Presentation from January 8, 2008 Dinner Meeting

download Presentation from January 8, 2008 Dinner Meeting

of 20

Transcript of Presentation from January 8, 2008 Dinner Meeting

  • 8/9/2019 Presentation from January 8, 2008 Dinner Meeting

    1/20

    1

    Courtney LaneINCOSE WMA Dinner Meeting

    January 8, 2008

    Its More Than Just Numbers:How to Implement a Qualitative

    Risk Analysis Approach

    This document is confidential and is intended solely for the use and information of the client to whom it is addressed.

  • 8/9/2019 Presentation from January 8, 2008 Dinner Meeting

    2/20

    2

    P urpose

    Describe the difference between qualitative andquantitative risk analysis

    Discuss common problems associated with qualitativeanalysis

    Examine best practices for implementing a qualitative riskanalysis approach

  • 8/9/2019 Presentation from January 8, 2008 Dinner Meeting

    3/20

    3

    S tandard Risk Management P rocess

    DevelopStrategy

    This presentation will focus on the analysis sub-process. This sub-processshould be defined in an organizations risk management strategy

    Analyze

    PlanMonitor

    andControl

    Identify

  • 8/9/2019 Presentation from January 8, 2008 Dinner Meeting

    4/20

    4

    C omponents of Risk Analysis

    Probability of occurrence

    Impact to a projects cost, schedule, and technicalobjectives

    Timeframe

    Handling method

    B y identifying these components, project managers will be able to determinethe magnitude of the risk and effectively prioritize handling of the risks

  • 8/9/2019 Presentation from January 8, 2008 Dinner Meeting

    5/20

    5

    D ifference Between Qualitative and QuantitativeAnalysis

    Qualitative vs. Quantitative

    U se ranges to selectprobability and impactrankings

    Absolute numericalestimates are used for impact and probability

    Focuses on overall level of individual risks (e.g. high,medium, low)

    Allows projects toaggregate individual risksto determine the overalllevel of project risk

    Allows programs to quicklyprioritize risks based on anumber of criteria

    U ses complicated analysissuch as Monte Carlosimulation to prioritizerisks

  • 8/9/2019 Presentation from January 8, 2008 Dinner Meeting

    6/20

    6

    W hy use Qualitative Analysis over Quantitative?

    Lack of historical data

    Lack of the necessary time and resources to conductcomplicated analysis

    Desire to use criteria for prioritization that is difficult toquantify

    Timeframe

    Critical dependencies Political considerations

    The type of analysis appropriate for an organization is dependent upon therisk management maturity level of the organization

  • 8/9/2019 Presentation from January 8, 2008 Dinner Meeting

    7/20

    7

    Risk Management Maturity ModelLevel C haracteristics1: Chaotic isks are ignored or managed in an ad hoc fashion

    2: Reactive Processes definedManagement uncomfortable discussing riskMost efforts spent on resolving issues

    3 : Proactive Processes standardized across the organizationManagement comfortable with risk managementRisk management data used in decision making processes

    4 : Predictive U se of quantitative analysis to predict future resultsCost/benefit analysis implemented

    5 : Optimization Opportunities to exceed project objectives are identified andmanagedS ource: Modified from SEI s Capability Maturity Model

    M ost organizations are not at an appropriate maturity level toimplement quantitative risk analysis

  • 8/9/2019 Presentation from January 8, 2008 Dinner Meeting

    8/20

    8

    Top P roblems Related to Qualitative Analysis

    #1U sing inappropriate criteria to determineprobability and consequence levels

    #2 Trying to quantify qualitative data

    #3Relying on risk scores generated by riskmanagement tools to determine a list of toprisks

  • 8/9/2019 Presentation from January 8, 2008 Dinner Meeting

    9/20

    9

    P roblem #1: Inappropriate C riteria

    Criteria is often too detailed

    Subject matter experts lack the necessary expertise toappropriately select the criteria

    Easy to game the analysis since justification of criteriaselection is extremely subjective

    P oor criteria definitions make it difficult for risk analysts toaccurately reflect impacts to cost, schedule, and performance

  • 8/9/2019 Presentation from January 8, 2008 Dinner Meeting

    10/20

    10

    S olution: Understand Your Audience

    Determine what questions decision makers want the riskmanagement process to answer

    Assess the level of expertise of those performing the riskassessments

    Select criteria that balances the needs and abilities of both parties

  • 8/9/2019 Presentation from January 8, 2008 Dinner Meeting

    11/20

    11

    Ex amples of Qualitative Analysis C riteriaNegligible

    (A)Marginal

    (B)

    S ignificant(C )

    C ritical(D )

    C atastrophic(E )

    C ost Minimal or noimpact

    $2 5K- $5 0K $5 0K- 100 K $100 K- 25 0K > $25 0K

    S chedule Schedule slip < 7 days

    Schedule slipbetween 7 and 1 4 days

    Schedule slipbetween 1 4 and21 days

    Schedule slipbetween 21 and3 0 days

    Schedule slipgreater than 1month

    P erformance Minimal or noimpact

    No impact to keyperformanceparameter;

    degradedcapabilityperformance

    Degradedenterprisecapability

    performance

    Degradedcapabilityperformance with

    impacts to onekey performanceparameter

    Degradedcapabilityperformance with

    impacts to morethan one keyperformanceparameter

    C riteria is too detailed and thus difficult to assess

  • 8/9/2019 Presentation from January 8, 2008 Dinner Meeting

    12/20

    12

    Ex amples of Qualitative Analysis C riteriaNegligible

    (A)Marginal

    (B)S ignificant

    (C )C ritical

    (D )C atastrophic

    (E )

    C ost Minimal or noimpact

    10% of overallbudget

    S chedule Minimal or noimpact

    Additionalresourcesrequired; able tomeet need dates

    Minor slip in keymilestones; notable to meet needdates

    Major slip in keymilestone or critical pathimpacted

    Cant achieve keyteam or major project milestone

    P erformance Minimal or noimpact

    Acceptable withsome reduction inmargin

    Acceptable withsignificantreduction inmargin

    Acceptable; noremaining margin

    U nacceptable

    S ource: Risk Management Guide for DoD Acquisition

    C riteria is extremely subjective and could be easily gamed

  • 8/9/2019 Presentation from January 8, 2008 Dinner Meeting

    13/20

    13

    Ex amples of Qualitative Analysis C riteriaNegligible

    (A)Marginal

    (B)

    S ignificant(C )

    C ritical(D )

    C atastrophic(E )

    C ost Minimal or noimpact

    Cost impactscontained withinthe project

    Cost impactscontained withinthe program

    Cost impactscontained withinthe organization

    Cost impactsaffect externalpartners andcould jeopardizeprogram

    S chedule Minimal or noimpact

    Impacts to criticalpath containedwithin the project

    Impacts to criticalpath containedwithin the program

    Impacts to criticalpath of more thanone program inthe organization

    Impacts thecritical path of external partnersand could

    jeopardizeprogram

    P erformance Minimal or noimpact

    Impacts to criticalfunctions of the

    project

    Impacts to criticalfunctions of the

    program

    Impacts to criticalfunctions of the

    organization

    Impacts to criticalfunctions of

    external partnersand could jeopardize theprogram

    C riteria definitions are easy to assess and impact levels areconsistent across criteria

  • 8/9/2019 Presentation from January 8, 2008 Dinner Meeting

    14/20

    14

    P roblem #2: Quantifying Qualitative D ata

    Engineers often feel more comfortable using numberswhen performing analysis

    Assign numbers to levels of impact U se specific probabilities instead of ranges

    Risk scores often determined by multiplying impact by probability

    However, most risk analysis uses uncalibrated ordinalscales

    Cannot perform math on uncalibrated scales Gives a false sense of rigor Decisions made on inaccurate data

    P erforming math on qualitative data may lead to inaccurateconclusions and a false sense of rigor

  • 8/9/2019 Presentation from January 8, 2008 Dinner Meeting

    15/20

    15

    S olution: D o Not Include Numbers in Analysis

    Avoid assigning numbers to levels of impact andprobability

    U se probability ranges U se letters to represent levels of impact and probability

    U se the highest level of individual impacts to determineoverall impact (dont average impacts)

    U se a risk matrix to determine overall level of risk

  • 8/9/2019 Presentation from January 8, 2008 Dinner Meeting

    16/20

    16

    Ex ample Qualitative Risk Analysis

    O verall level of riskis Red

  • 8/9/2019 Presentation from January 8, 2008 Dinner Meeting

    17/20

    17

    P roblem #3: O veremphasizing Risk S cores

    If problem #2 is not overcome, this becomes a muchlarger problem

    Even if numerical scores are not used, rankings could beincorrect

    Risk tools can generate a list of top risks based on locations on therisk matrix

    Cannot rely solely on the placement on the risk matrix

    Dependencies, political issues and timeliness factors also play apart

    O veremphasis of risk scores to determine top risks resultsmay result in poor decisions made by senior leaders

  • 8/9/2019 Presentation from January 8, 2008 Dinner Meeting

    18/20

    18

    S olution:

    Tailor list of top risks based on the audience

    Consider all factors, not just likelihood and consequence,when creating the list

    Do not use arbitrary thresholds to determine handlingstrategies

    Aim to manage all yellow and red risks

  • 8/9/2019 Presentation from January 8, 2008 Dinner Meeting

    19/20

    19

    S ummary and C onclusion

    Select the appropriate type of analysis based on the riskmanagement maturity level of the organization

    Typical challenges associated with qualitative analysiscan be overcome:

    K now your audiences Avoid using numbers to perform analyses Consider other factors when selecting list of top risks

    Q ualitative analysis can provide leaders with enoughinformation to make sound decisions if implemented properly

  • 8/9/2019 Presentation from January 8, 2008 Dinner Meeting

    20/20

    20

    C ontact Information

    Courtney LaneSenior Consultant

    Booz Allen [email protected]

    7 03- 96 1-800 9