Presentation to the Portfolio Committee on Water and Sanitation
on the Bucket Eradication Programme
Steven ArumugamActing Director-General: NWRIDate: 23 May 2017
BUCKET TOILET BACKLOG AND PROGRESS SUMMARY AS AT 19 MAY 2017
2
DWS verified Bucket Eradication Target 52 249
LESS – Completed Work as at 19 May 2017 26 957
Outstanding Work to be completed 25 292
To be completed by May 2017Implementing Agents – 10 899
DWS – 14 393
3
APPOINTMENT OF IMPLEMENTING AGENTS FOR THE ERADICATION OF BUCKETS
• Troika suggested the use of Public Entities to commence implementation of the programme in 2013 with a view of replacing all buckets by March 2014 (6 months)
• Original scope – dry sanitation – revised scope (Water borne sanitation)
• The change in scope Inevitably has both a time and cost implication
3
PHASING OUT OF IA’S
•EC
•Implementing Agent : NURCHA•Completion Date: June 2015 (Closing off Project)
•LP •Implementing Agent : LEPELLE•Completion Date: Completing remaining Units
•FS•Implementing Agent : BLOEM WATER /BABEREKI•Completion Date: May 2016 AND ON-GOING
•NC
•Implementing Agent : MISA•Completion Date: September 2015 (IA terminated Contract of
Contractor)
•NC
•Implementing Agent : SEDIBENG WATER•Completion Date: June 2017
•NW
•Implementing Agent : MAGALIES WATER•Completion Date: December 2014
4
5
PROJECT PACKAGING AND IMPLEMENTATION
PROVINCE CONTRACTOR NUMBER OF PROJECTS
COMPLETED PROJECTS
Eastern Cape DWS Contractor 3 3
Free StateBloemwater / Babereki 13 1
DWS Contractor 12 3
Northern Cape Sedibeng Water Board 2 0
DWS Contractor 16 9
North West DWS Contractor 2 2
TOTAL 48 18
PROJECT METHODOLOGY AND SCOPE
6
7
Ince
ption
Proj
ect P
eak
Proj
ect C
lose
-Out
Sept 2015 Sept 2016 March 2018
• Introduction of the National Approach to Munic’s
• Participation of SMME’s in projects
• Disputes over labour rates• Productivity of labour• Material availability
• Outstanding Designs vs completed designs
• Very difficult soil conditions (no feasibility since its
formalised areas)• Review of design based on
soil conditions• Close proximity of houses
use manual excavations• Extent of the work to be
performed excessive• Funding to complete project
slow progress for 2 months
THE PROJECT CYCLE
PROJECT FLOW• By MARCH 2015, 98% of toilet structures were completed with
reticulation in progress• Installation of services (Work in progress) excessive to conclude by
March 2015 however, only 5 projects (quick win) were concluded;• Toilets will only be flushing once reticulation is complete• BEP did not meet the proposed target date – overflow into the next
financial year as work progress and toilets are connected• Aged infrastructure / Replacement of infrastructure
Mar /Apr 16
2015/16 2016/17
March 2018Sept 2015 Sept 2016
8
BEP PERFORMANCEDWS Contractors
Province Target Units Completed
Flushing /Handed
over
Not yet Flushing / handed
over
Structures to be
constructed
Reticulation(% completed on Average )
Water Sewer
NC 7 618 7 134 5 278 1 856 484 92% 94%
EC 3 319 3 319 3 319 0 0 100% 100%
NW 223 223 223 0 0 100% 100%
FS 13 880 13 698 1827 11 871 182 56% 67%
TOTAL 25 040 24 374 10 647 13 727 6669
BEP PERFORMANCEImplementing Agents
Province Target Units Completed
Flushing /Handed
over
Not yet Flushing / handed
over
Structures to be
constructed
Reticulation(% completed on Average )
Water Sewer
NC 1 114 1 114 0 1114 0 98% 98%
FS 9 785 3204 430 2 774 6 581 WIP WIP
TOTAL 10 899 4 318 430 3 888 6 581
10
CASHFLOW PROJECTION FOR BEP2013/14
R’0002014/15
R’0002015/16
R’0002016/17
R’0002017/18
R’000TOTALR’000
Allocation 650 000 899 177 975 399 422 000 328 000 3 274 576
Expenditure650 000
(transferred to IA’s)
281 779 998 466 831 390 190 616 2 952 251
Roll-over -389 300
(not approved
)- -
Forfeited - 617 398 - -
• In 2015/16 some R206,1m was paid to IA’s whom should have completed projects in 2014/15 thus reducing the R975,3m allocation effectively to R769,2m;
11
BUCKET ERADICATION PROGRAMMEPROPOSED PROJECT COMPLETION
Target Completed
Flushing
To be completed
1st Qtr 2nd Qtr 3rd Qtr 4th Qtr
FS 13 880 13 698 1827 182
NC 7618 7 134 5 278 484
EC 3319 3 319 3 319 0 - - - -
NW 223 223 223 0 - - - -
TOTAL 25040 24 374 10 647 66612
BEP EXPENDITURE: CONTRACTORS
PROVINCE BOQ EXPENDITURE TO DATE
AVAILABLE TO DATE
OUTSTANDING BALANCE
Eastern Cape 260 280 260 280 -
Free State 1 609 410 931 328137 384
678 082
Northern Cape 857 477 522 831 334 646
North West 16 369 16 369 -
TOTAL 2 743 536 1 730 808 137 384 875 344
13
BEP EXPENDITURE: IA’S
PROVINCE ALLOCATIONR’000
EXPENDITURE TO DATE
OUTSTANDING BALANCE
R’000
LimpopoLepelle Northern
Water134 876 117 752 17 124
MISA 4 536 - 4 536
Northern CapeSedibeng Water 36 324 7 430 28 894
TOTAL 175 736 125 182 50 554
14
VARIATION ORDERS RECEIVED - DWS TURNKEY CONTRACTORS
PROVINCE VARIATION ORDERS AT HAND OUSTANDING BALANCE R’000
Free State 9 417 9 417
Northern Cape 61 763 61 763
TOTAL 71 180 71 180
15
BEP COST – PROJECT MANAGERS
PROVINCE
TOTAL VALUE PROJECT
MANAGERS R’000
AMOUNT PAID TO PROJECT
MANAGERS PROJECT MANAGEMENT FEES BASED ON PROJECT
COSTOUTSTANDING BALANCE(8%)
R’000
Eastern Cape 20 822-
20 822
Free State 99 12410 071
89 053
Northern Cape 63 61822 455
41 163
TOTAL 183 564 32 526 151 03816
SHORTFALL SUMMARY
SERVICE PROVIDERALLOCATION
R’000
DWS-Turnkey Contractors 875 344
Implementing Agents 50 554
Project Managers 151 038
Variation Orders 71 180
TOTAL 1 148 116
17
WATER SERVICES INFRASTRUCTURE GRANT (WSIG) ALLOCATION 2017/18 FY
PROVINCE ALLOCATION
Free State 256 400 000.00
Northern Cape 71 600 000.00
TOTAL 328 000 000.00
18
REGIONAL BULK INFRASTURE GRANT (RBIG) ALLOCATION 2017/18 FY
PROVINCE ALLOCATION
Eastern Cape 12 000 000.00
Free State 204 877 624.00
Northern Cape 17 000 000.00
TOTAL 233 877 624.00
19
NATIONAL TREASURY RESPONSE
• Numerous engagements with National Treasury were done,
• National Treasury directed the Department to revise its budget allocation on WSIG to cover the budget shortfall,
• The Department was only able to allocate R328 million towards the programme
20
21
MOTIVATION FOR ADDITIONAL FUNDING
• With 97% Top Structures (Toilets) built approximately 43% of such are currently connected and flushing;
• Infrastructure is already installed in all the projects • Un-connected toilets will be subject to use like a pit
latrine / bucket toilet and risk spillages and pollution;• High risk of vandalism on constructed toilets and
reticulation;• Increase in cost of completing the project• Litigations from contractors / claims for standing time
22