Varelrollerconedrillbits 13261086839331-phpapp01-120109053222-phpapp01
Presentation211 1264359193394 Phpapp01
Transcript of Presentation211 1264359193394 Phpapp01
DPL LTD.
Clint Dalziel
Owen Lanktree
Seema Pallan
Replace Sucker rod pump at the well 3-22-21-26W4M near Herronton, Alberta. Based on our comparison of these three pumps
1) Progressive Cavity Pumping System
2) Beam Pump/ Reciprocating Rod Pump
3) Electric Submersible Pumping System
Artificial Oil Lift Technologies-Agenda
3-22-21-26W4MOffsetting Wells
3-22-21-26W4M
Depth 2171m-KB
Reservoir Pressure (May 2007)
1371psig
Bottom hole Temperature ≈ 120oF
Average Daily Fluid Production
≈ 345 STB/Day
Well Information03-22-21-26W4M
Progressive Cavity Pump
Progressive Cavity Pump
Operating Volumes 10BPD – 10,000BPD
Operating Depth 2,000ft to 6,000ft
Operating Temp 75oF – 350oF
Bottomhole pressures -Maximum ≈5000psig
Capital Cost -1/2 of the rod pumping system , 1/5 of an ESP
Efficiency -Excellent, typically 60%-70%
Operating Cost -Low to Moderate
Reliability -Varies-Stator elastomers are sensitive to some well fluids
Progressive Cavity Pump
Travelling
Reciprocating Rod Pump
Reciprocating Rod Pump
Operating Volumes 5BPD-1500 BPD
Operating Depth 100ft -11,000ft
Operating Temp 100oF – 350oF
Bottom hole pressures -50 –100 psig minimum
Capital Cost -Low to moderate, dependant on depth reached
Efficiency -With full pump fillage, around 45%-60% is possible
Operating Cost -Low for depths <7500ft, and production <400 BPD
Reliability -Excellent reliability if good operating practices are followed
Reciprocating Rod Pump
MLE Cable
Submersible Pump
Intake
Protector
Motor
Shaft
HousingDiffuser
Impeller
Electric Submersible Pumps
Electric Submersible Pump
Operating Volumes 200BPD – 30000BPD
Operating Depth 1000ft to 15000ft
Operating Temp 100oF – 400oF
Bottomhole pressures >250psig
Capital Cost -Relatively low if electricity is available, increases with horsepower
Efficiency -Normally around 40%-50%
Operating Cost -High energy cost-High repair cost
Reliability -Sensitive to temperatures and electrical failure.-Short run life
Electric Submersible Pump
Summary of Condition Ranges
Operating Conditions
Pump System
PCP ESP Beam
Operating Volumes 10 –10,000BPD 200 – 30,000BPD 5-1,500 BPD
Depth 2,000ft-6,000ft 1,000ft-15,000ft 100-ft1,100 ft
Pressure <5,000 psig >250 psig >50-100psig
Temperature 75-350oF 100-400oF 100-350oF
Replace the sucker rod system at 3-22-21-26W4M near Herronton Gas Plant
Use the information we were given and our knowledge of the three systems to choose the best system for this well.
Problem
3-22-21-26W4MOffsetting Wells
3-22-21-26W4M
Operating Conditions
Depth 2171m-KB
Reservoir Pressure (May 2007)
1371psig
Bottom hole Temperature ≈ 120oF
Average Daily Production ≈ 345 STB/Day
03-22-21-26W4M Bottomhole Conditions
.
Operating Conditions
Pump System
PCP ESP Beam
Operating Volumes
200 –30000BPD
200 – 30000BPD 5-1500 BPD
Depth 2000ft-6000ft 1000ft-15000ft 100-ft1100 ft
Pressure <5000 psig >250 psig >50-100psig
Temperature 75-350oF 100-400oF 100-350oF
Typical Operating Efficiency
14-22-021-26W4
06-22-021-26W4
04-27-021-26W4
03-22-021-26W4
02-21-21-26W4
0.0
50.0
100.0
150.0
200.0
250.0
Average Total Fluid Production per Day (lifetime)
Well Location
Ave
rag
e T
ota
l F
luid
Pro
dcu
tio
n
(m3/
day
)
14-22-021-26W4
06-22-021-26W4
04-27-021-26W4
03-22-021-26W4
02-21-21-26W4
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
Average Net Oil Production per Day (lifetime)
Well Location
Ave
rag
e P
rod
uct
ion
(m
3/d
ay)
ESP
PCP
RRPRRP
RRP
RRP
PCP
ESPRRP
RRP
Production Comparison
months to payout @
Totals Oil Gas H20 boe's/day 14.2Option # 1 Upsize Rod pump and upsize Pump jack 2 11 58 77.7
Rig time 10,000Pump 8,000Rods Fiberglass/Co-rod 30,000Surface Equip pumpjack 95,000Surface tie-in 10,000
total 153,000 4.6
Option # 2 PCP pump (around the corner) 2 11 58 77.7
Rig time 12,000Pump 16,000Rods 39,000Upsize tbg 10,000Surface Equip 28,000Surface tie-in 10,000
total 115,000 3.5*1854m of coated tbg and couplers 37,000
total 152,000 4.6
Option #2aPCP pump perforation design 20,000
total 119,000 3.6*1854m of coated tbg and couplers 37,000
total 156,000 4.7
Option # 3 ESP (around the corner) 2 11 58 77.7
Rig time 10,000Pump and cable 92,000Surface Equip 43,500Surface tie-in 10,000
total 155,500 4.7
Predicting a Six to Nine month run life??Pump change $70,000
Herronton 3-22-21-26w4
We have decided the more expensive Progressive Cavity system would be the best system to replace the pump on this well with.
Conclusion
The PCP system has: Lower pump cost, which allows us to
replace tubing within the same cost range as an ESP or Rod Pump system.
Lower operating and maintenance cost. Typically higher operating efficiency. High reliability if good operating.
practises are followed. Proven to produce well in this area.
Why?
http://www2.agric.gov.ab.ca/icons/acis/maps/agricultural_land_resource_atlas_of_alberta/overview/township_grid_system_of_alberta/alberta_township_grid_big_map.png
http://www.glossary.oilfield.slb.com/files/OGL05015.gif
http://upload.wikimedia.org/wikipedia/commons/archive/3/3f/20080803011212!Pump_Jack_labelled.png
http://www.weatherford.com
http://www.spe.org/jpt/2009/08/performance-benefits-of-progressing-cavity-pumps-touted/
http://www.glossary.oilfield.slb.com/DisplayImage.cfm?ID=523
Sources