6. PREPARING YOUR TRADES – PROJECT GOALS AND REQUIREMENT S. Page 24. Management of Green Job-Sites. Everyone on your team needs to be on the same page about the requirements of a green job. 2. Sustainability Training Issues Across Trades Pages 24-25. Inter-Trade Coordination. Examples: - PowerPoint PPT Presentation

Transcript of PREPARING YOUR TRADES – PROJECT GOALS AND REQUIREMENT S

Page 1: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

PREPARING YOUR TRADES – PROJECT GOALS AND REQUIREMENTS

6

Page 24

Page 2: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO 2

Everyone on your team needs to be on the same page about the requirements of a green job.

Sustainability Training Issues Across Trades Pages 24-25

Management of Green Job-Sites

Page 3: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

Inter-Trade Coordination

Examples:•Floor penetrations•Underfloor distribution of HVAC and wiring•Building management systems•Low-VOC materials

Sustainability Training Issues Across Trades Pages 25-26

Page 4: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

Waste Disposal

• Fluorescent lamps

• Magnetic ballasts

• Recycle or reuse steel conduit

Sustainability Training Issues Across Trades Page 26

Fluorescent lampsSteel conduit

Page 5: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

Temporary Light and Power

• Reuse equipment and material at future job sites

• Minimize energy use during construction

• All non-emergency lights to shut down and emergency lights to drop to code minimums

• Efficient design of on-site and temporary power

Sustainability Training Issues Across Trades Pages 26-27

Construction site at nightEfficient lighting saves energy and money.

Page 6: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO Sustainability Training Issues Across Trades Page 27

Site Environmental Quality:No-Smoking Policy

Page 7: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

Site Environmental Quality

Pay attention to conditions while construction is underway:•Bathroom Use•Food Waste•Air Filters

Sustainability Training Issues Across Trades Pages 27-28

Page 8: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

Job-Site Orientation

• Orientation should occur whenever new trades show up on job-site.

• Every worker on the job should understand:

• This is a green building• What makes this project

green• What are responsibilities

of trades to achieve sustainable goals

Sustainability Training Issues Across Trades Page 28

Page 9: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

Trade Training – All Trades

• IAQ and VOCs

• Materials storage

• Waste reduction

• Cx process

• How to collect and provide documentation

• Green sequence of installation issues

• Recycled & regional materials

Sustainability Training Issues Across Trades Pages 24-28

Page 10: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

Issues Relevant to Specific Trades: Core and Shell

Issues Relevant to Specific Trades Pages 28-29

Excavation/Demolition: •ESC Plan

•Low-sulfur fuel use

Formwork:•FSC wood requirements

•Reusable formwork

•Formaldehyde-free wood for forms that remain in place

•Layout issues with in-slab or underground elements

Page 11: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

Green Construction Impacts: Core and Shell

Foundation:•Concrete wash-out control

Steel:•Recycled content documentation

Concrete:•Recycled content calculations (mix or just cement)

•Regional content requirements: sand/gravel

•Submittals for recycled and regional content

Issues Relevant to Specific Trades Pages 29-30

Page 12: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

Green Construction Impacts: Core and Shell

Envelope:Specifications for:

• Hi-performance glazing

• Wall and roof insulation

• Reflective roofing

• Green roof systems

• Sealing of joints & penetrations

Issues Relevant to Specific Trades Page 30

Page 13: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

• Confirm specified materials

• Rapidly renewable materials

• FSC wood

• Material storage

Issues Relevant to Specific Trades Page 30

Page 14: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

• Allow for possible longer curing times when using low-VOC materials

• Provide MSDS documentation for all products

• Air sealing coordination

• Lead abatement

Issues Relevant to Specific Trades Page 30

Page 15: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

• New products & technologies

• Piping routes & installation sequences

• Consider sequence installation

• HVAC controls

• Systems training

Issues Relevant to Specific Trades Page 31

Page 16: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

• New products & technologies

• Commissioning of lighting & dimming controls and other electrical systems

• Coordination with air sealing

Issues Relevant to Specific Trades Page 30

Page 17: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

• Separation of recyclables

• On-site sorting

• Tracking pickups

• Material storage

Issues Relevant to Specific Trades Page 31

Page 18: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

CLASS DISCUSSION:

Tradesperson training:

Introduce new trades to your green building goals

Page 19: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

TEST YOURSELF:1. Why is it important to train your trades on project

goals and requirements?

2. What are the primary green training issues for all trades?

3. Which sustainable strategies can be classified as construction process activities?

4. What green issues must the CM/GC track in each work area as the project proceeds?

Page 31

Page 20: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

SHOP DRAWINGS & SUBMITTALS7

Page 32

Page 21: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

Submittal Process Overview

Submittal Process Overview Page 32

Integrated with standard best practices.

Review subs' submittals before they go to A/E for compliance with sustainability goals.

Page 22: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO 22

Material Submissions – Substitute Carefully!

Anyone making purchases or overseeing receipt of materials must ensure that the materials match the specifications.

•Wood certified by the Forest Stewardship Council (FSC)

•VOC limits

•Recycled content

Submittal Process Overview Pages 32-33

Page 23: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

Sustainable Sites:

• Erosion & Sedimentation Control Plan (ESC)

Water Efficiency:

• WaterSense and ENERGY STAR labeling

Energy & Atmosphere:

• Verification of ENERGY STAR labeling

• Cx documentation

23Special Issues for the CM/GC to

Require, Track, and Document Page 33

Special Issues for the CM/GC to Require, Track, and Document

Dual-flush toilet

Page 24: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO 24Special Issues for the CM/GC to Require,

Track, and Document Page 33

Special Issues for the CM/GC to Require, Track, and Document

Page 25: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

Indoor Environmental Quality:

• Green labeling and low-VOC product letters

• IAQ inspection checklist

25Special Issues for the CM/GC to Require,

Track, and Document Page 33

Special Issues for the CM/GC to Require, Track, and Document

Page 26: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

• Materials certification letters

• Reporting templates

Sample Materials Certification Form

Page 27: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

1. Four students will receive a LEED credit reporting form and are responsible for gathering verification data and filling the reporting form out.

2. All other students use cut sheets to deliver verification data to appropriate “Construction Manager.”

CLASSROOM EXERCISE:

Page 28: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

TEST YOURSELF:1. Is the shop drawing submittal process

different on a green job? If so, how?

2. What types of additional documentation are required from the CM/GC and your subcontractors?

3. What products require additional documentation to verify sustainable specification conformance?

Page 33

Page 29: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

ROUGH-IN, FINISHES & FIT-OUT

8

Page 34

Page 30: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO Primary Job Management Areas: Rough-In Pages 34-35

… and don't forget commissioning!

Primary Job Management Areas: Rough-In

Page 31: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

CLASS DISCUSSION:

What project management practices and tools can be used to ensure that you are properly tracking and addressing issues at this stage?

Page 32: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

Indoor Air Quality

1.Sequence installation

2.Proper on-site storage of materials

3.Ductwork protection per SMACNA guidelines

4.Confirm all openings in piping or ductwork sealed until start-up

5.Low VOC-emitting finishes

Primary Job Management Areas: Finish & Fit-Out Work Pages 35-36

Primary Job Management Areas:Finish & Fit-Out Work

Ductwork protection

Page 33: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO 33

MEP & Life Safety Systems

1. Confirm HVAC controls meet specs & set points

2. Ensure specifications on lighting, sensors, & renewable systems

3. Verify pipes and ducts are properly insulated

4. Confirm plumbing fixtures meet low-use specifications

Primary Job Management Areas: Finish & Fit-Out Work Page 36

Primary Job Management Areas:Finish & Fit-Out Work

Page 34: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

TEST YOURSELF:

1. What green elements require CM/GC tracking and verification at rough-in?

2. How do you use your Quality Control Plan to ensure that you are catching all the issues?

3. What are the primary green issues the CM/GC must watch out for at the finishes and fit-out stage?

Page 36

Page 35: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

COMMISSIONING & CLOSE-OUT9

Page 37

Page 36: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

The Commissioning Process

Commissioning Page 37

Commissioning (Cx):•Verifies that a facility has been designed, constructed and tested to perform as expected.•Relies on coordination and cooperation with all contractors for a successful project.

Page 37: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

Primary tasks:• Design Review• Construction

Inspections• Performance Testing• O&M Training &

Turnover

Commissioning Agent (CxA)'s Responsibilities

Commissioning Page 38

Page 38: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

Design Review

• Assist in value engineering

• Support development of the Cx Plan

• Provide submittals and shop drawings for review

Construction Inspections

• Arrange for installation inspections

• Coordinate pre-functional and start-up tests

O&M Training and Turnover

• Develop O&M manuals and training

• Troubleshoot systems

How the CM/GC is Involved in Cx Activities

Commissioning Page 38

Page 39: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

Fundamental vs. Enhanced Cx

Commissioning Page 38

Page 40: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

The Commissioning Plan

Commissioning Pages 38-39

The Commissioning Plan is generated during the design phase.

Cx Plan Details: •Overall testing plan and schedule of tests•Forms to record outcome•Required test devices•Personnel responsibilities

Page 41: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO Commissioning Pages 39-40

Coordination with the Trades

Best known benefit of Cx: Smoother, quicker turnover of building systems to operations staff.

A clear description of the expectations and responsibilities of each team member will help the Cx process.

Page 42: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

Primary Systems to be Commissioned

Energy-related systems including:

HVAC&R: Mechanical and passive systems and associated controls

Plumbing: Pumps, boilers, domestic hot water, recycling systems

Electrical: Lighting and daylighting controls,renewable energy systems

Commissioning Page 40

Page 43: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

Possible Other Systems to be Commissioned

Commissioning Page 40

Page 44: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

What Occurs During Testing?

During testing:• Check for damage,

deterioration, and component failures

• Functional tests of individual components

• Operational tests and measurements of the energized system

• (Deferred testing may not occur until after occupancy)

Commissioning Page 40

Page 45: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

If problems occur:• Troubleshooting

techniques• Consult equipment and

component manuals• Check wiring• Re-verify wiring

terminations

Troubleshooting During Testing

Safety checks should be performed at all times.

Commissioning Page 40

Page 46: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

Documentation for Commissioning

Keep track of all documentation including failed tests and remedial actions.

•Deficiency reports leads to remedial action

•Resolution record will show that the system functions correctly

•Use these records to help support future troubleshooting

(Don't forget to take photos)

Commissioning Pages 40-41

Page 47: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

O&M Training

Equipment is fully operational for the first time during Cx – use the opportunity to train O&M staff to prevent callbacks.

Commissioning Page 41

Page 48: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

Electrical Work and Commissioning

• The electrical distribution system is the foundation for all other systems in the building.

• Electricians play a critical role in building performance by preventing electrical failures.

Commissioning Page 41

Page 49: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

What Electrical Systems are Commissioned?

• Lighting and lighting controls• Emergency power• HVAC equipment• Uninterruptible power

Commissioning Page 41

Page 50: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO 50

OPERATIONS

Turning Building Over to Owner

COMMISSIONING CONSTRUCTION

Page 51: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

• Documentation is filed as project progresses

• CM/GC must obtain & organize verifications

• Sustainability Manager files final paperwork online with GBCI

• LEED certification depends on thorough filing!

Formal Project Close-Out Process Page 42

Formal LEED Close-Out

Page 52: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO 52

Close-Out Documentation Required

• LEED templates • HVAC systems

manuals• Materials &

certifications

Formal Project Close-Out Process Page 42

Page 53: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

Construction ProcessCourse Wrap-Up Discussion

What questions do you still have about managing a green project?

What are the biggestchallenges and the bestsolutions you have learned?

Page 54: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

TEST YOURSELF:1. Which building systems require the CM/GC's

involvement in the commissioning process?

2. How is the CM/GC's role different with Enhanced as opposed to Fundamental Commissioning?

3. What are the CM/GC's roles in commissioning at the various stages of construction?

4. What types of green-related documentation must the CM/GC provide at project close-out?

Page 40

Page 55: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

MEASUREMENT &VERIFICATION10

Page 41

Page 56: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO Measurement and Verification Pages 41-42

Measurement and Verification

You can't manage what you don't measure!

Page 57: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

Verification that Purchased Items Meet Specs

Find out what documentation is required and make sure all documents are retained

(Don't forget to take photos)

Measurement and Verification Page 42

Page 58: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

M&V and Retrofits

Simple!

Measure energy consumption before and after retrofits and improvements by collecting utility data.

Measurement and Verification Page 42

Page 59: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

M&V in New Construction

Measurement and Verification Pages 42-43

Page 60: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

• Description of the energy efficiency measures implemented

• Selection of the baseline and reporting periods

• Identification of routine and non-routine adjustments

• Selection of meters

What is Included in an M&V Plan

Measurement and Verification Page 43

Page 61: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

IPMVP from the EVO

IPMVP Protocols

Standards for verifying energy efficiency in buildings

•Efficiency Valuation Organization (EVO)

•International Performance Measurement and Verification Protocol (IPMVP)

Measurement and Verification Pages 43-44

Page 62: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

IPMVP Protocols

Four options for M&V depending on whether it's a:

•Retrofit

•New construction project

•Whole building

•Single system

Measurement and Verification Pages 43-44

IPMVP from the EVO

Page 63: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

Digital meter

Electromechanical meter

Meters For Measurement and Verification

• Standard energy meters

• Time-of-day meters

• Demand meters

• Interval meters

• Smart meters

Measurement and Verification Pages 44-45

Page 64: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

A Post-Occupancy Review & Assessment is the process of engaging a project team to review how goals stacked up to outcomes.

It looks at:

•Work flow•Management decisions•Team member accountability•Successes and failures•Possible improvements

Post-Occupancy Review and Assessment Page 45

Post-Occupancy Review and Assessment

Page 65: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO 65

Post-Occupancy Review and Assessment

What are the benefits of Review and Assessment?

1.Documents best practices

2.Learning exchange which benefits the group

3.Increase in understanding

4.Greater job satisfaction due to being able to give and receive constructive feedback

Post-Occupancy Review and Assessment Page 45

ACROS Fukuoka Prefectural International Hall

Page 66: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO Post-Occupancy Review and Assessment Pages 45-47

Conducting a Post-Occupancy Review and Assessment

Page 67: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

1. How accurate were our original estimates?

2. Were the funding opportunities realized?

3. What was most frustrating?

4. Describe any warning signs to notice next time?

5. Were the constraints, limitations, and requirements made clear to all?

6. Was there adequate clarity?

67

Sample Questions

Post-Occupancy Review and Assessment Pages 46-47

Page 68: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO Post-Occupancy Review and Assessment Page 48

Conducting a Post-Occupancy Review and Assessment

Page 69: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

TEST YOURSELF:1. Describe the different options available for

M&V in the IPMVP published by EVO.

2. Describe how energy efficiency is predicted and measured in the construction of a new building versus a retrofit.

3. Describe the value of a Post-Occupancy Review and Assessment.

Page 48

Page 70: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PRO

A knowledgeable and prepared CM/GC is critical to the successful construction of a green building.

You now have the tools and knowledge needed to facilitate a green project and are now part of a growing green building workforce and industry.

Conclusion

Conclusion Page 49

Page 71: PREPARING YOUR  TRADES – PROJECT GOALS  AND REQUIREMENT S

G|PROGreen Professional Building Skills Training