PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT...

36
P UBLIC I NFORMATION C ENTER OCEAN DRIVE (CR 621) UPGRADES AND BRIDGE IMPROVEMENTS LOCAL CONCEPT DEVELOPMENT STUDY May 2018 SOUTH JERSEY TRANSPORTATION PLANNING ORGANIZATION CAPE MAY COUNTY

Transcript of PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT...

Page 1: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

PUBLIC INFORMATION CENTEROCEAN DRIVE (CR 621) UPGRADES AND BRIDGE IMPROVEMENTSLOCAL CONCEPT DEVELOPMENT STUDY

May 2018

SOUTH JERSEY TRANSPORTATION PLANNING ORGANIZATIONCAPE MAY COUNTY

Page 2: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

2

WELCOME AND INTRODUCTIONS

PROJECT TEAM• South Jersey Transportation Planning Organization• Cape May County• New Jersey Department of Transportation • Cape May County Bridge Commission• Michael Baker International Team

Page 3: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

3

PROJECT LOCATION – TWO MILE BRIDGE

MillCreekBridge

UpperThorofareBridge

MiddleThorofareBridge

MP 0.00

MP 2.75

Page 4: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

4

PROJECT OVERVIEW

Land uses include: • Wetlands throughout the study area• Over a dozen marinas and fisheries• Restaurants• Residential areas

Local Officials, include:• Mayors• Council Members• Freeholders• Police, Fire, Public Safety and OEM• Planning and Engineering Departments

From:• Cape May County• Cape May County Bridge Commission • Cape May City• Lower Township• City of Wildwood• Wildwood Crest

Page 5: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

5

PROJECT OVERVIEW

Local Capital Project Delivery Program

Ocean Drive Causeway Needs:• Community Input• Existing Conditions• Project Purpose & Need

Page 6: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

6

PROJECT DELIVERY PROCESS

Local Concept Development

Local Preliminary Engineering

Final Design Construction

Data Collection and Environmental Screening Report

Final Purpose and Need Statement

Alternatives Development

Selection of Preliminary Preferred Alternative (PPA)

Concept Development Report

Preliminary Design Plans

Cost Estimates (Final Design, Right of Way & Construction)

Approved Project Plan

Approved Design Exception Report

Approved Environmental Document

Preliminary Engineering Report

Final Design Plans

Environmental Reevaluations

Environmental Permits

Acquisition of Right of Way

Construction Contract Documents, and Plans, Specs. & Estimates

Completed Construction

As-Builts

Close-out Documentation

Approximately 2 years Approximately 2 years Approximately 2 years Design Dependent

Fall2017

Spring2018

Summer2018

Fall2018

Spring2019

Duration

Page 7: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

7

PUBLIC INPUT PROCESS

DURING LOCAL CONCEPT DEVELOPMENT

Meeting #1 (Today)Provide Information Obtained During Data Collection and Obtain Public Input. Obtain feedback about who is currently using the causeway, what modes of transportation are being used, and what issues the Project Team should be aware of when developing alternatives.

Meeting #2 (Summer 2018)Present Alternatives Developed and Obtain Public Input on the Alternatives. Feedback obtained will be used to help determine which Alternative to select as the Preliminary Preferred Alternative.

Meeting #3 (Fall 2018)Present Preliminary Preferred Alternative (PPA).

Page 8: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

8

2. Document Existing Conditions and Develop Purpose & Need Statement – Winter 2017/2018

1. Data Collection – Fall 2017

3. Develop Alternatives – Spring 2018

4. Analyze Alternatives – Summer 2018

5. Select PPA, Develop Plans, Documentation – Fall 2018

• Conduct Data Collection• Identify Right of Way• Identify Stakeholders• Develop Public Involvement Action Plan

LOCAL CONCEPT DEVELOPMENT PHASE

Page 9: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

9

LOCAL CONCEPT DEVELOPMENT PHASE

• Evaluate Deficiencies• Utilities• Geotechnical• Stormwater Management• Traffic - Marine and Vehicular• Structural• Identify Substandard Design Elements

• Identify Resources• Environmental Screenings• Historic Landmarks• Parklands• Constraints Mapping• Potential Users

• Existing Conditions Documentation• Local Officials Meeting• Stakeholder Coordination Meeting• Public Information Center• Identify Future Demands or Needs• Purpose and Need Statement

2. Document Existing Conditions and Develop Purpose & Need Statement – Winter 2017/2018

1. Data Collection – Fall 2017

3. Develop Alternatives – Spring 2018

5. Select PPA, Develop Plans, Documentation – Fall 2018

4. Analyze Alternatives – Summer 2018

Page 10: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

10

LOCAL CONCEPT DEVELOPMENT PHASE

• Development of Alternatives

2. Document Existing Conditions and Develop Purpose & Need Statement – Winter 2017/2018

1. Data Collection – Fall 2017

3. Develop Alternatives – Spring 2018

5. Select PPA, Develop Plans, Documentation – Fall 2018

4. Analyze Alternatives – Summer 2018

Page 11: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

11

LOCAL CONCEPT DEVELOPMENT PHASE

• Alternatives Analysis & Documentation• Local Officials Meeting• Stakeholder Coordination Meeting• Public Information Center• Inter-Agency Review Committee Meeting

2. Document Existing Conditions and Develop Purpose & Need Statement – Winter 2017/2018

1. Data Collection – Fall 2017

3. Develop Alternatives – Spring 2018

5. Select PPA, Develop Plans, Documentation – Fall 2018

4. Analyze Alternatives – Summer 2018

Analysis includes avoidance, minimization and mitigation of impacts from the proposed alternatives

Page 12: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

12

LOCAL CONCEPT DEVELOPMENT PHASE

• Select Preliminary Preferred Alternative• Preliminary Preferred Alternative Cost Estimate • Local Officials Meeting• Stakeholder Coordination Meeting• Public Information Center• Obtain Resolutions of Support• Concept Development Report

2. Document Existing Conditions and Develop Purpose & Need Statement – Winter 2017/2018

1. Data Collection – Fall 2017

3. Develop Alternatives – Spring 2018

5. Select PPA, Develop Plans, Documentation – Fall 2018

4. Analyze Alternatives – Summer 2018

Page 13: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

13

EXISTING CONDITIONS REVIEW

• Ocean Drive and its bridges were constructed in 1939 and have been repaired and rehabilitated since the original construction.

• Important evacuation route for southern end of The Wildwoods.

• Consists of two Cape May County-owned bridges and one Cape May County Bridge Commission-owned bridge.

• Three main bridges on the causeway:

• Mill Creek Bridge

• Upper Thorofare Bridge

• Middle Thorofare

• Culvert located near Fish Dock Road

Traffic Data

Structural

Roadway

Utilities, ITS, Roadway Lighting

Environmental Screening

Page 14: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

14

BRIDGE INFORMATION

All three bridges were originally constructed in 1939.

Condition Mill Creek Upper Thorofare Middle Thorofare

Bridge Sufficiency

(out of 100)47.3

(Functionally Obsolete)

34(Structurally Deficient)

7(Functionally Obsolete)*

Superstructure

(scale of 1-9)5

(Fair)

5(Fair)

4(Poor)

Deck

(scale of 1-9)5

(Fair)

5(Fair)

6(Satisfactory)

Substructure

(scale of 1-9)5

(Fair)

4(Poor)

4(Poor)

Inspection Year 2016 2016 2015

Page 15: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

15

BRIDGE TERMS

• Abutment• Deck• Efflorescence• Functionally Obsolete• Pier• Scour• Spalling• Structurally Deficient• Superstructure• Substructure

Page 16: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

16

MILL CREEK BRIDGE

• Spalling and scaling on spans

• Cracking on deck

• Deteriorated and substandard bridge railing

• Spalling, cracking, scaling, and efflorescence on superstructure and substructure

• Undermining along both abutments

Page 17: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

17

UPPER THOROFARE BRIDGE

• Scaling and spalling on deck

• Deteriorated and substandard bridge railing

• Spalling, cracking, scaling, and

efflorescence on substructure

• Undermining along north

abutment

• Scour Critical

Page 18: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

18

MIDDLE THOROFARE BRIDGE

• Functionally Obsolete, due to

inability to carry loads greater than

15 tons. Originally built to carry

loads of 17.5 tons.

• Cracks and spalls on deck

• Deteriorated and substandard bridge railing

• Movable span in good condition

• Cracking and spalling on

substructure

• Scour Critical

Page 19: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

19

ON-GOING MAINTENANCE

• Bridge Railing Upgrades

• Addition of EZ-Pass

• Any Necessary Repairs

Page 20: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

20

EXISTING CONDITIONS REVIEW

Automatic Traffic Recorders (ATRs) were installed at three locations along the corridor:

Mill Creek Bridge• Peak Season = N/A• Off-Peak Season = 2,207 vehicles per day (vpd)

Upper Thorofare Bridge• Peak Season = 9,898 vpd• Off-Peak Season = 1,990 vpd

Middle Thorofare Bridge• Peak Season = 9,901 vpd• Off-Peak Season = 1,720 vpd

Turning Movement Counts (TMCs) conducted at the intersection of NJ 109 and Ocean Drive (CR 621)

Traffic Data

Structural

Roadway

Utilities, ITS, Roadway Lighting

Environmental Screening

Page 21: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

21

EXISTING CONDITIONS REVIEW

Peak Hours along Ocean Drive

Peak SeasonAM Peak Hour 8:00 – 9:00 AM 618 vehiclesPM Peak Hour 4:45 – 5:45 PM 1,376 vehiclesSaturday Peak 12:00 – 1:00 PM 1,488 vehicles

Off-Peak SeasonAM Peak Hour 7:45 – 8:45 AM 554 vehiclesPM Peak Hour 3:45 – 4:45 PM 623 vehiclesSaturday Peak 12:15 – 1:15 PM 526 vehicles

Traffic Data

Structural

Roadway

Utilities, ITS, Roadway Lighting

Environmental Screening

Peak season volumes are more than double during the PM and Saturday peaks.

Page 22: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

22

EXISTING CONDITIONS REVIEW

Marine Traffic• Bridge Opening Data 2015 – 2017

• Seasonal Peak - Memorial Day to Labor Day

• Seasonal Peak accounts for 60% of openings

Traffic Data

Structural

Roadway

Utilities, ITS, Roadway Lighting

Environmental Screening

2015 2016 2017 Average

Total: 5,223 5,642 5,203 5,356

Off Peak: 1,898 2,446 2,050 2,131

Peak: 3,325 3,196 3,153 3,225

Peak % 64% 57% 61% 60%

Bridge Openings (per year)

Page 23: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

23

EXISTING CONDITIONS REVIEW

Traffic Operations

• Level of Service (LOS) analyses conducted for the

intersection of NJ 109 and Ocean Drive

• Traffic operates at acceptable LOS during the Off-Peak

Non-Motorized Activity

• Pedestrians and bicyclists not observed during TMCs

(December, 2017)

• Bicyclists, including employees in the fishing, restaurant

and hotel industries, use Ocean Drive for commuting

Traffic Data

Structural

Roadway

Utilities, ITS, Roadway Lighting

Environmental Screening

*Additional traffic data will be collected during the Summer of 2018*

Page 24: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

24

EXISTING CONDITIONS REVIEW

Traffic Safety and Crash Review• 2014-2016 NJDOT data

Traffic Data

Structural

Roadway

Utilities, ITS, Roadway Lighting

Environmental Screening

Crash Type Total # of Crashes Percentage

Same Direction – Rear End 8 25.8%

Fixed Object 11 35.5%

Right Angle 3 9.7%

Opposite Direction - Sideswipe 3 9.7%

Other 2 6.5%

Non-Fixed Object 1 3.2%

Left Turn/U-Turn 1 3.2%

Same Direction - Sideswipe 1 3.2%

Struck Parked Vehicle 1 3.2%

TOTAL 31 100.0%

Page 25: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

25

EXISTING CONDITIONS REVIEW

Traffic Safety and Crash Review• 2014-2016 NJDOT data

• Crashes at the bridges are higher than the state-wide crash rate

Traffic Data

Structural

Roadway

Utilities, ITS, Roadway Lighting

Environmental Screening

Project Segment MilepostShoulder

present?Crash Rate

State-wide Crash

Rate (2016) *

NJ 109 to Mill Creek Bridge 0.00 - 0.80 Yes 1.41 3.90

Mill Creek Bridge 0.80 - 0.85 No 9.03 2.64

Mill Creek Bridge to Upper Thorofare Bridge 0.85 - 1.30 Yes 1.50 3.90

Upper Thorofare Bridge 1.30 - 1.36 No 11.29 2.64

Upper Thorofare Bridge to Middle Thorofare Bridge 1.36 - 1.70 Yes 2.66 3.90

Middle Thorofare Bridge 1.70 - 1.88 No 8.78 2.64

Middle Thorofare Bridge to Madison Avenue 1.88 - 2.75 Yes 1.82 3.90

* Source: NJDOT Crash Rates by Cross Section Geometryfor State and Interstate Routes (2006-2016). County RouteCrash rates by Cross Section Geometry are not available.

Page 26: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

26

EXISTING CONDITIONS REVIEW

• Classified as Rural Minor Arterial

• Urban Minor Arterial east of Fish Dock Road

• Cape May County jurisdiction

• Posted speed limits vary

• Travel way 24’ on pavement, 20’ wide on bridges

• Shoulders vary from 0’ to 16’ wide

• Lack of shoulders on bridges restricts sight distances

• Susceptible to flooding due to low elevation

• Substandard horizontal curves at the southern and

northern study limits

• Vertical curve at the Middle Thorofare Bridge

• Toll booth on the Middle Thorofare Bridge

• No dedicated pedestrian or bicycle facilities within the

study area

Traffic Data

Structural

Roadway

Utilities, ITS, Roadway Lighting

Environmental Screening

Page 27: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

27

EXISTING CONDITIONS REVIEW

Inventory of Regulated Resources:• Cultural resources• Parklands• Sensitive receptors to air and noise• Wetlands• Surface water resources• Floodplains• Protected habitat and species• Hazardous materials• Community facilities• Socioeconomics• Historic Landmarks• Environmental justice communities

Federal Authorizations identified

State Permits/Approval/Coordination identified

Traffic Data

Structural

Roadway

Utilities, ITS, Roadway Lighting

Environmental Screening

Purpose of the Environmental Screening:Identify fatal flaws that would prevent the project from advancing to construction.Identify resources for which impacts should be considered as part of the alternatives analysis.

Page 28: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

28

EXISTING CONDITIONS REVIEW

Utilities with facilities within the project limits:

• Atlantic City Electric

• South Jersey Gas

• Verizon

• Comcast

• Township of Lower Municipal Utilities – Water

• Township of Lower Municipal Utilities – Sanitary Sewer

Traffic Data

Structural

Roadway

Utilities, ITS, Roadway Lighting

Environmental Screening

Page 29: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

29

PURPOSE AND NEED

“The LCD Phase involves drafting a well-defined and well-justified Purpose & Need Statement focusing on the primary transportation need to be addressed.”

Community Outreach

Data Collection

ConceptualAlternative Selection

Environmental Resources

Purpose &Need

Statement

The Purpose & Need Statement will be used to develop and evaluate potential roadway and bridge alternatives.

Page 30: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

30

COMMUNITY INVOLVEMENT

The Public Outreach Approach is ITERATIVE

Present initial concepts

Stakeholder/ Public

feedback

Concept refinement

Page 31: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

31

Meeting Set #1 (Completed Today) – Existing Conditions- Local Officials Briefing- Community Stakeholders Meeting- Public Information Center

Meeting Set #2 (Summer 2018) – Present Alternatives- Local Officials Briefing- Community Stakeholders Meeting- Public Information Center

Meeting Set #3 (Fall 2018) – Present PPA- Local Officials Briefing- Community Stakeholders Meeting- Public Information Center

COMMUNITY INVOLVEMENT - MEETINGS

Page 32: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

32

Community Input Survey – Please Provide Input• Tell us how and when you use the Ocean Drive Causeway• Help us understand who is using the causeway• Let us know what you think are the issues• Results will be used to help make decisions – What should we consider

when developing alternatives?

COMMUNITY INVOLVEMENT - SURVEY

Copies at the sign-in deskVisit project website: www.capemaytwomilebridge.com

Page 33: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

33

NEXT STEPS

• Gather and Summarize Community Input Survey Feedback (Spring 2018)

• Finalize Purpose & Need Statement(Spring 2018)

• Develop Alternatives(Spring 2018): • No Build• Rehabilitation• Build - In Place• Build - New Alignment

Page 34: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

34

NEXT STEPS

Public Information Center #2

SUMMER 2018

Alternatives Presentation

Public Information Center #3

FALL 2018

Preliminary Preferred Alternative

Page 35: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

35

NEXT STEPSProject website

https://capemaytwomilebridge.com/

Page 36: PowerPoint Presentation · 2018-05-08 · 7 PUBLIC INPUT PROCESS DURING LOCAL CONCEPT DEVELOPMENT Meeting #1 (Today) Provide Information Obtained During Data Collection and Obtain

36

DISCUSSION

Questions and Comments