2
Hugh Gloster First and Second Floor Renovations Project Summary Week of November 3rd, 2017 HUGH GLOSTER FIRST FLOOR CONSTRUCTION ACTIVITIES FIN ANCIALS Completed Activities: Phase 1C East Interior door and window frame install MEP in-wall rough-in Curtainwall install Install of underground plumbing Plumbing and Electrical in-wall rough-in Hanging Sheetrock Drywall Finishing Activities Prime Paint GMP : $17,305,262 Ongoing/Upcoming Activities: Phase 1C East Overhead MEP rough-in Electrical in slab install Ceiling Grid Install Light Fixture Install Interior Glazing Install Install of Ceiling Grid & O/H MEP Install of Light Fixtures and Diffusers

Transcript of PowerPoint Presentation · 2017. 12. 18. · Title: PowerPoint Presentation Author: Chelsea Webb...

Page 1: PowerPoint Presentation · 2017. 12. 18. · Title: PowerPoint Presentation Author: Chelsea Webb Created Date: 11/3/2017 1:41:54 PM

Hugh Gloster First and

Second Floor Renovations

Project Summary Week of

November 3rd, 2017

HUGH GLOSTER FIRST FLOOR

CONSTRUCTION ACTIVITIES

FINANCIALS

Completed Activities:Phase 1C East

• Interior door and window frame

install

• MEP in-wall rough-in

• Curtainwall install

• Install of underground plumbing

• Plumbing and Electrical in-wall

rough-in

• Hanging Sheetrock

• Drywall Finishing Activities

• Prime Paint

GMP : $17,305,262

Ongoing/Upcoming Activities:Phase 1C East

• Overhead MEP rough-in

• Electrical in slab install

• Ceiling Grid Install

• Light Fixture Install

• Interior Glazing Install

Install of Ceiling Grid & O/H MEP

Install of Light Fixtures and Diffusers

Page 2: PowerPoint Presentation · 2017. 12. 18. · Title: PowerPoint Presentation Author: Chelsea Webb Created Date: 11/3/2017 1:41:54 PM

Hugh Gloster First and

Second Floor Renovations

Project Summary Week of

November 3rd, 2017

HUGH GLOSTER FIRST FLOOR

CONSTRUCTION ACTIVITIES

GMP : $17,305,262

Completed Activities:Phase 1C Executive Vice Dean

• Interior window and door frame

installation

• Store front install

• Final metal stud framing

• Plumbing and electrical in-wall

rough-in

• Hanging Sheetrock

• Drywall Finishing Activities

• Prime Paint

Ongoing/Upcoming Activities:Phase 1C Executive Vice Dean

• MEP O/H ceiling installation

• Ceiling Grid Install

• Lighting Fixture Install

Install of Ceiling Grid

Install of Office Light Fixtures