PRE-FEASIBILITY REPORT -...
Transcript of PRE-FEASIBILITY REPORT -...
PRE-FEASIBILITY REPORT
FOR
3RD PHASE EXPANSION BY ADDITION OF 5TH STREAM IN ALUMINA REFINERY AT NALCO,
DAMANJODI, DIST: KORAPUT, ODISHA
AUGUST 2015
M. N. DASTUR & COMPANY (P) LTD C o n s u l t i n g E n g i n e e r s
KOLKATA
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
- i -
M. N. DASTUR & COMPANY (P) LTD
TABLE OF CONTENTS
Page EXECUTIVE SUMMARY .. 6 pages 1 - INTRODUCTION Project proponent & identification of the project .. 1-1 Brief description of the nature of the project .. 1-2 Need for the project .. 1-2 Demand-supply gap .. 1-4 Imports vs. indigenous production & export possibility .. 1-5 Domestic/export markets .. 1-5 Employment generation due to the project .. 1-8 Authorisation .. 1-9 Acknowledgement .. 1-9 2 - PROJECT DESCRIPTION Type of project including interlinked project .. 2-1 Location .. 2-1 Details of alternate sites considered .. 2-1 Layout .. 2-2 Magnitude of operation .. 2-3 Project description with process details .. 2-3 Basis of design .. 2-3 Technological details .. 2-5 Laboratory .. 2-21 Requirement of raw materials and probable Sources 2-21 Power requirement .. 2-23 Instrumentation, automation & communication system for the 5th stream of the alumina refinery.. 2-24 Fire detection and alarm system .. 2-25 Water supply system for alumina refinery .. 2-26 Water system for co-generation power plant .. 2-29 Fire fighting water system .. 2-31 Utility system .. 2-32 Co-generation power plant .. 2-33 Resource optimization and reuse .. 2-37 Waste Management and Disposal 2-38
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
- ii -
M. N. DASTUR & COMPANY (P) LTD
TABLE OF CONTENTS (continued)
Page 3 - SITE ANALYSIS Connectivity .. 3-1 Land form, land use and land ownership .. 3-1 Topography .. 3-2 Existing land use .. 3-3 Drainage .. 3-3 Soil .. 3-4 Climatic conditions .. 3-4 Existing physical & social infrastructure .. 3-4
4 - PLANNING BRIEF Population projection .. 4-1 Nearby Existing Industries .. 4-1 Assessment of infrastructure demand (social) .. 4-2
5 - PROPOSED INFRASTRUCTURE Industrial area .. 5-1 Residential area .. 5-1 Proposed social infrastructure .. 5-2 Air pollution control measures .. 5-3 Water pollution control measures .. 5-4 Drinking and sanitation water .. 5-5 Sewage treatment plant .. 5-6 Solid waste management and disposal .. 5-7 Spent acid management 5-8 Work zone pollution control measures 5-8 Corrosion control 5-9 Plant green belt and landscaping 5-9 6 - REHABILITATION AND RESETTLEMENT PLAN 7 - IMPLEMENTATIONSCHEDULE AND COST ESTIMATES Implementation schedule .. 7-1 Cost estimate .. 7-2
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
- iii -
M. N. DASTUR & COMPANY (P) LTD
TABLE OF CONTENTS (continued)
7 - IMPLEMENTATION SCHEDULE AND COST ESTIMATES (cont’d) Page Plant cost .. 7-2 Land and land development .. 7-2 Civil and structural steelwork .. 7-3 Plant and equipment .. 7-3 Technology supply by process licensor .. 7-3 Township .. 7-3 Design, engineering, consultancy services and Administration during construction (DE & ADC) .. 7-3 Contingency .. 7-4 Pre-project activities .. 7-4 Margin money for working capital .. 7-4 Interest during construction .. 7-5 Total capital cost .. 7-5 Financial indicators .. 7-5
8 - ANALYSIS OF PROPOSAL Financial and social benefits .. 8-1 Final recommendations .. 8-3
TABLES Table 2B-1 - Bauxite grade .. 2-4 Table 2B-2 - Quality parameters .. 2-5 Table 2B-3 - Annual requirement of major raw materials.. 2-21 Table 2B-4 - Estimated power requirements for 5th Stream alumina refinery .. 2-23 Table 2B-5 - Make-up water requirement for refinery .. 2-27 Table 2B-6 - Total water consumption in refinery units .. 2-28 Table 2B-7 - Make-up water requirement for power plant.. 2-30 Table 2B-8 - Power plant performance indices .. 2-36 Table 7B-1 - Plant cost estimate .. 7-4 Table 7B-2 - Capital cost estimate .. 7-5 Table 7B-3 - Financial indicators .. 7-5
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
- iv -
M. N. DASTUR & COMPANY (P) LTD
TABLE OF CONTENTS (continued)
APPENDICES
App 2B-1 - Schematic representation of the Refinery .. 1 App 7B-1 - Preliminary overall implementation schedule .. 1
FIGURES
Fig. 2B-1- Site location map Fig. 2B-2- Schematic Flow diagram of EIA steps Fig. 3B-1- Topography of Alumina Refinery Area Fig. 3B-2- Existing Land Use
DRAWINGS Dwg 11253-B-02-0001 - General Layout of Damanjodi alumina refinery Dwg 11253-B-02-0002 - Block flow diagram of alumina refinery Dwg 11253-B-02-0003 - Schematic water balance diagram Aluminium refinery and co-generation plant
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
- 1 -
M. N. DASTUR & COMPANY (P) LTD
EXECUTIVE SUMMARY
This summary presents a concise outline of the Pre-feasibility
Report for the proposed 3rd phase expansion by addition of 5th stream
in Alumina Refinery at Damanjodi, Odisha.
1. NALCO is planning to set up the 5th Stream in its Alumina
Refinery at Damanjodi, Dist: Koraput, Odisha, as a part of
the expansion programme (3rd Phase expansion). The
capacity of this Stream will be 1.0 MTPA. The total expansion
capacity will increase from 2.275 MTPA to 3.275 MTPA. The
processing technology will be based on medium pressure
digestion, as it is found more economical compared with the
existing atmospheric pressure digestion system.
2. The projected availability of alumina in domestic market
beyond 2015-16 is estimated at about 8 million tons based
on the assumption that the alumina refineries that are
currently under initial stages of planning will also
materialise and start production by the projected dates. In
terms of global scenario, the anticipated shortfall of alumina
in global market ranges from 2-10 million tons through years
2015, 2020 and 2025.
3. The proposed 5th stream of the Refinery will come up on the
land owned by NALCO, adjacent to the existing four refinery
streams. NALCO’s captive bauxite mine (Centre & North
block Mining Lease and South block Mining Lease) at
Panchapatmali hill is located at a distance of about 14 km
towards the North-East of the Refinery at Damanjodi,
Dist: Koraput, Odisha.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
Executive summary (cont’d)
- 2 -
M. N. DASTUR & COMPANY (P) LTD
4. One additional overland conveyor system with length of
around 11km between Panchapatmali deposit and Refinery at
Damanjodi has been planned for transfer of bauxite. Alumina
and caustic lye storage and handling facilities have been
envisaged at NALCO’s port facility at Visakhapatnam Port
Trust (VPT) area, Visakhapatnam, Andhra Pradesh.
5. Rio-Tinto-Alcan Medium Pressure (MP) digestion process has
been considered for aluminia refining.
6. The implementation period for the project has been
considered as 48 months.
7. NALCO bauxite (from Central & North Block mining lease
and South Block mining lease of Panchpatmali deposit) is
easy to digest and most of the available alumina (tri-hydrate
alumina) can be extracted even under atmospheric
conditions. This type of bauxite however lends itself very
compatible to medium pressure (MP) digestion process
(1450C) as well, with the resulting increase in liquor
productivity. MP digestion combined with high solids
precipitation will enable NALCO to expand the production
capacity of the Damanjodi refinery by 1.0 MTPA in Line 5.
The high yield and liquor productivity will allow reduction of
the sizes of all equipment such that the facilities proposed
for expansion programme can be installed within NALCO
owned land with minor extension of existing plant boundary.
Against this, the existing technology of atmospheric pressure
digestion would have allowed expansion only by 0.8 MTPA.
The adverse impact on MP digestion caused by increase in
impurities in process circuit and higher boehmite reversion
losses, as generally seen in MP digestion plants, are not
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
Executive summary (cont’d)
- 3 -
M. N. DASTUR & COMPANY (P) LTD
expected to occur with NALCO bauxite due to low level of
impurities in the same. The specific investment cost of MP
digestion is lower by about 20 per cent than that for
Atmospheric pressure digestion process due to higher
productivity. Likewise, the differential operating cost of MP
digestion is also lower by about 3 per cent. As such, it may
be concluded that MP digestion process is more favourable
for NALCO 5th Stream than atmospheric pressure digestion
in terms of both CAPEX and OPEX.
8. Bauxite is the major raw material for the refinery and will be
obtained entirely from Central & North Block mining lease
and South Block mining lease of Panchpatmali mine.
Caustic soda in the form of lye will be received by ship at
Visakhapatnam Port, stored in storage tanks at port
facilities, and then transported to refinery by rail. Slaked
Lime is used for causticization of the caustic digestion
liquor, and also for coating the filter media, shall be obtained
from nearby external source or from Madhya Pradesh and
Rajasthan. Coal required for steam & power generation at the
co-generation plant of additional capacity of 1 MTPA alumina
refinery, is proposed to be obtained from Talcher & IB Valley
coalfields of Western Odisha through linkage arrangement
and also by e-auction procurement. Coal will be transported
by rail up to the alumina refinery. Fuel oil required for
calciners will be purchased from any one of the existing
refineries at Visakhapatnam and will be transported by rail
to the refinery site.
9. The production programme will be as follows:
Facility Production
Alumina refinery 1 MTPA
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
Executive summary (cont’d)
- 4 -
M. N. DASTUR & COMPANY (P) LTD
The major units of the alumina refinery will comprise the
following:
- Bauxite storage and handling system
- Grinding unit
- Pre-desilication unit
- Digestion unit
- Settler and washer unit
- Causticisation unit
- Security filtration unit
- Precipitation unit
- Hydrate classification and seed filtration unit
- Calcination and product filtration unit
- Alumina handling unit
- Caustic, acid, floculant & fuel oil storage and handling unit
- Compressor house
- Evaporation unit
- Raw water intake
- Cooling towers
- Co-Generation Plant
- Coal Handling System
- Electrical systems and power distributions
- Water supply systems
Bauxite will be sourced from NALCO’s captive mine located
at Panchpatmali. Annual requirement of bauxite for
production of 1 MTPA alumina is about 3.20 tons. Capacity
expansion in mine is also envisaged for additional production
of 3.20 MTPA bauxite.
This Pre-Feasibility Report describes proposed 5th stream
alumina refinery expansion project only. Necessary details
pertaining to mining expansion project at Panchpatmali will
be presented in a separate Pre Feasibility Report.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
Executive summary (cont’d)
- 5 -
M. N. DASTUR & COMPANY (P) LTD
10. The estimated power requirement of the refinery with
cogeneration power plant auxiliaries is given below:
5th Stream
Annual energy consumption, kWh x 106 316 Average demand, MW 43 15-min. maximum demand, MW 41 1-min. peak demand, MW 44
Power requirement will be met from co-generation power plant as well as the power supply received from Grid through wheeling arrangement from Nalco Captive power Plant at Angul.
11. The total make up water requirement for refinery and power
plant will be 572 cu m/hr and will be sourced from Kerandi
River or back water of upper Kolab reservoir or Muran river,
Koraput District.
12. Fuel oil will be required for calciner and start-up of co-
generation power plant.
13. The auxiliary facilities required for the proposed plant include
air compressors, laboratory and administrative buildings at
their respective locations.
14. The proposed refinery will generate pollutants such as fugitive
dusts, emission from boiler & calciner, ash, red mud, etc. The
required red mud storage/disposal pond and other pollution
control measures for the proposed refinery including the
cogeneration plant will be designed to achieve the desired level
of cleanliness without affecting the plant productivity and
operational economics of the plants.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
Executive summary (cont’d)
- 6 -
M. N. DASTUR & COMPANY (P) LTD
15. Implementation of various major activities has been
scheduled in a progressive manner in order to ensure
integrated execution of the project. Commissioning schedule
for Alumina refinery would be 48 months from the ‘Go-
Ahead’. It is estimated that the total manpower
requirement for 5th stream alumina refinery different
facilities will be about 462 persons.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
1-1
M. N. DASTUR & COMPANY (P) LTD
1 - INTRODUCTION
Project proponent and identification of the project
National Aluminium Company Limited (NALCO), a
Government of India Enterprise and a Navaratna Company, owns
and operates a large integrated Mines-Alumina-Aluminium
Complex in India. It has multi-location operations as follows:
- Mines and Alumina Refinery, Damanjodi, Dist: Koraput,
Odisha - Aluminium Smelter & Captive Power Plant, Dist: Angul,
Odisha - Port Handling Facilities, Visakhapatnam, Andhra Pradesh
(for alumina export and caustic soda import)
The Greenfield Alumina-Aluminium Complex was set up with
an initial installed capacity of 0.8 million tons per annum (MTPA)
of alumina and 0.230 MTPA of metal. The refinery was based on
bauxite from Panchpatmalli bauxite deposits; the smelter and a
coal-based captive power plant were located in Angul. The project
was started up in 1987 with technology supplied by Aluminium
Pechiney, France (now Rio Tinto Alcan). The 1st Phase expansion of
the integrated complex was started in 1997 which included
capacity augmentation of the two alumina plant streams, and
addition of another line for the refinery as well as the smelter. The
implementation of 2nd Phase expansion of the integrated complex
started in October 2004. The 2nd phase included addition of
another line(4th) in the refinery as well as smelter, and is now
operational.
Further, capacities of Bauxite Mines and 4th Stream of
Alumina Refinery have been augmented through de-bottlenecking.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
1 – Introduction (cont’d)
1-2
M. N. DASTUR & COMPANY (P) LTD
The refinery also includes steam & power plants (SSP) with
capacities of 4 x 200 and 1 x 250 tons/hr of steam generation, and
4 x 18.5 MW expansion - back pressure turbines for co-generation
of power. Another backpressure turbine (5th one) is being added in
the existing SPP.
As a part of the future expansion programme (3rd Phase
expansion), NALCO is planning expansion by addition of 5th
Stream in its Alumina Refinery at Damanjodi based on
Panchpatmali Bauxite Deposits.
Brief description of the nature of the project
The capacity of the proposed stream would be one 1.0 MTPA
and processing technology would be based on medium pressure
digestion system. There would also be expansion in the mining
capacity of Panchpatmali mines by 3.2 MTPA after capacity
upgradation and M&R activities. A new overland land bauxite
conveying system is proposed to transport bauxite from central
block- sector-II and South block to proposed 5th stream in alumina
refinery.
This Pre-Feasibility Report (PFR) is based on bauxite supply
from Panchpatmali Mines and state-of-the-art process technology
of Rio Tinto Alcan International Ltd (RTAIL) for alumina production
at medium pressure (MP) digestion. The stream capacity is much
higher than any of the existing ones at Damanjodi as it is based on
the recent advancement in alumina technology as well as
equipment sizing.
Need for the project
The most commercially mined aluminium ore is bauxite, as it
has the highest content of the base metal. India has the fifth
largest bauxite reserves with deposits of about 3 billion tonnes or
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
1 – Introduction (cont’d)
1-3
M. N. DASTUR & COMPANY (P) LTD
5% of world deposits. India’s share in world aluminium capacity
rests at about 3%. Production of 1 tonne of aluminium requires
2 tonnes of alumina while production of 1 tonne of alumina
requires about 2.5 to 3.5 tonnes of bauxite. The principal user
segment in India for aluminium continues to be electrical and
power distribution sector followed by the automotive and
transportation, building and construction, packaging, consumer
durables, industrial and other applications including defence.
India with its abundant supply of quality bauxite and low
cost labour has established itself as a low cost producer of primary
aluminium As per demand supply analysis of alumina, the
domestic as well as global scenario strongly favour creation of new
capacities in alumina. In this background, NALCO has a uniquely
advantageous position on account of the following factors:
- Currently NALCO sells part of its alumina produced within
India and exports the remaining quantity. NALCO exported nearly 0.94 MT, 1.30MT and 1.18 MT of alumina in the year of 2012-2013, 2013-2014 and 2014-2015 respectively. This establishes a clear opportunity for NALCO to export additional 1 MT of Alumina globally from 2015 onwards.
- There is a huge shortfall in China and GCC countries. There
is presently no operating refinery in GCC countries. The one being built in Saudi Arabia would be captive to the smelter and the second being planned in UAE is in initial stage of implementation. NALCO is favourably placed to export their surplus alumina to these countries apart from USA and Russia nearby.
- NALCO being a consistent exporter of alumina for more than
two decades has earned the impeccable reputation of product quality and alumina supply commitments in international markets. NALCO therefore has the capability to market higher quantum of alumina in domestic as well as international market.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
1 – Introduction (cont’d)
1-4
M. N. DASTUR & COMPANY (P) LTD
- NALCO is one of the low cost producers of alumina in the
world owing to having access to bauxite deposits with a low landed cost at the plant. Consequently, it has a far greater capability to complete with other alumina producers in the domestic as well as international market even if there is a surplus of alumina in the market.
In view of above, the project comes up as the need of the
hour and its marketability is quite assured.
Demand-supply gap
The projected availability of alumina in domestic market
beyond 2015-16 is estimated at about 8 MT based on the
assumption that the alumina refineries that are currently under
initial stages of planning will also materialise and start production
by the projected dates. The alumina demand is projected to be
about 13 MT & 25 Mt in the years 2020-21 & 2025-26 respectively.
Based on the demand availability scenario of alumina, the
anticipated shortfalls in the domestic market have been estimated
below:
2015-16 2020-21 2025-26 A. Demand .. 6 13 25 B. Availability .. 8 11 14 C. Likely import .. 0.4 0.8 1 D. Shortfall (A-B-C) .. (-) 2.4 1.2 10
From the above it is seen that there is surplus alumina
supply in India till 2015-16 which gradually reduce and generates
a shortfall in 2025-26.
In terms of global scenario, the anticipated shortfall of
alumina in global market ranges from 2-10 MT through years 2015,
2020 and 2025.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
1 – Introduction (cont’d)
1-5
M. N. DASTUR & COMPANY (P) LTD
Import vs. indigenous production and export possibility
The production of Alumina in India is presently around 4.8
MT. In addition, a number of alumina refineries are reported to be
in various stages of implementation. Besides, expansion of some
plants has also been undertaken. The total alumina production is
likely to be around 10.8 MT in the year 2020-21 following the
completion of the proposed expansion and implementation of new
units.
India is currently importing and also exporting alumina.
However, export of alumina from India has been much more than
import, and India exported alumina mainly to China, GCC
countries, Romania and Egypt in recent years whereas Australia is
the major importing country, as presented below:
2008-09 2009-10 2010-11
Import of India 212.6 337.1 534.1
Export of India 968.2 702.8 681.9
Domestic/Export markets
Consumption growth of aluminium over the last 5 years has
been about 11 per cent. According to projections made by NALCO
and Mckinsey & Co, CAGR of demand for aluminium in India will
be 13-15 per cent from 2012 to 2022, and 9-11 per cent from 2010
to 2015 respectively. Demand for alumina is mainly driven by
primary aluminium. At present the per capita aluminium
consumption in India is very low at 1.3 kg and is expected to
increase subsequently. Considering the growth rate of alumina to
be same as growth rate of aluminium and considering
Source: Various issues of Indian Mineral Yearbook
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
1 – Introduction (cont’d)
1-6
M. N. DASTUR & COMPANY (P) LTD
past consumption of alumina, the likely domestic demand for
alumina in the years 2015-16, 2020-21 and 2025-26 could be as
given below:
Year Alumina demand
mill. tons
2015-16 6 2020-21 13 2025-26 25
Currently sectoral consumption of aluminium in India is
given below:
Sector Share %
Packaging 4 Construction 13 Transportation 15 Electrical & power distribution
48
Industrial machinery 7 Consumer durables 7 Others 6
Total 100 Source: AAI National directory of aluminium industry 2010.
Indian architects are gradually using more aluminium for
decor and style. Rising per capita income, demand of smaller
houses, easy access to credit, rural housing schemes run by state
governments are key growth factors in India. These factors would
result in healthy growth in both urban and rural construction
areas till the year 2020, and well beyond. Besides, a huge
investment is planned for the infrastructure development of the
country in the 12th five year plan. There would be large scale
investments to tackle energy shortages, which would involve
the use of aluminium for power transmission lines, while the
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
1 – Introduction (cont’d)
1-7
M. N. DASTUR & COMPANY (P) LTD
government’s tax breaks for wind-farm projects and renewable
energy sources would boost demand for aluminium for use in the
production of wind turbines. As per the 11th and 12th plans there
would be a total consumption of about 4 million tons of aluminium
in the power sector by the year 2020. Besides, there is a possibility
of increase in demand once the country having signed the
international civil nuclear co-operation deal starts building nuclear
power plants. The developed countries have on an average 140 kg
of aluminum per vehicle, while India is at 40 kg levels. First
aluminium can body manufacturing facility - Can Pack of Poland
came into operation in India in July 2009. Can is a major
consumption form of aluminium, and is expected to contribute to
aluminium growth in India in a big way. Accordingly, the average
growth rate of aluminium demand works out to be 12 per cent.
On analysis of global market it was observed that the future
world demand for alumina will be primarily driven by production of
primary aluminium. It was also observed that world consumption
of primary aluminium had almost doubled between 2002 and 2011.
According to recent projections by CARE Research, demand growth
for primary aluminium for 2010-2015 would be 5.3 per cent.
Considering this projection, past trend in consumption of
aluminium and prevalent global economic turmoil due to financial
crisis of Europe, the likely world demand for primary aluminium in
the years 2015, 2020 and 2025 could be 51, 65 & 72 MT
respectively. The likely availability of primary aluminium in the
years 2015, 2020 and 2025 is estimated to be 50, 55 & 56 MT
respectively.
The likely demand for alumina considering the requirement
for production of primary aluminium, as well as the demand for
other end-uses, could be as given below:
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
1 – Introduction (cont’d)
1-8
M. N. DASTUR & COMPANY (P) LTD
Alumina, mill. Tons
Year For
aluminium(1) For other end-uses(2) Total
2015 101 5 106 2020 120 5 125 2025 129 6 135
NOTES: (1) At 2 tons alumina per ton of aluminium. (2) At 4.5 per cent of alumina for aluminium production.
Employment generation due to the project
It is estimated that the total direct employment generation
from the 5th Stream expansion project will be about 462. In
addition to this, mining expansion project will also generate
number of direct employment and manpower requirement of mining
expansion project is presented separately in the pre feasibility
report for mine.
The 5th stream Alumina Refinery will be headed by a Deputy
General Manager (DGM) and he will report to the existing GM
(Refinery) of NALCO. As the 5th stream refinery is an expansion in
the existing Refinery so it is presumed that the existing corporate
administrative service will be available for necessary help so only a
skeleton administrative service is considered for this expansion.
The new DGM who will be the in-charge of the new expansion unit
and will report to the existing General Manager who is the full-time
Chief Executive of the total Plant. The DGM will be responsible for
the new units operations including planning, production,
maintenance and services, quality, safety & environment).
The DGM will be assisted by senior managers for production
and for maintenance and services. The quality control and Lab will
be headed by a Metallurgist and will directly report to the DGM.
The summary of manpower is given below:
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
1 – Introduction (cont’d)
1-9
M. N. DASTUR & COMPANY (P) LTD
Admin dept M E S HSK SK SSK O Total on pay roll
Refinery
Administration 5 10 10 25
Works management 4 6 6 10 8 7 2 43
Maintenance & services
4 28 21 25 48 22 4 152
Production 5 38 30 26 95 45 3 242
Total 18 82 67 61 151 74 9 462
(M–Management staff , E–Engineers and officers, S–Supervisory staff HSK– Highly skilled staff, SK–Skilled staff, SSK– Semi skilled staff O–Office staff)
Authorisation
National Aluminium Company Limited (NALCO) vide its
Letter Reference No. P&T/CONT/61 dated 9th February 2015
commissioned M. N. Dastur & Company (P) Ltd, Consulting
Engineers, Kolkata to prepare a Pre-Feasibility Report on
5th stream alumina refinery expansion project.
Acknowledgement
CONSULTING ENGINEERS gratefully acknowledge the
co-operation and assistance extended by NALCO in preparation of
this Pre-Feasibility report.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2-1
M. N. DASTUR & COMPANY (P) LTD
2 - PROJECT DESCRIPTION
This Chapter gives an elaborate description of the
installation of 5 th stream in the Alumina Refinery along with its
auxiliaries and necessary enablers.
TYPE OF PROJECT INCLUDING INTERLINKED PROJECT
NALCO is planning 3rd phase expansion by addition of 5th
Stream in its Alumina Refinery with proposed capacity of 1.0 MTPA
at Damanjod, Odisha. There will also be expansion in the mining
capacity of Panchpatmali mines by 3.20 MTPA after capacity
upgradation and M&R activities. A new overland land bauxite
conveying system is also proposed to transport bauxite from
central block- sector-II and south block mining lease to proposed
5th stream in alumina refinery.
LOCATION
NALCO intends to set up 5th stream in Alumina Refinery
within existing plant of NALCO. NALCO Refinery is located at
Damanjodi in Koraput District of Odisha State, India. The tentative
co-ordinate of the existing plant is 18°46'20"N/82°55'1"E. The
location of the plant is shown in Fig. 2B-1 on the next page.
DETAILS OF ALTERNATIVE SITE CONSIDERED
This proposed project is a part of 3rd Phase expansion plan of
NALCO that includes expansion of 1.0 MTPA Alumina production
by introducing a 5th stream in its Alumina Refinery. This expansion
project is sited within the existing plant of NALCO at Damanjodi,
Odisha and no other alternate sites have been considered. Total
area of the existing plant is around 615 acres out of which,
approximately 62 acres will be utilised for 5th stream expansion.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-2
M. N. DASTUR & COMPANY (P) LTD
LAYOUT
For the refinery, all the new facilities have been proposed to
be installed within the existing land limit of NALCO. Though in
order to accommodate some of the proposed units, the existing
boundary wall of works needs to be modified at different locations.
Plant general layout of Damanjodi alumina refinery 11253-B-02-
0001, showing the proposed facilities is enclosed with this report.
FIG. 2B-1 : SITE LOCATION MAP
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-3
M. N. DASTUR & COMPANY (P) LTD
MAGNITUDE OF OPERATION
Addition of 5th stream in alumina refinery will increase the
alumina production capacity by 1 MTPA. The annual requirement
of bauxite for production of 1 million tons of alumina will be about
3.2 million tons. Mining activity at Central Block Sector-II & south
block of Panchpatmali bauxite mine (Captive mine of NALCO) will
have to be geared for this scale of operation.
PROJECT DESCRIPTION WITH PROCESS DETAILS
The process technology for 5th Stream is based on medium
pressure digestion of bauxite from Panchpatmali mines. This
enables complete digestion of gibbsite at reduced residence time
and higher liquor RP (Al2O3/Na2O ratio), though at a higher
digestion temperature when compared with atmospheric pressure
digestion.
A block flow diagram of alumina refining process is placed as
Drawing 11253-B-02-0002 that reflects the various processing
steps adopted. The flow sheet is similar to the one for existing
plant, except that medium pressure digestion process has been
recommended rather than atmospheric pressure digestion. A
schematic representation of the Refinery is furnished in
Appendix 2B-1.
Basis of design
The basis of design for Stream-5 is the Process Package
received from Rio Tinto Alcan International Ltd. (RTAIL), who has
also been associated with NALCO expansions under Phase-I and
Phase-II, besides the Greenfield plant itself. This technology is
being followed in almost all the plants worldwide that are based on
use of gibbsitic bauxite. As the medium pressure digestion
technology has now been offered by RTAIL to achieve 1 mtpa
production rate from a single stream at much higher liquor
productivity, it has become quite attractive to adopt at NALCO.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-4
M. N. DASTUR & COMPANY (P) LTD
The bauxite grade considered is as given in Table 2B-1.
TABLE 2B-1 - BAUXITE GRADE
Al2O3 Total .. 45.20 % ATH .. 40.4 % SiO2 Total .. 2.70 % SiO2 Reactive .. 1.96 % Fe2O3 Total .. 24.40 % CaO .. 0.05 % C Mineral .. 0.024 % C Organic .. 0.065 % C Total .. 0.089 % S Total .. 0.021 % TiO2 .. 2.22 % P2O5 .. 0.065 % LOI .. 25.0 %
As the medium pressure digestion process may lead to higher
build up of impurities, the plant design has considered that the
liquor of this stream will not be mixed with the existing streams.
Based on operating experience, NALCO may decide to mix these in
future. However, due to relatively clean Panchpatmali bauxites, the
liquor impurities are expected to remain close to existing levels in
spite of medium pressure digestion.
The precipitation process will be based on the Rio Tinto
Alcan/AP Sursat process comprising high concentration solids
precipitation that is currently in application at the NALCO
Damanjodi refinery. This will provide the highest possible liquor
productivity (yield) in conjunction with digestion at 145OC.
International quality standards are envisaged for alumina
produced such that the product alumina can be exported to
consumers worldwide. The quality parameters considered are as
given below in Table 2B-2.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-5
M. N. DASTUR & COMPANY (P) LTD
TABLE 2B-2 - QUALITY PARAMETERS
Loss On Ignition 300 - 1000°C .. 0.5% - 1.0% Bulk Density (t/m3) .. 0.90 - 1.05 Particle Size Distribution +125 µm .. 15% max - 45 µm .. 8.0% - 10.0% max BET Surface Area .. 55 to 80 sq m/g Soda Content (w/w %) .. 0.32 - 0.42 Soluble Soda Content .. <5% of total soda
The latest equipment design and sizes have been considered
so as to minimize the operation and maintenance requirement.
Technological details
Bauxite handling and secondary crushing: Bauxite from
Panchpatmali deposit will be brought to the new bauxite storage
area (adjacent to the existing one) of the refinery by overland
conveyor. It is proposed to provide independent bauxite storage
facility such that normally Panchpatmali bauxite can be fed to
Line-5. Two additional stock piles are considered for 5th stream.
Combined capacity of the two stock piles considered will be about
360,000 tons. The bauxite to Line-5 will be separately handled and
secondary-crushed in a manner similar to the existing plant, and
no significant change is envisaged. The product size envisaged is
100 per cent passing 30 mm.
Bauxite grinding: The crushed bauxite will be ground in
open circuit ball mills to a product size of:
- P100 of approximately 1,700 µm - P95 of approximately 600 µm - P80 of approximately 250 - 300 µm
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-6
M. N. DASTUR & COMPANY (P) LTD
The green liquor from evaporation is extracted (at about
103 0C), from a suitable stage of digestion area heaters, as feed to
grinding mill. The ground product is maintained at very high
solids concentration (about 1000 g/L) for improved performance of
pre-desilication, and reduced steam injection into the first digester.
Milk of lime is added at the mill feed end at a rate of about 0.3 per
cent CaO on dry bauxite for phosphorous control in process liquor.
Two ball mills (1 working + 1 standby) are proposed for this
expansion project
Pre-desilication: Reactive silica (kaolinite) from bauxite goes
into solution when it comes in contact with caustic soda. It re-
precipitates in various stages of the Bayer process at lower caustic
concentration, high residence time or at elevated temperature.
The purpose of providing desilication is to react and
precipitate a significant proportion of the soluble silica prior to
digestion. This is performed by heating up the mill slurry to an
optimum desilication temperature (102oC) with steam injection,
and then providing residence time for the silica precipitation
reaction in agitated tanks.
Desilication step may be carried out in the slurry prior to
digestion (called pre-desilication), or after digestion (and dilution -
called post-desilication), or both, as is being practiced in the other
4 lines at Damanjodi. Pre-desilication is preferred because of the
following reasons:
- Silica scales during digestion are drastically reduced,
which is very critical for medium and high pressure digestion.
- Auto precipitation of hydrate (that occurs significantly
in post-desilication) does not take place if post desilication is avoided.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-7
M. N. DASTUR & COMPANY (P) LTD
- Sand separation step, that was required for protecting
the post-desilication tank agitators, can be avoided.
Post desilication will occur in digesters during the digestion
step at medium or higher temperature digestion.
For Line-5 there will be provision for direct heating of
bauxite slurry in injection heaters before entering pre-desilication
tanks as in the existing plant. The heated slurry will be sent to the
first online pre-desilication tank.
Digestion: The aim of Digestion is to react the bauxite ore
with caustic liquor at the prescribed temperature to achieve the
required extraction of gibbsitic alumina and to reduce silica
concentration in the process liquor to within acceptable level.
Full utilization of bauxite resources is dependent on the
efficiency of digestion. The most important parameters for
digestion are:
- Digestion temperature - Residence time - Caustic concentration - RP (Al2O3/Na2O) of liquor after digestion - Silica concentration in liquor after digestion
A dual stream digestion process has been proposed in which
green liquor is heated independently with the recovered process
flash vapour (regenerative steam) and finally by live steam in
heaters; and the desilicated bauxite slurry is mixed with the hot
liquor at entry to the first digester. Sparge steam may also be
required to be added in the first online digester in order to attain
the required slurry temperature (145 0C). Sufficient residence time
(about 1.3 - 1.5 hours) is allowed for gibbsite extraction and
adequate desilication of the resulting slurry.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-8
M. N. DASTUR & COMPANY (P) LTD
Flash vessels are used to gradually reduce the slurry
pressure to atmospheric and concurrently remove water, enabling
heat recovery to the green liquor. Water is removed in the form of
flash vapour from each flash stage.
Slurry from last flash tank passes into the Blow-Off Tank
where dilution liquor (first washer overflow) is added. Flashing, if
any, is transferred to the Relief Tank as also from the pressure
relief lines of pressure safety valves in this area.
The flash condensate from heaters is pumped to the process
condensate tank in the Tank Farm; and the MP live condensate is
flashed to the LP condensate pressure after which it is pumped to
the power plant for recycle. The green liquor caustic concentration
has been specified at approximately 190 g/L.
The digestion parameters are carefully chosen so as to
minimize boehmite and gibbsite reversion. The impurities present
in bauxite also dissolve in the liquor to various degrees during
digestion; notable being organics, vanadium, phosphate, etc. The
solids residue after digestion (red mud) contains alumina in forms
that cannot be extracted at the adopted digestion parameters.
Acid cleaning provision is made for all heaters in this area.
As such, a new Acid Cleaning area has been added for Line-5 to
facilitate cleaning of equipment in Digestion and other areas. The
diluted and passivated acid will be pumped from Acid Cleaning
area, passed through the digestion heater tubes as required and
returned to Acid Preparation. In this manner the acid will be
circulated through digestion heaters for cleaning.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-9
M. N. DASTUR & COMPANY (P) LTD
Red mud settling: The objective of Settling Area is to
separate the red mud solids from aluminate liquor, and to have
minimal suspended solids in the overflow.
The separation of red mud from the liquor will be done in Rio
Tinto Alcan’s (RTA’s) proprietary high rate decanter (HRD). It is a
high performance thickener where very high settling rates as well
as high underflow solids concentration are achieved with the help
of modern synthetic flocculants. The unit size and residence time
being much shorter than conventional decanters, the temperature
drop and resulting alumina hydrolysis loss is significantly reduced.
The overflow liquor from HRDs, 765 cu m/h/decanter at
103OC and containing approximately 150-200 mg/L of suspended
solids will gravity fed a settler overflow tank from where it will be
transferred by pump to Security Filtration area.
A part of HRD Overflow is used for preparation of tri calcium
aluminate (TCA) with milk of lime such that the resultant solids
concentration is 40 g/L with a residence time of about 2 hours at
100OC. The TCA slurry is continuously dosed into HRD Overflow
being pumped to Diastar filters so as to maintain 2.9 g/L solids in
the feed to filters. The TCA forms a porous coating of coarse solids
on the filter leaves of the security filters. This coating enhances
the operating cycle of filter by preventing blinding of filter cloth.
Each HRD will be de-scaled at approximately 3 months
intervals. The HRD’s will be cleaned by caustic cleaning/hydro
blasting.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-10
M. N. DASTUR & COMPANY (P) LTD
The selection of flocculants is very important for the
optimum performance of HRDs. The selection is made by carrying
out tests with various flocculants on the red mud slurry at varying
dosage rates. Two types of flocculants (identified as ‘A’ and ‘B’) will
be used for decanters. The flocculant solutions will be prepared in
accordance with recommendations of the supplier and RTAIL; and
fed to HRDs as required in the feedpipe and feed-well.
Red mud washing and mud disposal: The aim of mud
washing is to recover the valuable soda from the HRD Underflow
stream such that net soluble soda losses are approximately equal
to 10 kg Na2O/t alumina, and the washed mud will be thick
enough for stacking in the mud disposal area.
Mud thickening and washing are carried out in Deep Cone
Washers (DCW) operating in a series of counter-current stages.
While the main objective of HRD was to minimize solids suspended
with the overflow, and the underflow solids concentration was a
minor objective; the main objective of DCW is to achieve high
underflow solids concentration. As a result of high underflow
solids concentration, the requirement of wash stages to achieve the
same degree of soda loss, everything else being unchanged, is
much reduced with the installation of DCWs (RTA proprietary
design). Five wash stages have been proposed with a view to limit
the soda loss to within 10 kg Na2O/t alumina.
The underflow mud from HRD is continuously transferred
from the first stage washer towards the last stage; while water is
added to the last wash stage, and is continuously transferred
towards the first one – thus ensuring counter current washing.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-11
M. N. DASTUR & COMPANY (P) LTD
The mud exiting the last washer will be transferred by
positive displacement pumps at 1,000 g/L solids concentration and
14 g/L caustic and stacked in the existing red mud disposal area.
This area also provides liquor for causticization in order to
maintain liquor causticity of Bayer circuit.
Flocculant preparation: A common facility will be provided
for preparation of secondary flocculant as per recommendation of
flocculant supplier as well as RTAIL, the supplier of HRDs and
DCWs to their proprietary design.
It has been proposed to use three types of flocculants – - Flocculants A and B for HRDs, and - Flocculants B and C for DCWs The flocculent preparation facility will include handling of
liquid Neat Flocculant containers, facility for primary and
secondary dilution and the requisite pumps for uninterrupted
supply of any of the recommended flocculent to each HRD and
DCW.
Primary dilution of flocculent will be done in alkaline media,
for which fresh caustic will need to be added to each batch of
flocculant.
Each HRD and DCW will be provided dedicated pumps for
the two types of flocculent - positive displacement, low shear
pumps that will minimize flocculant shearing. The pump speed
will be regulated by a VFD to eliminate the need of control valves.
The two types of flocculants for DCW (identified as ‘B’ and
‘C’) will be used depending upon the caustic concentrations
prevailing in DCWs.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-12
M. N. DASTUR & COMPANY (P) LTD
Liquor causticization: The carbonates and/or organics
from bauxite may get into the process liquor which may lead to
degradation of plant liquor and increase of carbonate content. The
objective of the liquor causticization area is to control the buildup
of inactive sodium salts - principally Na2CO3 in the liquor circuit,
which will otherwise reduce process efficiency if left to accumulate.
The plant is designed for a liquor causticity level of 88 per cent.
Causticization of plant liquor is carried out by reacting it
with milk of lime for conversion of sodium carbonate back into
sodium hydroxide. By adding adequate excess lime other liquor
impurities such as P2O5, V2O5, As2O5, TiO2, F etc. are also removed.
For optimum plant operation and liquor productivity,
causticity of plant liquor needs to be controlled through
causticization of a suitable DCW overflow with lime slurry at
prescribed temperature and residence time. The selection of DCW
liquor to be causticized and the feed rate are decided on the basis
of carbonate destruction required for maintaining the prescribed
causticity.
For Line 5, the suggested stream for liquor causticization is a
mixture of stabilization liquor and DCW 3/4 overflow liquor.
Causticization will be carried out at 95oC and residence time of
2.5 hours. After causticization the slurry will be fed to a thickener,
underflow of which will go to a DCW downstream (to DCW 4/5);
while the thickener overflow will be taken to an upstream DCW (to
DCW 2/3).
Security filtration: The objective of Security Filtration area
is to remove most of the red mud solids from HRD Overflow such
that the filtrate contains less than 20 mg/L suspended solids. If
not controlled, the product alumina will contain higher than
acceptable impurities.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-13
M. N. DASTUR & COMPANY (P) LTD
The HRD Overflow is to be carried out in pressure filters; the
existing NALCO Streams-1, 2 and 3 had adopted horizontal Kelly
filters. The more recent Diastar filters have been introduced in
Line-4, and the same are proposed for Line-5 as well. The benefit
of these filters lies in achieving higher specific filtration rates (up
to 1.2 cu m/sq m/h against 0.8 cu m/sq m/h achieved in Kelly
filter).
As these filters operate in closed cycle automatically, the
operator is exposed much less to hot caustic fumes. The wash
water consumption is also reduced since back-wash of filters is
done by filtered liquor itself.
A specific filtration rate of 1.17 cu m/sq m/h (max.) and
1.0 cu m/sq m/h (normal) has been considered for design. As
such, three operating and one spare filters of 460 sq m area each
have been considered adequate.
An aluminate liquor storage capacity equivalent to about
2 hours has been provided. This appears adequate in view of
additional storage provisions for spent and green liquors.
Heat interchange: The heat interchange devices/plate heat
exchangers (HID) will cool the aluminate liquor coming from
security filtration area to the temperature required by the
precipitation area. The heat removed will be used to heat the spent
liquor coming from white side on its way to the evaporation area
and to heat the washer overflow and stabilization liquor coming
from the DCW 3 en route to the causticization area.
The filtered aluminate liquor (AL) comes out of Security
Filtration at 1030C. This needs to be cooled to about 700C, and
cooling is achieved by exchanging heat with a mixture of DCW 3
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-14
M. N. DASTUR & COMPANY (P) LTD
overflow & stabilization liquor being sent for causticization, and
spent liquor (SPL) being sent to Evaporation. The Heat Interchange
Department (HID) provides a series of stainless steel plate heat
exchangers for exchanging heat of aluminate liquor first with
causticizer feed (DCW 3 overflow and stabilization liquor) to heat it
from 70oC to 96oC in the first stage coolers; and then with spent
liquor to heat it from 490C to 78-800C in the second stage coolers.
Due to high flow rate involved, the spent liquor heaters
require a large heat transfer area (about 920 sq m). As such,
2 stages of plate heat exchangers, each 460 sq m, have been
considered.
These plate heat exchangers will be periodically cleaned with
sulphuric and nitric acid for descaling on both sides.
Hydrate filtration: The seed slurry from precipitation area
will be filtered on large diameter vacuum disc filters. The coarse
seed cake will be slurried with previously cooled aluminate liquor
(AL). The aluminate liquor will be directed to the inclined portion
of cake discharge chutes so as to form a liquid film at its base.
This film will aid in sliding the filter cake into the seed tank. It is
proposed to feed the cake discharged from the 3 operating filters
into one operating seed tank.
The product hydrate slurry from hydrate classifying cyclones
is to be filtered on 1st Stage Product Filters for separation of spent
liquor from the coarse product. The product cake is to be slurried
with product wash filtrate and pumped to product filters.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-15
M. N. DASTUR & COMPANY (P) LTD
The spent liquor filtrate collected from various filters will be
used for dilutions as required, and for preparing caustic cleaning
liquor. The remaining liquor is to be hydro cycloned for removal of
residual solids (hydrate), that will otherwise reduce liquor
productivity, before being sent to plate heat exchangers..
It is preferable to use large diameter disc filters (44 sq m
discs) for seed filtration in order to minimize number of installed
filters; whereas smaller (20 sq m discs) for 1st Stage Product
Filters.
Precipitation: The Precipitation area is designed to achieve
a chemical yield (liquor productivity) of 92.6 g/L, which is essential
for achieving the rated production capacity. The precipitation
process will be based on the Rio Tinto Alcan/AP Sursat process
that is currently in application at the NALCO Damanjodi refinery.
The seed slurry will arrive at Precipitation area through three
pipelines, two of which will be in use at any time. Split flow of
seed slurry will be used such that discharge of one line is led into
the first online precipitator, and that of the other line into the
second one. Split flow will be used as a lever to reduce the hydrate
occluded soda content by reducing the super saturation level in the
first stage of precipitation.
Inter stage Coolers (Barriquand type) will be provided
alongside precipitation tanks 4, 5, 6, 7, 8, 9 and 10 to increase
liquor super-saturation and thus maintain high liquor productivity.
As the slurry proceeds through the precipitators, the hydrate seed
particles will be enlarged and strengthened by hydrate
precipitation. Typically, the slurry from the last on-line precipitator
will contain hydrate with 10 - 12 per cent -45 microns at ~900 g/L
solids.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-16
M. N. DASTUR & COMPANY (P) LTD
Slurry from third-last precipitator is to be pumped to the
classifying cyclones for separation of coarse product hydrate, while
the fine slurry will be returned to the second-last precipitator.
Slurry from the second-last precipitator is to be pumped to the
seed filters, while the last precipitator serves as buffer storage.
Hydrate classification: Classifying cyclones will be
provided for separation of coarse hydrate particles as product. The
cyclones are to be placed in two stages such that the coarse
underflow of the first stage is fed to the second one for obtaining a
close size range of the product underflow.
The first stage cyclone will receive slurry from the third-last
precipitator. As this slurry will be at about 900 g/L solids, it
needs to be diluted to 400 g/L by Spent Liquor (SPL) addition in
the feed pipe. The overflow of these cyclones is returned to the
second last precipitator, while the underflow will be fed to the
second stage cyclones after dilution.
The second stage cyclone overflow will also be returned to
the second last precipitator, while underflow (the product) is sent
to the 1st Stage Product Filter.
Hydro cyclones of 280 mm diameter are considered for both
the cyclone stages.
Second stage filtration: The second stage product filtration
area has been designed for the purposes as give below:
- Wash the hydrate filter cake such that the soluble soda content is less than 200 ppm Na2O on calcined alumina basis
- Produce a hydrate filter cake with a moisture content of
around 5.5 per cent which is suitable for feeding to calciner.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-17
M. N. DASTUR & COMPANY (P) LTD
The filter cake from 1st Stage Product Filter will be slurried
with the second stage wash filtrate; and pumped as feed to the
second stage product filters. 2nd Stage Product Filter has been
preferred over vacuum drum filters since higher solids loading (up
to 3 t/sq m/h) is possible due to horizontal bed, and a single 2nd
Stage Product Filter will be adequate for Line-5. Cake can be
effectively washed on the filter surface as 3 stage counter current
washing is possible.
The filter cake drops into a conveyor that takes it to the
calciner for stream 5, or, through reverse rotation of the conveyor,
to hydrate storage when feeding to calciner is stopped.
The filtrate and wash filtrates are collected separately and
the wash filtrate is sent to the 1st Stage Product Filter for cake re-
slurry. The remaining mixture of filtrates is added (as stabilization
liquor) to washer 3 overflow as causticizer feed after cycloning.
Calcination: A fluid bed calciner will be provided to work as
a dedicated calciner for Line-5. The washed product hydrate will
be fed to the calciner to get converted to alumina under operating
temperature of 1,000-1,100 0C maintained by combustion of
furnace oil.
The hydrate fed to calciner is expected not to exceed 7 per
cent moisture in order to minimize fuel consumption. Besides, the
calciner will be designed to limit particles breakage across the
equipment to 3 per cent. The product discharged by calciner will
be cooled to within 800C in order to protect the belt conveyors and
also to attain higher thermal efficiency. The electrostatic
precipitator associated with the calciner shall be provided with an
extra field such that permissible particulate emission levels are
achieved even with one field out of service.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-18
M. N. DASTUR & COMPANY (P) LTD
Alumina handling, storing and wagon loading: Alumina
handling and storage system will be augmented for handling of
additional 1 million tons alumina. The twin conveyors of
calcination plant for 5th Stream expansion will feed either of two
new conveyors. One of the new conveyors will be used for feeding
existing conveyor for onward transmission and despatch of
alumina through existing silos. The other new conveyor will be
used for feeding for onward transmission and despatch of alumina
through proposed two numbers new silos. Two (2) tracks below the
alumina silos for wagon loading and one full CSR track at the
north of the new silos for stabling the rake have been proposed at
the same level of the existing tracks. These tracks will be
connected with the ‘Holding Yard’.
The alumina powder will be transported from alumina plant
to the Visakhapatnam Port in special BTAP tank wagons, unloaded
and stored therein for subsequent despatch for loading into ships.
One (1) concrete silo (silo No. 4) of capacity 25000 tons is
envisaged at port facilities of NALCO at Visakhapatnam for storing
of alumina.
Evaporation: The objective of Evaporation area is to remove
sufficient water from the process liquor stream to maintain the
target caustic concentration of liquor to digestion, and to provide
sufficient liquor storage between the red and white sides of the
refinery to allow an adequate buffer for continuous operation of the
refinery.
A storage volume for spent liquor equivalent to about 3
hour’s residence time is provided in the area. Green liquor will
also be stored in this area for a residence time of 3.5 hours. There
being additional storage of spent liquor in the Hydrate Filtration
area, this provision is considered adequate buffer capacity for
uninterrupted plant operation.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-19
M. N. DASTUR & COMPANY (P) LTD
Long tube, falling film, counter current, sextuple effect
evaporator sets will be installed as in the existing plant. The
normal capacity of each unit will be 135 tph with 6 body, 6 effect
configuration as normal operation. However, in case higher
evaporation rates are required (e.g. due to exceptionally heavy
rainfall periods), it is possible to operate under varied conditions,
but by sacrificing steam economy. The same evaporator set will be
able to provide about 185 tph with 6 body, 5 effect configuration,
and 165 tph with 5 body, 5 effect configuration (in case one of the
bodies is bypassed for maintenance etc.).
The nominal evaporation load is 231 tph which means
normally both the units will be in operation. The caustic
concentration of feed liquor (spent liquor) is 153 g/L as Na2O,
while the concentrated liquor (Green Liquor) is required at 196 g/L.
The target steam economy with the normal 6 body, 6 effect
configuration is 3.6 t/t.
Condensate tank farm: The condensate storage area will be
designed to collect the process condensate from digestion and
evaporation areas; and its distribution to the appropriate users
around the refinery. This area will also have provision for receiving
the steam condensate that has been dumped by transmitters and
valves due to high conductivity in the steam condensate lines to
power plant.
Evaporation condensate being of better quality than
digestion condensate (due to absence of red mud carry over), will
be exclusively used for product wash and cooling towers make up.
The excess evaporation condensate (high quality or HQ condensate)
will overflow into the digestion pocess condensate tank where red
mud pond return water will be added to produce the required
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-20
M. N. DASTUR & COMPANY (P) LTD
amount of red mud wash water for feed to DCW 5. In the absence
of, or during shortage of HQ condensate fresh water may be used
for product wash, while use of red mud pond water will be
increased in the other red areas.
The residence time provided for HQ as well as process
condensates being 5 hours, disruptions in operation of the
operating units can be easily handled without wasting/overflow of
condensates.
Acid cleaning facility: The acid cleaning facility is designed
for circulating diluted acid, supplemented with an inhibitor and a
defoamer, across process units that are susceptible to scaling and
resulting in lowering of throughput. This generally happens in
plant areas heavily dependent on heat transfer such that the
surfaces get scaled e.g. in digestion (liquor heaters), HID (plate
heat exchangers), evaporation (calendria) etc.
A common facility is, therefore, provided for supplying the
acid of acceptable quality to the above areas whenever a fall in
performance is observed.
It is anticipated that annually about 1,000 tons of
concentrated sulphuric acid will be required. The acid will be
brought by road tankers and stored in a tank (70 cum capacity)
bounded within a dyked area. Also within the dyked area will be
one dilute acid tank (150 cum capacity) and spent acid tanks for
circulation and pump off of acid across the refinery areas and
disposal into mud pond area. A wash water tank is also provided
for pumping and storage of water for washing of the piping and
equipment.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-21
M. N. DASTUR & COMPANY (P) LTD
Laboratory
It is envisaged that with the addition of certain equipment,
the existing central laboratory will be able to meet the analysis and
testing requirement of additional sample load arising due to
capacity expansion.
Requirement of raw materials and probable sources
The annual requirement of major raw materials for 5th
Stream shall be approximately as tabulated in Table 2B-3.
TABLE 2B-3 - ANNUAL REQUIREMENT OF MAJOR RAW MATERIALS
Raw material Total tpa
Bauxite 3,200,000 Coal 629,000 Caustic soda 100,000 Lime 48,330 Flocculant 420 Fuel oil 80,000
Bauxite: Bauxite is the primary raw material subsequently
reduced to produce aluminium metal in aluminium smelter.
Bauxite is to be sourced central and north block mining lease and
south block mining lease of Panchpatmali bauxite deposit identified
by NALCO to feed the 5th Stream of alumina refinery at Damanjodi
for production of one million tons per annum of alumina.
Caustic soda: Caustic soda is used for digestion of bauxite
to effect separation of alumina. Caustic soda in the form of lye will
be received by ship at Visakhapatnam Port, stored in a storage
tank of 5000 cu m storage capacity at port facilities and then
transported to refinery by rail. The caustic required in the new
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-22
M. N. DASTUR & COMPANY (P) LTD
stream will be supplied by augmenting a new Caustic storage
system of adequate capacity. The caustic for the new stream will be
unloaded from the rail tankers and pumped to the augmented new
caustic tank of 4,000 cu m storage capacity.
Lime: Slaked Lime is used for re-causticisation of the caustic
digestion liquor and also for coating the filter media shall be
obtained from nearby source or from Madhya Pradesh and
Rajasthan. Storage provision is made for lime arriving by wagons in
bags. The lime bags will be emptied and transferred to the new silo
(600 cu m) and to the new slaker and classifier. The slaking is
done in water/process condensate at 7 TPH slaking capacity. The
slaked lime overflows into a tank from where it is pumped to the
ring header for process use. The grit from classifier is transferred
to tractor trailers and disposed off to red mud pond or land fill.
Coal: Coal is required for steam & power generation at the
co-generation plant of alumina refinery, is proposed to be obtained
from Talcher & IB Valley coalfields of Western Odisha. Coal will be
transported by rail upto the alumina refinery.
Heavy fuel oil (HFO): Fuel oil required for calciners will be
purchased from any one of the existing refineries at
Visakhapatnam and will be transported by rail to the refinery site.
The gross CV of the HFO will be about 10,000 Kcal/Kg. The Fuel oil
will be unloaded and stored in a new storage tank of 4000 KL
storage capacity.
Light diesel oil (LDO): Light diesel oil (LDO) will be used for
cold start-up of boiler, and heavy fuel oil (HFO) will be used for
load raising and flame stabilisation up to 40% of BMCR. The gross
CV of the HFO will be about 10,700 Kcal/Kg. The LDO will be
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-23
M. N. DASTUR & COMPANY (P) LTD
transported from the nearest source available to the refinery
through road and unloaded in a storage tank of 25 KL storage
capacity near the power plant.
Synthetic flocculants: Flocculants are used in the refinery
in the red mud settlers and washers as settling aid.
Power requirement
The estimated overall power requirements of the alumina
refinery are given in Table 2B-4.
TABLE 2B-4 - ESTIMATED POWER REQUIREMENTS FOR 5TH STREAM ALUMINA REFINERY
Annual energy consumption, kWh x 106 .. 316 Average demand, MW .. 43 15-min. maximum demand, MW .. 41 1-min. peak demand, MW .. 44
Source of power: The power requirements of 5th Stream
alumina refinery plant expansion will be met from two sources,
namely;
i) Co-generation plant power generation system ii) Power supply from GRID through wheeling arrangement
by 220/132 kV MRSS through two (2) nos. of 31.5/40MVA,220/33/11kV transformers.
To meet any exigency of total power failure, provision will be
made for local emergency diesel generator (DG) sets of required
capacity to ensure human safety and safeguard critical equipment
of various plant units. Emergency lighting power supply for these
plant units will also be taken from the DG sets. For other areas not
provided with DG sets, provision will be made for taking emergency
lighting power supply in the substations, control rooms, etc from
the control battery banks, where provided, or from the portable
emergency lighting units.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-24
M. N. DASTUR & COMPANY (P) LTD
Diesel powered silent type environment friendly generator
sets with auto mains failure and control panel of adequate capacity
shall be provided to take care of the back up power requirements
and long power outages including provision for at least 20% future
loading. Diesel engine driven pumps shall be provided for fire
hydrant pumping station as well. SEP (Static Emergency Power)
supply (AC) along with VLRA battery back up shall be provided for
feeding emergency lights. The emergency lighting system should
have LED based luminaries.
Instrumentation, Automation & Communication system for the 5th Stream of the alumina refinery
Centralized control & monitoring system will monitor and
control all significant variables in accordance with the process
requirements, provide all operating requirements and necessary
sequencing, interlocking and safety functions including alarms for
abnormal conditions. The automation system will be designed as
an integrated system for drives control and instrumentation of the
plant unit.
The 5 th stream of the plant is divided into various areas for
which automation systems will be suitably interfaced over data
bus, and the process status and conditions of each area can be
monitored by the operator of the other area, but controlling
facilities will be provided to the respective operators of the areas.
Operation of one area from the other area will not be provided.
For each of the above areas independent distributed control
systems (DCS) with redundant controllers will be considered along
with relevant system hardware and other peripheral devices. The
DCS considered will be connected to the existing plant automation
network over dual bus system. Protocol for the data exchange will
be decided at the time of engineering. All plant data/status will be
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-25
M. N. DASTUR & COMPANY (P) LTD
made available at the central main control room of the plant.
Consolidated storage facility for the process events/data will be
located at the main control room. The automation network will be
independent comprising of required numbers of network switches,
ethernet cables, optical fibre cables (single mode and multi mode
as required), optical link modules etc.
Signals for all electrical driven equipment will be hardwired
to the DCS from the HT/LT switchboard/MCC. The critical
feedback signals for the incoming feeder will also need to be
hooked up with the DCS.
HMI graphics will generally be in line with that followed in
the existing plant. Concept of spare shall be in line with the
existing philosophy, however shall be decided prior to
commencement of engineering.
The following communication systems are envisaged with
respect to the aluminum refinery:
- Plant telephone system - Plant wireless communication system - Plant loudspeaker intercommunication (LSIC) system
Fire detection and alarm system
The fire detection and alarm system will be intelligent,
microprocessor based, automatic addressable type and with self-
checking type network. The system shall be designed and installed
in accordance with NFPA, TAC & IS-2189 standards.
The system will comprise of fire alarm control panel (FACP)
with different of types of detectors & interfacing modules as per
requirement. Required numbers of hooters, strobe lights etc. will
be provided to warn people in case of emergency. The FDA system
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-26
M. N. DASTUR & COMPANY (P) LTD
will have necessary interfacing with different types of fire
protection/fighting systems and interlocking with HVAC system
using control modules. Required nos. of manual call points will
also be provided for initiating alarms manually in case of fire or
any other emergency.
The complete FDA system will be UPS powered and will
include a telephone auto dialer to notify concerned authorities
about a possible emergency situation. The FDA system will also be
provided with networking facilities over Ethernet TCP/IP to allow
monitoring of fire alarm system status from a FDA monitoring PC.
Independent FDA systems with monitoring facilities will be
provided for the various plant units/areas of the alumina refinery -
5th stream, co-generation power plant and infrastructure facilities
of the mines area.
Water supply system for alumina refinery
Water is required for alumina refinery as process water,
wash water, cooling medium in the heat transfer equipment etc.
The break-up of make-up water for various consumers in alumina
refinery is given in Table 2B-5 on the next page. The schematic
water balance diagram is shown in Drawing 11253-B-02-0003.
Estimated make up water requirement for alumina refinery and co
generation power plant is about 572 cu m/hr.
Source of water for the refinery and power plant will be from
Kerandi River, Muran River and back water of upper Kolab
reservoir, District Koraput. Application for necessary sanction from
the Water Resource Development Authority, Govt. of Odisha has
been submitted for allocation of 3 MGD water from Kerandi River.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-27
M. N. DASTUR & COMPANY (P) LTD
TABLE 2B-5 - MAKE-UP WATER REQUIREMENT FOR REFINERY (cu m/hr)
System Raw water
consumption
Recovered
water from
process
Reclaimed water
from existing/
proposed plant
Aluminium Refinery
Process water
requirement
300 389 -
Drinking and sanitation purpose
20 - -
Dust suppression for bauxite handling
- 19* 61
Total 320 408 61
The proposed intake water system for refinery and co
generation power plant is designed for pumping 580 cu m/hr river
water from Kerandi River, to the plant. Raw water reservoir to store
about 10 days requirement of water is envisaged inside the plant
boundary. The capacity of reservoir will be of 1,40,000 cu m. The
proposed reservoir will be interconnected to the existing raw water
reservoir. Existing Raw water treatment plant has a capacity of
1,700 cu m/hr (9 MGD). The existing system is adequate to cater
the demand of water for various consumers in the proposed
refinery and co-generation plant. The filtered water is stored in the
proposed filtered water storage tank in closed construction where
from it is pumped to various facilities.
Water is required as cooling medium in the evaporator,
precipitator and inter-stage coolers, wash water for mud washing/
hydrate washing and chemical preparation etc in the alumina
refinery plant. Estimated shop-wise break-up of the filtered
water/recovered water from the process in various amenities is
given in the following Table 2B-6.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-28
M. N. DASTUR & COMPANY (P) LTD
TABLE 2B-6 - TOTAL WATER CONSUMPTION
IN REFINERY UNITS
Water recovered from process Condensate Water
consumption Zone
Live steam
Evapo- ration
Digestion
Recovered
Pond Water
Filtered water Total
Mud wash - - 45 104 33 182
Hyd. Wash 8 69 - - - 77
CT make-up - 121 42 - - 163
Lime slaking - - - - 48 48
Flocculant preparation
-
-
-
- 35 35
Purge/gland ater - - - - 85 85
Hosing/others - - - - 99 99
Total 8 190 87 104 300 689
The following facilities will be envisaged to meet the refinery
water requirements:
- Re-circulating cooling water system of capacity 4,600 cu m/hr for evaporators and 6,400 cu m/hr for precipitators and inter-stage coolers.
- Fire hydrant system with dedicated fire water reservoir
complete with piping and hydrant accessories, fire sprinkler system and fire detection & alarm system.
- Pipe work pertaining to process, water, steam,
condensate, effluent, & red mud disposal. Re-circulating cooling water system: Re-circulating
cooling water system comprises of two separate closed cooling
water recirculation circuit with cooling tower and cooling water
pumps to serve equipment cooling in the following areas:
- Evaporators - Precipitators - Inter-stage coolers
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-29
M. N. DASTUR & COMPANY (P) LTD
Cooling tower: Cold water from the cooling tower basins
will be pumped by the recirculating cooling water pumps to the
evaporation unit, precipitators and inter-stage coolers unit in the
refinery.
The hot water return from the consumers will be returned to
the cooling tower for cooling and recirculation. The condensate
from the process will be added as make-up water to the cold water
sump to compensate the evaporation and drift losses.
Two submersible type dewatering pumps of 100 cu m/hr x
15 MWC each will be provided for dewatering the basin during
maintenance, one for each cooling tower.
Fire fighting water system: The filtered water from the
existing water treatment plant will be stored in a fire water sump
in closed construction which will be used for the fire fighting. The
fire fighting and protection system covers water hydrant system,
high/medium velocity spray system, fire detection alarm system,
fire extinguishers, etc.
Water system for co-generation power plant
The break-up of make-up water for various consumers in co-
generation plant is given in Table 2B-7. The schematic water
balance diagram is shown in Drawing 11253-B-02-0003.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-30
M. N. DASTUR & COMPANY (P) LTD
TABLE 2B-7 - MAKE-UP WATER REQUIREMENT FOR
POWER PLANT
(cu m/hr)
System Raw water
consumption
Recovered water from process
Reclaimed water from existing/ proposed
plant
Co-generation power plant make-up
Make-up water for cooling tower
137 - -
Demineralised water for Boiler make-up (Loss due to process steam supply and boiler blow down)
80 - 80
Ash handling system 35 13
(CT blow down)
-
Total 252 13 80
Recirculation cycle cooling water system is envisaged to cater
the cooling water requirements of dump condenser and cooling of
auxiliary equipment viz. lube oil coolers, generator air coolers,
gland steam condensers, boiler feed pumps, plant air compressors,
air-conditioning, ash handling system compressors, ash coolers
and sampling coolers etc.
De-mineralized (DM) water is used as make up water for the
boilers. The DM water requirement for the proposed boiler is about
80 cu m per hour considering the loss due to boiler blow down and
losses due to process steam supply in refinery plant. To meet the
above mentioned requirement, De-mineralization plant of capacity
2 x 75 cu m/hr has been proposed. The demineralised water will
be stored in the two (2) Nos. of DM water storage tank each of
capacity 900 cu m.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-31
M. N. DASTUR & COMPANY (P) LTD
The DM water from the DM water storage tanks will be
pumped by means of DM water transfer pumps to the boiler.
Necessary piping up to proposed boilers is envisaged. Proposed DM
water piping will be routed in the existing trestle and further
supports will be required upto proposed boiler.
Service water requirement will be met by using part of
cooling tower blow down water. A service water tank and service
water pumps will be provided for cleaning main plant area, fuel oil
tank farm etc.
Effluent treatment: The blow down from the cooling tower
will be utilised for green belt development, make-up for bottom ash
handling system, service water system and coal dust suppression
system in fuel storage area.
Run-off from coal handling area and coal piles generally
contains suspended solids. It is proposed to provide a peripheral
drain around coal yard and collected into a coal settling tank.
Decanted water from the settling tank shall be re-used for dust
suppression.
Service water effluent drains will be led to a sump which
will generally contain oily waste from the fuel oil area. Service
water will be passed through a tube settler for removal of
suspended solids. Treated service water will be sent to service
water tank for re-use.
Fire fighting water system
Fire protection system generally will be designed based on
tariff advisory committee (TAC)/loss prevention association (LPA)
guidelines and NFPA standards.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-32
M. N. DASTUR & COMPANY (P) LTD
For the purpose of system design, the co-generation power
plant is considered as ORDINARY HAZARD risk as per the
classification of TAC.
The various types of fire prevention/protection systems
considered for fighting the fires in different plant areas/buildings
are Fire hydrant system, Fire detection and spray system and Fire
detection and alarm system
Utility system
Fuel oil system: It is envisaged that HFO will be used as
fuel for calcination process in Alumina refinery and as start-up
fuel in boiler. The HFO oil storage system consists of unloading
pumps, HFO storage tanks, heating units, pumping units, pipe
work upto day oil tanks of the refinery and power plant.
Compressed air system: The total requirement of the
compressed air is 200 N cu m/min for 5th Stream. This
requirement is to be met by replacing the existing 3 x 55 N cu
m/min capacity reciprocating compressors with 3 x 120 N cu
m/min capacity water cooled centrifugal air compressors.
Two water cooled centrifugal air compressors each of
capacity 7,200 N cu m/hr are envisaged for meeting the
requirement of service air. One water cooled centrifugal air
compressor of capacity 7,200 N cu m/hr is envisaged for meeting
the requirement of instrument air.
Ventilation and air conditioning system: The ventilation
air quantity will be selected either to maintain room inside
temperature of 50C over outside ambient temperature or to have
fifteen air changes per hour in the ventilated areas, whichever is
higher. Cable cellars will be provided with suitable capacity of wall
mounted axial flow exhaust fans. The fresh air will be drawn by
means of wall mounted gravity louvers.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-33
M. N. DASTUR & COMPANY (P) LTD
Heat dissipated within the premises will be taken out by
properly designed air conditioning and air cooling systems to
achieve the specified room inside conditions. The areas where
controlled and specific rooms inside conditions are required to be
maintained, air conditioning and air cooling systems will be
provided at those areas. Floor mounted direct expansion (DX) type,
water cooled package AC unit based air conditioning system will be
provided for the centralized control rooms VFD, SAS room of all the
respective sub stations in order to maintain dry bulb temperature
of 23 ±2OC and relative humidity of 55 ±5%. Floor mounted direct
expansion [DX] type, water cooled package AC unit based air
cooling system will be provided for all the switchgear rooms/MCC
rooms and transformer rooms in order to maintain inside
condition of 32OC (DB) and RH not exceeding of 70 per cent. There
will be one standby unit for every two working units of 50 per cent
total capacity. Wall mounted, split air conditioning units will be
provided for permanently manned plant facilities such as
engineer’s room, conference rooms, staff rooms etc. in order to
maintain dry bulb temperature of 23 ±2OC. Split air conditioners
will be provided where stringent temperature and humidity control
is not required. These units are complete with evaporator,
condenser, fan, refrigerant piping, drain connection, electrics and
other accessories Refrigerant used in these units will be eco-
friendly.
Co-generation power plant
The process steam and power requirements of the existing
alumina refinery are met by the existing five boilers (4 x 200 TPH
and 1 x 250 TPH) and four turbo-generator each of 18.5 MW
capacity. The shortfall in power is drawn from the grid. As a part of
current expansion, one turbo-generator designated as TG-5 of 18.5
MW capacity is being installed.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-34
M. N. DASTUR & COMPANY (P) LTD
The power & process steam requirement of the proposed 5th
stream in alumina refinery will be shared by the above five TGs
and one proposed turbo-generator of 18.5 MW capacity which will
be designated as TG-6. The shortfall in power will be drawn from
power wheeled from NALCO’s power plant at Angul through the
grid.
The maximum MP and LP process steam requirement for the
proposed expansion is about 273 tph. Hence it is envisaged to
install one boiler of 300 tph capacity (including margin).
Based on the above, the following configuration of the power
plant has been envisaged:
- Boiler .. 1 x 300 TPH - Turbo-generator .. 1 x 18.5 MW
The boiler will be designed to fire 100 per cent Indian coal.
Coal is proposed to be obtained from Talcher or IB valley, Odisha
through linkage arrangement and also by e-auction procurement
Light diesel oil (LDO) will be used for cold start-up of boiler
and heavy fuel oil (HFO) will be used for load raising and flame
stabilisation up to 20 per cent of BMCR.
The capacity of the boiler considered for the proposed co
generation power plant will be about 300 tons/hr (including
margin). Considering that only coal will be used for the boiler, PC
fired boiler is recommended because of higher boiler efficiency,
lesser auxiliary power consumption and hence higher net send out
power compared to CFBC/AFBC Boiler.
It is envisaged to connect the superheater outlet of the
proposed boiler to the existing common main steam header. The
proposed TG-6 will also draw steam from this header. By adopting
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-35
M. N. DASTUR & COMPANY (P) LTD
this system, any boiler can supply steam to any operating TG’s
which enables the uninterrupted operation of all the TG’s even
when one of the boiler is taken for maintenance or for annual
statutory shutdown. The pressure and temperature of the common
main steam header is 68 ksca, 485OC. Considering the pressure
drop in the proposed main steam pipelines, the steam parameters
at the proposed boiler superheater outlet is selected as 70 ksca,
485OC.
Basically there are two types of turbo-generators, viz. back
pressure turbine and condensing turbine. NALCO has been
operating four identical back pressure turbo-generator each of 18.5
MW capacity to cater to the requirements of the existing Alumina
refinery. Currently one more identical back pressure TG of 18.5
MW capacity is being installed. Considering the requirement of
constant power generation and supply of process steam from the
proposed turbo-generator (TG-6), it is suggested that the turbo-
generator will be of condensing cum extraction type of 18.5 MW
capacity. Since, abundant quantity of water is available near to the
site, water cooled condenser is considered.
Power plant performance indices: The performance indices
of the proposed co-generation power plant are shown in
Table 2B-8 on the next page.
Proposed power plant cycle: The existing common main
steam header pressure and temperature are maintained at 68 ksca
and 485 ±50C. The outlet of the proposed boiler will be connected
to the existing common main steam header. So, the steam
parameter at the proposed boiler MSSV outlet is selected to suit
the existing header pressure and temperature.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-36
M. N. DASTUR & COMPANY (P) LTD
TABLE 2B-8 - POWER PLANT PERFORMANCE INDICES
Plant capacity, MW .. 18.5 Annual rated power generation capability, .. 162 million units/annum Annual gross power generation, million .. 145.85 units/annum (@ 90% load factor) Annual auxiliary power consumption, .. 74.46 million units/annum Net power available for alumina refinery, .. 71.39 million units/annum Annual steam generation, million .. 2.36 tons/annum Annual process steam consumption, million tons/annum - Medium pressure process steam .. 0.66 - Low pressure process steam .. 1.40
The proposed one (1) condensing cum extraction turbine
(TG-6) of 18.5 MW capacity will draw steam from the existing
common main steam header.
The proposed TG will also have two controlled extractions
similar to the existing TG’s, one for supplying medium pressure
(MP) and the 2nd for supplying low pressure (LP) process steam.
The 1st controlled extraction will be connected to the existing
common MP process steam header after desuperheating and the 2nd
one to existing common LP process steam header after
desuperheating.
Process return condensate and DM make up water will be
added to one (1) No. make-up water deaerator. The operating
pressure/temperature of make-up water deaerator will be
4.5 ksca/147OC and the operating pressure/temperature of Feed
water deaerator shall be 6 ksca/160OC.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-37
M. N. DASTUR & COMPANY (P) LTD
During start up and normal operation, steam required for the
make-up water deaerators and feed water deaerators will be
supplied from auxiliary steam header. The MP/LP process steam
requirement for the 5th stream in alumina refinery will be shared
by existing five TGs (5th one presently under construction) and the
proposed TG-6.
Plant facilities: The proposed co-generation power plant
will have the following plant facilities:
- Boiler and auxiliaries - Steam turbine and auxiliaries - Coal handling system - Water system - Fire fighting system - Ash handling system - Power generation and distribution system - Instrumentation and control system - Cranes, hoists and elevators - Utility system
Ash pond: The existing ash pond area is about 70.10 hectare
at reduced level 940.00 Meter. The present ash pond dyke height is
930 m from MSL & safe operating level of 927.5 M. At 927.5 meter
level, the area of Ash pond is 56.9 hectares and volume is 9 Million
M3. The pond is filled up to 925.12 m. and the corresponding filled
volume is 8.47 Million M3. Balance volume available is 0.53 Million
M3. Considering 300000 MT of pond ash recovery from ash pond,
the expected life of the pond is up to Sept’ 2017. However, the ash
pond is under expansion to raise the dyke level up to 940 meter.
With crest height of 940 meters, safe operating level is 937.5 meter
and the corresponding volume is 15.30 Million M3 and the
estimated life of the pond is up to 2028 considering 600000 MT
ash generation & 10% utilization of dry fly ash.
RESOURCE OPTIMISATION/RECYCLING AND REUSE
� The process technology for 5th Stream is based on
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-38
M. N. DASTUR & COMPANY (P) LTD
medium pressure digestion of bauxite from Panchpatmali mines.
� This enables over 98% digestion of gibbsite at reduced
residence time and higher liquor RP(Al2O3/Na2O ratio)/higher liquor productivity. Energy recovered during various process steps like increased liquor productivity, use of HRD/DCW for mud settling and washing, etc. in the process.
� Energy efficient electrical equipment have been envisaged
to minimise loss of electrical energy. � Co generation power plant will further optimise the energy
utilization. � Water will be recovered from various process steps and
will be recycled to the main process. � The final treated water from sewage treatment plant will
be utilized for gardening purpose. Necessary measures have been envisaged to minimise loss of various raw materials used for the process, as well as the final product.
� Efficient mud washing technology has been considered to
recover the valuable soda. � Fly ash to be generated from co generation power plant
will be stored temporarily for transporting outside the plant at regular intervals by trucks for commercial use like cement making and brick making.
NALCO has already engaged various agencies to explore
diverse uses of Red Mud (red brick for construction, glass ceramics
etc) which are in the R&D stage.
WASTE MANAGEMENT AND DISPOSAL
Details of waste utilisation (Ash, red mud and spent acid)
and disposal have been described suitably in Chapter-5.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
2 – Project description (cont’d)
2-39
M. N. DASTUR & COMPANY (P) LTD
A Schematic representation of the feasibility drawing which
give information of EIA purpose is given in Fig. 2B-2.
Fig. 2B-2
Project Concept
Form-1, Pre-Feasibility Report
with proposed TOR to EAC
Scoping by EAC (Site visit by
Sub group of EAC, if ncessary)
TOR approved by
EAC (Industry)
EC-rejected by IAA on the
recommendation of EAC
(Industry)
Draft EIA report to
SPCB by project
proponent
Summary EIA and Form-
1- Display on the web
site by
Public consultation
process by SPCB
Proceeding of
public consultation
Display at Panchayet
,ZP, DM/DC/Dy. Com
& on the SPCB website
To proponent for
submission of final EIA
report/supplementary
report to draft EIA
Referred back to EAC
under communication to
the project proponent
Display on MoEF &CC
website & project
proponent website
Submission of half yearly
compliance report to
MoEF/RO-MoEF
Display of
compliance
report on
MoEF
&CCwebsie
te
Appraisal and
recommendation by
EAC (Industry)
Approval by
IAA,MoEF, GoI
Rejected Approved
Post EC monitoring
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
3-1
M. N. DASTUR & COMPANY (P) LTD
3 - SITE ANALYSIS
The technical details of the proposed expansion of the
refinery capacity to 1.0 MTPA alumina is described in the
preceding chapter. This chapter mainly focuses on the location of
the proposed expansion.
Connectivity
NALCO Refinery is located at Damanjodi in Koraput District
of Odisha State, India. Damanjodi is well connected by roads. It is
around 10 km away from National Highway 26 (Vizag-Raipur) at
Semiliguda junction, Koraput, the district Head Quarter, is situated at
a distance of about 45 km via Damanjodi and Similiguda. The town
Damonjodi is located at about 180 km north-west of
Visakhapatnam, Andhra Prasdesh. Public transport by bus is
available to the nearest town of Koraput (District Headquarter), the
larger town of Jeypore, the township of Hindustan Aeronautics
Limited, Sunabeda and many other major towns and cities of the
state of Odisha. The nearest rail head is at Damanjodi, on the
Rayagada-Koraput broad guage rail section of East Coast Railways,
located about 6 km west of the plant. The nearest airport is four (4)
hours away in the city of Visakhapatnam, AP. The nearest airport
& port Visakhapatnam is at a distance of about 200 km from the
plant area.
Land form, land use and land ownership
The proposed expansion will occur within the existing plant
of NALCO in their own acquired land. The present land use is
basically built-up area for industrial purpose with greenbelt, water
reservoir and solid waste processing & storage area.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
3 – Site analysis (cont’d)
3-2
M. N. DASTUR & COMPANY (P) LTD
Topography
The entire study area is occupied by dense forest, highly
rugged mountains, interspersed with narrow intermountain valleys.
The average altitude of the hilly terrain ranges from 900 to 1,400 m
above msl. The refinery unit located in Damanjodi is in a valley
situated among the Panchpatmali Hills. The topography features of
refinery area can be seen from Fig 3B-1 below:
FIG. 3B-1 - TOPOGRAPHY OF ALUMINA REFINERY AREA
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
3 – Site analysis (cont’d)
3-3
M. N. DASTUR & COMPANY (P) LTD
Existing land use
The land use in 10 Km. radius is assessed based on the
satellite imagery (IRS P6, Liss4 mx) and the area statistics.
FIG. 3B-2 - EXISTING LAND USE
The study area mainly consists of scrub land with dense
scrub consisting of about 20% and rest being scattered scrub land.
Agricultural land consists of about 16% of the total landuse. Water
bodies take up about 2% of the total area. Industry and other
built-up area consist of only 3% of the total land area.
Drainage
There are neither perennial nor seasonal nala on the plateau
of study area. Seasonal nalas originate from the periphery of the
plateau and flows along the slopes towards the toe to meet the
perennial sources. A perennial nala exists on the western side and
flows towards Jhulaguda River which is dammed to have a storage
capacity of 1,500 cu m water. Numerous springs flowing from its
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
3 – Site analysis (cont’d)
3-4
M. N. DASTUR & COMPANY (P) LTD
western flank of Panchpatmali hills culminate into the major
drainage system comprising the ‘Deogiri Nadi’ and the ‘Muran
Nadi’. The Indravati & Kolab river and their tributaries constitute
the main drainage system of the study area. The rivers in general
exhibit dendritic drainage pattern and are effluent and perennial in
nature.
Soil
The subsoils are of good quality. It is characterised by stiff to
very stiff / hard, silty clay / clayey silt followed by weathered rock
layer and that layer continues upto the terminating depth of some
boreholes. The standing water table is around an average depth of
7.00m below ground level.
Climatic conditions
The area has a dry, humid and hot climate. The summers
have a good deal of rainfall, while the winters are normally dry. The
average annual temperature is 23.0 °C in Damanjodi. The rainfall
averages to about 1522 mm (IMD data of Koraput district).
Existing physical & social infrastructure
Administration: The area of Damanjodi constitutes of three
sectors. These sectors comprise of housing quarters laid out in
well-planned lanes and streets. Facilities include nationalized
banks with networked ATMs, large co-operative stores and market
complexes. The local administration supplies basic amenities like
that of water and sewerage. It is also authorize to build roads
within Census Town limits and impose taxes on properties coming
under its jurisdiction.
Water: The census town is characterized by a well-developed
water supply and treatment plant. Dug wells and hand
pumps/tube-wells are prevalently used in peripheral villages.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
3 – Site analysis (cont’d)
3-5
M. N. DASTUR & COMPANY (P) LTD
Electricity: Individual occupants are drawing power from
SOUTHCO. Uninterrupted captive power supply is also provided by
NALCO.
Education: Saraswati Vidaya Mandir (Oriya Medium) and
Delhi Public School are two major schools in this township. In
addition, there is Shri Aurobindo Complete Study Circle (private
school) and the Malushanta Govt. High School. State Goverment
programme on Adult education are operational.
Medical facilities: Medical facilities are administered by
institutions namely NALCO Hospital in Damanjodi, Government
District Head Hospital and Government Hospital Koraput. Since
2009 Organizational activities have initiated Mobile Health Units
(MHUs) to bring health services (free medicine, diagnostics,
awareness) to the doorsteps of the needy in the remote villages in
Damanjodi. The Mobile Health Units through Information,
Education and Communication (IEC) activities are being operated
through Wockhardt Foundation at Damanjodi. Additionally
medical camps are conducted for patients from periphery villages
of Damanjodi and treated free of cost.
Recreation: Religion, Sports and Festivals are major modes of
recreation in the district. A State level Tribal Festival ‘PARAB’ is
organized by District Administration at Koraput. Organizational
activities in Damanjodi encourage rural sports/tournaments are
organized annually. There are several parks (Nehru Children Park,
Biju Patnaik Science Park), stadiums (Netaji Stadium, B.R. Ambedkar
Stadium), clubs, community centres, open air pandel areas, mandap
areas, temples and a mosque in Damanjodi. There are a number of
hotels in and around the town for visitors.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
4-1
M. N. DASTUR & COMPANY (P) LTD
4 – PLANNING BRIEF
Population projection
Damanjodi, a Census Town is situated among the
Panchpatmali hills, in the district of Koraput, Odisha. As per the
2011 Census of India, the population of Damanjodi Census Town is
8,862 of which 4,633 are males while 4,229 are females.
Population of Children with age of 0-6 is 965 which constitute
10.89% of total population. The average literacy rate is 93.23%,
which is higher than state average of 72.87%. Male literacy is
around 96.38 % while female literacy rate is 89.78%. The Sex Ratio
is of 913 against state average of 979. The total number of
households is over 2,519 houses. Schedule Caste (SC) constitutes
14.77% while Schedule Tribe (ST) is 13.47% of total population in
Damanjodi (CT). Out of total population 2,974 people were engaged
in work or business activity. Of this 2,570 were males while 404
were females. Of total 2974 working population, 95.86 % were
engaged in Main Work while 4.14 % of total workers were engaged
in Marginal Work. The population is cosmopolitan in nature. Apart
from local population, significant population has migrated in from
varied regions outside the state.
The population of Damanjodi Census Town in the years
2001 and 2011 are 8475 & 8862 respectively. The decadal growth
is of 4.57 %. Thus the projected population of Damanjodi Census
Town for the year 2015 is around 9024.
Nearby existing industries
The major industries identified near the NALCO Alumina
complex at Damanjodi are Hindusthan Aeronautics Limited (HAL)-
Engine Divison at Sunabeda & Odisha Timber and Engineering
Works, also at Sunebeda.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
4 – Planning brief (cont’d)
4-2
M. N. DASTUR & COMPANY (P) LTD
Assessment of infrastructure demand (Social)
NALCO has a strong Social Accountability Policy. It works
towards continual improvement initiatives in all social issues and
sustenance of SA 8000 Standard.
A committee i.e. Rehabilitation & Peripheral Development
Advisory Committee (RPDAC) with RDC (SD), Berhampur as
Chairman; Honb’le MP(LS), Koraput; MLAs of Pottangi, Koraput,
Laxmipur; President Zilla Parishad, Koraput, District officials and
Management representatives of NALCO as members, have been
constituted by the Government and is in operation. Additionally
Social Impact Assessment was carried out for the year 2012-13 by the
Central University of Odisha at Koraput. Furthermore Needs
Assessment Study, Water & Energy Study are conducted in the
peripheral villages of Damanjodi.
The projects are envisioned post needs assessment of the
community. During the process of needs assessment, the opinion
of the community, local government and district authorities are
also taken into account. Regular assessment and examination of
the demands of the community are undertaken. Through these
processes, it is ensured that the demands of social infrastructure
and community development initiatives are successfully adopted.
The activities of the aforementioned committee and studies
emphasize to cater to varied interests and concerns of different cross
section of people of the Koraput District. In the beginning of each
financial year, plans on the various need-based activities that are to
be implemented within the District for that year are formulated. The
main peripheral development activities undertaken are in the area of
Social Infrastructure.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
4 – Planning brief (cont’d)
4-3
M. N. DASTUR & COMPANY (P) LTD
With regard to the continuing demands related to Social
Infrastructure in the Project Influence Area, some activities
undertaken by NALCO are mentioned below:
- Assisting establishments of remedial schools for drop-out children and distribution of educational kits in the peripheral villages
- Promotion of solar energy in rural households by distribution of solar lanterns in periphery villages of Damanjodi
- Organization of Medical Camps promoting awareness about prevention of diseases like malaria and providing gears like mosquito nets
- Propagation of safe drinking water by distributing water filters
- Construction and upkeep of Canteen, rest shelter / room, recreation Room within the Plant
Under the Peripheral Development schemes, emphasis has been
laid on social infrastructure programmes concentrating on areas of
education, health, water supply etc. The objective is to bring about in-
depth rural development and to encompass many more villages under
the development scheme.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
5-1
M. N. DASTUR & COMPANY (P) LTD
5 – PROPOSED INFRASTRUCTURE
The proposed expansion for 5th stream of alumina refinery for
production of smelter grade alumina from bauxite and coal based
co-generation power plant has been described in the earlier
chapters. This chapter accordingly gives an outline of the social
infrastructure, principle types of pollution and highlights the
proposed environmental pollution control measures in compliance
with the prevailing Acts and Rules and its amendments thereafter.
Industrial area
The total area plant area is about 248 Ha, within the
boundary of which the proposed expansion will take place. The
process units, water reservoir, solid waste processing & storage
area for the existing facilities as well as the proposed will be
housed within this area of 248 Ha.
Residential area
The existing township at Damanjodi has approximately
3,000 dwelling units (DU). The present township is self sufficient
in all respect with all services and amenities. The existing
township will have to accommodate about 410 families of different
categories after the expansion programme. However, several
numbers of dwelling units have to be constructed within the
township to accommodate the additional personnel.
Types of buildings planned for housing will range from G+2
to G+3 apartment type of housing blocks which are a cluster of
dwelling units with common staircase and lobby. The apartment
blocks will be divided into several categories of dwelling units of
different covered areas ranging from 100 sq m (1,075 sft), 120 sq m
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
5 – Proposed infrastructure (cont’d)
5-2
M. N. DASTUR & COMPANY (P) LTD
(1,290 sft) and 150 sq m (1,615 sft) respectively. Number of
dwelling units per floor will always be two numbers only to avoid
congestion in the common lobbies. The circulation pattern of the
existing township will be followed here with segregation of
pedestrian and vehicular movements on the roads.
The basic needs of a township with respect to service
facilities pertaining to water supply, electricity and telecom
network and drainage and sewerage system will be provided with
efficient service facilities and easy maintenance provisions.
Proposed social infrastructure
The expansion project entails provision of the following in
the Project Influence Area:
- Increase of scale of services for improvement of Canteen facilities, drinking water supply, recreation etc.
- Increase of Residential Buildings/Dwelling Units - Maintenance of approach roads towards the Refinery &
peripheral road networks
- Increase of greenery development in and around the study area
- Better management of municipal waste and recycling of
waste water for its effective utilization after treatment
- Assessment of additional power requirement and supply
- Rain water harvesting and promotion of alternate sources of energy like solar power in the nearby villages
- Upgradation/ augmentation of the existing educational
facilities and establishment of new units
- Enhancement of vocational training facilities for the villagers
- Augmentation of medical camps for increasing awareness towards prevention of various diseases
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
5 – Proposed infrastructure (cont’d)
5-3
M. N. DASTUR & COMPANY (P) LTD
- Increase of potable water supply and improvement of
sanitation facilities
Air pollution control measures
Raw material handling section at Refinery: Dust
emissions arising from received bauxite from mines via overland
conveyors, crushing/grinding section, roads, stockpiles etc will be
controlled by water sprinkling and dust extraction (DE) system by
installing bag filter. The bauxite and coal will be conveyed in
covered conveyors. All transfer point of conveyor to conveyor,
conveyor to equipment and dry circuit of crushing and screening
will be provided with dry fogging (DF) system.
Calcination: Fuel oil will be used for drying the alumina in
calciner. Hot flue gas from the calciner passes counter currently to
the hydrate resulting in removal of moisture and bound water. The
dust laden air will be sucked through duct and then cleaned in an
ESP before letting into atmosphere through a stack of adequate
height.
Co-generation power plant: Power generation by firing
100% Indian steam coal will generate particulates, NOx and SO2.
The combustion gas after used to raise steam for generation of
electricity will be cleaned in ESP to separate out the particulates
and the clean flue gas will be vented into atmosphere through a
stack of appropriate height. NOx emission will be controlled by
using low NOx burners and controlling excess air during
combustion. Due to the low sulphur content of the coal to be
received from Talcher or IB valley, the emission of SOx will be
within the permissible limit.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
5 – Proposed infrastructure (cont’d)
5-4
M. N. DASTUR & COMPANY (P) LTD
Water pollution control measures
The make up water required for cooling towers related to
evaporator, precipitator & inter-stage coolers and red mud washing
water will be met by utilizing recovered water from the process.
The clear water from red mud pond will be reclaimed and
send back to the process. The drained water from the process,
including that from spillage, leakage etc, will be taken to the
Alkaline pond and finally to the red mud pond.
The cleaning system will comprise of caustic cleaning & acid
cleaning. The spent liquor from caustic & acid cleaning (containing
H2SO4) will be sent to the red mud pond. The spent HNO3 from
acid cleaning will be neutralized by lime before sending to the red
mud pond.
Water is mainly required in cogeneration power plant as
boiler feed water and in cooling tower. The waste water generated
in Demineralization Plant (DM) plant will be neutralized in the
neutralization pit and routed to a reservoir where waste water from
other units like boiler blow down, cooling tower blow down etc will
get mixed. The treated waste water will be utilised for green belt
development, make-up for bottom ash handling system, service
water system and coal dust suppression system in fuel storage
area.
Run-off from coal handling area and coal piles generally
contains suspended solids. It is proposed to provide a peripheral
drain around coal yard and collected into a coal settling tank.
Decanted water from the settling tank will be re-used for dust
suppression. Service water effluent drains will be let to a sump
which generally contains oily waste from the fuel oil area. Service
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
5 – Proposed infrastructure (cont’d)
5-5
M. N. DASTUR & COMPANY (P) LTD
water will be passed through a tube settler for removal of
suspended solids. Treated service water will be sent to service
water tank for re-use.
To meet the drinking water and sanitation requirement of
plant personnel, filtered and chlorinated water from filtration unit
is pumped into overhead storage tank using drinking water fill up
pumps from filtered water storage tank. The water will be stored in
an overhead storage tank of 200 cum capacity, where from water
will be supplied to all consuming points.
Drinking and sanitation water
To meet the drinking, sanitation and service water
requirement for proposed and existing facilities in refinery and co-
gen power plant, treated water from the existing raw water
treatment is utilized.
The following facilities are envisaged for the drinking water
system:
i) Drinking water fill-up pumps: Two horizontal
centrifugal pumps of capacity 350 cu m/hr with suitable head (1 working +1 standby) are envisaged to transfer the water from the filter water reservoir in existing raw water treatment to the proposed drinking water tank which is located at the hill top.
ii) Drinking water storage tank: Overhead drinking water storage tank in RCC construction of capacity 1,000 cu m is envisaged to cater the proposed and existing drinking water requirement. The existing and proposed tanks are interconnected with isolation valve in order to utilize the existing storage tank. The storage capacity of existing and proposed tank together will be around 1,720 cu m (existing 720 cu m + proposed 1,000 cu m) with 8 hrs retention period. The proposed tank will be located near to the existing drinking water tank location at the hill top.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
5 – Proposed infrastructure (cont’d)
5-6
M. N. DASTUR & COMPANY (P) LTD
iii) Pipe work: The piping from the proposed drinking water
storage tank will be distributed to the various consumers by gravity through pipelines.The specification for the distribution pipelines will be as follows:
- DN 100 & below : S1239 (Part-I) heavy, ERW,
galvanized - DN 125 to 150 : IS1239 (Part-I) heavy, ERW. - Above 150 : Factory made as per IS 3589 Service water and the water required for safety eye wash
shall be drawn from the drinking water header. Isolation valve is considered in the inlet line of each consumer.
Sewage treatment plant
It is proposed to provide a sewage treatment plant
of 200 cu m/day capacity to treat the sewage generated within the
plant. The sewage generated from the plant premises will be
collected through sewage network system to the sump of sewage
treatment plant. RCC/HDPE pipes will be used for sewage disposal
pipes in sewage network.
The raw sewage will be pumped from collection sump
provided in the sewage treatment plant to bar screen chamber
followed by fine screen chamber. The equalisation tank which
receives the sewage by gravity from bar screen chamber will be
provided with coarse bubble diffuser system to ensure proper
mixing thereby avoiding settlement and to provide pre-aeration to
avoid septicity. Then, it will be pumped into aeration tank provided
with fine bubble diffuser arrangement for the reduction of BOD and
COD level of sewage to desired level as per pollution control norms.
The supernatant liquid from the aeration tank will be passed
into clarifier for the removal of suspended solids. A portion of
underflow biomass from the clarifier will be re-circulated using
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
5 – Proposed infrastructure (cont’d)
5-7
M. N. DASTUR & COMPANY (P) LTD
sludge recirculation pumps to the aeration tank to maintain MLSS
level in the aeration tank, while other portion of the sludge will be
distributed equally to sludge dying bed.
The overflow from the clarifier will be filtered in pressure
sand filter followed by activated carbon filter to remove the
suspended solids, traces of odour and organics etc. The final
treated water will be utilised for gardening purpose.
Solid waste management and disposal
Fly ash: The Fly ash collected from ESP hoppers & stack
hopper will be transported to covered fly ash silos. In the silos, fly
ash will be stored temporarily for transporting outside the plant at
regular intervals by trucks for commercial use like cement making
and brick making. Emergency provision will be kept for wet
disposal of ash in the existing ash pond earmarked for bottom ash
disposal.
Bottom ash: The bottom ash from the boiler will be collected
in bottom ash hopper and further transported to bottom ash silos.
Then, it will be mixed with water to form the high solid
concentration slurry. This slurry will be transported to the ash
pond through High Concentration Slurry disposal (HCSD) pump. A
peripheral greenbelt is in place around the embankment of the ash
pond.
Management & Disposal of Red mud: Red mud is a by-
product of alumina refinery process. It contains iron, silicon,
calcium, titanium and sodium in form of oxides depending on the
ore used. Apart from the high alkalinity from liquors the residue is
chemically stable, non- toxic and non hazardous in nature as per
Hazardous Waste (Management, Handling & transboundary
movement) Rules, 2008 and any amendments thereafter.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
5 – Proposed infrastructure (cont’d)
5-8
M. N. DASTUR & COMPANY (P) LTD
The red mud will be disposed in the existing specially
constructed storage site (Red Mud Pond). The Total Volume of
existing Red Mud Pond is 52.04 Million cum at EL-954.50M and
the total Volume filled up as on 31.03.2015 is 27.164 Million cu m.
Hence, the total space available is 24.886 Million cum.
NALCO has engaged various agencies like Moscow State
Institute of Steel & Alloys and Romelt Sail India Limited (RSIL),
IMMT-BBSR to explore diverse uses of Red Mud. These R&D
projects have identified the following uses of Red Mud:
- Manufacture of Red Brick for Construction purposes
- Manufacture of glass ceramic tile having excellent glossy finish, good mechanical strength, abrasion resistance & cost effective and are comparable to granite, marble and vitrified tiles available in the market.
Spent acid management
The concentrated acid will be brought by road tankers and
stored in a tank bounded within a dyked area. Spent acid obtained
from cleaning operation will be stored in spent acid storage tank
and will be finally disposed into red mud pond area, thus
neutralizing the acidic effect.
Work zone pollution control measures
The work zone pollution will be mostly fugitive dust, heat,
vibration and noise. The fugitive dust emission in all transfer
points will be controlled by DE/DS system as described earlier.
At the refinery, noise arising from the mechanical
machineries like such as turbo generator, pumps, fans, compressor
etc steam turbine cannot be eliminated fully but overall aim should
be to restrict the ambient as well as work zone noise within the
specified norms. The mitigation measures to be adopted for such
noise-prone equipment will be to install that noisy equipment in a
separate housing so as to enhance the noise attenuation.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
5 – Proposed infrastructure (cont’d)
5-9
M. N. DASTUR & COMPANY (P) LTD
Corrosion control
As the digestion process will require use of caustic soda, it is
imperative to install adequate corrosion protection measures as an
integral part of environment protection plan. Materials of
construction for caustic soda handling tank and pipe lines,
equipment etc will be selected on the basis of their corrosion
resistant properties. Proper care will be taken to prevent the
spillage of caustic soda in order to avoid contamination of the soil,
surface or ground water.
Plant greenbelt and landscaping
Greenbelt will be developed in around 33 per cent of the plant
area for peripheral greenbelt, gardening and tree plantations at the
site. This will arrest wind borne dust and also improve the
environment quality as well as the plant appearance from aesthetic
point of view.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
6-1
M. N. DASTUR & COMPANY (P) LTD
6 – REHABILITATION AND RESETTLEMENT PLAN
The expansion project does not require displacement of any
human settlement. Hence there are no issues relating to
rehabilitation and resettlement.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
7-1
M. N. DASTUR & COMPANY (P) LTD
7 - IMPLEMENTATION SCHEDULE AND COST ESTIMATE
This chapter deals with the estimated capital cost &
implementation schedule of the Project.
IMPLEMENTATION SCHEDULE
The preliminary overall implementation schedule for the
project, indicating the time required to complete the major
activities of engineering, procurement of equipment, construction,
erection, test, trial run and commissioning of the various plant
facilities along with external and internal facilities has been
developed in the form of a bar chart presented in Appendix 7B-1
The schedule has been developed on the basis of the estimated
quantum of work, expected delivery and installation periods of
plant and equipment and the need to commission the plant
facilities in the shortest possible time. The schedule envisages a
total project implementation period of 48 months from date of ‘Go-
ahead’.
It has been assumed that prior to commencement of the
project, following activities will be completed by NALCO:
i) Finalising arrangements for obtaining the requisite
finance as per the projections and matching with the implementation schedule
ii) Obtaining relevant statutory clearances
Commissioning of various major facilities has been
scheduled in a progressive manner in order to ensure integrated
operation of the plant. Commissioning schedule for Alumina
refinery will be 48 months from the ‘Go-ahead’.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
7 – Implementation schedule and cost estimate (cont’d)
7-2
M. N. DASTUR & COMPANY (P) LTD
COST ESTIMATE
The capital cost has been estimated based on the quotations
from various vendors for equipments/materials, data taken from
the past similar projects at 2013 -14 price level etc. The figures are
tentative & may vary during actual implementation to some extent.
A more pragmatic estimation can be worked out only after detailed
engineering.
The capital cost estimates of the refinery is presented under
the following heads:
- Plant cost
- Pre-Project Activities
- Working capital margin (WCM)
- Interest during construction (IDC)
Plant cost
The plant cost comprises cost of land and site development,
civil work & structural steelwork, plant & equipment and erection.
Cost towards technology supply by process licensor, township,
design, engineering, consultancy services and administration
during construction (DE & ADC) and provision for contingency are
also included.
Land and land development
The item wise break-up of the same is shown below:
Land & site development cost Refinery Rs. crore
Soil investigation and Survey 0.26
Site Levelling 76.46
Road, Drainage & sewerage 19.33
Track work 14.17
Boundary Wall 4.37
Wall dismantling 0.41
Over bridge 4.72 Watch tower and gate house, Paver Block and Barbed Wire Fencing 0.26 Horticulture and earthen Raw Water Reservoir for Mines 0.21
Total 120.2
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
7 – Implementation schedule and cost estimate (cont’d)
7-3
M. N. DASTUR & COMPANY (P) LTD
Civil and structural steelwork
The total cost of civil & structural steelwork will be about
747.9 Crore for the refinery. This is again sub dived into cost for
Alumina Plant, Vizag Port and Power Plant as shown below:
Item Alumina Plant
Vizag Port Power Plant
Total Refinery
Rs. crore Rs. Crore Rs. crore
Civil work 370.8 25.0 32.2 428.0
Structural work 296.4 - 23.5 319.9 Total 667.2 25.0 55.7 747.9
Plant and equipment
The cost estimates for major plant and equipment are based
on the indicative prices received for similar equipment from
reputed suppliers. The cost estimates for the balance equipment
are based on information available with Consulting Engineers.
Charges for erection of equipment including foreign supervision of
erection have also been considered at normative basis.
Technology supply by Process licensor
This includes Technology supply price by Process licensor
and is included in the estimate of the plant cost for the refinery.
Township
This includes cost of developing separate townships (dwelling
units) for the refinery.
Design, engineering, consultancy services and administration during construction (DE & ADC)
A provision of about Rs 125.6 crore has been kept at 4 per
cent on supply price of equipment together with civil and
structural to take care of expenses towards design, engineering,
consultancy services and administration during construction for
the refinery.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
7 – Implementation schedule and cost estimate (cont’d)
7-4
M. N. DASTUR & COMPANY (P) LTD
Contingency
A contingency provision has been kept to cover expenses
towards any unforeseen item. This provision does not cover any
exchange rate variation and escalation during the construction
period.
Total plant cost including the above items is estimated at
about Rs 3,648.6 crore for refinery and is summarized in
Table 7B-1.
TABLE 7B-1 - PLANT COST ESTIMATE
Description Refinery
Rs. crore
Land & Site development 120.2
Civil and structural steelwork 747.9 Plant and equipment including erection 2,286.2 Technology supply price 123.4 Township 71.6 Design, engineering, consultancy and ADC
125.6
Contingency 173.8
Total plant cost 3,648.6
Pre-project activities
The pre-project activities include cost for construction power
and water and have been considered for refinery. Preliminary
expenses on a lump-sum basis have been considered. Preoperative
expenses include raw material inventory for Bauxite, Hydrate,
Caustic, Fuel Oil, Lime and Flocculants. The start-up expenses
have been calculated at 15 days of manufacturing cost.
Margin money for working capital
Twenty-five per cent of estimated working capital for 1st year
of operation has been considered as margin money for working
capital for the refinery.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
7 – Implementation schedule and cost estimate (cont’d)
7-5
M. N. DASTUR & COMPANY (P) LTD
Interest during construction
Interest during construction is calculated based on the
following assumptions:
- Debt-equity ratio of 2:1
- Phasing of expenditure as per implementation schedule
- Equitable drawl of fund
Total capital cost
The capital cost thus worked out on the above basis for all
the facilities are presented in Table 7B-2.
TABLE 7B-2 - CAPITAL COST ESTIMATE
Description Refinery Rs. crore Plant cost 3,648.6 Pre-project activities 177.5 Margin money for working capital 23.5 Interest during construction 507.6 Total 4,357.2
Financial indicators
The salient financial indicators of the 5th stream alumina
refinery expansion project as presented in Table 7B-3 are
calculated based on sourcing of bauxite from proposed captive
bauxite mine (Central block, Sector-II) at Panchpatmali.
TABLE 7B–3 – FINANCIAL INDICATORS
Internal rate of return (post tax), % 11.4
Pay–back period, years 7.7
Break–even capacity, % 71.1
Cash break–even capacity, % 43.7
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
7 – Implementation schedule and cost estimate (cont’d)
7-6
M. N. DASTUR & COMPANY (P) LTD
Based on the technical and financial review carried out in
this report, it is concluded that the project is techno−−−−economically
viable and recommended for speedy implementation.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
8-1
M. N. DASTUR & COMPANY (P) LTD
8 – ANALYSIS OF PROPOSAL
Financial and social benefits
Expected financial and social benefits from the proposed
project are outlined below:
- The proposed project will generate direct and indirect employment opportunities.
- Employment will be also generated at construction phase
of the project. - This kind of project investment will establish small and
medium scale engineering ancillary in local area. - The proposed project will generate revenue to state by way
of royalty, taxes and duties. - Indirect employment opportunities for local people will be
developed in contractual work. There will be wide variety of contractual work like transportation, sanitation, supply of goods and services to the project and other community members.
- A major part of the labour force will be mainly from the
local villages. Hence, the project will enhance the income level of the local villagers and will improve socio-economic status of the nearby villages.
- Project will help to sustain the development of the area
including further development of physical infrastructure facilities. The following physical infrastructure facilities will be improved on account of the proposed project.
� Road and transport facilities � Housing facilities � Water supply and sanitation � Power
- Market and business establishment facilities will increase.
- The peripheral development activities of the organization extend to cover the entire District of Koraput.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
8 – Analysis of proposal (cont’d)
8-2
M. N. DASTUR & COMPANY (P) LTD
- In the sphere of health, NALCO has set up one company-
run specialty hospital at Damanjodi. The organisation in association with the Wockhardt Foundation, is also operating four (4) Mobile Health Units (MHUs) that cover 142 villages of the Koraput District. These units work throughout the year, offering primary health services and free medicines and creating awareness through Information, Education and Communication (IEC) activities, to the local population. Furthermore in addition to MHU’s, NALCO organises regular health camps in the Project Influence Area (PIA) and engage in distribution of supplementary items to tribal households, like that of insecticide-treated mosquito nets to curb malaria and water filters to address water-borne diseases like diarrhoea, cholera and jaundice.
- In the area of education, NALCO Foundation has
collaborated with reputed residential institutions for sponsoring residential education to numeorus children of the tribal households of Koraput. The NALCO Foundation’s funding covers all the costs related to study, lodging and boarding of the students across the residential schools namely Koraput Development Foundation Model School and Bikash Vidyalaya. The funding for residential education for the enrolled students is planned till the completion of their schooling. Additionally NALCO has set up Oriya medium and English medium schools in Koraput which lay emphasis on quality education in the study area at subsidized rates.
- With regard to Social Infrastructure, NALCO has
undertaken promotion of alternate sources of energy and pilot projects in the area of sanitation. The organisation has distributed solar lamps to tribal households and has installed 30 solar street lights in the villages of Putraghati and Karidiguda of Koraput District, where the villagers did not have access to electricity.
- In addition to government initiatives of Ministry of Human
Resource Development (MHRD) and non governmental initiatives of organisation like that of ‘Gram Vikas’ in Koraput, NALCO too has initiated a pilot project, in the area of sanitation. In association with Sulabh International Social Service Organisation (SISSO), NALCO has installed three (3) toilets in two (2) schools of Koraput.
Pre-Feasibility Report for 3
rd phase expansion by addition of
5th
stream in Alumina Refinery of NALCO at Damanjodi, Dist: Koraput, Odisha
8 – Analysis of proposal (cont’d)
8-3
M. N. DASTUR & COMPANY (P) LTD
- NALCO aims at continued social commitment towards the
local community. The organization carries out its social benefit plan for: • Promotion of education • Eradication of poverty by activities on livelihood and
income generation • Promotion of Health and Sanitation • Protection of environment, water and energy resources
and sustainability • Building community infrastructure • Providing relief measures for redressal of calamities,
disasters • Enhancing vocational skills • Reaching out to socially marginalized sections with
special emphasis on differently-abled persons in society
• Promoting cultural activities of local community - The proposed expansion project with increased
investment will augment the above mentioned plan and will promote:
• Improvement in the socio-economic status of the
region by generation of direct and indirect employment opportunities (NALCO has a strong policy against child labour).
• Development of ancillary small and medium industries,
trade and commercial establishments and local entrepreneurship
- NALCO, to facilitate their social responsibility, operates
on a defined agenda and undertakes a participatory and inclusive approach. They consistently exceed the stipulated guidelines and requirement of Department of Public Enterprises (DPE) with regard to the funds spent on the CSR activities.
Final recommendations
Based on the state of the art technology to be adopted for the
expansion project, techno-economic viability, financial and social
benefits as presented above, it may be inferred that it is worth
considering speedy implementation of the proposed project.
A P P E N D I X
APPENDIX 2B-1
Schematic Representation of the Refinery