PREFEASIBILITY REPORT FOR BRICK EARTH MINE€¦ · 1. EXECUTIVE SUMMARY The land area of the Soil...

14
RAI ENVIROMENTAL SERVICES PVT. LTD.-LUCKNOW M/s Badri Ent Udyog, Village-Hiramanpur Pratapur, Tehsil-Handia, District- Allahabad, U.P. PREFEASIBILITY REPORT FOR BRICK EARTH MINE Developed By- M/s Badri Ent Udyog, Village-Hiramanpur Pratapur, Tehsil-Handia, District- Allahabad, U.P. RAI ENVIRONMENTAL SERVICES PVT. Page 1

Transcript of PREFEASIBILITY REPORT FOR BRICK EARTH MINE€¦ · 1. EXECUTIVE SUMMARY The land area of the Soil...

Page 1: PREFEASIBILITY REPORT FOR BRICK EARTH MINE€¦ · 1. EXECUTIVE SUMMARY The land area of the Soil excavation project Location is at M/s Badri Ent Udyog from 774 ... Ugrasen Railway

RAI ENVIROMENTAL SERVICES PVT. LTD.-LUCKNOW

M/s Badri Ent Udyog, Village-Hiramanpur Pratapur, Tehsil-Handia, District- Allahabad, U.P.

PREFEASIBILITY REPORT FOR

BRICK EARTH MINE

Developed By-

M/s Badri Ent Udyog,Village-Hiramanpur Pratapur, Tehsil-Handia,

District- Allahabad, U.P.

RAI ENVIRONMENTAL SERVICES PVT.

Page 1

Page 2: PREFEASIBILITY REPORT FOR BRICK EARTH MINE€¦ · 1. EXECUTIVE SUMMARY The land area of the Soil excavation project Location is at M/s Badri Ent Udyog from 774 ... Ugrasen Railway

RAI ENVIROMENTAL SERVICES PVT. LTD.-LUCKNOW

M/s Badri Ent Udyog, Village-Hiramanpur Pratapur, Tehsil-Handia, District- Allahabad, U.P.

C O N T E N T S

------------------------------------------------------------------------------------------------------------

S.No. CHAPTERS

------------------------------------------------------------------------------------------------------------

1 EXECUTIVE SUMMARY

2 INTRODUCTION OF THE PROJECT / BACKGROUND INFORMATION

3 PROJECT DESCRIPTION

4 SITE ANALYSIS

5 PLANNING BRIEF

6 PROPOSED INFRASTRUCTURE

7 REHABILITATION AND RESETTLEMENT (R & R) PLAN

8 PROJECT SCHEDULE & COST ESTIMATES.

9 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)

------------------------------------------------------------------------------------------------------------

Page 2

Page 3: PREFEASIBILITY REPORT FOR BRICK EARTH MINE€¦ · 1. EXECUTIVE SUMMARY The land area of the Soil excavation project Location is at M/s Badri Ent Udyog from 774 ... Ugrasen Railway

RAI ENVIROMENTAL SERVICES PVT. LTD.-LUCKNOW

M/s Badri Ent Udyog, Village-Hiramanpur Pratapur, Tehsil-Handia, District- Allahabad, U.P.

1. EXECUTIVE SUMMARY

The land area of the Soil excavation project Location is at M/s Badri Ent Udyog from 774Hiramanpur; 7,117,169,143,1143,1196 da,37,175,263,265 at village karuadeeh, Tehsil- Handia,District - Allahabad, U.P (Area-3.323 hac) and falls under Category- B (Sub-category B2), as perEnvironment (Protection) Rules, 1986, vide number S.O. 2588(E), dated 15th Jan, 2016,) theapplicant is seeking prior environmental clearance less than 5.0 ha from DEIAA of concerningDistrict. Project Area 3.323 hac

Location ofexcavation site

Latitude- 25°30'2.10"N to 25°30'5.13"N

Longitude- 82° 9'57.67"E to 82° 9'55.71"E

Toposheet No. 63K/3

Gata No. M/s Badri Ent Udyog from 774 Hiramanpur; 7,117,169,143,1143,1196da,37,175,263,265 at village karuadeeh, Tehsil- Handia, District - Allahabad,U.P (Area-3.323 hac)

Topography Undeveloped flat with gentle slopeMinerals ofexcavation site

Brick Clay

Proposedproduction ofexcavation site

Proposed production is 9689.8 cu.mtr/ 33,91,430 bricks per annum & totalmineable reserve is 48449 cu.mtr.

Method of mining ManualDrilling/Blasting No drilling and blasting is proposedWater demand 2.0 KLDSources of water Water will be supplied from potable water from tanker supplier.Ultimate depth ofexcavation site

As per agreements but not more than 2 meters

Man power 20 LaboursSolid Waste Local labours from nearby villages will be hired; no generation of solid waste

is anticipated due to proposed project activity.Nearest railwaystation

Ugrasen Railway Station 11 km from the project site in NE direction.

Nearest statehighway/Nationalhighway

NH-2 road- 15 km towards S direction from the project site.

Nearest Airport Allahabad Bamrauli Airport- 42.9 Km SW.

2. INTRODUCTION

Page 3

Page 4: PREFEASIBILITY REPORT FOR BRICK EARTH MINE€¦ · 1. EXECUTIVE SUMMARY The land area of the Soil excavation project Location is at M/s Badri Ent Udyog from 774 ... Ugrasen Railway

RAI ENVIROMENTAL SERVICES PVT. LTD.-LUCKNOW

M/s Badri Ent Udyog, Village-Hiramanpur Pratapur, Tehsil-Handia, District- Allahabad, U.P.

2.1 Identification of Project and Project Proponent

The soli will be excavated from proposed project site. The details of the project and itsProponents/Partners are given below:Name of theapplicant

Ram Pyare Patel

Address Village-Karuadeeh Pratappur, Tehsil-Handia, District- Allahabad,U.P.

Khasra/ Gata No. M/s Badri Ent Udyog from 774 Hiramanpur;7,117,169,143,1143,1196 da,37,175,263,265 at village karuadeeh,Tehsil- Handia, District - Allahabad, U.P (Area-3.323 hac)

Area 3.323 hacMineral Brick ClayStatus of Mine Fresh application for Environmental Clearance for Excavation of soil.

2.2 Brief description of the nature of the projectThe proposed project is to mine brick clay from above mentioned plots sustainably and

scientifically. Mining will be opencast and manual as per mining rules keeping all the nearby plots

unaffected. Following geo-scientific methods are proposed to carry out the activity:

Mining will be confined to extraction of Brick Clay in its existing form, from their allotted

plots only.

Mining of Brick Clay from their allotted plot (s) will be restricted to a maximum depth of 2

m from the surface.

No drilling and blasting is proposed.

Approximately 9689.8 cu.mtr/ 33,91,430 bricks per annum minor mineral will be

extracted.

No mining activity will be undertaken during the monsoon season.

In order to avoid environmental pollution or any accidental hazards, the mining activity will

be restricted to daytime only.

The operation will remain manual, using tools like shovel, spade, sieve etc.

2.3 Need for the project and its importance to the country and region

The proposed land is undulated land. To make the land flat suitable for agriculture, the

excavated soil from the undulated land would be used for commercial purpose. The excavation

work will provide employment to the local labours.

2.4 Demands-Supply Gap

Page 4

Page 5: PREFEASIBILITY REPORT FOR BRICK EARTH MINE€¦ · 1. EXECUTIVE SUMMARY The land area of the Soil excavation project Location is at M/s Badri Ent Udyog from 774 ... Ugrasen Railway

RAI ENVIROMENTAL SERVICES PVT. LTD.-LUCKNOW

M/s Badri Ent Udyog, Village-Hiramanpur Pratapur, Tehsil-Handia, District- Allahabad, U.P.

Brick Clay has become a very important mineral for the manufacturing of Bricks which

contributes to the expansion of infrastructure in the society. With the increase of urbanization the

demand for Bricks is growing in infrastructure sector in our country. Individual and private

companies are increasingly demanding Brick for construction purposes and this has immense

pressure on brick clay resources. This increasing demand and extraction makes this an

environmental issue.

2.5 Domestic/ Export MarketsDue to the increased industrial and infrastructural growth of the rural and urban areas

demand of Brick is very high. Construction companies and local vendors in the nearby town and

cities are the potential market for the brick made up of brick clay.

2.6 Employment GenerationThe proposed project will generate direct /indirect employment to the people of all class of

society. During the operational phase not more than 20 semi skilled and non skilled workers will be

hired. The contractors will get the direct or indirect benefit from the project activity.

3.0 PROJECT DESCRIPTION3.1 Type of project including interlinked and interdependent projects, if any

This is a new mining project. The proposed project is for the extraction of Brick Clay from

the allotted plot(s) manually.

3.2 Location (map showing general location and project boundary and project site) withcoordinates.

The site is located in M/s Badri Ent Udyog from 774 Hiramanpur; 7,117,169,143,1143,1196da,37,175,263,265 at village karuadeeh, Tehsil- Handia, District - Allahabad, U.P (Area-3.323 hac)The excavation lease area falls in Survey of India Toposheet (63K/3).

Page 5

Page 6: PREFEASIBILITY REPORT FOR BRICK EARTH MINE€¦ · 1. EXECUTIVE SUMMARY The land area of the Soil excavation project Location is at M/s Badri Ent Udyog from 774 ... Ugrasen Railway

RAI ENVIROMENTAL SERVICES PVT. LTD.-LUCKNOW

M/s Badri Ent Udyog, Village-Hiramanpur Pratapur, Tehsil-Handia, District- Allahabad, U.P.

Google 5 km Buffer Zone Map of Proposed Project Site: M/s Badri Ent Udyog , Village-Hiramanpur Pratapur, Tehsil-Handia, District- Allahabad, U.P.

Google 500 m Buffer Zone Map of Proposed Project Site: M/s Badri Ent Udyog , Village-Hiramanpur Pratapur, Tehsil-Handia, District- Allahabad, U.P.

Page 6

Page 7: PREFEASIBILITY REPORT FOR BRICK EARTH MINE€¦ · 1. EXECUTIVE SUMMARY The land area of the Soil excavation project Location is at M/s Badri Ent Udyog from 774 ... Ugrasen Railway

RAI ENVIROMENTAL SERVICES PVT. LTD.-LUCKNOW

M/s Badri Ent Udyog, Village-Hiramanpur Pratapur, Tehsil-Handia, District- Allahabad, U.P.

3.3 Details of alternate sites consideredThe soil excavation site is site specific, hence there are no alternative sites considered.

3.4 Size or magnitude of operationThe proposed excavation area is 3.323 ha. The total excavated Brick clay would be 9689.8 m3 per annum & total mineable reserve is 48449 cu.mtr.

3.5 Project description with process detailsThe proposed project is to mine Brick Clay from plot(s) under agreement sustainably and

scientifically. Mining will be opencast and manual along the plot(s) keeping the nearby

plot(s) unaffected. Following geo-scientific methods are proposed to carry out the activity:

Mining will be confined to extraction of Brick Clay in its existing form from the allotted

plot(s) only.

Mining of Brick Clay from the allotted plot(s) will be restricted to a maximum depth of 2 m

from the surface in proper bench form as per MCR-1960.

No drilling and blasting is proposed.

Approximately 9689.8 m3 or 33,91,430 bricks per annum per year minor mineral will be

extracted.

No mining activity will be undertaken during the monsoon season.

In order to avoid environmental pollution or any accidental hazards, the mining activity will

be restricted to daytime only.

The operation will remain manual, using tools like shovel, spade, sieve etc.

During the agreement period, the deposit will be worked from the top surface to 2 m.

3.6 Raw Material Required Along With Estimated Quantity, Likely Source, MarketingArea of Final Product/S, Mode of Transport of Raw Material and Finished ProductNo raw material will be required in the proposed project. The operation involves the

extraction of Brick Clay in its existing form. Raw bricks will be cast and transported to the

kiln site by carts and tractor trolleys through village chak roads.

Page 7

Page 8: PREFEASIBILITY REPORT FOR BRICK EARTH MINE€¦ · 1. EXECUTIVE SUMMARY The land area of the Soil excavation project Location is at M/s Badri Ent Udyog from 774 ... Ugrasen Railway

RAI ENVIROMENTAL SERVICES PVT. LTD.-LUCKNOW

M/s Badri Ent Udyog, Village-Hiramanpur Pratapur, Tehsil-Handia, District- Allahabad, U.P.

3.7 Resource optimization/ recycling and reuseNot envisaged.

3.8 Availability of water its source, energy/ power requirement and source

3.8.1 Water Requirement

There will be very little requirement of water to carry out operations as it will be done

manually. The water will be required either for drinking purposes or for casting of bricks. It is

projected that not more than 20 labours will be required for the proposed project. Apart from

casting of bricks, the total water requirement will be 2.0 KLD which include 1.2 KLD for

sprinkling & plantation and 0.8 KLD for Drinking.

All the activities will be carried out manually. The operation will be done in day time;

hence there is no power requirement for the project at site.

3.8.2 Power RequirementThe operation will be done only from sun rise to sunset. Hence there is no power

requirement.

3.9 Quantity of wastes to be generated (liquid and solid) and scheme for theirmanagement/disposal.

3.9.1 Solid Waste Generation & its DisposalThe entire mineral extracted is saleable. The labours from nearby villages will be hired to

carry out work in day time only, hence there will be no or very less waste is expected to generated.

3.9.2 Liquid EffluentNo liquid effluent will be generated at the excavation site.

Page 8

Page 9: PREFEASIBILITY REPORT FOR BRICK EARTH MINE€¦ · 1. EXECUTIVE SUMMARY The land area of the Soil excavation project Location is at M/s Badri Ent Udyog from 774 ... Ugrasen Railway

RAI ENVIROMENTAL SERVICES PVT. LTD.-LUCKNOW

M/s Badri Ent Udyog, Village-Hiramanpur Pratapur, Tehsil-Handia, District- Allahabad, U.P.

3.9 Schematic representation of the feasibility drawing which give information of EIA purpose-

4. SITE ANALYSIS4.1 Connectivity

Allahabad Bamrauli Airport- 42.9 Km SW. NH-2 road- 15 km towards S direction from the project site. Ugrasen Railway Station 11 km from the project site in NE direction.

4.2 Land form, land use and land ownership

Page 9

Page 10: PREFEASIBILITY REPORT FOR BRICK EARTH MINE€¦ · 1. EXECUTIVE SUMMARY The land area of the Soil excavation project Location is at M/s Badri Ent Udyog from 774 ... Ugrasen Railway

RAI ENVIROMENTAL SERVICES PVT. LTD.-LUCKNOW

M/s Badri Ent Udyog, Village-Hiramanpur Pratapur, Tehsil-Handia, District- Allahabad, U.P.

The proposed project is located at M/s Badri Ent Udyog from 774 Hiramanpur;7,117,169,143,1143,1196 da,37,175,263,265 at village karuadeeh, Tehsil- Handia, District -Allahabad, U.P (Area-3.323 hac). The excavation of soil will be from the Non-Agricultural land.4.2.1 Sensitivity of Location:The Proposed Mining Activity of brick clay will be carried out. It is a small scale mining withoutsignificant hazard. However, the other sensitive areas are discussed below-

There is no Reserved Forest/Protected Forest within 5 km from proposed projectsite.

There is no National Park, Wild Life Sanctuary within 5 km from proposed projectsite.

The nearest settlement is Handia 16.5 km in SE Direction from Project Site.

4.3 Topography/Physiography of the area:Brick earth area is marked on cadastral map. The area is almost flat. General slope of the areais towards south east. The highest point is 99mRL and the lowest point is 98mRL.

4.4.4 Geology: Geologically the district is formed by sub-recent to recent rocks composed of theordinary gangetic alluvium. The alluvium probably on the north- eastward sloping basementconsiting of gnisses, granites and patches of vindhyans.

4.4 Existing land use patternCurrently the land is Non-Agricultural land located at The proposed project is located at M/s BadriEnt Udyog from 774 Hiramanpur; 7,117,169,143,1143,1196 da,37,175,263,265 at villagekaruadeeh, Tehsil- Handia, District - Allahabad, U.P (Area-3.323 hac). The excavation of soil fromthe Non-Agricultural land.to make the land flat suitable for the agriculture, the excavation of soil isproposed for commercial purpose. The excavation work will provide employment to the locallabours.

4.5 Soil classification

Soil is characterized mainly by Ordinary soils.

4.6 Climatic data from secondary sources

CLIMATE Warm humid subtropical climate with cool, dry winters from December to February and

dry, hot summers from April to June. The rainy season is from mid-June to mid-September Inwinter the maximum temperature is around 25° Celsius and the minimum is in the 4° to 8° Celsiusrange. Fog is quite common from late December to late January. Summers are very hot withtemperatures rising to the 40° to 45° Celsius range.

4.7 Reserves

Reserve Estimation:

Page 10

Page 11: PREFEASIBILITY REPORT FOR BRICK EARTH MINE€¦ · 1. EXECUTIVE SUMMARY The land area of the Soil excavation project Location is at M/s Badri Ent Udyog from 774 ... Ugrasen Railway

RAI ENVIROMENTAL SERVICES PVT. LTD.-LUCKNOW

M/s Badri Ent Udyog, Village-Hiramanpur Pratapur, Tehsil-Handia, District- Allahabad, U.P.

Brick earth reserves have been estimated as per standard procedures. The area of mining

land (as per agreement details) and average thickness of mineral(not more than 2 m) is multiplied to

get the volume. 10% area wise wide berm will be left all along the periphery of mining land to get

the area available for actual mining. About 10% mining losses reserves blocked due to slope has

been considered to get the mineable quantity. Detail of calculation is given below:

4.7.1 Classification of Reserves:

Khasara No.Area in

HaArea in

SqmMaximumdepth (m)

Area ofBirmleft

(10%)

Top soilin cum

Reserves in cum

GeologicalReserve

MineableReserves

(90%)

774 0.321 3210 2.0 321.0 577.8 5778 4680.2

7 0.506 5060 2.0 506.0 910.8 9108 7377.5

117 0.55 5500 2.0 550.0 990 9900 8019

169 0.406 4060 2.0 406.0 730.8 7308 5919.5

143 0.248 2480 2.0 248.0 446.4 4464 3615.8

1143 0.023 230 2.0 23.0 41.4 414 335.3

1196 da 0.028 280 2.0 28.0 50.4 504 408.2

37 0.426 4260 2.0 426.0 766.8 7668 6211.1

175 0.616 6160 2.0 616.0 1108.8 11088 8981.3

263,265 0.199 1990 2.0 199.0 358.2 3582 2901.4

Total 3.323 33230 3323.0 5981.4 59814 48449

4.7.2 Geological Reserves: 59814 cum

4.7.3 Mineable Reserves: 48449 cum

4.8 Social Infrastructure

Allahabad Bamrauli Airport- 42.9 Km SW. NH-2 road- 15 km towards S direction from the project site. Ugrasen Railway Station 11 km from the project site in NE direction.

5. PLANNING BRIEF

Page 11

Page 12: PREFEASIBILITY REPORT FOR BRICK EARTH MINE€¦ · 1. EXECUTIVE SUMMARY The land area of the Soil excavation project Location is at M/s Badri Ent Udyog from 774 ... Ugrasen Railway

RAI ENVIROMENTAL SERVICES PVT. LTD.-LUCKNOW

M/s Badri Ent Udyog, Village-Hiramanpur Pratapur, Tehsil-Handia, District- Allahabad, U.P.

5.1 Planning conceptThe proposed project is to mine brick clay from plot(s) sustainably and scientifically. The

minor mineral (clay) will be excavated from the plot(s) as per mining rules and casting of raw

bricks will be done which will be transported to the kiln through horse cart, trolleys etc. through

village chak roads. Mining will be opencast Manual keeping nearby plot(s) unaffected. Maximum

depth of mining will be only upto 2 m as per agreement.

5.2 Population projectionThe project will employ the workers from nearby villages. There will not be any increase in

population due to the project.

5.3 Landuse planningThe land use of the mine lease area is agricultural and there will be no change in landuse

after operation. The ultimate land use of the mine lease area will not be change. Extracted mineral

will be used in casting raw bricks which will be transported directly to the kiln, the workers will be

hired locally and temporarily, no housing facility will be required.

5.4 Assessment of Infrastructure DemandExtracted mineral will be casted into raw bricks and will be transported directly to the

owned kiln, there will be no stock yard required for storage, also the workers will be hired locally

and temporarily, no housing facility will be required.

5.5 Amenities/facilitiesDrinking water and first aid facility will be made available to the mine workers.

6. PROPOSED INFRASTRUCTURE6.1 Industrial area (Processing Area)

No industrial area is proposed.

6.2 Residential area (Non Processing Area)

The project will employ most of the workers from nearby villages. So, no housing facility is

required.

6.3 Green belt

It is proposed to plant trees along the road sides and nearby civic amenities in consultation

with district administration.

Page 12

Page 13: PREFEASIBILITY REPORT FOR BRICK EARTH MINE€¦ · 1. EXECUTIVE SUMMARY The land area of the Soil excavation project Location is at M/s Badri Ent Udyog from 774 ... Ugrasen Railway

RAI ENVIROMENTAL SERVICES PVT. LTD.-LUCKNOW

M/s Badri Ent Udyog, Village-Hiramanpur Pratapur, Tehsil-Handia, District- Allahabad, U.P.

6.4 Connectivity

There are metalled roads and unmetalled at the project site.

6.5 Social Infrastructure

Temporary rest shelters, drinking water and first aid facility are made available to the mine

workers with all the required medicines and vaccines.

6.6 Drinking Water Management

Water for drinking is required to be 0.80 KLD. It is proposed to obtain water from

construction/potable water from tanker supplier.

6.7 Sewerage SystemNo sewerage system is proposed at the mine site.

6.8 Industrial Waste ManagementNot applicable.

6.9 Solid Waste management No solid waste generation is expected from the miningoperation.

6.10 Power Requirement & Supply/ Source All the activities will be carried out manually. Theoperation will be restricted to day time only; hence there is no power requirement for the project atsite.7. REHABILITATION AND RESETTLEMENT (R&R) PLAN

.

8. PROJECT SCHEDULE & COST ESTIMATESThe project will commence once Environmental Clearance and other necessary certificates

are obtained from the respective departments. The total cost of project would be approx Rs. 14 lacs

for 1 years.

CSR Plan

CSR (Corporate Social Responsibility) details for the Project

CSR plan is given below:-

Estimated Cost of the Project = Rs. 14 lacs/annum

CSR cost for the project, i.e. 5 % of the total project cost

Page 13

R & R Plan is not applicable for the project as the area . The Area is non Agricultural land. Local people will be employed for excavation work. Economic and social of status of the local people will be improved after excavation work.

Page 14: PREFEASIBILITY REPORT FOR BRICK EARTH MINE€¦ · 1. EXECUTIVE SUMMARY The land area of the Soil excavation project Location is at M/s Badri Ent Udyog from 774 ... Ugrasen Railway

RAI ENVIROMENTAL SERVICES PVT. LTD.-LUCKNOW

M/s Badri Ent Udyog, Village-Hiramanpur Pratapur, Tehsil-Handia, District- Allahabad, U.P.

Rs. 56 Lacs x 0.05 = Rs. 2.8 lakh for 4 year

Ladies and gents toilets will be provided for nearby colleges.

Assistance in providing Safe Drinking Water .

In improving awareness regarding benefit schemes of government for poor distribution of

blankets to poor people of nearby villages.

9.0 ANALYSIS OF PROPOSAL ( FINAL RECOMMENDATION)

Overall the project will have positive and long term impact on environment. The project

will also bring positive changes in terms of socio economic development by way of generating

direct and indirect employment opportunities to the people of vicinity.

The project will also help to make the field cultivable land otherwise may lead to change the

shape of the field to a raised land making area unusable for agriculture.

Also the project will bring economical benefit to the state in terms of revenue generation.

***********

Page 14