Presentation 3Nov

23
Renewable Energy Scenario in Himachal Pradesh 1 Presentation By: SUBHASH GUPTA Chief Engineer Directorate of Energy

Transcript of Presentation 3Nov

8/3/2019 Presentation 3Nov

http://slidepdf.com/reader/full/presentation-3nov 1/23

Renewable Energy Scenario

inHimachal Pradesh

1

Presentation By:

SUBHASH GUPTA 

Chief Engineer Directorate of Energy

8/3/2019 Presentation 3Nov

http://slidepdf.com/reader/full/presentation-3nov 2/23

Himachal Pradesh at a Glance

Directorate of Energy

2

Area 55673 Sq. km

otal Population 68,00,000

owns 57

Census Villages 20,118

Inhabited Villages 17,495

8/3/2019 Presentation 3Nov

http://slidepdf.com/reader/full/presentation-3nov 3/23

Basin-wise Hydro Power Potential In HP

3

LAHAUL & SPITI

CHAMBA

KANGRA

HAMIRPUR

UNA BILASPUR

SOLAN

SIRMOUR

SHIMLA

KULLUKINNAUR

8/3/2019 Presentation 3Nov

http://slidepdf.com/reader/full/presentation-3nov 4/23

Directorate of Energy

4

STATUS OF POWER POTENTIAL

Identified Power Potential 23000 MW (681Projects)

Commissioned till date 7911 MW (92Projects)Under Implementation 12747 MW (556 Projects)

Under Litigation/Abandoned 1830 MW (11 Projects)

Balance to be Allotted 512 MW (22 Projects)

8/3/2019 Presentation 3Nov

http://slidepdf.com/reader/full/presentation-3nov 5/23

Proposed Distribution of Total

Identified Hydro Potential

Sr. No. Sector Proposed

allocation

1 State 16%

2 Central & Joint 40%

3 Private Above 5 MW 38%

4 Private Upto 5 MW 6%

5

Directorate of Energy

8/3/2019 Presentation 3Nov

http://slidepdf.com/reader/full/presentation-3nov 6/23

Directorate of Energy

6

Sector Wise Status of Allotted Power

Potential

Sector Commissioned Under Implementation Others

No of Projects Capacity in

MWs

No of

Projects

Capacity in MWs No of Projects Capacity in

MWs

State Sector

>5MW

Up to 5MW

10 445.9 24 3147.64

21 27.5 20 75.95

Central/Joint

Sector

9 5644.3 7 3604.07

Private Sector

>5 MW

Up to 5MW

8 1621.40 81 4918.50

44 172.55 424 1001.43

Under litigation/

dispute/ A

bonded

11 1830.00

Total 92 7911 556 12747 11 1830.00

GRAND TOTAL 22488 MW

8/3/2019 Presentation 3Nov

http://slidepdf.com/reader/full/presentation-3nov 7/23Directorate of Energy

7

Status of Projects Up to 25 MW

Sector Commissioned Under Implementation Others

No of Projects Capacity in

MWs

No of

Projects

Capacity in MWs No of Projects Capacity in

MWs

State Sector

>5MW

Up to 5MW

6 79.95 3 22.60

21

27.25 20 75.95

Private Sector

>5 MW

Up to 5MW

4 43.40 49 599.5

44 172.55 424 1001.43

Under litigation

Abonded

4 100

Total 75 323 496 1699 4 100

Grand Total 2122 MW

8/3/2019 Presentation 3Nov

http://slidepdf.com/reader/full/presentation-3nov 8/23

Directorate of Energy

8

Scheduled Commissioning Targets

Five Year Plans Upto 25 MW Above 25 MW

Capacity in MWs Capacity in MWs

2011-12 153.95 921

12th Plan 963.2 5569

13th Plan 582.2 4558

Total 1699 11048

Grand Total 12747 MWs

8/3/2019 Presentation 3Nov

http://slidepdf.com/reader/full/presentation-3nov 9/23

HPSEBL  – RPPO Obligation

Directorate of Energy

9

IPP Self Generation RPPO Compliance

Sr. No Year Installed

Capacity

(MW)

Availabi

lity

(MUs)

Installed

Capacity

(MW)

Availabi

lity

(MUs)

Total RE

Availabi

lity

Total

Require

ment

Net

Surplus

1 2011-12 173 643.00 101.00 306 949 907.66 41.34

2 2012-13 231 896.00 105.00 359 1255 984.15 270.85

3 2013-14 286 1124.00 115.00 401 1525 939.72 585.28

4 2014-15 326 1290.00 115.00 401 1691 958.68 732.32

5 2015-16 343 1361.00 115.00 401 1762 1115.21 646.79

6 2016-17 343 1361.00 115.00 401 1762 1286.99 475.02

8/3/2019 Presentation 3Nov

http://slidepdf.com/reader/full/presentation-3nov 10/23

Power Sector Set Up In Himachal Pradesh

10

Directorate of Energy

Deptt Of MPP & Power

Deptt Of NES

8/3/2019 Presentation 3Nov

http://slidepdf.com/reader/full/presentation-3nov 11/23

Deptt Of NES

11

Directorate of Energy

Identification, Allotment & Monitoring of Projects upto 5MW.

Policy Formulation for Other Renewable Sources, Wind and Solar.

SPV Power plant 200kw commissioned in Sirmour Distt.

Implementation of programme under Jawaharlal Nehru SolarMission.

Two State level Energy Parks are being developed under SADPScheme of MNRE GoI.

GoI Approved the proposal to develop Shimla & Hamirpur as SolarCities.

HIMURJA is agency under Dept of NES with following Major functions

8/3/2019 Presentation 3Nov

http://slidepdf.com/reader/full/presentation-3nov 12/23Directorate of Energy

12

Directorate of Energy

Chief Electrical

Inspectorate

HPPCL HPTCL HPSEBL

8/3/2019 Presentation 3Nov

http://slidepdf.com/reader/full/presentation-3nov 13/23Directorate of Energy

13

ROLE OF DIRECTORATE OF ENERGY

After trifurcation of State Electricity Board, Directorate of Energy

was created for performing following activities: Allotment of Projects

Monitoring implementation of Projects

Grant of TEC (Techno Economic Clearance)

Sale of GoHP share of Power 

Energy Conservation & Efficiency

Controlling SLDC Society

Accreditation of Renewable Energy Certificates

8/3/2019 Presentation 3Nov

http://slidepdf.com/reader/full/presentation-3nov 14/23Directorate of Energy

14

RE-ASSESSMENT OF POWER POTENTIAL

Work awarded to Lahmeyer International (I) Pvt. Ltd, for :

 – Identification of balance Power Potential

 – Basin-wise Digitization of Power Potential

 – Marking of Project Domains

8/3/2019 Presentation 3Nov

http://slidepdf.com/reader/full/presentation-3nov 15/23Directorate of Energy

15

Allotment Policy & Milestones

Allotment Policy

- Well Defined and Transparent

- Through International Competitive Bidding (above 5 MW)

Practicable time frame for milestones & penalties for delay - DPR preparation & submission

- Signing of IA

- TEC/Statutory clearances

- Start of Construction work

- SCOD

8/3/2019 Presentation 3Nov

http://slidepdf.com/reader/full/presentation-3nov 16/23

16

Three stage monitoring system

Routine monitoring by Directorate of 

EnergyAt District level by a committee headed by

DCs

At GOHP Level by a committee Headed by

Chief Secretary

Well defined Monitoring Mechanism

Directorate of Energy

8/3/2019 Presentation 3Nov

http://slidepdf.com/reader/full/presentation-3nov 17/23

Directorate of Energy

17

LOCAL AREA DEVELOPMENT FUND

Clarity in objectives & utilization of 1.5%/1% ofthe total project cost.

Effective Institutional Management

Parameters for allocation of Funds

Clarity on shelf of schemes

1% additional free power for LADF (Cash transferto the families located in project affected areawith additional benefit to BPL families)

Revised Guidelines for LADF Management

8/3/2019 Presentation 3Nov

http://slidepdf.com/reader/full/presentation-3nov 18/23

Directorate of Energy

18

SALE OF GOHP SHARE OF POWER

Total Generation 7911 MW (92 Projects)

-Total Free Power To GoHP 550 MW (17 Projects)

-Total Equity Power Available 330 MW (1 Project)-Total Saleable Power 880 MW (17 Projects)

HPSEB LTD.Short Term PPA

We Sell Through PTC

Power Exchange

8/3/2019 Presentation 3Nov

http://slidepdf.com/reader/full/presentation-3nov 19/23

DOE is SDA under EC Act under the aegis of BEE (MoP)GoIThree Pronged Approach

KAP Survey Amendment of Building Code I&PH PumpingSystems

Renewable Energy Certificates

DOE is SA for REC designated by HPSERCIn process of issuing REC accreditation to the power generators upto

25 MW capacity that can be traded to get better price for the power 

produced

Directorate of Energy

19

ENERGY CONSERVATION FUND

8/3/2019 Presentation 3Nov

http://slidepdf.com/reader/full/presentation-3nov 20/23

Directorate of Energy

20

Accreditation under REC accorded to Three

projects with aggregate capacity of 21 MW

Accreditation under process for two hydro

projects with aggregate capacity 10.5 MW

Accreditation under process for one solar power

project with capacity .25 MW

Status of REC

8/3/2019 Presentation 3Nov

http://slidepdf.com/reader/full/presentation-3nov 21/23

Directorate of Energy

21

 The requirement of Basin Studies

- Time consuming process

- Min. 2 yrs even if started todayIntegrated Environment management Plans

- Issue of cost sharing mechanism

Issues of Riparian Distance- Relook at entire planning as Hydro projects

being a site specific project

Environmental Concerns

8/3/2019 Presentation 3Nov

http://slidepdf.com/reader/full/presentation-3nov 22/23

Directorate of Energy

22

Limited Corridors & Environmental issues

Staggered schedule of generating stations

coming into production.

Huge investments in transmission remain

under utilized for years together.

High wheeling charges in initial year.

TRANSMISSION ISSUES

8/3/2019 Presentation 3Nov

http://slidepdf.com/reader/full/presentation-3nov 23/23

Directorate of Energy

23

 THANKS