Hugh Gloster First and Second Floor Renovations Project Summary Week of August 31 th 2017 HUGH GLOSTER FIRST FLOOR CONSTRUCTION ACTIVITIES FIN ANCIALS Ongoing Activities: Phase 1C Overhead utility coordination GMP : $17,305,262

Transcript of PowerPoint Presentation€¦ · Title: PowerPoint Presentation Author: Chelsea Webb Created Date:...

Page 1: PowerPoint Presentation€¦ · Title: PowerPoint Presentation Author: Chelsea Webb Created Date: 8/31/2017 11:22:43 AM

Hugh Gloster First and

Second Floor Renovations

Project Summary Week of

August 31th

2017

HUGH GLOSTER FIRST FLOOR

CONSTRUCTION ACTIVITIES

FINANCIALS

Ongoing Activities:Phase 1C

• Overhead utility coordination

GMP : $17,305,262

Page 2: PowerPoint Presentation€¦ · Title: PowerPoint Presentation Author: Chelsea Webb Created Date: 8/31/2017 11:22:43 AM

Hugh Gloster First and

Second Floor Renovations

Project Summary Week of

August 31th

2017

HUGH GLOSTER FIRST FLOOR

CONSTRUCTION ACTIVITIES

FINANCIALS

Ongoing Activities:Phase 1C East

• Metal stud framing

• One side of drywall

• MEP in-wall rough-in

• HVAC and Fire sprinkler ceiling

installation

• Curtainwall install

• Install of underground plumbing

GMP : $17,305,262

Page 3: PowerPoint Presentation€¦ · Title: PowerPoint Presentation Author: Chelsea Webb Created Date: 8/31/2017 11:22:43 AM

Hugh Gloster First and

Second Floor Renovations

Project Summary Week of

August 31th

2017

HUGH GLOSTER FIRST FLOOR

CONSTRUCTION ACTIVITIES

GMP : $17,305,262

Ongoing Activities:Phase 1C Executive Vice Dean

• Metal stud framing

• MEP in-wall rough-in

• HVAC and Fire sprinkler ceiling

installation

• Interior window and door frame

installation