Preservation and capping of a mineshaft under … · Preservation and capping of a mineshaft under...
Transcript of Preservation and capping of a mineshaft under … · Preservation and capping of a mineshaft under...
Hughes, C.G.C, Mokhtari, A. & West, B. (2013)
Preservation and capping of a mineshaft under SH25 in Thames, New Zealand Proc. 19th NZGS Geotechnical Symposium, Ed. CY Chin, Queenstown
Preservation and capping of a mineshaft under SH25 at Thames, New
Zealand
C G C Hughes Opus International Consultants Limited, Hamilton, New Zealand
A Mokhtari Opus International Consultants Limited, Hamilton, New Zealand
B West Opus International Consultants Limited, Paeroa, New Zealand [email protected]
Keywords: Thames Goldmine, Pump Shaft, SH25, bracing of shaft walls, capping.
ABSTRACT
A number of engineering challenges were faced in the design of the shaft wall support and
capping of a mine shaft under State Highway 25 (SH25) at Thames on the North Island in New
Zealand.
A ‘hole in the road’ was reported towards the end of April 2012 and over the next few days an
abandoned mine pump shaft 3m wide by 4m long was carefully exposed by the highway
maintenance contractor. The design of the remedial options and the subsequent construction of
the mine shaft cover and the reinstatement of the highway were carried out by engineers from a
number of disciplines encompassing the highway network maintenance, structural, geotechnical
and archaeological teams.
Conventional treatment of mineshafts is to infill and cap to ground level. However, in
agreement with all parties it was decided to try and preserve this unique bit of New Zealand
heritage by shoring and capping the exposed shaft. The final design comprised a metal plate
held in place by props to brace and support the shaft walls. Precast prestressed reinforced
concrete slabs were then placed on rubber strip bearings to span the shaft before backfilling the
remainder of the excavation and restoring the road pavement.
The construction phase was carried out quickly, safely and with no issues on site. Propping and
capping of this shaft was a unique first in New Zealand and the success of this project came
about from good liaison and understanding between each of our teams.
1 INTRODUCTION
On the 18th April 2012 we were called out to inspect a hole that had appeared in State Highway
25 in Thames, North Island (Figure 1). It became quickly clear that there was a bigger problem
at the site than initially anticipated and further investigation was required to expose the extent
and origin of the hole. New Zealand Transport Agency (NZTA) engaged Opus to carry out the
investigation and to provide detail design drawings for the remediation in order to get the road
open as soon as possible.
The purpose of this paper is to present the investigation findings, the unique design challenges
and to describe the sequence of uncovering of the shaft and the construction process from start
to finish for the remediation works.
Hughes, C.G.C, Mokhtari, A. & West, B. (2013).
Preservation and capping of a mineshaft under SH25 in Thames, New Zealand
Figure 1: Site Location Plan Figure 2: Hole in SH25 at start
of investigation
2 INVESTIGATION OF THE SHAFT
Over the next few days a mine shaft 3m wide by 4m long was carefully exposed (Figure 2 to 4)
by the Contractor (Downer). The shaft was found to be lined by stone blocks with an average
block size 0.5m by 0.5m by 1m. Timber beams spanning between the shaft wall were also
uncovered.
Figure 3: Mine Shaft as uncovered Figure 4: Excavation extended around shaft
The groundwater level in the shaft was 4m below the top of the shaft wall and the apparent void
of the shaft was 13m deep.
We then extended the excavation beyond the shaft sides to uncover the full extent of the stone
block lining at the top and to try and define how thick the walls may be.
Hughes, C.G.C, Mokhtari, A. & West, B. (2013). Preservation and capping of a mineshaft under SH25 in Thames, New Zealand
A survey team was then commissioned to carry out a topographical survey in order to map out
the shaft dimensions and layout, and the extent of the stone blocks.
Mining related fill (brown gravelly sand) was exposed to the side of the stone blocks. Scala
tests were carried out in this fill and proved the material to be loose to medium dense in nature,
becoming dense from approximately 2.2m depth.
3 DISCUSSION ON THE CAUSE
From the initial inspections carried out, we determined that there may have been additional
timber beams spanning the shaft and that these had rotted away over time. In combination with
possible settlement of fill within the shaft, this had allowed a void to form, and the material
spanning the shaft then settled, forming the hole in SH25.
4 RECORDS SEARCH
We reviewed the publically available geological
maps1 for the subject site and identified that the
site was underlain by recent alluvial soils
associated with the Firth of Thames.
Hydrothermally altered andesites are present below
the alluvial soils. The geological map identified
the shaft to be ‘Big Pump’ at the location of the
hole in the road.
The shaft was inspected by archaeologists and by
mine historians of the Thames School of Mines
and their review of records held identified that the
shaft was part of a water pumping system dating
around the late 1800’s which was used to drain the
mines on the Thames goldfield.
The former pump house floor and old machinery
were uncovered by the initial excavations (Figure
5). From review of the records held, the shaft itself
was thought to be close to 200m deep. When it
was decommissioned it may have been filled in.
Figure 5: Old Machinery in Shaft
5 REMEDIATION OF MINE SHAFTS, METHODS GENERALLY ADOPTED
Methods for dealing with unused shafts are varied across the world but normally involve at least
filling the shaft. Historically, the materials used to fill the shaft could be highly variable (refuse,
colliery waste, timbers, granular fill) and would typically be chosen from what was readily
available at that time.
As an example, general protocol for dealing with shallow untreated mine shafts in the UK
include filling the shaft (incorporating a program of drilling and grouting) and placement of a
reinforced concrete cap over the shaft. A detail for mine shaft treatment from the UK is
provided below (Figure 6):
Hughes, C.G.C, Mokhtari, A. & West, B. (2013). Preservation and capping of a mineshaft under SH25 in Thames, New Zealand
Figure 6: General arrangements and recommended design for a capped shaft (Sourced
from CIRIA Special Publication 32, 19842)
6 DESIGN CHALLENGES
The shaft under SH25 presented a number of remedial challenges, both from an archaeological
and an engineering perspective. These challenges were required to be overcome as quickly as
possible as our brief was to re-open SH25 at the earliest opportunity.
The unusual archaeological and historical value of the shaft meant that New Zealand Historic
Places Trust (NZHPT) required we come up with a suitable design that prevented damage to the
structure as much as reasonably practicable. This ruled out the option of simply backfilling the
shaft and placing a concrete cap over it.
Two remedial options were discounted at an early stage:
1) The shaft location is within a built up part of Thames and as such re-routing SH25 to
outside the influence of the shaft was not an option. A temporary diversion had been
put into place whilst SH25 was closed but this started to draw complaints from local
residents and increase the urgency to get SH25 open again.
2) The option of installing piles and then spanning beams to support SH25 was discounted
at an early stage due to time constraints and the high costs of large spans and piling.
Our geotechnical and structural teams came up with a design comprising installing precast
reinforced concrete bridge slabs to span the shaft and fill over the void. One of the benefits of
this option was that existing reinforced concrete bridge slabs were readily available from a
concrete precast supplier and as such this option could be implemented quickly by the lead
contractor.
There remains a minor risk with this option of catastrophic collapse of the shaft below the
propped zone. For this to happen, the fill in the shaft would need to substantially settle or be
Hughes, C.G.C, Mokhtari, A. & West, B. (2013). Preservation and capping of a mineshaft under SH25 in Thames, New Zealand
washed out in order to provide the space and room for the wall blocks at depth to move or
collapse into. In terms of likelihood of this threat, we considered this would be a rare
occurrence (happening less than once per 50 years).
This risk was put to and accepted by the highway authority (NZTA) after due consideration of
the large size and the excellent condition of the shaft wall stone blocks that line the shaft and the
presence of fill in the shaft from below 13m depth.
7 STRUCTURAL CONSIDERATIONS
Five reinforced concrete bridge slabs were available and a structural inspection of these was
carried out on the 10th May 2012. We were advised that the slabs (approximately 2290mm wide
x 5010mm long and 280mm thick) were part of a temporary bridge on a recent subdivision
construction site in Tauranga and were used for around 2 years.
There was some minor damage to the edges of a number of the slabs (Figure 7).
The most significant area of damage was to the corner of one of the units where the end of a
prestressing strand and a stirrup had been exposed. The exposed strand end and the exposed
stirrup were cleaned and coated with
two coats of bitumen.
Units with hairline crack and exposed
stirrup were used as bearing pads. The
remaining units with only minor
defects were used to span the shaft.
Figure 7: Bridge slab units at
contractor’s yard
Structural engineers assessed the slab
units to confirm that they are capable
of carrying HN-HO-72 loading as required by the NZTA Bridge Manual3.
8 GEOTECHNICAL CONSIDERATIONS
Two of the key geotechnical design considerations were for bearing capacity of the ‘abutments’
and the likely lateral loads that may be applied to the shaft wall.
We decided to utilise all of the bridge slabs and designed an arrangement to spread the applied
loads over as wide an area possible. Structural calculations were carried out to determine the
loads (factored and unfactored) applied to the stone blocks at the top of the shaft. We then
checked the bearing capacity (following Verification Method, B1/VM44) assuming the fill
properties estimated from the Scala test results.
We calculated the horizontal load acting on the mine shaft wall at each end of the contact area
and designed metal plates and props to counter this loading.
The final design incorporated use of concrete block units to counter a step in the stone block
floor that lined the shaft. The concrete components (i.e. precast slab and supporting concrete
blocks) of the bridge over the shaft would provide a 100 year design life as required by the
NZTA Bridge Manual.
Hughes, C.G.C, Mokhtari, A. & West, B. (2013). Preservation and capping of a mineshaft under SH25 in Thames, New Zealand
In addition we incorporated detailed requirements for preparation and coating of the metal
components (the plate and props) to ensure a design life of approximately 50 years. This means
that a maintenance check will be required towards the end of this design life in order to identify
metal components requiring re-application of corrosion protection coatings.
9 REMEDIAL DESIGN
A sketch detail of the remedial design is presented in Figure 8 below.
Figure 8: Sketch detail of the remedial option
The components used in the construction were treated where needed for corrosion protection.
This included both utilising galvanised metal components and treating the previously identified
damage on the bridge slabs.
10 CONSTRUCTION
Construction work progressed from the middle of May 2012 and initially involved preparing the
site for the concrete slab bridge units that were to be used span the shaft (Figure 9).
Hughes, C.G.C, Mokhtari, A. & West, B. (2013). Preservation and capping of a mineshaft under SH25 in Thames, New Zealand
Figures 9 & 10: Preparing the shaft for the placement of the bridge slabs
Once the foundation was set, concrete mass blocks (Figure 10) were put into place to counter
the difference in floor level. The latter part of the construction work (Figures 11 to 16) involved
mobilising two cranes to the site to install the steel plate and the props within the shaft, before
finally covering the shaft with the reinforced concrete bridge units.
Figures 11 & 12: Lifting the steel plates into position inside the shaft
Figures 13 &14: Installing plate, props then placing bridge units to cover the shaft
Hughes, C.G.C, Mokhtari, A. & West, B. (2013). Preservation and capping of a mineshaft under SH25 in Thames, New Zealand
Figures 15 and 16: Final concrete pour prior to backfill and pavement reconstruction
11 CONCLUSION: A SUCCESSFUL PROJECT OUTCOME
Design of the remedial options and
the subsequent construction of the
mine shaft cover and the
reinstatement of SH25 was carried
out by engineers and staff from a
number of disciplines
encompassing our network
maintenance, structural,
geotechnical and archaeological
teams.
SH25 was re-opened to the public
by the end of 15th June 2012
(Figure 17).
Figure 17: SH25 as reinstated
The success of this project came about from good liaison and understanding between each of
our teams and in particular from engaging all disciplines at the early phase of the design work to
agree the most appropriate and safe way forwards.
ACKNOWLEDGEMENTS This paper has been written with the approval of the New Zealand Transport Agency, who
commissioned Opus International Consultants Limited to undertake investigation and design of
the mine shaft remedial works.
REFERENCES
The Geology of the Thames Subdivision, Hauraki, Auckland, by Colin Fraser. New Zealand
Geological Survey, Bulletin No 10, dated 1910. Geological Map 1:10,000 scale.
Copy of Figure 35, ‘Construction over abandoned mine workings’, by PR Healey, JM Head.
CIRIA Special Publication 32, PSA Civil Engineering Technical Guide 34, dated
1984, reprinted 2002.
NZTA Bridge Manual, 2nd
edition 2003.
Verification Method, B1/VM4, Building Industry Authority, 1 December 2000.