of the previous KSCZMA meeting held on 08.07.2016. The Proceedings of the previous KSCZMA meeting held on 08.07.2016 are read out and the proceedings were confirmed as there were no comments received from the members. 16.3 Action Taken Report on the proceedings of the previous KSCZMA meeting held on 08.07.2016. Action Taken Report at annexure -1 was perused and the Authority noted the action taken. 16.4 Status of Preparation of State Coastal Zone Management Plan : It was brought to the notice of the Authority that, preparation of Coastal Zone Management Plan (CZMP) as per CRZ Notification, 2011, has been awarded to the National Center for Sustainable Coastal Management (NCSCM), Chennai for Rs. 1,93,43,058/- on 02.11.2016. further it is also brought to the notice of the authority that the validity of approved CZMP as per CRZ Notification 1991, has been further extended up to 31 st July 2017 vide Notification dated 23.02.2017 of MoEF, & CC Government of India, New Delhi.

Transcript of Proceedings of the 16 th meeting of Karnataka State...

Page 1: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 1 of 61

Proceedings of the 16th meeting of Karnataka State Coastal Zone Management

Authority (KSCZMA) held on 18.03.2017 at 11.00 A.M. at Room No. 252, 2nd

Floor, 2nd Gate, M. S. Building, Bengaluru under the chairmanship of

Additional Chief Secretary to Government, Forest, Ecology & Environment

Department.

Members Present: As per the list enclosed

The Chairman welcomed the members present. All the files were placed

before the Authority for perusal and the subjects were deliberated as per the

Agenda.

16.1 A Brief Presentation on CRZ Notification, 2011.

Presentation on CRZ Notification, 2011 was made before the Authority by

the Member Secretary highlighting the salient features of the said notification

and the powers and duties of the Authority in enforcing the provision of the

notification, 2011.

16.2 Confirmation of the proceedings of the previous KSCZMA meeting held

on 08.07.2016.

The Proceedings of the previous KSCZMA meeting held on 08.07.2016 are

read out and the proceedings were confirmed as there were no comments

received from the members.

16.3 Action Taken Report on the proceedings of the previous KSCZMA

meeting held on 08.07.2016.

Action Taken Report at annexure -1 was perused and the Authority noted

the action taken.

16.4 Status of Preparation of State Coastal Zone Management Plan :

It was brought to the notice of the Authority that, preparation of Coastal

Zone Management Plan (CZMP) as per CRZ Notification, 2011, has been

awarded to the National Center for Sustainable Coastal Management (NCSCM),

Chennai for Rs. 1,93,43,058/- on 02.11.2016. further it is also brought to the notice

of the authority that the validity of approved CZMP as per CRZ Notification

1991, has been further extended up to 31st July 2017 vide Notification dated

23.02.2017 of MoEF, & CC Government of India, New Delhi.

Page 2: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 2 of 61

16.5 Online Submission of applications for CRZ clearance and Monitoring of

CRZ Clearances

It was brought to the notice of the Authority that, the Ministry of

Environment, Forest and Climate Change, Government of India has launched a

portal for online submission of applications for CRZ Clearances on 06.03.2017.

The NIC division of MoEF & CC, Government of India is organizing a workshop

in this regard on 20th March 2017 at Indira Paryavaran Bhavan, New Delhi. In

future the applications seeking CRZ clearances shall have to be received online

and processed accordingly by KSCZMA. The Authority noted the same.

The Authority suggested to send Sri. Rajanna, Scientific Officer to attend the

workshop on 20th March 2017 at New Delhi.

16.6 New Proposals

16.6.1 Request for issue of CRZ Clearance from Assistant Executive Engineer,

PWD Dept, Udupi for Improvement work to Hejamadi Kodi Fisheries Road

under National Cyclone Risk Mitigation Project (NCRMP) in Udupi Taluk

and District (FEE 281 CRZ 2016)

1. Name of the Project Improvement work to Hejamadi Kodi Fisheries Road under National Cyclone Risk Mitigation Project (NCRMP).

2. Name of the Applicant Assistant Executive Engineer, PWD Dept, Udupi Sub-division.

3. Location of the Project Village/Town, Taluk, Dt.

Hejamadi Kodi, Udupi Taluk and District.

4. R.S. No.s -

5. Extent of land -

6. CRZ Classification NDZ and outside the NDZ of CRZ-III (as per the CZMP approved 1996).

7. Project Cost Rs. 171 Lakhs

8. Activities proposed • Total length of the road project is 1.40 KM.

• CRZ clearance has already been issued for a length of 0.66 KM from P2 to P3,

• Now they have requested CRZ clearance for P1 to P2 and P3 to P4 for a balance length of 0.74 KM.

Page 3: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 3 of 61

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes.

As per the provisions under para 8 III CRZ -

III, (iii) (j) and para 8 III CRZ-III B (viii) of CRZ

Notification, 2011, construction of

dispensaries, schools, public rain shelter,

community toilets, bridges, roads, provision of

facilities for water supply, drainage, sewerage,

crematoria, cemeteries and electric sub-station

which are required for the local inhabitants are

permitted activities.

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The subject was placed before the DCZMC, Udupi on 16.09.2016 and the DCZMA has recommended the project.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA. As per para 8 III CRZ - III, (iii) (j) and para 8 III CRZ-III B (viii) of CRZ Notification, 2011 the above activity is permissible.

The Authority after discussion and deliberations decided to issue CRZ clearance

for the improvement work to Hejamadi Kodi Fisheries Road from P1 to P2 and P3 to P4

for a balance length of 0.74 KM by the Assistant Executive Engineer, PWD Dept.

Mangalore, as per the recommendation of the DCZMC, under para 8 III CRZ - III, (iii) (j)

and para 8 III CRZ-III B (viii) of CRZ Notification 2011, with the following conditions:

1. Waste materials such as mud bitumen etc should be properly disposed in a

scientific manner and it should not be dumped in water bodies.

2. The sand from the CRZ area should not be extracted and used for this purpose.

The project proponent should source the material required from authorized

quarry only.

3. Mangroves if any in the adjacent area should not be disturbed.

Page 4: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 4 of 61

16.6.2 Request for issue of CRZ Clearance from Assistant Executive Engineer,

PWD Dept, Improvement to Tenka Yermal Fisheries Road under National

Cyclone Risk Mitigation Project (NCRMP) in Udupi Taluk and District

(FEE 282 CRZ 2016)

1. Name of the Project Improvement to Tenka Yermal Fisheries Road under National Cyclone Risk Mitigation Project (NCRMP)

2. Name of the Applicant Assistant Executive Engineer, PWD Dept

3. Location of the Project Village/Town, Taluk, Dt.

Tenka Yermal, Udupi Taluk and District.

4. R.S. No.s -

5. Extent of land -

6. CRZ Classification NDZ and outside the NDZ of CRZ-III. (as per the CZMP approved 1996).

7. Project Cost Rs. 250 Lakhs.

8. Activities proposed • Total length of the road project is 2.45 KM

• CRZ clearance has already been issued for a length of 0.88 KM,

• Now they have requested for CRZ clearance for improvements to Tenka Yermal Fisheries Road from P1 to P2 and P4 to P5 for a balance length of 1.57 KM

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes.

As per the provisions under para 8 III CRZ - III, (iii) (j) and para 8 III CRZ-III B (viii) of CRZ Notification, 2011, construction of dispensaries, schools, public rain shelter, community toilets, bridges, roads, provision of facilities for water supply, drainage, sewerage, crematoria, cemeteries and electric sub-station which are required for the local inhabitants are permitted activities.

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The subject was placed before the DCZMC, Udupi on 16.09.2016 and the DCZMA has recommended the project.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA. As per para 8 III CRZ - III, (iii) (j) and para 8 III CRZ-III B (viii) of CRZ Notification 2011, the above activity is permissible.

Page 5: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 5 of 61

The Authority after discussion and deliberations decided to issue CRZ clearance

for the improvement work to Hejamadi Kodi Fisheries Road from P1 to P2 and P3 to P4

for a balance length of 0.74 KM by the Assistant Executive Engineer, PWD Dept.

Mangalore, as per the recommendation of the DCZMC, as per para 8 III CRZ - III, (iii) (j)

and para 8 III CRZ-III B (viii) of CRZ Notification 2011, with the following conditions:

1. Waste materials such as mud bitumen etc should be properly disposed in a

scientific manner and it should not be dumped in water bodies.

2. The sand from the CRZ area should not be extracted and used for this purpose.

The project proponent should source the material required from authorized

quarry only.

3. Mangroves if any in the adjacent area should not be disturbed.

16.6.3 Request for issue of CRZ Clearance from Assistant Executive Engineer,

PWD Dept, Udupi for Improvement to Road from Malpe Thottam

Gujjarabettu Fisheries Road in Badanidiyur and Tenkanidiyur village,

Udupi Taluk and District under National Cyclone Risk Mitigation Project

(NCRMP) (FEE 283 CRZ 2016)

1. Name of the Project Improvement to Road from Malpe Thottam Gujjarabettu Fisheries Road (NCRMP)

2. Name of the Applicant Assistant Executive Engineer, PWD Dept, Udupi Sub-division.

3. Location of the Project Village/Town, Taluk, Dt.

Badanidiyur and Tenkanidiyur village, Udupi Taluk and District.

4. R.S. No.s -

5. Extent of land -

6. CRZ Classification Outside the NDZ of CRZ III (as per the CZMP approved 1996).

7. Project Cost Rs. 310 Lakhs

8. Activities proposed • Total length of the road project is 2.00 KM

• CRZ clearance has already been issued for a length of 1.83 KM from P1 to P2 and P3 to P4,

• Now they have requested CRZ clearance for improvements to Road from Malpe Thottam Gujjarabettu Fisheries Road in Badanidiyur and Tenkanidiyur village from P2 to P3 for a balance length of 0.17 KM.

Page 6: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 6 of 61

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes.

As per the provisions under para 8 III CRZ-III B (viii) of CRZ Notification 2011 Construction of dispensaries, schools, public rain shelter, community toilets, bridges, roads, provision of facilities for water supply, drainage, sewerage, crematoria, cemeteries and electric sub-station which are required for the local inhabitants are permitted activities.

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The subject was placed before the DCZMC, Udupi on 16.09.2016 and the DCZMA has recommended the project.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA. As per para 8 III CRZ-III B (viii) of CRZ Notification 2011, the above activity is permissible.

The Authority after discussion and deliberations decided to issue CRZ clearance for

improvements to Road from Malpe Thottam Gujjarabettu Fisheries Road in Badanidiyur

and Tenkanidiyur village from P2 to P3 for a balance length of 0.17 KM by the Assistant

Executive Engineer, PWD Dept as per the recommendation of the DCZMC, under para 8

III CRZ-III B (viii) of CRZ Notification 2011, with the following conditions:

1. Waste materials such as mud bitumen etc should be properly disposed in a

scientific manner and it should not be dumped in water bodies.

2. The sand from the CRZ area should not be extracted and used for this purpose.

The project proponent should source the material required from authorized

quarry only.

3. Mangroves if any in the adjacent area should not be disturbed.

16.6.4 Request for issue of CRZ Clearance from Assistant Executive Engineer,

PWD Dept. Kundapura for Improvements to Road from Herikudru Temple

to National Highway in Anagalli Village, Kundapura Taluk and Udupi

District under National Cyclone Risk Mitigation Project (NCRMP) (FEE

284 CRZ 2016)

1. Name of the Project Improvements to Road from Herikudru Temple to National Highway (NCRMP)

Page 7: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 7 of 61

2. Name of the Applicant Assistant Executive Engineer, PWD Dept, Udupi, Sub-division.

3. Location of the Project Village/Town, Taluk, Dt.

Anagalli Village, Kundapura Taluk and Udupi District

4. R.S. No.s -

5. Extent of land -

6. CRZ Classification NDZ of CRZ-III (as per the CZMP approved 1996).

7. Project Cost Rs. 165.5 Lakhs

8. Activities proposed • Total length of the road project is 2.12 KM

• CRZ clearance has already been issued for a length of 0.71 KM from P1 to P2,

• Now they have requested CRZ clearance for improvements to Road from Herikudru Temple to National Highway in Anagalli Village from P2 to P3 for a balance length of 1.41 KM.

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes.

As per the provisions under para 8 III CRZ-III,

(iii) (j) of CRZ Notification, 2011, construction

of dispensaries, schools, public rain shelter,

community toilets, bridges, roads, provision of

facilities for water supply, drainage, sewerage,

crematoria, cemeteries and electric sub-station

which are required for the local inhabitants

may be permitted activities.

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The subject was placed before the DCZMC, Udupi on 16.09.2016 and the DCZMA has recommended the project.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA. As per para 8 III CRZ - III, (iii) (j) of CRZ Notification 2011, the above activity is permissible.

The Authority after discussion and deliberations decided to issue CRZ clearance for

improvements to Road from Herikudru Temple to National Highway in Anagalli Village

from P2 to P3 for a balance length of 1.41 KM, by the Assistant Executive Engineer,

Page 8: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 8 of 61

PWD Dept as per the recommendation of the DCZMC, under para 8 III CRZ - III, (iii)

(j) of CRZ Notification 2011, with the following conditions:

1. Waste materials such as mud bitumen etc should be properly disposed in a

scientific manner and it should not be dumped in water bodies.

2. The sand from the CRZ area should not be extracted and used for this purpose.

The project proponent should source the material required from authorized

quarry only.

3. Mangroves if any in the adjacent area should not be disturbed.

16.6.5 Request for issue of CRZ Clearance from Assistant Executive Engineer, PWD Dept, Udupi for Improvements to Road from Herikudru School Road to National Highway at Anagalli Village, Kundapura Taluk, Kundapura Taluk and Udupi District under National Cyclone Risk Mitigation Project (NCRMP) (FEE 285 CRZ 2016)

1. Name of the Project Improvements to Road from Herikudru School Road to National Highway (NCRMP)

2. Name of the Applicant Assistant Executive Engineer, PWD Dept, Udupi Sub-division.

3. Location of the Project Village/Town, Taluk, Dt.

Anagalli Village, Kundapura Taluk and Udupi District.

4. R.S. No.s -

5. Extent of land

6. CRZ Classification NDZ of CRZ-III. (as per the CZMP approved 1996).

7. Project Cost Rs. 58.00 Lakhs

8. Activities proposed • Total length of the road project is 0.82 KM

• CRZ clearance has already been issued for a length of 0.70 KM from P2 to P3,

• Now they have requested CRZ clearance for Improvement to Road from Herikudru School Road to National Highway at Anagalli Village from P1 to P2 for a balance length of 0.12 KM.

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes.

As per the provisions under para 8 III CRZ-III,

(iii) (j) of CRZ Notification 2011, construction of

dispensaries, schools, public rain shelter,

community toilets, bridges, roads, provision of

facilities for water supply, drainage, sewerage,

crematoria, cemeteries and electric sub-station

which are required for the local inhabitants are

permitted activities.

Page 9: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 9 of 61

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The subject was placed before the DCZMC, Udupi on 16.09.2016 and the DCZMA has recommended the project.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA. As per para 8 III CRZ-III, (iii) (j) of CRZ Notification 2011 the above activity is permissible.

The Authority after discussion and deliberations decided to issue CRZ clearance for

Improvement to Road from Herikudru School Road to National Highway at Anagalli

Village from P1 to P2 for a balance length of 0.12 KM, by the Assistant Executive

Engineer, PWD Dept as per the recommendation of the DCZMC, para 8 III CRZ-III, (iii)

(j) of CRZ Notification 2011, with the following conditions:

1. Waste materials such as mud bitumen etc should be properly disposed in a

scientific manner and it should not be dumped in water bodies.

2. The sand from the CRZ area should not be extracted and used for this purpose.

The project proponent should source the material required from authorized

quarry only.

3. Mangroves if any in the adjacent area should not be disturbed.

16.6.6 Request for issue of CRZ Clearance from Assistant Executive Engineer,

PWD Dept, Udupi for Improvements to road from Bengri Naga temple to

Trasi Gangolli Main Road in Gujjadi village, Kundapura Taluk and Udupi

District under National Cyclone Risk Mitigation Project (NCRMP) (FEE

286 CRZ 2016)

1. Name of the Project Improvements to road from Bengri Naga temple to Trasi Gangolli Main Road

(NCRMP)

2. Name of the Applicant Assistant Executive Engineer, PWD Dept, Udupi Sub-division.

3. Location of the Project Village/Town, Taluk, Dt.

Gujjadi village, Kundapura Taluk and Udupi District

4. R.S. No.s -

5. Extent of land -

6. CRZ Classification NDZ and outside the NDZ of CRZ-III (as per the CZMP approved 1996).

Page 10: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 10 of 61

7. Project Cost Rs. 54.00 Lakhs

8. Activities proposed • Total length of the project is 1.04 KM

• CRZ clearance already been issued for a length of 0.50 KM from P2 to P3

• Now they have requested to issue CRZ clearance for improvements to road from Bengri Naga temple to Trasi Gangolli Main Road from P1 to P2 for a balance length of 0.54 KM.

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes.

As per the provisions under para 8 III CRZ -

III, (iii) (j) and para 8 III CRZ-III B (viii) of

CRZ Notification 2011, construction of

dispensaries, schools, public rain shelter,

community toilets, bridges, roads, provision

of facilities for water supply, drainage,

sewerage, crematoria, cemeteries and electric

sub-station which are required for the local

inhabitants are permitted activities.

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The subject was placed before the DCZMC, Udupi on 16.09.2016 and the DCZMA has recommended the project.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA. As per the provisions under para 8 III CRZ - III, (iii) (j) and para 8 III CRZ-III B (viii) of CRZ Notification 2011, the above activity is permissible.

The Authority after discussion and deliberations decided to issue CRZ clearance for

improvements to road from Bengri Naga temple to Trasi Gangolli Main Road from P1 to

P2 for a balance length of 0.54 KM, by the Assistant Executive Engineer, PWD Dept as

per the recommendation of the DCZMC, under para 8 III CRZ - III, (iii) (j) and para 8

III CRZ-III B (viii) of CRZ Notification 2011, with the following conditions:

1. Waste materials such as mud bitumen etc should be properly disposed in a

scientific manner and it should not be dumped in water bodies.

Page 11: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 11 of 61

2. The sand from the CRZ area should not be extracted and used for this purpose.

The project proponent should source the material required from authorized

quarry only.

3. Mangroves if any in the adjacent area should not be disturbed.

16.6.7 Request for issue of CRZ Clearance from Assistant Executive Engineer,

PWD Dept, Udupi for Improvement work to Uppunda Medical Alvekode

Fisheries Road at Kundapura Taluk and Udupi District under National

Cyclone Risk Mitigation Project (NCRMP). (FEE 287 CRZ 2016)

1. Name of the Project Improvement work to Uppunda Medical Alvekode Fisheries Road (NCRMP)

2. Name of the Applicant Assistant Executive Engineer, PWD Dept, Udupi, Sub-division.

3. Location of the Project Village/Town, Taluk, Dt.

Alvekode Village, Kundapura Taluk and Udupi District.

4. R.S. No.s -

5. Extent of land

6. CRZ Classification NDZ and outside the NDZ of CRZ-III (as per the CZMP approved 1996.

7. Project Cost Rs. 162.00 Lakhs

8. Activities proposed • Total length of road project is 1.80 KM

• CRZ clearance has already been issued for a length of 1.30 KM,

• Now they have requested to issue CRZ clearance for improvement work to Uppunda Medical Alvekode Fisheries Road for a balance length of 0.50 KM

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes.

As per the provisions under para 8 III CRZ-

III, (iii) (j) and para 8 III CRZ-III B (viii) of

CRZ Notification 2011, construction of

dispensaries, schools, public rain shelter,

community toilets, bridges, roads, provision

of facilities for water supply, drainage,

sewerage, crematoria, cemeteries and electric

sub-station which are required for the local

inhabitants are permitted activities.

10. The details of recommendations of the District Coastal Zone Management Authority

The subject was placed before the DCZMC, Udupi on 16.09.2016 and the DCZMA has recommended the project .

Page 12: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 12 of 61

(DCZMA)

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA. As per the provisions under para 8 III CRZ-III, (iii) (j) and para 8 III CRZ-III B (viii) of CRZ Notification 2011, the above activity is permissible.

The Authority after discussion and deliberations decided to issue CRZ clearance for

improvement work to Uppunda Medical Alvekode Fisheries Road for a balance length of

0.50 KM by the Assistant Executive Engineer, PWD Dept. Mangalore, as per the

recommendation of the DCZMC, under para 8 III CRZ-III, (iii) (j) and para 8 III

CRZ-III B (viii) CRZ Notification 2011, with the following conditions:

1. Waste materials such as mud bitumen etc should be properly disposed in a

scientific manner and it should not be dumped in water bodies.

2. The sand from the CRZ area should not be extracted and used for this purpose.

The project proponent should source the material required from authorized

quarry only.

3. Mangroves if any in the adjacent area should not be disturbed.

16.6.8 Request for issue of CRZ Clearance from Assistant Executive Engineer,

PWD Dept, Udupi for Improvement work to Yadthare – Paduvari –

Customs to National Highway 66, Kundapura Taluk and Udupi District

under National Cyclone Risk Mitigation Project (NCRMP). (FEE 288 CRZ

2016)

1. Name of the Project Improvement work to Yadthare – Paduvari – Customs to National Highway 66 (NCRMP)

2. Name of the Applicant Assistant Executive Engineer, PWD Dept, Udupi, Sub-division.

3. Location of the Project Village/Town, Taluk, Dt.

Yadthare – Paduvari Village, Kundapura Taluk and Udupi District

4. R.S. No.s -

5. Extent of land -

6. CRZ Classification NDZ and outside the NDZ areas of CRZ-III (as per the CZMP approved 1996).

7. Project Cost Rs. 144.00 Lakhs

8. Activities proposed • Total length of road project is 1.6 KM out of which, from P1 to P2

• CRZ clearance has already been issued for a length of 1.18 KM.

Page 13: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 13 of 61

• Now they have requested to issue CRZ clearance for improvement work to Yadthare – Paduvari – Customs to National Highway 66 for a balance length of 0.42 KM.

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes.

As per the provisions under para 8 III CRZ-

III, (iii) (j) and para 8 III CRZ-III B (viii) of

CRZ Notification 2011, construction of

dispensaries, schools, public rain shelter,

community toilets, bridges, roads, provision

of facilities for water supply, drainage,

sewerage, crematoria, cemeteries and electric

sub-station which are required for the local

inhabitants are permitted activities.

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The subject was placed before the DCZMC, Udupi on 16.09.2016 and the DCZMA has recommended the project.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA. As per the provisions under para 8 III CRZ-III, (iii) (j) and para 8 III CRZ-III B (viii) of CRZ Notification 2011, the above activity is permissible.

The Authority after discussion and deliberations decided to issue CRZ clearance for

improvement work to Yadthare – Paduvari – Customs to National Highway 66 for a

balance length of 0.42 KM by the Assistant Executive Engineer, PWD Dept. Mangalore,

as per the recommendation of the DCZMC, under para 8 III CRZ-III, (iii) (j) and para 8

III CRZ-III B (viii) of CRZ Notification 2011, with the following conditions:

1. Waste materials such as mud bitumen etc should be properly disposed in a

scientific manner and it should not be dumped in water bodies.

2. The sand from the CRZ area should not be extracted and used for this purpose.

The project proponent should source the material required from authorized

quarry only.

3. Mangroves if any in the adjacent area should not be disturbed.

Page 14: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 14 of 61

16.6.9 Request for issue of CRZ Clearance from Assistant Executive Engineer,

PWD Dept, Udupi for Improvement work to Yadthare Market Road,

Yadthare & Paduvari Village, Kundapura Taluk and Udupi District under

National Cyclone Risk Mitigation Project (NCRMP) (FEE 289 CRZ 2016)

1. Name of the Project Improvement work to Yadthare Market Road, (NCRMP)

2. Name of the Applicant Assistant Executive Engineer, PWD Dept, Udupi, Sub-division.

3. Location of the Project Village/Town, Taluk, Dt.

Yadthare & Paduvari Village, Kundapura Taluk and Udupi District

4. R.S. No.s -

5. Extent of land -

6. CRZ Classification NDZ and outside the NDZ areas of CRZ-III (as per the CZMP approved 1996).

7. Project Cost Rs. 144.00 Lakhs

8. Activities proposed • Total length of road project is 1.60 KM,

• CRZ clearance has already been issued for a length of 1.19 KM from P2 to P3

• Now they have requested to issue CRZ clearance for taking up improvement work of Yadthare Market Road for a balance length of 0.41 KM.

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes.

As per the provisions under As per the

provisions under para 8 III CRZ-III, (iii) (j)

and para 8 III CRZ-III B (viii) of CRZ

Notification 2011, of CRZ Notification 2011,

construction of dispensaries, schools, public

rain shelter, community toilets, bridges,

roads, provision of facilities for water supply,

drainage, sewerage, crematoria, cemeteries

and electric sub-station which are required

for the local inhabitants are permitted

activities.

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The subject was placed before the DCZMC, Udupi on 16.09.2016 and the DCZMA has recommended the project.

11. Any other details -

Page 15: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 15 of 61

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA. As per the provisions under para 8 III CRZ-III, (iii) (j) and para 8 III CRZ-III B (viii) of CRZ Notification 2011, the above activity is permissible.

The Authority after discussion and deliberations decided to issue CRZ clearance for

improvement work to Yadthare Market Road for a balance length of 0.41 KM by the

Assistant Executive Engineer, PWD Dept, Mangalroe, as per the recommendation of the

DCZMC, under para 8 III CRZ-III, (iii) (j) and para 8 III CRZ-III B (viii) of CRZ

Notification 2011, with the following conditions:

1. Waste materials such as mud bitumen etc should be properly disposed in a

scientific manner and it should not be dumped in water bodies.

2. The sand from the CRZ area should not be extracted and used for this purpose.

The project proponent should source the material required from authorized

quarry only.

3. Mangroves if any in the adjacent area should not be disturbed.

16.6.10 Request for issue of CRZ Clearance from Assistant Executive Engineer,

PWD Dept, Udupi for Improvement works to Road from National Highway

66 to shiroor under bridge approach Road at Kundapura Taluk and Udupi

District under National Cyclone Risk Mitigation Project (NCRMP) (FEE

290 CRZ 2016)

1. Name of the Project Improvement works to Road from National Highway 66 to shiroor under bridge approach Road (NCRMP)

2. Name of the Applicant Assistant Executive Engineer, PWD Dept, Udupi, Sub-division.

3. Location of the Project Village/Town, Taluk, Dt.

shiroor Village, Kundapura Taluk and Udupi District

4. R.S. No.s -

5. Extent of land -

6. CRZ Classification NDZ and outside of CRZ-III (as per the CZMP approved 1996).

7. Project Cost Rs. 108.00 Lakhs

8. Activities proposed • Total length of road project is 1.20 KM

• CRZ clearance has already been issued for a length of 0.90 KM,

• Now they have requested to issue CRZ clearance for improvement works to Road

Page 16: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 16 of 61

from National Highway 66 to shiroor under bridge approach Road from P2 to P3 for a balance length of 0.30 KM.

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes.

As per the provisions under para 8 III CRZ-

III, (iii) (j) and para 8 III CRZ-III B (viii) of

CRZ Notification 2011, construction of

dispensaries, schools, public rain shelter,

community toilets, bridges, roads, provision

of facilities for water supply, drainage,

sewerage, crematoria, cemeteries and electric

sub-station which are required for the local

inhabitants are permitted activities.

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The subject was placed before the DCZMC, Udupi on 16.09.2016 and the DCZMA has recommended the project.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA. As per the provisions under para 8 III CRZ-III, (iii) (j) and para 8 III CRZ-III B (viii) of CRZ Notification 2011, the above activity is permissible.

The Authority after discussion and deliberations decided to issue CRZ clearance for

improvement works to Road from National Highway 66 to shiroor under bridge approach

Road from P2 to P3 for a balance length of 0.30 KM, by the Assistant Executive

Engineer, PWD Dept, Mangalore, as per the recommendation of the DCZMC, under para

8 III CRZ-III, (iii) (j) and para 8 III CRZ-III B (viii) of CRZ Notification 2011,with the

following conditions:

1. Waste materials such as mud bitumen etc should be properly disposed in a

scientific manner and it should not be dumped in water bodies.

2. The sand from the CRZ area should not be extracted and used for this purpose.

The project proponent should source the material required from authorized

quarry only.

3. Mangroves if any in the adjacent area should not be disturbed.

Page 17: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 17 of 61

16.6.11 Request for issue of CRZ Clearance from Assistant Executive Engineer,

PWD Dept, Udupi for Improvement work to Yadthare – Alvegadde

Fisheries Road in Shiroor village, Kundapura Taluk and Udupi District

under National Cyclone Risk Mitigation Project (NCRMP) (FEE 291 CRZ

2016)

1. Name of the Project Improvement work to Yadthare – Alvegadde Fisheries Road (NCRMP)

2. Name of the Applicant Assistant Executive Engineer, PWD Dept, Udupi, Sub-division.

3. Location of the Project Village/Town, Taluk, Dt.

Shiroor village, Kundapura Taluk and Udupi District

4. R.S. No.s -

5. Extent of land -

6. CRZ Classification NDZ and outside of NDZ areas of CRZ-III (as per the CZMP approved 1996)

7. Project Cost Rs. 166.00 Lakhs

8. Activities proposed • Total length of the road project is 1.90 KM,

• CRZ clearance has already been issued for a length of 1.01 KM from P2 to P3,

• Now they have requested to issue CRZ clearance for taking up improvement work to Shiroor – Alvegadde Fisheries Road from P1 to P2 for a balance length of 0.89 KM.

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes.

As per the provisions para 8 III CRZ-III, (iii)

(j) and para 8 III CRZ-III B (viii) of CRZ

Notification 2011, construction of

dispensaries, schools, public rain shelter,

community toilets, bridges, roads, provision

of facilities for water supply, drainage,

sewerage, crematoria, cemeteries and

electric sub-station which are required for

the local inhabitants are permitted activities.

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The subject was placed before the DCZMC, Udupi on 16.09.2016 and the DCZMA has recommended the project.

Page 18: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 18 of 61

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA. As per the provisions under para 8 III CRZ-III, (iii) (j) and para 8 III CRZ-III B (viii) of CRZ Notification 2011, the above activity is permissible.

The Authority after discussion and deliberations decided to issue CRZ clearance for

improvement work to Shiroor – Alvegadde Fisheries Road from P1 to P2 for a balance

length of 0.89 KM, by the Assistant Executive Engineer, PWD Dept, Mangalore, as per

the recommendation of the DCZMC, under para 8 III CRZ-III, (iii) (j) and para 8 III

CRZ-III B (viii) of CRZ Notification, 2011 with the following conditions:

1. Waste materials such as mud bitumen etc should be properly disposed in a

scientific manner and it should not be dumped in water bodies.

2. The sand from the CRZ area should not be extracted and used for this purpose.

The project proponent should source the material required from authorized

quarry only.

3. Mangroves if any in the adjacent area should not be disturbed.

16.6.12 Request for issue of CRZ Clearance from Assistant Executive Engineer,

PWD Dept, Udupi for Improvement works to Yadthare - Paduvari –

Someshwara Road in Paduvari village, Kundapura Taluk and Udupi

Districtunder National Cyclone Risk Mitigation Project (NCRMP) (FEE 292

CRZ 2016)

1. Name of the Project Improvement works to Yadthare - Paduvari – Someshwara Road (NCRMP)

2. Name of the Applicant Assistant Executive Engineer, PWD Dept, Udupi, Sub-division.

3. Location of the Project Village/Town, Taluk, Dt.

Paduvari Village, Kundapura Taluk and Udupi District

4. R.S. No.s -

5. Extent of land

6. CRZ Classification NDZ and outside the NDZ areas of CRZ-III (as per the CZMP approved 1996).

7. Project Cost Rs. 286.00 Lakhs

8. Activities proposed • Total length of road project is 3.30 KM and out of which,

• CRZ clearance has already been issued from P1 to P2 for a length of 1.47 KM,

Page 19: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 19 of 61

• Now they have requested to issue CRZ clearance for taking up improvement works to Yadthare - Paduvari – Someshwara Road in Paduvari village from P2 to P3 for a balance length of 1.83 KM.

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes.

As per the provisions under para 8 III CRZ-

III, (iii) (j) and para 8 III CRZ-III B (viii) of

CRZ Notification 2011, construction of

dispensaries, schools, public rain shelter,

community toilets, bridges, roads, provision

of facilities for water supply, drainage,

sewerage, crematoria, cemeteries and electric

sub-station which are required for the local

inhabitants are permitted activities.

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The subject was placed before the DCZMC, Udupi on 16.09.2016 and the DCZMA has recommended the project.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA. As per the provisions under para 8 III CRZ-III, (iii) (j) and para 8 III CRZ-III B (viii) of CRZ Notification 2011, the above activity is permissible.

The Authority after discussion and deliberations decided to issue CRZ clearance

for taking up improvement works to Yadthare - Paduvari – Someshwara Road in

Paduvari village from P2 to P3 for a balance length of 1.83 KM, by the Assistant

Executive Engineer, PWD Dept, Mangalore, as per the recommendation of the DCZMC,

under para 8 III CRZ-III, (iii) (j) and para 8 III CRZ-III B (viii) of CRZ Notification,

2011 with the following conditions:

1. Waste materials such as mud bitumen etc should be properly disposed in a

scientific manner and it should not be dumped in water bodies.

2. The sand from the CRZ area should not be extracted and used for this purpose.

The project proponent should source the material required from authorized

quarry only.

3. Mangroves if any in the adjacent area should not be disturbed.

Page 20: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 20 of 61

16.6.13 Request for issue of CRZ Clearance from Assistant Executive Engineer,

PWD Dept, Udupi for Improvement work to road from Thekkatte to Kome

Fisheries Road (Subramanya Temple Road), Kundapura Taluk and Udupi

District under National Cyclone Risk Mitigation Project (NCRMP) (FEE

293 CRZ 2017)

1. Name of the Project Improvement work to road from Thekkatte to Kome Fisheries Road (Subramanya Temple Road (NCRMP)

2. Name of the Applicant

Assistant Executive Engineer, PWD Dept, Udupi, Sub-division.

3. Location of the Project Village/Town, Taluk, Dt.

Thekkattee to kome Village, Kundapura Taluk and Udupi District

4. R.S. No.s -

5. Extent of land -

6. CRZ Classification NDZ and outside the NDZ areas of CRZ –I and CRZ-III (as per the CZMP approved 1996).

7. Project Cost Rs. 181.00 Lakhs

8. Activities proposed Total length of road project is 2.10 KM. The GPS Readings of P1 of said road is N 130 32’ 52.3” and E 740 42’ 06.3” GPS Readings of P2 of said road is N 130 32’ 42.5” and E 740 40’ 56.4”.

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes.

As per the provisions under para 8 III CRZ-III, (iii) (j)

and para 8 III CRZ-III B (viii) of CRZ Notification

2011, construction of dispensaries, schools, public rain

shelter, community toilets, bridges, roads, provision

of facilities for water supply, drainage, sewerage,

crematoria, cemeteries and electric sub-station which

are required for the local inhabitants are permitted

activities..

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The subject was placed before the DCZMC, Udupi on 16.09.2016 and the DCZMA has recommended the project.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA. As per the provisions under para 8 III CRZ-III, (iii) (j) and para 8 III CRZ-III B (viii) of CRZ Notification 2011, the above activity is permissible.

[

Page 21: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 21 of 61

The Authority after discussion and deliberations decided to issue CRZ clearance

for Improvement works to Beejadi Fisheries Road by the Assistant Executive Engineer,

PWD Dept, Mangalore, as per the recommendation of the DCZMC, under para 8 III

CRZ-III, (iii) (j) and para 8 III CRZ-III B (viii) of CRZ Notification 2011, with the

following conditions:

1. Waste materials such as mud bitumen etc should be properly disposed in a

scientific manner and it should not be dumped in water bodies.

2. The sand from the CRZ area should not be extracted and used for this purpose.

The project proponent should source the material required from authorized

quarry only.

3. Mangroves if any in the adjacent area should not be disturbed.

16.6.14 Request for issue of CRZ Clearance from Assistant Executive Engineer,

PWD Dept, Udupi for Improvement works to Beejadi Fisheries Road in

Kundapura Taluk and Udupi District under National Cyclone Risk

Mitigation Project (NCRMP) (FEE 294 CRZ 2017)

1. Name of the Project Improvement works to Beejadi Fisheries Road (NCRMP)

2. Name of the Applicant Assistant Executive Engineer, PWD Dept, Udupi, Sub-division.

3. Location of the Project Village/Town, Taluk, Dt.

Beejadi Village, Kundapura Taluk and Udupi District

4. R.S. No.s -

5. Extent of land -

6. CRZ Classification NDZ and outside the NDZ areas of CRZ-III (as per the CZMP approved 1996).

7. Project Cost Rs. 190.00 Lakhs

8. Activities proposed Total length of road project is 2.15 KM. The GPS Readings of the project site is N 130 34’ 36.4” E 740 41’ 50.2” to N 130 34’ 36.9” E 740 40’ 39.7”.

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes.

As per the provisions under para 8 III CRZ-III,

(iii) (j) and para 8 III CRZ-III B (viii) of CRZ

Notification 2011, construction of

dispensaries, schools, public rain shelter,

community toilets, bridges, roads, provision of

facilities for water supply, drainage, sewerage,

crematoria, cemeteries and electric sub-station

which are required for the local inhabitants are

permitted activities.

Page 22: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 22 of 61

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The subject was placed before the DCZMC, Udupi on 16.09.2016 and the DCZMA has recommended the project.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA. As per the provisions under para 8 III CRZ-III, (iii) (j) and para 8 III CRZ-III B (viii) of CRZ Notification 2011, the above activity is permissible.

The Authority after discussion and deliberations decided to issue CRZ clearance

for Improvement works to Beejadi Fisheries Road for a length of 2.15 KM by the

Assistant Executive Engineer, PWD Dept Mangalore, as per the recommendation of the

DCZMC under para 8 III CRZ-III, (iii) (j) and para 8 III CRZ-III B (viii) of CRZ

Notification 2011, with the following conditions:

1. Waste materials such as mud bitumen etc should be properly disposed in a

scientific manner and it should not be dumped in water bodies.

2. The sand from the CRZ area should not be extracted and used for this purpose.

The project proponent should source the material required from authorized

quarry only.

3. Mangroves if any in the adjacent area should not be disturbed.

[

16.6.15 Request for issue of CRZ Clearance from Assistant Executive Engineer, PWD Dept, Udupi for Improvement works to Koderi Fisheries Road in Kundapura Taluk and Udupi District under National Cyclone Risk Mitigation Project (NCRMP). (FEE 295 CRZ 2016)

1. Name of the Project Improvement works to Koderi Fisheries Road (NCRMP)

2. Name of the Applicant Assistant Executive Engineer, PWD Dept, Udupi, Sub-division.

3. Location of the Project Village/Town, Taluk, Dt.

Koderi Village, Kundapura Taluk and Udupi District

4. R.S. No.s -

5. Extent of land -

6. CRZ Classification NDZ and outside the NDZ areas of CRZ-III (as per the CZMP approved 1996).

7. Project Cost Rs. 90.00 Lakhs.

8. Activities proposed Total length of road project is 1.00 KM. The GPS Readings of the project site is N 130 47’ 21.6” E 740 37’ 37.8” to N 130 47’ 07.3” E 740 37’ 55.7”.

Page 23: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 23 of 61

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes.

As per the provisions under 8 III CRZ-III, (iii) (j) and

para 8 III CRZ-III B (viii) of CRZ Notification 2011,

construction of dispensaries, schools, public rain

shelter, community toilets, bridges, roads, provision

of facilities for water supply, drainage, sewerage,

crematoria, cemeteries and electric sub-station which

are required for the local in habitants are permitted

activities.

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The subject was placed before the DCZMC, Udupi on 16.09.2016 and the DCZMA has recommended the project.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA. As per the provisions under para 8 III CRZ-III, (iii) (j) and para 8 III CRZ-III B (viii) of CRZ Notification 2011, the above activity is permissible.

The Authority after discussion and deliberations decided to issue CRZ clearance

for Improvement works to Beejadi Fisheries Road by the Assistant Executive Engineer,

PWD Dept Mangalore, as per the recommendation of the DCZMC, under para 8 III CRZ-

III, (iii) (j) and para 8 III CRZ-III B (viii) of CRZ Notification 2011, with the following

conditions:

1. Waste materials such as mud bitumen etc should be properly disposed in a

scientific manner and it should not be dumped in water bodies.

2. The sand from the CRZ area should not be extracted and used for this purpose.

The project proponent should source the material required from authorized

quarry only.

3. Mangroves if any in the adjacent area should not be disturbed.

16.6.16 Request for issue of CRZ Clearance to Joint Director of Fisheries,

Fishing Harbours, Malpe for construction of Breakwater /Guide Bund

adjacent to the Navigational Channel at Gangolli Fishing Harbour in

Kundapura Taluk -regarding (FEE 4 CRZ 2017).

1. Name of the Project Construction of Breakwater /Guide Bund adjacent to the Navigational Channel

2. Name of the Applicant Joint Director of Fisheries, Fishing Harbours, Malpe

Page 24: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 24 of 61

3. Location of the Project Village/Town, Taluk, Dt.

Gangolli Fishing Harbour in Kundapura Taluk and Udupi District

4. R.S. No.s -

5. Extent of land -

6. CRZ Classification CRZ-IV.

7. Project Cost 102.00 Crores.

8. Activities proposed Proposed to construct guide bund from 126m to 700 m on northern side and 0 to 900 m on southern side of Navigational Channel.

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes, it is a permitted activity,

As per para 4 (i) (f) of CRZ Notification 2011,

construction and operation for ports and

harbours, jetties, wharves, quays, slipways,

ship construction yards, breakwaters, groynes,

erosion control measures; are permitted

activities.

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The subject was placed before the DCZMC, Udupi on 21.12.2016 and the DCZMA has recommended the project.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA. As per para 4 (i) (f) of CRZ Notification 2011, the above activity is permissible.

The Authority after discussion and deliberations decided to issue CRZ clearance

for construction of Breakwater /Guide Bund adjacent to the Navigational Channel at

Gangolli Fishing Harbour by the Joint Director of Fisheries, Fishing Harbours, Malpe as

per the recommendation of the DCZMC, under as per para 4 (i) (f) of CRZ Notification

2011, with the following conditions:-

1. Ecologically sensitive areas like mangroves/mud flats/ turtle nesting areas/

Salt Marshes should not be disturbed.

2. Safe and scientific disposal of wastes

3. The materials required for construction of breakwater/guide bund should be

source from outside the CRZ area.

4. Steps should be taken to prevent any pollution due to operation of

machines.

Page 25: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 25 of 61

16.6.17 Request for issue of CRZ Clearance to Udupi Power Corporation

Limited (UPCL) for Laying of pipeline for Sea Water Intake and Outfall for

Proposed Expansion of UPCL from 1200MW to 2800MW at Yelluru Village,

Udupi Taluk and District (FEE 5 CRZ 2017)

1. Name of the Project Laying of pipeline for Sea Water Intake and Outfall for Proposed Expansion of UPCL from 1200MW to 2800MW

2. Name of the Applicant Udupi Power Corporation Limited (UPCL)

3. Location of the Project Village/Town, Taluk, Dt.

Yelluru Village, Udupi Taluk and District

4. R.S. No.s -

5. Extent of land Existing land corridor (25 mts width)

6. CRZ Classification CRZ I , III, IV.

7. Project Cost -

8. Activities proposed • Proposed new pipeline for 2800 MW TPP in existing land corridor in CRZ –I & CRZ III.

• Intake pipes from land Fall Point (LP) to Caisson with option of off-shore pump house at proposed intake point in CRZ –IV at -6.8 meters CD and -650 meters from shore-line.

• Outfall pipe to diffusers at proposed outfall point in CRZ –IV at 7.5 meter CD and -1750 meters from the shore-line.

• Seawater requirement for TPP after expansion to 2800 MW, shall be 24,381 M3/Hr which is proposed to met from Arabian Sea.

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes.

As per the provisions under para 4 (ii) (d) & 4 (ii)

(f) of CRZ Notification 2011, it is a permitted

activity.

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The subject was placed before the DCZMC, Udupi on 21.12.2016 and the DCZMA has recommended the project.

11. Any other details Earlier CRZ clearance was issued for laying of pipeline for the existing 2x600 MW unit by MoEF vide letter dated 18.05.2010. The pipeline runs to a total distance of 598 mts out of which 520 mts is in CRZ-III and 78 meters in CRZ-I.

Page 26: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 26 of 61

The existing corridor is 25 M wide all through, the existing intake point is 1430 M inside the sea and the outfall point is 670 M from HTL. Due to operational constraints faced in the sea water intake system of the existing phase -1 sea water intake system will be designed to cater both phase I & II water requirements up to sea water intake pump house.

• Seawater requirement for existing 2x600 MW units are 10,000 M3/Hr which is met from Arabian Sea.

• For existing unit 87.6 MCM/year sea water is require. After expansion to 2800 MW, total intake & outfall of Sea water shall be 213.6 MCM/year & 175.2 MCM respectively.

• Proposed intake and outfall coordinates have been recommended by NIO after Modeling Studies.

• The 3 existing pipelines of 1.1 meter dia will be replaced with new pipelines of 1.4 meter dia for each of 2 intake pipelines and 1.2 meter dia for 1 outfall pipeline in the existing land corridor of 25 mts width.

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of National Coastal Zone Management Authority. As per para 4 (ii) (d) and 4 (ii) (f) of CRZ Notification 2011, the above activity requires clearance from the Ministry of Environment and Forests, Government of India, with the recommendation of SCZMA.

The Authority perused the information furnished by the proponent and after

discussion and deliberations, decided to recommend the proposal to MoEF with standard

conditions to issue CRZ clearance for laying of pipelines within the approved land

corridor of 25 mts width as per para 4 (ii) (d) and for laying pipeline for sea water intake

and outfall, as per para 4 (ii) (f) of CRZ Notification 2011.

Page 27: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 27 of 61

16.6.18 Request for issue of CRZ Clearance to Removal of Sand by dredging

from adjoining waterfront area of M/s. Waterways Shipyard Pvt. Ltd., at Sy.

No. 53 and 56 of Balekudru Village, Hungarkatta, Udupi -regarding (FEE 6

CRZ 2017)

1. Name of the Project Removal of Sand by dredging from adjoining waterfront area

2. Name of the Applicant Assistant Executive Engineer, PWD Dept

3. Location of the Project Village/Town, Taluk, Dt.

Balekudru Village, Hungarkatta, Udupi

4. R.S. No.s Sy. No. 53 and 56

5. Extent of land 150 meter length & 50 meter width.

6. CRZ Classification CRZ-IV

7. Project Cost -

8. Activities proposed Due to accumulation of sand, etc in the adjoining waterfront of project site, dredging is to be carried out for safety lanching of vessels.

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes.

As per the para 4 (i) (f) of CRZ Notification,

2011, construction and operation for ports and

harbours, jetties, wharves, quays, slipways,

ship construction yards, breakwaters, groynes,

erosion control measures; are permitted

activities.

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The subject was placed before the DCZMC, Udupi on 21.12.2016 and the DCZMA has recommended the project subject to the following conditions;

1. Mines and Geology Department shall be intimated before work is to be taken up by the proponent and removed sand should be handed over to Mines and Geology Department.

2. The proponent shall follow all the rules and regulations which are in force at the time of execution of work.

3. The proponent should restrict the activity to the permitted depth and quantity of material.

4. The proponent shall take necessary action for safe disposal of waste materials.

Page 28: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 28 of 61

11. Any other details Estimated area of dredging is 150 m X50 M with 4 m depth. The depth required for the vessels to float is around 1.5 m to 2 m. Based on the above details, estimated quantity of removal of sand, silt and other materials is 30,000 Cum.

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA. As per the para 4 (i) (f) of CRZ Notification, 2011, Construction and operation for ports and harbours, jetties, wharves, quays, slipways, ship construction yards, breakwaters, groynes, erosion control measures; are permitted activities.

The Authority after discussion and deliberations decided to issue CRZ clearance

for Removal of Sand by dredging from adjoining waterfront area by the M/s.

Waterways Shipyard Pvt. Ltd., as per the recommendation of the DCZMC, under para

4 (i) (f) of CRZ Notification 2011, with the following conditions:-

1. Ecologically sensitive areas like mangroves/mud flats/ turtle nesting areas/ Salt

Marshes should not be disturbed.

2. Safe and scientific disposal of wastes

3. Steps should be taken to prevent any pollution due to operation of machines.

16.6.19 Request for issue of CRZ Clearance to Chief Officer,

Municipality, Kundapura for construction of OHT (Over Head Tank) at Sy.

No. 294/3P2 of Kasba Village in Kundapura -regarding (FEE 250 CRZ 2016).

1. Name of the Project Construction of OHT (Over Head Tank)

2. Name of the Applicant Chief Officer, Municipality

3. Location of the Project Village/Town, Taluk, Dt.

Kasba Village in Kundapura and Udupi District

4. R.S. No.s Sy. No. 294/3P2

5. Extent of land 0.1.00 Acre.

6. CRZ Classification Project site falls in CRZ-II and at a distance of 25 mts from sea (as per CZMP approved 1996).

7. Project Cost Rs.1.45 Crores.

8. Activities proposed Construction of OHT to provide water supply facility.

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes.

As per under para 8 (II) CRZ-II (i) of CRZ

Notification, 2011, buildings shall be

permitted only on the landward side of the

existing road, or on the landward side of

existing authorized structures. Hence it is a

permissible activity.

Page 29: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 29 of 61

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The subject was placed before the DCZMC, Udupi on 01.07.2016 and the DCZMA has recommended the project.

11. Any other details There is a fisheries road. Project site falls landward side of the existing road.

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA. As per under para 8 (II) CRZ-II (i) of CRZ Notification 2011, the above activity is permissible.

The Authority after discussion and deliberations decided to issue CRZ clearance with

standard condition for construction of OHT by the Chief Officer, Municipality,

Kundapura as per the recommendation of the DCZMC, under para 8 (II) CRZ-II (i) of

CRZ Notification 2011.

16.6.20 Request for issue of CRZ Clearance to Project Director, Project

Management Unit Department of Ports & Inland Water Transport,

Mangalore for “Community Coastal Protection Pilot Study Project” in

Kirimanjeshwara Village-regarding (FEE 251 CRZ 2016)

1. Name of the Project Community Coastal Protection Pilot Study Project.

2. Name of the Applicant Project Director, Project Management Unit Department of Ports & Inland Water Transport, Mangalore.

3. Location of the Project Village/Town, Taluk, Dt.

Kirimanjeshwara beach site of Kundapura

Taluk, Udupi District.

4. R.S. No.s -

5. Extent of land Approximately 1.0 KM of coastal length.

6. CRZ Classification CRZ-I

7. Project Cost Rs. 40.00 Lakh

8. Activities proposed • This is a shore line management program to demonstrate soft coastal protection measure.

• Construction & maintenance of a dune project with a minimum dune height of 4.35 m.

• The sand volume required for the designed dune is 12,000-15,000 cubic meters.

• Sand from the nearby sandbars is proposed to be used for the dune construction.

Page 30: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 30 of 61

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes.

As per the provisions under para 4(i) (f) of

CRZ Notification, 2011, erosion control

measures is a permissible activity since this

study project is connected to erosion control

measures it may have to be considered under

the same provision.

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The subject was placed before the DCZMC, Udupi on 01.07.2016 and the DCZMA has recommended the project.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA. As per under para 4(i) (f) of CRZ Notification 2011, the above activity is permissible.

The Authority after discussion and deliberations opined that this activity is

connected to take up the suitable erosion control measures and decided to issue CRZ

clearance for Community Coastal Protection Pilot Study Project to Project Director,

Project Management Unit, Department of Ports & Inland Water Transport, Mangalore,

as per the recommendation of the DCZMC, under para 4(i) (f) of CRZ Notification 2011,

with the following conditions:-

1. Should not disturb mud flats /breeding areas, Mangroves etc.,

2. The results of the project should be shared with KSCZMA.

16.6.21 Request for issue of NOC from the Commissioner, City council, Udupi

for Construction of sewage treatment plant at sy. No. 262/1C1A1 of

Kodavoor Village, Udupi Taluk (FEE 278 CRZ 2016)

1. Name of the Project Construction of sewage treatment plant

2. Name of the Applicant Commissioner, City council, Udupi

3. Location of the Project Village/Town, Taluk, Dt.

Kodavoor Village, Udupi Taluk

4. R.S. No.s 262/1C1A1

5. Extent of land 1.5 Acre

6. CRZ Classification CRZ-III.

7. Project Cost 17.00 Crores.

8. Activities proposed To provide sewerage system for Malpe area by constructing of 2.80 MLD STP.

Page 31: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 31 of 61

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes.

As per under para 3 (v) (c) of CRZ Notification,

2011., facilities required for treatment of waste

and effluents arising from hotels, beach resorts

and human settlements located in CRZ areas

other than CRZ-I and disposal of treated

wastes and effluents; is permitted.

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The subject was placed before the DCZMC, Udupi on 16.09.2016 and the DCZMA has recommended the project.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA. As per para 3 (v) (c) of CRZ Notification 2011, the above activity is permissible.

The Authority after discussion and deliberations decided to issue CRZ clearance for

Construction of sewage treatment plant by the Commissioner, City council, Udupi as per

the recommendation of the DCZMC, under para 3 (v) (c) of CRZ Notification 2011, with

the following conditions;

1. To adopt Latest Technology and the treated water should conform to the

latest standards issued by CPCB.

2. Treated Water should be reused and sludge should be managed

scientifically as per the CPCB guidelines.

3. EC should be obtained from the SEIAA as per EIA Notification 2006.

4. To install online monitoring system as per CPCB guideline.

16.6.22 Request for issue of NOC from the Commissioner, City council, Udupi

for Construction of raw water treatment plant at sy. No. 325/1 of Shivalli

Village, Udupi Taluk (FEE 279 CRZ 2016)

1. Name of the Project Construction of Raw water treatment plant

2. Name of the Applicant Commissioner, City council, Udupi

3. Location of the Project Village/Town, Taluk, Dt.

Shivalli Village, Udupi Taluk

4. R.S. No.s Sy. No. 325/1

5. Extent of land 0.65 acre

6. CRZ Classification NDZ of CRZ-III.

7. Project Cost Rs. 3.5 Crores.

8. Activities proposed To provide 24X7 Water supply system

Page 32: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 32 of 61

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes.

As per under para 8 (III) CRZ III A (iii) (j) of

CRZ Notification, 2011, construction of

dispensaries, schools, public rain shelter,

community toilets, bridges, roads, provision

of facilities for water supply, drainage,

sewerage, crematoria, cemeteries and electric

sub-station which are required for the local

inhabitants permitted activities.

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The subject was placed before the DCZMC, Udupi on 16.09.2016 and the DCZMA has recommended the project.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA. As per para 8 (III) CRZ III A (iii) (j) of CRZ Notification 2011, the above activity is permissible.

The Authority after discussion and deliberations opined that, this activity is related

to water supply work and decided to issue CRZ clearance with standard condition for

construction of raw water treatment plant by the Commissioner, City council, Udupi as

per the recommendation of DCZMC, under para 8 (III) CRZ III A (iii) (j) of CRZ

Notification, 2011.

16.6.23 Request for issue of NOC from the Commissioner, City council, Udupi

for construction of Sewage water storage plant at sy. No. 124/5BP1 of Puttur

Village, Udupi Taluk (FEE 280 CRZ 2016).

1. Name of the Project Construction of Sewage water storage plant.

2. Name of the Applicant Commissioner, City council, Udupi.

3. Location of the Project Village/Town, Taluk, Dt.

Puttur Village, Udupi Taluk.

4. R.S. No.s Sy. No. 124/5BP1.

5. Extent of land Area of 0.10 acre.

6. CRZ Classification NDZ of CRZ-III.

7. Project Cost Rs. 17.00 Crores.

8. Activities proposed To provide sewage system for udupi city.

Page 33: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 33 of 61

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes.

As per the provisions under para 8 (III)

CRZ III A (iii) (j) of CRZ Notification,

2011. construction of dispensaries,

schools, public rain shelter, community

toilets, bridges, roads, provision of

facilities for water supply, drainage,

sewerage, crematoria, cemeteries and

electric sub-station which are required

for the local inhabitants are permitted

activities.

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The subject was placed before the DCZMC, Udupi on 16.09.2016 and the DCZMA has recommended the project.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA. As per para 8 (III) CRZ III A (iii) (j) of CRZ Notification 2011, the above activity is permissible.

The Authority after discussion and deliberations decided to issue CRZ clearance for

construction of Sewage water storage plant by the Commissioner, City council, Udupi as

per the recommendation of the DCZMC, under para 8 (III) CRZ III A (iii) (j) of CRZ

Notification 2011, with the following conditions;

1. To adopt latest Technology and the treated water should conform to the

latest standards issued by CPCB.

2. Treated Water should be reused and sludge should be managed

scientifically as per the CPCB guidelines.

3. EC should be obtained from the SEIAA as per EIA Notification 2006.

4. To install online monitoring system as per CPCB guideline.

[

16.6.24 Request for issue of CRZ Clearance from Commanding Officer, Indian

Coast Guard Station, Neval Base, Post office arga, for establishment of

Radar Station at sy. No. 193 of Belekeri Village, Ankola Taluk. [FEE 319

CRZ 2016]

1. Name of the Project Establishment of Radar Station

2. Name of the Applicant Commanding Officer, Indian Coast Guard Station, Neval Base, Post office arga

Page 34: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 34 of 61

3. Location of the Project Village/Town, Taluk, Dt.

Belekeri Village, Ankola Taluk

4. R.S. No.s Sy. No. 193

5. Extent of land Area of 20 Guntas

6. CRZ Classification NDZ of CRZ-III. (as per the CZMP approved 1996)

7. Project Cost Rs. 2.00 Crore

8. Activities proposed The proposal is for establishing radar station for coastal security network project at Belekeri port. Radar lattice tower with allied structures and offices.

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes, it is a permitted activity,

As per the provisions under para 8 III CRZ III

(iii) (i) of CRZ Notification 2011, weather

radars is a permitted activity.

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The subject was placed before the DCZMC, Karwar on 16.09.2016 and the DCZMA has recommended the project

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of National Coastal Zone Management Authority. As per under para 8 III CRZ III (iii) (i) of CRZ Notification 2011, the above activity requires clearance from the Ministry of Environment and Forests, Government of India, with the recommendation of SCZMA.

The Authority after discussion and deliberations decided to recommend the

proposal to MoEF, New Delhi with standard conditions as per para 8 III CRZ III (iii)

(i) of CRZ Notification 2011.

16.6.25 Request for issue of CRZ Clearance from Project Director, Project

Management Unit Department of Ports & Inland Water Transport,

Mangalore for community coastal protection pilot projects at sy. No.

1483/A3 of Majali Village, Karwar Taluk (FEE 322 CRZ 2016)

1. Name of the Project Community Coastal Protection Pilot projects in Majili.

Page 35: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 35 of 61

2. Name of the Applicant Project Director, Project Management Unit Department of Ports & Inland Water Transport, Mangalore.

3. Location of the Project Village/Town, Taluk, Dt.

Majili beach site of Kundapura Taluk, Udupi

District.

4. R.S. No.s -

5. Extent of land Approximately 1.0 KM of coastal length

6. CRZ Classification CRZ-I

7. Project Cost Rs. 60.00 Lakh

8. Activities proposed • These community coastal protection are study projects for demonstration of climate change in to costal protection and management.

• It is recommended to construct a dune with a minimum dune height of 4.5 m. The sand volume required for the designed dune is 15,000-18,000 cubic meters.

• Sand from the nearby sandbar at Kali River entrance is proposed to be used for the dune construction as removal of the sand bar will be helpful for safe navigation of fishing boats.

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes.

As per the provisions under para 4(i) (f) of

CRZ Notification, 2011, erosion control

measures is a permissible activity since this

study project is connected to erosion control

measures it may have to be considered under

the same provision.

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The subject was placed before the DCZMC, Karwar on 01.07.2016 and the DCZMA has recommended the project.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA. As per under para 4(i) (f) of CRZ Notification 2011, the above activity is permissible.

Page 36: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 36 of 61

The Authority after discussion and deliberations opined that this activity is

connected to take up suitable erosion control measures and decided to issue CRZ

clearance for Community Coastal Protection Pilot Study Project to Project Director,

Project Management Unit, Department of Ports & Inland Water Transport, Mangalore,

as per the recommendation of the DCZMC, under para 4(i) (f) of CRZ Notification

2011, with the following conditions:-

1. Should not disturb mud flats /breeding areas, Mangroves etc.,

2. The results of the project should be shared with KSCZMA.

16.6.26 Request for issue of CRZ Clearance to M/s. Mysore Mercantile Company Limited for “Storing Cane Molasses” at Sy. No. 1379 of Baada III (Aligadda) Village-regarding (FEE 1 CRZ 2017).

- Name of the Project Storing Cane Molasses

2. Name of the Applicant M/s. Mysore Mercantile Company Limited

3. Location of the Project Village/Town, Taluk, Dt.

Baad-III (Aligadda) Village, Karwar Taluk,

Uttara Kannada District.

4. R.S. No.s Sy. No. 1379

5. Extent of land -

6. CRZ Classification CRZ-III.

7. Project Cost 8.2 Crores

8. Activities proposed Construction of Storage Tank of 5,000 KL capacity for Storing Cane molasses.

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes.

As per provisions of Para 8 III CRZ- III B (iv) of CRZ

notification, 2011,

Storage of non-hazardous cargo such as, edible oil, fertilizers, food grain in notified ports is permitted.

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

-

11. Any other details Earlier CRZ clearance has been issued for

storage of only Edible Oil, Plam Oil, Kerosene,

Aviation Fuel, High Speed Diesel, Lubrication

Oil, Furnace Oil, Low Sulphar Heavy Stock

except Molasses, as per the decision of

Page 37: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 37 of 61

KSCZMA meeting held on 30.01.2016.

Now the project proponent M/s. Mysore

Mercantile Company Ltd., has given

representation requesting to review the decision

taken and to grant approval for storage of

Molasses, as the Molasses is not a hazardous

waste. The project proponent has also stated

that, there are three tank Terminals presently

operating at Karwar for export of Molasses with

CRZ clearance obtained from MoEF & CC, New

Delhi. As per Hazardous waste (Management

Handling) Rules, 2016, Molasses is not found in

the list of hazardous materials in the schedule.

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA. As per para 8 III CRZ- III B (iv) of CRZ notification

2011, the above activity is permissible.

The Authority after discussion and deliberations decided to issue CRZ clearance

with standard conditions to M/s. Mysore Mercantile Company Ltd., for construction of

5,000 KL capacity storage tank to store molasses since it is not a hazardous material.

16.6.27 Request for issue of NOC from Sri. Dileep Devadiga for reconstruction

of residential house at Sy. No. 96/6B2 of Bada Village, Udupi Taluk-

regarding (FEE 24 CRZ 2017)

1. Name of the Project Reconstruction of residential house.

2. Name of the Applicant Sri. Dileep Devadiga.

3. Location of the Project Village/Town, Taluk, Dt.

Bada Village, Udupi Taluk.

4. R.S. No.s 96/6B2.

5. Extent of land 0.25 acre.

6. CRZ Classification NDZ of CRZ III.

7. Project Cost -

8. Activities proposed • Proposal for reconstruction of residential house.

• The plinth area of existing building is 56.88 Sqm.

Page 38: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 38 of 61

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

As per the provisions under para 8(i) III CRZ III A (ii) of CRZ Notification 2011, repairs or reconstruction of existing authorized structure not exceeding existing FSI, existing, plinth area and existing density and for permissible activities under the notification including facilities essential for the said activities are permissible.

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The subject was placed before the DCZMC, Udupi on 21.12.2016 and the DCZMA has recommended the project.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA. As per the provisions under para 8(i) III CRZ III A (ii) of CRZ Notification 2011, the above activity is permissible.

The Authority after discussion and deliberations decided to issue CRZ clearance for

reconstruction of residential house by Sri. Dileep Devadiga, as per the recommendation of

the DCZMC, under para 8(i) III CRZ III A (ii) and Para 6 (d) i & ii of CRZ

Notification, 2011, with the following conditions:-

1. The proposed building should not exceed existing FSI, existing, plinth area and

existing density.

2. This building should not be used for any commercial activity.

3. This building should not be sold or transferred to non traditional coastal

community.

16.6.28 Request for issue of CRZ Clearance for M/s. Mangalore Refinery and

Petrochemicals Ltd., for laying pipeline to BS-VI Auto Fuel Quality &

Associated Projects Facilities at MRPL (FEE 323 CRZ 2016)

1. Name of the Project Laying pipeline to BS-VI Auto Fuel Quality & Associated Projects Facilities.

2. Name of the Applicant M/s. Mangalore Refinery and Petrochemicals Ltd.

3. Location of the Project Village/Town, Taluk, Dt.

-

4. R.S. No.s -

5. Extent of land -

6. CRZ Classification CRZ-I & CRZ-II.

7. Project Cost -

Page 39: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 39 of 61

8. Activities proposed Laying of pipeline from MRPL unit to New Mangalore Port by MRPL in the existing Road cum Pipeline Corridor of MSEZ. Width of the Pipeline is 3.60 m.

9. Whether permitted activity as per CRZ Notification? If yes, specify the relevant rules

Yes, it is a permitted activity,

As per the provisions under para 4(ii) (d) of CRZ Notification, 2011, laying of pipelines, conveying systems, transmission line.

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

-

11. Any other details • Environment clearance for construction of dedicated 70/100 m wide road cum pipe line corridor for movement of Corgo Crude and products between NMPT and MSEZ, has already been issued vide letter no: 21-383/2007-IA-III dated 03-04-2008, subsequent amendments dated: 13-07-2012, 27-08-2014 and 18-06-2015.

• MRPL has entered into an agreement with MSEZL for utilizing 10% of the MSEZL existing pipeline corridor which has already got the required Environment Clearance.

• MRPL has submitted the proposal for establish BS VI Auto fuel Quality Compliance & Associated projects, along with project document including Form-1, PFR and draft ToR, as per the EIA Notification,2006 and MoEF has issued ToR for proposed project.

• Further, MRPL has requested amendments in existing ToR due to additional tankage, Pipeline and others features, Appraisal Committee noted that, due to laying Pipeline to New Mangalore Port, the CRZ clearance to be obtained as applicable and prior SCZMA recommendation.

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

National Coastal Zone Management Authority. As per para (4) (ii) (d) of the CRZ notification 2011, the above activity requires clearance from the Ministry of Environment and Forests, Government of India.

Page 40: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 40 of 61

The Authority after discussion and deliberations, the Authority noted that MRPL

has entered into an agreement with MSEZL for utilizing 10% of the MSEZL existing

pipeline corridor which has already got the required Environment Clearance vide MoEF

letter dated 13.04.2008. Hence, it was opined that separate CRZ clearance is not required

since MRPL is laying pipeline in the existing MSEZL pipeline corridor. It was decided to

communicate the same to the MoEF & CC GoI, New Delhi.

16.6.29 Proposal of removal of Sand from Sand Bar of Kali River ( SB-KL-1) in

Karwar Taluk of Uttara Kannada District for issue of CRZ Clearance [File

No. FEE 84 CRZ 2017)

1. Name of the Project Removal of Sand from Sand Bar ( SB-KL-1)

2. Name of the Applicant District Sand Monitoring Committee (CRZ), Uttara Kannada district.

3. Location of the Project Village/Town, Taluk, Dt.

Kali River in Karwar Taluk

4. R.S. No.s -

5. Extent of land

Length Width Area Acre/Ha.

600m 150m 22.23 A/9.00 Ha.

6. CRZ Classification CRZ area

7. Project Cost -

8. Activities proposed Estimated Quantity of Removable Sand from Sand Bar Area Depth Quantity

22.23 Acre 0.60m 92,340m3

9. Whether permitted activity

as per CRZ Notification? If

yes, specify the relevant

rules

Yes

Sand bars which obstruct the movement of

fishing vessels may be removed.

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The proposals were cleared in District Sand Monitoring Committee meeting held on 07.01.2017 & DCZMC meeting held on 28.01.2017.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA.

Page 41: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 41 of 61

16.6.30 Proposal of removal of Sand from Sand Bar of Kali River ( SB-KL-2)in

Karwar Taluk of Uttara Kannada District for issue of CRZ Clearance [File

No. FEE 85 CRZ 2017)

1. Name of the Project Removal of Sand from Sand Bar ( SB-KL-2)

2. Name of the Applicant District Sand Monitoring Committee (CRZ), Uttara Kannada district.

3. Location of the Project Village/Town, Taluk, Dt.

( SB-KL-2)

4. R.S. No.s -

5. Extent of land

Length Width Area Acre/Ha.

800m 200m 39.53 A/16.00 Ha.

6. CRZ Classification CRZ area

7. Project Cost -

8. Activities proposed Estimated Quantity of Removable Sand from Sand Bar

Area Depth Quantity

39.53 A 0.60 m 1.64.160m3

9. Whether permitted activity

as per CRZ Notification? If

yes, specify the relevant

rules

Yes

Sand bars which obstructing the movement of

fishing vessels may be removed

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The proposals were cleared in District Sand Monitoring Committee meeting held on 07.01.2017 & DCZMC meeting held on 28.01.2017.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA.

Page 42: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 42 of 61

16.6.31 Proposal of removal of Sand from Sand Bar of Kali River ( SB-KL-3) in

Karwar Taluk of Uttara Kannada District for issue of CRZ Clearance [File

No. FEE 86 CRZ 2017)

1. Name of the Project Removal of Sand from Sand Bar ( SB-KL-3)

2. Name of the Applicant District Sand Monitoring Committee (CRZ), Uttara Kannada district.

3. Location of the Project Village/Town, Taluk, Dt.

SB-KL-3

4. R.S. No.s -

5. Extent of land

Length Width Area Acre/Ha.

1100m 200m 54.36 A/22.00 Ha.

6. CRZ Classification CRZ area

7. Project Cost -

8. Activities proposed Estimated Quantity of Removable Sand from Sand Bar

Area Depth Quantity

54.36 A 0.60 m 2,25,720m3

9. Whether permitted activity

as per CRZ Notification? If

yes, specify the relevant

rules

Yes

Sand bars which obstructing the movement of

fishing vessels may be removed

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The proposals were cleared in District Sand Monitoring Committee meeting held on 07.01.2017 & DCZMC meeting held on 28.01.2017.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA.

Page 43: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 43 of 61

16.6.32 Proposal of removal of Sand from Sand Bar of Kali River ( SB-KL-4) in

Karwar Taluk of Uttara Kannada District for issue of CRZ Clearance [File

No. FEE 87 CRZ 2017)

1. Name of the Project Removal of Sand from Sand Bar ( SB-KL-4)

2. Name of the Applicant District Sand Monitoring Committee (CRZ), Uttara Kannada district.

3. Location of the Project Village/Town, Taluk, Dt.

SB-KL-4

4. R.S. No.s -

5. Extent of land

Length Width Area Acre/Ha.

1000m 180m 44.47 A/18.00 Ha.

6. CRZ Classification CRZ area

7. Project Cost -

8. Activities proposed Estimated Quantity of Removable Sand from Sand Bar

Area Depth Quantity

44.47A 0.60 m 1,84,680m3

9. Whether permitted activity

as per CRZ Notification? If

yes, specify the relevant

rules

Yes

Sand bars which obstructing the movement of

fishing vessels may be removed

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The proposals were cleared in District Sand Monitoring Committee meeting held on 07.01.2017 & DCZMC meeting held on 28.01.2017.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA.

Page 44: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 44 of 61

16.6.33 Proposal of removal of Sand from Sand Bar of Kali River ( SB-KL-5) in

Karwar Taluk of Uttara Kannada District for issue of CRZ Clearance [File

No. FEE 88 CRZ 2017)

1. Name of the Project Removal of Sand from Sand Bar ( SB-KL-5)

2. Name of the Applicant District Sand Monitoring Committee (CRZ), Uttara Kannada district.

3. Location of the Project Village/Town, Taluk, Dt.

SB-KL-5

4. R.S. No.s -

5. Extent of land

Length Width Area Acre/Ha.

1000m 133m 32.93 A/13.33 Ha.

6. CRZ Classification CRZ area

7. Project Cost -

8. Activities proposed Estimated Quantity of Removable Sand from Sand Bar

Area Depth Quantity

32.93A 0.60 m 1,36,458m3

9. Whether permitted activity

as per CRZ Notification? If

yes, specify the relevant

rules

Yes

Sand bars which obstructing the movement of

fishing vessels may be removed

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The proposals were cleared in District Sand Monitoring Committee meeting held on 07.01.2017 & DCZMC meeting held on 28.01.2017.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA.

Page 45: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 45 of 61

16.6.34 Proposal of removal of Sand from Sand Bar of Gangavalli river (SB-

GA-1)in Ankola Taluk of Uttara Kannada District for issue of CRZ

Clearance [File No. FEE 89 CRZ 2017)

1. Name of the Project Removal of Sand from Sand Bar (SB-GA-1)

2. Name of the Applicant District Sand Monitoring Committee (CRZ), Uttara Kannada district.

3. Location of the Project Village/Town, Taluk, Dt.

SB-GA-1

4. R.S. No.s -

5. Extent of land

Length Width Area Acre/Ha.

275m 138m 9.39 A/3.8 Ha.

6. CRZ Classification CRZ area

7. Project Cost -

8. Activities proposed Estimated Quantity of Removable Sand from Sand Bar

Area Depth Quantity

9.39 A 0.60 m 38,988m3

9. Whether permitted activity

as per CRZ Notification? If

yes, specify the relevant

rules

Yes

Sand bars which obstructing the movement of

fishing vessels may be removed

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The proposals were cleared in District Sand Monitoring Committee meeting held on 07.01.2017 & DCZMC meeting held on 28.01.2017.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA.

Page 46: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 46 of 61

16.6.35 Proposal of removal of Sand from Sand Bar of Gangavalli river (SB-

GA-2) in Ankola Taluk of Uttara Kannada District for issue of CRZ

Clearance [File No. FEE 90 CRZ 2017)

1. Name of the Project Removal of Sand from Sand Bar (SB-GA-2)

2. Name of the Applicant District Sand Monitoring Committee (CRZ), Uttara Kannada district.

3. Location of the Project Village/Town, Taluk, Dt.

SB-GA-2

4. R.S. No.s -

5. Extent of land

Length Width Area Acre/Ha.

755m 100m 18.65 A/7.55 Ha.

6. CRZ Classification CRZ area

7. Project Cost -

8. Activities proposed Estimated Quantity of Removable Sand from Sand Bar

Area Depth Quantity

18.65 A 0.60 m 77,463m3

9. Whether permitted activity as

per CRZ Notification? If yes,

specify the relevant rules

Yes

Sand bars which obstructing the movement of

fishing vessels may be removed

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The proposals were cleared in District Sand Monitoring Committee meeting held on 07.01.2017 & DCZMC meeting held on 28.01.2017.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA.

Page 47: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 47 of 61

16.6.36 Proposal of removal of Sand from Sand Bar of Aghanashini river (SB-

AG-1) in Kumta Taluk of Uttara Kannada District for issue of CRZ

Clearance [File No. FEE 91 CRZ 2017)

1. Name of the Project Removal of Sand from Sand Bar (SB-AG-1)

2. Name of the Applicant District Sand Monitoring Committee (CRZ), Uttara Kannada district.

3. Location of the Project Village/Town, Taluk, Dt.

(SB-AG-1)

4. R.S. No.s -

5. Extent of land

Length Width Area Acre/Ha.

610m 165m 24.85 A/10.06 Ha.

6. CRZ Classification CRZ area

7. Project Cost -

8. Activities proposed Estimated Quantity of Removable Sand from Sand Bar

Area Depth Quantity

24.85 A 0.60 m 1,03,216m3

9. Whether permitted activity

as per CRZ Notification? If

yes, specify the relevant

rules

Yes

Sand bars which obstructing the movement of

fishing vessels may be removed

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The proposals were cleared in District Sand Monitoring Committee meeting held on 07.01.2017 & DCZMC meeting held on 28.01.2017.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA.

Page 48: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 48 of 61

16.6.37 Proposal of removal of Sand from Sand Bar of Aghanashini river (SB-

AG-2) in Kumta Taluk of Uttara Kannada District for issue of CRZ

Clearance [File No. FEE 92 CRZ 2017)

1. Name of the Project Removal of Sand from Sand Bar (SB-AG-2)

2. Name of the Applicant District Sand Monitoring Committee (CRZ), Uttara Kannada district.

3. Location of the Project Village/Town, Taluk, Dt.

(SB-AG-2)

4. R.S. No.s -

5. Extent of land

Length Width Area Acre/Ha.

950m 120m 28.17 A/11.4 Ha.

6. CRZ Classification CRZ area

7. Project Cost -

8. Activities proposed Estimated Quantity of Removable Sand from Sand Bar

Area Depth Quantity

28.17 A 0.60 m 1,16,946m3

9. Whether permitted activity

as per CRZ Notification? If

yes, specify the relevant

rules

Yes

Sand bars which obstructing the movement of

fishing vessels may be removed

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The proposals were cleared in District Sand Monitoring Committee meeting held on 07.01.2017 & DCZMC meeting held on 28.01.2017.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA.

Page 49: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 49 of 61

16.6.38 Proposal of removal of Sand from Sand Bar of Aghanashini river (SB-

AG-3)in Kumta Taluk, Uttara Kannada District for issue of CRZ Clearance

[File No. FEE 93 CRZ 2017)

1. Name of the Project Removal of Sand from Sand Bar of Aghanashini river in Kumta Taluk,

2. Name of the Applicant District Sand Monitoring Committee (CRZ), Uttara Kannada district.

3. Location of the Project Village/Town, Taluk, Dt.

SB-AG-3

4. R.S. No.s -

5. Extent of land

Length Width Area Acre/Ha.

850m 85m 17.84 A/7.22 Ha.

6. CRZ Classification CRZ area

7. Project Cost -

8. Activities proposed Estimated Quantity of Removable Sand from Sand Bar

Area Depth Quantity

17.84 A 0.60 m 74,128m3

9. Whether permitted activity

as per CRZ Notification? If

yes, specify the relevant

rules

Yes

Sand bars which obstructing the movement of

fishing vessels may be removed

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The proposals were cleared in District Sand Monitoring Committee meeting held on 07.01.2017 & DCZMC meeting held on 28.01.2017.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA.

Page 50: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 50 of 61

16.6.39 Proposal of removal of Sand from Sand Bar of Aghanashini river (SB-

AG-4)in Kumta Taluk, Uttara Kannada District for issue of CRZ Clearance

[File No. FEE 94 CRZ 2017)

1. Name of the Project Removal of Sand from Sand Bar of Aghanashini river in Kumta Taluk,

2. Name of the Applicant District Sand Monitoring Committee (CRZ), Uttara Kannada district.

3. Location of the Project Village/Town, Taluk, Dt.

SB-AG-4

4. R.S. No.s -

5. Extent of land

Length Width Area Acre/Ha.

770m 106.9m 20.33 A/8.23 Ha.

6. CRZ Classification CRZ area

7. Project Cost -

8. Activities proposed Estimated Quantity of Removable Sand from Sand Bar

Area Depth Quantity

20.33 A 0.60 m 84,440m3

9. Whether permitted activity

as per CRZ Notification? If

yes, specify the relevant

rules

Yes

Sand bars which obstructing the movement of

fishing vessels may be removed

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The proposals were cleared in District Sand Monitoring Committee meeting held on 07.01.2017 & DCZMC meeting held on 28.01.2017.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA.

Page 51: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 51 of 61

16.6.40 Proposal of removal of Sand from Sand Bar of Aghanashini river (SB-

AG-5)in Kumta Taluk, Uttara Kannada District for issue of CRZ Clearance

[File No. FEE 95 CRZ 2017)

1. Name of the Project Removal of Sand from Sand Bar of Aghanashini river in Kumta Taluk,

2. Name of the Applicant District Sand Monitoring Committee (CRZ), Uttara Kannada district.

3. Location of the Project Village/Town, Taluk, Dt.

SB-AG-5

4. R.S. No.s -

5. Extent of land

Length Width Area Acre/Ha.

660m 40m 6.42 A/2.6 Ha.

6. CRZ Classification CRZ area

7. Project Cost -

8. Activities proposed Estimated Quantity of Removable Sand from Sand Bar

Area Depth Quantity

6.42 A 0.60 m 25,086m3

9. Whether permitted activity

as per CRZ Notification? If

yes, specify the relevant

rules

Yes

Sand bars which obstructing the movement of

fishing vessels may be removed

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The proposals were cleared in District Sand Monitoring Committee meeting held on 07.01.2017 & DCZMC meeting held on 28.01.2017.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA.

Page 52: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 52 of 61

16.6.41 Proposal of removal of Sand from Sand Bar of Sharavathi river (SB- SH-

15)in Honnavar Taluk, Uttara Kannada District for issue of CRZ Clearance

[File No. FEE 96 CRZ 2017)

1. Name of the Project Removal of Sand from Sand Bar of Shravathi river in Honnavar Taluk,

2. Name of the Applicant District Sand Monitoring Committee (CRZ), Uttara Kannada district.

3. Location of the Project Village/Town, Taluk, Dt.

SB- SH-15

4. R.S. No.s -

5. Extent of land

Length Width Area Acre/Ha.

500m 300m 37.06 A/15 Ha.

6. CRZ Classification CRZ area

7. Project Cost -

8. Activities proposed Estimated Quantity of Removable Sand from Sand Bar

Area Depth Quantity

37.06 A 0.9 m 2,02,500m3

9. Whether permitted activity

as per CRZ Notification? If

yes, specify the relevant

rules

Yes

Sand bars which obstructing the movement of

fishing vessels may be removed

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The proposals were cleared in District Sand Monitoring Committee meeting held on 07.01.2017 & DCZMC meeting held on 28.01.2017.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA.

Page 53: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 53 of 61

16.6.42 Proposal of removal of Sand from Sand Bar of Sharavathi river (SB- SH-

16)in Honnavar Taluk, Uttara Kannada District for issue of CRZ Clearance

[File No. FEE 97 CRZ 2017)

1. Name of the Project Removal of Sand from Sand Bar of Shravathi river in Honnavar Taluk,

2. Name of the Applicant District Sand Monitoring Committee (CRZ), Uttara Kannada district.

3. Location of the Project Village/Town, Taluk, Dt.

SB- SH-16

4. R.S. No.s -

5. Extent of land

Length Width Area Acre/Ha.

1000m 100m 24.71 A/10.00 Ha.

6. CRZ Classification CRZ area

7. Project Cost -

8. Activities proposed Estimated Quantity of Removable Sand from Sand Bar

Area Depth Quantity

24.71 A 0.8 m 1,20,000m3

9. Whether permitted activity

as per CRZ Notification? If

yes, specify the relevant

rules

Yes

Sand bars which obstructing the movement of

fishing vessels may be removed

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The proposals were cleared in District Sand Monitoring Committee meeting held on 07.01.2017 & DCZMC meeting held on 28.01.2017.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA.

Page 54: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 54 of 61

16.6.43 Proposal of removal of Sand from Sand Bar of Sharavathi river (SB- SH-

18)in Honnavar Taluk, Uttara Kannada District for issue of CRZ Clearance

[File No. FEE 98 CRZ 2017)

1. Name of the Project Removal of Sand from Sand Bar of Shravathi river in Honnavar Taluk,

2. Name of the Applicant District Sand Monitoring Committee (CRZ), Uttara Kannada district.

3. Location of the Project Village/Town, Taluk, Dt.

SB- SH-18

4. R.S. No.s -

5. Extent of land

Length Width Area Acre/Ha.

550m 150m 20.4 A/8.3 Ha.

6. CRZ Classification CRZ area

7. Project Cost -

8. Activities proposed Estimated Quantity of Removable Sand from Sand Bar

Area Depth Quantity

20.4 A 0.8 m 99,600m3

9. Whether permitted

activity as per CRZ

Notification? If yes,

specify the relevant rules

Yes

Sand bars which obstructing the movement of

fishing vessels may be removed

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The proposals were cleared in District Sand Monitoring Committee meeting held on 07.01.2017 & DCZMC meeting held on 28.01.2017.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA.

Page 55: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 55 of 61

16.6.44 Proposal of removal of Sand from Sand Bar of Sharavathi river (SB- SH-

19)in Honnavar Taluk, Uttara Kannada District for issue of CRZ Clearance

[File No. FEE 99 CRZ 2017)

1. Name of the Project Removal of Sand from Sand Bar of Shravathi river in Honnavar Taluk,

2. Name of the Applicant District Sand Monitoring Committee (CRZ), Uttara Kannada district.

3. Location of the Project Village/Town, Taluk, Dt.

SB- SH-19

4. R.S. No.s -

5. Extent of land

Length Width Area Acre/Ha.

650m 150m 24.08 A/9.75 Ha.

6. CRZ Classification CRZ area

7. Project Cost -

8. Activities proposed Estimated Quantity of Removable Sand from Sand Bar

Area Depth Quantity

24.08 A 0.8 m 1,17,000m3

9. Whether permitted

activity as per CRZ

Notification? If yes,

specify the relevant rules

Yes

Sand bars which obstructing the movement of

fishing vessels may be removed

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The proposals were cleared in District Sand Monitoring Committee meeting held on 07.01.2017 & DCZMC meeting held on 28.01.2017.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA.

Page 56: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 56 of 61

16.6.45 Proposal of removal of Sand from Sand Bar of Sharavathi river (SB- SH-

20) in Honnavar Taluk, Uttara Kannada District for issue of CRZ Clearance

[File No. FEE 100 CRZ 2017)

1. Name of the Project Removal of Sand from Sand Bar of Shravathi river in Honnavar Taluk,

2. Name of the Applicant District Sand Monitoring Committee (CRZ), Uttara Kannada district.

3. Location of the Project Village/Town, Taluk, Dt.

SB- SH-20

4. R.S. No.s -

5. Extent of land

Length Width Area Acre/Ha.

900m 120m 26.67 A/10.8 Ha.

6. CRZ Classification CRZ area

7. Project Cost -

8. Activities proposed Estimated Quantity of Removable Sand from Sand Bar

Area Depth Quantity

26.67 A 0.8 m 1,29,600m3

9. Whether permitted

activity as per CRZ

Notification? If yes,

specify the relevant rules

Yes

Sand bars which obstructing the movement of

fishing vessels may be removed

10. The details of recommendations of the District Coastal Zone Management Authority (DCZMA)

The proposals were cleared in District Sand Monitoring Committee meeting held on 07.01.2017 & DCZMC meeting held on 28.01.2017.

11. Any other details -

12. Whether issue of clearance is within the scope of SCZMA or NCZMA? Specify relevant rules.

Issue of clearance is within the scope of SCZMA.

Before appraising the above sand bar removal proposals,the Member Secretary,

brought to the notice of the Authority, Hon’ble NGT judgment in OA No. 111 of 2016

dated 27.02.2017.

Page 57: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 57 of 61

The 17 proposals for removing sand bars submitted by the District Sand Monitoring

Committee has been placed before the Authority and it has been deliberated with respect

to the observations made by the Hon’ble NGT in its order dated 27.02.2017 , and OM’s

of the MoEF & CC dated 24.02.2011, 09.06.2011 and 08.11.2011. After the deliberation

and discussion the Authority observed the following:-

1. Seven Member committee has not been constituted as per OM of MoEF &

CC dated 08.11.2011, as provided in the OM, there should be two

representatives one each from local civil society and local fishing

community.

2. In the technical report submitted by the NITK, Surathkal, there was no

mention about the actual presence of sand bars, depth at which sand bars

are deposited and whether these sand bars are actually obstructing the

fishing vessels or not.

3. In the technical report of NITK, ‘Kudrus’ which are naturally formed

Islands have been proposed to be removed which is not allowed as per CRZ

Notification, 2011.

In view of the above the Authority decided to inform the applicant accordingly and

to get the revised proposals.

16.6.46 Appointment of Government Advocates to represent the State before

various courts at Mangalore, Udupi & Karwar district with respect to

violations cases:

The Members Secretary, brought to the notice of the Authority that number of

violations cases are pending for want of Appointment of Government Advocates to

represent the KSCZMA. Accordingly the opinion was sought form the Law

Department and the Law Department has given opinion high lighting the provisions

of the Karnataka Law Officers (Appointment of Conditions of Service) Rules, 1977,

as follows:-

1. If the case pertaining to encroachment in CRZ area is a civil case, the

administrative department may engage the services of the District

Government Pleader/Addl. D.G.P.s as the case may be

2. If the case is a criminal case, the administrative department will have to

engage the services of the Public Prosecutors and Assistant Public

Prosecutors to represent the State in view of Sec. 24 & 25 of Cr.P.C.

Page 58: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 58 of 61

3. If the administrative department intends to engage the services of a Special

Counsel, the same is governed by Rule 30 of Karnataka Law Officers

(Appointment of Conditions of Service)Rules, 1977.

4. If the administrative department intends to appoint Special Counsel, then

as per Rule 30 (2), the administrative department may consult the Hon’ble

Advocate General if the appointment is in relation to a Civil Case and the

Director of Prosecution if the appointment is in relation to a Criminal Case.

5. The Department can appoint Advocates for the above purpose by way of

empanelment.

The Authority after discussion and deliberations decided to instruct the

concerned Regional Directors Mangalore, Udupi and Karwar to take action to

send the Panel of Advocates for approval of the Panel for appointing the

Advocates by the Authority.

It was also decided that the next meeting will be held on 05.04.2017 at Mangalore.

The meeting concluded with vote of thanks to the Chair.

Sd/- (P. Ravikumar)

Additional Chief Secretary to Government, Forest, Ecology & Environment Department

& Chairman, Karnataka State Coastal Zone Management Authority.

(Vijay Kumar)

Special Director (Technical Cell)

& Member Secretary, KSCZMA

Forest, Ecology and Environment Department.

No. FEE 255 CRZ 2016

Page 59: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 59 of 61

Meeting of the 16th Karnataka State Coastal Zone Management Authority

(KSCZMA) held on 18.03.2017 at 11.00 A.M. at Room No. 252, 2nd Floor, 2nd

Gate, M. S. Building, Bengaluru under the chairmanship of Additional Chief

Secretary to Government, Forest, Ecology & Environment Department.

LIST OF MEMBERS/OFFICERS PRESENT

1. Sri. P. Ravikumar, IAS.,

Chairman, KSCZMA &

Additional Chief Secretary to Government,

Department of Forest, Ecology & Environment,

M S Building, Bangalore – 560 001

Present

2. Principal Secretary to Government,

Tourism Department,

Vikasa Soudha Bangalore.

-

3. Additional Chief Secretary to Government,

Industries and Commerce Department,

Vikasa Soudha, Bangalore

-

4. Sri. Ramachandhra, IFS,

Secretary to Govt. (Ecology & Environment)

Forest, Ecology and Environment Department

Bangalore- 560 001.

Present

5. Sri. S.Shanthappa, IFS.,

Member Secretary,

Karnataka State Pollution Control Board,

No. 49, Parisara Bhavan, Church Street,

Bangalore- 560 001.

Present

6. Sri. Ramesha.C

Project Development Officer,

Environment Management and Policy Research

Institute (EMPRI),

Hasiru Bhavana', Doresanipalya Forest Campus,

Vinayaka Nagara Circle, J. P. Nagar, 5th Phase,

Bangalore-560 076.

Present

7. Principal Secretary to Government,

Animal Husbandry and Fisheries Department.

-

Page 60: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 60 of 61

8. Sri. Ashoka Reddy, Director,

Karnataka State Remote Sensing Application Centre,

KSRSAC, BMTC-Central Office Building TTMC ‘B’

Block, 4th Foor, Shanthinagar, KH Road, Bangalore –

560 027.

Present

9. Dr. K.S. Jayappa, Professor,

Department of Marina Geology, Mangalore

University,

Mangalore-575004.

Present

10. Dr. Dwarakish G.S.,

Professor and Head,

Department of Applied Mechanics and Hydraulics,

National Institute of Technology, Karnataka,

Suratkal, Manalore.

Present

11. Dr. Jagannath L Rothod

Associate Professr,

Department of Studies in Marine Biology, Kodibag,

Karwar.

Present

12. Dr. Lakshmipathi M.T.

Associate Professor ,

Aquatic Environment Management Department,

College of Fisheries, Mangalore.

Present

13. Sri Vijayakumar, IFS.,

Special Director (Technical Cell)

and Secretary,

Karnataka State Coastal Zone Management

Authority,

Forest, Ecology and Environment Department.

Present

14. Director,

Directorate of Municipal Administration,

Bangalore

Representative

15. Shri. M. Dinesh Nayak,

President,

Sasyashyamala Vittal,

Dakshina Kannada District.

Present

Page 61: Proceedings of the 16 th meeting of Karnataka State ...karunadu.karnataka.gov.in/ksczma/english/Documents...Proceedings of the 16 th meeting of Karnataka State Coastal Zone Management

Page 61 of 61

16. Sri. S.J. Chandra Shekar,

Regional Director (Environment),

Forest, Ecology & Environment Department,

1st Floor, C Block, Rajathadri,

District Administrative Centre,

Manipal- 576104, Udupi District.

Present

17. Sri. Prasanna K. Patagar,

Regional Director (Environment),

Forest, Ecology & Environment Department,

Meera Building, I Floor, Kajubagh, Karwar,

Uttara Kannada District.

Present

18. Dr. Dinesh Kumar Y.K.

Regional Director (Environment),

Forest, Ecology & Environment Department,

Corporation Commercial Complex,

I Floor, Lalbagh, Mangalore-575 003.

Present

** *** **