Plant Parameter Envelope: Concept and Application for OPG ...
Transcript of Plant Parameter Envelope: Concept and Application for OPG ...
Plant Parameter Envelope: Concept and Application for
OPG New Nuclear at Darlington
Presentation to the CNSC
Jack Vecchiarelli Section Manager, Safety Analysis
Darlington New Nuclear Project
December 9, 2009
2
To brief CNSC staff on the Plant Parameter Envelope (PPE) concept and its licensing application for the OPG New Nuclear at Darlington project
Purpose of Presentation
3
IntroductionBackground on PPE Concept (origin, etc.)Use of PPE
PPE Development ProcessOrganization of PPESummary of PPE
Site ParametersDesign Parameters
• Reactor Class Specific Parameters• Vendor Design Specific Parameters
Conclusion
Outline
4
The PPE is a tabular set of data that:
-relates to the interaction between a nuclear power plant and the site/environment
-provides a bounding envelope of plant design and site parameter values for use in the Licence To Prepare Site (LTPS) Application and Environmental Assessment (EA)
-is derived from available vendor information for multiple reactor designs
Introduction
5
5
Background
PPE approach was proposed in U.S. by Nuclear Energy Institute (NEI) to allow utilities to apply for Early Site Permits (ESP) before committing to a particular design
-ESP is analogous to Canadian site preparation licence
PPE approach has been accepted by US NRC
Used successfully by 3 U.S. utilities in obtaining ESPs:-Dominion Nuclear (North Anna site)
ESP issued November 2007
-Energy Resources Inc. (Grand Gulf site) ESP issued April 2007
-Exelon Generation Company (Clinton site) ESP issued March 2007
6 Use of PPE (1)
The PPE is used in support of the LTPS Application and EA for the OPG New Nuclear at Darlington project – before a design has been selected-evaluation of impact of plant on environment
-part of EA bounding framework
-part of exclusion zone determination
-evaluation of impact of site on plant
-site evaluation to support suitability of the site for a new build
PPE provides high-level design information consistent with CNSC INFO-0756 and RD-346 requirements
7 Use of PPE (2)
The PPE defines part of the licensing boundary/basis
-PPE is a living document which OPG will maintain
With the LTPS Application, PPE is used to demonstrate site is suitable for construction of a Nuclear Facility as bounded by the PPE
If the selected Nuclear Facility is not bounded by the PPE, the PPE will be updated and appropriate assessment of the impacts will be undertaken as required
-addressed during the more detailed design stages of the licensing process, i.e., Construction License Application
8 OPG PPE Development Process
9Development of the PPE for the
OPG New Nuclear at Darlington Project
Candesco provides draft. OPG sends PPE to vendors. AECL, Areva and GE confirm designs bounded.
Jan 2008
PPE Rev 2 submitted with LTPS Application.Sep 2009
PPE Rev 2 issued by OPG – approved by CNE.Mar 2009
PPE Rev 1 submitted to CNSC. OPG begins PPE update for Vendor Specific Design parameters.
Oct 2008
PPE Rev 1 issued by OPG – approved by CNE.Aug 2008
AECL, Areva, Westinghouse reply. PPE Rev 1 prepared. Jul 2008
OPG sends Draft PPE Rev 1 to 3 vendors.Jun 2008
PPE Rev 0 issued by OPG – approved by CNE. IO RFP issued. Three responses. OPG begins revision of PPE.
Apr 2008
OPG arranges for Independent Peer Review of draft PPE Rev 0.Feb 2008
Contractor (Candesco) analyzes data per its QA program.Aug 2007
Vendors provide data per their QA program.Jul 2007
OPG requests data on 9 designs.Jun 2007
10 Limiting Value Determination
The PPE is based on limiting values – the value for each parameter that describes the greatest impact of the plant on the site/environment, or of the site on the plant
the maximum or minimum from the set of vendor values for a given parameter, as appropriate, chosen conservatively
ACR-1000 AP1000 EPR3000 Pa 3591 Pa 4788 Pa
ACR-1000 AP1000 EPR-31.2 C -40 C -40 C
Limiting Minimum Value: Snow & Ice Load
Limiting Maximum Value: Min. Amb.Temp. for full power operation
11 Organization of the PPE
To consider multiple units on site, the PPE includes prorated values for Reactor Class Specific and Vendor Design Specific parameters.
12 Summary of PPE Tables
Site Parameters – 39 parameters related to the impact of the site on the plant, as assumed in the plant designs
Examples: snow load, earthquakes, design basis tornado
Reactor Class Specific (RCS) – 127 parameters that are similar within each reactor class (PWR, PHR)
Examples: fuel enrichment, total mass of zirconium alloy in core, heaviest construction shipment
Some RCS parameters were added by OPG to those adopted from NEI list
Vendor Design Specific – 35 parameters which address radiological effects due to nuclear fuel
Examples: Airborne effluent, liquid radwaste, solid radwaste
13 Sample PPE Values and Usage
Aquatic Environment Assessment of Environmental Effects TSD NND EA, Section 2.2.1, Project Basis for Assessment, page 2-2
228,400 L/s
(4 ACR-1000)
2.6.2 Cooling Water Flow Rate (once-through cooling)
Exclusion Zone Determination for Darlington New Nuclear Project
Section 4.0 Conclusions
3 EPR
4 AP1000
4 ACR-1000
(Table 2) Number of Reactor Units On Site
Site Evaluation of the OPG New Nuclear at Darlington – Part 6: Evaluation of Geotechnical Aspects
Section 5.1, Table 5.1-1 – “Site Parameters – Composite Table” (Relevant to Geotechnical Aspects)
718 kPa
(EPR)
1.5.2 Minimum Required Bearing Capacity (Static) – Soil Property
Site Evaluation of the OPG New Nuclear at Darlington – Part 2: Dispersion of Radioactive Materials In Air and Water
Section 3.1, Table 3.1-2 – Airborne Release Parameters (for estimation of public dose due to normal operation)
71.3 m
(AP1000)
1.1.1 Building Height
Where UsedValueParameter
14 Sample Site Parameters
EPR8274 PaDBT max pressure drop
ACR-100046 mDBT radius of maximum rotational speed
EPR368 km/hDesign Basis Tornado (DBT) max wind speed
EPR, AP1000232 km/hBasic wind speed
EPR-1 mMaximum ground water
EPR, AP1000, ACR-1000
0.3 gPeak ground acceleration
ACR-10003000 PaSnow and ice load
ACR-1000400 mm/d
100 mm/h
30 mm/15 min
Maximum rain fall rate
Limiting Reactor Limiting ValueParameter
15Sample Reactor Class Specific Parameters:
Plant Characteristics
13.5 mEPR12.7 mFoundation Embedment
65.8 mAP100071.3 mBuilding Height
60 yearsAll60 yearsDesign Life
>95% annual
>90% lifetime
EPR94%Capacity Factor
3200 MWEPR4590 MWThermal Power
1165 MW gross
1085 MW net
EPR1708 MWElectrical Output
PHR
(ACR-1000)
PWR Limiting Reactor
PWR Limiting Value
Parameter
16Sample Reactor Class Specific Parameters:
Fuel
5246
metric tons
EPR2712
metric tons
Total mass, discharged fuel
15
metric tons
EPR43
metric tons
Mass of zirconium alloys in core
115
metric tons
EPR146.26
metric tons
Mass of fuel in core
2.5%EPR5% Fuel enrichment
PHR
(ACR-1000)
PWR Limiting Reactor
PWR Limiting ValueParameter
17Sample Reactor Class Specific Parameters:
Construction
2000 to 2500EPR4200Construction population
32.9 acres EPR12.6 acresLaydown area
422 metric tons (on land)
1600 metric tons (by water)
800 metric tons(calandria)
AP-1000861.8 metric tonsHeaviest construction shipment
Length 17.37 m
Width 10.1 m
Height 10.45 m
Longest item Length 40 m
AP-1000Length 28.35 m
Width 25 m
Height 27.43 m
Diam. 39.62 m
Module dimensions
PHR
(ACR-1000)
PWR Limiting Reactor
PWR Limiting valueParameter
18Sample Reactor Class Specific Parameters:
Decommissioning
92,000 (Qty: 4)
52,600 (Qty: 4)
5,380 (Qty: 4)
21,280 (Qty: 4)
1,600
10.5 m H 17.4 m L 10.1 m W
PHR (ACR-1000)
EPR (Qty: 3)
540,000Mass non-active material (T)
EPR (Qty: 3)
45,000Mass low active material (T)
EPR (Qty: 3)
2700Mass moderately active material (T)
EPR (Qty: 3)
2,400Mass highly active material (T)
EPR350Heaviest shipment metric tons (T)
EPR25 m long 7 m diam.
Decommissioning dimensions, Largest
PWR Limiting Reactor
PWR Limiting Value
Parameter
19Sample Vendor Design Specific Parameters:
Normal Operating Source Term
2.1×1010 Bq/y9.46×109 Bq/y7.15×109 Bq/yLiquid source term
1.2×1014 Bq/y3.74×1013 Bq/y6.14×1013 Bq/yLiquid H-3 source term
5.0×1013 Bq/y1.295×1013 Bq/y6.67×1012 Bq/yGaseous H-3 emission
5.9×1013 Bq/y4.08×1014 Bq/y1.77×1015 Bq/yNormal gaseous emission source term
ACR-1000AP-1000EPRParameter
20 Conclusions
The PPE provides bounding values based on multiple vendor technologies
helps define the bounding conditions for EA purposes
facilitates robust evaluations before a reactor design has been selected
consistent with other jurisdictions (e.g. U.S.)
As such, the PPE is used by OPG to support the EA and the LTPS Application for the OPG New Nuclear at Darlington project
is a living document which OPG will maintain
represents licensing limits within a modern regulatory framework that features built-in margins
will be used to confirm selected technology is bounded by present/updated evaluations
Page 1 of 2
Canadian Nuclear Commission canadienne Safety Commission de sûreté nucléaire
P.O. Box 1046 Station B 280 Slater Street Ottawa, Ontario Canada K1P 5S9
C.P. 1046 Succursale B 280, rue Slater Ottawa (Ontario) Canada K1P 5S9
Meeting SummaryE-Docs #3472463: File/Dossier:2.01
CEAR #: 07-05-29525Date: December 9, 2009
SUBJECT OBJET
CNSC Meeting with OPG – Plant Parameter Envelope: Concept and
Application for OPG New Nuclear at Darlington
ATTENDEES
PARTICIPANTS
CNSC Marcel De Vos Barclay Howden Andrew McAllister Julie Mecke Dave Newland Doug Miller Garry Schwarz Sang Shim Ross Richardson
OPG Leslie Mitchell Jack Vecchiarelli
CEAA Jill Adams Robyn-Lynne Virtue (by teleconference)
LOCATION OF MEETING
ENDROIT DE LA RÉUNION
Canadian Nuclear Safety Commission 280 Slater Street, Ottawa (Ontario)
(Room #03-070)
DATE December 9th, 2009
TIME/HEURE 9:00 am – 11:30 am
REMARKS
REMARQUES
1. Meeting Purpose
Leslie Mitchell (OPG): Provided context for the purpose of the meeting, which was to brief CNSC and CEAA staff on the Plant Parameter Envelope (PPE) concept and its application in the Environmental Impact Statement (EIS) and Licence to Prepare Site (LTPS) Application for the OPG New Nuclear at Darlington Project.
2. OPG Presentation Jack Vecchiarelli (OPG): Presented the PPE Concept and Application for OPG New Nuclear at Darlington (see E-doc 3472460 for OPG Presentation). OPG clarified that Revisions 0, 1, and 2 of the PPE were approved by the Chief Engineer for the New Nuclear at Darlington project.
3. CNSC/CEAA Staff Discussion Points
CNSC and CEAA staff raised a number of discussion points during the OPG presentation. These points are summarized as follows:
• OPGs confidence in the PPE data provided by the reactor vendors.
• Linkages between the PPE data and its usage in the EIS and LTPS Application.
Page 2 of 2
• Linkages between site parameters provided in the PPE and the site characteristics provided in the site evaluation studies.
• Consistency in information presented in the PPE versus information presented in the EIS and LTPS Application.
• Differences between OPG’s PPE approach and USNRCs accepted PPE approach for Early Site Permit (ESP) Applications.
CNSC and CEAA staff indicated that further questions on the PPE concept may be raised as proposed Information Requests to the Darlington Joint Review Panel.
Staff also indicated that the other members of the Federal Review Team would benefit from receiving a similar presentation by OPG. OPG agreed in principle to provide this presentation to the Federal Review Team in early 2010.
NOTES WRITTEN BY
Name(s)/Nom(s) : Ross Richardson/Melanie Mallette