PM Assignment2 AETTZG523 (2)
-
Upload
gopal-athani -
Category
Documents
-
view
214 -
download
0
description
Transcript of PM Assignment2 AETTZG523 (2)
![Page 1: PM Assignment2 AETTZG523 (2)](https://reader036.fdocuments.us/reader036/viewer/2022073120/563db79d550346aa9a8cb554/html5/thumbnails/1.jpg)
Birla Institute of Technology & Science, Pilani
Work-Integrated Learning Programmes Division
Second Semester 2014-2015
Assignment-2
(EC-1)
Course No. : AETT ZG523
Course Title : Project Management
Weightage : 10%
Submission date : 20-June 2015
N.B. Both assignments 1 & 2 below should be attempted. Do not copy- work independently in
order to derive value and to get credit.
1. You are serving as Project Manager on a critical communications project, and are now well
along in the project. The following table summarizes the actual progress as of today (all figures
are given in thousands of rupees) Develop a narrative status report for the board of directors of
the chain store that discusses the status of the project to date and at completion. Be as specific as
you can using numbers given and those you might develop. Remember, your audience is not
familiar with the jargon used by project managers and computer software personnel; therefore,
some explanation may be necessary. Your report will be evaluated on your detailed use of the
data, your total perspective of the current status and future status of the project, and your
recommended changes (if any). NAME PV EV AC SV CV BAC EAC
COMMUNICATIONS PROJECT 420 395 476 -25 -81 915 1103
H 1.0 HARDWARE 92 88 72 -4 16 260 213
H 1.1 Hardware specifications (DS) 20 20 15 0 5 20 15
H 1.2 Hardware design (DS) 30 30 25 0 5 30 25
H 1.3 Hardware documentation (DOC) 10 6 5 -4 1 10 8
H 1.4 Prototypes (PD) 2 2 2 0 0 40 40
H 1.5 Test prototypes (T) 0 0 0 0 0 30 30
H 1.6 Order circuit boards (PD) 30 30 25 0 5 30 25
H 1.7 Preproduction models (PD) 0 0 0 0 0 100 100
OP 1.0 OPERATING SYSTEM 195 150 196 -45 -46 330 431
OP 1.1 Kernel specifications (DS) 20 20 15 0 5 20 15
OP 1.2 Drivers 45 55 76 10 -21 70 97
OP 1.2.1 Disk drivers (DEV) 25 30 45 5 -15 40 60
OP 1.2.2 I/O drivers (DEV) 20 25 31 5 -6 30 37
OP 1.3 Code software 130 75 105 -55 -30 240 336
OP 1.3.1 Code software (C) 30 20 40 -10 -20 100 200
OP 1.3.2 Document software (DOC) 45 30 25 -15 5 50 42
OP 1.3.3 Code interfaces (C) 55 25 40 -30 -15 60 96
OP 1.3.4 Beta test software (T) 0 0 0 0 0 30 30
U 1.0 Utilities 87 108 148 21 -40 200 274
U 1.1 Utilities specifications (DS) 20 20 15 0 5 20 15
U 1.2 Routine utilities (DEV) 20 20 35 0 -15 20 35
U 1.3 Complex utilities (DEV) 30 60 90 30 -30 100 150
U 1.4 Utilities documentation (DOC) 17 8 8 -9 0 20 20
U 1.5 Beta test utilities (T) 0 0 0 0 0 40 40
S 1.0 System integration 46 49 60 3 -11 125 153
S 1.1 Architecture decisions (DS) 9 9 7 0 2 10 8
S 1.2 Integration hard/soft (DEV) 25 30 45 5 -15 50 75
S 1.3 System hard/software test (T) 0 0 0 0 0 20 20
S 1.4 Project documentation (Doc) 12 10 8 -2 2 15 12
S 1.5 Integration acceptance testing (T) 0 0 0 0 0 30 30
2. From your experience, consider any one project that you worked on or managed. Giving a brief
description of the project, discuss the following:
a. The project organization structure used. Was it appropriate?
b. The communication plan implemented. Did it serve the requirements of the project?
c. Draw the project priority matrix for the project.
d. How did the project perform on the three criteria for project success?
e. Prepare a suitable lessons learned document in an appropriate format—doc file attached
![Page 2: PM Assignment2 AETTZG523 (2)](https://reader036.fdocuments.us/reader036/viewer/2022073120/563db79d550346aa9a8cb554/html5/thumbnails/2.jpg)
Glossary: EV Earned value for a task is simply the percent complete times its original budget.
Stated differently, EV is the percent of the original budget that has been earned by actual work completed. [The older acronym for this value was BCWP—budgeted cost of the work performed.] PV The planned time-phased baseline of the value of the work scheduled. An approved cost estimate of the resources
scheduled in a time-phased cumulative baseline [BCWS—budgeted cost of the work scheduled]. AC Actual cost of the work completed. The sum of the costs incurred in accomplishing work. [ACWP—actual cost of the
work performed]. CV Cost variance is the difference between the earned value and the actual costs for the work completed to date where
CV = EV - AC. SV Schedule variance is the difference between the earned value and the baseline line to date where SV = EV - PV. BAC Budgeted cost at completion. The total budgeted cost of the baseline or project cost accounts. EAC Estimated cost at completion. ETC Estimated cost to complete remaining work. VAC Cost variance at completion. VAC indicates expected actual over- or underrun cost at completion.
Suggested format-headings for “lessons learned” documentation:
INTRODUCTION
LESSONS LEARNED APPROACH
LESSONS LEARNED FROM THIS PROJECT
The following chart lists the lessons learned for the project. These lessons are categorized by
project knowledge area and descriptions, impacts, and recommendations are provided for
consideration on similar future new construction projects. It is important to note that not only
failures or shortcomings are included but successes as well.
Category Issue Name Problem/Success Impact Recommendation
Procurement
Management
Human
Resources
Management
Scope
Management
Quality
Management
Risk
Management
LESSONS LEARNED KNOWLEDGE BASE / DATABASE .
LESSONS LEARNED APPLIED FROM PREVIOUS PROJECTS
PROCESS IMPROVEMENT RECOMMENDATIONS