Transcript of PN Facility Report WEEK 45
Engineering
Design &
DevelopmentSM EDD OPERATIONS
Prepared by:Julius O. SalacupResident EngineerSM Center Las Piñas
SM CENTER LAS PIÑASEngineering Weekly ReportOctober 29 -04November, 2012
Engineering
Design &
Development
SMPN GENERAL INFORMATION SHEET
ALABANG-ZAPOTE ROAD, BRGY. PAMPLONA DOS, LAS PIÑAS C ITY
DATE OF OPENING: OCTOBER 02, 2009 LAND AREA: 28,626 sq. m.
CFA: 40,267 sq. m. TOTAL LEASABLE AREA: 16,308.54 sq. m.
FOOD TENANTS: 12 NON-FOOD TENANTS: 41
OPEN PARKING: 311 slots MOTORCYCEL PARKING: 80 slots
PARKING FOR PWD: 6 slots
CINEMA SEATING CAPACITY (NO CINEMA)
CINEMA N/A CINEMA N/A CINEMA N/A CINEMA N/A
SM CENTER LAS PIÑAS
WEEKLY REPORT (29OCT TO 04NOV 2012)
Engineering
Design &
Development
SM CENTER LAS PIÑAS
WEEKLY REPORT (29OCT TO 04NOV 2012)
SMPN GENERAL INFORMATION SHEETALABANG-ZAPOTE ROAD, BRGY. PAMPLONA DOS, LAS PIÑAS C ITY
ELECTRICITY DISTRIBUTOR: MERALCO CKT. #49xd
SUBSTATION CAPACITY: 1x3MVA; 13.5KV/460V; 3Ø; 60Hz; ELE TTROMECCANICA COLOMBO
GENSETS CAPACITY: 2x21.25MVA; 460V; 3Ø; 60Hz; CATSYNCHRO PANEL:Ed. Ent.
SHOCKBLOCK: YES
DIESEL TANK CAPACITY: 2x4642gal. (9284L – GROSS)
CHILLERS CAPACITY: 2x500TR; CVHF485; 275KW; TRANE
COOLING TOWER CAPACITY: 2x500TR; 50Hp; BAC STP CAPACIT Y: SBR TYPE; 142 cu.m.
TOTAL NO OF AHU: 24 UNITS PRIMARY AERATION BLOWERS: 1x7 .5Hp TECO
TOTAL NO OF FCU: 5 UNITS SECONDARY AERATION BLOWERS: 2 x7.5Hp TECO
TOTAL NO OF KEF: 8UNITS TTP FILTER PUMPS 2x2Hp
TOTAL NO OF KSF: 6 UNITS LPG FARM CAPACITY: 8x250kg(MA CRO)
TOTAL NO OF FAF: 7 UNITS FDAS ADDRESSABLE TYPE
TOTAL NO OF EF: 6 UNITS CPS PUMP (POTABLE): 2x7.5Hp
TOTAL NO OF SF 2 UNITS CPS PUMP (NON-POTABLE): 2x7.5Hp
TOTAL NO OF SEF: 4 UNITS FIRE PUMP: 1x75Hp
TOTAL NO OF PB: JOCKEY PUMP: 1x5Hp
TOTAL NO OF LEF: CISTERN TANK CAPACITY: 363.8cu.m.
WALKALATOR: (HYUNDAI): 2x7.5Hp; FIRE TANK CAPACITY: 459 .8cu.m.
FREIGHT ELEVATORS (HYUNDAI): 4x15Hp; 1200kg cap. NON-P OTABLE TANK CAPACITY: 21 cu.m.
PASSENGER ELEVATORS (HYUNDAI):
1x15Hp; 60m/min. 1200kg cap.
Engineering
Design &
Development
REPORT OUTLINE:
1. FACILITIES STATUS UPDATES.
2. EQUIPMENTS BREAKDOWN REPORT.
3. SMR UPDATES.
4. UTILITIES CONSUMPTION, PRODUCTION AND DELIVERIES UPDATES.
5. ENGINEERING AND MAINTENANCE ACTIVITIES SUMMARY AND UPDATES.
(BUILDING AND PERIMETER)
6. BUSTED LIGHTS MONITORING UPDATES.
7. COMFORT ROOMS MONITORING UPDATES.
8. ISSUES AND NEEDS LIST.
SM CENTER LAS PIÑAS
WEEKLY REPORT (29OCT TO 04NOV 2012)
Engineering
Design &
Development
SM CENTER LAS PIÑAS
WEEKLY REPORT (29OCT TO 04NOV 2012)
1. FACILITIES STATUS UPDATES.
CATEGORY 29OCT 30OCT 31OCT 01NOV 02NOV 03NOV 04NOV
POWER INTERRUPTIONS 0 0 0 0 0 1 0
WATER SUPPLY INTERRUPTIONS 0 0 0 0 0 0 0
GAS SUPPLY INTERRUPTIONS 0 0 0 0 0 0 0
TOTAL INCIDENTS: 0 0 0 0 0 0 0
DESCRIPTION OF INTERRUPTION INCIDENTSCATEGORY DESCRIPTION
POWER INTERRUPTIONS The fluctuation last for seconds
WATER SUPPLY INTERRUPTIONS
GAS SUPPLY INTERRUPTIONS .
Engineering
Design &
Development
SM CENTER LAS PIÑAS
WEEKLY REPORT (29OCT TO 04NOV 2012)
2. EQUIPMNENTS BREAKDOWN REPORT.EQUIPMENT DESCRIPTION
CAUSE OF DOWNTIME DATE OF DOWNTIME
DAYS NON-OPERATIONAL STATUS/REMARKS
FREIGHT ELEVATOR 1 (HYPERMARKET)
DAMAGE CAR DOOR 25SEP2012 42
The liability was transferred to Mall Operation, already requested quotation to Hyundai regarding the damage of the said freight, On Monday Nov. 5, 2012
Engineering
Design &
Development
3. SMR UPDATES.RECEIVED SMR
29OCT TO 04NOV2012COMPLETED SMR
1JAN2012 TO 04NOV2012TOTAL RECEIVED SMR
1JAN2012 TO 04NOV2012PENDING 2012 PROJECTS FOR
SMR PREPARATION
1 24 38 6
SMR BREAKDOWNCATEGORY / NATURE OF
WORKSCOMPLETED SMR
1JAN2012 TO 04NOV2012TOTAL RECEIVED SMR
1JAN2012 TO 04NOV2012PENDING 2012 PROJECTS FOR
SMR PREPARATION
ELECTRICAL AND AUXILLIARY 13 14 1
PLUMBING AND SANITARY 3 4 1
AIR CONDITIONING AND VENTILATION
9 10 1
LPG SUPPLY 0 0 0
CIVIL AND WATERPROOFING 2 2 2
PUMPS AND MOTORS 6 6 0
FDAS 0 0 1
SM CENTER LAS PIÑAS
WEEKLY REPORT (29OCT TO 04NOV 2012
Engineering
Design &
Development
SM CENTER LAS PIÑAS
WEEKLY REPORT (29OCT TO 04NOV 2012)
4. UTILITIES CONSUMPTION, PRODUCTION AND DELIVERIES UPDATESDESCRIPTION 29-OCT 30-OCT 31-OCT 01-NOV 02-NOV 03-NOV 04-NOV
ELECTRICITY CONSUMPTION 178kWh 159kWh 213kWh 200kWh 197kWh 189kWh 253kWh
DIESEL FUEL CONSUMPTION 43.81L
DIESEL FUEL DELIVERIES
POTABLE WATER CONSUMPTION 317 cu.m.
309 cu.m.
289 cu.m.
316 cu.m.
210 cu.m.
199cu.m.
489 cu.m.
RE-USE WATER CONSUMPTION 45 cu.m.
43 cu.m.
35 cu.m.
52 cu.m.
42 cu.m.
39 cu.m.
29 cu.m.
RE-USE WATER PRODUCTION 226 cu. m.
167 cu.m
178 cu. m
145 cu. m
130cu. m
129 cu. m
172 cu. m
COOLING TOWER POTABLE WATER CONSUMPTION
26 cu.m.
19 cu.m.
7 cu.m.37
cu.m.38
cu.m.20
cu.m.19
cu.m.
COOLING TOWER RE-USE WATER CONSUMPTION
64 cu.m.
76 cu.m.
48 cu.m.
58 cu.m.
47 cu.m.
47 cu.m.
58 cu.m.
LPG CONSUMPTION 445kg 217kg 440kg 390kg 456kg 494kg 457 kg
LPG DELIVERIES 965kg
Engineering
Design &
Development
SM CENTER LAS PIÑAS
WEEKLY REPORT (29OCT TO 04NOV 2012)
5. ENGINEERING AND MAINTENANCE ACTIVITIES SUMMARY - T ENANTS
CATEGORY TENANT SERVICE CALLS
SERVICE REQUESTS
ELECTRICAL AND AUXILLIARY 2 0
PLUMBING AND SANITARY 1 0
AIR CONDITIONING AND VENTILATION 1 0
LPG SUPPLY 0 0
WATER LEAKS 1 0
5. ENGINEERING AND MAINTENANCE ACTIVITIES SUMMARY – B UILDING AND PERIMETER
CATEGORY NEW INSTALLATION
PREVENTIVE CORRECTIVE
ELECTRICAL AND AUXILLIARY 1 0 2
PLUMBING AND SANITARY 0 0 1
AIR CONDITIONING AND VENTILATION 0 0 1
LPG SUPPLY 0 0 0
CIVIL 0 0 1
Engineering
Design &
Development
SM CENTER LAS PIÑAS
WEEKLY REPORT (29OCT TO 04NOV 2012)
5. ENGINEERING AND MAINTENANCE ACTIVITIES UPDATES – B UILDING AND PERIMETER AND TENANT
DESCRIPTION DESCRIPTIONDE clogging of Washtub at Employees CR DE clogging of Washtub at Employees CR
Engineering
Design &
Development
5. ENGINEERING AND MAINTENANCE ACTIVITIES UPDATES – B UILDING AND PERIMETER AND TENANT
SM CENTER LAS PIÑAS
WEEKLY REPORT (29OCT TO 04NOV 2012)
DESCRIPTION DESCRIPTIONReplacement of MH at Mall Canopy Replacement of MH at Mall Canopy
Engineering
Design &
Development
5. ENGINEERING AND MAINTENANCE ACTIVITIES UPDATES – B UILDING AND PERIMETER TENANT
DESCRIPTION DESCRIPTIONReplacement of Lamp Post at South Parking Cleaning Hypermarket Foul odor source
SM CENTER LAS PIÑAS
WEEKLY REPORT (29OCT TO 04NOV 2012)
Engineering
Design &
Development
5. ENGINEERING AND MAINTENANCE ACTIVITIES UPDATES – B UILDING AND PERIMETER AND TENANT
DESCRIPTION DESCRIPTIONRectification of Lamp post at west Tunnel Rectification of Lamp post at west Tunnel
SM CENTER LAS PIÑAS
WEEKLY REPORT (29OCT TO 04NOV 2012)
Engineering
Design &
Development
5. ENGINEERING AND MAINTENANCE ACTIVITIES UPDATES – B UILDING AND PERIMETER AND TENANT
DESCRIPTION DESCRIPTIONRepainting of STP Wall Repainting of STP Tank
SM CENTER LAS PIÑAS
WEEKLY REPORT (29OCT TO 04NOV 2012)
Engineering
Design &
Development
5. ENGINEERING AND MAINTENANCE ACTIVITIES UPDATES – B UILDING AND PERIMETER AND TENANT
DESCRIPTION DESCRIPTIONRectification of Executive Optical Washtub Rectification of Executive Optical Washtub
SM CENTER LAS PIÑAS
WEEKLY REPORT (29OCT TO 04NOV 2012)
Engineering
Design &
Development
5. ENGINEERING AND MAINTENANCE ACTIVITIES UPDATES – B UILDING AND PERIMETER AND TENANT
DESCRIPTION DESCRIPTIONTightening handrail of Moving Walk-upward Tightening handrail of Moving Walk-upward
SM CENTER LAS PIÑAS
WEEKLY REPORT (29OCT TO 04NOV 2012)
Worn-outhandrail
Engineering
Design &
Development
LOCATIONQTTY. OF BUSTED
LIGHTSQTTY OF REPLACED
BUSTED LIGHTSREMARKS
MALL INTERIOR AREA
MALL AREA 1F 2 2Trouble shoot and replaced busted lightat wall-shop
MALL AREA 2F 0 0
TENANT FRONT SIGNAGES 0 0
AD BOXES 0 0
OFFICES 0 0
UTILITY ROOMS 0 0
COMFORT ROOMS 0 0
ELEVATORS 0 0
MALL NIGHT LIGHTS 0 0
TENANT NIGHT LIGHTS 0 0
BACK ALLEYS, HALLWAYS AND STAIRCASES.
0 0
TOTAL: 2 2
SM CENTER LAS PIÑAS
WEEKLY REPORT (29OCT TO 04NOV 2012)
6. BUSTED LIGHT MONITORING UPDATES
Engineering
Design &
Development
LOCATIONQTTY. OF BUSTED
LIGHTSQTTY OF REPLACED
BUSTED LIGHTSREMARKS
MALL EXTERIOR AREA
CANOPY LIGHTS, AL FRESCO LIGHTS. 1 1Busted lights at entrance stairway, Already replaced
SM LOGO (FAÇADE) 0 0
LIGHTED SIGNAGES (FAÇADE) 0 0
DROPDOWN SIGNAGES 0 0
ACCENT LIGHTS 0 0
SM LOGO (PYLON TOWER) 0 0
SIGNAGES (PYLON TOWER) 5 0Defective wiring, already request for quotation
CINEMA SIGNAGES N/A N/A
COVERED WALKWAYS AND PEDESTRIAN OVERPASS
0 0
PARKING LIGHTS 21 0Defective emergency lights at covered car park and one fluorescent lamp, already RS a battery
PARKING TOWER LIGHTS 0 0
TRANSPORTATION TERMINAL LIGHTS 0 0
PEDESTRIAN OVERPASS 0 0
TOTAL: 27 1
6. BUSTED LIGHT MONITORING UPDATES
SM CENTER LAS PIÑAS
WEEKLY REPORT (29OCT TO 04NOV 2012)
Engineering
Design &
Development
7. COMFORT ROOMS MONITORING UPDATES
LOCATION
EVENT CENTER
FOODCOURT RDU1 CINEMA 1&2 CINEMA 3&4EMPLOYEECR SCMC
ADMIN
DF RDF DF RDF DF RDF DF RDF DF RDF DF RDF
ELECTRICAL WIRINGS 0 0 n/a n/a 0 0 n/a n/a n/a n/a 0 0
GENERAL LIGHTS 0 0 n/a n/a 0 0 n/a n/a n/a n/a 1 0
PLUMBING AND SANITARY 0 0 n/a n/a 0 0 n/a n/a n/a n/a 1 1
AIRCONDITIONING & VENTILATION 0 0 n/a n/a 0 0 n/a n/a n/a n/a 0 0
CIVIL 0 0 n/a n/a 0 0 n/a n/a n/a n/a 0 0
SM CENTER LAS PIÑAS
WEEKLY REPORT (29OCT TO 04NOV 2012)
Employees CR SCMC ADMIN:
One defective emergency light battery, already RS for replacementClogged washtub and employees CR already rectified
Engineering
Design &
Development
SM CENTER LAS PIÑAS
WEEKLY REPORT (29OCT TO 04NOV 2012)
8. ISSUES AND NEEDS LIST
DESCRIPTION STATUS REMARKS
REPLACEMENT OF THE BURN-OUT DRUM EXTENSION BY SOUTHERNSTAR(JANITORIAL)
NOT YET REPLACED
ALREADY SENT MESSAGE TO BAO’S FOR THE REPLACEMENTOF THE SAID EXTENSION
DEFECTIVE LADDER LIFT BY (TRIPPLE SEVEN AND SOUHTERNSTAR)
NO INITIATED REPAIRALREADY SENT MESSAGE TO BAO’S FOR THE REPLACEMENTOF THE SAID EXTENSION
PONDING AT FREIGTH ELEVATOR # 1 PIT ALREADY DRAINEDTHE WATER IS CAME FROM SEEPAGES AT GROUND
TROUBLE SHOOTING OF PYLON TOWER SPOT LIGHTS
ALREADY REQUESTED FOR QUOTATION
QUOTATION ALREADY SENT, WAITNG FOR QUOTATION OF OTHER CONTRACTOR
DEFECTIVE MACHINE ROOM DOOR KNOBALREADY RAISE THIS TO CHARLIE FOR RECTIFICATION
THE DOOR KNOB WAS ALREADY RECTIFIED
Engineering
Design &
Development
END OF PRESENTATION-THANK YOU-
SM CENTER LAS PIÑAS
WEEKLY REPORT (29OCT TO 04NOV 2012)