Post Go-Live Questionnaire

6
Post Go-Live Questionnaire EVO31 Post go-live questionnaire 1 Project Date Project Manager (Pastel) Project Manager (Cust) Enter customer name Objective: The objective of this questionnaire is to document the results and possible issues of the initial Pastel Evolution Go-Live and to determine whether additional services and/or enhancement are desired or recommended to gain additional value from the Pastel Evolution implementation. This questionnaire should be discussed with the customer about two to three weeks after initial go-live. Contents Pastel Evolution Go-Live Results................................................................................................................... 2 Project Management .................................................................................................................................. 2 System Management ................................................................................................................................. 2 System Availability and Activity Check ....................................................................................................... 3 System Administration ................................................................................................................................ 4 User Acceptance ........................................................................................................................................ 4 Enhancements ............................................................................................................................................... 5 Functions .................................................................................................................................................... 5 Configuration .............................................................................................................................................. 5 Documentation ........................................................................................................................................... 6 Signatures .................................................................................................................................................. 6

description

questionaire post implementation

Transcript of Post Go-Live Questionnaire

  • Post Go-Live Questionnaire

    EVO31 Post go-live questionnaire 1

    Project Date Project Manager (Pastel) Project Manager (Cust)

    Enter customer name

    Objective:

    The objective of this questionnaire is to document the results and possible issues of the initial Pastel Evolution Go-Live and to determine whether additional services and/or enhancement are desired or recommended to gain additional value from the Pastel Evolution implementation.

    This questionnaire should be discussed with the customer about two to three weeks after initial go-live.

    Contents

    Pastel Evolution Go-Live Results ................................................................................................................... 2

    Project Management .................................................................................................................................. 2

    System Management ................................................................................................................................. 2

    System Availability and Activity Check ....................................................................................................... 3

    System Administration ................................................................................................................................ 4

    User Acceptance ........................................................................................................................................ 4

    Enhancements ............................................................................................................................................... 5

    Functions .................................................................................................................................................... 5

    Configuration .............................................................................................................................................. 5

    Documentation ........................................................................................................................................... 6

    Signatures .................................................................................................................................................. 6

  • Post Go-Live Questionnaire

    EVO31 Post go-live questionnaire 2

    Pastel Evolution Go-Live Results Verify that all components of Pastel Evolution implemented during the initial go-live are functional and have generated the desired results.

    Project Management

    Is the backup strategy performed on a regular basis? Yes No

    Have there been any issues with the backup strategy? Yes No

    If yes, please provide additional detail.

    Is recovery of the database possible at any time using the current backups?

    Yes No

    If no, please provide additional detail.

    Have there been any issues with the stability of the database? Yes No

    If yes, please provide additional detail.

    System Management

    Has all hardware been installed and operative?

    Yes No

    If no, please provide additional detail.

    Has system performance been satisfactory?

    Yes No

    If no, please provide additional detail.

    Are unique business processes addressed?

    Yes No

    If no, please provide additional detail.

    Are SDK developments and add-ons satisfactory?

    Yes No

    If no, please provide additional detail.

    Other comments:

  • Post Go-Live Questionnaire

    EVO31 Post go-live questionnaire 3

    System Availability and Activity Check

    Are all interfaces operative? Yes No

    If no, please provide additional detail.

    Is document printing working properly? Yes No

    If no, please provide additional detail.

    Could all in-scope key business processes be completed properly with the system?

    Yes No

    If no, please provide additional detail.

    Have the following document types been created in the system:

    Sales documents Yes No

    Purchasing documents Yes No

    Accounting documents Yes No

    Inventory transactions Yes No

    If no, please provide additional information.

    Are bank reconciliations performed? Yes No

    If no, please provide additional information.

    Can customer run all reports as required? Yes No

    If no, please provide additional information.

    Has period-end closing been successfully completed? Yes No

    If no, please provide additional information.

    Other comments:

  • Post Go-Live Questionnaire

    EVO31 Post go-live questionnaire 4

    System Administration

    Has customer been able to complete all system administration procedures?

    Yes No

    If no, please provide additional information.

    Has outside support from consulting partner or Pastel been needed? Yes No

    If yes, please provide additional information.

    Were there any escalations? Yes No

    If yes, please provide additional information.

    Other comments:

    User Acceptance

    Do all users know their part of the system and how to operate it? Yes No

    If no, please provide additional information.

    Is there any need for additional training? Yes No

    If yes, please provide additional information.

  • Post Go-Live Questionnaire

    EVO31 Post go-live questionnaire 5

    Enhancements Additional possibilities with Pastel Evolution to further the return gained from the software investment made by the customer.

    Functions

    Are there any additional functions/requirements in the areas listed below that customer would like to have addressed?

    Functional area Comments

    Administration Yes No

    Sales Yes No

    Purchasing Yes No

    Accounting Yes No

    Banking Yes No

    Inventory Management Yes No

    Service Management Yes No

    Others, please list:

    ___________________

    Configuration

    Which reports are frequently being used by the customer?

    List reports needed but currently not available in customer Pastel Evolution implementation?

    Is MS Excel being used?

    Are alerts needed? If yes, in which areas?

    Are additional interfaces needed? If yes, please elaborate.

    Are additional queries needed? If yes, where?

    Other comments:

  • Post Go-Live Questionnaire

    EVO31 Post go-live questionnaire 6

    Documentation

    Have all business processes been documented?

    Yes No

    If no, please provide additional information.

    Signatures By signing below, the parties agree that the information in this document is correct and that the Pastel Evolution system is ready in production database.

    Signature: ______________________________ Signature: __________________________

    Name: ______________________________ Name: ______________________________

    Position held: ______________________________ Position held: ______________________________