PowerPoint Presentation Template - Amazon Web Services… · · 2015-05-13Case Study: Arlington...
Transcript of PowerPoint Presentation Template - Amazon Web Services… · · 2015-05-13Case Study: Arlington...
May 13, 2015
Case Study: Arlington Mill Community CenterJennifer Smith, Columbia Pike Revitalization Coordinator,Department of Community Planning, Housing & Development
Presentation Outline
• Background
• Initial Development Proposal (2002 – 2005)
• Mixed Use Proposal (2005 – 2009)
• Final Project (2009 – 2013)
• Lessons Learned
2
Background
1996: County purchases vacant Safeway site at Dinwiddie Street and Columbia Pike• Acquisition cost: $2.35M• Renovation cost: $1.66M
1998: County leases 63% of building to APS• APS programs intended to
move to old Shirlington Library site after 5 years
3
Initial Development Proposal
• APS and County decide to jointly fund and build a shared facility at Arlington Mill
• Community Center• Continuing education high school• Arlington Education and Employment Program (REEP)
• Allocation of space within facility approximately 50/50 County/School programs
4
Initial Development Proposal
• March 2002: County adopts Columbia Pike Initiative – A Revitalization Plan
• Arlington Mill site designated for a “civic building”
• 2002 – 2003: Work team consisting of County and APS staff, community members, and design team develop overall vision for building and programs
• Included public forums and work sessions with program and service providers
• More diverse set of services than typically offered at County community centers
• Much larger facility than other County Community Centers
5
Initial Development Proposal
• 2004: Arlington Mill Steering Committee established• Work with APS & County staff and architect to develop schematic design,
using 2003 Community Process Report as benchmark• Provide input on materials, landscape, Four Mile Run buffers, parking
strategies
• Early 2005: Design work begins on project
• September 2005: County and APS decide to proceed independently on respective programs
• APS interest in moving ahead with a shorter timeline at an alternate site• County interest in pursuing public-private partnership to help finance
community center• Columbia Pike Revitalization Plan and its 2005 update emphasized
mixed-use development and affordable housing
6
Mixed Use Development Proposal
• Winter 2005-06: County finalizes community center program, including community preference for larger gym and flexible classrooms
• Summer/Fall 2006: County issues Request for Qualifications (RFQ) for private development partner
• Responses indicate multi-family housing as an additional use
7
Mixed Use Development Proposal
• November 2006: Voters approve $26M bond funding to construct community center
• May 2007: County selects Public Private Alliances as joint development partner
• 2007 – 2008: Arlington Mill Review Committee meetings, and frequent Community Update meetings with Steering Committee allow for public input on development proposal
8
Mixed Use Development Proposal
• County/PPA Form-Based Code proposal:
• 6-story mixed use community center/retail/residential building
• 5-story residential building• 3 stories of below-grade parking• Public plaza• Residential component: 192
apartments (131 market rate and 61 affordable)
• Affordable component financed in part by Low Income Housing Tax Credits (LIHTC)
Image source: PPA
9
Mixed Use Development Proposal
• June 2008: County Board approves use permit for project
• PPA unable to secure financing for market rate portion of development due to recession
10
Final Mixed Use Project
• December 2009: County Board directs staff to proceed with modified, phased plan for community center and plaza, including parking structure
• Decision eliminates residential portion of community center building
• Board commits to development of at least 61 affordable units on remainder of site
• June 2010: County gives initial consideration to relocating Columbia Pike Library to Arlington Mill site
• County Manager withdraws proposal due to strong community support for keeping library at existing location
11
Final Mixed Use Project
• June 2010: County issues Request for Proposals for a new development partner for residential component
• September 2010: County Board approves Use Permit Amendment
• Separates project into two phases for community center and residential building
• Community center building height changes from approved 6 stories (3 community center + 3 housing) to 5 stories (all for community center uses with ground floor retail)
• October 2010: County selects Arlington Partnership for Affordable Housing (APAH) as new development partner
12
Final Mixed Use Project
• APAH Proposal for Arlington Mill Residences:• Approved residential building reduced to 122 units; height
reduced to 4 stories• Addressed community concerns• Reduced construction costs per unit• Shortened construction time
• 100% committed affordable units, including 13 permanent supportive housing units and units for lower-income households (30, 50, and 60% of the Area Median Income)
• County offered below-market rate ground lease, built parking garage for entire site at one time (APAH purchased its share of common garage)
• Co-location with community center reduced costs by $75,000 per unit
13
Lessons Learned
• County seized the opportunity to acquire an available site without a definite long term program plan
• Later community engagement process and broader Columbia Pike planning led to vision of a mixed-use project to anchor revitalization efforts
• Form-Based Code anticipated civic buildings along corridor
• Prescriptive set of design standards, allowed for more streamlined process
• Community embraced code; helped build community support for mixed-use development
16
Lessons Learned
• Neighborhood Steering Committeewas critical to site programmingand design
• Persistence – keep working thedeal
• County maximized height andbuilding space of communitycenter at time of construction
• Portions of building left unfinished toallow for future program expansionas County grows
• Less costly to build upfront than toadd on later
17
Lessons Learned
• Constructing parking garage upfrontsaved on total project costs versusseparate garages for each phase andcaused less disruption to theneighborhood
• Community center retail space notyet occupied – difficulties of locatingin a public building
• Form-Based Code approval process allowed housing to meet ambitious timeline without delaying community center construction
18
Lessons Learned
• Affordable housing can be a good partner in public land• Reduced land costs allowed
APAH to leverage LIHTC equity and provide housing at lower income tiers
• Meets County goals of locating affordable housing near transit and providing community center programs and amenities to residents
19